Lear Siegler Services v. Rumsfeld, Secretary of Defense , 457 F.3d 1262 ( 2006 )


Menu:
  •  United States Court of Appeals for the Federal Circuit
    06-1080
    LEAR SIEGLER SERVICES, INC.,
    Appellant,
    v.
    Donald H. Rumsfeld, SECRETARY OF DEFENSE,
    Appellee.
    Daniel B. Abrhams, Epstein Becker & Green, P.C, of Washington, DC, argued for
    appellant. With him on the brief was Shlomo D. Katz.
    Marla T. Conneely, Attorney, Commercial Litigation Branch, Civil Division, United
    States Department of Justice, of Washington, DC, argued for appellee. With her on the
    brief were Peter D. Keisler, Assistant Attorney General; David M. Cohen, Director; and
    James M. Kinsella, Deputy Director. Of counsel on the brief was John T. Lauro,
    Department of the Air Force, Air Force Legal Services Agency, of Arlington, Virginia.
    Terry R. Yellig, Sherman, Dunn, Cohen, Leifer & Yellig, P.C., of Washington, DC,
    for amicus curiae International Association of Machinists and Aerospace Workers, AFL-
    CIO.
    Mark D. Colley, Holland & Knight LLP, of Washington, DC, for amicus curiae
    Professional Services Council. With him on the brief were David P. Metzger, Kara L.
    Daniels, and Eric L. Yeo.
    Appealed from: United States Armed Services Board of Contract Appeals
    United States Court of Appeals for the Federal Circuit
    06-1080
    LEAR SIEGLER SERVICES, INC.,
    Appellant,
    v.
    Donald H. Rumsfeld, SECRETARY OF DEFENSE,
    Appellee.
    ________________________
    DECIDED: July 28, 2006
    ________________________
    Before, NEWMAN, GAJARSA, and LINN, Circuit Judges.
    GAJARSA, Circuit Judge.
    Lear Siegler Services, Inc. (“LSI” or “the contractor”) appeals from the decision of
    the Armed Services Board of Contract Appeals (“Board”), granting summary judgment
    to the government and denying summary judgment to LSI. Lear Siegler Servs., Inc.,
    2005 ASBCA LEXIS 31, 2005-1 B.C.A. (CCH) P32,937, 
    ASBCA No. 54449
    , aff’d on
    reconsideration, 2005 ASBCA LEXIS 90, 2005-2 B.C.A. (CCH) P33,110.               LSI had
    claimed that the Price Adjustment Clause (part of the regulatory scheme of the Service
    Contract Act of 1965) required the government to compensate LSI for increases in the
    cost of providing its employees with a defined-benefit health plan, as required by the
    terms of a collective bargaining agreement (“CBA”). See Service Contract Act of 1965,
    ch. 286, Pub. L. No. 89-286, 
    79 Stat. 1034
     (codified as amended at 
    41 U.S.C. § 351
    -
    358); 
    48 C.F.R. § 52.222-43
     (“Price Adjustment Clause”). LSI timely appealed.
    The Board had jurisdiction pursuant to the Contract Disputes Act, 
    41 U.S.C. § 607
    (d)(2), and we have jurisdiction pursuant to 
    28 U.S.C. § 1295
    (a)(10) and 
    41 U.S.C. § 607
    (g)(1)(A).    For the reasons discussed below, we hold that the Board erred in
    granting summary judgment in favor of the government, and it abused its discretion in
    denying summary judgment to LSI. Accordingly, we reverse.
    I.     BACKGROUND
    The Air Force awarded a firm, fixed price contract to LSI, under which LSI was to
    provide aircraft maintenance services at Sheppard Air Force Base, Texas. The base
    year of the contract ran from October 2001 to October 2002, with multiple renewal
    options thereafter. LSI’s predecessor contractor was Lockheed Martin.
