Raytheon Company v. United States , 809 F.3d 590 ( 2015 )


Menu:
  •   United States Court of Appeals
    for the Federal Circuit
    ______________________
    RAYTHEON COMPANY,
    Plaintiff-Appellant
    v.
    UNITED STATES, LOCKHEED MARTIN
    CORPORATION, NORTHROP GRUMMAN
    SYSTEMS CORPORATION,
    Defendants-Appellees
    ______________________
    2015-5086
    ______________________
    Appeal from the United States Court of Federal
    Claims in No. 1:15-cv-00077-MMS, Judge Margaret M.
    Sweeney.
    ______________________
    Decided: October 23, 2015
    ______________________
    MARK COLLEY, Arnold & Porter LLP, Washington,
    DC, argued for appellant. Also represented by KARA L.
    DANIELS, NICOLE B. NEUMAN, PAUL E. POMPEO.
    STEVEN MICHAEL MAGER, Commercial Litigation
    Branch, Civil Division, United States Department of
    Justice, Washington, DC, argued for appellee United
    States. Also represented by ALEXANDER V. SVERDLOV,
    KIRK T. MANHARDT, ROBERT E. KIRSCHMAN, JR., BENJAMIN
    2                                  RAYTHEON COMPANY    v. US
    C. MIZER; MARK E. ALLEN, ADAM N. OLSEN, United States
    Air Force, Joint Base Andrews, MD.
    MARCIA MADSEN, Mayer Brown LLP, Washington,
    DC, argued for appellee Lockheed Martin Corporation.
    Also represented by DAVID F. DOWD, LUKE P. LEVASSEUR.
    RICHARD A. SAUBER, Robbins, Russell, Englert, Or-
    seck, Untereiner & Sauber LLP, Washington, DC, argued
    for appellee Northrop Grumman Systems Corporation.
    Also represented by DENEEN J. MELANDER, PETER B.
    SIEGAL, JENNIFER S. WINDOM.
    ______________________
    Before NEWMAN, DYK, and TARANTO, Circuit Judges.
    TARANTO, Circuit Judge.
    The United States awarded a procurement contract to
    one of three bidders. A General Accountability Office
    review process, launched by the losing bidders’ protests,
    then led the government to conclude, among other things,
    that it had given the bidders disparate information on an
    important subject, thereby violating a regulation that
    governs the bidding process. When the government
    reopened the bidding, the initial winning bidder protested
    the government’s reopening decision. The Court of Fed-
    eral Claims denied the protest. Raytheon Co. v. United
    States, 
    121 Fed. Cl. 135
    (2015) (public version of opinion).
    We affirm, concluding that the reopening decision was
    proper based on the disparate-information violation. We
    need not and do not address a second basis for the gov-
    ernment’s decision to reassess its original award.
    BACKGROUND
    The United States Air Force solicited bids from pri-
    vate companies to supply the complex mix of equipment
    and services the government was seeking to acquire in
    order to build a new radar system. Raytheon, 121 Fed. Cl.
    RAYTHEON COMPANY   v. US                                  3
    at 138. The procurement process had several stages.
    Raytheon Company, Northrop Grumman Systems Corpo-
    ration, and Lockheed Martin Corporation cleared early-
    stage hurdles, allowing them to proceed to the next stage.
    
    Id. at 140;
    J.A. 290. The Air Force issued to the three
    companies (and only them) a solicitation for proposals for
    Engineering and Manufacturing Development. 
    Raytheon, 121 Fed. Cl. at 140
    ; J.A. 336–513.
    Each bidder, in supporting the price it offered, had to
    provide detailed estimates of the costs it would incur in
    performing the contract. J.A. 362–75. More specifically,
    the bidders all had to “identify and support their proposed
    cost reductions,” 
    Raytheon, 121 Fed. Cl. at 140
    , i.e., their
    means of lowering the price they would charge to the Air
    Force under this contract while still performing all work
    needed to get the job done. See 
    id. at 163;
    J.A. 369–74.
    The Air Force made clear from the start, and repeatedly,
    that it would scrutinize each bidder’s estimates, including
    any cost-reduction means (or “affordability initiative”), to
    try to ensure that it did not choose a supplier whose price
    was unrealistic: an unrealistic price could indicate that
    the firm did not understand what was needed to do the
    job and could end up delaying completion or raising the
    cost of the radar system. 
