The Minesen Co. v. McHugh , 671 F.3d 1332 ( 2012 )


Menu:
  •   United States Court of Appeals
    for the Federal Circuit
    __________________________
    THE MINESEN COMPANY,
    Appellant,
    v.
    JOHN MCHUGH, SECRETARY OF THE ARMY,
    Appellee.
    __________________________
    2010-1453
    __________________________
    Appeal from the Armed Services Board of Contract
    Appeals in No. 56346, Administrative Judge Michael T.
    Paul.
    _____________________________
    Decided: March 2, 2012
    _____________________________
    SANDRA B. WICK MULVANY, McKenna Long & Aldridge
    LLP, of Denver, Colorado, argued for appellant. With her
    on the brief were THOMAS A. LEMMER and JOSEPH G.
    MARTINEZ,III.
    JAMES SWEET, Trial Attorney, Commercial Litigation
    Branch, Civil Division, United States Department of
    Justice, of Washington, DC, argued for appellee. With
    him on the brief were TONY WEST, Assistant Attorney
    General, JEANNE E. DAVIDSON, Director, and KIRK
    MANHARDT, Assistant Director. Of counsel on the brief
    MINESEN CO   v. ARMY                                     2
    were SCOTT N. FLESCH and ERICA BEARDSLEY, Trial
    Attorneys, United States Army Litigation Center, Con-
    tract Appeals Division, of Arlington, Virginia.
    __________________________
    Before BRYSON, O’MALLEY, and REYNA, Circuit Judges.
    Opinion for the court filed by Circuit Judge REYNA.
    Dissenting opinion filed by Circuit Judge BRYSON.
    REYNA, Circuit Judge.
    The Minesen Company (“Minesen”) appeals the final
    decision of the Armed Services Board of Contract Appeals
    (“ASBCA” or “Board”) which granted the motion to dis-
    miss of the United States Army’s Morale, Welfare, and
    Recreation Fund (“the Fund”). Minesen has been under
    contract with the Fund since 1993 to build and operate a
    hotel facility at a military base on Oahu Island, Hawaii.
    With eighteen years remaining on the agreement, the
    ASBCA determined that the Fund breached the core of
    the contract and the parties entered the quantum phase
    of the dispute. While in the quantum phase, Minesen
    filed a separate complaint alleging that the Fund had
    done nothing to cure its ongoing breach. The ASBCA
    dismissed Minesen’s second complaint as duplicative of
    the first breach of contract action. Minesen appeals the
    ASBCA dismissal of its second complaint. Because we
    find that Minesen voluntarily waived its right to appeal to
    this court under its negotiated contract with the Fund, we
    dismiss.
    I. BACKGROUND
    Minesen, a small business from Denver, Colorado,
    was created for the purpose of acquiring and fulfilling
    government contracts. In January of 1993, after several
    years of negotiation, Minesen and the Fund entered into
    3                                       MINESEN CO   v. ARMY
    Contract No. NAFBA3-93-C-0001 (“the Contract”) to
    create accommodations for travelling military personnel.
    The Contract provided that Minesen would construct and
    operate, for a term of thirty-two years, a “transient lodg-
    ing facility” at Schofield Barracks in central Oahu. Joint
    Appendix (“J.A.”) 272. Schofield Barracks is an 18,000
    acre site twenty-three miles northwest of Honolulu, and is
    the largest Army installation in Hawaii. The Minesen
    lodging facility, to be built on four acres leased from the
    government, became known as the Inn at Schofield Bar-
    racks (“the Inn”). The Inn was to feature 184 rooms with
    kitchenettes, as well as other hotel amenities such as a
    vending area, guest laundry, playground, convenience
    store, and deli. Id. On a secure installation, the Inn
    would offer lodging only to eligible active and temporary
    military personnel, their families, and qualifying veter-
    ans. Under the Contract, Minesen’s lease and operation
    of the Inn terminates in 2026. Id.
    In addition to revenue generated operating the facil-
    ity, Minesen’s consideration for the bargain was that the
    Inn was officially deemed “government quarters” under
    the Joint Federal Travel Regulation (“JFTR”). Id. at 274.
    This designation was significant because it required
    travelling military personnel to patronize the Inn or else
    forfeit reimbursement for lodging costs. The Contract
    stated:
    The completed [Inn] will fall within the current
    Joint Federal Travel Regulation definition of gov-
    ernment quarters. . . . Travelers receiving gov-
    ernment per diem payment, in order not to forfeit
    their per diem entitlement, will be required to pa-
    tronize the [Inn] on a mandatory basis as long as
    confirmed reservation priorities are in accordance
    with those provided at Section III, Operation Re-
    quirements.
    MINESEN CO   v. ARMY                                       4
    Id. The Contract did not require the Fund to deliver any
    specific level of occupancy to the Inn.
    The Contract indicated on its face that “NO FUNDS
    OF THE UNITED STATES GOVERNMENT WILL BE
    PAID OR BE DUE TO THE CONTRACTOR BY VIRTUE
    OF THIS CONTRACT.” Id. at 271 (emphasis original).
    In the definition section, the Contract further specified
    that: “The Fund is . . . a nonappropriated fund instrumen-
    tality (NAFI) of the United States . . . . The Government
    is not a party to this contract, and no funds appropriated
    by Congress are in any way obligated or can be obligated
    by virtue of any provision of this contract.” Id. at 273.
    Significant for purposes of this appeal are the Con-
    tract’s express provisions regarding dispute resolution. In
    the “Disputes Clause” at § II(6), the Contract stated:
    a. This contract is not subject to the Contract
    Disputes Act of 1978 (41 U.S.C. 601-613).
    ***
    c. All disputes arising under or relating to this
    contract shall be resolved under this clause.
    ***
    g. The Contracting Officer’s decision shall be fi-
    nal unless the Contractor appeals as provided in
    paragraph h. of this clause.
    h. The Contracting Officer’s final decision may be
    appealed by submitting a written appeal to the
    Armed Services Board of Contract Appeals within
    90 days of receipt of the Contracting Officer’s final
    decision. Decisions of the Armed Services Board
    of Contract Appeals are final and are not subject
    to further appeal.
    5                                       MINESEN CO   v. ARMY
    J.A. 276-78 (emphasis original). On February 1, 1993, the
    parties executed Lease No. DACA84-1-91-14, which
    became an attachment to the Contract. After the parties
    finalized the Contract in early 1993, the Inn was con-
    structed and opened for business by June 1994.
    In 1997 and 1998, the JFTR, the travel regulation in-
    centivizing military personnel to patronize the Inn, was
    amended. As a result of the amendments, the Depart-
    ment of Defense began reimbursing for any lodging costs
    up to the amount charged at government quarters,
    whether or not the traveler actually stayed at government
    quarters such as the Inn.
    On June 7, 1999, Minesen filed a certified claim with
    the Contracting Officer (“CO”) in which it alleged that the
    JFTR amendments eliminating the mandatory per diem
    forfeiture breached the Contract and negatively impacted
    occupancy rates. Minesen sought (1) $2,541,670.14 in lost
    revenues through May of 1999, and (2) future perform-
    ance, or alternatively, immediate termination of the
    Contract with a payment of $25,506,325.00.
    The CO denied the claim. On February 18, 2000,
    Minesen submitted further claims to the CO, seeking,
    inter alia, anticipatory profits for breach of contract.
    These claims were also denied by the CO. Minesen timely
    appealed both claims to the ASBCA, a right guaranteed in
    the Contract.
    On November 20, 2006, after a five-week merits hear-
    ing, the ASBCA issued its decision. Minesen Co., ASBCA
    Nos. 52488, 52811, 
    07-1 BCA ¶ 33,456
     (the “2006 Deci-
    sion”). The ASBCA rejected Minesen’s argument that the
    Fund had repudiated the Contract by acquiescing to the
    changes in the JFTR. The administrative judge (“AJ”)
    found no outright repudiation of the Contract because the
    Fund never stated that it refused to perform. But the AJ
    MINESEN CO   v. ARMY                                        6
    also found that the Contract provision requiring travelers
    receiving the per diem reimbursement to patronize the
    Inn
    constituted the core of Minesen’s benefit of the
    bargain. The Inn was located on a secure military
    installation and was not open to the general pub-
    lic. In order to capture a market for its services,
    Minesen had to rely on an incentive to encourage
    official travellers [sic] to stay at the Inn. This de-
    vice was the mandatory forfeiture provision of
    Clause 7. In acquiescing to the 1997 and 1998
    changes in the JFTR which removed this manda-
    tory forfeiture provision, the Fund affected [sic] a
    basic alteration in the parties’ contractual rela-
    tionship.
    