    LSI’s contract incorporated the terms of the Service Contract Act (“SCA”), which
    serves generally to protect the wages and fringe benefits of service workers.              The
    contract included both a SCA wage/benefit determination, which incorporated the
    wages and fringe benefits set forth in the CBA between the Air Force and Lockheed’s
    predecessor, and a Price Adjustment Clause, which required the government to pay LSI
    for “increase[s] . . . in applicable . . . fringe benefits . . . made to comply with . . . [the]
    wage determination . . . .” 
    48 C.F.R. § 52.222-43
    .
    LSI’s CBA specifically required it to provide its employees with a defined-benefit
    health plan.      As distinct from a defined-contribution plan, a defined-benefit plan
    obligates an employer to spend whatever is necessary to continue to provide its
    employees with an agreed-upon level of benefit. A defined-benefit plan thereby ensures
    06-1080                                        2
    that employees will continue to receive the same level of benefit (here health coverage),
    even as costs rise. Although the future costs of providing benefits under a defined-
    benefit plan are not known with certainty at the time of contracting, such costs may
    reasonably be projected on the basis of actuarial determinations.
    In February, 2003, LSI submitted a request for a price adjustment under the SCA
    Price Adjustment Clause for Option Year 2003, seeking reimbursement for the
    increased costs of providing its employees with the defined-benefit health plan. The Air
    Force denied the request, and LSI appealed to the Board. The Board distinguished
    between increases in an employer’s costs of providing benefits, which it deemed
    insufficient to trigger the Price Adjustment Clause, and increases in the benefits
    themselves. See 
    48 C.F.R. § 52.222-43
    (d) (requiring “increase[s] . . . in applicable . . .
    fringe benefits . . . ”).
    Observing that there had been no “change in the CBA . . . [or the] scope of
    benefits to be provided,” it concluded that the CBA-based wage determination did not
    require LSI to incur the increased cost of maintaining the defined level of health benefit,
    and that the Price Adjustment Clause was therefore inapplicable.         Accordingly, the
    Board granted summary judgment in favor of the Air Force and denied LSI’s request for
    the same. The Board also rejected LSI’s course-of-dealing argument, holding that a
    course of dealing cannot alter the meaning of an unambiguous contract term. LSI
    timely appealed to this court, and we have jurisdiction pursuant to 
    28 U.S.C. § 1295
    (a)(10) and 
    41 U.S.C. § 607
    (g)(1)(A).
    06-1080                                       3
    II.    DISCUSSION
    The principal issue on appeal is whether the Board erred in its construction of the
    Price Adjustment Clause. For the reasons discussed below, we conclude that it did
    commit legal error in its determination, and we reverse the judgment of the Board
    without needing to reach the merits of LSI’s other arguments.
    A.     Standard of Review
    This case requires us to review the Board’s construction of the Price Adjustment
    Clause.   Our standard of review is governed by the Contracts Disputes Act, which
    provides that “the decision of the agency board on any question of law shall not be final
    or conclusive . . . .” 
    41 U.S.C. § 609
    (b). Statutory and regulatory constructions are
    questions of law, which we review de novo. The interpretation of a government contract
    is also question of law, which we review de novo on appeal. Forman v. United States,
    
    329 F.3d 837
    , 841 (Fed. Cir. 2003). Nonetheless, we give the Board’s legal conclusions
    “careful consideration due to the board’s considerable experience in construing
    government contracts.” Wickham Contracting Co. v. Fischer, 
    12 F.3d 1574
    , 1577 (Fed.
    Cir. 1994). See also Titan Corp. v. West, 
    129 F.3d 1479
    , 1481 (Fed. Cir. 1997) (“The
    Board’s interpretation of a contract is not final, and is subject to de novo review on
    appeal, although due respect is often warranted by the Board’s experience in
    interpreting the Federal Acquisition Regulations (FAR).”); Erickson Air Crane Co. v.
    United States, 
    731 F.2d 810
    , 814 (Fed. Cir. 1984) (“[L]egal interpretations by tribunals
    having expertise are helpful to us, even if not compelling.”).
