Supreme Foodservice Gmbh v. Director of the Defense Logistics Agency ( 2022 )


Menu:
  • Case: 21-1965   Document: 65     Page: 1    Filed: 12/05/2022
    United States Court of Appeals
    for the Federal Circuit
    ______________________
    SUPREME FOODSERVICE GMBH,
    Appellant
    v.
    DIRECTOR OF THE DEFENSE LOGISTICS
    AGENCY,
    Appellee
    ______________________
    2021-1965
    ______________________
    Appeal from the Armed Services Board of Contract Ap-
    peals in Nos. 57884, 57884-QUAN, 58666, 58666-QUAN,
    59636, 59636-QUAN, 61361, 61361-QUAN, Administra-
    tive Judge J. Reid Prouty, Administrative Judge Michael
    N. O’Connell, Administrative Judge Richard Shackleford.
    ______________________
    Decided: December 5, 2022
    ______________________
    JOHN PRAIRIE, Wiley Rein LLP, Washington, DC, ar-
    gued for appellant. Also represented by JAMES RYAN
    FRAZEE.
    P. DAVIS OLIVER, Commercial Litigation Branch, Civil
    Division, United States Department of Justice, Washing-
    ton, DC, argued for appellee. Also represented by BRIAN
    M. BOYNTON, PATRICIA M. MCCARTHY.
    ______________________
    Case: 21-1965     Document: 65    Page: 2    Filed: 12/05/2022
    2                             SUPREME FOODSERVICE GMBH v.
    DIRECTOR OF THE DEFENSE LOGISTICS AGENCY
    Before MOORE, Chief Judge, PROST and HUGHES, Circuit
    Judges.
    HUGHES, Circuit Judge.
    Supreme Foodservice GmbH appeals an Armed Ser-
    vices Board of Contract Appeals decision concluding that
    Supreme’s contract claims against the government were
    barred by Supreme’s prior material breach. Supreme ar-
    gues that the government waived its prior material breach
    defense and seeks Contract Disputes Act interest on money
    the Board found the government over-withheld. Because
    we agree that the government did not waive its defense,
    and because Supreme’s prior material breach means there
    is no valid underlying contractor’s claim through which Su-
    preme may recover CDA interest, we affirm.
    I
    A
    In 2005, the Defense Logistics Agency (DLA) awarded
    a “subsistence prime vendor” (SPV) contract to Supreme to
    furnish and deliver food to U.S. forces in Afghanistan. Ini-
    tially, the contract only required Supreme to deliver food
    by truck to four main U.S. military bases, but DLA later
    modified the contract to direct Supreme to begin delivering
    food to other forward operating bases in Afghanistan.
    The parties then began negotiating payment for those
    deliveries to forward operating bases, known as Premium
    Outbound Transportation (POT). During negotiation, Su-
    preme submitted inflated cost proposals that were, accord-
    ing to Michael Epp, Supreme’s Commercial Division
    Director, “completely false.” J.A. 9. Because Supreme
    threatened to withhold payments to subcontractors (thus
    potentially cutting off food supply to troops in Afghani-
    stan), the parties executed Modification No. P00010 on Au-
    gust 2, 2006, agreeing to Supreme’s proposed rates “subject
    to final verification.” J.A. 13. DLA asked the Defense
    Case: 21-1965     Document: 65     Page: 3    Filed: 12/05/2022
    SUPREME FOODSERVICE GMBH v.                                 3
    DIRECTOR OF THE DEFENSE LOGISTICS AGENCY
    Contract Audit Agency (DCAA) to audit Supreme’s pro-
    posed POT costs. The parties then entered into Modifica-
    tion No. P00012, which provided that DLA would
    reimburse Supreme at 75 percent of the P00010 rates until
    the audit was complete.
    DCAA performed two audits of Supreme’s proposed
    POT costs and concluded that Supreme’s submitted docu-
    mentation was not adequate to support its proposal. In its
    second and more-thorough audit, DCAA examined over
    $602 million in claimed costs and questioned more than
    $375 million of those costs due to inadequate documenta-
    tion.