    Id. at 123-24
    . The ASBCA concluded that the Fund
    should have fashioned a remedy to the JFTR amend-
    ments, ranging anywhere from a new reimbursement
    scheme to a complete termination of the Contract for
    convenience. “It failed to do so,” the ASBCA held, “and,
    thus, breached the contract, entitling Minesen to recover
    damages.” 
    Id. at 124
    .
    The ASBCA remanded the case to the CO for a de-
    termination of damages. Minesen claimed entitlement to
    past lost profits; interest; and future lost profits. Mine-
    sen’s statement of costs calculated “anticipatory profits
    from January 1, 2008 through the end of Minesen’s con-
    tract equal [to] $34,024,454.” J.A. 314. The Fund identi-
    fied various documents it claimed were necessary to verify
    damages, particularly those showing what Minesen would
    have earned from soldiers who declined to stay at the Inn
    but who did not forfeit the lodging reimbursement.
    Minesen did not promptly provide, among other things, its
    audited financial statements for FY 1994 through FY
    7                                       MINESEN CO   v. ARMY
    1996, preventing the Fund from comparing the Inn’s
    profitability before and after breach.
    In early 2008, barely a year into the quantum phase,
    Minesen filed a new complaint (the “2008 Claim”) alleging
    that, subsequent to the 2006 Decision, the Fund had
    failed to cure its ongoing breach. Minesen asserted that
    failure to cure over the intervening fifteen months consti-
    tuted an independent ground of material breach as of
    December 31, 2007, given that eighteen years were left on
    the Contract.
    The CO denied the 2008 Claim, stating: “[T]here is no
    new dispute. This claim duplicates claims which you
    previously filed . . . and to which the Board, as described
    above, has already rendered a decision on the merits.” 
    Id. at 150
    . The CO noted that the earlier action “is now in
    the quantum phase in which the parties are working to
    effect settlement of the dispute.” 
    Id.
     Minesen again
    appealed to the ASBCA.
    On July 7, 2008, Minesen moved for partial summary
    judgment, alleging that the Fund had done nothing to
    cure its continuing breach despite having been found
    liable in 2006. The Fund countered with a motion to
    dismiss, arguing that the 2006 Decision did not require
    anything more than what it was presently doing—
    cooperating in the quantum phase on remand. According
    to the Fund, no new claim was warranted because it “has
    regularly kept Minesen informed of the status of its
    efforts to calculate damages, and thus, has provided
    adequate assurances of a remedy.” Minesen Co., 
    ASBCA No. 56346
    , Slip Op. at 5 (July 16, 2010).
    On July 16, 2010, the ASBCA denied Minesen’s mo-
    tion for partial summary judgment and granted the
    Fund’s motion to dismiss. The ASBCA found genuine
    issues of material fact precluding summary judgment for
    MINESEN CO   v. ARMY                                        8
    Minesen, including evidence that throughout the quan-
    tum phase the Fund actively pursued discovery, con-
    ducted an audit, and responded to requests. The ASBCA
    also held that the 2008 Claim was merely duplicative, and
    not a new cause of action:
    We also agree with the Fund that Minesen’s “new”
    claim in 
    ASBCA No. 56346
     is duplicative. The
    factual premise of this claim is in dispute, as is its
    legal conclusion that it has identified “a new, in-
    dependent claim for material breach.” As the
    Fund states in its brief, “the only ‘new’ facts the
    Appellant cites are those related to the amount of
    time the parties are taking to resolve the contro-
    versy in ASBCA Nos. 55996 and 55997.” 
    ASBCA No. 56346
    , thus, is not a new cause of action, is
    duplicative, and must be dismissed.
    
    Id. at 7
    . Pursuant to the ASBCA final determination
    dismissing the 2008 Claim, Minesen appealed to this
    court.
    II. DISCUSSION
    Minesen argues on appeal that the ASBCA dismissal
    of the 2008 Claim was improper because it constitutes a
    new and distinct claim over that decided in the 2006
    Decision. The Fund responds that this court should not
    even reach the merits of whether the new claim is dupli-
    cative because at least two threshold defects estop Mine-
    sen’s appeal before this court.
    First, according to the Fund, the decision of the
    ASBCA was not rendered under the Contract Disputes
    Act (“CDA”), 
    41 U.S.C. § 7101
     et seq., such that the Fed-
    eral Circuit lacks statutory jurisdiction over this case.
    The Fund argues that the CDA does not apply to the
    Contract because the Fund is a nonappropriated fund
    9                                       MINESEN CO   v. ARMY
    instrumentality (“NAFI”). Second, the Fund argues that
    Minesen waived any right to appeal to the Federal Circuit
    pursuant to the disputes clause of the Contract, which
    states that ASBCA decisions are final. The Fund main-
    tains that this is a valid and enforceable provision that
    expressly precludes appeal to this court by consent of the
    parties.
    A. Statutory Jurisdiction
    Under 
    28 U.S.C. § 1295
    (a)(10), this court has jurisdic-
    tion to hear appeals from an ASBCA final decision. The
    Fund argues that this court lacks jurisdiction to consider
    this appeal because it is a non-enumerated NAFI, as
    agreed in the Contract. NAFIs are “federal government
    entities whose monies do not come from congressional
    appropriation but rather primarily from [their] own
    activities, services, and product sales.” El-Sheikh v.
    United States, 
    177 F.3d 1321
    , 1322 (Fed. Cir. 1999) (in-
    ternal quotation marks omitted). Under the “NAFI
    doctrine,” entities that have NAFI status are not typically
    subject to suit on contract claims because any damages
    awarded against them would be paid using appropriated
    funds. See Furash & Co. v. United States, 
    252 F.3d 1336
    ,
    1338-43 (Fed. Cir. 2001). This court has clearly held that
    it lacks jurisdiction under the CDA to hear contract
    claims against NAFIs. 
    Id. at 1342-44
     (holding the NAFI
    doctrine applicable to CDA cases).
    Minesen counters that our recent holding in Slattery
    v. United States, 
    635 F.3d 1298
     (Fed. Cir. 2011) (en banc),
    changes this rule. The court in Slattery indeed concluded
    that the Tucker Act provides jurisdiction over claims
    against NAFIs. 
    Id. at 1301
     (“Tucker Act jurisdiction does
    not depend on and is not limited by whether the govern-
    ment entity receives or draws upon appropriated funds.”).
    While Slattery did not directly reach the CDA in its
    MINESEN CO   v. ARMY                                      10
    holding, Minesen asserts that the jurisdictional analysis
    would be identical. Thus, Minesen invites this court to
    view the recent rescission of the NAFI doctrine as applied
    to the Tucker Act as necessarily eliminating the NAFI
    doctrine’s applicability to the CDA also.
    We decline to decide this issue here. While we are
    generally obligated to resolve jurisdictional challenges
    first, Supreme Court precedent only requires federal
    courts to answer questions concerning their Article III
    jurisdiction—not necessarily their statutory jurisdiction—
    before reaching other dispositive issues. See Steel Co. v.
    Citizens for a Better Environment, 
    523 U.S. 83
    , 95-97, 101
    (1998); Restoration Pres. Masonry, Inc. v. Grove Eur. Ltd.,
    
    325 F.3d 54
    , 59 (1st Cir. 2003) (“[W]hile Article III juris-
    dictional disputes are subject to Steel Co., statutory
    jurisdictional disputes are not.”). Here, the jurisdictional
    issues are strictly statutory, and not constitutional. Even
    without this exception for statutory jurisdictional dis-
    putes, Justice Breyer, concurring in Steel Co., noted with
    approval that “[t]his Court has previously made clear that
    courts may ‘reserve difficult questions of . . . jurisdiction
    when the case alternatively could be resolved on the
    merits in the favor of the same party.’” 
    523 U.S. at
    111
    (citing Norton v. Matthews, 
    427 U.S. 524
    , 532 (1976)); see
    also Bowers v. Nat’l Collegiate Athletic Ass’n, 
    346 F.3d 402
    , 415-16 (3d Cir. 2003); cf. United States v. Caruthers,
    
