McHugh v. Kellogg Brown & Root Services, Inc. , 626 F. App'x 974 ( 2015 )


Menu:
  •        NOTE: This disposition is nonprecedential.
    United States Court of Appeals
    for the Federal Circuit
    ______________________
    JOHN M. MCHUGH, SECRETARY OF THE ARMY,
    Appellant
    v.
    KELLOGG BROWN & ROOT SERVICES, INC.,
    Appellee
    _____________________
    2015-1053
    ______________________
    Appeal from the Armed Services Board of Contract
    Appeals in Nos. 56358, 57151, 57327, 58559, Administra-
    tive Judge Mark N. Stempler, Administrative Judge
    Monroe E. Freeman, Jr., Administrative Judge Richard
    Shackleford.
    ______________________
    Decided: September 15, 2015
    ______________________
    JONATHAN REID PROUTY, Commercial Litigation
    Branch, Civil Division, United States Department of
    Justice, Washington, DC, argued for appellant. Also
    represented by BENJAMIN C. MIZER, ROBERT E.
    KIRSCHMAN, JR.
    JASON NICHOLAS WORKMASTER, Covington & Burling
    LLP, Washington, DC, argued for appellee. Also repre-
    2                   ARMY   v. KELLOGG BROWN & ROOT SERVICES
    sented by RAYMOND B. BIAGINI, HERBERT L. FENSTER,
    DANIEL L. RUSSELL, JR., ALEJANDRO LUIS SARRIA, JOHN W.
    SORRENTI.
    ______________________
    Before PROST, Chief Judge, LOURIE and BRYSON, Circuit
    Judges.
    PROST, Chief Judge.
    The Secretary of the Army (“Army”) appeals from a
    final decision of the Armed Services Board of Contract
    Appeals (“Board”) in favor of Kellogg, Brown & Root
    Services, Inc. (“KBR”). The Board ruled in favor of KBR,
    finding that the contract between the Army and KBR did
    not preclude the use of armed subcontractors and that the
    Army contracting officer’s additional claim against KBR
    in 2013 was barred by the statute of limitations. Kellogg
    Brown & Root Servs., Inc., Contract No. DAAA09-02-D-
    0007, ASBCA Nos. 56358, 57151, 57327, and 58559, 14-1
    BCA ¶ 35,639, 
    2014 WL 2931488
    (June 17, 2014) (“Board
    Decision”). We affirm the Board’s conclusion on the
    statute of limitations. On the contract interpretation
    issue, however, KBR focuses on its contention that the
    Army breached its force protection obligations under the
    contract, which the Board did not rule on and is the
    subject of a separate case pending before the Board.
    Limited to the narrow contract interpretation issue now
    before us, we agree with the Army. We therefore affirm
    in part, reverse in part, vacate in part, and remand.
    BACKGROUND
    The Army contracted with KBR on December 4, 2001
    to provide dining facilities services in the Iraq war under
    Contract 0007 in the U.S. Army’s Logistics Civil Augmen-
    tation Program or the LOGCAP III contract. Some of
    KBR’s subcontractors hired armed escorts by Private
    Security Contractors (“PSCs”) in response to deteriorating
    security conditions and an alleged inability to obtain force
    ARMY   v. KELLOGG BROWN & ROOT SERVICES                   3
    protection from the Army. The use of these PSCs under
