CCI, Inc. v. McHugh ( 2015 )


Menu:
  •        NOTE: This disposition is nonprecedential.
    United States Court of Appeals
    for the Federal Circuit
    ______________________
    CCI, INC.,
    Appellant
    v.
    JOHN MCHUGH, Secretary of the Army,
    Appellee
    ______________________
    2014-1470
    ______________________
    Appeal from the Armed Services Board of Contract
    Appeals in No. 57316, Administrative Judge Cheryl L.
    Scott.
    ______________________
    Decided: April 10, 2015
    ______________________
    JAMES E. HOWARD, Davis Wright Tremaine LLP, Seat-
    tle, WA, argued for appellant. Also represented by LISA M.
    MARCHESE, TRAEGER MACHETANZ, JONATHAN A. DEMELLA.
    JEFFREY A. REGNER, Commercial Litigation Branch,
    Civil Division, United States Department of Justice,
    Washington, DC, argued for appellee. Also represented by
    JOYCE R. BRANDA, ROBERT E. KIRSCHMAN, JR., MARTIN F.
    HOCKEY, JR.
    ______________________
    2                                          CCI, INC.   v. ARMY
    Before NEWMAN, REYNA, and HUGHES, Circuit Judges.
    HUGHES, Circuit Judge.
    CCI appeals the Armed Services Board of Contract
    Appeals’ denial of its Type I claim for equitable relief
    under Differing Site Condition Clause FAR 52.236-2. The
    Board concluded that CCI had not proven any of the four
    elements necessary to establish a Type I equitable ad-
    justment claim. Accordingly, to prevail on appeal, CCI
    must show the Board erred on all four elements. Because
    substantial evidence supports the Board’s decision on at
    least two of these elements—whether the site conditions
    were reasonably foreseeable to CCI and whether CCI
    relied on the alleged site representations—we find that
    CCI has not met this burden. Accordingly, we affirm.
    I
    On April 25, 2008, the Army issued a Request for
    Proposals (RFP) to plan, design, and construct an L-
    shaped pier and perform related work at Umm Qasr, the
    only deep-water seaport in Iraq. The Army found that
    Umm Qasr was “a critical link towards the import of life-
    providing assistance being provided to the people of Iraq.”
    J.A. 4859.
    Attached to the RFP was a 2007 engineering report
    from Andrea Engineering Tests Laboratory (the Andrea
    Report). The Andrea Report describes a field investiga-
    tion of an area including the Umm Qasr project site, and
    included results obtained from disturbed samples 1, undis-
    1   Disturbed samples have been altered in a way
    that makes them unrepresentative of in-situ conditions.
    They are frequently used to determine properties of the
    soil that are not dependent on in-situ conditions, such as
    soil grain size.
    CCI, INC.   v. ARMY                                         3
    turbed samples 2, and a Standard Penetration Test 3
    performed on three boreholes.
    In the “Discussion of Results” section, the Andrea Re-
    port includes several descriptions of the soil, such as:
    •    “The site subsoil consists mainly from two layers,
    the first layer of very soft, soft to medium gray
    sandy silty clay with amount of soluble salts and
    organic matter overlaying on a layer of medium,
    dense to very dense gray silty sand.” J.A. 4809.
    •    “[T]he site was within the ebb and tide zone of the
    sea. The saturated soil condition below the water
    table makes the problem of settlement significant
    . . . .” 
    Id. • “The
    low bearing capacity of the soft clayey layer;
    could lead to excessive settlement to go out of con-
    trol.” J.A. 4810.
    •    “[The] samplers that extruded from shelby tubes of
    the soft clayey layer . . . exudes between the fingers
    when squeezed in the fist so this could described as
    very soft to soft sandy clayey soil.” 
    Id. • “Investigation
    of the site area has produced evi-
    dence of some kind of collapse due to the reaction
    between fundamental compounds of the soil (sandy
    2    Undisturbed samples contain conditions close
    enough to the in-situ conditions to be used to approximate
    in-situ structural properties.
    3    A Standard Penetration Test is a common test
    used to determine the geotechnical engineering properties
    of soil. It involves driving a thick-walled hollow tube into
    the soil with a 140-pound hammer and recording the blow
    count—the number of blows to the hammer necessary to
    increase the depth of the tube by a predetermined dis-
    tance.
    4                                           CCI, INC.   v. ARMY