    458 F.3d 459
    , 472 n.6 (6th Cir. 2006).
    Because the question of whether claims against
    NAFIs can be made pursuant to the CDA is complex post-
    Slattery, and because the question has a statutory prove-
    nance, we will assume jurisdiction for present purposes
    and proceed directly to the substance of the appellate
    waiver argument.
    11                                       MINESEN CO   v. ARMY
    B. Appellate Waiver
    The parties agreed in the Contract’s “Dispute Clause”
    at § II(6)(h) that the ASBCA was the exclusive and final
    appellate review forum: “The Contracting Officer’s final
    decision may be appealed by submitting a written appeal
    to the Armed Services Board of Contract Appeals within
    90 days of receipt of the Contracting Officer’s final deci-
    sion. Decisions of the Armed Services Board of Contract
    Appeals are final and are not subject to further appeal.”
    J.A. 278. Minesen does not dispute the plain language
    interpretation of this contract provision, nor does it dis-
    pute that it voluntarily and knowingly agreed to the
    finality of ASBCA decisions. Minesen instead contends
    that it could not legally consent to waive its statutory
    right under 
    41 U.S.C. § 7107
    (a) to an appeal before the
    Federal Circuit. In sum, Minesen concedes that it con-
    tracted to curtail its right to review by this court, but now
    argues that its obligation is contrary to the CDA and
    public policy embodied therein.
    i. Waiving Federal Circuit Appeal Is Not Contrary
    to the CDA
    According to Minesen, its right to appear before the
    Federal Circuit is guaranteed by Congress, despite any
    contrary contract language to which it may have agreed.
    Minesen argues—without reference to any specific provi-
    sion of the CDA—that Congress did not intend that the
    right to appeal to this forum be waivable.
    In order to conclude that Congress intended for the
    CDA to include protection against waiving appeals from
    the ASBCA to this court, that intention must be discern-
    able from the text or the legislative history. See Mitsubi-
    shi Motors Corp. v. Soler Chrysler-Plymouth, Inc., 
    473 U.S. 614
    , 628 (1985) (“We must assume that if Congress
    intended the substantive protection afforded by a given
    MINESEN CO   v. ARMY                                     12
    statute to include protection against waiver of the right to
    a judicial forum, that intention will be deducible from text
    or legislative history.”); Brooklyn Sav. Bank v. O’Neil, 
    324 U.S. 697
    , 705 (1945) (“[T]he question of whether the
    statutory right may be waived depends upon the intention
    of Congress as manifested in the particular statute.”);
    McCall v. U.S. Postal Serv., 
    839 F.2d 664
    , 667 (Fed. Cir.
    1988) (holding that appellant did not show that his volun-
    tary waiver of a statutory right to appeal was contrary to
    congressional intent). Thus, the burden is on Minesen, as
    the party opposing enforcement of a contractual waiver, to
    show that Congress intended to preclude such waivers.
    
    Id.
    We find no such intention here. The plain words and
    meaning of the relevant provision, 
    41 U.S.C. § 7107
    (a)(1),
    do not proscribe a waiver of appeal rights through con-
    tract. The provision reads:
    Judicial review of agency board decisions
    (a)Review.
    (1) In general. The decision of an agency board
    is final, except that—
    (A) a contractor may appeal the decision to the
    United States Court of Appeals for the Federal
    Circuit within 120 days from the date the contrac-
    tor receives a copy of the decision; or
    (B) if an agency head determines that an ap-
    peal should be taken, the agency head, with the
    prior approval of the Attorney General, may
    transmit the decision to the United States Court
    of Appeals for the Federal Circuit for judicial re-
    view under section 1295 of title 28, within 120
    13                                      MINESEN CO   v. ARMY
    days from the date the agency receives a copy of
    the decision.
    
    Id.
     If Congress did not want this right altered by agree-
    ment, it would have said so; but this provision contains no
    express prohibition on appellate waivers beyond the
    ASBCA.
    Nor does anything in the CDA’s legislative history
    demonstrate that Congress did not intend for parties to be
    able to agree to the finality of ASBCA decisions. On the
    contrary, Congress recognized first among the express
    purposes of the CDA “induc[ing] resolution of more con-
    tract disputes by negotiation prior to litigation,” S. Rep.
    No. 95-1118, at 1 (1978), and “encourag[ing] the informal,
    quick resolution of disputes before they can develop into
    expensive and time-consuming administrative tangles or
    litigation,” 124 Cong. Rec. 31,645 (1978).
    Recognizing these legislative goals, we do not find
    that Congress wanted to prevent parties from properly
    contracting to simplify dispute resolution. Agreeing to the
    finality of ASBCA decisions accomplishes precisely what
    Congress intended, at least in part, in passing the CDA.
    See Pathman Constr. Co. v. United States, 
    817 F.2d 1573
    ,
    1578 (Fed. Cir. 1987) (“A major purpose of the [Contract]
    Disputes Act was to induce resolution of contract disputes
    with the government by negotiation rather than litiga-
    tion.”) (internal quotation marks omitted); cf. 
    41 U.S.C. § 7103
    (h)(1) (permitting parties to fashion “other mutu-
    ally agreeable procedures” for resolving claims). Having
    agreed to simplify disputes by pursuing resolution under
    the terms of the Contract, Minesen should be held to its
    bargain as it does not conflict with—indeed it advances—
    statutory purposes. See Mitsubishi Motors, 
    473 U.S. at 628
     (“Having made the bargain, . . . the party should be
    held to it unless Congress itself has evinced an intention
    MINESEN CO   v. ARMY                                    14
    to preclude a waiver of judicial remedies for the statutory
    rights at issue.”).
    ii. Waiving Federal Circuit Appeal Is Not Contrary
    to the CDA’s Purpose
    Minesen argues as a matter of public policy that al-
    lowing a party to waive Federal Circuit appeal skews the
    balance between the government and contractors during
    contract negotiations. Minesen argues that its promise to
    waive appeal rights to the Federal Circuit should be held
    unenforceable because of the government’s superior
    bargaining power.
    a. Extensive Case Law Permits Voluntary
    Waivers
    The Supreme Court and this court have long held that
    the government, if not otherwise prohibited by statute,
    can enforce a voluntary contractual waiver with the same
    force as a private party, notwithstanding superior bar-
    gaining power. Town of Newton v. Rumery, 
    480 U.S. 386
    ,
    392-94 (1987); see also Lynch v. United States, 
    292 U.S. 571
    , 579 (1934) (“When the United States enters into
    contract relations, its rights and duties therein are gov-
    erned generally by the law applicable to contracts be-
    tween private individuals.”); Do-Well Mach. Shop, Inc. v.
    United States, 
    870 F.2d 637
    , 641 (Fed. Cir. 1989) (“Just as
    the common law limits the government’s power to con-
    tract in the same way it limits a private person, it also
    protects the government’s power to contract in the same
    way it protects a private person.”) (emphasis original).
    In Rumery, the Supreme Court addressed an argu-
    ment analogous to Minesen’s and held that the mere
    possibility of intimidation in contracting with the gov-
    ernment cannot justify invalidating all such agreements.
    
    480 U.S. at 392-94
    . The Court explained that parties are
    15                                      MINESEN CO   v. ARMY
    often forced to make difficult choices which effectively
    forego statutory or constitutional rights. 
    Id. at 393
    .
    Parties can be held to such obligations if contracted
    knowingly and voluntarily. 
    Id.
    In McCall, this court held that a postal employee
    could enter into an agreement with the government
    waiving his statutorily conferred right to appeal an
    agency disciplinary action. 
    839 F.2d at 665
    . The agree-
    ment at issue concluded by stating that, “the removal will
    be . . . with no rights of appeal to any forum . . . .” 
    Id.
    When the removal action was later appealed despite the
    express agreement, the AJ dismissed, finding McCall’s
    waiver of appellate rights valid and enforceable. 
    Id. at 666
    . This court affirmed, directly addressing McCall’s
    contention that such waivers are unenforceable as against
    public policy due to unequal bargaining power. 
    Id.
     at 666-
    67. The court explained:
    The waiver agreement in this case, like that in
    Rumery, reflects a rational judgment on the part
    of McCall. . . . Because his choice was knowing
    and voluntary, the public interest against invol-
    untary waivers of rights does not weigh against
    the enforcement of this agreement and it is not
    void as a matter of public policy.
    