    Raytheon, 121 Fed. Cl. at 141
    ,
    143 (Air Force notice to Raytheon and Northrop: “It is
    imperative the Offeror substantiate and the Government
    fully understand any claimed initiative which the Offeror
    desires to incorporate into its proposed cost/price.”); J.A.
    362, 394, 398–99, 1209, 1214, 1228, 50839–40.
    Raytheon, Northrop, and Lockheed submitted bids.
    
    Raytheon, 121 Fed. Cl. at 142
    . The Air Force thereafter
    sent Evaluation Notices to Raytheon and Northrop that
    addressed one means of reducing the costs that had to be
    built into the price for the radar-system contract—
    namely, treatment of certain costs as independent re-
    search and development (IR & D) costs. That classifica-
    tion addresses research conducted by a contractor but not
    4                                  RAYTHEON COMPANY    v. US
    specifically for a particular government project. See 48
    C.F.R. §§ 31.205-18, 9904.420. Although such work is
    contract-independent, its fruits can actually help the
    contractor deliver the goods and services promised in a
    particular contract. When that is so, the cost of work
    implicitly needed for a particular contract, which other-
    wise might have to be built into the price for that con-
    tract, may instead be treated as an IR & D cost, in which
    case the contractor may recover it through other means
    (such as, where allowed, by allocation across a wide range
    of government or private contracts). 48 C.F.R. § 31.205-
    18. The result is a “cost reduction” for the particular
    contract without compromising the contractor’s ability to
    fulfill its promises in that contract.
    In this case, the Air Force, citing a Federal Acquisi-
    tion Regulation (FAR) provision, stated in its initial
    notices to Raytheon and Northrop on the subject: “In
    accordance with (IAW) FAR 31.205-18 and 10 USC 2320
    [sic], any cost claimed or considered to be IR & D or a
    capital investment shall not be allowable as indirect
    charges for work implicitly required for performance
    (necessary to perform the contract) or explicitly required
    to be done by the terms of the contract.” J.A. 1210, 1215,
    quoted in 
    Raytheon, 121 Fed. Cl. at 143
    . “In other words,”
    as the Court of Federal Claims said, “the contractors
    would not be permitted to use IR & D costs to reduce their
    costs of performing the . . . contract if those costs were
    implicitly or explicitly required for contract performance.”
    
    Raytheon, 121 Fed. Cl. at 163
    –64 (emphasis added).
    In response, Northrop did not take issue with the
    agency’s statement precluding treatment of the cost of
    “implicitly required” work as an IR & D cost. See 
    id. at 143.
    The Court of Federal Claims found that Northrop
    “raised no objections to the Air Force’s statements regard-
    RAYTHEON COMPANY   v. US                                  5
    ing the allowability of IR & D costs.” 
    Id. at 165.
    1 Raythe-
    on, in contrast, did object. Raytheon told the agency that
    its statement was contrary to ATK Thiokol, Inc. v. United
    States, 
    598 F.3d 1329
    , 1334–35 (Fed. Cir. 2010), which,
    Raytheon said, “held that research and development costs
    are allowable as IR & D costs unless specifically required
    by the contract.” J.A. 1218, quoted in Raytheon, 121 Fed.
    Cl. at 143.
    What occurred thereafter is undisputed in the re-
    spects relevant to our decision. The Air Force changed its
    view: “the Air Force’s understanding changed to conform
    1    That finding refers to Northrop’s response to one
    of the Evaluation Notices, but it is true more generally.
    The Court of Federal Claims also stated that “[d]uring
    the first round of discussions, Northrop unambiguously
    disclaimed any reliance on IR & D cost reductions in
    response to one [Evaluation Notice].” 
