  • Case: 20-1084    Document: 55     Page: 1   Filed: 12/23/2020
    United States Court of Appeals
    for the Federal Circuit
    ______________________
    BGT HOLDINGS LLC,
    Plaintiff-Appellant
    v.
    UNITED STATES,
    Defendant-Appellee
    ______________________
    2020-1084
    ______________________
    Appeal from the United States Court of Federal Claims
    in No. 1:18-cv-00178-PEC, Judge Patricia E. Campbell-
    Smith.
    ______________________
    Decided: December 23, 2020
    ______________________
    MILTON C. JOHNS, Executive Law Partners, PLLC, Ma-
    nassas, VA, argued for plaintiff-appellant.
    BORISLAV KUSHNIR, Commercial Litigation Branch,
    Civil Division, United States Department of Justice, Wash-
    ington, DC, argued for defendant-appellee. Also repre-
    sented by JEFFREY B. CLARK, ELIZABETH MARIE HOSFORD,
    ROBERT EDWARD KIRSCHMAN, JR.
    ______________________
    Before PROST, Chief Judge, BRYSON and STOLL, Circuit
    Judges.
    Case: 20-1084    Document: 55      Page: 2    Filed: 12/23/2020
    2                         BGT HOLDINGS LLC   v. UNITED STATES
    BRYSON, Circuit Judge.
    BGT Holdings LLC appeals from a decision of the
    United States Court of Federal Claims (“the Claims Court”)
    dismissing its claims arising from the U.S. Navy’s with-
    holding of certain government-furnished equipment under
    a fixed-price contract. The dismissal followed the court’s
    ruling that BGT had contractually waived its claims of con-
    structive change through ratification, official change
    through waiver, and breach for failure to award an equita-
    ble adjustment. The court also held that BGT insuffi-
    ciently alleged a breach of the implied duty of good faith
    and fair dealing. We affirm the dismissal of the breach of
    good faith and fair dealing claim but vacate the court’s dis-
    missal of the remaining claims.
    I
    A
    In 2014, BGT contracted with the Navy to construct
    and deliver a gas turbine generator. The Navy agreed to
    supply certain government-furnished equipment (“GFE”)
    that BGT would use to construct the generator. Two of the
    GFE items identified in the contract—an exhaust collector
    and engine mounts—are relevant to this appeal because
    the Navy ultimately did not deliver those items to BGT.
    The withdrawal of those items and the Navy’s failure to
    compensate BGT for that withdrawal are the source of the
    dispute in this case.
    The contract incorporated various clauses from the
    Federal Acquisition Regulation (“FAR”). For convenience,
    we cite to the FAR when referencing those contract clauses.
    One such clause, the “government property” clause, pro-
    vides as follows in relevant part:
    Case: 20-1084    Document: 55      Page: 3   Filed: 12/23/2020
    BGT HOLDINGS LLC   v. UNITED STATES                         3
    (d) Government-furnished property.
    (1) The Government shall deliver to the Contractor
    the Government-furnished property described in
    this contract. . . .
    (2) The delivery and/or performance dates specified
    in this contract are based upon the expectation that
    the Government-furnished property will be suita-
    ble for contract performance and will be delivered
    to the Contractor by the dates stated in the con-
    tract.
    (i) If the property is not delivered to the Contractor
    by the dates stated in the contract, the Contracting
    Officer shall, upon the Contractor’s timely written
    request, consider an equitable adjustment to the
    contract.
    ...
    (3)(i) The Contracting Officer may by written no-
    tice, at any time—
    (A) Increase or decrease the amount of Govern-
    ment-furnished property under this contract;
    ...
    (C) Withdraw authority to use property.
    (ii) Upon completion of any action(s) under para-
    graph (d)(3)(i) of this clause, and the Contractor’s
    timely written request, the Contracting Officer
    shall consider an equitable adjustment to the con-
    tract.
    ...
    (i) Equitable adjustment. Equitable adjustments
    under this clause shall be made in accordance with
    the procedures of the Changes clause. However,
    Case: 20-1084     Document: 55     Page: 4    Filed: 12/23/2020
    4                          BGT HOLDINGS LLC   v. UNITED STATES
    the Government shall not be liable for breach of
    contract for the following:
    (1) Any delay in delivery of Government-furnished
    property.
    (2) Delivery of Government-furnished property in a
    condition not suitable for its intended use.
    (3) An increase, decrease, or substitution of Gov-
    ernment-furnished property.
    
    48 C.F.R. § 52.245-1
    .
    To summarize, subsection (d)(1) of the government
    property clause requires the Navy to deliver the designated
    GFE; subsection (d)(2)(i) provides that the Navy “shall con-
    sider” an equitable adjustment if it does not deliver the des-
    ignated GFE by the agreed-upon date; subsection (d)(3)(i)
    gives the Navy the right to modify its GFE commitments;
    and subsection (d)(3)(ii) provides that the Navy “shall con-
    sider” an equitable adjustment if it modifies those GFE
    commitments. Separately, subsection (i) requires that eq-
    uitable adjustments be made according to the procedures
    in the contract’s changes clause. Subsection (i) also pro-
    vides that neither the Navy’s modifications to its GFE com-
    mitments nor its untimely delivery of GFE will constitute
    a breach of the contract.