    Id. at 667
    . The McCall court added that the possibility of
    coercion in a civil context was less serious than what was
    acceptable in Rumery, where criminal sanctions loomed.
    
    Id.
    This court has further held that contractors can waive
    even constitutional rights in litigation with the govern-
    ment. Seaboard Lumber Co. v. United States, 
    903 F.2d 1560
     (Fed. Cir. 1990). The Fund argues based on Sea-
    board that if contractors can waive a constitutional right
    to a jury by contracting into a particular forum, they can
    MINESEN CO   v. ARMY                                      16
    also waive a statutory right to appeal by contracting out
    of the Federal Circuit. In Seaboard, a private party had
    accepted a government contract provision providing for
    dispute resolution in a forum where there was no entitle-
    ment to a jury. When the provision was contested, this
    court found that, “[t]he Supreme Court has long recog-
    nized that a private litigant may waive its right to a jury
    and to an Article III court in civil cases,” either expressly
    or impliedly. 
    Id. at 1563
    . The Federal Circuit rearticu-
    lated the voluntary nature of the government-contractor
    relationship in negotiation: “‘Respondents were not com-
    pelled or coerced into making the contract [with the
    government]. It was a voluntary undertaking on their
    part. As competent parties they have contracted for the
    settlement of disputes in an arbitral manner.’” 
    Id. at 1565
     (quoting Wunderlich v. United States, 
    342 U.S. 98
    ,
    100 (1951)).
    In this case, the record and pleadings indicate that
    Minesen freely agreed to the finality of ASBCA decisions.
    While a promise can be unenforceable if the interest in its
    enforcement is outweighed by public policy, Rumery, 
    480 U.S. at 392
    , public policy is not per se offended when a
    sophisticated contractor knowingly and voluntarily agrees
    to an appellate waiver provision denying Federal Circuit
    review.
    b. Burnside-Ott Does Not Apply in this Case
    This court in Burnside-Ott Aviation Training Center
    v. Dalton, 
    107 F.3d 854
     (Fed. Cir. 1997), analyzed public
    policy concerns associated with waiving review of contract
    disputes in a narrow context. Burnside-Ott held that
    parties may not waive review of CO decisions to the
    ASBCA, but it did not address waiving appeals from the
    ASBCA to the Federal Circuit.
    17                                        MINESEN CO   v. ARMY
    The court in Burnside-Ott reminded generally that
    “parties to a contract may voluntarily waive certain
    rights, including the right to receive an impartial and
    independent federal adjudication, otherwise available to
    the parties under the law.” 
    Id. at 858
    . However, the
    court determined that under the CDA at least one impar-
    tial review of CO decisions was necessitated by the stat-
    ute’s goal of “equaliz[ing] the bargaining power of the
    parties when a dispute exists,” a requirement satisfied by
    review in the ASBCA. 
    Id.
     (citing S. Rep. No. 95-1118, at
    1). Whereas the ASBCA is a neutral tribunal and not a
    representative of the agency, 1 the CO is unquestionably
    biased, permitting the government to “commandeer the
    final decision on all disputes of fact arising under the
    contract” if its decisions remain unreviewable. 
    Id. at 858
    .
    The court explained:
    In government contract disputes, unlike contract
    disputes between two private parties, the initial
    1   The ASBCA is described by Congress as a
    “quasi-judicial” body whose
    members serve as administrative judges in an ad-
    versary-type proceeding, make findings of fact,
    and interpret the law. Their decisions set the
    bulk of legal precedents in Government contract
    law, and often involve substantial sums of money.
    In performing this function they do not act as a
    representative of the agency, since the agency is
    contesting the contractor’s entitlement to relief.
    S. Rep. No. 95-118, at 26; see also Boeing Petro. Servs.,
    Inc. v. Watkins, 
    935 F.2d 1260
    , 1261 (Fed. Cir. 1991)
    (under the CDA, the review boards are established as
    independent, quasi-judicial forums, entities “quite distinct
    from” their contracting agencies). Indeed, “[t]he contrac-
    tor should feel that he is able to obtain his ‘day in court’ at
    the agency boards and at the same time have saved time
    and money through the agency board process.” S. Rep.
    No. 95-118, at 25.
    MINESEN CO   v. ARMY                                      18
    determination in each dispute is made by one of
    the parties, i.e., the CO. Congress commanded
    that the CO’s decision on any matter cannot be
    denied Board review. . . . Permitting parties to
    contract away Board review entirely would sub-
    vert this purpose and return contractors to the po-
    sition they occupied before the passage of the
    CDA.
    Id. at 858-59.
    Minesen is not in the same situation described in
    Burnside-Ott, wherein the contractor was stuck with the
    determination of the CO, deemed “one of the parties” to
    the case. Id. at 858. This court confirmed that Congress
    “provide[d] a fair and balanced system” under the CDA to
    review claims related to government contracts, id., includ-
    ing unwaivable contractor access to the ASBCA for a de
    novo review of CO determinations, recourse sufficient to
    allay policy concerns inherent in the CDA. There is no
    suggestion in Burnside-Ott law that appeal to this court is
    additionally required to equalize bargaining power. Id.;
    see also Seaboard, 903 F.3d at 1565.
    An unwaivable right to ASBCA review as distin-
    guished from optional review before the Federal Circuit is
    supported by the CDA’s legislative history. Congress
    intended under the CDA that contractors benefit from a
    “flexible system that provides alternative forums for
    resolution of particular kinds of disputes,” either in the
    federal courts or before agency boards. S. Rep. No. 95-
    118, at 13. Thus, while Congress ensured immutable
    access to the United States Court of Federal Claims
    (“Court of Federal Claims”) under § 7104(b) because
    “[c]ontractors should not be denied a full judicial hearing
    on a claim they deem important enough to warrant the
    maximum due process available under our system,” for
    19                                      MINESEN CO   v. ARMY
    contractors desiring a simplified process Congress pro-
    vided another option under the CDA—agency boards, “the
    least expensive, most expeditious forum available.” Id. at
    12. Congress explained that
    The aim of any remedial system is to give the par-
    ties what is due them as determined by a thor-
    ough, impartial, speedy, and economical
    adjudication. . . . The claimant should be able to
    choose a forum according to the needs of his par-
    ticular case; that is, one where the degree of due
    process desired can be balanced by the time and
    expense considered appropriate for the case.
    Id. at 13. The CDA thus enlarged the contractor’s options
    for dispute resolution: “Congress mandated that the
    government had to include in its contracts the broader
    review provisions set out in the CDA, that is, the dual
    avenues of review either by appeal to a Board of Contract
    Appeals or by a direct access suit in the Court of Claims.”2
    Seaboard, 903 F.3d at 1565.
    The dissent contends that exercising the option for
    flexible, expeditious review provided by the CDA creates
    an “anomaly.” See Dissent Op. at 13. Yet neither the
    CDA nor its legislative history requires that the dual
    avenues necessarily be coterminous, such that both end
    by appeals in this court. Agency boards are designed
    instead for contractors who find that their case does not
    warrant “the maximum due process available under our
    2  The Federal Courts Improvement Act of 1982, Pub
    L. No. 97-164, § 105(a), 
    96 Stat. 25
     (amending 
    28 U.S.C. § 171
    (a)), established the United States Claims Court.
    The United States Claims Court inherited the jurisdiction
    of its predecessor, the United States Court of Claims.
    Congress renamed it the United States Court of Federal
    Claims by the Federal Courts Administration Act of 1992,
    Pub. L. No. 102-572, § 902, 106 Stat. at 4516.
    MINESEN CO   v. ARMY                                      20
    system,” and instead opt for “a swift, inexpensive method
    of resolving contract disputes.” S. Rep. No. 95-118, at 12.
    Allowing voluntary waiver of § 7107(a) appeals from the
    ASBCA implements Congress’s intent that the dual
    avenues serve different ends.
    Minesen could have, as the dissent notes, arrived be-
    fore this court through the Court of Federal Claims pur-
    suant to § 7104(b) (a provision actually containing the
    “notwithstanding any contract provision” guarantee), but
    Minesen chose instead to accept ASBCA decisions as
    final, and filed in that forum when a dispute arose in
    2008. Minesen freely chose the path of streamlined
    adjudication and tailored its dispute resolution mecha-
    nisms with the Fund accordingly. We therefore decline
    Minesen’s invitation to extend Burnside-Ott to this case.
    iii. The CDA’s Standard of Review Provision Is
    Irrelevant to Contractual Waiver
    The dissent raises a novel theory that a standard of
    review provision found at 
    41 U.S.C. § 7107
    (b) reveals
    Congress’s intent that appeals from the ASBCA under
    § 7107(a) be unwaivable. Dissent Op. at 7. We disagree.
    The theory that § 7107(b) renders Federal Circuit ap-
    peal unwaivable was never briefed by Minesen. Minesen
    did not argue that specific language in the CDA speaks to
    the appellate waiver issue, and the Fund did not have a
    proper opportunity to present arguments interpreting
    § 7107(b). It is well-established that federal appellate
    courts do not consider arguments not timely raised by the
    parties. Singleton v. Wulff, 
    428 U.S. 106
    , 120 (1976).
    This rule permits litigants “the opportunity to offer all the
    evidence they believe relevant to the issues” and prevents
    them from being “surprised on appeal by final decision
    there of issues upon which they have had no opportunity
    21                                      MINESEN CO   v. ARMY
    to introduce evidence.” 
    Id.
     (quoting Hormel v. Helvering,
    
