Cooley Construction v. Matthews CA4/3 ( 2015 )


Menu:
  • Filed 2/24/15 Cooley Construction v. Matthews CA4/3
    NOT TO BE PUBLISHED IN OFFICIAL REPORTS
    California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
    publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication
    or ordered published for purposes of rule 8.1115.
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    FOURTH APPELLATE DISTRICT
    DIVISION THREE
    COOLEY CONSTRUCTION, INC.,
    G050422
    Plaintiff and Respondent,
    (Super. Ct. No. CIVVS703800)
    v.
    OPINION
    PATRICK MATTHEWS et al.,
    Defendants and Appellants.
    Appeal from an order of the Superior Court of San Bernardino County,
    Marsha Slough, Judge. Reversed and remanded.
    Wagner Kirkman Blaine Klomparens & Youmans, Carl P. Blaine and Eric
    R. Garner for Defendants and Appellants.
    Law Offices of Gregory J. Hout and Gregory J. Hout for Plaintiff and
    Respondent.
    *                  *                  *
    Defendants Patrick Matthews and Home Builders, Inc., (collectively,
    Matthews) appeal from the trial court’s order limiting them to one-third of their requested
    costs as the prevailing parties in a contract action and denying their motion for attorney
    fees. Plaintiff Cooley Construction, Inc., (Cooley) sued Matthews and other defendants
    for payment of the $400,000 remainder owed for paving and grading work Cooley
    completed on a residential subdivision project in Victorville. Cooley claimed Matthews
    was the alter ego or de facto partner and true contracting party behind the limited
    partnership, Victorville Wildbrook, LP, and CH Builders, Inc. (collectively, Wildbrook),
    with whom Cooley signed the paving and grading contract. Cooley sued both Matthews
    and Wildbrook for the money due on the contract, and Cooley prevailed against
    Wildbrook, but not Matthews.
    The contract included an attorney fees provision for the prevailing party in
    payment disputes and, although Matthews did not sign the contract, Cooley had sought in
    its complaint an award of attorney fees against Matthews based on the contract,
    presumably on alter ego grounds. In a bench trial on the underlying payment dispute, the
    trial court rejected the notion Matthews “engaged in, induced, [or] led anyone . . . to
    believe that” Matthews was Wildwood’s alter ego or the true party entering the contract
    with Cooley. The court therefore decided the lawsuit in Matthews’ favor against Cooley,
    but rejected Matthews’ motion for attorney fees, apparently on the basis that Matthews
    did not sign the contract. But case law establishes a nonsignatory sued on a contract in
    these circumstances is entitled to attorney fees under the contract, and we therefore
    reverse the judgment. The matter is remanded for the trial court to determine the amount
    of attorney fees and costs to which Matthews is entitled.
    I
    DISCUSSION
    Because the parties’ dispute centers on the attorney fee terms of the paving
    and grading contract, and neither party offered extrinsic evidence to aid in interpreting
    2
    the contract, we turn immediately to the contract itself, which we interpret de novo. (See
    Zalkind v. Ceradyne, Inc. (2011) 
    194 Cal. App. 4th 1010
    , 1022 [“When, as in this case, no
    extrinsic evidence is introduced, the appellate court independently construes the
    contract”].) The common, ordinary meaning of the words used in a contract are
    controlling. (Ibid.) “The terms of a contract are determined by objective rather than by
    subjective criteria. The question is what the parties’ objective manifestations of
    agreement or objective expressions of intent would lead a reasonable person to believe.
    [Citations.]” (Winograd v. American Broadcasting Co. (1998) 
    68 Cal. App. 4th 624
    , 632.)
    Here, the contract included two separate attorney fees provisions, one
    governing payment disputes (Paragraph 11) and the other governing “construction”
    disputes (§ 9(E)(1)(d)). The former provided for attorney fees in payment disputes, while
    the latter dictated the parties would bear their own attorney fees in resolving through
    mediation and binding arbitration disputes arising during construction. The mediation
    and arbitration provision covered only construction disputes.
    As Matthews explains, the dual fee and dispute resolution provisions made
    sense in the context of a fast-moving construction project: “The construction dispute fee
    provision is part of a dispute resolution mechanism designed to quickly resolve
    construction issues or disputes occurring in the field: change order, scope of work,