    The contract incorporates the standard FAR changes
    clause for fixed-price contracts, 
    48 C.F.R. § 52.243-1
    . The
    fixed-price changes clause covers the Navy’s modifications
    to the method of shipment, the method of packing, the place
    of delivery, and the “[d]rawings, designs, or specifications”
    for specially manufactured items. 
    Id.
     The clause provides
    that if the Navy makes any of those modifications, the con-
    tracting officer “shall make an equitable adjustment.” 
    Id.
    The contract also incorporates a changes clause from
    outside the FAR that defines “authorized changes” for the
    entire contract. That clause is unique to the Naval Surface
    Case: 20-1084    Document: 55      Page: 5   Filed: 12/23/2020
    BGT HOLDINGS LLC   v. UNITED STATES                         5
    Warfare Center Carderock Division and is referred to as
    the NSWCCD changes clause. It states as follows:
    (a) Except as specified in paragraph (b) below, no
    order, statement, or conduct of Government per-
    sonnel who visit the Contractor’s facilities or in any
    other manner communicates with Contractor per-
    sonnel during the performance of this contract
    shall constitute a change under the “Changes”
    clause of this contract.
    (b) The Contractor shall not comply with any order,
    direction or request of Government personnel un-
    less it is issued in writing and signed by the Con-
    tracting Officer, or is pursuant to specific authority
    otherwise included as a part of this contract.
    The NSWCCD changes clause lists the contact infor-
    mation for the contracting officer, Mr. John Stefano, and
    declares that “[t]he Contracting Officer is the only person
    authorized to approve changes in any of the requirements
    of this contract.” The clause then warns that “any change
    at the direction of any person other than the Contracting
    Officer . . . will be considered to have been made without
    authority and no adjustment will be made in the contract
    price to cover any increase in charges incurred as a result
    thereof.”
    B
    We recount the facts according to BGT’s factual allega-
    tions in its amended complaint, which we accept as true for
    purposes of the Navy’s motion to dismiss. See Ashcroft v.
    Iqbal, 
    556 U.S. 662
    , 678 (2009).
    A few months into the contract performance, the Navy
    procurement team—including Ms. Suzanne Onesti, the
    procurement manager—informed BGT that the Navy
    would not deliver the exhaust collector and engine mounts
    unless BGT provided a “cost savings” to the Navy, i.e., a
    decrease in the contract price commensurate with the
    Case: 20-1084    Document: 55      Page: 6    Filed: 12/23/2020
    6                         BGT HOLDINGS LLC   v. UNITED STATES
    amount BGT would save by not having to procure the ex-
    haust collector and engine mounts on its own. When asked
    about cost savings at oral argument, neither the govern-
    ment nor BGT identified a contract provision giving the
    Navy the right to demand a cost savings in exchange for
    supplying the designated items of GFE.
    BGT declined to offer a cost savings for the exhaust col-
    lector and engine mounts that were to be provided as GFE.
    The Navy then notified BGT that the exhaust collector and
    engine mounts had been reallocated as fleet assets and
    would no longer be made available to BGT. To continue
    performing under the contract, BGT purchased those items
    on the commercial market at a cost of $610,775. BGT then
    submitted a request for an equitable adjustment for the
    cost of those items. In early 2017, BGT delivered the com-
    pleted gas turbine generator to the Navy. The Navy ac-
    cepted the generator but rejected BGT’s request for an
    equitable adjustment for the cost of the exhaust collector
    and engine mounts.
    According to BGT, the Navy’s request for a cost savings
    and the Navy’s final notice of GFE withdrawal were com-
    municated at the direction of the contracting officer, Mr.
    Stefano. BGT does not allege, however, that the contract-
    ing officer issued a signed order concerning either commu-
    nication.
    Instead, BGT alleges facts that circumstantially con-
    nect the contracting officer to the GFE negotiations. Ac-
    cording to BGT, the Navy instructed BGT to direct all
    communications to Navy employees Ms. Onesti and Ms.
    Carolyn McCloskey, “the conduits to the larger Navy
    team.” BGT also alleges that it was the “usual course of
    performance” for the contracting officer’s decisions to be
    communicated through Ms. Onesti or Ms. McCloskey. For
    example, Ms. Onesti communicated a directive that BGT
    should use its own testing data to size the water treatment
    system for the gas turbine.            Mr. Stefano later
    Case: 20-1084     Document: 55     Page: 7    Filed: 12/23/2020
    BGT HOLDINGS LLC   v. UNITED STATES                         7
    acknowledged that “when Ms. Onesti advised BGT that
    [the Navy] agreed that the water test results provided by
    BGT were to be used in sizing water treatment system for
    the [turbine], it could be construed as being tantamount to
    acceptance and authorization to proceed with the contrac-
    tor’s intended revisions.”