    312 U.S. 552
    , 556 (1941)).
    In any event, the dissent’s attempt to infer Congress’s
    intent by shoehorning § 7107(b)’s “notwithstanding any
    contract provision” language into § 7107(a) is not convinc-
    ing. By its terms, § 7107(b) merely defines this court’s
    standard of review in CDA cases. Thus, while parties can
    waive Federal Circuit appeal available under § 7107(a), if
    they elect not to waive § 7107(b) merely sets out the
    review standard that must be followed. We refuse the
    dissent’s suggestion to rewrite the statute by applying
    language from § 7107(b) that Congress declined to provide
    directly in § 7107(a). See supra § II.B.i. Congress was
    aware of how to make CDA provisions unwaivable when it
    wanted. Do-Well, 
    870 F.2d at 641
     (finding of the CDA
    that, “[w]here Congress did not want the Act altered by
    parties’ agreements, it said so”). Congressional silence in
    this case should be construed as permitting appellate
    rights beyond the ASBCA to be governed by the parties’
    agreement. See 
    id.
    Recognizing the lack of express language in the rele-
    vant provision, the dissent relies on the spirit of the
    repealed Wunderlich Act, Pub. L. No. 83-356, 
    68 Stat. 81
    (1954), to justify a strained interpretation of the CDA.
    Dissent Op. at 7-11. The Wunderlich Act of 1954 was
    passed to legislatively overturn the ruling in United
    States v. Wunderlich, 
    342 U.S. 98
     (1951). See H.R. Rep.
    No. 83-1380 (1954). In Wunderlich, a government con-
    tract clause provided that factual disputes would be
    decided by the CO, with right of appeal only to the Secre-
    tary of the Interior. 
    342 U.S. at 99
    . The effect of Wunder-
    lich was to keep out of the Court of Claims all cases
    except those claiming fraud. 
    Id.
     Congress, to prevent the
    agency representative from “act[ing] as a judge in his own
    case,” 
    id. at 103
     (Jackson, J., dissenting), “as a matter of
    MINESEN CO   v. ARMY                                     22
    grace, provided for narrow judicial review of a contracting
    officer’s decision” in the Wunderlich Act, Seaboard, 
    903 F.2d at 1565
     (emphasis added). The legislative fix en-
    sured that contractors would always have a right to
    review CO determinations before the Court of Claims. 
    Id.
    In passing the CDA, Congress already renewed the
    guarantee of direct access from the partial CO to the
    Court of Federal Claims, “notwithstanding any contract
    provision . . . to the contrary,” 
    41 U.S.C. § 7104
    (b). The
    Wunderlich Act’s “narrow” focus on preventing CO deci-
    sions from being unreviewable does not inform our under-
    standing of congressional intent regarding appeals from
    the impartial ASBCA to this court.
    III. CONCLUSION
    The disputed contract provision states that,
    “[d]ecisions of the Armed Services Board of Contract
    Appeals are final and are not subject to further appeal.”
    J.A. 278. We find that Minesen knowingly and voluntar-
    ily waived its right to appeal to this court, and we respect
    the clear intent of the parties agreeing to the finality of
    the ASBCA result. We dismiss.
    DISMISSED
    COSTS
    No costs.
    United States Court of Appeals
    for the Federal Circuit
    __________________________
    THE MINESEN COMPANY,
    Appellant,
    v.
    JOHN MCHUGH, SECRETARY OF THE ARMY,
    Appellee.
    __________________________
    2010-1453
    __________________________
    Appeal from the Armed Services Board of Contract
    Appeals in No. 56346, Administrative Judge Michael T.
    Paul.
    __________________________
    BRYSON, Circuit Judge, dissenting.
    I do not agree that the disputes clause of Minesen’s
    contract with the Army Morale Welfare and Recreation
    Fund (“the Fund”) constituted an enforceable waiver of
    Minesen’s right to appeal to this court, requiring the
    dismissal of this appeal. I would therefore hold that this
    court has jurisdiction over Minesen’s appeal. On the
    merits, however, I would affirm the Board’s dismissal of
    Minesen’s claims as duplicative of claims brought in the
    company’s ongoing action for breach of contract.
    MINESEN CO   v. ARMY                                      2
    I
    The majority dismisses Minesen’s claim based on a
    contractual provision that purports to bar any judicial
    review of a decision of the Armed Services Board of Con-
    tract Appeals. I consider that provision to be unenforce-
    able, and I therefore conclude that the Contract Disputes
    Act (“CDA”) authorizes Minesen to take this appeal. In
    order to reach that issue, however, it is necessary to
    dispose of several preliminary arguments made by the
    government, all of which I find to be legally insupport-
    able. The majority does not address those issues because
    it concludes that the waiver argument by itself disposes of
    this appeal.
    A
    The government first argues that Minesen’s claim is
    not covered by the CDA because the Fund is a non-
    appropriated fund instrumentality (“NAFI”). We held in
    Pacrim Pizza Co. v. Pirie, 
    304 F.3d 1291
     (Fed. Cir. 2002),
    that contracts with NAFIs other than those specifically
    identified in the Tucker Act, 
    28 U.S.C. § 1491
    , fall outside
    the scope of the CDA. 
    304 F.3d at 1293
    . Since the CDA
    offers the only route of appeal to this court from decisions
    of the Board, see Zinger Constr. Co. v. United States, 
    753 F.2d 1053
    , 1054 (Fed. Cir. 1985), the government argues
    that Pacrim Pizza forecloses our review of Minesen’s
    claim.
    The government’s argument runs afoul of this court’s
    recent en banc decision in Slattery v. United States, 
    635 F.3d 1298
     (Fed. Cir. 2011). We held in Slattery that “the
    source of funding of an agency’s activities or for payment
    of its judgments is not a limitation on Tucker Act jurisdic-
    tion.” 
    Id. at 1320
    . Thus, contracts with NAFIs presump-
    3                                       MINESEN CO   v. ARMY
    tively fall within the Tucker Act’s waiver of sovereign
    immunity, and “exceptions require an unambiguous
    statement by Congress.” 
    Id. at 1320-21
    .
    Although Slattery did not address the NAFI doctrine
    in the context of the CDA, its holding applies equally to
    claims brought under that Act, because the reach of the
    CDA is tied to the waiver of sovereign immunity in the
    Tucker Act. The CDA is applicable to “any express or
    implied contract (including those of the nonappropriated
    fund activities described in [the Tucker Act]) made by an
    executive agency . . . .” 
    41 U.S.C. § 7102
    (a). We specifi-
    cally held in Slattery that the enumeration of certain
    NAFIs in the Tucker Act did not signal any intent on the
    part of Congress to retain sovereign immunity over con-
    tracts with other NAFIs. 
    635 F.3d at 1313-14
    . After
    Slattery, the CDA must be deemed to apply to “any ex-
    press or implied contract . . . made by an executive
    agency,” irrespective of the source of funds used to carry
    out the contract. The dissenting judges in Slattery con-
    tended that Congress reaffirmed the existence of the
    NAFI doctrine when it enacted the CDA, 
    id. at 1326-27
    (Gajarsa, J., dissenting), but a majority of this court was
    not persuaded by that argument. Our holdings in Pacrim
    Pizza and prior cases that were predicated on the NAFI
    doctrine are no longer good law in the wake of Slattery.
    Thus, Minesen may proceed under the CDA even if the
    Fund is considered a NAFI.
    B
    The government next argues that no appeal can be
    taken in this case because the Fund is not an “executive
    agency,” and the CDA applies only to contracts entered
    into by “executive agencies.” See 
    41 U.S.C. § 7102
    (a).
    That position is contrary to the text of the CDA, which
    MINESEN CO   v. ARMY                                     4
    provides that nonappropriated fund activities entered into
    by executive agencies are covered by the Act. As a fall-
    back position, the government relies on Pacrim Pizza to
    argue that the only NAFIs that qualify as “executive
    agencies” are those listed in the Tucker Act. As noted,
    however, Pacrim Pizza is no longer good law on that
    point. Therefore, the Fund must be considered an “execu-
    tive agency” for purposes of the CDA.
    C
    The government’s next argument is that Minesen’s
    contract is not covered by the CDA because the contract
    does not concern a “procurement.”       That argument is
    based on the government’s proposed definition of “pro-
    curement,” which is tied to the definition of the term
    “acquisition” found in the statutes governing the Office of
    Federal Procurement Policy. Those statutes define “ac-
    quisition” as a process that uses appropriated funds. 
    41 U.S.C. § 131
    . The government argues that because this
    court has defined “procurement” under the CDA as “all
    stages of the process of acquiring property or services,”
    Distributed Solutions, Inc. v. United States, 
    539 F.3d 1340
    , 1345-46 (Fed. Cir. 2008), the CDA does not cover
    government contracts that concern only nonappropriated
    funds.
    This court made clear in United States v. General
    Electric Corp., 
    727 F.2d 1567
     (Fed. Cir. 1984), that
    “[n]othing in the [CDA] limits its application to appropri-
    ated funds.” 
    727 F.2d at 1570
    ; see also Furash & Co. v.
    United States, 
    252 F.3d 1336
    , 1342 (Fed. Cir. 2001) (“the
    CDA contains no express provision limiting it to agencies
    supported by appropriated funds”). Furthermore, the
    government’s “procurement” argument is at odds with the
    CDA’s express coverage of contracts involving nonappro-
    5                                       MINESEN CO   v. ARMY
    priated fund activities. The definition of “acquisition”
    that the government relies on was added by the National
    Defense Authorization Act for Fiscal Year 2004, Pub. L.
    No. 108-136, § 1411, 
    117 Stat. 1392
    , 1663-64 (2003). The
    government has pointed to no evidence that the drafters
    of that unrelated statute intended for it to have the effect
    of narrowing the scope of the CDA. See United States v.
    Fausto, 
    484 U.S. 439
    , 453 (1988) (“it can be strongly
    presumed that Congress will specifically address lan-
    guage on the statute books that it wishes to change”). In
    sum, the term “procurement” does not bar a government
    contractor from proceeding under the CDA simply be-
    cause the contracting agency does not use appropriated
    funds for the contract.
    D
    The government’s principal argument on appeal is
    that the “disputes clause” of the contract between Mine-
    sen and the Fund constituted an enforceable waiver of
    Minesen’s right to appeal to this court. The majority
    agrees with the government on that issue, but I do not.
    The clause at issue was specifically designed for in-
    corporation into NAFI contracts at a time when the NAFI
    doctrine was in effect. See Army Regulation 215-4, ch. 2-
    14(b) (1987); DA Form 4075-R (1987) (clause I-25). The
    Board’s charter grants it the authority to hear claims
    arising under the CDA, 48 C.F.R. ch. 2, app. A, but that
    route of review was of no use to contractors who entered
    into agreements with NAFIs, because of the NAFI doc-
    trine. Even absent the disputes clause, Minesen’s appeal
    could not have been heard by this court before our deci-
    sion in Slattery, because the Tucker Act had not been
    interpreted to waive sovereign immunity for causes of
    action arising from contracts with non-enumerated
    MINESEN CO   v. ARMY                                        6
    NAFIs. Moreover, Minesen could not have proceeded
    under the CDA because we had tied the scope of that Act
    to the NAFI doctrine, see Pacrim Pizza, 
    304 F.3d at 1293
    ,
    and Board rulings that were not made pursuant to the
    CDA could not be appealed to this court, Zinger Constr.,
    
