Nova group/tutor-saliba v. United States ( 2023 )


Menu:
  • Case: 22-1740    Document: 46     Page: 1   Filed: 12/11/2023
    United States Court of Appeals
    for the Federal Circuit
    ______________________
    NOVA GROUP/TUTOR-SALIBA,
    Plaintiff-Appellant
    v.
    UNITED STATES,
    Defendant-Appellee
    ______________________
    2022-1740
    ______________________
    Appeal from the United States Court of Federal Claims
    in Nos. 1:15-cv-00885-MCW, 1:16-cv-00925-MCW, Senior
    Judge Mary Ellen Coster Williams.
    ______________________
    Decided: December 11, 2023
    ______________________
    G. SCOTT WALTERS, Smith, Currie & Hancock LLP, At-
    lanta, GA, argued for plaintiff-appellant. Also represented
    by ROBERT O'NEAL FLEMING, JR.; SARAH CARPENTER, Char-
    lotte, NC; ALEXANDER GORELIK, Tysons, VA.
    ANDREW JAMES HUNTER, Commercial Litigation
    Branch, Civil Division, United States Department of Jus-
    tice, Washington, DC, argued for defendant-appellee. Also
    represented by BRIAN M. BOYNTON, STEVEN JOHN
    GILLINGHAM, PATRICIA M. MCCARTHY.
    ______________________
    Case: 22-1740     Document: 46     Page: 2    Filed: 12/11/2023
    2                             NOVA GROUP/TUTOR-SALIBA v. US
    Before CHEN, CUNNINGHAM, and STARK, Circuit Judges.
    STARK, Circuit Judge.
    Nova Group/Tutor-Saliba (“NTS”) appeals from the
    judgment of the United States Court of Federal Claims
    that NTS failed to demonstrate it was entitled to recover
    additional compensation for alleged differing site condi-
    tions it encountered during the performance of a construc-
    tion contract. We affirm.
    I
    In May 2008, the United States Department of the
    Navy, acting through the United States Naval Facilities
    Engineering Command (collectively, the “government”),
    awarded NTS a contract to build a new aircraft carrier
    maintenance pier at Naval Base Kitsap in Bremerton,
    Washington. The contract required NTS to demolish an old
    pier; design and build a replacement pier (“Pier B”); and
    build a new structure, known as the Mole Quaywall, that
    would be designed by the government. The Mole Quaywall
    would be integrated with the adjacent Pier B to create a
    contiguous surface.
    Construction of both the Mole Quaywall and Pier B in-
    volved driving supporting concrete piles into the subsur-
    face soils until they reached certain “pile tip elevations.” 1
    The pile tip elevations for the government-designed Mole
    Quaywall were prescribed in the solicitation for bids. In
    particular, that solicitation included a geotechnical engi-
    neering report, known as the Geotechnical Engineering
    Baseline Survey (“GEBS”). The GEBS supplied infor-
    mation about the subsurface soil conditions at the Mole
    1 Here, the “pile tip elevation” refers to the depth be-
    low ground, not the altitude above ground, to which the
    successful bidder would be required to drive the concrete
    piles.
    Case: 22-1740    Document: 46      Page: 3    Filed: 12/11/2023
    NOVA GROUP/TUTOR-SALIBA v. US                              3
    Quaywall construction site and the adjacent Pier B site. It
    was anticipated, then, that the successful bidder for the
    contract, which included both the Mole Quaywall and the
    Pier B sites, would use the information provided in the
    GEBS to formulate its design for the pile tip elevations at
    Pier B. The successful bidder would also be responsible for
    calculating the length and required materials for the piles
    to be installed at the Mole Quaywall and Pier B.