    Furthermore, according to BGT, the contracting officer
    must have directed the Navy’s communications regarding
    the exhaust collector and engine mounts because he was
    the only person with authority to withdraw those GFE
    items and reallocate them as fleet assets. Relatedly, BGT
    alleges that the contracting officer “knew or should have
    known” of the Navy’s request for a cost savings and the
    Navy’s threatened withdrawal of GFE because BGT com-
    municated those issues in progress reports that were regu-
    larly distributed to the contracting officer.
    C
    BGT organized its amended complaint into five counts.
    Two of those counts, Counts IV and V, are not at issue in
    this appeal.
    A fair reading of the allegations in Counts I through III
    reveals five possible grounds for relief: First, the complaint
    alleges that the Navy’s decision to withdraw the exhaust
    collector and engine mounts constituted a constructive
    change of the GFE provision for which BGT is entitled to
    an equitable adjustment. Although the contracting officer
    did not issue a signed order withdrawing those items of
    GFE, the complaint alleges that the contracting officer rat-
    ified the Navy’s decision to withdraw those items by real-
    locating them as fleet assets, thus providing the requisite
    authority for a constructive change.
    Second, the complaint alleges that the contracting of-
    ficer waived the Navy’s rights under the NSWCCD changes
    clause, thus converting the Navy’s decision to decrease
    Case: 20-1084    Document: 55     Page: 8    Filed: 12/23/2020
    8                         BGT HOLDINGS LLC   v. UNITED STATES
    GFE into an official change for which BGT is entitled to an
    equitable adjustment.
    Third, the complaint alleges that the Navy breached its
    contractual duty to deliver the exhaust collector and engine
    mounts, and that BGT is entitled to contract damages for
    that breach.
    Fourth, the complaint alleges that the Navy breached
    its contractual duty to provide BGT an equitable adjust-
    ment after failing to deliver those GFE items, and that
    BGT is entitled to contract damages for that breach.
    Fifth, the complaint alleges that the Navy breached its
    implied duty of good faith and fair dealing by intentionally
    withholding those GFE items and thus obstructing BGT’s
    performance under the contract. BGT contends that it is
    entitled to an award of damages for that breach.
    Under each of its theories of liability, BGT seeks an
    award of $610,775, the cost BGT incurred in purchasing
    the exhaust collector and engine mounts on the commercial
    market.
    The Claims Court dismissed Counts I through III of
    BGT’s amended complaint and entered a final judgment on
    those counts under Rule 54(b) of the Rules of the Court of
    Federal Claims. BGT Holdings, LLC v. United States, 
    142 Fed. Cl. 474
    , 484 (2019). The Rule 54(b) judgment entitled
    BGT to take an immediate appeal from the dismissal of
    those counts.
    The Claims Court consolidated its analysis of BGT’s
    first two claims—constructive change through ratification
    and official change through waiver. The court held that
    neither claim entitled BGT to an equitable adjustment, be-
    cause “the specific contract language at issue here pre-
    cludes [BGT’s] arguments relating to ratification and
    waiver.” 
    Id.
     at 479–80, 482 (citing the NSWCCD changes
    clause and subsection (i) of the government property
    clause).
    Case: 20-1084     Document: 55       Page: 9    Filed: 12/23/2020
    BGT HOLDINGS LLC   v. UNITED STATES                           9
    The court held BGT’s claim of breach for failure to de-
    liver the exhaust collector and engine mounts to be pre-
    cluded by subsection (i) of the government property clause,
    which states that “the Government shall not be liable for
    breach of contract for . . . [a]n increase, decrease, or substi-
    tution of [GFE].” 
    Id.
     at 482–83. Likewise, the court held
    that the contract precluded BGT’s claim of breach for fail-
    ure to provide an equitable adjustment, rejecting that
    claim based on its analysis of BGT’s first two claims. 
    Id. at 482
    . The court rejected BGT’s final claim, alleging breach
    of the implied duty of good faith and fair dealing, given the
    Navy’s right to decrease or withdraw GFE under the con-
    tract. 
    Id.
     at 483–84.
    II
    On appeal, BGT does not challenge the court’s holding
    that the government property clause precludes BGT’s
    claim of breach for failure to deliver the exhaust collector
    and engine mounts. See 
    48 C.F.R. § 52.245-1
    (i) (precluding
    claims of breach for the increase, decrease, substitution, or
    delay in delivery of GFE). BGT challenges the dismissal of
    its remaining claims, however. With respect to rights aris-
    ing under the contract, BGT argues that it is entitled to an
    equitable adjustment under both the government property
    clause and the fixed-price changes clause. In addition,
    BGT contends that it is entitled to compensation because
    the government breached its implied duty of good faith and
    fair dealing by withdrawing GFE items and then refusing
    to compensate BGT for that withdrawal through an equi-
    table adjustment.
    A
    The most straightforward claim in BGT’s amended
    complaint is that the Navy breached the government prop-
    erty clause, 
    48 C.F.R. § 52.245-1
    , by failing to provide an
    equitable adjustment after it withheld the GFE items it
    had agreed to deliver under the contract.