    Summary judgment is properly granted only when there is no genuine issue of
    material fact. Fed. R. Civ. P. 56(c); Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 247-
    06-1080                                       4
    48 (1986). While we review de novo a district court’s grant of summary judgment, we
    review its denial of summary judgment for abuse of discretion. Pickholtz v. Rainbow
    Techs., 
    284 F.3d 1365
    , 1371 (Fed. Cir. 2002).
    B.    Service Contract Act
    The SCA requires most government service contracts to contain clauses that
    protect workers’ wages and fringe benefits. See 
    41 U.S.C. § 351
    (a). More specifically,
    the SCA directs the Secretary of Labor (“Secretary”) to issue special minimum wage
    orders, called “wage determinations,” for each class of service worker employed in a
    particular locality, and it forbids contractors (that is, employers) from paying less than
    the Secretary’s wage determinations.      See 
    41 U.S.C. § 351
    (a)(1).      A similar SCA
    provision applies to fringe benefits. See 
    41 U.S.C. § 351
    (a)(2).
    In this manner, the SCA prevents contractors from underbidding each other (and
    hence being awarded government contracts) by cutting wages or fringe benefits to its
    service workers:
    Since labor costs are the predominant factor in most service contracts, the
    odds on making a successful low bid for a contract are heavily stacked in
    favor of the contractor paying the lowest wages. Contractors who wish to
    maintain an enlightened wage policy may find it almost impossible to
    compete for Government service contracts with those who pay wages to
    their employees at or below the subsistence level. When a Government
    contract is awarded to a service contractor with low wage standards, the
    Government is in effect subsidizing subminimum wages.
    Fort Hood Barbers Ass’n v. Herman, 
    137 F.3d 302
    , 309 (5th Cir. 1998) (citing H.R. Rep.
    No. 89-948, at 2-3 (1965); S. Rep. No. 89-798, at 3-4 (1965), reprinted in 1965
    U.S.C.C.A.N. 3737, 3739).
    Although the SCA, as originally enacted, worked well to prevent the depression
    of wages/benefits (by using wage determinations to set a wage/benefit “floor”), it did not
    06-1080                                      5
    provide a mechanism to prevent the erosion of wage/benefit gains made through
    collective   bargaining,   wherein   labor   groups   had   succeeded   in   negotiating
    wages/benefits that were higher than the Secretary’s general wage determination. As
    the Fifth Circuit aptly noted:
    [T]he nature of government contracting, calling for frequent rebidding,
    combined with the SCA's sole emphasis and reliance on the prevailing
    wage rate scheme, effectively diminished the bargaining power of
    unionized workforces. A contractor without a CBA covering its employees,
    or with a CBA setting comparatively low wage and benefit rates, was able
    to easily outbid an incumbent contractor bound by a CBA with higher
    wages and rates that would survive the commencement date of the new
    contract.
    
    Id.
    Consequently, the SCA was amended to insert the so-called “successor
    contractor rule,” which prohibits a successor contractor from paying its employees less
    than its predecessor had paid its employees pursuant to the predecessor’s CBA:
    No contractor or subcontractor under a contract, which succeeds a
    contract subject to this Act and under which substantially the same
    services are furnished, shall pay any service employee under such
    contract less than the wages and fringe benefits, including accrued wages
    and fringe benefits, and any prospective increases in wages and fringe
    benefits provided for in a collective-bargaining agreement as a result of
    arm’s-length negotiations, to which such service employees would have
    been entitled if they were employed under the predecessor contract . . . .
    
    41 U.S.C. § 353
    (c); see also Gracey v. Int’l Bhd. of Elec. Workers, 
    868 F.2d 671
    , 675
    (4th Cir. 1989) (“[T]he purpose of that section was to remedy the practice of
    underbidding for government contracts by slashing wages.”); see also 
    29 C.F.R. § 4.163
    (k) (“No provision of this section shall be construed as permitting a successor
    contractor to pay its employees less than the wages and fringe benefits to which such
    06-1080                                      6
    employees would have been entitled under the predecessor contractor’s collective
    bargaining agreement.”).
