Otay Mesa Property, L.P. v. United States , 779 F.3d 1315 ( 2015 )


Menu:
  •   United States Court of Appeals
    for the Federal Circuit
    ______________________
    OTAY MESA PROPERTY, L.P., RANCHO VISTA
    DEL MAR, OTAY INTERNATIONAL, LLC, OMC
    PROPERTY, LLC, D & D LANDHOLDINGS, LP,
    INTERNATIONAL INDUSTRIAL PARK, INC.,
    (also known as Rancho De La Fuente),
    Plaintiffs-Appellants
    KYDDLP & RDLFGFT NO. 1, LLC.,
    Plaintiff
    v.
    UNITED STATES,
    Defendant-Cross Appellant
    ______________________
    2013-5122, 2014-5002
    ______________________
    Appeals from the United States Court of Federal
    Claims in Nos. 06-CV-0167, 06-CV-0877, 06-CV-0876, 06-
    CV-1670 and 06-CV-1671, Judge Thomas C. Wheeler.
    ______________________
    Decided: March 6, 2015
    ______________________
    ROGER J. MARZULLA, Marzulla Law LLC, Washington,
    DC, argued for plaintiffs-appellants. Also represented by
    NANCIE GAIL MARZULLA.
    2                            OTAY MESA PROPERTY, L.P.   v. US
    JOHN EMAD ARBAB, Environment and Natural Re-
    sources Division, United States Department of Justice,
    Washington, DC argued for defendant-cross-appellant.
    Also represented by SAM HIRSCH.
    ______________________
    Before TARANTO, SCHALL, and CHEN, Circuit Judges.
    SCHALL, Circuit Judge.
    DECISION
    This is the second time this case has been before us.
    In Otay Mesa Property, L.P. v. United States, 
    670 F.3d 1358
    (Fed. Cir. 2012) (“Otay Mesa I”), we held that the
    United States was liable to plaintiffs Otay Mesa Property,
    L.P., Rancho Vista Del Mar, Otay International, LLC,
    OMC Property, LLC, D & D Landholdings, LP, and Inter-
    national Industrial Park, Inc. (collectively, “Otay Mesa”)
    for the taking of property owned by them. 1 Specifically,
    we ruled that the U.S. Border Patrol’s placement of
    motion sensors on five separate parcels of land owned by
    Otay Mesa adjacent to the Mexican border in Southern
    California constituted the taking of permanent easements
    over the parcels. 
    Id. at 1365.
    We remanded the case to
    the United States Court of Federal Claims for a determi-
    nation of the damages to which Otay Mesa was entitled as
    a result of the taking. 
    Id. at 1369–70.
        On remand, the Court of Federal Claims held (1) that
    Otay Mesa was entitled to no damages for the taking of
    an easement over land that could be developed for indus-
    trial use (“the development property”); (2) that it was
    1   In relevant part, the Fifth Amendment requires
    that the United States pay “just compensation” whenever
    it takes private property for public use. U.S. Const.
    amend. V (“[N]or shall private property be taken for
    public use, without just compensation.”).
    OTAY MESA PROPERTY, L.P.   v. US                            3
    entitled to damages in the amount of $455,520 for the
    taking of an easement over land that could be used for
    environmental mitigation purposes (“the mitigation
    property”); and (3) that interest on the $455,520 damages
    award should run from August 28, 2008, the date the
    court found Otay Mesa became aware of the taking as a
    result of the filing of a stipulation of liability by the
    government. Otay Mesa Prop., L.P. v. United States, 
    110 Fed. Cl. 732
    , 743–47 (2013) (“Otay Mesa II”) (interest on
    the damages award was initially deemed to run from
    October 16, 2008, but the date was adjusted following a
    motion for reconsideration, 
    111 Fed. Cl. 422
    , 424 (2013)
    (“Reconsideration Decision”)).
    Otay Mesa appeals the decision of the Court of Feder-
    al Claims denying damages for the taking of an easement
    over the development property. It also appeals the deci-
    sion of the court to compute interest on the $455,520
    damages award from August 28, 2008, rather than from
    the dates sensors were first installed on the parcels
    containing the mitigation property, as stated in the gov-
    ernment’s stipulation of liability. For its part, the gov-
    ernment cross-appeals the damages award for the taking
    of an easement over the mitigation property.
    For the reasons set forth below, we affirm the decision
    of the Court of Federal Claims denying damages for the
    taking of an easement over the development property.
    We also affirm the decision of the court awarding Otay
    Mesa $455,520 in damages for the taking of an easement
    over the mitigation property. However, we vacate the
    decision of the court computing interest on the $455,520
    damages award from August 28, 2008. As we explain,
    Otay Mesa is entitled to interest computed from when
    sensors were first placed on its property. The dates the
    Border Patrol first placed sensors on Otay Mesa’s proper-
    ty are set forth in the government’s stipulation of liability.
    We thus affirm-in-part, vacate-in-part, and remand. On
    remand, the Court of Federal Claims will determine the
    4                             OTAY MESA PROPERTY, L.P.   v. US
    amount of interest to which Otay Mesa is entitled on the
    $455,520 damages award.
    BACKGROUND
    The facts of the case are set forth in Otay Mesa I and
    in the several decisions of the Court of Federal Claims.
    We recite here the facts pertinent to the issues now before
    us.
    I.