    timing and materials issues. This mechanism first requires mediation, an informal
    negotiation and then arbitration. It is designed to be a quick, alternative means to
    resolving construction disputes so as not to disrupt or unnecessarily hold up a project. It
    is in construction disputes only that the parties clearly agreed to bear their own fees.
    Quite differently, in disputes concerning failure to pay, the parties plainly agreed . . . that
    the prevailing party shall be entitled to reasonable attorney fees.”
    Specifically, the payment provisions in the contract provided that “Progress
    payments shall be provided for all completed work” within “30 calendar days after
    invoice” (Paragraph 8), that “Final payment” was “due 60 days after completion” of
    3
    Cooley’s work (Paragraph 10), and that “[i]f it becomes necessary to enforce provisions
    of this proposal or terms of payment, the prevailing party shall recover reasonable
    attorney’s fees and all costs otherwise provided by law” (Paragraph 11). (Italics added.)
    The parties agreed this language carried over from Cooley’s successful bid proposal and
    was incorporated into the paving and grading contract.
    Unlike the attorney fee provision in Paragraph 11 for payment disputes,
    Section 9(E)(1)(d) specified the parties would bear their own fees in resolving
    construction disputes. Specifically, it provides that the parties “acknowledge and agree
    that all construction disputes regarding the Project shall be resolved in accordance with
    the procedures set forth below,” consisting first of “Mediation” (§ 9(E)(1)(a)), then good
    faith consultation and negotiation, followed by binding arbitration (§ 9(E)(1)(b)).
    Subpart (d) of this section provides that in resolving the “construction disputes”
    according to the mediation and arbitration procedure outlined in § 9(E)(1), “each party
    shall be responsible for and shall pay its own attorney’s fees and costs incurred in
    conjunction therewith without right of reimbursement from the other party.” (Italics
    added.) Viewing Paragraph 11 in conjunction with Section 9(E)(1)(d), it is plain that the
    former covers payment disputes, for which attorney fees are authorized, and the latter
    governs construction disputes, in which each party bears their own attorney fees. We
    must give effect to this plain language. (See, e.g., Civ. Code, § 1641 [“The whole of a
    contract is to be taken together, so as to give effect to every part”].)
    Noting that the payment provisions of the paving and grading contract first
    appeared in Cooley’s successful bid proposal for the paving and grading project, Cooley
    contends the attorney fees provision in Paragraph 11 is limited to enforcing the bid
    proposal. This interpretation fails for two reasons. First, the bid proposal itself provided
    that its terms would be incorporated into the ensuing paving and grading project,
    including an identical attorney fees provision for enforcing payment terms. (See Bid
    Proposal, ¶¶ 2 & 15.) Second, Cooley does not identify any payments due solely under
    4
    the bid proposal, and therefore it would not make sense to limit the attorney fees
    provision to enforcing payments due solely under the bid proposal because there were
    none. For instance, nothing suggests Cooley was paid to submit its bid or to do any
    preliminary work in conjunction with submitting its bid. Rather, the only payments
    contemplated in both the bid proposal and the ensuing paving and grading contract were
    for actual paving and grading work Cooley completed. Therefore, the attorney fee
    provision in Paragraph 11 applied to enforcing payment for that work.
    Indeed, that is exactly what Cooley claimed in its complaint. Cooley
    alleged in its complaint that “said written agreement [i.e., the paving and grading
    contract] provides for reasonable attorney’s fees and court costs incurred in enforcing the
    terms and conditions thereof. Plaintiff [i.e., Cooley] should be allowed a reasonable sum
    as attorney’s fees for the commencement and prosecution of this action.” As we explain
    below, the expression that “what is good for the goose is good for the gander” applies to
    make contractual attorney fees reciprocal for prevailing defendants, including
    nonsignatories sued as alleged contracting parties.
    Now on appeal, Cooley contends its lawsuit was not fundamentally to
    enforce payment, but rather to ascertain what amounts were due under the contract for its
    paving and grading work and who was responsible for making those payments. These
    very issues, however, are the gravamen of enforcing payment. Cooley also argues that