    the LOGCAP III contract was not authorized by the
    Army. Some of KBR’s subcontractors charged their PSC
    costs incurred from 2003 to 2006 to KBR, which in turn
    passed on the costs to the Army. The Army paid those
    PSC costs.
    In late 2006, however, the Army started to question
    KBR about the use of PSCs. Between 2007 and 2010, the
    Army withheld three payments to KBR for PSC costs
    previously paid by the Army. The three withheld pay-
    ments totaled over $44 million. KBR submitted a certi-
    fied claim to the Army’s contracting officer for each of the
    withheld payments under the Contract Disputes Act of
    1978 (“CDA”). The contracting officer failed to respond
    within sixty days of receiving the respective claims for
    withheld payments and the claims were deemed denied;
    the associated appeals to the Board were docketed as
    ASBCA Nos. 56358, 57151, and 57327. On January 30,
    2013, the Army’s contracting officer issued a final decision
    demanding from KBR an additional amount of nearly $12
    million for disallowed PSC costs. KBR appealed this
    decision and it was docketed as ASBCA No. 58559.
    The Board consolidated the four cases for hearing.
    Shortly before trial for the four consolidated cases, KBR
    moved to consolidate an additional case, ASBCA No.
    58583, in which it alleged that the Army breached its
    contractual obligation to provide adequate force protec-
    tion. The Board denied KBR’s motion. It agreed with the
    Army’s argument that the Army would be prejudiced if
    KBR were allowed to raise its new breach theory at the
    trial of the four consolidated cases. The Board proceeded
    with the hearings on the four consolidated cases and
    issued a decision on June 17, 2014 in favor of KBR. The
    Board dismissed the Army’s affirmative claim for nearly
    $12 million in ASBCA No. 58559 because the Army’s
    contracting officer asserted the claim on January 30,
    2013, beyond the six-year statute of limitations under the
    4                  ARMY   v. KELLOGG BROWN & ROOT SERVICES
    CDA. The Board then rejected the Army’s contention that
    the terms of the contract did not allow for the use of PSCs
    and ordered the Army to pay the withheld $44 million at
    issue in ASBCA Nos. 56358, 57151, and 57327.
    The Army timely appealed to this court. We have ju-
    risdiction under 28 U.S.C. § 1295(a)(10) and 41 U.S.C.
    § 7107(a)(1).
    DISCUSSION
    Under the CDA, 41 U.S.C. §§ 7101–7109, we review
    the Board’s decisions on questions of law de novo. Sharp
    Elecs. Corp. v. McHugh, 
    707 F.3d 1367
    , 1371 (Fed. Cir.
    2013). Contract interpretation is a question of law. Teg-
    Paradigm Envtl., Inc. v. United States, 
    465 F.3d 1329
    ,
    1336 (Fed. Cir. 2006). Factual findings shall be set aside
    if “the decision is (A) fraudulent, (B) arbitrary, or capri-
    cious, or so grossly erroneous as to necessarily imply bad
    faith, or (C) not supported by substantial evidence.” 41
    U.S.C. § 7107(b)(2); Ingalls Shipbuilding, Inc. v. O’Keefe,
    