    Otay Mesa owns eleven contiguous parcels of largely
    undeveloped land adjacent to the Mexican border in the
    Otay Mesa area of San Diego County. Otay Mesa 
    I, 670 F.3d at 1360
    . Five of those parcels, Nos. 1, 3, 4, 5, and 10,
    are at issue in this case. Beginning in April 1999 and
    continuing through November 2005, the Border Patrol
    placed a total of fourteen motion sensors on those parcels
    in order to detect illegal immigrants entering the United
    States from Mexico.       The motion sensors are approxi-
    mately one cubic foot in size and are buried underground,
    except for a one foot antenna that remains above the
    surface of the soil. Joint Appendix (“J.A.”) 1792 at ¶ 3; see
    also Otay Mesa 
    II, 110 Fed. Cl. at 734
    .
    In 2006, Otay Mesa filed suit in the Court of Federal
    Claims alleging, inter alia, that the installation of the
    sensors constituted a taking of Otay Mesa’s property,
    entitling it to “just compensation” under the Fifth
    Amendment’s Takings Clause. Otay Mesa Prop., L.P. v.
    United States, 
    86 Fed. Cl. 774
    , 775 (2009) (“Liability
    Decision”). 2 On August 28, 2008, prior to the trial on
    liability, the government filed a document in which it
    2    From our review of the record, it appears that
    plaintiff KYDDLP & RDLFGFT No. 1, LLC., is not named
    as an appellant here because the parcel it owns, or at one
    time owned, No. 9, is not at issue on appeal.
    OTAY MESA PROPERTY, L.P.   v. US                            5
    stipulated that “by virtue of its placement of the 14 sen-
    sors on the five parcels of land, it had taken a property
    interest in the nature of an easement over the parcel of
    land on which the sensors have been placed.” J.A. 1793 at
    ¶ 6; see also Liability 
    Decision, 86 Fed. Cl. at 777
    , 790–91.
    The document stated that the Border Patrol had installed
    sensors during the period beginning April 1999 and
    ending November 2005. The document described the
    easement, in relevant part, as:
    A perpetual and assignable easement to locate,
    construct, operate, maintain and repair or replace
    the specified underground seismic intrusion sen-
    sors on the specified parcels, including the right to
    ingress and egress to each sensor location. The
    easement shall be deemed to have commenced on
    the date the sensor is listed as having been in-
    stalled, and will continue until the sensor is no
    longer needed or the property is developed. Each
    sensor is and shall be located so as not to affect
    the functionality of the property. Should the
    landowner desire to develop any portion of the
    subject parcel, the sensor will be removed or rede-
    ployed upon 30 days written notice that a grading
    permit has been issued by the County of San Die-
    go permitting development of all or a portion of
    the property. Upon removal of a sensor, the por-
    tion of the easement relating to that sensor shall
    terminate.
    J.A. 1794 at ¶ 7; see also Otay Mesa 
    I, 670 F.3d at 1361
    –
    62.
    Based on the government’s stipulation, the Court of
    Federal Claims held that the government was liable for
    the physical taking of a temporary easement over the five
    parcels for the purpose of installing and operating the
    sensors. The court reserved the determination of damag-
    es for subsequent proceedings. Otay Mesa 
    I, 670 F.3d at 6
                                 OTAY MESA PROPERTY, L.P.   v. US
    1362. Following a trial on damages, the court determined
    that Otay Mesa was entitled to compensation in the
    amount of $3,043,051, plus interest for the taking of the
    easement. 
    Id. II. The
    government appealed the decision of the Court of
    Federal Claims. According to the government, the trial
    court incorrectly ruled that the taking of the easement
    was temporary rather than permanent. That ruling, the
    government contended, led the court to use the fair mar-
    ket rental value method of determining compensation,
    rather than the before-and-after method, which resulted
    in an erroneous calculation of Otay Mesa’s damages. 3 The
    government argued that, under the before-and-after
    method, Otay Mesa was entitled to only a nominal award,
    in view of the court’s finding that the use of the sensors
    had not resulted in any restriction on the functionality of
    the property. 
    Id. at 1363.
    For its part, Otay Mesa cross-
    appealed the Court of Federal Claims’ decision to limit
    the scope of the taking to five parcels of land (Nos. 1, 3, 4,
    5, and 10) and the time period (April 1999 through No-
    vember 2005) identified in the government’s stipulation.
    
    Id. In Otay
    Mesa I, we held that the Border Patrol’s blan-
    ket easement to install, maintain, and service sensors on
    Otay Mesa’s property constituted a permanent physical
    taking. 
    Id. at 1365.
    We thus remanded the case to the
    3    As we noted in Otay Mesa I, the usual measure of
    compensation for a temporary taking is the fair rental
    value of the property for the period of the taking, where-
    as, for a permanent taking, the owner is typically entitled
    to the diminution in the fair market value of the 
    property. 670 F.3d at 1364
    . The latter measure of compensation is
    sometimes referred to as the “before-and-after” method.
    OTAY MESA PROPERTY, L.P.   v. US                          7
    Court of Federal Claims for a redetermination of damag-
    es. We stated that, “[o]n remand, the court should deter-
    mine damages based upon the Border Patrol having taken
    a permanent blanket easement over Otay Mesa’s proper-
    ty, as set forth in the stipulation.” 
    Id. at 1368.
    We agreed
    with the government that the Court of Federal Claims
    erred in ruling that the Border Patrol had temporarily
    taken Otay Mesa’s property. We did not, however, en-
    dorse the government’s view that Otay Mesa’s damages
    should be determined based upon a before-and-after
    methodology. 
    Id. at 1369.
    Rather, we stated:
    As noted, the government has argued before
    us that Otay Mesa’s damages should be deter-
    mined based upon a before-and-after methodology.
