Grunley Construction Co., Inc. v. The Architect of the Capitol ( 2011 )


Menu:
  • NOTE: This order is nonprecedential
    United States Court of AppeaIs
    for the FederaI Circuit
    GRUNLEY CONSTRUCTION CO., INC.,
    Appellant, '
    V.
    THE ARCHITECT OF THE CAPITOL,
    Appellee.
    2010-6001 _
    Appeal from the G0ve1'nment Acc0un1;ability OfEce,
    Contract Appeals B0ard, CAB N0. 2009-1.
    ¢».--»..__.¢._____-----------
    GRUNLEY CONSTRUCTION CO., INC.,
    Appellee,
    V.
    THE ARCHITECT OF THE CAPITOL,
    Appellant.
    2011-6011
    GRUNLEY CONSTRUCTION V. AOC 2
    Appeal from the Government Accountability OfEce,
    Contract Appeals Board, CAB No. 2009-1.
    Before NEWMAN, SCHALL, and DYK, Circu,it Judges.
    NEWMAN, Circuit Ju.dge.
    0 R D E R
    The Architect of the Capitol (AOC) moves to dismiss
    Grunley Construction Co.’s appeal from the Government
    Accountability OfEce, Contract Appeals Board, and its
    own conditional cross-appeal, for lack of jurisdiction.
    Grunley opposes. AOC replies.
    In April 2004, AOC issued to Grunley a fixed-price
    contract to provide construction services to m0dernize
    portions of the Supreme Court of the United States. The
    contract required that “[c]ertain events during the con-
    struction period will require the Contractor' to suspend
    work for given periods of time, including but not limited
    to key events indicated on the Court calendar." That
    clause further provided that for bidding purposes "the
    Contractor shall anticipate sixteen (16) days per calendar
    year of interrupted work days."
    During the course of performance, the Marsha1 of the
    Supreme Court began imposing work restrictions during
    days the court was in session or in conference Grunley
    alleges that those restrictions effectively precluded it from
    performing the work on time and on budget as expected
    In October 2005, Grunley shifted some day work to night
    shifts as a result of the Marshal’s imposed restrictions In
    late 2006, however, Grunley determined that it would be
    more productive to work all but specified night trades in
    the normal work day and to have crews sit out the hours
    on court days.
    On Ootober 1, 2008, Grunley certified a single claim
    seeking an equitable adjustment from the contracting
    officer (CO) for $1,095,128 as a result of the Marshal’s
    l
    1
    1
    3 GRUNLEY CONSTRUCTION V. AOC
    imposed restrictions. Grunley alleged that the restric-
    tions constructively changed the contract resulting in
    increased costs associated with the work between October
    2005 and December 2007 . Grunley’s claim consisted of
    two components: (1) costs for night shift premiums and
    night-time inefficiency costs from October 2005 through
    December 31, 2006; and (2) standby costs incurred during
    the day. The CO denied Grunley’s claim on the grounds
    that pursuant to the events clause Grunley budgeted for
    delays during court days. _
    On cross-motions for summary judg1nent, the Con-
    tract Appeals Board held that Grunley’s claim for an
    adjustment for standby costs incurred during the day was
    prohibited under the contract’s "no damage for delay"
    clause. However, with regard to its night shift premium
    and inefficiency cost argument, the Board disagreed with
    the CO’s interpretation of the events clause. lnstead, the
    Board agreed with Grunley that any interruptions more
    than 16 days per calendar year could be entitled to com-
    pensation but only under the “suspension of work" clause.
    The Board held that "Grunley is entitled to recover the
    night shift differential that was necessarily incurred and
    was not for work otherwise required to be performed at
    night, so long as the conditions of the suspension of work
    clause are met." The Board expressly declined to reach
    certain issues on summary judgment, e.g., declining to
    decide whether the contracting officer engaged in any acts
    to suspend work because of "insufticient undisputed facts
    in the record." Grunley filed an appeal seeking review in
    this court. The issue of Grunley’s entitlement to compen-
    sation under the suspension clause remains open.
    The AOC contends that Grunley’s appeal from the
    Board’s summary judgment order is not final We agree.
    Although Grunley presents its claim as having multiple
    cost components, it certified only a single claim arising
    out of essentially interrelated services and closely con-
    GRUNLEY CONS'l``RUCTION V. AOC 4
    nected facts. See Teller E'nvtl. Sys. v. U.S., 
    802 F.2d 1385
    ,
    1389 (Fed. Cir. 1986) (rejecting characterizing of multiple
    claims when the demands for adjustments involved
    interrelated services and closely connected facts). The
    matter of Grunley’s entitlement to an adjustment remains
    open. Allowing for an appeal from an order resolving in
    part motions for summary judgment, before all issues are
    determined, would undermine the primary purpose of the
    Hnal judgment rule in avoiding the inefficiencies of
    piecemeal litigation. See Catlin v. U.S, 324  229, 233
    (1945).
    Accordingly,
    IT ls 0RDERED THAT:
    (1) The motion to dismiss is granted Both appeals
    are dismissed. Grunley may appeal the matter after final
    judgment.
    (2) Each side shall bear its own costs. ``
    FOR THE COURT
    dl.ll_ 1 2011 /s/ Jan Horbaly
    Date J an I-Iorbaly
    C1 k FI E
    er u.s. count olF A9>zALs son
    cc: Herman M. Braude, Esq.
    Steven J. Gillingham, Esq.
    s19
    lssUED As A MANDA'rE; ill 7 2911
    THE FEDERAL CIRCU|T
    JUL 0-7 2011
    JAN HORBALY
    CLERK
    

Document Info

Docket Number: 2010-6001, 2011-6011

Judges: Newman, Schall, Dyk

Filed Date: 7/7/2011

Precedential Status: Non-Precedential

Modified Date: 11/5/2024