Affordable Clean Water Alliance v. Santa Clarita Valley etc. CA2/5 ( 2022 )


Menu:
  • Filed 2/16/22 Affordable Clean Water Alliance v. Santa Clarita Valley etc. CA2/5
    NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS
    California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on
    opinions not certified for publication or ordered published, except as specified by rule
    8.1115(b). This opinion has not been certified for publication or ordered published for
    purposes of rule 8.1115.
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    SECOND APPELLATE DISTRICT
    DIVISION FIVE
    AFFORDABLE CLEAN                                       B303831
    WATER ALLIANCE,
    (Los Angeles County
    Plaintiff and Appellant,                       Super. Ct. No. BS170983)
    v.
    ORDER MODIFYING
    SANTA CLARITA VALLEY                                   OPINION AND DENYING
    SANITATION DISTRICT OF                                 PETITION FOR
    LOS ANGELES COUNTY,                                    REHEARING
    Defendant and                                     [NO CHANGE IN
    Respondent.                                            JUDGMENT]
    The opinion filed on January 19, 2022, is modified as
    follows:
    1.         On page 27, delete footnote 7 and replace with the
    following:
    To the extent the Alliance argues that the doctrine of
    collateral estoppel did not bar it from challenging the
    District’s failure to consider alternatives to the Chloride
    Compliance Project, that is, alternatives to removing
    chloride from the treated wastewater, it did not challenge
    the District’s failure to consider any such alternatives in
    the trial court. “We do not consider new matters raised for
    the first time on appeal.” (Citizens Opposing a Dangerous
    Environment v. County of Kern (2014) 
    228 Cal.App.4th 360
    ,
    380, fn. 16.)
    The petition for rehearing is denied. There is no change in
    judgment.
    ____________________________________________________________
    BAKER, Acting P. J.         MOOR, J.               KIM, J.
    2
    Filed 1/19/22 Affordable Clean Water Alliance v. Santa Clarita Valley etc. CA2/5
    (unmodified opinion)
    NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS
    California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions
    not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion
    has not been certified for publication or ordered published for purposes of rule 8.1115.
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    SECOND APPELLATE DISTRICT
    DIVISION FIVE
    AFFORDABLE CLEAN                                             B303831
    WATER ALLIANCE,
    (Los Angeles County
    Plaintiff and Appellant,                            Super. Ct. No. BS170983)
    v.
    SANTA CLARITA VALLEY
    SANITATION DISTRICT OF
    LOS ANGELES COUNTY,
    Defendant and
    Respondent.
    APPEAL from a judgment of the Superior Court of Los
    Angeles County, James C. Chalfant, Judge. Affirmed.
    The Silverstein Law Firm, Robert P. Silverstein, James S.
    Link, and Naira Soghbatyan, for Plaintiff and Appellant.
    Cox, Castle, & Nicholson, Michael H. Zischke, David P.
    Waite, and Alexander M. DeGood, for Defendant and
    Respondent.
    I. INTRODUCTION
    Plaintiff Affordable Clean Water Alliance (the Alliance)
    appeals from a judgment denying its petition for writ of mandate.
    The Alliance asserted that the Santa Clarita Valley Sanitation
    District of Los Angeles County (the District) violated the
    California Environmental Quality Act (CEQA; Pub. Resources
    Code, § 21000 et seq.)1 when it certified a project to reduce the
    chloride levels in wastewater treated at its water reclamation
    plants. The trial court denied the petition. We affirm.
    II. BACKGROUND
    A.    The Initial Project and 2013 EIR
    The District is responsible for treating wastewater for the
    Santa Clarita Valley, which it accomplishes through its Valencia
    and Saugus water reclamation plants. The treatment process
    produces high-quality wastewater that is suitable for reuse. In
    2013, a portion of the treated wastewater (referred to as recycled
    water) was reused and a portion was discharged into the Santa
    Clara River (the River).2
    1    Further statutory references are to the Public Resources
    Code unless otherwise indicated.
    2     Recycled water is treated wastewater that, instead of being
    discharged into the River, is reused by local communities.