    While diminution in value is a useful methodology
    in many cases, we reiterate that the focus of the
    damages analysis must always remain on award-
    ing just compensation for what has been taken.
    To award just compensation, a court must some-
    times deviate from the traditional permanent tak-
    ing-diminution in value and temporary taking-
    rental value approaches.
    
    Id. We thus
    instructed that, on remand, the Court of
    Federal Claims “will have discretion in identifying a
    methodology that fulfills the goal of awarding Otay Mesa
    just compensation.” 
    Id. We emphasized
    that what was
    important was for the focus to be on awarding just com-
    pensation for exactly what had been taken in the case.
    We identified what had been taken as “a minimally
    invasive permanent easement to use undeveloped land
    that is unilaterally terminable by Otay Mesa.” 
    Id. at 1368.
        Turning to Otay Mesa’s cross-appeal, we concluded
    that the Court of Federal Claims had not clearly erred
    when it limited the scope of the taking to the parcels of
    8                             OTAY MESA PROPERTY, L.P.   v. US
    land and the period of time identified in the government’s
    stipulation. 
    Id. at 1370.
    Accordingly, we affirmed-in-part
    and vacated-in-part the decision of the Court of Federal
    Claims. We remanded the case to the court for further
    proceedings consistent with our opinion. 
    Id. III. On
    remand, the Court of Federal Claims approached
    the damages issue by considering the two types of land
    that make up parcels 1, 3, 4, 5, and 10. The court deter-
    mined, and the parties generally agree, that of the 897
    acres of land at issue, approximately 278 acres are suita-
    ble for development (the development property), while
    approximately 619 acres are suitable for environmental
    mitigation purposes (the mitigation property). 4 Otay
    Mesa II, 110 Fed Cl. at 734, 738, 740. The court held that
    Otay Mesa was entitled to no damages for the taking of
    an easement over the development property. Based upon
    the evidence before it, the court determined that the
    sensor easement “would have no material effect” on the
    development property because Otay Mesa could have any
    sensors removed upon thirty days written notice that the
    4    In valuing real property, a primary consideration
    is its “highest and best use”—i.e., its most profitable use.
    Some of Otay Mesa’s property’s highest and best use is as
    mitigation land, which is land that qualifies under federal
    and state regulations for use by developers to offset
    development of other environmentally sensitive land.
    Otay Mesa 
    II, 110 Fed. Cl. at 735
    –36. Because developers
    may find it difficult to locate appropriate mitigation land,
    landowners can profit from selling certain land that
    compensates for adverse effects on protected species and
    habitats. 
    Id. at 736.
    The balance of Otay Mesa’s property
    has a highest and best use as land suitable for standard
    industrial development. 
    Id. at 738.
    OTAY MESA PROPERTY, L.P.   v. US                            9
    property had been approved for development. 
    Id. at 734,
    744.
    The Court of Federal Claims determined, however,
    that Otay Mesa was entitled to $455,520 in damages for
    the taking of an easement over the mitigation property.
    This figure represented five percent of the $9,110,400 fair
    market value appraisal for the mitigation property. 
    Id. at 747.
    Faced, on the one hand, with Otay Mesa’s argument
    that the placement of the sensors on the mitigation prop-
    erty had reduced the value of the property by forty per-
    cent, and on the other, by the government’s contention
    that the sensor placement had not had any effect on the
    value of the property, the court stated:
    Despite the Court’s conclusion that the conflicting
    evidence tilts in Defendant’s favor, the Court is
    not convinced that a landowner would willingly
    convey an interest in land to the Government for
    absolutely no compensation whatsoever, nor that
    the encumbrance has absolutely no effect on the
    value of the subject property. . . . Here, Plaintiffs
    undeniably face a risk that their environmentally
    sensitive property will not be approved for mitiga-
    tion use. The Court does not assess this risk to be
    anywhere near the 40 percent level advocated by
    [Otay Mesa’s expert], but the risk is significant
    enough that the Court cannot accept the Govern-
    ment’s position of a zero impact either. For Plain-
    tiffs to assume this risk without any compensation
    for the admitted Fifth Amendment taking would
    leave Plaintiffs in a worse position than before the
    taking occurred. . . . [I]t is plausible that the Gov-
    ernment’s sensor easement might prevent the use
    of Plaintiffs’ property for mitigation purposes.
    Even if this outcome never occurs, Plaintiffs’ as-
    sumption of the risk should be ascribed some val-
    ue.
    10                           OTAY MESA PROPERTY, L.P.   v. US
    
    Id. at 746–47.
         In its decision, the Court of Federal Claims awarded
    Otay Mesa interest from October 16, 2008, “the date,” the
    court stated, “on which [Otay Mesa] became aware of the
    taking through the Government’s filing of the stipula-
    tion.” 
    Id. at 747.
    Otay Mesa moved for reconsideration
    on the issue of interest. It argued that interest should
    run from April 1999, when the first sensor was installed
    on its property, not from the date when the government
    filed its stipulation of liability in 2008, which, in any
    event, was August 28, 2008, not October 16, 2008. The
    court granted the motion for the limited purpose of setting
    August 28, 2008, as the starting date for the computation
    of interest. Reconsideration 
    Decision, 111 Fed. Cl. at 424
    .
    In all other respects it denied it. The court acknowledged
    “the existence of ample case law holding that interest in a
    Fifth Amendment taking should run from the date of the
    taking.” 
    Id. at 423.