    986 F.2d 486
    , 488-89 (Fed. Cir. 1993).
    The Army raises two issues on appeal. First, the Ar-
    my argues that the contract prohibited the use of PSCs
    and therefore KBR was not entitled to payment for the
    use of PSCs. Second, the Army argues that the Army’s
    affirmative demand against KBR on January 30, 2013
    was not barred by the CDA’s six-year statute of limita-
    tion. We address each issue in turn.
    I. Contract Interpretation
    The Army’s theory is that the contract prohibited the
    use of PSCs because “PSCs, by definition, consist of armed
    subcontractor employees,” and the contract prohibited the
    arming of such employees. Reply Br. 3. The Army cites
    Clause H-21 of the contract for prohibiting the use of
    personally owned firearms by contractor personnel. The
    Army also cites Clause H-13 of the contract for requiring
    that all personnel hired by or for the contractor shall
    ARMY   v. KELLOGG BROWN & ROOT SERVICES                  5
    comply with all applicable guidance, instructions, and
    general orders, thus further incorporating Army regula-
    tions that prohibited the use of armed civilian personnel.
    The regulations relied upon by the Army include
    CENTCOM General Order No. 1A, Army Regulation 715-
    9, entitled “Contractors Accompanying the Force,” and the
    Army’s “Contractors on the Battlefield” field manual.
    Based on the Army Regulation and the field manual, the
    Army further explains that arming contractor personnel
    could jeopardize their status as civilians.
    KBR does not dispute that the contract prohibited the
    arming of employees of KBR and its food services subcon-
    tractors. Rather, KBR implies that the contract’s weap-
    ons prohibition did not apply to the PSCs, arguing that
    “[n]ot a single one of the provisions upon which the Gov-
    ernment relies, however, even remotely alludes to the
    hiring or use of PSCs” and that there was a “material
    difference between arming individual contractor employ-
    ees and retaining a professional private armed security
    company having its own employees, arms and ammuni-
    tion.” Appellee’s Br. 34–35 (internal quotation marks
    omitted).
    KBR’s arguments simply mirror the Board’s reason-
    ing. The Board’s opinion rested on the central premise
    that the contract and applicable regulations lacked explic-
    it and specific prohibition against the use of PSCs. The
    Board reasoned that the relevant contract provision
    addressed only individual employee’s access to firearms
    for self-defense, but did not address the use of armed
    private security companies. The Board similarly inter-
    preted the weapons prohibition in CENTCOM General
    Order No. 1A as a code of personal conduct not relevant to
    the question of using armed private security contractors.
    The Board did not address Army Regulation 715-9 and
    the Army’s “Contractors on the Battlefield” field manual
    that the Army cites on appeal.
    6                  ARMY   v. KELLOGG BROWN & ROOT SERVICES
    KBR and the Board are correct that the contract and
    the applicable Army regulations did not specifically
    mention Private Security Contractors or PSCs. But a lack
    of specific reference to PSCs does not mean that KBR and
    its subcontractors were free to hire PSCs with civilian
    personnel carrying privately-owned weapons.           Under
    KBR’s theory, the contract and Army regulations prohib-
    ited, for example, truck drivers and other food services
    subcontractor employees from carrying their own rifles in
    the delivery trucks. But according to KBR, the contract
    and Army regulations permitted KBR’s food services
    subcontractors to subcontract further for the services of
    PSCs, employing civilians carrying privately-owned
    weapons to protect the delivery trucks. KBR contends
    without explanation that there was a “material differ-
    ence” in the weapons prohibition as applied to employees’
    self-protection and the hiring of other civilians for protec-
    tion. Appellee’s Br. 35.
    We are not persuaded that KBR’s alleged “material
    difference” existed. We discern no support in the contract
    or the applicable Army regulations to place KBR and its
    direct (food services) subcontractors on one side of the
    weapons prohibition and secondary (security) subcontrac-
    tors on the other. There is no question that the PSCs’
    personnel were civilians carrying nongovernment-issued
    weapons. Army regulations such as CENTCOM General
    Order No. 1A prohibited such civilian personnel from the
    possession or use of privately owned firearms, ammuni-
    tion and explosives. E.g., J.A. 550. This longstanding
    Army policy was incorporated into the LOGCAP III
    contract by clauses H-13 and H-19.
    We therefore interpret the contract’s weapons prohibi-
    tion to apply equally to the employees of KBR and its food
    services subcontractors, as well as to the personnel of the
    security subcontractors engaged for the LOGCAP III