    Case: 20-1084    Document: 55      Page: 10     Filed: 12/23/2020
    10                        BGT HOLDINGS LLC   v. UNITED STATES
    While the Navy was entitled to withdraw GFE under
    the government property clause, it was not free to do so
    without consequence. Two subsections of the government
    property clause are applicable to withdrawals of GFE.
    First, under subsection (d)(3)(i) of that clause, the contract-
    ing officer “may, by written notice, at any time—(A) In-
    crease or decrease the amount of Government-furnished
    property under this contract; . . . .” In that event, subsec-
    tion (d)(3)(ii) requires that the contracting officer “shall
    consider an equitable adjustment to the contract.” Second,
    under subsection (d)(2)(i) of the government property
    clause, if the GFE promised under the contract “is not de-
    livered to the Contractor by the dates stated in the con-
    tract, the Contracting Officer shall, upon the Contractor’s
    timely written request, consider an equitable adjustment
    to the contract.” Those two subsections cover cases in
    which GFE is not delivered, either by formal order of the
    contracting officer or otherwise. In either event, the rem-
    edy is the same: The contracting officer must consider an
    equitable adjustment.
    BGT pleaded facts sufficient to support a claim of
    breach under the government property clause. Count II of
    the amended complaint alleges that the Navy’s “refusal to
    provide an equitable adjustment was a material breach of
    the Contract.” J.A. 33. Count II also incorporates facts
    from earlier portions of the amended complaint, including
    that the Navy withdrew certain GFE items, that BGT was
    forced to purchase those items on the commercial market
    because they were not delivered, that BGT requested an
    equitable adjustment in a timely manner, and that the
    Navy denied that request.
    Even assuming that the contracting officer is not
    chargeable—through ratification or otherwise—with hav-
    ing ordered the withdrawal of the exhaust collector and en-
    gine mounts, the Claims Court erred by not considering the
    pathway to relief under subsection (d)(2)(i) of the govern-
    ment property clause.       That pathway is available
    Case: 20-1084    Document: 55      Page: 11    Filed: 12/23/2020
    BGT HOLDINGS LLC   v. UNITED STATES                        11
    regardless of whether the contracting officer executed a
    written authorization for withdrawing items of GFE iden-
    tified in the contract.
    If relief under subsection (d)(2)(i) were not available,
    and the contractor could seek relief only under subsection
    (d)(3)(ii), the government could avoid liability for reneging
    on its GFE commitments in any case simply by withdraw-
    ing GFE items without a written notice from the contract-
    ing officer. The availability of relief under subsection
    (d)(2)(i) provides a backstop against such a ploy.
    The government argues that BGT’s claim under sub-
    section (d)(2)(i) is untenable because the contracting officer
    was required only to “consider BGT’s request for an equi-
    table adjustment—not to grant the adjustment to BGT.”
    Appellee’s Br. 27. 1 Under the government’s theory, the
    phrase “shall consider” gave the contracting officer discre-
    tion to grant or deny an equitable adjustment and imposed
    no duty to grant an adjustment even if BGT could prove
    financial loss due to the government’s withdrawal of the
    exhaust collector and engine mounts.
    We reject the government’s interpretation of the term
    “shall consider” because it would produce absurd results
    under the government property clause. See United States
    v. Winstar Corp., 
    518 U.S. 839
    , 907 (1996) (avoiding a con-
    tract interpretation that “would be absurd”); Keepseagle v.
    Perdue, 
    856 F.3d 1039
    , 1047 (D.C. Cir. 2017) (interpreting
    an ambiguous contract term in order to avoid an absurd
    result). To illustrate, assume that the committed GFE in
    this case had a total value nearing $5 million, well over half
    of the contract price of $8.25 million. See J.A. 24–25. If the
    1   While the government asserted this argument in
    connection with subsection (d)(3)(ii), its logic would extend
    to subsection (d)(2)(i) because that subsection also includes
    the “shall consider” phrase.
    Case: 20-1084     Document: 55      Page: 12    Filed: 12/23/2020
    12                         BGT HOLDINGS LLC   v. UNITED STATES
    Navy had withdrawn all GFE, as the contract allows, it
    would be implausible to posit that the Navy’s only obliga-
    tion would be merely to “think over” BGT’s request for an
    equitable adjustment before denying it. It is dubious, to
    say the least, that the drafters of the FAR’s government
    property clause, 
    48 C.F.R. § 52.245-1
    , envisioned that the
    government would essentially have an unfettered right to
    withdraw promised GFE from a contract without conse-
    quence.
    The correct interpretation of “shall consider” in this
    contract setting does not give the government absolute dis-
    cretion, but instead holds the government to a duty of good
    faith and reasonableness. See Goldstein v. Johnson &
    Johnson, 
    251 F.3d 433
    , 444 (3d Cir. 2001) (“Ordinary con-
    tract principles require that, where one party is granted
    discretion under the terms of the contract, that discretion
    must be exercised in good faith—a requirement that in-
    cludes the duty to exercise the discretion reasonably.” (cit-
    ing the Restatement (Second) of Contracts § 205 & cmt. a));
    Walsh v. Zurich Am. Ins. Co., 
    853 F.3d 1
    , 14 (1st Cir. 2017)
    (stating the same under New Hampshire law); Stokes v.