    It determined, though, that that
    proposition did not apply in this case. The court pointed
    out that, in arriving at its $455,520 damages award, it
    had ascribed a value (five percent) to the risk Otay Mesa
    assumed in having its property subjected to the govern-
    ment’s easement. Pointing to August 28, 2008, the court
    stated that, before that date, “only the Government knew
    that the sensors were in use on Otay Mesa’s property.”
    
    Id. at 424.
    The court reasoned, “[i]f no person or entity
    outside of the Government was aware of the sensors until
    the disclosure date in 2008, the risk on which the Court’s
    damages award is based did not exist until 2008.” 
    Id. On July
    22, 2013, the Court of Federal Claims entered
    judgment awarding Otay Mesa damages in the amount of
    $455,520, with interest computed on that amount from
    August 28, 2008. Otay Mesa’s current appeal and the
    government’s cross-appeal followed. We have jurisdiction
    pursuant to 28 U.S.C. § 1295(a)(3).
    OTAY MESA PROPERTY, L.P.   v. US                        11
    DISCUSSION
    Following a damages trial, we review the Court of
    Federal Claims’ legal conclusions de novo and its factual
    findings for clear error. Ind. Mich. Power Co. v. United
    States, 
    422 F.3d 1369
    , 1373 (Fed. Cir. 2005); Am. Pelagic
    Fishing Co. v. United States, 
    379 F.3d 1363
    , 1371 (Fed.
    Cir. 2004). “A finding is ‘clearly erroneous’ when alt-
    hough there is evidence to support it, the reviewing court
    on the entire evidence is left with the definite and firm
    conviction that a mistake has been committed.” Renda
    Marine, Inc. v. United States, 
    509 F.3d 1372
    , 1378 (Fed.
    Cir. 2007) (quoting United States v. U.S. Gypsum Co., 
    333 U.S. 364
    , 395 (1948)).
    As noted above, Otay Mesa appeals the denial of
    damages for the taking of an easement over the develop-
    ment property. The government cross-appeals the award
    of damages for the taking of an easement over the mitiga-
    tion property. And Otay Mesa appeals the court’s deci-
    sion not to award interest from the date sensors were first
    installed on the parcels containing mitigation property. 5
    We first address Otay Mesa’s appeal with respect to the
    development property.
    I.
    A.
    The Court of Federal Claims found that the “Border
    Patrol’s sensor easement would have no material effect on
    5    In its motion for reconsideration, Otay Mesa re-
    quested that interest run from the date the first sensor
    was installed, in April 1999. Reconsideration 
    Decision, 111 Fed. Cl. at 424
    . On appeal, Otay Mesa argues that
    interest should run from the date a sensor was first
    installed on each respective parcel containing mitigation
    property.
    12                           OTAY MESA PROPERTY, L.P.   v. US
    the developable land” and denied damages for the gov-
    ernment’s easement over that portion of Otay Mesa’s
    property. Otay Mesa 
    II, 110 F.3d at 734
    . While Otay
    Mesa’s expert witness testified that the easement caused
    a ten percent diminution in the value of the development
    property, the court found much of that evidence to be
    “minimally persuasive,” and instead credited the govern-
    ment’s evidence to the contrary. After weighing the
    competing evidence, the court ultimately held that Otay
    Mesa “failed to prove actual damages with respect to a
    diminution in value of developable land.” 
    Id. On appeal,
    Otay Mesa contends that it met its burden
    of showing a fair and reasonable approximation of dam-
    ages as to the development property. See Ark. Game &
    Fish Comm’n v. United States, 
    736 F.3d 1364
    , 1379 (Fed.
    Cir. 2013); Precision Pine & Timber Inc. v. United States,
    
    596 F.3d 817
    , 833 (Fed. Cir. 2010). It argues that all that
    was required to prove its damages case was “reasonable
    certainty,” not absolute precision. Otay Mesa states that,
    in addition to its diminution in value theory, it presented
    evidence showing that other parties, such as utility com-
    panies and the Border Patrol itself, paid relatively large
    sums for easements over the development property in
    question and other nearby land owned by Otay Mesa. It
    points to testimony suggesting that the very existence of
    the easement could negatively affect the ability to receive
    project approvals. Otay Mesa argues that the court
    ignored much of this evidence and, thus, its decision to
    deny damages was clearly erroneous. It contends that the
    court’s holding amounts to a conclusion that Otay Mesa
    would have conveyed the easement to the government for
    no consideration at all.
    In response, the government contends that Otay Me-
    sa’s evidence was not ignored, but, rather, was considered
    and found to be insufficient, or was not probative of
    damages. The government points out that the Court of
    Federal Claims discounted Otay Mesa’s expert witness’s
    OTAY MESA PROPERTY, L.P.   v. US                          13
    valuation as being premised on faulty assumptions. The
    government also states that evidence relating to prior
    easements over Otay Mesa’s property was not presented
    during the remand trial and that, in any event, those
    easements were not probative of damages because they
    were not examples of the “minimally invasive” or “unilat-
    erally terminable” easements at issue here. Unlike the
    prior easements, the government points out, the sensor
    easements require the Border Patrol to remove or rede-
    ploy the sensors upon thirty days written notice. The
    government reasons that, because Otay Mesa failed to
    provide reliable expert witness evidence or to produce any
    comparable easement sales, the court’s decision to credit
    the government’s valuation and to deny damages was not
    clearly erroneous.
    B.
    We conclude that the Court of Federal Claims’ deci-
    sion to deny damages for the easement over 278 acres of
    development property was not clear error. As an initial
    matter, the fact that a taking occurred does not itself
    establish what compensation should be awarded. What is
    critical in the determination of just compensation is not
    the gain to the government from the taking, but the
    actual loss to the landowner. United States ex rel. Tenn.