    contract. Because the contract prohibited contractors’ and
    subcontractors’ employees from carrying nongovernment-
    ARMY   v. KELLOGG BROWN & ROOT SERVICES                 7
    issued weapons, we conclude that the use of armed PSCs
    fell outside the scope of the LOGCAP III contract. We
    therefore reverse the Board’s conclusion that the
    LOGCAP III contract allowed the use of PSCs.
    This narrow contract interpretation based on the
    weapons prohibition, however, may not fully resolve the
    dispute between the parties. KBR argues that we could
    alternatively affirm the Board based on its “holding that
    the use of PSCs was an allowable ‘remedy’ for the Gov-
    ernment’s breach of its contractual obligation to provide
    adequate force protection.” Appellee’s Br. 21. A threshold
    question for us is whether these breach and remedy issues
    are properly before us on appeal. We note that the
    Board’s opinion made several findings of fact that appear
    favorable to KBR concerning its allegations of the Army’s
    prior breach of contract and of using PSCs as an allowable
    remedy. But we do not read the Board’s opinion as reach-
    ing any ultimate legal conclusion on these issues.
    Indeed, even KBR conceded during oral argument
    that there is some vagueness in the Board’s opinion on
    whether the Board ruled on the breach and remedy is-
    sues.      Oral Arg. at 19:35–23:10, available at
    http://www.cafc.uscourts.gov/oral-argument-recordings/
    15-1053/all. We therefore remand ASBCA Nos. 56358,
    57151, and 57327 to the Board to decide in the first in-
    stance whether KBR properly raised its breach and reme-
    dy allegations, and if so, to rule on those contentions. 1
    II. Statute of Limitations
    The Board also dismissed the Army’s affirmative
    claim for nearly $12 million in ASBCA No. 58559 because
    1   We have also considered KBR’s contentions that
    we could affirm the Board’s conclusions in favor of KBR
    on additional alternative grounds. We do not find any of
    those purported alternative grounds persuasive.
    8                  ARMY   v. KELLOGG BROWN & ROOT SERVICES
    the Army’s contracting officer asserted the claim on
    January 30, 2013, more than six years after the claim
    accrued on June 10, 2005. See 41 U.S.C. § 7103(a)(4)(A).
    The Board found that on June 10, 2005, an Army con-
    tracting officer consented to a food services subcontract
    document submitted by KBR in which the pricing justifi-
    cation expressly included the statement that the subcon-
    tractor was “using the services of a professional security
    company to transport” the food services personnel to their
    respective sites. Board Decision at ¶ 60 (quoting J.A.
    5550).
    The Army argues that the Board erred because the
    statute of limitations did not start when the Army knew
    or should have known of the use of PSCs. The operative
    marker, according to the Army, should be when it knew or
    should have known that KBR would be seeking reim-
    bursement from the Army for the use of PSCs.
    Even if we accept the Army’s contention on the proper
    event to start the statute of limitations period, the Army
    still loses on this issue. The June 10, 2005 KBR docu-
    ment cited by the Board was entitled “REQUEST FOR
    CREDIT” that was submitted to and approved by the
    Army. J.A. 5544. This June 10, 2005 credit request
    included correspondence from a KBR subcontractor to
    KBR that explicitly justified a price increase for: “Securi-
    ty: Private companies are contracted to escort personnel
    to and from sites. In addition, when military convoys are
    not available, we use private security companies.” J.A.
    5550.
    The Army’s only challenges to the June 10, 2005 cred-
    it request are that the document did not explicitly state
    KBR’s intent to seek payment for the PSC costs and that
    there was no witness testimony about this credit request.
    But the Army offers no explanation why a credit request
    attaching a subcontractor’s justification for a price in-
    crease based on the use of PSCs should not have put the
    ARMY   v. KELLOGG BROWN & ROOT SERVICES                 9
    Army on notice that it would be paying for the use of
    PSCs. Because of the specificity of the information in the
    June 10, 2005 credit request, we are not persuaded by the
    Army’s arguments. We therefore conclude that KBR’s
    June 10, 2005 credit request provided substantial evi-
    dence to support the Board’s finding that the statute of
    limitations period began by June 10, 2005. We therefore
    affirm the Board’s dismissal of ASBCA No. 58559 because
    the Army asserted the claim more than six years after it
    accrued.
    AFFIRMED-IN-PART, REVERSED-IN-PART,
    VACATED-IN-PART and REMANDED
    COSTS
    Each party shall bear its own costs.
    

Document Info

Docket Number: 2015-1053

Citation Numbers: 626 F. App'x 974

Judges: Prost, Lourie, Bryson

Filed Date: 9/15/2015

Precedential Status: Non-Precedential

Modified Date: 10/19/2024