    The successor contractor rule is a direct statutory obligation that is self-
    executing. See Guardian Moving & Storage Co. v. Hayden, 
    421 F.3d 1268
    , 1270 (Fed.
    Cir. 2005) (“[The successor-contractor rule] is a direct statutory obligation and
    requirement placed on the successor contractor . . . and is not contingent or dependent
    upon the issuance or incorporation in the contract of a wage determination based on the
    predecessor     contractor’s   collective   bargaining   agreement.”   (citing   
    29 C.F.R. § 4.163
    (b))).
    Here, LSI is subject to the successor contractor rule because it succeeded
    Lockheed on the contract and was thus a successor in its base year of the contract. In
    addition, LSI was also a “successor contractor” during its first option year (the second
    year it was providing services), because LSI succeeded itself. See 
    29 C.F.R. § 4.163
    (e)
    (stating that a contractor can also become a successor to itself, such as when it, like
    LSI, performs an additional term pursuant to an option exercised by the government).
    C.     Price Adjustment Clause
    LSI’s contract with the government incorporated by reference the provisions of 
    48 C.F.R. § 52.222-43
    , including the so-called “Price Adjustment Clause.”
    (a) This clause applies to both contracts subject to area prevailing wage
    determinations and contracts subject to collective bargaining agreements.
    ***
    (d) The contract price or contract unit price labor rates will be adjusted to
    reflect the Contractor’s actual increase or decrease in applicable wages
    and fringe benefits to the extent that the increase is made to comply with
    or the decrease is voluntarily made by the Contractor as a result of:
    06-1080                                        7
    (1) The Department of Labor wage determination applicable on the
    anniversary date of the multiple year contract, or at the beginning of
    the renewal option period.
    
    48 C.F.R. § 52.222-43
     (emphases added).
    Regulations make clear that the term “wage determination” includes a CBA-
    defined benefit level. See 
    29 C.F.R. § 4.50
     (explaining that there are two types of wage
    and fringe benefit determinations, namely those that are based on prevailing wage data
    generally and those based on the level of benefits required pursuant to a CBA that a
    successor contractor is required to maintain); see also 
    48 C.F.R. § 52.222-43
    (a) (“This
    clause applies to both contracts subject to area prevailing wage determinations and
    contracts subject to collective bargaining agreements.”).          In addition, the parties
    stipulated that the CBA of LSI’s predecessor listed fringe benefits that included the
    defined-benefit health insurance at issue in this case.
    D.     Analysis
    Here we must determine whether a “wage determination” (i.e., the CBA) required
    an “actual increase . . . in . . . fringe benefits . . . .”   
    48 C.F.R. § 52.222-43
    .     We
    conclude that it did, thereby triggering the government’s obligations under the Price
    Adjustment Clause. For several reasons, we find no merit in the argument that the
    Price Adjustment Clause is triggered only by enlarged benefits rather than enlarged
    costs of providing those benefits.
    First, the language of the clause itself is instructive. See 
    48 C.F.R. § 52.222
    -
    43(d) (“The contract price or contract unit price labor rates will be adjusted to reflect the
    Contractor’s actual increase or decrease in applicable wages and fringe benefits . . . .”)
    (emphasis added).       The Clause does not address increases in the nature of the
    06-1080                                         8
    contract’s requirements, but rather the effect on the Contractor, which logically can only
    refer to changes in cost.