    Valley Auth. v. Powelson, 
    319 U.S. 266
    , 281 (1943) (noting
    the “well settled rule” that it is “the owner’s loss, not the
    taker’s gain, which is the measure of compensation for the
    property taken”); United States v. Chandler-Dunbar
    Water Power Co., 
    229 U.S. 53
    , 80–81 (1913) (“[I]n a con-
    demnation proceeding, the value of the property to the
    government for its particular use is not a criterion.”).
    Once a taking has been established, it is the landowner
    who bears the burden of proving an actual loss has oc-
    curred. Bd. of Cnty. Supervisors of Prince William Cnty.,
    Va. v. United States, 
    276 F.3d 1359
    , 1364 (Fed. Cir. 2002).
    To carry its burden, the landowner must show actual
    damages “with reasonable certainly,” which “requires
    14                           OTAY MESA PROPERTY, L.P.   v. US
    more than a guess, but less than absolute exactness.”
    Precision 
    Pine, 596 F.3d at 833
    .
    During the trial on remand, Otay Mesa presented just
    one expert, Randy Tagg. Mr. Tagg, who is an appraiser,
    testified as to the damages resulting from the taking of an
    easement over the development property. Mr. Tagg’s
    assertion that there was a ten percent diminution in the
    value of the development property was based on the prior
    testimony of a witness from the 2009 trial and on the
    results of a telephonic market survey. Otay Mesa 
    II, 110 F.3d at 743
    . In weighting the credibility of Mr. Tagg’s
    damages assessment, the Court of Federal Claims found
    that the prior testimony contained “pervasive generali-
    ties” and was based on the “mistaken assumption” that
    the easement does not limit the number of sensors. 
    Id. The court
    also found that Mr. Tagg’s telephonic market
    survey of land developers was “casual, undocumented,
    and narrow,” consisting of only seven telephone calls and
    four responses. 
    Id. at 744.
    Two of the responsive partici-
    pants, the court noted, refused to provide any estimate of
    diminution of value, while the other two responses were
    “minimally persuasive,” as they were also premised on the
    erroneous assumption that the easement does not limit
    the number of sensors allowed on the property. 
    Id. Mr. Tagg,
    the court stated, “exchanged no written correspond-
    ence with these developers, and his work files [did] not
    contain any notes of his conversations with them.” 
    Id. at 739.
    It was the judgment of the court that, considering
    foundational flaws of Mr. Tagg’s valuation, a “ten percent
    reduction in value [was] dubious.” 
    Id. at 744.
        On the other hand, the Court of Federal Claims found
    the testimony of the government’s expert witness—who
    testified that the easement would have no impact on the
    development property—to be “much more instructive.” 
    Id. The government’s
    expert, Stephen Roach, an appraiser in
    San Diego, based his valuation on the wording of the
    easement itself. First, Mr. Roach concluded that the
    OTAY MESA PROPERTY, L.P.   v. US                        15
    easement was limited to no more than fourteen sensors.
    
    Id. at 740.
    Second, he found that the language stating
    that, “should the landowner desire to develop any por-
    tion . . . , the sensor will be removed or redeployed upon
    30 days written notice that a grading permit has been
    issued by the County of San Diego” meant there could be
    no measurable effect on the suitability of the development
    property for future development. 
    Id. That conclusion
    was
    buttressed by the prior testimony of Richard Shick, one of
    the government’s experts from the 2009 trial. Mr. Shick,
    who is project manager for the County of San Diego
    Department of Public Works, was designated as the most
    knowledgeable in his department on the impact of ease-
    ments on the process of receiving grading permits for the
    development of land. 
    Id. His work
    responsibilities in-
    cluded issuing grading permits for development of land
    within the central and southern regions of San Diego
    County, where Otay Mesa’s property lies. J.A. 889. His
    opinion in 2009 was that the easement would likely not
    prevent his department from issuing a grading permit,
    but might result in an “advisory note” on the development
    plans advising the applicant to notify the United States
    within thirty days of issuance. Otay Mesa 
    II, 110 F.3d at 737
    .
    We agree with the Court of Federal Claims that the
    government’s position on the development property is
    much more persuasive than that of Otay Mesa. Otay
    Mesa presents no persuasive argument why, in view of
    the language of the stipulation, it was clear error for the
    court to credit the government’s zero-damage valuation
    over its own clearly flawed ten-percent-diminution valua-
    tion. The Court of Federal Claims properly exercised its
    judgment in its role as the trier of fact by weighting the
    credibility of the respective witnesses and their before-
    and-after valuations of the land.
    Otay Mesa’s contention that the Court of Federal
    Claims ignored relevant evidence stems from its belief
    16                           OTAY MESA PROPERTY, L.P.   v. US
    that the trial court was required to construct a damages
    valuation from evidence presented during the 2009 trial,
    despite such evidence never being formally presented
    during the remand trial. Although we believe the trial
    court was properly within its discretion in denying dam-
    ages based on the evidence presented during the trial on
    remand, we nevertheless address Otay Mesa’s argument.