    clayey layer) with organic matter, this collapse is
    impact the settlement of shallow foundation about
    (2 – 5) %.” J.A. 4810–11.
    Appendix B of the Andrea Report includes soil de-
    scriptors and the blow count data obtained from the
    Standard Penetration Test. The parties agree that Ap-
    pendix B of the Andrea Report contains inconsistent
    information, because the soil descriptors indicate the soil
    is very soft to soft, but the blow count data indicates the
    soil is harder.
    Another attachment to the RFP is a U.S. Agency for
    International Development report entitled “Umm Qasr
    Port Assessment” (the USAID Report). The USAID
    Report was prepared as a “general assessment of func-
    tions at the port and historical dredging operations at the
    port.” J.A. 18354. It describes the history of dredging at
    the site, the need for continuous dredging at the site, and
    the locations of the dredged material disposal sites. The
    report also includes the following site condition descrip-
    tion:
    The streams are alluvial and the channels are ap-
    parently composed primarily of sand and silt. Clay
    may be present, but no clay balls were seen in the
    dredged material disposal areas. There is a thin
    film of sun-cracked silt or clay at some of the final
    settlement ponding areas. Boring information
    shows the materials encountered in the original
    “new” port excavation as silty sand with small fine
    gravel and clay. Infill sediments since then may
    be of a finer, more silty nature.
    J.A. 4863.
    After the RFP issued, CCI agreed to join two other
    companies, PolyEarth Construction, International LLC
    (PCI) and PND Engineers, Inc. (PND), in preparing a bid
    proposal for the Umm Qasr project. PND and PCI were
    CCI, INC.   v. ARMY                                      5
    responsible for the engineering and logistical aspects of
    the proposal, and CCI was responsible for the financial
    aspects of the proposal.
    During the Umm Qasr bidding period, a number of
    questions were submitted to, and subsequently answered
    by, the Army. Two are relevant to this appeal:
    Question 11: Soil investigation not enough we
    need more point of locations.
    Answer 11: The best soil investigation data avail-
    able to the government is provided in Appendix-C
    Geotechnical Investigation of the SOW. The con-
    tractor should assume the data provided in Ap-
    pendix C is representative of the project site.
    Question 42: Geotechnical Conditions: Will the
    government be providing any bidding assumptions
    associated with the existing geotechnical condi-
    tions? For bidding purposes, should the contrac-
    tor assume the three borings provided are
    representative of the entire site?
    Answer 42: The contractor should assume the
    three borings provided are representative of the
    entire site for the purposes of developing a pro-
    posal. However, additional geotechnical infor-
    mation may be required during the design phase
    of this project.
    J.A. 4833; J.A. 4838.
    In May 2008, CCI submitted an initial proposal for
    the Umm Qasr project. In August 2008, CCI submitted a
    revised proposal. On September 10, 2008, the Army
    awarded CCI the contract for the Umm Qasr project. The
    contract incorporated Differing Site Conditions Clause
    FAR 52.236-2 and Site Investigations Affecting the Work
    Clause FAR 52.236-3.
    6                                          CCI, INC.   v. ARMY
    In 2009, CCI began construction on the Umm Qasr
    project. CCI initially used land-based construction meth-
    ods and encountered difficulties building a crane pad due
    to the soil conditions at the project site. It ultimately
    switched to marine-based construction to complete the
    project.
    In August 2009, CCI submitted a Type I request for
    equitable adjustment to the Army, alleging that it in-
    curred additional costs as a result of soil conditions that
    were different than represented in the Andrea Report.
    The Army denied CCI’s claim, and CCI appealed to the
    Board. The Board also denied CCI’s claim. CCI appeals.
    We have jurisdiction under 28 U.S.C. § 1295(a)(10).
    II
    To receive an equitable adjustment for a Type I differ-
    ing site condition, a contractor must prove by a prepon-
    derance of the evidence that: (1) “a reasonable contractor
    reviewing the contract documents as a whole would
    interpret them as making a representation about the site
    conditions”; (2) “the actual site conditions were not rea-