    2
    Under the federal Clean Water Act and the California
    Porter-Cologne Water Quality Control Act, the California
    Regional Water Quality Control Board – Los Angeles Region
    (Control Board) regulates discharges into the River. In 2002, the
    Control Board adopted the Upper Santa Clara River Chloride
    Total Maximum Daily Load (Chloride TMDL) order, which set a
    chloride limit of 100 milligrams per liter for treated wastewater
    that was discharged from the District’s reclamation plants into
    the River. The Control Board set a 2015 deadline for the District
    to comply with the Chloride TMDL order. The water reclamation
    plants, however, were not designed to remove chloride from
    treated wastewater.
    In October 2013, the District prepared the Chloride
    Compliance Facilities Plan (the Initial Project) and
    Environmental Impact Report (2013 EIR). The objectives of the
    Initial Project were: to comply with the state-mandated chloride
    level limit; to create wastewater treatment facilities for chloride
    removal and future expansion of the Valencia water reclamation
    plant; and to “[p]rovide a wastewater treatment and effluent
    management program that accommodates recycled water reuse
    opportunities in the Santa Clarita Valley while protecting
    beneficial uses of the [River].”
    The Initial Project consisted of two components: the
    Chloride Compliance Project, which addressed the first two
    objectives, and the Recycled Water Project, which addressed the
    third objective. The 2013 EIR discussed a range of alternatives
    to comply with the Chloride TMDL order and identified four final
    alternatives. Alternative 1 involved treating a portion of the
    wastewater at the Valencia water reclamation plant with
    microfiltration and reverse osmosis, a process that would produce
    3
    “a salty water byproduct called brine that require[d] proper
    disposal.” Alternative 1 proposed disposing of the resulting brine
    via a pipeline to the Los Angeles Basin.
    Alternative 2 was “similar to Alternative 1 except that
    brine would be disposed via [deep well injection] and [ultraviolet]
    disinfection would replace the existing chloride-based disinfection
    systems at both [water reclamation plants].”
    Alternative 3 was “similar to Alternative 2 except that
    brine would be disposed via trucking to an unloading terminal”
    and would eventually flow into the ocean.
    Alternative 4, known as Phased AWRM, consisted of two
    phases. Phase I involved the use of ultraviolet disinfection
    systems at both water reclamation plants, salt management
    facilities in Ventura County, and supplemental water. In the
    event Phase I could not provide consistent water quality in
    compliance with the Chloride TMDL order, Phase II provided for
    microfiltration and reverse osmosis, as well as disposal of brine
    via deep well injection. Alternative 4 was contingent on support
    by Ventura County stakeholders.
    After evaluating these four alternatives, the District
    selected Alternative 4, with Alternative 2 serving as a back-up.
    The 2013 EIR also discussed the Recycled Water Project
    component of the Initial Project. The District explained that each
    of the alternatives described in the 2013 EIR would include
    making recycled water available in quantities needed to support
    the Recycled Master Plan prepared by the Santa Clarita Valley
    Water Agency (Water Agency). That master plan made recycled
    water available for use by local municipalities and projected that
    the need for recycled water would increase over time as the
    population of the community using the water grew. Because any
    4
    treated wastewater that was used for the Recycled Water Master
    Plan would necessarily be diverted from discharge into the River,
    the 2013 EIR found that the Recycled Water Project “could result
    in a reduction in flow discharged by the [water reclamation
    plants] to the [River] under each alternative.” The 2013 EIR
    considered the potential impact of the Recycled Water Project on
    the statutorily-protected unarmored threespine stickleback fish
    (stickleback) and concluded that even though “discharge of
    treated wastewater from the [water reclamation plants] to the
    [River] could decrease [because of the Recycled Water Project] . . .
    the combined [water reclamation plant] discharges would not be
    lower than the minimum flow of 13 [million gallons per day]
    identified to sustain the river’s biological resources.”
    On October 24, 2013, Ventura County stakeholders notified
    the District by letter that they would not support Alternative 4.
    On October 28, 2013, the District’s board certified the 2013 EIR
    and adopted Alternative 2.
    B.    Case No. BS145869
    On November 27, 2013, in case No. BS145869, the Alliance
    filed a petition for writ of mandate, alleging that the District had
    violated CEQA. The Alliance sought to compel the District to set
    aside its approval of the 2013 EIR.
    On March 11, 2015, the District’s board voted to abandon
    Alternative 2 as the deep well injection portion of this alternative
    was no longer viable.
    On March 27, 2015, the Alliance filed a first amended
    petition, the operative pleading in case No. BS145869.
