M.E.S., Inc. v. McHugh , 502 F. App'x 934 ( 2013 )


Menu:
  •        NOTE: This disposition is nonprecedential.
    United States Court of Appeals
    for the Federal Circuit
    ______________________
    M.E.S., INC.,
    Appellant,
    v.
    JOHN MCHUGH, SECRETARY OF THE ARMY,
    Appellee.
    ______________________
    2012-1457, -1466
    ______________________
    Appeal from the Armed Services Board of Contract
    Appeals in Nos. 56349, 57074, Administrative Judge
    Monroe E. Freeman, Jr.
    ______________________
    Decided: January 15, 2013
    ______________________
    MICHAEL H. PAYNE, Cohen Seglias Pallas Greenhall &
    Furman, of Philadelphia, Pennsylvania, for appellant. Of
    counsel was JOSEPH A. HACKENBRACHT, JR.
    DANIEL B. VOLK, Trial Attorney, Commercial Litiga-
    tion Branch, Civil Division, United States Department of
    Justice, of Washington, DC, for appellee. With him on the
    brief were STUART F. DELERY, Acting Assistant Attorney
    2                                        M.E.S., INC.   v. ARMY
    General, JEANNE E. DAVIDSON, Director, BRYANT G. SNEE,
    Deputy Director.
    ______________________
    Before DYK, MOORE, and WALLACH, Circuit Judges.
    PER CURIAM.
    M.E.S., Inc. appeals a decision by the Armed Services
    Board of Contract Appeals (“Board”) denying M.E.S.’s
    claims for equitable adjustments under a construction
    contract. The Board found that M.E.S. had failed to
    present sufficient evidence to support the two claims at
    issue in this appeal. We affirm.
    BACKGROUND
    On September 29, 2001, the U.S. Army Corps of En-
    gineers (“Corps”) awarded M.E.S. a $10.3 million firm-
    fixed-price contract to design and build a fitness center at
    McGuire Air Force Base in New Jersey. The scheduled
    duration of the contract was 720 days, with a planned
    completion date of November 4, 2003. The project was
    repeatedly delayed, for reasons ranging from unusually
    severe weather to the discovery of unexpected quantities
    of asbestos in the existing structure. The Corps agreed to
    postpone the contract completion date twelve times,
    extending its duration by 345 days and awarding M.E.S.
    $626,469 in additional compensation. Three of the modifi-
    cations were issued unilaterally by the Corps, and most of
    the remaining, bilateral modifications included a clause
    reserving M.E.S.’s right “to request additional compensa-
    tion for the delay and impact costs, as well as any ad-
    justment to the Overhead charged.” J.A. 3. Though M.E.S.
    disputes it, at least one modification appears to have
    included an allowance for additional home office overhead
    accrued by M.E.S. as a result of the delay. The work was
    substantially completed on October 14, 2004.
    M.E.S., INC.   v. ARMY                                  3
    M.E.S. submitted five claims for equitable adjust-
    ments to the Corps’ contracting officer, totaling
    $1,250,597.33 (later amended to $1,593,949). The con-
    tracting officer denied each of the claims, and M.E.S.
    appealed to the Board. The Board sustained two of the
    appeals, awarding M.E.S. $105,286.03 (consisting of
    $97,908.70 for 155 days of additional field office overhead
    and $7377.33 for rental and installation of temporary
    bleachers, including profit and fourteen percent over-
    head), and denied three others. M.E.S. has appealed two
    of those denials.
    In the first of the appealed claims (the “cost overrun
    claim”), M.E.S. sought $575,113 in cost overruns related
    to thirteen work activities, plus profit and overhead.
    M.E.S. sought compensation on two theories: first, that
    government-caused delays had created inefficiencies and
    increased M.E.S.’s material and labor costs, and second,
    that the government had constructively accelerated the
    project by denying M.E.S. additional time extensions.
    M.E.S. sought to recover the entire difference between the
    actual cost of each activity, including seven percent profit
    and fourteen percent overhead, and the projected value of
    the activity as included in its contract bid. The Board
    rejected this claim, finding that M.E.S. “ha[d] failed to
    prove that the claimed increased [cost] over and above the
    ‘as-bid’ amounts . . . was caused by government-directed
    acceleration or . . . government delays.” J.A. 11; see also
    J.A. 14 (noting that M.E.S. had “failed to establish a
    causative connection between the delays and the alleged
    increased costs claimed”).