    Id. We read
    that
    statement as finding only that Northrop at the time was
    not relying on IR & D cost reductions, not that Northrop
    disclaimed the possibility of relying on IR & D cost reduc-
    tions if the Air Force permitted. The broader reading
    would be unsupported. Earlier in the Court of Federal
    Claims’ opinion, where details are given, the only perti-
    nent specific finding about Northrop’s responses to the Air
    Force quotes Northrop as saying simply that “ ‘[t]he
    execution of this contract does not require . . . IR & D
    funding,’ ” 
    id. at 142
    (emphasis added), which does not
    make any disclaimers about whether Northrop would use
    IR & D funding if permitted. And in its complaint in this
    case, Raytheon acknowledged that “the GAO attorney
    [who gave the prediction of the GAO’s view that led the
    Air Force to reopen the award to Raytheon] said that
    Northrop had not disclaimed any possibility of relying on
    future IR&D in the event the Agency took a different
    view.” J.A. 72.
    6                                  RAYTHEON COMPANY    v. US
    to Raytheon’s interpretation; the [Evaluation Notices]
    that the Air Force had sent to Raytheon and Northrop no
    longer reflected its position on the allowability of IR & D
    costs related to implicit contract requirements.” Raythe-
    
    on, 121 Fed. Cl. at 147
    ; 
    id. at 164;
    J.A. 1837–39. The Air
    Force communicated its new view to Raytheon, in sub-
    stance if not in words, by accepting Raytheon’s treatment
    of certain costs as IR & D costs. In contrast, the Air Force
    never communicated its new view to Northrop—whose
    last communication on the subject from the government
    therefore remained the earlier, contrary view. “Thus, as
    far as Northrop was aware, the Air Force would not
    accept IR & D cost reductions for work implicitly required
    for contract performance.” 
    Raytheon, 121 Fed. Cl. at 164
    ;
    see 
    id. at 165,
    166.
    When the bidders later submitted their final pro-
    posals, Raytheon “proposed IR & D cost reductions” of a
    certain amount, 
    id. at 167,
    whereas Northrop did not
    “propos[e] IR & D cost reductions in line with the IR & D
    cost reductions proposed by Raytheon,” 
    id. at 146.
    The
    Air Force judged all three bidders to be in technical
    compliance, rated them the same on “all three technical
    subfactors,” and found “that all of the proposed costs and
    prices were reasonable and realistic.” 
    Id. at 145.
    Raythe-
    on had offered “the lowest total price” in the initial round
    of proposals, 
    id. at 142
    , and in the final proposals, Ray-
    theon received “the lowest Best Value Assessment,” 
    id. at 145
    (brackets deleted), a figure dependent on the final
    proposed prices, 
    id. at 141.
    See also 
    id. at 167
    (noting
    “differential in proposed prices” between Northrop and at
    least Raytheon). On that basis, the Air Force awarded
    the contract to Raytheon. 
    Id. at 145.
        Northrop and Lockheed filed a series of protests with
    the Government Accountability Office under 31 U.S.C.
    § 3551 et seq. See 
    Raytheon, 121 Fed. Cl. at 145
    –46. In
    one of the protests, Northrop challenged the Air Force’s
    RAYTHEON COMPANY   v. US                                  7
    communications about treating certain costs as IR & D
    costs. 
    Id. at 146.
    The Air Force defended its conduct. 
    Id. After a
    hearing before the GAO, “the GAO attorney
    assigned to the protests invited counsel for the parties to
    participate in an alternative dispute resolution outcome
    prediction conference,” at which the attorney would
    inform the parties how she was drafting a written deci-
    sion for the GAO, though there had not yet been a deci-
    sion. 
    Id. at 148.
    In the conference held on January 15,
    2015, the GAO attorney advised that, if the case proceed-
    ed to a final decision, it was “highly likely” that the GAO
    would sustain the protests “on only two grounds.” 
    Id. One of
    the grounds concerned IR & D costs: “the Air
    Force’s discussions with Northrop [on that subject] were
    misleading and unequal.” 
    Id. at 149.
    The GAO attorney
    “recommended that the Air Force . . . reopen cost/price
    discussions with all three contractors to explain its cur-
    rent view of the allowability of IR & D costs[ ] and permit
    the submission of new final proposal revisions.” 
    Id. The next
    day, in response to the GAO’s prediction, the
    Air Force wrote a letter to the GAO, with copies to the
    parties, saying that it had “decided to take corrective
    action.” J.A. 2239, quoted in 
    Raytheon, 121 Fed. Cl. at 149
    . In particular, it stated that it “intend[ed] to reopen
    discussions with all offerors to clarify the allowability of
    Independent Research and Development (IR & D) as it
    relates to the cost/price evaluation.” 