    Relying on information uncovered during the audit, the
    contracting officer (CO) issued a final decision (COFD I) on
    December 9, 2011, establishing final POT rates that were
    significantly lower than Supreme’s initial, inflated pro-
    posed rates. Using the final rates, the CO determined that
    DLA had overpaid Supreme by $567,267,940 and de-
    manded Supreme return that money. DLA then began
    withholding money from Supreme’s monthly payments,
    eventually totaling over $540 million. In response, Su-
    preme submitted a “reverse image” claim of the govern-
    ment’s December 9, 2011 claim, contending that it was
    entitled to the proposed rates from the start of performance
    and that, in total, it was due an additional $1.8 billion dol-
    lars. The CO denied that claim (COFD II). Supreme then
    submitted a second claim seeking $598,769,101. The CO
    never issued a final decision on that claim. Supreme ap-
    pealed that deemed denial.
    B
    In its proposal, Supreme stated that it would get local,
    market-ready items from Barakat Vegetable and Fruits
    Co., which would consolidate items at a facility in Dubai
    and then airlift them to Afghanistan. Supreme later re-
    quested that Jamal Ahli Foods Co., LLC (JAFCO) be
    Case: 21-1965    Document: 65     Page: 4    Filed: 12/05/2022
    4                            SUPREME FOODSERVICE GMBH v.
    DIRECTOR OF THE DEFENSE LOGISTICS AGENCY
    approved as an additional place of performance for such
    items. DLA approved this request in September 2005.
    In March 2009, Paul Rigby, a self-described “disgrun-
    tled former employee” of Supreme, wrote to the CO and
    DLA, alleging potentially fraudulent activity surrounding
    JAFCO. Specifically, he alleged that JAFCO was wholly
    owned by Supreme, and that when JAFCO would source
    and consolidate local market ready items, it would include
    an “undisclosed mark-up” (a 35 percent increase to the pur-
    chase price) which increased Supreme’s margin to “60ish
    percent.” J.A. 6026; Appellant’s Br. 11. DLA then referred
    the matter to the Defense Criminal Investigation Service,
    and an investigation followed.
    In September 2014, the United States filed a Criminal
    Information in the Eastern District of Pennsylvania
    against Supreme, alleging three counts of fraud. Supreme
    pled guilty to all three counts in December 2014. In its
    Guilty Plea Agreement, Supreme confirmed that it had de-
    vised a scheme to “use JAFCO to make profits over and
    above the profits made from the Distribution Fees in the
    SPV Contract by fraudulently increasing the Delivered
    Price for Local Market Ready . . . goods sold to the United
    States.” J.A. 11087.
    Supreme had also sourced bottled water for U.S. forces
    in Afghanistan. Supreme collected water from various sup-
    pliers and then charged the U.S. $6.45 per case, telling the
    CO that that was the average price it paid. Mr. Epp, Su-
    preme’s Commercial Division Director, later testified that
    water was the most profitable item on the contract because
    Supreme was actually paying less than $2 per case in some
    instances. The $6.45 price also included transportation
    costs, even when the government transported the water.
    Supreme’s guilty plea also acknowledged that it had de-
    frauded the United States by overcharging for bottled wa-
    ter.
    Case: 21-1965    Document: 65     Page: 5    Filed: 12/05/2022
    SUPREME FOODSERVICE GMBH v.                               5
    DIRECTOR OF THE DEFENSE LOGISTICS AGENCY
    In March 2010, Mr. Epp, as relator, filed a qui tam com-
    plaint against Supreme under the False Claims Act in the
    Eastern District of Pennsylvania, alleging the fraudulent
    behavior described above. The United States intervened.
    The relator provided documents from his time at Supreme
    to the Assistant U.S. Attorney, who in turn informed DLA
    that the complaint had been filed and that they had “a fair
    volume of documents” regarding the fraudulent activity.
    J.A. 5436. In 2014, Supreme entered into a civil settlement
    agreement with the relator and the Department of Justice
    to resolve the qui tam action.
    C
    While the fraud investigations were underway and
    with Supreme’s contract set to expire in December 2010,
    the parties entered into Modification No. P00092 on De-
    cember 20, 2010 (the Modification), a two-year extension of
    the contract. In its Justification for Other than Full and
    Open Competition Memo regarding the contract extension,
    DLA explained that “[t]he proposed contract extension is
    required in order to maintain continuous prime vendor cov-
    erage and uninterrupted supply of vitally needed subsist-
    ence items, until implementation of the new, competitively
    awarded prime vendor contract for foodservice support can
    be put in place.” J.A. 11028. The Modification included new
    distribution prices that specifically covered JAFCO. And in
    June 2012, after the Department of Defense and the De-
    partment of Justice had had more than three years to in-
    vestigate any fraud but before Supreme had entered any
    guilty plea, DLA issued a second bridge contract extending
    Supreme’s contract through December 12, 2013.