    753 F.2d at 1054
    . Thus, at the time the contract was
    signed, the disputes clause set forth Minesen’s only right
    to review of decisions of the contracting officer. And the
    disputes clause allowed the Board (but not this court) to
    hear appeals under a provision of its charter that permits
    it to review claims relating to contracts entered into by
    any authorized representative of the Army, irrespective of
    the source of funds used to carry out the contract. 48
    C.F.R. ch. 2, app. A; see, e.g., In re Atlantis Constr. Corp.,
    
    ASBCA No. 44044
    , 
    96-1 BCA ¶ 28,045
     (assuming jurisdic-
    tion over appeal based not on the CDA but on the disputes
    clause in a contract with a NAFI).
    In the aftermath of Slattery, the disputes clause is in
    tension with 
    41 U.S.C. § 7107
    (a)(1)(A), the provision of
    the CDA that permits this court to review decisions of the
    Boards of Contract Appeals. The majority concludes that
    the disputes clause controls based on the general princi-
    ple that a party can freely contract away its right to
    judicial review. That principle is not applicable, however,
    when a provision of a government contract conflicts with a
    federal statute. Am. Airlines, Inc. v. Austin, 
    75 F.3d 1535
    ,
    1538 (Fed. Cir. 1996); see generally The Bremen v. Zapata
    Off-Shore Co., 
    407 U.S. 1
    , 15 (1972) (contract’s choice-of-
    forum clause unenforceable “if enforcement would contra-
    vene a strong public policy of the forum in which the suit
    is brought, whether declared by statute or by judicial
    decision”); Restatement (Second) of Contracts § 178
    (1981). The majority rules that enforcing a contractual
    waiver of the right of appeal to this court is not contrary
    to public policy. The court’s ruling, however, ignores the
    7                                         MINESEN CO   v. ARMY
    fact that Congress has already made the determination
    that enforcing such a waiver is contrary to public policy.
    We are obligated to respect that determination. See
    Restatement (Second) of Contracts § 178 (“A promise or
    other term of an agreement is unenforceable on grounds
    of public policy if legislation provides that it is unenforce-
    able . . . .”).
    The CDA provides the exclusive remedy for all con-
    tract disputes that fall within its scope. Dalton v. Sher-
    wood Van Lines, Inc., 
    50 F.3d 1014
    , 1017 (Fed. Cir. 1995).
    It provides a right to judicial review of Board decisions, 
    41 U.S.C. § 7107
    (a)(1)(A), and it prescribes particular stan-
    dards of review that this court must adhere to
    “[n]otwithstanding any contract provision . . . to the
    contrary,” 
    id.
     § 7107(b). The disputes clause, which
    prohibits any such review, thus conflicts with the CDA.
    As a “contract provision to the contrary,” the disputes
    clause must yield to the CDA.
    While the provision of the CDA that grants the right
    of appeal to this court, 
    41 U.S.C. § 7107
    (a)(1)(A), does not
    contain language regarding conflicting contractual provi-
    sions, the standard of review provision, 
    id.
     § 7107(b),
    reveals the intent of Congress to permit review by this
    court of all government contract disputes brought under
    the CDA. 1 The language of that provision hews closely to
    1   Because Minesen did not discuss section 7107(b)
    in its brief, the majority deems it improper to consider
    section 7107(b) in analyzing whether appeals under
    section 7107(a) can be waived. The question whether the
    right to appeal under section 7107(a) can be waived was
    fully briefed by the parties, and Minesen argued that
    under applicable case law the CDA bars contractual
    waivers of that right. Reference to section 7107(b) helps
    show why that statutory argument is correct and why the
    case law on which Minesen relies should be applied here.
    MINESEN CO   v. ARMY                                      8
    the language of the Wunderlich Act, Pub. L. No. 83-356,
    