    Id. Raytheon filed
    a protest in the Court of Federal
    Claims under 28 U.S.C. § 1491(b) to challenge the Air
    Force’s decision to take corrective action. 
    Raytheon, 121 Fed. Cl. at 149
    . Following § 1491(b)(4)’s directive to apply
    the standards set forth in the Administrative Procedure
    Act, the court considered whether the Air Force’s decision
    to take corrective action “lacked a rational basis or in-
    volved a violation of regulation or procedure.” 
    Raytheon, 121 Fed. Cl. at 150
    . Under those standards, the court
    8                                  RAYTHEON COMPANY    v. US
    sustained the Air Force’s decision, and rejected Raythe-
    on’s challenge, on the administrative record. 
    Id. at 167–
    68.
    In particular, the court made the findings recited
    above regarding the Air Force’s disparate communication
    of its views about treating certain costs as IR & D costs.
    Among other things, it held that, by advising Raytheon
    but not Northrop “that it would accept IR & D cost reduc-
    tions notwithstanding the language of its [Evaluation
    Notices,] the Air Force engaged in unequal discussions
    with the contractors.” 
    Id. at 165.
    Quoting a regulatory
    command in the FAR that bars an acquiring agency from
    engaging in “conduct that . . . [f]avors one offeror over
    another,” 48 C.F.R. § 15.306(e)(1), the court explained
    that “[d]iscussions are unequal when a procuring agency
    favors ‘one offeror over another.’ ” 
    Raytheon, 121 Fed. Cl. at 164
    . Accordingly, the court held, the GAO attorney’s
    conclusion to that effect “was rational, and the Air Force’s
    reliance on her conclusion in deciding to take corrective
    action was also rational.” 
    Id. at 165.
         The court went on to reject Raytheon’s argument that
    Northrop had not shown that the Air Force’s conduct
    prejudiced Northrop. The court ruled that “the GAO
    attorney . . . implicitly concluded that Northrop had
    established that it was prejudiced by the Air Force’s
    misleading and unequal discussions,” i.e., that “Northrop
    had a substantial chance of receiving the contract in the
    absence of the Air Force’s misleading and unequal discus-
    sions.” 
    Id. at 167.
    The court held that conclusion to be
    rational, noting Northrop’s size as a government contrac-
    tor, the Air Force’s equal technical ratings of the bidders,
    the difference in the final proposed prices of Raytheon and
    Northrop, Raytheon’s proposed IR & D cost reductions,
    and, therefore, Northrop’s financial means to propose IR
    & D cost reductions of its own that could overcome the
    “differential in proposed prices.” 
    Id. RAYTHEON COMPANY
      v. US                                  9
    Raytheon appeals. We have jurisdiction under 28
    U.S.C. § 1295(a)(3). We now affirm.
    DISCUSSION
    A
    Raytheon accepts that, for us to uphold the Air Force
    decision to reopen the bidding process, it is sufficient for
    us to conclude that the grounds relied on by the Air
    Force—here, the grounds informally set out by the GAO
    attorney in predicting the GAO’s likely ruling on the
    protests of the initial award to Raytheon—rationally
    justified the reopening under governing law. See Raythe-
    on Opening Br. 51. We agree that such a conclusion
    suffices under the standards of the Administrative Proce-
    dure Act, which are incorporated by the bid-protest provi-
    sion under which this case was brought. 28 U.S.C.
    § 1491(b)(4); see Banknote Corp. of America v. United
    States, 
    365 F.3d 1345
    , 1350 (Fed. Cir. 2004) (following 5
    U.S.C. § 706(2)(A) for bid-protest cases). Moreover, we
    have upheld agency corrective actions taken on the basis
    of formal GAO determinations where the GAO determina-
    tions were rational. Honeywell, Inc. v. United States, 
    870 F.2d 644
    , 647 (Fed. Cir. 1989); Turner Construction Co. v.
    United States, 
    645 F.3d 1377
    , 1383 (Fed. Cir. 2011).
