Oregon Woods, Inc. v. Secretary of the Interior ( 2009 )


Menu:
  •                      NOTE: This disposition is nonprecedential.
    United States Court of Appeals for the Federal Circuit
    2009-1271
    OREGON WOODS, INC.,
    Appellant,
    v.
    Ken Salazar, SECRETARY OF THE INTERIOR,
    Appellee.
    C. Michael Arnold, Arnold Law Office, LLC of Eugene, Oregon, for appellant.
    Steven M. Mager, Attorney, Commercial Litigation Branch, Civil Division, United
    States Department of Justice, of Washington, DC, for appellee. With him on the brief
    were Tony West, Assistant Attorney General, Jeanne E. Davidson, Director, and Brian
    M. Simkin, Assistant Director.
    Appealed from: Civilian Board of Contract Appeals
    Administrative Judge Stephen M. Daniels
    NOTE: This disposition is nonprecedential.
    United States Court of Appeals for the Federal Circuit
    2009-1271
    OREGON WOODS, INC.,
    Appellant,
    v.
    Ken Salazar, SECRETARY OF THE INTERIOR,
    Appellee.
    Appeal from the Civilian Board of Contract Appeals in case nos. 1072 and 1072-R,
    Administrative Judge Stephen M. Daniels.
    ___________________________
    DECIDED: December 10, 2009
    ___________________________
    Before RADER, ARCHER, and LINN, Circuit Judges.
    PER CURIAM.
    I.
    The United States Civilian Board of Contract Appeals (“CBCA”) granted summary
    judgment in favor of the United States Fish and Wildlife Service (“FWS”) after the
    agency terminated a contract previously awarded to Oregon Woods, Inc. (“Oregon
    Woods”). Because FWS had a rational basis for terminating the contract, the court
    affirms.
    II.
    On September 4, 2007, FWS awarded a contract to Oregon Woods under a
    competitive procurement bid solicitation to remove and replace the Blackshore Lake
    boardwalk at the Turnbull National Wildlife Refuge near Cheney, Washington. Oregon
    Woods signed the contract the next day. The contract incorporates by reference the
    Federal Acquisition Regulation (“FAR”) Clause, which provides that “[t]he Government
    may terminate performance of work under this contract in whole or, from time to time, in
    part if the Contracting Officer determines that a termination is in the Government’s
    interest.” 48 C.F.R. 52.249-2. In addition, the contract provided that the “Contracting
    Officer may, at any time, . . . make changes in the work within the general scope of the
    contract, including changes . . . [to] the specifications” of the job.
    The day after Oregon Woods signed the contract, the contracting officer issued
    modification 1, stating: “Terminate for Convenience of the Government as evaluation
    process is not complete.”       According to the contracting officer’s notes, FWS had
    misplaced two offers during the evaluation process. Nonetheless, after considering the
    two misplaced offers, FWS still recommended that Oregon Woods be awarded the
    contract.
    On September 13, an engineer with the FWS contacted the contracting officer via
    electronic mail expressing his view that the specifications and drawings submitted in the
    solicitations were inadequate.       In particular, he noted that no qualified engineer
    approved the specifications and drawings and that various changes to the boardwalk
    design would need to be undertaken. On the same day, the chief of the regional FWS
    engineering division also sent an e-mail echoing those sentiments.
    In response to a letter from Oregon Woods expressing their concern with
    modification 1, the contracting officer rescinded the contract as void ab initio. After a
    second letter by Oregon Woods, the contracting officer issued modification 2, which
    2009-1271                                      2
    replaced modification 1 in its entirety.      Modification 2 terminated the contract for
    convenience based upon an “[i]mproper evaluation criteria posted in the solicitation” and
    “[i]nadequate specifications and drawings.”
    Oregon Woods then submitted claims for damages to the contracting officer for
    breach of contract and termination for convenience. The contracting officer denied both
    claims and Oregon Woods appealed to the CBCA.                FWS then filed a motion for
    summary judgment. Citing the FWS engineer correspondences for support, the CBCA
    found that FWS had a reasonable basis for terminating the contract and granted
    summary judgment accordingly. Oregon Woods timely appealed to this court.
    III.
    The CBCA’s decision to grant summary judgment is a legal conclusion, which
    this court reviews without deference. Rex Sys., Inc. v. Cohen, 
    224 F.3d 1367
     (Fed. Cir.
    2000). Summary judgment is appropriate in the absence of genuine issues of material
    fact when the record shows that the moving party is entitled to prevail as a matter of
    law. Fed. R. Civ. P. 56(c). “The decision of [an] agency board on any question of law
    shall not be final or conclusive, but the decision on any question of fact shall be final
    and conclusive and shall not be set aside unless the decision is fraudulent, or arbitrary,
    or capricious, or so grossly erroneous as to necessarily imply bad faith, or if such
    decision is not supported by substantial evidence.” 
    41 U.S.C. § 609
    (b). “In the absence
    of bad faith or clear abuse of discretion, [a] contracting officer’s election to terminate for
    the government's convenience is conclusive.” T&M Distribs., Inc. v. United States, 
    185 F.3d 1279
    , 1283 (Fed. Cir. 1999).
    2009-1271                                     3
    On appeal, Oregon Woods contends that summary judgment in favor of FWS
    was inappropriate because the record shows that an engineer did review the job
    specifications before the solicitation was sent out—that is, an engineer did find the
    specifications adequate.     In particular, Oregon Woods highlights that FWS made
    technical modifications to the specification twice during the solicitation process long
    before the contract was actually awarded.
    While this may be true, it does not create a material issue of fact which precludes
    summary judgment. Assuming that an engineer reviewed the solicitation, this court still
    does not detect any evidence of bad faith or an abuse of discretion on the part of the
    contracting   officer.     Significantly,   two   separate   FWS   engineers    submitted
    correspondences detailing their concerns with the solicitation and their ultimate opinions
    that the specifications were inadequate. Each discussed in fair detail what would likely
    need to be modified. The contracting officer was well within his discretion to rely on
    those recommendations and terminate the contract with Oregon Woods. In addition,
    the record does not indicate that a qualified engineer reviewed the specifications as one
    of the FWS engineers highlighted.
    Based on these considerations, this court cannot say that a material issue of fact
    exists as to whether the contracting officer acted in bad faith or clearly abused his
    discretion. We have considered all other arguments put forth by Oregon Woods and
    come to the same conclusion.
    2009-1271                                     4
    IV.
    For the foregoing reasons, the judgment of the CBCA is affirmed.
    COSTS
    No costs.
    2009-1271                                5
    

Document Info

Docket Number: 2009-1271

Judges: Percuriam, Rader, Archer, Linn

Filed Date: 12/10/2009

Precedential Status: Non-Precedential

Modified Date: 11/5/2024