    In January 2015, based on Supreme’s December 2014
    guilty plea, DLA issued a third CO final decision (COFD
    III) demanding the return of all money paid under the con-
    tract, about $8 billion dollars. Supreme appealed COFD III
    to the Board.
    Case: 21-1965    Document: 65      Page: 6    Filed: 12/05/2022
    6                            SUPREME FOODSERVICE GMBH v.
    DIRECTOR OF THE DEFENSE LOGISTICS AGENCY
    In October 2017, a fourth CO final decision (COFD IV)
    updated the debt determination in COFD I regarding the
    POT rates and duplicated costs. DLA asserted that Su-
    preme owed a total debt of around $350 million. Supreme
    also appealed that decision to the Board.
    D
    In May 2020, the Board issued its decision. As to the
    POT claims, it largely found in DLA’s favor, concluding
    that Supreme had failed to meet its burden of producing
    evidence of its costs sufficient to justify its proposed POT
    rates. The Board then considered DLA’s affirmative de-
    fenses to Supreme’s claims. It discussed whether DLA
    could assert affirmative defenses to a COFD that appears
    to be its own government claim, rather than a typical con-
    tractor claim. The Board concluded that it could address
    DLA’s affirmative defenses because DLA had already with-
    held about $540 million from Supreme to recoup the over-
    payments. “Due to the size of the DLA withholding . . .
    there is a significant possibility that DLA will have to re-
    turn some money to Supreme. If so, Supreme will be poten-
    tially entitled to [Contract Disputes Act] interest on the
    amounts withheld. This interest, then, would fit into the
    ‘box’ of being a contractor claim and, as such, would be sub-
    ject to DLA’s affirmative defenses.” J.A. 55. Thus, the
    Board concluded that it could address DLA’s affirmative
    defense that Supreme’s fraud was a prior material breach
    barring recovery of CDA interest.
    Supreme argued that DLA waived its affirmative de-
    fense by continuing to contract with Supreme even after it
    first learned of Supreme’s fraud. Even though DLA “had
    ample evidence of Supreme’s extensive fraud” by June
    2010, yet still continued with its contract, the Board held
    that DLA had not waived its affirmative defense of first
    material breach because it did not continue the contract af-
    ter Supreme pled guilty. J.A. 56–58. The Board based its
    decision on our prior decision in Laguna Construction
    Case: 21-1965     Document: 65      Page: 7   Filed: 12/05/2022
    SUPREME FOODSERVICE GMBH v.                                 7
    DIRECTOR OF THE DEFENSE LOGISTICS AGENCY
    Company, Inc. v. Carter, where we held that the govern-
    ment could not waive its prior material breach defense un-
    til it had a “known right” to the defense—i.e., when a
    contractor pled guilty to fraud. 
    828 F.3d 1364
    , 1369 (Fed.
    Cir. 2016). The Board also rejected Supreme’s contention
    that DLA’s prior material breach defense did not apply to
    the bridge contract from 2012–2013 because “the SPV and
    bridge contracts were inextricably intertwined for POT
    purposes and the parties treated them as such.” J.A. 60.
    The Board concluded that Supreme committed the first
    material breach and had lost its right to CDA interest.
    Supreme moved for reconsideration of the Board’s de-
    cision, arguing that the Board treated CDA interest as a
    contractual entitlement, rather than a statutory one. The
    Board denied the motion. It agreed with Supreme “that
    CDA interest is a statutory right on a valid claim,” but con-
    cluded that “Supreme’s prior material breach through its
    commission of fraud bars its claim for interest.” J.A. 80.
    The parties subsequently agreed upon quantum amounts,
    and the Board adopted them.
    Supreme now appeals. We have jurisdiction under 
    28 U.S.C. § 1295
    (a)(10).
    II
    Our review of the Board’s decision is limited by statute.