    Although this case involves a GAO outcome prediction,
    rather than a GAO decision, Raytheon accepts, and we
    agree, that rationality of the GAO outcome prediction
    should suffice. In stating what grounds are sufficient to
    uphold the bid reopening, we do not and need not say
    what grounds are necessary.
    We conclude that the Air Force’s unequal communica-
    tions regarding IR & D accounting, one of the GAO attor-
    ney’s grounds, provide a rational basis for the reopening.
    In 10 U.S.C. § 2305(f)(1), Congress provided that “[i]f, in
    connection with a protest, the head of an agency deter-
    mines that [an] . . . award does not comply with the
    requirements of law or regulation, the head of the agen-
    10                                 RAYTHEON COMPANY    v. US
    cy . . . may take any action set out in” 31 U.S.C.
    § 3554(b)(1)(A)–(F), and it is not disputed that the permit-
    ted actions include reopening of the bidding process here.
    See also 4 C.F.R. § 21.8 (GAO authority to recommend
    corrective actions, including where an “award does not
    comply with statute or regulation”); 48 C.F.R.
    § 33.102(b)(1) (similar for agency decision on protest).
    We conclude, agreeing with the GAO attorney, Air Force,
    and Court of Federal Claims, that the Air Force violated a
    regulation by its disparate communications regarding the
    treatment of costs as IR & D costs, a matter of potentially
    great importance to the bidder’s final bidding decisions.
    That violation provides a rational basis for reopening.
    Under 48 C.F.R. § 15.306(e)(1), “[g]overnment person-
    nel involved in the acquisition shall not engage in conduct
    that—(1) Favors one offeror over another.” That regula-
    tion, in its common-sense meaning in the context of
    competitive bidding, requires that the agency avoid giving
    materially disparate information to bidders on matters
    that could easily affect their decisions about important
    aspects of the final competing offers that the agency will
    be comparing. See, e.g., AshBritt, Inc. v. United States, 
    87 Fed. Cl. 344
    , 368–69 (2009); Metcalf Construction Co. v.
    United States, 
    53 Fed. Cl. 617
    , 625, 633–35 (2002); Dynacs
    Engineering Co. v. United States, 
    48 Fed. Cl. 124
    , 133–34
    (2000). The Air Force violated that requirement in com-
    municating an important position on cost accounting to
    Raytheon and Northrop, changing that position, then
    telling Raytheon but not Northrop of the change. Specifi-
    cally, the Air Force made clear to Raytheon that it could
    broadly use IR & D accounting—a matter of clear poten-
    tial importance to the bottom-line prices of the final
    bids—and did not give the same information to Northrop,
    leaving Northrop but not Raytheon to rely on the contrary
    position the Air Force had earlier stated to the two bid-
    ders. That disparity in information favored Raytheon
    over Northrop, in violation of the regulation.
    RAYTHEON COMPANY    v. US                                  11
    We also conclude that it was proper for the Court of
    Federal Claims to infer that the GAO attorney implicitly
    found that the violation was prejudicial. 
    Raytheon, 121 Fed. Cl. at 167
    . In many contexts, officials are presumed
    to be following the law governing their actions. See, e.g.,
    United States v. Chem. Found., Inc., 
    272 U.S. 1
    , 14–15
    (1926) (“The presumption of regularity supports the
    official acts of public officers, and, in the absence of clear
    evidence to the contrary, courts presume that they have
    properly discharged their official duties.”); Nat’l Archives
    & Records Admin. v. Favish, 
    541 U.S. 157
    , 174 (2004);
    PowerOasis, Inc. v. T-Mobile USA, Inc., 
    522 F.3d 1299
    ,
    1304 (Fed. Cir. 2008) (agency is “presumed to have
    properly done its job”). Here, in the absence of a written
    decision from the GAO—an absence inherent in the
    outcome-prediction situation presented—it is proper to
    presume that the GAO attorney was relying on the legal
    standards the GAO would have applied in deciding the
    protest, which include consideration of prejudice, 4 C.F.R.
