Montano Electrical Contractor v. United States ( 2015 )


Menu:
  •        NOTE: This disposition is nonprecedential.
    United States Court of Appeals
    for the Federal Circuit
    ______________________
    MONTANO ELECTRICAL CONTRACTOR,
    Plaintiff-Appellant
    v.
    UNITED STATES,
    Defendant-Appellee
    ______________________
    2014-5133
    ______________________
    Appeal from the United States Court of Federal
    Claims in No. 1:13-cv-00435-CFL, Judge Charles F.
    Lettow.
    ______________________
    Decided: April 13, 2015
    ______________________
    JOSE A. MONTANO, Madison, AL, pro se.
    BARBARA E. THOMAS, Commercial Litigation Branch,
    Civil Division, United States Department of Justice,
    Washington, DC, for defendant-appellee. Also represented
    by JOYCE R. BRANDA, ROBERT E. KIRSCHMAN, JR., BRIAN A.
    MIZOGUCHI.
    ______________________
    Before CHEN, BRYSON, and HUGHES, Circuit Judges.
    2                    MONTANO ELECTRICAL CONTRACTOR     v. US
    PER CURIAM.
    Jose Montano appeals from the final decision of the
    United States Court of Federal Claims (Claims Court)
    granting the Government’s motion to dismiss for lack of
    jurisdiction and denying Mr. Montano’s motion to trans-
    fer. Montano Electrical Contractor v. United States, 
    114 Fed. Cl. 675
     (2014). We affirm.
    BACKGROUND
    In 1999, the Army Corps of Engineers (the Corps)
    awarded a contract to American Renovation & Construc-
    tion Company (ARC) for the design and construction of
    family housing at Redstone Arsenal in Huntsville, Ala-
    bama. ARC then subcontracted the electrical work on the
    project to Mr. Montano. At some point, ARC apparently
    defaulted on its contract with the Corps, which resulted in
    ARC’s surety, St. Paul Mercury Insurance Company (St.
    Paul), assuming ARC’s obligations under the contract and
    arranging for Soltek Pacific (Soltek) to complete the
    project as completion contractor. As part of this transi-
    tion, Mr. Montano’s subcontract was assigned to Soltek
    and Mr. Montano continued to perform under the subcon-
    tract.
    Thereafter, Mr. Montano filed a claim with St. Paul,
    seeking payment for electrical work he performed at
    Redstone Arsenal. After St. Paul rejected this claim, Mr.
    Montano repeatedly sought assistance from the contract-
    ing officer at the Corps. Each time, the contracting officer
    explained that he was unable to provide the requested
    assistance because Mr. Montano did not have a contract
    with the government, and thus the government was not a
    party to the dispute. The contracting officer also ex-
    plained that Mr. Montano should pursue any such claim
    MONTANO ELECTRICAL CONTRACTOR    v. US                  3
    against the prime contractor under the Miller Act, 
    40 U.S.C. § 3133
    . 1
    In response, Mr. Montano filed a request with the
    Armed Services Board of Contract Appeals (ASBCA)
    seeking assistance resolving his contract matter. The
    ASBCA docketed Mr. Montano’s request as an appeal and
    dismissed the appeal for lack of subject matter jurisdic-
    tion.
    Mr. Montano then filed an action in the Claims Court
    seeking monetary relief from the government for the
    money owed on his subcontract. In addition, Mr. Montano
    asserted that the government was liable for the tortious
    conduct of the contracting officer. Specifically, Mr. Mon-
    tano asserted that the contracting officer breached his
    purported duty to inform Mr. Montano of his cause of
    action against the prime contractor under the Miller Act
    before the limitations period expired. The Claims Court
    concluded that it lacked jurisdiction over Mr. Montano’s
    contract claim because he was not in privity with the
    government. The Claims Court also determined that it
    lacked jurisdiction over Mr. Montano’s tort claim because
    claims brought under the Federal Tort Claims Act (FTCA)
    are expressly excluded from the Claims Court’s jurisdic-
    tion. Finally, the Claims Court concluded that it could
    not transfer Mr. Montano’s FTCA claim because Mr.
    1    The Miller Act requires a Government contractor
    to post a payment bond “for the protection of all persons
    supplying labor and material in the prosecution of the
    work provided for” in the contract. 
    40 U.S.C. § 3131
    (b)(2).
    The Act then provides that a person who has furnished
    labor or material under that contract—i.e., a subcontrac-
    tor—and has not been paid in full within 90 days after the
    last labor was performed, may initiate a law suit in feder-
    al district court on the payment bond for the unpaid
    amount. 
    40 U.S.C. § 3133
    .
    4                    MONTANO ELECTRICAL CONTRACTOR     v. US
    Montano had failed to file an administrative claim and
    therefore no district court could exercise jurisdiction over
    the claim. The present appeal followed. We have juris-
    diction under 
    28 U.S.C. § 1295
    (a)(3).
    DISCUSSION
    We review a dismissal for lack of subject matter juris-
    diction de novo. Brandt v. United States, 
    710 F.3d 1369
    ,
    1373 (Fed. Cir. 2013). Although we generally review a
    decision by the Claims Court not to transfer a matter
    under 
    28 U.S.C. § 1631
     for abuse of discretion, the under-
    lying determination that no transferee court would pos-
    sess jurisdiction over the matter is reviewed de novo.
    Rick’s Mushroom Serv., Inc. v. United States, 
    521 F.3d 1338
    , 1342–43 (Fed. Cir. 2008).
    A
    In his complaint, Mr. Montano first seeks relief for
    the money he is owed under his subcontract for the per-
    formance of electrical work at Redstone Arsenal. The
    Tucker Act authorizes the Claims Court to exercise juris-
    diction over claims against the government involving “any
    express or implied contract with the United States.” 
    28 U.S.C. § 1491
    (a)(1). Similarly, the Contract Disputes Act
    permits a contractor to bring an action challenging an
    adverse decision by a contracting officer in the Claims
    Court. 
    41 U.S.C. § 7104
    (b)(1). Because a subcontractor
    ordinarily lacks privity with the government, however, a
    subcontractor generally cannot bring such an action
    unless the prime contractor sues the government on the
    subcontractor’s behalf. E.R. Mitchell Const. Co. v. Danzig,
    