    
    5 C. 2016
     Trucking SEIR
    On September 18, 2015, the District issued a notice of
    preparation, and on November 17, 2015, it issued a notice of
    availability for a Supplemental Environmental Impact Report for
    Brine Concentration and Limited Trucking (2016 Trucking
    SEIR).3 The first two objectives of the Revised Project were to
    comply with the Chloride TMDL order “by the State’s deadline[]”;
    and to use an existing industrial facility for brine disposal. The
    third objective was identical to the third objective of the Initial
    Project.
    Because Alternative 1 would not be completed in a timely
    manner and Alternative 2 was no longer viable, the District
    concluded that Alternative 3, with “enhanced brine concentration
    technology” and limited trucking to an existing industrial facility
    for brine disposal, was the best alternative for the Revised
    Project. The District noted that only Alternative 3 could be
    implemented by July 1, 2019, the final deadline for compliance
    with the Chloride TMDL order. The District also stated that in
    order to avoid delays, the Recycled Water Project would “no
    longer [be] part of the currently recommended project” and
    “would be separately considered by the [District] Board after
    further environmental and public review in a separate CEQA
    document.”
    3     For purposes of clarity, we will refer to the revised project
    described in the 2016 Trucking SEIR as the “Revised Project.”
    6
    D.    Trial Court’s Ruling in Case No. BS145869
    On December 7, 2015, the Alliance filed its memorandum of
    points and authorities in supports of its petition challenging the
    2013 EIR in case No. BS145869. The Alliance argued that the
    District: had approved a project that was impermissible; violated
    the Department of Fish and Wildlife’s directions; failed to provide
    substantial evidence that the stickleback would not be impacted
    by the Initial Project; failed to mitigate harm to the arroyo toad;
    and failed to provide a project description in compliance with
    CEQA.4
    On February 23, 2016, the trial court granted the Alliance’s
    petition in part. Although it rejected the Alliance’s argument
    that the District violated CEQA by approving Alternative 2,
    finding that the issue was moot because the District had
    abandoned that alternative, it agreed with the Alliance that the
    District had yet to approve Alternative 3. Therefore, the court
    concluded that any project approvals must be set aside.
    Regarding the stickleback, the trial court rejected the
    Alliance’s assertion that the Department of Fish and Wildlife
    required the District to perform “a specific analysis of the
    stickleback in the [2013 EIR].” The court, however, agreed with
    the Alliance that the 2013 EIR lacked substantial evidence to
    support a finding that the stickleback “will not be taken within
    the meaning of Fish and Game Code section 5515.”
    4     In the first amended petition in case No. BS145869, the
    Alliance alleged that the District failed to analyze a reasonable
    range of project alternatives. This argument was not raised in its
    memorandum of points and authorities before the trial court.
    7
    The trial court found against the Alliance regarding the
    lack of mitigation measures to protect the arroyo toad and the
    project description in the 2013 EIR.
    The trial court granted the Alliance’s petition in part as
    follows: “(1) the [2013 EIR] lacks substantial evidence for its
    conclusion of no significant impact (no take) on stickleback
    populations, and (2) since the District has abandoned Alternative
    2 and there is as yet no approved Project for Alternative 3, the
    Project approvals must be set aside.”
    On March 9, 2016, the trial court issued the judgment in
    case No. BS145869. The court directed the District to: decertify
    the 2013 EIR; set aside and invalidate all project approvals; and
    “[r]efrain from taking any steps to carry out the [Initial] Project
    until and unless [the District] has fully complied with CEQA, all
    other applicable laws, and the writ, and the writ has been
    discharged.” On March 17, 2016, the court issued the peremptory
    writ of mandate. The District was directed to file a return on the
    writ. No appeal was taken from the judgment.
    E.    The District Certifies 2016 Trucking SEIR and the Alliance
    Challenges the District’s Return on the Writ
    On March 23, 2016, the District decertified the 2013 EIR
    and vacated the associated project approvals. The District then
    re-certified the 2013 EIR as augmented by the 2016 Trucking
    SEIR.5
    5     On April 20, 2016, the Alliance filed a second petition for
    writ of mandate in case No. BS161742, alleging that the 2016
    Trucking SEIR violated CEQA. On September 26, 2017, the trial
    court granted the District’s motion to dismiss case No. BS161742
    8
    On April 14, 2016, the District filed a return to the writ in
    case No. BS145869, asserting that it had fully complied with the
    writ by decertifying the 2013 EIR and approving the 2016
    Trucking SEIR.