    NTS was awarded the contract. During NTS’ construc-
    tion of the Mole Quaywall according to the government’s
    design, NTS encountered subsurface soil conditions that
    made it difficult to drive some of the piles to reach the tip
    elevations prescribed by the government. This required
    NTS to cut off greater lengths of those piles than planned,
    adding to the expense of the project. The subsurface con-
    ditions also caused some piles to move during installation
    and fall outside the specified levels of tolerance for varia-
    tions.
    In December 2009, NTS submitted a request for equi-
    table adjustment (“REA 5”), seeking additional costs in-
    curred due to the site conditions it encountered at the Mole
    Quaywall, in the amount of over $1 million. In response,
    the government issued Contract Modification No. A00057
    (“Mod. A00057”). Mod. A00057 was entered into pursuant
    to the authority of “FAR 52.236-2 Differing Site Conditions
    (APR 1984)” and provided for “settlement of contractor[’]s
    Request for Equitable Adjustment Number 5 for differing
    site conditions encounter[ed] at the [M]ole [Quaywall].”
    J.A. 17959-61. Under Mod. A00057, the total cost of the
    contract was increased by $675,000.
    Based on its experience with the site conditions at the
    adjacent Mole Quaywall, NTS made multiple modifications
    to its Pier B design, including revising the pile tip eleva-
    tions. NTS encountered pile-driving problems at Pier B
    just as it had at the Mole Quaywall. Some Pier B piles
    Case: 22-1740    Document: 46     Page: 4    Filed: 12/11/2023
    4                            NOVA GROUP/TUTOR-SALIBA v. US
    could not reach the designed tip elevations, forcing longer-
    than-expected cutoffs, and numerous piles fell outside of
    the specified tolerance levels.
    In October 2011, NTS submitted another request for
    equitable adjustment (“REA 9”), this one for the additional
    costs incurred due to the Pier B site conditions. REA 9,
    which alleged differing site conditions at Pier B, sought
    more than $10 million of additional payments, which the
    government denied. NTS then filed suit in the Court of
    Federal Claims. NTS alleged that it had encountered
    “Type I differing site conditions” at the Pier B site due to
    conditions and obstructions not disclosed in the contract
    documents, or alternatively a “Type II differing site condi-
    tion” due to “unknown physical condition.” 2 J.A. 36.
    During discovery, the government produced a pre-ne-
    gotiation business clearance memorandum pertaining to
    REA 5 and Mod. A00057. The memo stated that while the
    government did “not see” the condition at the Mole Quay-
    wall “as being a differing site condition,” it agreed it was
    responsible for the additional costs NTS had incurred
    “[d]ue to the Government providing the [Mole Quaywall’s]
    pile tip elevations.” J.A. 8633. NTS sought to exclude the
    memo from being introduced into evidence in the Court of
    Federal Claims trial on its Pier B-related claim, invoking
    the parol evidence rule. The Court of Federal Claims de-
    nied NTS’ motion in limine and, over NTS’ objection,
    2   A Type I differing site condition arises “when the
    conditions encountered differ from what was indicated in
    the contract documents.” Renda Marine, Inc. v. United
    States, 
    509 F.3d 1372
    , 1376 (Fed. Cir. 2007). A Type II dif-
    fering site condition arises “when the conditions encoun-
    tered are of an unusual nature and differ materially from
    those normally encountered in the kind of work contem-
    plated by the contract.” 
    Id.
    Case: 22-1740    Document: 46      Page: 5    Filed: 12/11/2023
    NOVA GROUP/TUTOR-SALIBA v. US                              5
    admitted the memo and then permitted witness testimony
    supporting the government’s contention that it did not ac-
    tually believe the situation in REA 5 constituted a differing
    site condition at the Mole Quaywall. J.A. 7309-15.
    The Court of Federal Claims issued its post-trial opin-
    ion in March 2022. See Nova Grp./Tutor-Saliba v. United
    States, 
    159 Fed. Cl. 1
     (2022). It found that NTS failed to
    demonstrate that it was entitled to relief on its Pier B dif-
    fering site condition claim. See 
    id. at 34-44
    . Specifically,
    the Court of Federal Claims held that NTS had not estab-
    lished a Type I differing site condition because, among
    other things, the contract documents disclosed that NTS
    would encounter unpredictable subsurface conditions and
    possible obstructions, and indicated that “[h]ard [d]riving
    [w]as to be [e]xpected.” 