    175 F.3d 1369
    , 1370 (Fed. Cir. 1999).
    In this case, Mr. Montano acknowledges that he was
    not in privity with the government. In addition, Mr.
    Montano cannot assert that he nevertheless can bring the
    suit through the prime contractor because neither St.
    Paul nor Soltek are plaintiffs in this action. Thus, the
    MONTANO ELECTRICAL CONTRACTOR    v. US                    5
    Claims Court correctly concluded that it lacked jurisdic-
    tion over Mr. Montano’s contract claims.
    B
    Mr. Montano next seeks monetary relief for damages
    suffered as a result of the contracting officer’s alleged
    negligence. Specifically, he argues that the contracting
    officer acted negligently in failing to timely advise Mr.
    Montano of his rights under the Miller Act. The sole
    vehicle for asserting such a tort claim is the FTCA. 
    28 U.S.C. § 1346
    (b). The FTCA explains, however, that
    the district courts . . . shall have exclusive juris-
    diction of civil actions on claims against the Unit-
    ed States, for money damages . . . for injury or loss
    of property, or personal injury or death caused by
    the negligent or wrongful act or omission of any
    employee of the Government while acting within
    the scope of his office or employment . . . .
    
    Id.
     § 1346(b)(1). Likewise, the Tucker Act expressly
    excludes any claims “sounding in tort,” from the Claims
    Court’s jurisdiction. 
    28 U.S.C. § 1491
    (a)(1). Thus, the
    Claims Court correctly concluded that it lacked jurisdic-
    tion to adjudicate Mr. Montano’s claims alleging tortious
    conduct by the contracting officer.
    C
    Finally, Mr. Montano argues that, the Claims Court
    erred in refusing to transfer his FTCA claim to an appro-
    priate district court. When a court concludes that it lacks
    jurisdiction to hear an action, 
    28 U.S.C. § 1631
     permits
    that court to transfer the action “to any other such court
    in which the action or appeal could have been brought at
    the time it was filed . . . .” A court may not, however,
    transfer an action to a court that would itself lack juris-
    diction. Jan’s Helicopter Serv., Inc. v. Fed. Aviation
    Admin., 
    525 F.3d 1299
    , 1303 (Fed. Cir. 2008) (“A case
    6                    MONTANO ELECTRICAL CONTRACTOR     v. US
    may be transferred under section 1631 only to a court
    that has subject matter jurisdiction.”).
    Although the FTCA permits tort claims seeking mon-
    etary relief from the government to be filed in district
    court, any person making such a claim must first—as a
    jurisdictional prerequisite—file the asserted tort claim
    with the appropriate agency. 
    28 U.S.C. § 2675
    (a); Dal-
    rymple v. United States, 
    460 F.3d 1318
    , 1324 (11th Cir.
    2006). Here, before a district court could exercise its
    jurisdiction over a tort claim by Mr. Montano under the
    FTCA, Mr. Montano was first required to file his claim
    asserting negligence by the contracting officer with the
    Corps. The only claim in this record, however, is the
    claim that Mr. Montano filed with the ASCBA. Nothing
    in the record suggests that this claim related in any way
    to the alleged negligent conduct of the contracting officer.
    Thus, Mr. Montano has failed to establish this jurisdic-
    tional predicate to filing a claim under the FTCA. We
    agree with the Claims Court that no district court would
    have possessed jurisdiction over Mr. Montano’s FTCA
    claim at the time he filed it in the Claims Court and,
    therefore, affirm the Claims Court’s decision that it could
    not transfer Mr. Montano’s case.
    CONCLUSION
    We have considered Mr. Montano’s remaining argu-
    ments and find them unpersuasive.
    AFFIRMED
    No costs.
    

Document Info

Docket Number: 2014-5133

Judges: Chen, Bryson, Hughes

Filed Date: 4/13/2015

Precedential Status: Non-Precedential

Modified Date: 11/7/2024