    DISH Network, L.L.C., 
    838 F.3d 948
    , 952 (8th Cir. 2016)
    (stating the same under Colorado law). Moreover, the FAR
    demands that the contracting officer exercise impartiality,
    fairness, and equitable treatment when considering re-
    quests for equitable adjustments. See 
    48 C.F.R. § 1.602-2
    (“Contracting officers shall . . . (b) Ensure that contractors
    receive impartial, fair, and equitable treatment; . . . .”). The
    government’s interpretation of “shall consider” would in-
    vite subversion of that responsibility.
    Accordingly, we vacate the dismissal of BGT’s claim
    that the Navy breached its duty to provide an equitable ad-
    justment after it failed to deliver the exhaust collector and
    engine mounts. On remand, the Claims Court must deter-
    mine whether BGT is entitled to an equitable adjustment
    as fair compensation for the failure to deliver those GFE
    items.
    Case: 20-1084    Document: 55      Page: 13    Filed: 12/23/2020
    BGT HOLDINGS LLC   v. UNITED STATES                        13
    B
    Apart from subsection (d)(2)(i) of the government prop-
    erty clause, BGT argues that it is entitled to an equitable
    adjustment under either subsection (d)(3)(ii) of the govern-
    ment property clause or the fixed-price changes clause.
    The Claims Court rejected that claim on the ground that
    the Navy’s withdrawal of GFE was not communicated in a
    writing signed by the contracting officer, as required by the
    NSWCCD changes clause, and therefore was not compen-
    sable under the contract. 2
    In response, BGT argues that the Navy’s withdrawal of
    the exhaust collector and engine mounts constituted a con-
    structive change to the contract because that withdrawal
    was ratified by the contracting officer after the fact. In the
    alternative, BGT argues that the Navy’s withdrawal of
    those GFE items constituted an official change to the
    2   The government argues that BGT waived its claim
    for an equitable adjustment based on a constructive change
    because the amended complaint did not contain a citation
    to the changes clause, 
    48 C.F.R. § 52.243-1
    . Rule 9(k) of
    the Rules of the Court of Federal Claims, on which the gov-
    ernment relies, requires a party pleading a claim founded
    on a contract to identify the substantive provisions of the
    contract on which the party relies or annex to the com-
    plaint a copy of the contract, indicating the relevant por-
    tions. BGT annexed a copy of the contract to its amended
    complaint, and its claim of constructive change effectively
    identified the changes clause as the source of its asserted
    right to an equitable adjustment. See J.A. 31. Moreover,
    the government waived this argument by not raising it be-
    fore the Claims Court. The government’s only reference to
    Rule 9(k) before the Claims Court related to the govern-
    ment property clause, not the changes clause. See J.A. 180.
    Case: 20-1084    Document: 55      Page: 14    Filed: 12/23/2020
    14                        BGT HOLDINGS LLC   v. UNITED STATES
    contract because the Navy waived any requirement that
    the change be approved in writing by the contracting of-
    ficer. 3
    1
    To demonstrate a constructive change, a plaintiff must
    show (1) that it performed work beyond the contract’s re-
    quirements, and (2) that the additional work was ordered,
    expressly or impliedly, by the government. Bell/Heery v.
    United States, 
    739 F.3d 1324
    , 1335 (Fed. Cir. 2014). As to
    the second element, the directive ordering the additional
    work must come from an individual having actual author-
    ity to bind the government. RMA Eng’g S.A.R.L. v. United
    States, 
    140 Fed. Cl. 191
    , 234 (2018) (citing Winter v. Cath-
    dr/Balti Joint Venture, 
    497 F.3d 1339
    , 1344 (Fed. Cir.
    2007)). A clause that explicitly and exclusively assigns
    modification authority to a contracting officer ensures that
    other employees are not deemed to have implied authority
    to modify the contract. Winter, 
    497 F.3d at 1346
    . In this
    case, the NSWCCD changes clause assigned modification
    authority exclusively to the contracting officer. As a result,
    3   Because both parties treat the NSWCCD changes
    clause as applicable to the withdrawal of the GFE in this
    case, we accept that premise for purposes of the changes
    clause arguments. It is not clear, however, that the
    changes clause applies with full force to a case such as this
    one, in which the government is not directing the contrac-
    tor to make changes but is unilaterally making the changes
    itself. In that setting, it makes little sense to say that the
    contractor should not undertake to make changes other
    than as directed in a written order by the contracting of-
    ficer, since the contractor has no way to decline to make a
    change that was made unilaterally by the government,
    whether directed by the contracting officer or otherwise.
    Case: 20-1084    Document: 55     Page: 15    Filed: 12/23/2020
    BGT HOLDINGS LLC   v. UNITED STATES                       15
    other Navy employees, including Ms. Onesti, did not have
    actual or implied authority to modify the contract.