    Id. at 39
    . NTS had failed to prove
    a Type II differing site condition because it had “not demon-
    strated that any of [the] potential causes for hard driving
    . . . were unknown or unusual in the region or materially
    different from comparable work.” 
    Id. at 44
    .
    NTS timely appealed. The Court of Federal Claims had
    jurisdiction pursuant to 
    28 U.S.C. § 1491
    (a)(2) and we have
    jurisdiction under 
    28 U.S.C. § 1295
    (a)(3).
    II
    We review the Court of Federal Claims’ legal determi-
    nations de novo and its fact findings for clear error. See
    Ind. Mich. Power Co. v. United States, 
    422 F.3d 1369
    , 1373
    (Fed. Cir. 2005). Contract interpretation is a question of
    law, which we review de novo. See Nw. Title Agency, Inc.
    v. United States, 
    855 F.3d 1344
    , 1347 (Fed. Cir. 2017).
    The parol evidence rule precludes the admission of ex-
    trinsic evidence “to modify, supplement, or interpret the
    terms of an integrated agreement.” Barron Bancshares,
    Inc. v. United States, 
    366 F.3d 1360
    , 1375 (Fed. Cir. 2004).
    Our precedent has not explicitly set out the standard of
    Case: 22-1740     Document: 46       Page: 6   Filed: 12/11/2023
    6                             NOVA GROUP/TUTOR-SALIBA v. US
    review of a trial court’s application of the parol evidence
    rule. We have, however, recognized that the parol evidence
    rule is “a rule of substantive law,” not a rule of evidence.
    Id.; see also David Nassif Assocs. v. United States, 
    557 F.2d 249
    , 256 (Ct. Cl. 1977). We have further explained that
    certain issues preliminary to the application of the parol
    evidence rule, including whether a contract is completely
    integrated and whether an ambiguity exists in a contract,
    are questions of law subject to de novo review. See
    Rumsfeld v. Freedom NY, Inc., 
    329 F.3d 1320
    , 1328 (Fed.
    Cir. 2003) (whether contract is completely integrated);
    Gardiner, Kamya & Assocs., P.C. v. Jackson, 
    467 F.3d 1348
    , 1353 (Fed. Cir. 2006) (whether ambiguity exists in
    contract). It follows that we review the trial court’s appli-
    cation of the parol evidence rule de novo. In so holding, we
    join our sister circuits that have addressed this issue. See,
    e.g., GTE Wireless, Inc. v. Cellexis Int’l, Inc., 
    341 F.3d 1
    , 4
    (1st Cir. 2003); Simmons Foods, Inc. v. Hill’s Pet Nutrition,
    Inc., 
    270 F.3d 723
    , 726 (8th Cir. 2001); Day v. Am. Seafoods
    Co., 
    557 F.3d 1056
    , 1057 (9th Cir. 2009); McCurdy Grp.,
    LLC v. Am. Biomedical Grp., Inc., 
    9 F. App’x 822
    , 830 (10th
    Cir. 2001).
    III
    NTS raises two issues on appeal. First, it argues that
    the Court of Federal Claims erred in considering parol evi-
    dence that, it asserts, contradicted the government’s
    “stated basis” for issuing Mod. A00057. Appellant’s Br. at
    2. Second, it contends that the Court of Federal Claims
    erred in denying its Pier B differing site condition claim
    based on the design-build nature of the contract. We ad-
    dress each issue in turn.