    68 Stat. 81
     (1954), which was specifically intended to
    prohibit the government from inserting jurisdiction-
    defeating provisions in government contracts.         The
    Wunderlich Act was repealed during the pendency of this
    appeal as part of the recodification of Title 41. Pub. L.
    No. 111-350, 
    124 Stat. 3677
    , 3859 (Jan. 4, 2011). The
    Wunderlich Act was intended to be “superseded by section
    10 of the Contract Disputes Act of 1978 (41 U.S.C. 609
    [recodified at 
    41 U.S.C. § 7107
    ]),” H.R. Rep. No. 111-42,
    at 9 (2009), 2 so even prior to its repeal, the Wunderlich
    Act would not have controlled this case. Nevertheless, an
    understanding of the Wunderlich Act is important to the
    proper interpretation of the CDA’s judicial review provi-
    sions.
    The Wunderlich Act consisted of two provisions. The
    first allowed for judicial review of any agency decision
    alleged to be arbitrary or capricious, unsupported by
    substantial evidence, fraudulent, or made in bad faith,
    notwithstanding any contractual provision to the con-
    When analyzing a party’s argument, this court is not
    confined to the party’s table of authorities in determining
    whether that argument has merit. That is particularly
    true with respect to jurisdictional questions, as we have
    an independent duty to inquire into whether we have
    jurisdiction over a matter, without regard to how (or even
    whether) the parties have briefed that issue.
    2    According to the legislative history, the Wunder-
    lich Act was, in fact, meant to be repealed by the CDA,
    but “due to apparent oversight, repeal was not enacted.”
    H.R. Rep. No. 111-42, at 9; see also S. Rep. No. 95-1118, at
    34 (1978) (“Section 14(i) repeals 41 U.S.C. 321–322. The
    provisions in the repealed Wunderlich Act set a standard
    of review for agency board appeals which is no longer
    applicable in [the CDA].”).
    9                                       MINESEN CO   v. ARMY
    trary. Pub. L. No. 83-356 (codified before repeal at 
    41 U.S.C. § 321
    ); see S&E Contractors, Inc. v. United States,
    
    406 U.S. 1
    , 17-18 (1972) (decisions of boards of contract
    appeals fall within the scope of this provision). The
    second stated that “[n]o Government contract shall con-
    tain a provision making final on a question of law the
    decision of any administrative official, representative, or
    board.” Pub. L. No. 83-356 (codified before repeal at 
    41 U.S.C. § 322
    ). The Wunderlich Act did not itself waive
    sovereign immunity for government contractor claims, but
    it allowed contractors to bring suit under the Tucker Act.
    The Wunderlich Act prevented government contrac-
    tors from “bargain[ing] away their right to full-scale
    judicial review of administrative decisions on questions of
    law,” Lockheed Aircraft Corp. v. United States, 
    375 F.2d 786
    , 790 (Ct. Cl. 1967), or their right to limited judicial
    review of agency decisions on questions of fact. Congress
    intended to “retain for the judiciary their proper func-
    tions,” notwithstanding standard government contract
    clauses purporting to withdraw judicial review. Hoel-
    Steffen Constr. Co. v. United States, 
    684 F.2d 843
    , 851 (Ct.
    Cl. 1982); see also S&E Contractors, 
    406 U.S. at 14
     (de-
    scribing the purpose of the Wunderlich Act as “to free
    citizens from a form of administrative tyranny”); Sea-
    board Lumber Co. v. United States, 
    903 F.2d 1560
    , 1565
    (Fed. Cir. 1990) (stating that the Wunderlich Act
    “limit[ed] by statute . . . the contractual options previ-
    ously available to the government”); Hoel-Steffen Constr.,
    684 F.2d at 851 (“we have in the history of the Wunder-
    lich Act a strong expression of repugnance by Congress to
    the creation of decisional finality by contract clause”).
    Such clauses were recognized by Congress as contrary to
    the “tradition that everyone should have his day in court.”
    H.R. Rep. No. 83-1380, at 4 (1954). Because contractors
    lacked ordinary negotiating power when entering into
    MINESEN CO   v. ARMY                                       10
    government contracts, provisions that made an agency’s
    decision unappealable were simply voided. Id. at 5. The
    Wunderlich Act, in short, was designed to invalidate
    jurisdiction-defeating clauses such as the one at issue in
    this case.
    In the Contract Disputes Act, Congress chose lan-
    guage that carefully tracked the Wunderlich Act in order
    to make clear that the CDA was continuing the prohibi-
    tion on contractual provisions that purport to foreclose
    judicial review. Subsection 7107(b) of Title 41, formerly
    subsection 609(b) of the same title, states:
    Notwithstanding any contract provision, regula-
    tion, or rule of law to the contrary, in an appeal by
    a contractor or the Federal Government from the
    decision of an agency board . . .
    (1) the decision of the agency board on a ques-
    tion of law is not final or conclusive; but
    (2) the decision of the agency board on a ques-
    tion of fact is final and conclusive and
    may not be set aside unless the decision
    is--
    (A) fraudulent, arbitrary, or capricious;
    (B) so grossly erroneous as to necessarily
    imply bad faith; or
    (C) not supported by substantial evidence.
    The CDA was not designed to diminish the statutory right
    government contractors previously held under the
    Wunderlich Act to obtain judicial review of decisions of
    agency boards. To the contrary, the CDA broadened
    contractors’ appeal rights. See Seaboard Lumber, 
    903 F.2d at 1565
     (“The CDA, which followed the Wunderlich
    Act, further restricted the government’s options on dis-
    11                                       MINESEN CO   v. ARMY
    pute resolution.”); 
    id.
     (describing CDA judicial review
    provisions as “broader” than those of the Wunderlich Act).
    Under the CDA, contractors are given the option ei-
    ther to pursue their claims before an agency board or to
    bring an action directly in the Court of Federal Claims.
    
    41 U.S.C. § 7104
    . Appeal rights to this court are available
    under either circumstance. See 
    41 U.S.C. § 7107
    (a)(1)(A)
    (providing for appeal to this court of a Board decision); 
    28 U.S.C. § 1295
    (a)(3) (providing for appeal to this court
    from the Court of Federal Claims). The standard of
    review in both the agency board and the Court of Federal
    Claims is de novo. Wilner v. United States, 
    24 F.3d 1397
    ,
    1401-02 (Fed. Cir. 1994) (en banc) (agency board review);
    