    BGT does not allege that Ms. Onesti or any other Navy
    employee acted with actual or implied authority when com-
    municating the Navy’s decision to withdraw the exhaust
    collector and engine mounts. Instead, BGT alleges ratifi-
    cation as a substitute for actual authority. See Northrop
    Grumman Sys. Corp. v. United States, 
    140 Fed. Cl. 249
    , 277
    (2018) (analyzing ratification as a substitute for actual au-
    thority within the context of constructive change); see also
    Winter, 
    497 F.3d at 1346
    ; Restatement (Third) of Agency
    § 4.01 (2006) (“Ratification is the affirmance of a prior act
    done by another, whereby the act is given effect as if done
    by an agent acting with actual authority.”).
    According to BGT’s amended complaint, the contract-
    ing officer ratified the Navy’s informal decision to decrease
    the GFE because the contracting officer had knowledge of
    that decision from submitted progress reports and affirmed
    that decision by reallocating the exhaust collector and en-
    gine mounts as fleet assets. Assuming that a constructive
    change did occur, BGT has a plausible path to a remedy
    under either subsection (d)(3)(ii) of the government prop-
    erty clause or the fixed-price changes clause. See NavCom
    Def. Elecs., Inc. v. England, 53 F. App’x 897, 900 (Fed. Cir.
    2002) (noting that the remedy for a constructive change is
    “an equitable adjustment under the ‘changes’ provision of
    the contract” (quoting Ets-Hokin Corp. v. United States,
    
    420 F.2d 716
    , 720 (Ct. Cl. 1970))).
    In dismissing BGT’s claim of constructive change, the
    Claims Court did not reach the merits of BGT’s ratification
    theory, i.e., whether BGT alleged sufficient facts to support
    a plausible claim of constructive change through ratifica-
    tion. See BGT Holdings, 142 Fed. Cl. at 479–82. Rather,
    the court held that BGT had contractually waived its right
    to assert ratification by agreeing to the NSWCCD changes
    clause. Id. at 481–82. The court noted that the NSWCCD
    Case: 20-1084    Document: 55      Page: 16    Filed: 12/23/2020
    16                        BGT HOLDINGS LLC   v. UNITED STATES
    changes clause warned BGT not to comply “with any order,
    direction or request” from anyone other than the contract-
    ing officer and that it put BGT on notice that “no adjust-
    ment will be made in the contract price to cover any
    increase in charges incurred as a result” of unauthorized
    orders. Id. at 482. According to the court, that unambigu-
    ous language precludes ratification, and by agreeing to
    that clause, BGT waived its right to assert ratification in
    future litigation. Id.
    BGT argues that the language of the NSWCCD
    changes clause does not address ratification and thus does
    not preclude a finding of ratification in this case. We agree.
    Our decision in Winter v. Cath-dr/Balti Joint Venture, 
    497 F.3d 1339
     (Fed. Cir. 2007), provides strong support for
    BGT’s argument on this issue. The changes clause in the
    contract at issue in Winter is quite similar to the NSWCCD
    changes clause in this case. And in spite of the changes
    clause in Winter, we effectively endorsed the possibility of
    ratification in Winter by remanding the case for a more de-
    tailed analysis of the plaintiff’s ratification theory.
    The government argues that Winter is distinguishable
    because the changes clause in that case contained addi-
    tional language stating that unauthorized modifications
    would not bind the government “unless formalized by
    proper contractual documents executed by the Contracting
    Officer prior to completion of this contract.” Winter, 
    497 F.3d at 1345
    . According to the government, that clause
    provided a contractual basis for the plaintiff’s ratification
    theory in Winter that is not present here. Second, the gov-
    ernment points out that contract-based waiver was not as-
    serted in the Winter case. As a result, the government
    argues that Winter did not resolve the issue of contract-
    based waiver.
    We disagree with the government’s first argument.
    The “unless” clause in Winter did not grant the contracting
    officer in that case any additional authority to ratify
    Case: 20-1084    Document: 55      Page: 17     Filed: 12/23/2020
    BGT HOLDINGS LLC   v. UNITED STATES                         17
    changes relative to the contracting officer’s authority in
    this case. It is clear that none of the contract provisions in
    this case—including the NSWCCD changes clause and sub-
    section (d)(3)(i) of the government property clause—re-
    strict the contracting officer’s authority to ratify an
    unauthorized change after the fact. If anything, relative to
    this case, the “unless” clause in Winter had the effect of lim-
    iting ratification authority by specifying the circumstances
    in which the contracting officer could ratify a prior action
    by an unauthorized government employee. The contract in
    Winter is thus not distinguishable from the contract in this
    case in a way that undermines BGT’s ratification argu-
    ment.
    As for the government’s second argument, it is true
    that Winter did not address contractual waiver and thus
    does not represent binding precedent as to that issue.
    Nonetheless, by recognizing the availability of ratification
    in the face of contract provisions similar to those in this
    case, Winter at least casts doubt on the proposition that
    contract language that is silent as to ratification, such as
    the language in the NSWCCD changes clause, is sufficient
    to bar a contractor’s ratification theory.