    A
    We begin with the parol evidence rule issue. There is
    no dispute that Mod. A00057, by which the government
    granted NTS’ REA 5 seeking additional payments for a
    Case: 22-1740     Document: 46     Page: 7    Filed: 12/11/2023
    NOVA GROUP/TUTOR-SALIBA v. US                               7
    differing site condition at the Mole Quaywall, is a fully in-
    tegrated agreement. NTS argues that since the terms of
    Mod. A00057 provided that the contract modification was
    issued under the authority of “FAR 52.236-2 Differing Site
    Conditions (APR 1984)” to settle “contractor[’]s Request for
    Equitable Adjustment Number 5 for differing site condi-
    tions encounter[ed] at the [M]ole [Quaywall],” J.A. 17959-
    61, the admission of evidence demonstrating that the gov-
    ernment did not actually believe there was a differing site
    condition at the Mole Quaywall violated the parol evidence
    rule. We disagree.
    “[T]he parol evidence rule does not, per se, foreclose
    consideration of matters external to the parties’ written
    agreement.” David Nassif, 557 F.2d at 256. Instead, the
    rule “prohibits the use of external evidence to add to or oth-
    erwise modify the terms of a written agreement . . . [that]
    has been adopted by the parties as an expression of their
    final understanding.” Barron, 
    366 F.3d at 1375
     (emphasis
    added); see also Rumsfeld, 
    329 F.3d at 1327
     (“[B]arring cer-
    tain limited exceptions (e.g., fraud), a party to a written
    contract cannot supplement or interpret [an integrated]
    agreement with oral or parol statements that conflict with,
    supplant, or controvert the language of the written agree-
    ment itself.”). Here, the evidence NTS challenges was not
    introduced by the government “to add to or otherwise mod-
    ify” the terms of Mod. A00057. The government moved the
    memo into evidence and elicited trial testimony relating to
    it not to modify its contractual obligation to pay NTS an
    additional $675,000 on REA 5 but, instead, to support its
    collateral contentions as to why it settled (i.e., because it
    was the government that prescribed the pile tip elevations
    for the Mole Quaywall project). See J.A. 8633; see also J.A.
    7309-15 (testimony that government did not agree there
    was differing site condition at Mole Quaywall). An agree-
    ment to settle a claim alleging a differing site condition un-
    der a clause governing differing site conditions is different
    Case: 22-1740     Document: 46      Page: 8    Filed: 12/11/2023
    8                             NOVA GROUP/TUTOR-SALIBA v. US
    from an agreement that the alleged differing site condition
    actually existed. As we see no provision in Mod. A00057
    that actually binds the government to an agreement that a
    differing site condition existed (as opposed to Mod. A00057
    unambiguously binding the government to settle a differing
    site condition claim), the memo and related testimony do
    not modify any term of the contract. The trial court, there-
    fore, did not violate the parol evidence rule.
    NTS’ contention fails for the additional reason that the
    parol evidence rule does not prevent a party to a contract
    from presenting evidence that “‘a recital of fact in an inte-
    grated agreement may be . . . untrue.’” United Pac. Ins. Co.
    v. Roche, 
    401 F.3d 1362
    , 1365 (Fed. Cir. 2005) (quoting Re-
    statement (Second) of Contracts § 218). In United Pacific,
    we held that the government was not obligated to pay the
    surety balance referenced in a takeover agreement’s
    “[w]hereas” clause because the “[w]hereas” clause is merely
    “a recital of fact.” Id. at 1365-66.
    Here, the provisions of Mod. A00057 on which NTS re-
    lies are, at best for NTS, “a recital of fact.” See Black’s Law
    Dictionary 1524 (11th ed. 2019) (defining “recital” as “pre-
    liminary statement in a contract or deed explaining the
    reasons for entering into it or the background of the trans-
    action”); see also 17A C.J.S. Contracts § 420 (stating recit-
    als are “explanations of the circumstances surrounding the
    execution of the contract”). We know the provisions on
    which NTS relies are recitals because they do not them-
    selves create promises, obligations, or substantive rights;
    therefore, they are not operative terms that are protected
    against alteration by the parol evidence rule. See, e.g., Pop-
    plewell v. Stevenson, 
    176 F.2d 362
    , 363 (10th Cir. 1949)
    (holding that parol evidence rule “has application to actions
    where the enforcement of an obligation created by the writ-
    ing is substantially the cause of action”). Therefore, again,
    the trial court’s admission of the memo and testimony re-
    lating to it did not violate the parol evidence rule.