    We review the Board’s legal conclusions de novo, but we
    may not set aside a factual finding unless it is “(A) fraudu-
    lent, arbitrary, or capricious; (B) so grossly erroneous as to
    necessarily imply bad faith; or (C) not supported by sub-
    stantial evidence.” 
    41 U.S.C. § 7107
    (b)(2); Kellogg Brown &
    Root Servs., Inc. v. Sec’y of the Army, 
    973 F.3d 1366
    , 1370
    (Fed. Cir. 2020). Contract interpretation is a question of
    law reviewed without deference. Kellogg Brown & Root
    Servs., Inc., 973 F.3d at 1370. The appellant bears the bur-
    den of establishing reversible error. See Fernandez v. Dep’t
    of the Army, 
    234 F.3d 553
    , 555 (Fed. Cir. 2000).
    Case: 21-1965    Document: 65       Page: 8   Filed: 12/05/2022
    8                            SUPREME FOODSERVICE GMBH v.
    DIRECTOR OF THE DEFENSE LOGISTICS AGENCY
    III
    A
    Supreme argues that DLA waived its prior material
    breach defense by continuing with performance of the con-
    tract even after learning of Supreme’s fraudulent behavior.
    Under the doctrine of prior material breach, “when a
    party to a contract is sued for breach, it may defend on the
    ground that there existed a legal excuse for its nonperfor-
    mance at the time of the alleged breach.” Barron
    Bancshares, Inc. v. United States, 
    366 F.3d 1360
    , 1380
    (Fed. Cir. 2004) (citing Coll. Point Boat Corp. v. United
    States, 
    267 U.S. 12
    , 15 (1925)). “The government may use
    the prior material breach doctrine to defeat a contractor’s
    breach claim.” Laguna, 828 F.3d at 1371.
    The Board held that DLA did not waive its prior mate-
    rial breach defense based on our decision in Laguna. J.A.
    56–57. In Laguna, the government learned of a kickback
    scheme in January 2008 on a construction contract where
    physical work was not complete until 2010. Laguna, 828
    F.3d at 1366. The government obtained its first guilty plea
    from one of Laguna’s project managers in October 2010. Id.
    The parties continued with “conducting audits and making
    cost reimbursements” after the completed physical work in
    2010. Id. at 1372. The government did not raise its first
    material breach defense to the contractor’s claim until after
    a final guilty plea by a Laguna senior executive in 2013. Id.
    at 1367. Laguna argued that the government’s “continued
    performance” of paying incurred costs and auditing La-
    guna’s statements, even after the government knew of the
    kickback scheme, constituted waiver of the prior material
    breach defense.
    We held that “[i]t was reasonable for the government
    to invoke the prior material breach rule after [the senior
    executive] entered a guilty plea in July 2013,” even though
    it had some notice of criminal conduct as early as 2008,
    Case: 21-1965     Document: 65     Page: 9    Filed: 12/05/2022
    SUPREME FOODSERVICE GMBH v.                                 9
    DIRECTOR OF THE DEFENSE LOGISTICS AGENCY
    because prior to the plea, “the government did not have a
    ‘known right’ that would have invoked the prior material
    breach rule.” Id. at 1372. Thus, the actions the government
    took in continuing with the contract after 2008 still “did not
    waive [the government’s] right to invoke the prior material
    breach rule.” Id.
    Laguna applies squarely to the facts of this case. Be-
    cause waiver “is an intentional relinquishment or abandon-
    ment of a known right,” Massie v. United States, 
    166 F.3d 1184
    , 1190 (Fed. Cir. 1983), DLA cannot have waived its
    defense prior to Supreme’s December 2014 guilty plea be-
    cause it did not have a known right until Supreme finally
    entered that guilty plea, conclusively ending the criminal
    investigation into its fraud. Even though DLA had some
    notice of Supreme’s fraudulent behavior beginning in 2009,
    it had no “known right” until Supreme’s guilty plea. And
    DLA never extended Supreme’s contract after Supreme
    pled guilty. Accordingly, we affirm the Board’s conclusion
    that DLA did not waive its affirmative defense of prior ma-
    terial breach.
    B
    Supreme next argues that, even if we conclude that
    DLA did not waive its affirmative defense, we should still
    determine that Supreme is entitled to CDA interest on
    money the government over-withheld. The CDA provides
    that “[i]nterest on an amount found due a contractor on a
    claim shall be paid to the contractor for the period begin-
    ning with the date the CO receives the contractor’s claim,
    pursuant to section 7103(a) of this title, until the date of
    payment of the claim.” 
