Ast Anlagen- Und Sanierungstechnick Gmbh v. Harvey ( 2005 )


Menu:
  •                  NOTE: Pursuant to Fed. Cir. R. 47.6, this disposition
    is not citable as precedent. It is a public record.
    United States Court of Appeals for the Federal Circuit
    05-1053
    AST ANLAGEN – UND SANIERUNGSTECHNICK GMBH,
    Appellant,
    v.
    Francis J. Harvey, SECRETARY OF THE ARMY,
    Appellee.
    __________________________
    DECIDED: December 6, 2005
    __________________________
    Before CLEVENGER, SCHALL, and BRYSON, Circuit Judges.
    PER CURIAM.
    DECISION
    AST Anlagen – und Sanierungstechnick GmbH (“AST”) appeals the final decision
    of the Armed Services Board of Contract Appeals (“Board”) in In re AST Anlagen – und
    Sanierungstechnik GmbH, No. 49969, 2004 ASBCA Lexis 68 (A.S.B.C.A. June 30,
    2004). In its decision, the Board denied AST’s claim that it was entitled to additional
    compensation under its construction contract with the Department of the Army (“Army”)
    by reason of government-caused delay to the project. We affirm.
    DISCUSSION
    I.
    This case grows out of a contract between AST and the Army for the renovation
    and replacement of roofing, for painting and plastering, and for work relating to exterior
    wall insulation, electrical lines, and water lines for three family housing units at Martin
    Luther King Village in Mainz, Germany. After the contract work was completed, AST
    submitted a certified claim to the contracting officer seeking additional compensation
    under the contract. In its claim, AST asserted that it had suffered delay damages as
    result of the Army’s failure to promptly accept its proposed Pumagro insulation system.
    After the deemed denial of its claim, AST timely appealed to the Board. Following a
    hearing, the Board denied AST’s claim, and this appeal followed. We have jurisdiction
    pursuant to 
    28 U.S.C. § 1295
    (a)(10) (2000).
    II.
    Our scope of review in an appeal from a decision of the Board is limited.
    Specifically, we must affirm the Board’s decision on any question of fact unless we find
    it to be fraudulent; arbitrary or capricious; so grossly erroneous as to necessarily imply
    bad faith; or not supported by substantial evidence. 
    41 U.S.C. § 609
    (b) (2000).
    The Board denied AST’s claim because it found that AST had not established
    that action or inaction on the part of the Army delayed the completion of the contract
    work. On appeal, AST argues that the Board’s decision must be reversed because it is
    not supported by substantial evidence. In making that argument, it attacks the Board’s
    05-1053                                     2
    underlying findings that (i) the Army did not stop AST from installing Pumagro, (ii) AST
    made a unilateral decision to install Pumagro insulation and began installing the
    insulation in March of 1985, and (iii) AST continued to work on the jobsite without
    interruption during the winter of 1985.
    We have no difficulty concluding that findings (ii) and (iii) above are supported by
    substantial evidence. Finding (i) is more troublesome. While it is true that no formal
    stop-work order was issued to AST during the period that the Army was deciding
    whether to approve the use of Pumagro insulation, it appears undisputed that the
    Army’s project inspector told AST not to proceed with the insulation work until approval
    was forthcoming. It also appears undisputed that the contracting officer was aware of
    the inspector’s direction to AST.
    However, even if AST is correct that it was told not to proceed with the insulation
    work pending Army review, the result in the case is no different. The Board’s two
    undisturbed findings provide substantial evidence for the ultimate finding that the time
    the Army took to approve the use of Pumagro did not delay the completion of the
    project. That is because these findings establish two things: first, AST proceeded with
    project work during the winter of 1985;1 and second, notwithstanding what AST asserts
    it was told by the project inspector, AST did not hesitate to commence the installation of
    the Pumagro insulation when it was ready to do so. In other words, as far as AST was
    concerned, the inspector’s instructions—whatever they were—were not an impediment
    to its proceeding with the insulation work. Under these circumstances, AST cannot
    establish that the Army delayed its completion of the contract work. See, e.g., Wilner v.
    1
    The record reflects that, except for six days when no work could be
    performed because of freezing temperatures, AST worked continuously on the project.
    05-1053                                     3
    United States, 
    24 F.3d 1397
    , 1401 (Fed. Cir. 1994) (en banc) (recognizing that to prove
    its claim for damages allegedly due to Government-caused delay, “the contractor has
    the burden of proving the extent of the delay, that the delay was proximately caused by
    Government action, and that the delay harmed the contractor”) (emphasis added).
    For the foregoing reasons, the final decision of the Board denying AST’s claim is
    affirmed.
    Each party shall bear its own costs.
    05-1053                                      4
    

Document Info

Docket Number: 2005-1053

Judges: Clevenger, Schall, Bryson

Filed Date: 12/6/2005

Precedential Status: Non-Precedential

Modified Date: 11/5/2024