    On May 10, 2016, the Alliance filed a motion challenging
    the return to the writ and requesting that the writ of mandate be
    maintained.
    On June 2, 2016, the trial court granted the Alliance’s
    motion, finding that the District failed to “present evidence why
    the [Initial] Project is severable into two components and why
    doing so will not affect the CEQA reporting process. . . . In the
    District’s words, it must show that the water recycling
    component’s effects will not change the scope or nature of the
    chloride compliance component. ” (Fn. omitted.) The court
    concluded that the District violated CEQA’s procedural
    requirements by separating the Initial Project’s two components
    (Chloride Compliance Project and Recycled Water Project)
    without public input. The court ordered the District “to
    reconsider its return to the writ and file an additional Return
    when it has certified an EIR for the [Initial] Project in a manner
    that complies with CEQA.”
    F.    Notice of Preparation for Supplemental EIR of Recycled
    Water Project
    On August 4, 2016, the District issued a notice of
    preparation for a project entitled “Santa Clarita Valley
    Sanitation District Supplemental Environmental Impact Report
    as moot because, as discussed below, the District subsequently
    decertified the 2016 Trucking SEIR.
    9
    for Study of Impacts to the Unarmored Threespine Stickleback
    Fish Under Reduced Discharge Conditions from the Santa
    Clarita Valley Sanitation District’s Water Reclamation Plants”
    (Recycled Water Project SEIR). The Recycled Water Project
    SEIR’s purpose was to evaluate the potential impact on the
    stickleback from the reduced wastewater discharge into the River
    caused by the Recycled Water Project. In the notice, the District
    stated, among other things, that “[t]he production and disposal of
    brine produced at Valencia [water reclamation plant] would
    reduce discharge to the [River], which supports special-status
    species. Increased use of recycled water could also reduce
    discharge to the [R]iver.”
    G.    2017 Recirculated EIR
    On February 17, 2017, the District issued a notice of
    preparation for the “Recirculated Santa Clarita Valley Sanitation
    District Chloride Compliance Project Environmental Impact
    Report – Separation of Recycled Water Project” (2017
    Recirculated EIR). The 2017 Recirculated EIR incorporated and
    used prior environmental analyses from the 2013 EIR and 2016
    Trucking SEIR and considered whether new information or
    changed circumstances required any update to the prior analyses.
    The District sought comments for the new content of the 2017
    Recirculated EIR only.
    On August 30, 2017, the District: decertified the 2013 EIR
    and the 2016 Trucking SEIR; certified the 2017 Recirculated EIR;
    and approved the Chloride Compliance Project.
    The 2017 Recirculated EIR explained that the objectives of
    the proposed project, which was now comprised of just the
    10
    Chloride Compliance Project, were to provide compliance with the
    Chloride TMDL order and to use an existing industrial facility for
    brine disposal. The District determined that separation of the
    Recycled Water Project and the Chloride Compliance Project
    “would generally lessen impacts on environmental resources as
    there would be no significant changes to current operations.” The
    2017 Recirculated EIR included updated analyses for: air
    quality, biological resources, hydrology and water quality,
    cumulative impacts, alternatives, growth inducement, and water
    resources. For all other resource areas previously studied in the
    2013 EIR and 2016 Trucking SEIR, the 2017 Recirculated EIR
    found that “[n]o impacts would result” from separately
    implementing the Chloride Compliance Project and Recycled
    Water Project.
    In discussing project alternatives, the District found that
    “[n]one of the alternatives evaluated in the 2016 Trucking SEIR
    . . . relied upon the Recycled Water Project.” Two of the
    alternatives initially discussed in the 2013 EIR relied upon the
    Recycled Water Project, but had been rejected as infeasible and
    the analysis that rejected those alternatives still applied.
    The 2017 Recirculated EIR concluded that the “the
    environmental impacts of the construction and operation of the
    proposed Chloride Compliance Project do not change as a result
    of separating the Recycled Water Project from the proposed
    project. Therefore, the previous alternative analysis contained in
    the 2013 EIR and the 2016 Trucking SEIR . . . are still applicable
    and cover the reasonable range of alternatives required by
    CEQA. The ‘no project’ alternative would not meet the objective
    of complying with the State-mandated Chloride TMDL. The
    alternative of maintaining both the Chloride Compliance Project
    11
    and the Recycled Water Project under the cover of one CEQA
    document does not meet the objective of compliance by [the
    District], in as timely a manner as is feasible, with the Chloride
    TMDL for its wastewater and discharge facilities.”