    § 21.8(b), under the “substantial chance” standard appli-
    cable in bid protests in court, In re Lockheed Martin
    Integrated Systems, Inc., B-408134.3, B-408134.5, 2013
    CPD ¶ 169, 
    2013 WL 3830053
    , at *5 (Comp. Gen. July 3,
    2013) (“Competitive prejudice is an essential element of a
    viable protest; where the protester fails to demonstrate
    that, but for the agency’s actions, it would have had a
    substantial chance of receiving the award, there is no
    basis for finding prejudice, and our Office will not sustain
    the protest.”). And that presumption finds confirmation
    in this case because notes from the outcome-prediction
    conference refer to the GAO attorney’s remarks about
    prejudice in discussing at least one of the protests at
    issue. J.A. 2213, 2215.
    On the merits of the prejudice issue, we agree with
    the Court of Federal Claims’ determination that there
    was a sufficient factual basis for the GAO attorney, and
    hence the Air Force, to find a “substantial chance” that
    12                                  RAYTHEON COMPANY     v. US
    Northrop would have received the award. 
    Raytheon, 121 Fed. Cl. at 167
    . That standard does not require a finding
    that a losing bidder “would have received the contract.”
    Id.; see Bannum, Inc. v. United States, 
    404 F.3d 1346
    ,
    1358 (Fed. Cir. 2005). On this issue, which is a question
    of fact, Advanced Data Concepts, Inc. v. United States, 
    216 F.3d 1054
    , 1057 (Fed. Cir. 2000), the implicit finding by
    the GAO attorney, and hence the Air Force, was properly
    reviewed deferentially by the Court of Federal Claims in
    its ruling on the administrative record. We have recited
    the public evidence in support of the prejudice finding,
    focused on what Northrop could have done to shrink the
    “differential in proposed prices” in the final offers had it
    known what Raytheon knew about the Air Force’s change
    of position regarding treatment of costs as IR & D costs.
    
    Raytheon, 121 Fed. Cl. at 167
    . Confidential portions of
    the record bolster the public basis for finding prejudice.
    We conclude that the Court of Federal Claims properly
    upheld the implied finding of prejudice from the dispar-
    ate-information violation.
    B
    Raytheon’s challenges do not undermine the foregoing
    rationale for upholding the Air Force’s reopening of the
    bidding based on the disparity between what the Air
    Force told Raytheon and what it told Northrop about the
    permissibility of treating certain costs as IR & D costs.
    1. Raytheon contends that Northrop waived its chal-
    lenge on this ground by failing to complain to the Air
    Force before the award was made. Raytheon Br. 49–50.
    That contention relies on decisions establishing a general
    rule that a losing bidder waives a post-award challenge to
    the terms of a solicitation if it does not object to the terms
    before the bidding process closes. See Bannum, Inc. v.
    United States, 
    779 F.3d 1376
    , 1380 (Fed. Cir. 2015);
    COMINT Systems Corp. v. United States, 
    700 F.3d 1377
    ,
    1381–82 (Fed. Cir. 2012); Blue & Gold Fleet, L.P. v.
    RAYTHEON COMPANY    v. US                                 13
    United States, 
    492 F.3d 1308
    , 1315 (Fed. Cir. 2007);
    Statistica, Inc. v. Christopher, 
    102 F.3d 1577
    , 1582 (Fed.
    Cir. 1996). But that principle does not apply to the dis-
    parate-information violation here.
    The disparate-information violation was not an error
    in the solicitation. It occurred during the Air Force’s post-
    solicitation process of discussion and evaluation, and
    Northrop had no reason to know before the award was
    made that the Air Force had changed its mind about IR &
    D costs and had told Raytheon but not Northrop of the
    change. See 
    Raytheon, 121 Fed. Cl. at 166
    . This kind of
    violation has not been, and cannot sensibly be, subject to
    a requirement of objection before the bidding closes. See
    
    Bannum, 779 F.3d at 1381
    (“at least as a general matter,
    a bidder cannot be expected to challenge an agency’s
    evaluation of bids, in contrast to the terms of solicitation,
    until the evaluation occurs”); 
    COMINT, 700 F.3d at 1383
    n.6 (not applying waiver principle to challenge to agency
    action during evaluation process that challenger did not
    learn of until the award).