    sonably foreseeable to the contractor, with the infor-
    mation available to the particular contractor outside the
    contract documents”; (3) “the contractor in fact relied on
    the contract representation”; and (4) “the conditions
    differed materially from those represented, and the con-
    tractor suffered damages as a result.” Int’l Tech. Corp. v.
    Winter, 
    523 F.3d 1341
    , 1348–49 (2008). Whether a rea-
    sonable contractor reading the contract documents as a
    whole would interpret them as making a site-condition
    representation is a legal question reviewed de novo. 
    Id. at 1349.
    The other three elements are questions of fact
    reviewed for substantial evidence. 
    Id. “Substantial evidence
    means such relevant evidence as a reasonable
    mind might accept as adequate to support a conclusion.”
    E.L. Hamm & Assocs., Inc. v. England, 
    379 F.3d 1334
    ,
    1338 (Fed. Cir. 2004).
    CCI, INC.   v. ARMY                                        7
    The Board held that CCI did not prove any of these
    four elements. Accordingly, to prevail on appeal, CCI
    must show that the Board erred on each of these four
    elements. See Int’l Tech. Corp., 
    523 F.3d 1348
    –49. Be-
    cause CCI has failed to show that the record does not
    provide substantial evidence to support the Board’s
    findings that (1) the site conditions were reasonably
    foreseeable to CCI or (2) CCI did not rely on the alleged
    site condition representations, CCI has not met this
    burden.
    A
    When determining whether site conditions were rea-
    sonably foreseeable to the contractor, both the contract
    and any other information available to the contractor are
    considered. 
    Id. at 1349.
    Under this standard, substantial
    evidence supports the Board’s finding.
    Specifically, the Andrea Report supports the finding
    that the soil conditions actually encountered were reason-
    ably foreseeable. It frequently describes the area as
    having soil settlement issues and as containing soft to
    very soft soils. See, e.g., J.A. 4809 (describing the first
    layer of the site subsoil as “very soft, soft to medium gray
    sandy silty clay”); 
    id. (“The saturated
    soil condition below
    the water table makes the problem of settlement signifi-
    cant . . . .”); J.A. 4810 (“The low bearing capacity of the
    soft clayey layer; could lead to excessive settlement to go
    out of control.”); 
    id. (“[The] samplers
    that extruded from
    Shelby tubes of the soft clayey layer . . . exudes between
    the fingers when squeezed in the fist so this could de-
    scribed as very soft to soft sandy clayey soil.”); J.A. 4810–
    11 (“Investigation of the site area has produced evidence
    of some kind of collapse due to the reaction between
    fundamental compounds of the soil (sandy clayey layer)
    with organic matter . . . .”).
    CCI asserts that because of the Army’s answer to
    Question 42—that contractors “should assume the three
    8                                           CCI, INC.   v. ARMY
    borings provided are representative of the entire site”—it
    reasonably relied solely on the borehole data in Appendix
    B of the Andrea Report. But even if this is correct, it does
    not show a lack of substantial evidence because the soil
    descriptors in Appendix B describe the soil near the
    project site at the relevant depth as being “[v]ery soft to
    soft gray to dark gray silty CLAY.” J.A. 4818–19.
    CCI argues that because the blow count data in Ap-
    pendix B of the Andrea Report indicates a harder soil, and
    engineers view objective data, such as blow count data, as
    more reliable than soil descriptors, the soil conditions it
    encountered were not reasonably foreseeable.
    The record shows that the inconsistencies in the An-
    drea Report caused engineers to be skeptical of its relia-
    bility. For example, the engineer CCI used to prepare its
    proposal, Mr. Nottingham, admitted that the information
    in Appendix B of the Andrea Report is “not consistent.”
    J.A. 330. The Army’s expert, Mr. Apted, agreed and
    testified that “it should have been clear that the Andrea
    report was limited in extent and quality and there was a
    risk of more difficult conditions” and that—given the
    amount of other data indicating softer soil conditions—the
    blow count data is “clearly an anomalous set of data[.]”
    J.A. 17468–69. According to Mr. Apted, the Andrea
    Report would have caused him to expect “very soft clay.”