    Second, this construction is consistent with other provisions of the regulatory
    scheme, which provide for the “equivalency” of fringe benefits to be measured not in
    terms of value to the employee, but cost to the employer. See 
    29 C.F.R. § 4.177
    (a)(3)
    (“When a contractor discharges his fringe benefit obligation by furnishing, in lieu of
    those benefits specified in the applicable fringe benefit determination, other ‘bona fide’
    fringe benefits, cash payments, or a combination thereof, the substituted fringe benefits
    and/or cash payments must be ‘equivalent’ to the benefits specified in the
    determination. As used in this subpart, the terms equivalent fringe benefit and cash
    equivalent mean equal in terms of monetary cost to the contractor.”) (emphasis added).
    Third, this court’s precedent in United States v. Service Ventures, Inc., leads to
    this conclusion. See 
    899 F.2d 1
     (Fed. Cir. 1990). In that case, the applicable wage
    determination required that employees be given specified amounts of vacation time,
    depending on their seniority. 
    Id. at 2
     (requiring Service Ventures to pay “2 weeks paid
    vacation after 1 year of service with a contractor or successor; 3 weeks after 5 years”).
    During the first option year, a greater number of employees were entitled to vacation
    benefits under the language of the wage determination. Accordingly, Service Ventures
    had to pay more in order to comply with the mandate of the wage determination, and it
    therefore sought to receive a price adjustment. 
    Id.
    As in this case, the actual language of the wage determination had not changed.
    Service Venture’s obligations had remained nominally the “same” in that it was still
    required to provide a specified level of benefits to each employee in a specified class.
    06-1080                                      9
    However, its costs of compliance had changed because of changes in the numbers of
    employees in each vacation benefit “class.” Far from adopting a narrow view of what
    constituted a “change” to a wage determination, in Service Ventures we held that the
    “benefits were due entirely to the [wage determination] applicable at the beginning of
    the renewal option period and were required to be paid in accordance with the [Price
    Adjustment] clause.” 
    Id. at 3
    .
    This case is analogous. In Service Ventures, the employer’s costs of compliance
    changed in a manner not known in advance with certainty, by virtue of changes in the
    composition of the workforce.         Nonetheless, the nominally unchanged wage
    determination required Service Ventures to pay out whatever total sum of benefits was
    necessary for it to meet its obligations thereunder.    Likewise, in this case, a wage
    determination (here, from a CBA) required LSI to pay whatever was necessary for it to
    meet its obligations to its employees, in light of changes in the costs of providing them
    with an agreed-upon level of health care benefit.
    Just as we held such changes in cost to trigger the Price Adjustment Clause in
    Service Ventures, we hold them to do so here. In short, the Price Adjustment Clause is
    triggered by changes in an employer’s cost of compliance with the terms of a wage
    determination.   The fact that there has been no nominal change in the mandated
    benefit—i.e., that there has been no change in the level of benefit provided by the
    defined-benefit plan—is simply irrelevant.
    Finally, we address the government’s argument that the Price Adjustment Clause
    does not apply because LSI can somehow satisfy its fringe-benefit obligations by
    making equivalent payments directly to its employees. See, e.g., 
    41 U.S.C. § 351
    (a)(2)
    06-1080                                      10
    (stating that “[t]he obligation [to provide fringe benefits] . . . may be discharged by
    furnishing any equivalent combinations of fringe benefits or by making equivalent or
    differential payments in cash under rules and regulations established by the Secretary”).
    We see no merit in this argument. If LSI pays its employees the “equivalent” of the
    fringe benefit, then applicable regulations would require it to pay them an amount equal
    to its own costs of providing the benefit. See 
    29 C.F.R. § 4.177
    (a)(3) (“[E]quivalent
    means equal in terms of monetary cost to the contractor.”). The extent of LSI’s CBA-
    based obligations would remain unchanged.
    ***
    For the reasons stated above, we hold that the Board erred in granting summary
    judgment in favor of the government, and it abused its discretion in denying summary
    judgment to LSI. We agree with the Board, however, that this case involves no genuine
    issue of material fact, and it is therefore suitable for summary judgment. Accordingly,
    we reverse both holdings below and grant summary judgment in favor of LSI.
    REVERSED
    Costs to Appellant.
    06-1080                                     11