    Specifically, although Otay Mesa concedes that it was
    unable to find any “comparable” easements sales, it urges
    that the Court of Federal Claims should have used prior,
    tangentially-related easement sales to create its own
    valuation of the property. The prior easements identified
    by Otay Mesa are easements that it sold for underground
    pipelines for sewer, water, gas, and electricity; they also
    are easements for roads and overhead power lines. While
    those sales may show that substantial value has been
    paid for easements over the subject land, we are unper-
    suaded that the mere existence of easements that are
    neither “minimally invasive” nor “unilaterally terminable”
    provides a basis for determining that the Court of Federal
    Claims committed clear error in accepting the govern-
    ment’s zero-damages valuation. Unassisted by expert
    reports or trial testimony on how those utility and road
    easements relate to the permanent sensor easements at
    issue here, the court was left to speculate as to how those
    easements would factor into a supposedly proper “just
    compensation” calculation. The court was not obligated to
    construct a damages award for Otay Mesa when it had
    substantial, credible evidence before it indicating that no
    actual loss was suffered. Vaizburd v. United States, 
    384 F.3d 1278
    , 1284–85 (Fed. Cir. 2004) (rejecting the “propo-
    sition that a court may not adopt one party’s credible
    appraisal over the other party’s less credible appraisal”
    and holding that the taking “did not diminish the market
    value of the [landowner’s] property”).
    In Precision Point, we concluded that a trial court is
    not necessarily stuck with the “stark choice” of accepting
    OTAY MESA PROPERTY, L.P.   v. US                            17
    or rejecting a party’s valuation, but it did not foreclose
    that 
    option. 596 F.3d at 832
    . “As the fact finder in the
    bench trial, the judge is responsible for deciding what
    evidence to credit or reject and what result to reach,”
    which is precisely what the trial judge did here. 
    Id. at 833.
    As we explained in Precision Point, while we may
    know more on an appeal from a bench trial than from a
    jury trial as a result of a written opinion, it “does not alter
    th[e] judge’s discretion to weigh evidence or our standard
    of review.” 
    Id. Similarly, in
    Yaist v. United States, the
    court noted that, where comparable sales data is lacking,
    it is permissible to fashion a damages award from “other
    evidence,” so long as it is “premised on a reasonably
    informed basis.” 
    17 Cl. Ct. 246
    , 257 (1989). Contrary to
    Otay Mesa’s contentions, it is doubtful whether the prior
    easement sales, without more, could have provided a
    “reasonably informed basis” to value a unique sensor
    easement that is minimally invasive, unilaterally termi-
    nable, and must also not affect the functionality of the
    land for development purposes.
    Finally, Otay Mesa calls it a “paradox” and “irrecon-
    cilable” that, as a temporary easement, the encumbrance
    had substantial value, yet as a permanent easement it
    was denied damages. But as we explained in Otay Mesa
    I, the prior valuation was based exclusively on the rental
    value of the property for skydiving and parachute train-
    
    ing. 670 F.3d at 1368
    . That rental market methodology
    was erroneous. 
    Id. Indeed, we
    explicitly instructed the
    Court of Federal Claims on remand not to “overlook
    exactly what has been taken by the Border Patrol—a
    minimally invasive permanent easement to use undevel-
    oped land that is unilaterally terminable by Otay Mesa.”
    
    Id. We reminded
    the court that, “should Otay Mesa wish
    to develop any portion of the property, any affected sensor
    will be removed or redeployed upon 30 days written
    notice” of a grading permit issuance. 
    Id. at 1369.
    And,
    we gave the court great leeway “to fashion an appropriate
    18                            OTAY MESA PROPERTY, L.P.   v. US
    measure of compensation.” 
    Id. In our
    view, considering
    the whole record before the court, it was not clear error to
    accept the government’s position and to deny damages for
    the development property.
    II.
    A.
    Following the damages trial on remand, the Court of
    Federal Claims rejected the government’s zero-percent
    diminution valuation of the mitigation property, as well
    as Otay Mesa’s forty-percent-diminution valuation. Otay
    Mesa 
    II, 110 Fed. Cl. at 746
    . The court then exercised its
    discretion in formulating a damages award that it be-
    lieved accounted for the real, but minimal, risk that the
    property would be rejected for mitigation use due to the
    sensor easement over it. 
    Id. at 747.
    It awarded $455,520
    for the taking of a permanent easement over Otay Mesa’s
    mitigation property—an award of five percent of the
    property’s $9,110,400 fair market value. 
    Id. The government
    now cross-appeals that award. It ar-
    gues that the damages award is based on clearly errone-
    ous factual findings and that it is inconsistent with other
    conclusions in the Court of Federal Claims’ damages
    decision. Specifically, the government contends that the
    court found that the easement would not affect the biolog-
    ical resources of the mitigation land. See 
    id. at 745.
    In
    addition, it notes that the court found that, even after the
    sensors were placed on its property, Otay Mesa used
    portions of the property for mitigation purposes. Recon-
    sideration 
    Decision, 111 Fed. Cl. at 424
    . It further points
    out that evidence was presented during the 2009 trial
    indicating that the sensors would have no measurable
    impact on the use of Otay Mesa’s land for mitigation
    purposes. Otay Mesa 
    II, 110 Fed. Cl. at 737
    . The gov-
    ernment, in other words, argues that there is no credible
    evidence from which the Court of Federal Claims could
    OTAY MESA PROPERTY, L.P.   v. US                         19
    conclude that there was a five percent risk that the prop-
    erty would not be approved for mitigation use.