    attorney fee provisions in a contract must be strictly construed, but that principle cuts
    against Cooley because, as noted, we must give effect to all the contract terms, whereas
    Cooley’s interpretation renders some terms surplusage.
    While it is thus clear in examining the contract that it provides for attorney
    fees to enforce its payment terms, the trial court concluded that provision did not apply to
    nonsignatories. The court observed, “[W]hy should that [attorney fees provision] be
    applicable to an individual defendant, who is not an individual party to any of the
    contracts [i.e., the successful bid proposal and ensuing paving and grading contract]?”
    5
    Our Supreme Court has answered this query by holding that under the
    reciprocity requirement in Civil Code section 1717 governing contractual attorney fee
    provisions, a nonsignatory defendant is entitled to recover its fees when the signatory
    plaintiff would have been entitled to fees had it prevailed. (Reynolds Metal Co. v.
    Alperson (1975) 
    25 Cal. 3d 124
    , 128-129.) As the Supreme Court later explained, “If
    section 1717 did not apply in this situation, the right to attorney fees would be effectively
    unilateral — regardless of the reciprocal wording of the attorney fee provision allowing
    attorney fees to the prevailing party — because only the party seeking to affirm and
    enforce the agreement could invoke its attorney fee provision. To ensure mutuality of
    remedy in this situation, it has been consistently held that when a party litigant prevails in
    an action on a contract by establishing that the contract is invalid [as to the defendant],
    inapplicable, unenforceable, or nonexistent, section 1717 permits that party’s recovery of
    attorney fees whenever the opposing parties would have been entitled to attorney fees
    under the contract had they prevailed.” (Santisas v. Goodin (1998) 
    17 Cal. 4th 599
    , 611.)
    Cooley does not dispute that nonsignatories are entitled to fees in these
    circumstances, but argues instead that the contract did not provide for attorney fees. That
    position contradicts Cooley’s claim in its complaint and, more to the point, fails under the
    express contract terms. Had Cooley prevailed in holding Matthews accountable for
    payment under the contract as Wildbrook’s alter ego or otherwise as the true party with
    whom Cooley actually negotiated and formed the paving and grading contract, Cooley
    would have been entitled to attorney fees under the contract. Under Civil Code
    section 1717’s reciprocity requirement, Matthews is therefore likewise entitled to
    attorney fees as the prevailing party.
    Cooley contends Matthews is not entitled to attorney fees because the
    attorneys defending the action named an entity other than Matthews in their billing
    invoices. But whether Matthews incurred attorney fees defending against Cooley’s
    lawsuit is a factual matter better left at this stage to the trier of fact on remand. Matthews
    6
    contends the trial court erred as a factual matter in approving only one-third of its costs
    request because Matthews actually incurred all of the litigation costs and attorney fees
    given the other defendant (Wildbrook) did not dispute it owed Cooley for the work it
    performed under the paving and grading contract The same attorneys represented both
    Wildbrook and Matthews (and their alleged alter egos, CH Builders and Home Builders,
    respectively). On remand, the attorneys’ billing records and other evidence in support of
    their fee claim will shed light on what portion of the attorneys’ work was allocated to
    each defendant, if it was severable. Because the allocation of costs likely will largely
    track the percentage of attorney fees attributable to each defendant, we reverse the trial
    court’s cost award for reconsideration in light of any evidence the parties present on the
    appropriate amount and allocation of attorney fees.
    II
    DISPOSITION
    The trial court’s attorney fees and costs order is reversed. The trial court in
    proceedings on remand shall determine the amount of attorney fees and allocation of
    costs to which Matthews and Home Builders, Inc. are entitled as prevailing parties.
    Matthews and Home Builders, Inc. are similarly entitled to their costs and attorney fees
    on appeal in an amount to be determined by the trial court.
    ARONSON, J.
    WE CONCUR:
    BEDSWORTH, ACTING P. J.
    IKOLA, J.
    7
    

Document Info

Docket Number: G050422

Filed Date: 2/24/2015

Precedential Status: Non-Precedential

Modified Date: 4/18/2021