    H.    Case No. BS170983
    On September 1, 2017, the Alliance filed its petition for
    writ of mandate in case No. BS170983, the petition at issue in the
    instant appeal. The Alliance alleged causes of action for violation
    of CEQA and requested a writ of mandate to invalidate the
    Chloride Compliance Project approvals and the 2017 Recirculated
    EIR. The Alliance asserted, among other things, that: the
    District engaged in piecemeal review (piecemealing) of the
    Chloride Compliance Project and the Recycled Water Project; the
    alternatives analysis for the Chloride Compliance Project was
    inadequate; and the cumulative environmental impacts analysis
    of the Chloride Compliance Project and the Recycled Water
    Project pertaining to the stickleback was inadequate.
    I.    Partial Return to and Partial Discharge of Writ
    On September 22, 2017, the District filed a partial return
    to the writ in case No. BS145869 and moved for an order to
    partially discharge the writ. The Alliance moved to challenge the
    return and sought an order to enforce the writ. On
    October 24, 2017, the trial court heard and granted the District’s
    motion and denied the Alliance’s motion. The court discharged
    the writ as it pertained to the Chloride Compliance Project,
    finding that the 2017 Recirculated EIR complied with the writ.
    12
    The court “retain[ed] jurisdiction over the remaining issue in the
    writ: an environmental review of the impacts to the stickleback
    caused by the Recycled Water Project, if that project goes
    forward.”
    J.    The District’s Rejection of Recycled Water Project and Full
    Discharge of Writ
    On February 25, 2019, the District issued a resolution that
    it had: ceased its planning efforts on the Recycled Water Project;
    withdrew the notice of preparation for the Recycled Water Project
    SEIR; and rejected the Recycled Water Project. The District
    concluded that the studies necessary to address the impact on the
    stickleback because of flow diversion and reduced discharges,
    coupled with the associated resource agency approvals for the
    flow diversion and reduced discharge, would not be timely or cost
    effective for ratepayers. The outcome of the project was also
    uncertain because of the probability of future litigation.
    On April 26, 2019, the District filed another return to the
    writ. The District asserted that it had addressed the remaining
    issue encompassed by the writ by rejecting the Recycled Water
    Project. The District also moved for the writ to be discharged.
    On May 21, 2019, the trial court granted the District’s motion,
    concluding that the writ was fully discharged.
    K.    Trial Court Denies Petition in Case No. BS170983
    On July 17, 2019, the Alliance filed its memorandum of
    points and authorities in support of its petition in case No.
    BS170983. It argued, among other things, that the District had:
    13
    failed to identify and analyze feasible alternatives in the 2017
    Recirculated EIR; piecemealed the Recycled Water Project and
    the Chloride Compliance Project; and failed to analyze
    cumulative impacts properly.
    The Alliance raised three different arguments in support of
    its claim that the 2017 Recirculated EIR failed to identify and
    analyze feasible alternatives. First, it argued that, because the
    2013 EIR had rejected some alternatives as not being able to
    meet an earlier May 2015 deadline for compliance with the
    Chloride TMDL order, and that deadline had been extended, the
    use of the 2013 EIR’s analysis was no longer “current” and
    needed to be updated. Second, it argued that the 2017
    Recirculated EIR did not adequately discuss alternatives to
    separating the Recycled Water Project from the Chloride
    Compliance Project. And, third, the Alliance contended that the
    2017 Recirculated EIR failed to identify a preferred alternative.
    Regarding cumulative impacts, the Alliance argued that
    the 2017 Recirculated EIR failed to analyze the impact of the
    Recycled Water Project on biological resources like the
    stickleback. The Alliance contended that because the Recycled
    Water Project was listed as a related project, a cumulative impact
    analysis was necessary.
    In support of its argument that the District had engaged in
    piecemealing, the Alliance asserted that the Chloride Compliance
    Project and the Recycled Water Project were part of one project
    that the District had “‘“chopp[ed]”’” into smaller ones, in an
    attempt “to defer or avoid identifying, analyzing, and mitigating
    impacts” of the project.