    Otay Mesa responds that, even though the Court of
    Federal Claims arrived at a damages award that neither
    party suggested, it was well within its broad discretion to
    do so. It argues that the court had ample evidence from
    which it could conclude that Otay Mesa’s land might not
    be approved for mitigation use. It contends that its
    appraiser, Mr. Tagg, as well as its other witnesses, testi-
    fied that there would be a diminution in the value of land
    as mitigation property as a result of an easement that
    provides for installation of sensors, as well as for ingress
    and egress to and from the sensors. It points, for exam-
    ple, to its expert on mitigation, James Carter, who testi-
    fied that ingress and egress to the sensors, in addition to
    the redeployment and relocation of the sensors, would
    negatively impact the ability to find a management com-
    pany that would take title to the land. J.A. 681–82. It
    explains that the Court of Federal Claims did not sua
    sponte fashion an arbitrary “risk” award, as it is charac-
    terized by the government, but that the court laid out
    factual bases for awarding a five percent diminution in
    value due to the identified risk.
    B.
    We conclude that the Court of Federal Claims proper-
    ly exercised its discretion in shaping an award that ac-
    counted for the potential that the mitigation property
    might not be approved for mitigation use. As noted above,
    we explicitly instructed that “on remand the Court of
    Federal Claims will have discretion in identifying a
    methodology that fulfills the goal of awarding Otay Mesa
    just compensation.” Otay Mesa 
    I, 670 F.3d at 1369
    .
    During the damages trial on remand, the court was
    confronted with conflicting evidence and relatively ex-
    treme valuations for the mitigation property—proposals
    of zero percent or forty percent diminution in value.
    20                              OTAY MESA PROPERTY, L.P.   v. US
    Recognizing that the “Plaintiffs undeniably face a risk
    that their environmentally sensitive property will not be
    approved for mitigation use,” but that the risk was not
    “anywhere near the 40 percent [diminution in value] level
    advocated by Mr. Tagg,” the court chose its own valuation
    that captured what it perceived as the risk of a “potential
    denial of a mitigation request.” Otay Mesa 
    II, 110 Fed. Cl. at 734
    , 746. It explained that, “[e]ven if this outcome
    never occurs, Plaintiffs’ assumption of the risk should be
    ascribed some value.” 
    Id. at 746.
    It found that Otay
    Mesa would not have willingly assumed that risk for its
    mitigation property without some, albeit minimal, consid-
    eration. 
    Id. We detect
    nothing inappropriate with the Court of
    Federal Claims looking at the evidence as a whole and
    using its own methodology to calculate a damages award.
    Contrary to the government’s assertion, the court’s deci-
    sion to ascribe its own valuation to the damages associat-
    ed with the mitigation land is consistent with both our
    instruction on remand and our case law. In Precision
    Pine, discussed above, we made clear that a trial court
    need not accept either party’s damages 
    position. 596 F.3d at 832
    –33. We explained that it is both correct and im-
    portant for a trial court to use its flexibility to tailor a fair
    and reasonable result based on the evidence it credits or
    rejects. Id.; see also Seravalli v. United States, 
    845 F.2d 1571
    , 1575 (Fed. Cir. 1988) (“[Trial] courts necessarily
    must have considerable discretion to select the method of
    valuation that is most appropriate in the light of the facts
    of the particular case.”). Here, where the parties took
    divergent and extreme positions, and the court believed
    that the landowner was in a worse position after the
    taking, the court had few options in determining a just
    OTAY MESA PROPERTY, L.P.   v. US                          21
    compensation award other than creating its own valua-
    tion. 6
    Moreover, the government overlooks that many of the
    arguments it advances for why it was not clear error for
    the Court of Federal Claims to deny damages for the
    easement over the development property likewise apply to
    the court’s decision to award damages for the easement
    over the mitigation property. When a trial court provides
    a damages award that is within the range of credible
    testimony, it is not an appellate court’s role to reweigh the
    evidence or second-guess the finder of fact. E.g., Rapid
    Transit Co. v. United States, 
    295 F.2d 465
    , 467 (10th Cir.
    1961) (finding that “[s]ince the award was well within the
    range of credible testimony this court may not reweigh
    the evidence or retry the facts”), cert. denied, 
    369 U.S. 819
    . The Court of Federal Claims’ five-percent award for
    the mitigation property—like its denial of damages for the
    development property—is reasonable on the evidence.
    III.
    A.
    Last, we address Otay Mesa’s appeal with respect to
    the date from which interest on its damages award should
    be calculated. Following the trial on remand, the Court of
    Federal Claims awarded compound interest from October
    16, 2008, the date on which it believed Otay Mesa first
    became aware of the taking through the government’s
    stipulation. Otay Mesa 
    II, 110 Fed. Cl. at 747
    . On recon-
    sideration, the trial court “acknowledge[d] the existence of
    6   To the extent the government contends that the
    court’s methodology is inconsistent with the methodology
    used in the original damages decision, that decision was
    based on the notion that the taking was temporary in
    nature. As discussed above, that methodology was incor-
    rect and was based on a rental value calculation.
    22                            OTAY MESA PROPERTY, L.P.   v. US
    ample case law holding that interest in a Fifth Amend-
    ment taking should run from the date of the taking,” but
    declined to adjust the date beyond granting a change from
    October to August 2008, when the government’s stipula-
    tion was first filed. Reconsideration 
    Decision, 111 Fed. Cl. at 423
    . The court believed that “[i]f no person or entity
    outside of the Government was aware of the sensors until
    the disclosure date in 2008, the risk on which the Court’s
    damages award is based did not exist until 2008.” 