    41 U.S.C. § 7109
    (a)(1) (emphases
    added). Typically, this provision entitles a contractor to in-
    terest on its own successful claim. But here, there is no
    such successful claim. Although the Board concluded that
    the government had over-withheld approximately $143
    million when addressing the government’s claim, the Board
    terminated Supreme’s claims based on the government’s
    Case: 21-1965     Document: 65      Page: 10     Filed: 12/05/2022
    10                            SUPREME FOODSERVICE GMBH v.
    DIRECTOR OF THE DEFENSE LOGISTICS AGENCY
    prior material breach defense. Supreme seeks interest on
    that over-withheld amount related to the government’s
    claim, despite the fact its own claims did not prevail.
    In Supreme’s view, this statutory language has only
    two requirements for a contractor to be entitled to interest:
    (1) that a contractor is owed a monetary recovery on any
    claim (an “amount found due”), and (2) that the contractor
    submitted its own certified claim to the CO (“on a claim”).
    Appellant’s Reply Br. 31. Under this view, it is enough for
    the contractor to simply submit its own claim—it need not
    prevail on that claim. Thus, Supreme argues that it is en-
    titled to recover interest on the $143 million that the Board
    found Supreme is owed from the money DLA withheld, be-
    ginning from the date Supreme submitted its own certified
    claim to the CO. Appellant’s Br. 61. We must decide
    whether the CDA requires a contractor to successfully pre-
    vail on its own claim to be entitled to interest; or whether
    interest may be assessed on any monetary recovery owed
    for which the contractor submitted a certified claim, re-
    gardless of how unsuccessful that claim may be.
    To answer this question, we look to the statutory text:
    Interest on an amount found due a contractor on a
    claim shall be paid to the contractor for the period
    beginning with the date the contracting officer re-
    ceives the contractor’s claim, pursuant to section
    7103(a) of this title, until the date of payment of the
    claim.
    
    41 U.S.C. § 7109
    (a)(1) (emphases added). This language is
    clear—the “claim” for which a contractor is owed interest
    is “the contractor’s claim.” 
    Id.
     (emphasis added). Nothing
    in this provision grants a contractor the right to receive in-
    terest on an amount due under the Government’s claim. See
    Ruhnau-Evans-Ruhnau Assocs. v. United States, 
    3 Cl. Ct. 217
    , 219 (1983) (“[W]here an award of interest against the
    government is at issue, such congressional silence cannot
    be read as an affirmative grant.”). Rather, it is obvious that
    Case: 21-1965     Document: 65      Page: 11    Filed: 12/05/2022
    SUPREME FOODSERVICE GMBH v.                                  11
    DIRECTOR OF THE DEFENSE LOGISTICS AGENCY
    a contractor must be successful on its own claim to be enti-
    tled to interest under the CDA.
    Supreme relies on a non-precedential decision, Secre-
    tary of the Army v. Kellogg Brown & Root Services, 779 F.
    App’x 716 (Fed. Cir. 2019), to argue that a claim alone is
    all that is required to recover interest. In Kellogg, the con-
    tractor, KBR, brought three certified CDA claims between
    2007 and 2010, seeking to recover a total of $44 million that
    the Army had withheld. Id. at 722. In September 2011,
    KBR brought a fourth certified CDA claim for that same
    $44 million plus interest under the CDA. Id. at 718. In the
    2011 claim, KBR alleged a new legal theory for recovering
    the $44 million plus interest. Id. Although KBR’s original
    legal theories did not prevail, KBR was ultimately success-
    ful on its 2011 legal theory and was awarded $44 million
    plus interest. Id. at 722. The issue on appeal was whether
    the clock for calculating interest on the $44 million recov-
    ery began when the claims for that $44 million were first
    made, or if it began when the prevailing legal theory was
    first raised. We concluded that the Board did not err in
    starting the interest clock as of the 2007 to 2010 claims,
    even though KBR’s prevailing legal theory was not raised
    until the September 2011 claim. Id.
    Kellogg is distinguishable from the circumstances here.