    In light of our decision in Winter, the language of the
    NSWCCD changes clause, and the contract as a whole, we
    hold that BGT did not contractually waive its ratification
    theory. The contract in this case does not mention “ratifi-
    cation.” Nor does the contract otherwise expressly limit the
    contracting officer’s authority to ratify prior actions that
    were not made in full compliance with procedures required
    by the contract. Contrary to the government’s contention,
    the NSWCCD changes clause simply does not address the
    fact pattern of ratification—an unauthorized employee
    communicating a change in the first instance, and the con-
    tracting officer taking affirmative steps to confirm that
    change.
    Case: 20-1084    Document: 55      Page: 18    Filed: 12/23/2020
    18                        BGT HOLDINGS LLC   v. UNITED STATES
    Accordingly, we vacate the dismissal of BGT’s claim
    that the Navy’s decision to decrease GFE was a construc-
    tive change through ratification. We remand for the
    Claims Court to determine whether BGT pleaded facts suf-
    ficient to support its ratification theory and, if so, whether
    BGT can prove that the contracting officer ratified the
    withdrawal of the exhaust collector and engine mounts.
    2
    In addition to pleading ratification, BGT alleges that
    the contracting officer waived the requirement that
    changes be made only through a signed writing, thus mak-
    ing the Navy’s decision to withdraw GFE an official change
    under the contract. If BGT prevails on its theory of official
    change through waiver, it would have a plausible path to a
    remedy under either subsection (d)(3)(ii) of the government
    property clause or the fixed-price changes clause.
    BGT asserts that the contracting officer waived the
    Navy’s rights under the NSWCCD changes clause through
    a pattern of conduct. In particular, BGT alleges that the
    contracting officer, by virtue of his position of authority,
    knew of the Navy’s right to make changes exclusively
    through a signed writing. BGT further alleges that the
    contracting officer relinquished that right when he author-
    ized the withdrawal of GFE—which only he had the au-
    thority to do—and did so other than through a signed,
    written order. Finally, BGT alleges that the contracting
    officer waived that right when he characterized a previous
    communication from Ms. Onesti as being “tantamount to
    acceptance and authorization” of a requested operating
    procedure.
    As with BGT’s claim of constructive change, the Claims
    Court did not address whether BGT alleged sufficient facts
    to support a plausible claim of change through waiver. See
    BGT Holdings, 142 Fed. Cl. at 479–82. Rather, the court
    dismissed BGT’s claim of waiver for the same reasons it
    dismissed BGT’s claim of constructive change: It held that
    Case: 20-1084    Document: 55     Page: 19    Filed: 12/23/2020
    BGT HOLDINGS LLC   v. UNITED STATES                       19
    BGT had contractually waived its right to assert waiver by
    agreeing to the NSWCCD changes clause, which was “un-
    ambiguously and diametrically opposed” to BGT’s waiver
    theory. Id. at 481–82.
    BGT argues that the language of the NSWCCD
    changes clause does not address waiver and thus does not
    preclude its waiver theory. The government takes the op-
    posite position. Neither party cites precedent that is di-
    rectly relevant to the issue. And our decision in Winter did
    not address the type of waiver theory that BGT asserts.
    We hold that BGT did not contractually waive its
    waiver theory. The NSWCCD changes clause has nothing
    to say about the fact pattern of waiver, i.e., an authorized
    individual with knowledge of a contract right taking ac-
    tions that evince an intent to abandon that right.
    The NSWCCD changes clause warns BGT not to com-
    ply with any order “unless it is in writing and signed by the
    Contracting Officer.” To be sure, that language addresses
    actions by the contracting officer, an authorized individual
    with knowledge of contract rights. But the purpose of that
    language is to warn BGT to disregard orders from unau-
    thorized personnel, not to prevent the contracting officer
    (or some other high-level official) from intentionally waiv-
    ing the government’s rights as to how changes must be or-
    dered.
    The government argues that BGT’s waiver theory con-
    tradicts the NSWCCD changes clause because that clause
    “unambiguously states that any directive by unauthorized
    Government personnel ‘will be considered to have been
    made without authority.’” Appellee’s Br. 21. Relatedly, the
    government argues that BGT’s waiver theory would con-
    tradict the settled principle that actions by unauthorized
    government employees do not bind the government.
    The government’s arguments miss the point. BGT is
    not asserting that lower-level employees waived the Navy’s
    Case: 20-1084    Document: 55     Page: 20    Filed: 12/23/2020
    20                       BGT HOLDINGS LLC   v. UNITED STATES
    rights. Nor could it make such an assertion, because the
    doctrine of waiver assumes that the individual committing
    waiver has authority to waive a right in the first instance.
    See Molton, Allen & Williams, Inc. v. Harris, 
    613 F.2d 1176
    , 1178 (D.C. Cir. 1980) (analyzing “whether the gov-
    ernment agent dealing with appellant had authority to and
    in fact did waive [a contract] provision”); Globe Indem. Co.
    v. United States, 
    102 Ct. Cl. 21
    , 38 (1944) (holding that the
    government’s engineer and architect did not have author-
    ity to waive certain contract rights). Rather, BGT is assert-
    ing that the contracting officer waived the Navy’s rights,
    which does not contradict the settled principle that actions
    by unauthorized government personnel cannot bind the
    government. See Winter, 
    497 F.3d at 1344
    .