    J.A. 2904. Given this evidence, a reasonable mind could
    conclude that the soil conditions were reasonably foresee-
    able to CCI.
    The USAID Report provides additional support for the
    Board’s finding. It describes the need for continuous
    dredging near the site and the locations of the dredged
    material disposal sites. The Army’s expert, Mr. Apted,
    testified that, given this report, “the risk of accumulation
    of silt and clay disposal arising[] from dredging could have
    reasonably be[en] foreseen as a significant risk.” J.A.
    17469.
    CCI, INC.   v. ARMY                                        9
    Moreover, CCI was already aware of the area’s dredg-
    ing issues before it read the USAID Report. Mr. Nunn, a
    civil and nuclear engineer and co-founder of PCI involved
    in the Umm Qasr proposal and project, worked near the
    project site before CCI submitted its proposal. He was
    familiar with the area’s dredging issues and knew that a
    dredging contractor was on site, that “[t]hey were spend-
    ing millions of dollars dredging the naval port[,]” and that
    “the other piers were already clogged with siltation.” J.A.
    420.
    In light of this evidence, we conclude that a reasona-
    ble mind could agree with Mr. Apted that “the conditions
    encountered could and should have been within the
    reasonable contemplation of CCI.” J.A. 17469. According-
    ly, we conclude that substantial evidence supports the
    Board’s finding that the soil conditions were reasonably
    foreseeable to CCI.
    B
    Substantial evidence also supports the Board’s finding
    that CCI did not prove that it relied on the alleged mis-
    representation. CCI admits that it viewed the Andrea
    Report as containing inconsistent information and being
    insufficient to determine whether the project could be
    completed with land-based construction. This admission
    makes it unlikely that CCI relied on the Andrea Report,
    and provides support for the Board’s finding.
    Additionally, we agree with the Board that the pro-
    posal itself does not support CCI’s assertion that it relied
    on the Andrea Report. Nothing in the proposal identifies
    whether land or marine construction would be performed.
    Although Mr. Nottingham testified that he relied on the
    Andrea Report and that the cost estimate in the proposal
    specifically factored in the cost of land-based construction,
    this does not mean that the Board was required to accept
    his testimony. The Board has “broad discretion in deter-
    mining credibility because he saw the witness and heard
    10                                          CCI, INC.   v. ARMY
    the testimony.” J.C. Equip. Corp. v. England, 
    360 F.3d 1311
    , 1315 (Fed. Cir. 2004) (internal quotation omitted).
    Accordingly, “[t]he Board’s determinations of witness
    credibility are virtually unreviewable.”     
    Id. (internal quotation
    omitted) (alteration in original). Moreover,
    even if Mr. Nottingham’s cost estimate shows that CCI
    assumed the project could be completed using land-based
    construction, it does not show that the Andrea Report was
    the basis for CCI’s assumption.
    Additionally, the proposal actually provides support
    for the Board’s finding that CCI did not rely on the An-
    drea Report. As CCI concedes, the Andrea Report and the
    proposal “depict different approximations of the depth at
    which sand and silt would be encountered.” Appellant’s
    Br. at 55. If CCI did in fact rely on the borehole log data
    from the Andrea Report to predict harder soil conditions,
    there is no plausible reason to believe it would not have
    also used the Andrea Report’s approximations for what
    depths sand and silt would be encountered.
    In light of this evidence, we hold that a reasonable
    mind could conclude that CCI did not rely on the Andrea
    Report in preparing its proposal.
    III
    Because we conclude that substantial evidence sup-
    ports the Board’s findings that (1) the site conditions were
    reasonably foreseeable to CCI and (2) CCI did not rely on
    the Andrea Report in preparing its proposal, we do not
    need to reach the other two elements of CCI’s equitable
    adjustment claim. Accordingly, we affirm the Board’s
    conclusion that CCI is not entitled to a Type I equitable
    adjustment.
    AFFIRMED
    

Document Info

Docket Number: 2014-1470

Judges: Newman, Reyna, Hughes

Filed Date: 4/10/2015

Precedential Status: Non-Precedential

Modified Date: 11/6/2024