    In the second claim (the “overhead claim”), M.E.S.
    sought $459,845 in “additional Home Office Overhead
    Costs” for the added duration of the contract. J.A. 12
    (quotation marks omitted). M.E.S. arrived at this figure
    by multiplying 210 days of allegedly government-caused
    4                                        M.E.S., INC.   v. ARMY
    delay 1 by a daily allocable home office overhead rate of
    $2189.74. 2 The Board rejected this claim, too, finding
    that:
    None of these alleged dollar amounts [relied on by
    M.E.S. to calculate its daily rate] are supported in
    the evidentiary record by a [government] audit
    report, or in the absence of such report, by testi-
    mony or affidavit of the accountant preparing the
    claim or copies of the pertinent financial state-
    ments . . . prepared contemporaneously in the
    regular course of business, or other persuasive
    substantiating accounting documents. Moreover,
    nowhere in the [M.E.S.] calculation is there any
    allowance for home office expense paid in the
    price adjustments previously granted in the modi-
    fications for compensable government delays.
    J.A. 13. The Board also found “no persuasive evidence
    that [M.E.S.] was required to remain on standby and/or
    was unable to shift its resources to other un-impacted
    work.” J.A. 12.
    1      The 210 “delay days” did not include the addi-
    tional extensions to which M.E.S. alleged that it was
    entitled in its cost overrun claim, but which it never
    received.
    2     M.E.S. calculated this daily rate by dividing
    its 2004 revenue from the contract ($3,971,284) by its
    total revenue for the year ($4,359,551); multiplying this
    fraction by its total home office overhead for the year
    ($692,303); and dividing the result by the number of days
    it worked on the contract during 2004 (288). In its origi-
    nal claim, M.E.S. provided a separate daily rate for each
    of the four years during which it worked on the contract;
    before the Board, however, it sought to be compensated
    for the entire delay at the substantially higher 2004 rate.
    M.E.S., INC.   v. ARMY                                  5
    M.E.S. timely appealed the Board’s disposition of
    these two claims, and we have jurisdiction under 28
    U.S.C. § 1295(a)(10).
    DISCUSSION
    This court may set aside the Board’s determination on
    a question of fact only if it is “fraudulent, arbitrary, or
    capricious; . . . so grossly erroneous as to necessarily
    imply bad faith; or . . . not supported by substantial
    evidence.” 41 U.S.C. § 7107(b)(2). A determination is
    adequately supported if it is based on “such relevant
    evidence as a reasonable mind might accept as adequate
    to support a conclusion.” E.L. Hamm & Assocs. v. Eng-
    land, 
    379 F.3d 1334
    , 1338 (Fed. Cir. 2004).
    I. The Cost Overrun Claim
    A. The delay theory
    A contractor who seeks compensation for costs alleg-
    edly caused by government-imposed delays “has the
    burden of proving the fundamental facts of liability and
    damages.” Wilner v. United States, 
    24 F.3d 1397
    , 1401
    (Fed. Cir. 1994). Here, the Board found “no persuasive
    and particularized evidence . . . establishing the nature
    and extent of specific interferences or inefficiencies and
    how they materially increased [M.E.S.’s] cost,” and con-
    cluded that “[M.E.S.] ha[d] failed to prove that the [cost
    overruns] w[ere] caused by . . . compensable government
    delays.” J.A. 8, 11.
    On appeal, M.E.S. points to testimony by its president
    and owner, George Makhoul, recounting the delays it
    experienced and tying them to a few specific cost escala-
    tors such as material and labor cost inflation and difficul-
    ty working in cold weather. M.E.S. has not attempted to
    quantify the specific additional costs directly attributable
    6                                          M.E.S., INC.   v. ARMY
    to any particular item, and instead has asserted that all
    its overruns on the thirteen activities, measured relative
    to the cost estimates developed for its bid, were caused by
    the delays. Substantial evidence therefore supports the
    Board’s conclusion.
    B. The acceleration theory
    Constructive acceleration occurs “when the govern-
    ment requires the contractor to adhere to the original
    performance deadline set forth in the contract even
    though . . . excusable delay[s] . . . entitle the contractor to
    a longer performance period.” Fraser Constr. Co. v. United
    States, 
    384 F.3d 1354
    , 1361 (Fed. Cir. 2004). To prove
    such a claim, the contractor must prove “that the govern-
    ment insisted on completion of the contract within a
    period shorter than the period to which the contractor
    would be entitled.” Id. Here, the Board found that M.E.S.
    “has not proven that it was entitled to any extension of
    the contract performance time beyond [October 14, 2004].”
    J.A. 10.
    The contractor’s theory was that it was entitled to ad-
    ditional delay days and that the government compelled it
    to complete by October 14, 2004, thus leading to an accel-
    eration claim. The evidence cited by M.E.S. on appeal to
    demonstrate that it was legally entitled to a later comple-
    tion date, beyond October 14, 2004, consists of two letters,
    from August and September 2004, in which the contractor
    stated, in a conclusory manner, that the completion date
    was January 2005 or later. See J.A. 207, 1115. The Board
    found the contractor’s evidence insufficient to “prove[]
    that it was entitled to any extension of the contract per-
    formance time beyond [October 14, 2004].” J.A. 10. Sub-
    stantial evidence supports the Board’s finding that M.E.S.
    “has failed to prove that the [cost overruns] w[ere] caused
    by government-directed acceleration.” J.A. 11.