    This case does not ask what event triggers the interest
    clock, but whether a contractor is at all entitled to CDA
    interest if it has not prevailed on its own claim. “The pur-
    pose of the [CDA] interest provision . . . is to provide ‘inter-
    est to the contractor upon a favorable decision on his
    claim. . . .’” Esprit Corp. v. United States, 
    6 Cl. Ct. 546
    , 548
    (1984) (emphases added) (quoting S. Rep. No. 95-1118, at
    32 (1978)). While KBR received a favorable decision on its
    own claim in Kellogg, Supreme has received no favorable
    decision here. Rather, Supreme’s claims failed because of
    the Army’s successful affirmative defense. If anything, Su-
    preme’s circumstances are more analogous to the cases
    that Kellogg distinguished and recognized “stand for the
    Case: 21-1965    Document: 65     Page: 12    Filed: 12/05/2022
    12                           SUPREME FOODSERVICE GMBH v.
    DIRECTOR OF THE DEFENSE LOGISTICS AGENCY
    proposition that defenses to government claims alone are
    not entitled to CDA interest.” Kellogg, 779 F. App’x at
    722–23 (citing, e.g., Magnus Pac. Corp. v. United States,
    
    133 Fed. Cl. 640
     (2017) (“[T]he CDA awards interest on suc-
    cessful contractor claims denied by a contracting officer,
    not on successful appeals of government claims.” (empha-
    ses in original))). Supreme’s prior material breach, through
    its commission of fraud, bars its claim for payment for both
    the underlying amount and any interest that might other-
    wise have been due. We affirm the Board’s denial of CDA
    interest.
    C
    Finally, Supreme argues that DLA’s first material
    breach defense cannot apply to the two subsequently
    awarded contract extensions covering 2010–2012 and
    2012–2013. It contends that those are separate contracts it
    did not breach and that it therefore should be able to re-
    cover CDA interest on the amounts DLA over-withheld
    during the periods of those two contracts. Appellant’s Br.
    66. The crux of its argument is that its actions that consti-
    tuted the material breach (i.e., the JAFCO and bottled wa-
    ter fraud) all occurred before DLA awarded the first
    contract extension in December 2010, and therefore Su-
    preme never breached the 2010–2012 or the 2012–2013
    contracts.
    The Board concluded that the first contract extension,
    from 2010–2012, was clearly not a separate contract be-
    cause it was implemented through a bilateral modification
    to the original contract, despite later references to the ex-
    tension as a bridge contract. J.A. 41, 59. We agree with that
    conclusion—the agreement is clearly styled and executed
    as a modification. See J.A. 4257 (agreement entitled
    “Amendment of Solicitation/Modification of Contract”).
    Thus, DLA’s prior material breach defense applies to the
    2010–2012 extension of the parties’ original contract.
    Case: 21-1965    Document: 65      Page: 13   Filed: 12/05/2022
    SUPREME FOODSERVICE GMBH v.                               13
    DIRECTOR OF THE DEFENSE LOGISTICS AGENCY
    The Board also concluded, and the government does
    not dispute, that the final extension from 2012–2013 is a
    bridge contract, not an extension. J.A. 59. But the Board
    found that the original SPV contract and the bridge con-
    tract “were inextricably intertwined for POT purposes and
    the parties have treated them as such.” J.A. 60. Specifi-
    cally, the bridge contract increased POT rates by 4.5 per-
    cent, but otherwise was very similar to the original
    contract—incorporating by reference all the terms, condi-
    tions, and modification of the original contract, and provid-
    ing that unresolved claims and requests for equitable
    adjustments were not affected by the bridge contract. J.A.
    59. Furthermore, the Board pointed out that “if the bridge
    contract were treated as a separate contract, Supreme
    would need to prove its costs during that contractual pe-
    riod, but it has not done so. It would not be consistent (or
    fair) to allow Supreme to treat the contracts as separate for
    purposes of DLA’s affirmative defenses but one and the
    same for purposes of proving its costs.” J.A. 60.
    We agree that we should not allow Supreme to treat
    the bridge contract as separate only when it attempts to
    evade the government’s affirmative defenses. The parties
    treated the original contract and the bridge contract as in-
    extricably intertwined, and so we shall too. We conclude
    that DLA’s prior material breach defense applies to the
    2012–2013 bridge contract as well.
    IV
    We have considered Supreme’s remaining arguments
    but find them unpersuasive. For the foregoing reasons, we
    affirm.
    AFFIRMED