All Courts |
Federal Courts |
US Court of Appeals Cases |
Court of Appeals for the Federal Circuit |
2011-07 |
-
NOTE: This order is nonprecedential United States Court of AppeaIs for the FederaI Circuit GRUNLEY CONSTRUCTION CO., INC., Appellant, ' V. THE ARCHITECT OF THE CAPITOL, Appellee. 2010-6001 _ Appeal from the G0ve1'nment Acc0un1;ability OfEce, Contract Appeals B0ard, CAB N0. 2009-1. ¢».--»..__.¢._____----------- GRUNLEY CONSTRUCTION CO., INC., Appellee, V. THE ARCHITECT OF THE CAPITOL, Appellant. 2011-6011 GRUNLEY CONSTRUCTION V. AOC 2 Appeal from the Government Accountability OfEce, Contract Appeals Board, CAB No. 2009-1. Before NEWMAN, SCHALL, and DYK, Circu,it Judges. NEWMAN, Circuit Ju.dge. 0 R D E R The Architect of the Capitol (AOC) moves to dismiss Grunley Construction Co.’s appeal from the Government Accountability OfEce, Contract Appeals Board, and its own conditional cross-appeal, for lack of jurisdiction. Grunley opposes. AOC replies. In April 2004, AOC issued to Grunley a fixed-price contract to provide construction services to m0dernize portions of the Supreme Court of the United States. The contract required that “[c]ertain events during the con- struction period will require the Contractor' to suspend work for given periods of time, including but not limited to key events indicated on the Court calendar." That clause further provided that for bidding purposes "the Contractor shall anticipate sixteen (16) days per calendar year of interrupted work days." During the course of performance, the Marsha1 of the Supreme Court began imposing work restrictions during days the court was in session or in conference Grunley alleges that those restrictions effectively precluded it from performing the work on time and on budget as expected In October 2005, Grunley shifted some day work to night shifts as a result of the Marshal’s imposed restrictions In late 2006, however, Grunley determined that it would be more productive to work all but specified night trades in the normal work day and to have crews sit out the hours on court days. On Ootober 1, 2008, Grunley certified a single claim seeking an equitable adjustment from the contracting officer (CO) for $1,095,128 as a result of the Marshal’s l 1 1 3 GRUNLEY CONSTRUCTION V. AOC imposed restrictions. Grunley alleged that the restric- tions constructively changed the contract resulting in increased costs associated with the work between October 2005 and December 2007 . Grunley’s claim consisted of two components: (1) costs for night shift premiums and night-time inefficiency costs from October 2005 through December 31, 2006; and (2) standby costs incurred during the day. The CO denied Grunley’s claim on the grounds that pursuant to the events clause Grunley budgeted for delays during court days. _ On cross-motions for summary judg1nent, the Con- tract Appeals Board held that Grunley’s claim for an adjustment for standby costs incurred during the day was prohibited under the contract’s "no damage for delay" clause. However, with regard to its night shift premium and inefficiency cost argument, the Board disagreed with the CO’s interpretation of the events clause. lnstead, the Board agreed with Grunley that any interruptions more than 16 days per calendar year could be entitled to com- pensation but only under the “suspension of work" clause. The Board held that "Grunley is entitled to recover the night shift differential that was necessarily incurred and was not for work otherwise required to be performed at night, so long as the conditions of the suspension of work clause are met." The Board expressly declined to reach certain issues on summary judgment, e.g., declining to decide whether the contracting officer engaged in any acts to suspend work because of "insufticient undisputed facts in the record." Grunley filed an appeal seeking review in this court. The issue of Grunley’s entitlement to compen- sation under the suspension clause remains open. The AOC contends that Grunley’s appeal from the Board’s summary judgment order is not final We agree. Although Grunley presents its claim as having multiple cost components, it certified only a single claim arising out of essentially interrelated services and closely con- GRUNLEY CONS'l``RUCTION V. AOC 4 nected facts. See Teller E'nvtl. Sys. v. U.S.,
802 F.2d 1385, 1389 (Fed. Cir. 1986) (rejecting characterizing of multiple claims when the demands for adjustments involved interrelated services and closely connected facts). The matter of Grunley’s entitlement to an adjustment remains open. Allowing for an appeal from an order resolving in part motions for summary judgment, before all issues are determined, would undermine the primary purpose of the Hnal judgment rule in avoiding the inefficiencies of piecemeal litigation. See Catlin v. U.S, 324 229, 233 (1945). Accordingly, IT ls 0RDERED THAT: (1) The motion to dismiss is granted Both appeals are dismissed. Grunley may appeal the matter after final judgment. (2) Each side shall bear its own costs. `` FOR THE COURT dl.ll_ 1 2011 /s/ Jan Horbaly Date J an I-Iorbaly C1 k FI E er u.s. count olF A9>zALs son cc: Herman M. Braude, Esq. Steven J. Gillingham, Esq. s19 lssUED As A MANDA'rE; ill 7 2911 THE FEDERAL CIRCU|T JUL 0-7 2011 JAN HORBALY CLERK
Document Info
Docket Number: 2010-6001, 2011-6011
Judges: Newman, Schall, Dyk
Filed Date: 7/7/2011
Precedential Status: Non-Precedential
Modified Date: 11/5/2024