    Because we disagree with the Claims Court’s ruling
    that BGT’s waiver theory was precluded by the contract,
    we vacate the dismissal of BGT’s claim of official change
    through waiver. We remand for the court to determine
    whether BGT pleaded facts sufficient to support its waiver
    theory and, if so, whether the contracting officer waived the
    requirement that changes be made only by a written order
    of the contracting officer.
    C
    The final claim for relief in BGT’s amended complaint
    is that the Navy breached its implied duty of good faith and
    fair dealing by intentionally withholding the exhaust col-
    lector and engine mounts and by communicating its deci-
    sion to withhold those GFE items in an unsanctioned
    manner. BGT alleges that the Navy’s conduct frustrated
    BGT’s ability to perform its contractual obligations by forc-
    ing it to incur $610,775 in excess costs.
    In dismissing BGT’s claim, the Claims Court consid-
    ered the express language of the contract, which gives the
    Navy the ability to decrease or withdraw GFE and pre-
    cludes a claim of breach for such actions. BGT Holdings,
    142 Fed. Cl. at 483–84 (citing subsections (d)(3)(i)(A),
    Case: 20-1084    Document: 55      Page: 21    Filed: 12/23/2020
    BGT HOLDINGS LLC   v. UNITED STATES                        21
    (d)(3)(i)(A)(C), and (i)(3) of the government property
    clause). As a result, the court held that the Navy’s with-
    drawal of GFE did not violate its implied duty of good faith
    and fair dealing. Id.
    We agree with the Claims Court that the implied duty
    of good faith and fair dealing provides no basis for extra-
    contractual relief in this case. The contract unquestionably
    gives the Navy the right to decrease or withdraw GFE.
    BGT cannot use the doctrine of good faith and fair dealing
    to complain of the very conduct that the contract expressly
    permits. See Precision Pine & Timber, Inc. v. United
    States, 
    596 F.3d 817
    , 831 (Fed. Cir. 2010) (“The implied
    duty of good faith and fair dealing cannot expand a party’s
    contractual duties beyond those in the express contract or
    create duties inconsistent with the contract’s provisions.”).
    For the reasons set forth in parts II-A and II-B above,
    the contract itself provides other avenues of relief for BGT
    that preempt the need to invoke the doctrine of good faith
    and fair dealing. BGT’s complaints regarding the Navy’s
    practice of communicating directives other than through
    the contracting officer’s signed writing are fully addressed
    by BGT’s alternative theories for relief under the govern-
    ment property clause and the fixed-price changes clause as
    we have construed them. See Hickcox-Huffman v. US Air-
    ways, Inc., 
    855 F.3d 1057
    , 1066 (9th Cir. 2017) (“[Appel-
    lant] has sufficiently alleged that [appellee] breached an
    express provision of terms of transportation and thus need
    not rely on this interpretive doctrine [of good faith and fair
    dealing].”); Cruz v. FXDirectDealer, LLC, 
    720 F.3d 115
    , 125
    (2d Cir. 2013) (finding good faith and fair dealing redun-
    dant “when a breach of contract claim, based upon the
    same facts, is also pled”); CFS Int’l Cap. Corp. v. United
    States, 
    118 Fed. Cl. 694
    , 701 (2014) (same). Moreover, be-
    cause the application of the “shall consider” language in the
    government property clause already imposes a duty of good
    faith on the Navy, there is no justification for invoking an
    Case: 20-1084      Document: 55      Page: 22    Filed: 12/23/2020
    22                        BGT HOLDINGS LLC     v. UNITED STATES
    extra-contractual duty of good faith that would be redun-
    dant of the duty imposed by that clause.
    Although BGT relies on the doctrine of good faith and
    fair dealing as a separate ground for relief, that claim is
    based on the same set of facts as BGT’s other claims. The
    contract itself defines the parties’ respective rights in light
    of those facts. If the contract had expressly authorized the
    Navy to withdraw the GFE without consequence, the par-
    ties’ rights would be settled by the contract, and the duty
    of good faith and fair dealing would have no role to play in
    resolving this dispute. Because we interpret the contract
    to provide BGT a mechanism for obtaining compensation
    for the withdrawal of GFE, BGT’s rights are likewise gov-
    erned by the contract, and the doctrine of good faith and
    fair dealing cannot be employed to readjust those rights.
    We therefore affirm the dismissal of BGT’s claim of breach
    of good faith and fair dealing.
    III
    In sum, we vacate the Claims Court’s dismissal of
    BGT’s claims of constructive change through ratification,
    official change through waiver, and breach for failure to
    provide an equitable adjustment, and we remand on those
    claims for further proceedings consistent with this opinion.
    We affirm the Claims Court’s dismissal of BGT’s claim of
    breach of the implied duty of good faith and fair dealing.
    No costs.
    AFFIRMED IN PART, VACATED IN PART, AND
    REMANDED