    2. Raytheon also argues that, under this court’s deci-
    sion in ATK Thiokol, the Air Force’s position expressly set
    forth in its initial IR & D announcement was so clearly
    inconsistent with the FAR regulation cited in that an-
    nouncement that this court must attribute to all bidders,
    including Northrop, knowledge of the correct understand-
    ing of IR & D treatment as a matter of law. Raytheon
    relies on attribution-of-knowledge reasoning in cases from
    other contexts, cases that resolve non-regulatory, non-
    protest issues distinct from the issues presented here. See
    
    Raytheon, 121 Fed. Cl. at 166
    (noting cases that involve
    claims for rescission or reformation of contracts). Raythe-
    on seeks to extend the attribution idea to this context. It
    contends that all bidders (hence Northrop) must be
    deemed to have had the same information as Raytheon (so
    that there was no unequal information) as a matter of
    law. Raytheon Br. 36–49. This contention is independent
    14                                 RAYTHEON COMPANY    v. US
    of the circumstances of any particular bidder in the pro-
    cess.
    The premise of Raytheon’s argument is that the Air
    Force’s initial view was clearly inconsistent with the cited
    FAR provision—an inconsistency that the Air Force did
    not initially perceive and that Northrop questions. But
    we need not rule on the soundness of that premise. Even
    without so ruling, we reject extension of the attribution-
    of-knowledge idea to cover the situation before us.
    The Air Force communicated disparate information to
    Raytheon and Northrop about its position regarding
    treatment of certain costs as IR & D costs. That disparity
    cannot be dismissed as a matter of law unless we can say
    that the information about the Air Force’s position simply
    could not have mattered in the bidding process (on the
    assumption that Raytheon is right about ATK Thiokol).
    Raytheon’s argument seeks to deny the facially evident
    regulatory violation based on disparate information by
    establishing that the particular information at issue—
    regarding the Air Force’s position on IR & D costs—so
    clearly could not matter to bidders that it must be disre-
    garded. We do not think that Raytheon has carried its
    burden of justifying that conclusion.
    3. Raytheon argues that Northrop in particular was
    not prejudiced by remaining in the dark about the Air
    Force’s revised view on the treatment of certain costs as
    IR & D costs. At bottom, Raytheon argues that Northrop
    would not have taken significant advantage of the new
    permissive approach to IR & D costs if it had known of the
    Air Force’s change of position before submitting its final
    bid. Raytheon Br. 50–60. Raytheon’s argument presents
    a record-specific question. The question is what Northrop
    might have done in its final offer had it been told of the
    new Air Force position. We think that the GAO attorney
    and the Air Force had sufficient reason to find prejudice
    RAYTHEON COMPANY   v. US                                 15
    under a substantial-chance standard, as the Court of
    Federal Claims held and as discussed above.
    At least in these circumstances, and perhaps more
    generally, there also is no basis for invoking a regulation
    that permits the government to “tailor” its discussions to
    particular bidders, 48 C.F.R. § 15.306(d)(1), to somehow
    negate or excuse the unequal-information violation.
    Accordingly, we hold that the government committed no
    error in reopening the bidding based on that violation.
    C
    The Air Force offered a second reason for reassessing
    its award to Raytheon—based, like the first, on the
    statements of the GAO attorney about a likely GAO
    ruling on the protests of that award. In particular, Ray-
    theon had made changes to the technology it was offering
    after the Air Force had conducted a technology assess-
    ment in an earlier round of the development process. The
    Air Force, following the GAO attorney, concluded that, in
    its final review leading to the award, it had not followed
    solicitation requirements for ensuring substantiation of
    the “technology readiness” of the altered “critical technol-
    ogy element” and therefore had to reassess Raytheon’s
    proposal. 
    Raytheon, 121 Fed. Cl. at 148
    –49.
    The Court of Federal Claims upheld that Air Force
    determination. 
    Id. at 160–63.
    But we need not address
    the issue. Raytheon has not offered, and we do not see,
    any reason that this technology-reassessment issue
    should be decided once we have concluded that the Air
    Force properly reopened the bidding process because of
    the unequal-information violation.
    CONCLUSION
    We affirm the judgment of the Court of Federal
    Claims denying Raytheon’s protest.
    No costs.
    16          RAYTHEON COMPANY   v. US
    AFFIRMED