    41 U.S.C. § 7104
    (b)(4) (Court of Federal Claims review);
    see also 
    id.
     § 7103(e) (contracting officer’s “specific find-
    ings of fact are not binding in any subsequent proceed-
    ing”). The standard of review applicable to appeals to this
    court from agency boards of contract appeals is the same
    as that set forth in the Wunderlich Act. Compare Pub. L.
    No. 83-356 with 
    41 U.S.C. § 7107
    (b); see S. Rep. No. 95-
    1118, at 14 (1978) (noting that the CDA adopted the
    Wunderlich Act’s “standards of finality of agency board
    decisions”); H.R. Rep. No. 95-1556, at 25-26 (1978) (same).
    And the legislative history of the CDA makes it clear that
    Congress intended the CDA to continue to permit contrac-
    tors to appeal to this court from decisions of agency
    boards of contract appeals notwithstanding any contrac-
    tual provision to the contrary. See S. Rep. No. 95-1118, at
    26 (“it would be an anomaly in the American judicial
    system for [agency boards] to have the final authority on
    decisions that set important precedents in procurement
    law”); see also 
    id. at 12
     (noting that certain disputes
    “ultimately must go to court”); 
    id. at 13
     (agency boards
    are a forum for the “initial resolution of disputes”).
    MINESEN CO   v. ARMY                                    12
    We addressed a situation similar to the present case
    in Burnside-Ott Aviation Training Center v. Dalton, 
    107 F.3d 854
    , 858-59 (Fed. Cir. 1997). The contractual provi-
    sion at issue in that case foreclosed review of a contract-
    ing officer’s calculation of an “award fee” due to the
    contractor. 
    107 F.3d at 856
    . This court held the clause
    unenforceable in light of two provisions in the CDA. One
    noted that a contracting officer’s factual determinations
    “shall not be binding in any subsequent proceeding.” 
    41 U.S.C. § 605
    (a) (1994), recodified as 
    41 U.S.C. § 7103
    (e).
    The other stated that an appeal from a contracting offi-
    cer’s decision “shall proceed de novo in accordance with
    the rules of the appropriate court.” 
    41 U.S.C. § 609
    (a)(3)
    (1994), recodified as 
    41 U.S.C. § 7104
    (b)(4). We reasoned
    that “any attempt to deprive the Board of power to hear a
    contract dispute that otherwise falls under the CDA
    conflicts with the normal de novo review mandated by the
    CDA and subverts the purpose of the CDA.” Burnside-
    Ott, 
    107 F.3d at 858
    ; see also 
    id. at 859
     (“the CDA trumps
    a contract provision inserted by the parties that purports
    to divest the Board of jurisdiction, unless the contract
    provision otherwise depriving jurisdiction is itself a
    matter of statute primacy”). We also noted that the
    purpose behind the CDA was to equalize bargaining
    power between the government and its contractors and to
    prevent the government from using disputes clauses to
    “commandeer the final decision on all disputes of fact
    arising under the contract.” 
    Id.
     The majority attempts to
    distinguish Burnside-Ott by stating that “it did not ad-
    dress waiving appeals from the ASBCA to the Federal
    Circuit.” I am not persuaded by that distinction. In
    Burnside-Ott, after determining that the Board did have
    jurisdiction to hear the appeal, notwithstanding the
    contractual provision at issue, we addressed the merits of
    the case, reviewing the issue de novo. See 
    107 F.3d at 860
    . By doing so, we made clear that the nonwaivable
    13                                       MINESEN CO   v. ARMY
    right of review conferred by the CDA extended not just to
    the Board, but to this court as well.
    Although the contractual provision at issue in this
    case purports to displace the provisions of the CDA alto-
    gether, it cannot have the effect of foreclosing a direct
    appeal to the Court of Federal Claims, because 
    41 U.S.C. § 7104
    (b)(1) provides that such an appeal can be brought
    “notwithstanding any contract provision . . . to the con-
    trary.” Id.; see Seaboard Lumber, 
    903 F.2d at 1565
     (in the
    CDA “Congress mandated . . . dual avenues of review
    either by appeal to a Board of Contract Appeals or by a
    direct access suit in the Court of Claims”); S. Rep. No. 95-
    1118, at 11-12 (addressing the importance of contractors
    being able to directly access a “fully judicialized, totally
    independent forum . . . .”). The court’s decision in this
    case therefore creates an anomaly. Notwithstanding the
    disputes clause, Minesen could have appealed the Con-
    tracting Officer’s decision directly to the Court of Federal
    Claims rather than the Board. See § 7104(b)(1). If Mine-
    sen had followed that course, the disputes clause would
    have been inapplicable, and there would have been no bar
    to review both in the Court of Federal Claims and ulti-
    mately in this court. Yet the majority holds that by
    choosing to appeal to the Board, Minesen has forfeited its
    appeal rights in this court, notwithstanding our statutory
    jurisdiction over appeals from Board decisions under the
    CDA. That is a type of contractual restriction on judicial
    review that the CDA, in following the Wunderlich Act,
    sought to avoid. While the CDA provided for “a flexible
    system” that allows a claimant “to choose a forum accord-
    ing to . . . the degree of due process desired . . . balanced
    by the time and expense considered appropriate for the
    case,” it was important to the statutory system that
    judicial review was available through either route. S.
    Rep. No. 95-1118. I therefore disagree with the majority’s
    MINESEN CO   v. ARMY                                    14
    ruling that the contractual provision preventing appeal to
    this court is enforceable.
    II
    Because I believe that this court has jurisdiction over
    this appeal, I would reach the merits. On the merits,
    however, I would affirm the Board’s decision that Mine-
    sen’s complaint is duplicative of the complaint in its
    pending quantum action.
    The Board has discretion to dismiss a complaint that
    it deems duplicative of a pending related action. See
    Finch v. Hughes Aircraft Co., 
    926 F.2d 1574
    , 1577 (Fed.
    Cir. 1991); see generally Colo. River Water Conservation
    Dist. v. United States, 
    424 U.S. 800
    , 817 (1976) (“the
    general principle is to avoid duplicative litigation”). In
    the first count of its complaint in this action, Minesen
    asserts that the Fund’s “knowing failure to cure the
    breach” of contract identified in the earlier proceeding
    constituted an independent material breach of contract.
    The second count of the complaint alleges that the Fund
    repudiated the contract by not curing its breach. Minesen
    requests damages for both counts in accordance with the
    contract’s termination-for-convenience provision. In other
    words, Minesen treats the contract as effectively termi-
    nated and seeks to recover damages for total breach.
    That theory of damages was rejected by the Board in
    the original proceeding. Although the Board determined
    that the Fund was in breach of the contract, the Board did
    not characterize that breach as a total breach or an an-
    ticipatory repudiation. Instead, the Board remanded for a
    calculation of damages for the Fund’s ongoing partial
    breach of contract. Thus, Minesen’s second complaint
    15                                      MINESEN CO   v. ARMY
    sought to revive a cause of action that had been rejected
    in a prior proceeding.
    The Board determined that Minesen’s second com-
    plaint did not raise any new cause of action that was not
    addressed in the previous proceeding, and the Board
    therefore dismissed the complaint. The Board reasoned
    that just as Minesen could not recover damages for total
    breach of contract in the initial proceeding, it could not
    recover those damages in the subsequent proceeding
    based only on the passage of time. Instead, it could bring
    a series of actions for partial breach of contract until the
    government performed. See Ind. Mich. Power Co. v.
    United States, 
    422 F.3d 1369
    , 1377 (Fed. Cir. 2005). The
    Board noted that the only new facts alleged by Minesen in
    the second proceeding “relate[] to the amount of time the
    parties are taking to resolve the controversy in [the prior
    proceeding].” The Board did not abuse its discretion in
    determining that delay alone is insufficient to justify the
    initiation of a separate proceeding on a theory of total
    contract breach. On the merits, therefore, I would affirm
    the decision of the Board. Because I would hold that this
    court has jurisdiction to address the merits of Minesen’s
    appeal, I respectfully dissent from the majority’s decision
    on that issue.
    

Document Info

Docket Number: 2010-1453

Citation Numbers: 671 F.3d 1332, 2012 U.S. App. LEXIS 4376, 2012 WL 678150

Judges: Bryson, O'Malley, Reyna

Filed Date: 3/2/2012

Precedential Status: Precedential

Modified Date: 11/5/2024

Authorities (25)

United States v. Fausto , 108 S. Ct. 668 ( 1988 )

Brooklyn Savings Bank v. O'Neil , 65 S. Ct. 895 ( 1945 )

Lockheed Aircraft Corporation v. The United States , 375 F.2d 786 ( 1967 )

american-airlines-inc-alaska-airlines-inc-continental-airlines , 75 F.3d 1535 ( 1996 )

seaboard-lumber-company-wt-burgess-logging-co-inc-big-flat-timber , 903 F.2d 1560 ( 1990 )

Singleton v. Wulff , 96 S. Ct. 2868 ( 1976 )

Restoration Preservation Masonry, Inc. v. Grove Europe Ltd. , 325 F.3d 54 ( 2003 )

Mohammed M. El-Sheikh v. United States , 177 F.3d 1321 ( 1999 )

Burnside-Ott Aviation Training Center v. John H. Dalton, ... , 107 F.3d 854 ( 1997 )

Furash & Company v. United States , 252 F.3d 1336 ( 2001 )

Do-Well MacHine Shop, Inc. v. The United States , 870 F.2d 637 ( 1989 )

Mitsubishi Motors Corp. v. Soler Chrysler-Plymouth, Inc. , 105 S. Ct. 3346 ( 1985 )

Steel Co. v. Citizens for a Better Environment , 118 S. Ct. 1003 ( 1998 )

Walter G. Finch v. Hughes Aircraft Company , 926 F.2d 1574 ( 1991 )

William A. McCall v. U.S. Postal Service , 839 F.2d 664 ( 1988 )

Zinger Construction Company, Inc. v. The United States , 753 F.2d 1053 ( 1985 )

Hormel v. Helvering , 61 S. Ct. 719 ( 1941 )

Pathman Construction Company, Inc. v. The United States , 817 F.2d 1573 ( 1987 )

Boeing Petroleum Services, Incorporated v. James D. Watkins,... , 935 F.2d 1260 ( 1991 )

Distributed Solutions, Inc. v. United States , 539 F.3d 1340 ( 2008 )

View All Authorities »