    Case: 22-1740    Document: 46      Page: 9    Filed: 12/11/2023
    NOVA GROUP/TUTOR-SALIBA v. US                              9
    B
    We next turn to NTS’ argument that the Court of Fed-
    eral Claims erred in denying its differing site condition
    claim on the basis that it was a design-build contract. This
    contention provides no basis to reverse the Court of Federal
    Claims because it mischaracterizes the trial court’s analy-
    sis.
    According to NTS, the Court of Federal Claims “ex-
    plained [its] ruling in a footnote.” Appellant’s Br. at 27.
    That footnote, in its entirety, reads:
    NTS suggests that because the Government
    granted an equitable adjustment of $675,000
    for differing site conditions at the adjacent
    Mole Quaywall under Contract Modification
    A00057, NTS is entitled to an equitable ad-
    justment for pile driving difficulties at Pier B.
    However, the Government did not deem the
    situation at the Mole Quaywall to be a differ-
    ing site condition. There is a significant dif-
    ference in what transpired at the Mole – the
    Government provided the design and pile tip
    elevations for the Mole Quaywall, while NTS
    designed and chose the pile lengths and ar-
    rangement for Pier B.
    Nova Grp., 159 Fed. Cl. at 35 n.17.
    This footnote, at most, addressed why NTS was not au-
    tomatically entitled to an equitable adjustment for pile-
    driving difficulties at Pier B just because the government
    had granted an equitable adjustment at the Mole Quay-
    wall. To suggest that this footnote constitutes the entire
    explanation of the Court of Federal Claims’ ruling, or even
    an alternative, independent basis for its judgment, is incor-
    rect. The Court of Federal Claims devotes approximately
    a dozen pages of its opinion to a thorough, element-by-
    Case: 22-1740    Document: 46      Page: 10    Filed: 12/11/2023
    10                            NOVA GROUP/TUTOR-SALIBA v. US
    element analysis of NTS’ Type I and Type II differing site
    condition claims, carefully reviewing the entirety of the
    record evidence and applying the appropriate legal stand-
    ards. See id. at 34-44. The court’s conclusion that NTS
    failed to establish a differing site condition at Pier B is
    clearly based on the totality of that analysis, not simply on
    the design-build nature of the Pier B project.
    Thus, while NTS is correct that the design-build nature
    of a contract does not place the risk of error in the govern-
    ment’s representations on the contractor, see Metcalf Con-
    str. Co. v. United States, 
    742 F.3d 984
    , 995-96 (Fed. Cir.
    2014), the Court of Federal Claims simply did not make a
    mistake on this issue here.
    IV
    We have considered NTS’ remaining arguments and
    find them unpersuasive. 3 For the foregoing reasons, then,
    we affirm the judgment of the Court of Federal Claims.
    AFFIRMED
    3   In its reply brief on appeal, NTS faults the trial
    court for failing to consider extrinsic evidence NTS argues
    “[r]efuted the [i]mproperly [a]dmitted [p]arol [e]vidence.”
    Reply Br. at 4-5. This issue is forfeited. See United States
    v. Ford Motor Co., 
    463 F.3d 1267
    , 1276 (Fed. Cir. 2006)
    (“Arguments raised for the first time in a reply brief are not
    properly before this court.”).
    

Document Info

Docket Number: 22-1740

Filed Date: 12/11/2023

Precedential Status: Precedential

Modified Date: 12/11/2023