    M.E.S., INC.   v. ARMY                                  7
    II. The Overhead Claim
    M.E.S. claims that the Board erred in denying its
    claim for additional home office overhead. As a general
    rule, home office overhead damages are calculated in
    government contract cases by applying a fixed percentage
    to the additional direct costs included in the contract
    modification or in the claim for equitable adjustment. See
    C.B.C. Enters., Inc. v. United States, 
    978 F.2d 669
    , 674-75
    (Fed. Cir. 1992). Indeed, the Corps included an allowance
    for home office overhead in at least one of the modifica-
    tions it issued to M.E.S., and M.E.S. was awarded a fixed
    percentage for overhead in one of the two claims allowed
    by the Board. M.E.S.’s second claim on appeal does not
    rely on this theory, however. 3 Rather, the overhead claim
    relies on the so-called Eichleay formula, derived from the
    Board’s decision in Eichleay Corp., ASBCA No. 5183, 60-2
    BCA ¶ 2688, aff’d on reconsid., 61-1 BCA ¶ 2894. 4
    In certain limited circumstances, this court has ap-
    proved the use of the Eichleay formula, which relies on a
    daily allocable overhead rate, as an alternative to the
    fixed-percentage method. In order to recover Eichleay
    3    M.E.S. did include a fixed percentage of over-
    head in the damages it sought in its first claim on appeal,
    the cost-overrun claim.
    4    In its reply brief, M.E.S. asserts for the first
    time that the damages it seeks are not Eichleay damages,
    but rather “insufficient compensation for its general and
    administrative expenses associated with contract modifi-
    cations.” Reply Br. 26. The formula it used to calculate its
    alleged damages is clearly based on Eichleay, however,
    and it previously claimed to be “using the Eikley [sic]
    formula,” see J.A. 70. In its briefs, M.E.S. refers inter-
    changeably to “overhead” and “G&A,” or “general and
    administrative,” expenses.
    8                                         M.E.S., INC.   v. ARMY
    damages, however, a contractor must demonstrate, among
    other elements, that “performance of the contract [was]
    suspended or significantly interrupted” by the govern-
    ment, and not merely that the period of contract perfor-
    mance was extended and an additional stream of direct
    costs created. See Interstate Gen. Gov’t Contractors, Inc. v.
    West, 
    12 F.3d 1053
    , 1056-58 (Fed. Cir. 1993); see also
    Cmty. Heating & Plumbing Co. v. Kelso, 
    987 F.2d 1575
    ,
    1581-82 (Fed. Cir. 1993), modified on reh’g, 1993 U.S.
    App. LEXIS 31453 (Fed. Cir. May 21, 1993); C.B.C. En-
    ters., 978 F.2d at 674-75. The requirement that the work
    on the contract must have been suspended or interrupted
    is one facet of the more general requirement that the
    government must have placed the contractor on
    “standby.” See Interstate, 12 F.3d at 1056-57 & n.5; see
    also P.J. Dick, Inc. v. Principi, 
    324 F.3d 1364
    , 1371-73
    (Fed. Cir. 2003) (outlining the elements of the standby
    requirement). Here, the Board found “no persuasive
    evidence that [M.E.S.] was required to remain on
    standby” during any of the additional time periods, J.A.
    12, and we find no reason to disturb this finding. 5
    Even if M.E.S. in this claim had proceeded on the the-
    ory that it is entitled to home office overhead as a fixed
    percentage of the additional direct costs caused by the
    5      On appeal, M.E.S. points to evidence showing
    that it had no other contracts during most of the time that
    it was engaged by the Corps. The “standby” element
    requires a contractor to show more than just that delays
    rendered it idle; it must also show that the government
    required it to remain idle, or that circumstances otherwise
    rendered mitigation “impractical.” See Daly Constr., Inc.
    v. Garrett, 
    5 F.3d 520
    , 522 (Fed. Cir. 1993); see also Cmty.
    Heating, 987 F.2d at 1582 (requiring the contractor to
    “demonstrate[] that it could not have taken on any other
    jobs during the contract period”).
    M.E.S., INC.   v. ARMY                                9
    contract modifications, M.E.S. could not prevail. M.E.S.
    has failed to present, at any stage of the litigation, a
    sufficient calculation of such damages. The Board found
    M.E.S.’s home office overhead calculation to be deficient
    both for its lack of substantiation and for its failure to
    account for those home office overhead amounts already
    included by the Corps in its price adjustments. Substan-
    tial evidence supports the Board’s determination that “the
    alleged increased home office expense incurred for com-
    pensable government delays is not proven in any
    amount.” J.A. 13.
    Thus, substantial evidence supports the Board’s find-
    ings that M.E.S. failed to prove that its overruns were
    caused by government delays; that any “acceleration” of
    the contract took place; or that M.E.S. is entitled to
    additional compensation for home office overhead.
    AFFIRMED