    Id. On appeal,
    Otay Mesa argues that the case law is un-
    equivocal that interest must be calculated from the date
    of the taking. And it argues that the date of the taking
    cannot be disputed, as the government expressly listed
    the dates that each sensor was first installed on the
    subject property in its 2008 stipulation. In response, the
    government defends the Court of Federal Claims’ deci-
    sion. It does so, not by arguing that the case law allows
    for interest to be computed from some other point in time
    other than the date of the taking, but, rather, by contend-
    ing that, since no damage occurred before 2008, the court
    essentially applied an interest rate on zero damages from
    the date of the taking until the date of the government’s
    stipulation. It argues that before the stipulation Otay
    Mesa did not know about the sensors and therefore could
    not have suffered any damages on which interest could be
    compounded. Awarding Otay Mesa interest from a date
    prior to the 2008 stipulation, the government contends,
    would place it in a better position than if the taking had
    never occurred.
    B.
    We hold, as a matter of law, that interest on Otay Me-
    sa’s damages award must be calculated from the date
    sensors first encumbered Otay Mesa’s property. The
    Supreme Court has long held that “just compensation”
    includes interest compounded from the date of a taking
    when payment for the taking does not coincide with the
    OTAY MESA PROPERTY, L.P.   v. US                          23
    taking itself. Phelps v. United States, 
    274 U.S. 341
    , 344
    (1927); Seaboard Air Line Ry. Co. v. United States, 
    261 U.S. 299
    , 306 (1923). In Phelps, the Court recognized that
    the “Plaintiffs’ property was taken before its value was
    ascertained or 
    paid.” 274 U.S. at 344
    . It explained that
    the “[j]udgment in 1926 for the value of the use of the
    property in 1918 and 1919, without more, [was] not
    sufficient to constitute just compensation.” 
    Id. The Court
    instructed that the landowner was “entitled to have the
    full equivalent of the value of such use at the time of the
    taking paid contemporaneously with the taking.” 
    Id. Thus, “if
    disbursement of the award is delayed, the
    owner is entitled to interest thereon sufficient to ensure
    that he is placed in as good a position pecuniarily as he
    would have occupied if the payment had coincided with
    the appropriation.” Kirby Forest Indus., Inc. v. United
    States, 
    467 U.S. 1
    , 10 (1984) (citing 
    Phelps, 274 U.S. at 344
    and 
    Seaboard, 261 U.S. at 306
    ). In order for an
    owner to be placed in “as good a position pecuniarily,”
    interest must be added to the damages award in order to
    compensate for the time value of money and the potential
    opportunity the owner has lost to earn income on its
    damages award as a result of the taking. It is now axio-
    matic that “the Fifth Amendment’s reference to ‘just
    compensation’ entitles the property owner to receive
    interest from the date of the taking to the date of payment
    as a part of his just compensation.” United States v.
    Thayer-W. Point Hotel Co., 
    329 U.S. 585
    , 588 (1947); see
    also Jacobs v. United States, 
    290 U.S. 13
    , 17 (1933)
    (“[J]ust compensation is comprehensive, and includes all
    elements, ‘and no specific command to include interest is
    necessary when interest is part of such compensation.’”).
    Here, as in Kirby Forest, the government stipulated to
    the precise date of its taking. It conceded in its 2008
    stipulation that “by virtue of its placement of the 14
    sensors specified above on the listed parcels of land, it has
    taken a property interest in the nature of an easement.”
    24                             OTAY MESA PROPERTY, L.P.   v. US
    J.A. 1793 at ¶ 6 (emphasis added). It stipulated that the
    “easement shall be deemed to have commenced on the
    date the sensor is listed as having been installed.” J.A.
    1794 at ¶ 7. The stipulation also enumerates the dates
    that each sensor was first installed: dates ranging from
    April 1999 to November 2005. J.A. 1793 at ¶ 5. Because
    the government’s payment of consideration for its taking
    was not paid contemporaneously with the taking, Otay
    Mesa is now entitled to interest “sufficient to ensure that
    [it] is placed in as good a position pecuniarily as [it] would
    have occupied if the payment had coincided with the
    appropriation.” Kirby 
    Forest, 467 U.S. at 10
    .
    We are not persuaded by the Court of Federal Claims’
    and the government’s justifications for why interest
    should not begin to run until the date of the government’s
    stipulation. To begin with, delaying the running of inter-
    est until Otay Mesa supposedly first knew about the
    taking would be contrary to the established precedent just
    discussed.    Moreover, if the government’s easement
    created a risk that Otay Mesa’s mitigation land might be
    denied approval for mitigation use as of 2008, then the
    sensor easement would have also created the same risk
    when the land was first encumbered. Otay Mesa’s
    knowledge of the easement is irrelevant to whether the
    easement objectively created that risk. Finally, if interest
    is not computed from the date of the taking, but instead
    from the date a landowner is first made aware of the
    taking, the government is presented with an incentive to
    delay disclosure of physical invasion for as long as possi-
    ble. We see no logic in creating such an incentive.
    Accordingly, we vacate the decision of the Court of
    Federal Claims to award interest from August 28, 2008,
    and remand for recalculation of the interest owed to Otay
    Mesa. As noted, Otay Mesa argues before us that interest
    should be calculated based on the different dates that the
    respective parcels constituting the mitigation property
    were first encumbered by a sensor easement. The gov-
    OTAY MESA PROPERTY, L.P.   v. US                       25
    ernment has not proposed a method for calculating inter-
    est in the event that we rule against it. On remand, after
    receiving the views of the parties, the Court of Federal
    Claims will be in a position to formulate a methodology
    for calculating interest.
    CONCLUSION
    For the foregoing reasons, we affirm-in-part and va-
    cate-in-part the decision of the Court of Federal Claims.
    The case is remanded to the court for further proceedings
    consistent with this opinion.
    AFFIRMED-IN-PART, VACATED-IN-PART, and
    REMANDED
    COSTS
    Each party shall bear its own costs.