    14
    On August 23, 2019, the District filed its opposition,
    asserting, among other things, that: the petition was moot
    because the Recycled Water Project had been abandoned by the
    District; and res judicata and collateral estoppel principles barred
    the Alliance’s assertions as the trial court had mostly upheld the
    Chloride Compliance Project in case No. BS145869.
    On September 26, 2019, the trial court heard oral
    argument on the petition in case No. BS170983.6 On October 11,
    2019, the court issued its decision denying the petition.
    While the trial court rejected the District’s res judicata
    arguments, the court found that the Alliance was “collaterally
    estopped from litigating any issue raised in [case No. BS145869]
    concerning the Chloride Compliance Project, with the exception of
    the Brine Trucking component and updates to the 2013 EIR.”
    The court noted that there were only two deficiencies in the 2013
    EIR: “(1) a lack of sufficient analysis on potential impacts to the
    stickleback fish; and (2) a lack of an alternative for brine
    management. . . . The court found no fault with the other
    components of the Chloride Compliance Project and thus the writ
    was granted only in part.” The court found that collateral
    estoppel applied because “the parties are identical, the issues
    concerning the Chloride Compliance Project were actually
    litigated and necessarily decided in [case No.] BS145869, and the
    court’s decision was not appealed and is final on the merits.”
    6     Although a court reporter was present at the hearing on
    September 26, 2019, due to a catastrophic “malfunction” of
    equipment, she was unable to prepare a transcript of the
    proceedings. The record therefore does not include a reporter’s
    transcript of the proceedings. Nor does it include a suitable
    substitute such as a settled or agreed statement.
    15
    Regarding the Alliance’s piecemealing argument, the trial
    court rejected it as moot. The court found that because the
    District had abandoned the Recycled Water Project, there were
    no longer two components to the Project.
    The trial court also rejected the Alliance’s cumulative
    impacts argument. Citing California Code of Regulations, title
    14, section 15130, subdivision (a)(1), the court ruled: “As the
    [2017 Recirculated EIR] states, the Chloride Compliance Project
    simply has no impacts—biological resource or otherwise—that
    accumulate with those of the Recycled Water Project. The
    Chloride Compliance Project will not result in any reduction of
    effluent discharge, the biological impacts of which were the only
    impact not sufficiently addressed in the 2013 EIR. Since the
    Chloride Compliance Project will not reduce water flow in the
    River, there are no cumulative impacts to resolve.” The court
    added, “[s]ince the Chloride Compliance Project will not have any
    biological resources impacts that accumulate with the Recycled
    Water Project, no cumulative impacts analysis is needed on that
    issue.”
    The trial court rejected the Alliance’s argument that the
    2017 Recirculated EIR’s reuse of the prior alternatives analysis
    from the 2013 EIR and the 2016 Trucking EIR was outdated and
    therefore invalid. The court found that “[the Alliance] fails to
    meet its burden of presenting substantial evidence that the
    passage of the [Chloride TMDL order] deadline is significant new
    information that requires an update of the alternatives analysis.
    [The Alliance] presents no evidence that the [Control Board]
    waived . . . the [Chloride TMDL order] deadline, and the history
    of [case No. BS145869] suggests the [Control Board] would not
    waive it. Thus, the urgency which caused the 2013 EIR to reject
    16
    alternatives remains in place, or at least [the Alliance] has not
    shown otherwise.”
    The trial court also rejected the Alliance’s argument that
    the District failed to consider other alternatives to separation of
    the Recycled Water Project from the Chloride Compliance Project.
    It disagreed with the District’s contention that the doctrine of
    collateral estoppel barred the Alliance from pursuing this
    argument, stating that the Alliance was “not barred from
    challenging alternatives to the separation of the Chloride
    Compliance Project from the Recycled Water Project.”
    Nonetheless, the court concluded that the Alliance’s challenge
    was moot because the District had abandoned the Recycled Water
    Project.
    Finally, the trial court rejected the Alliance’s argument
    that the 2017 Recirculated EIR failed to designate a preferred
    alternative as required by CEQA. The court noted that the
    preferred alternative was the Chloride Compliance Project and
    “the [2017 Recirculated EIR] found there [were] no other feasible
    alternatives from which to choose.”
    On December 4, 2019, the trial court entered judgment.
    The Alliance timely appealed.
    III. DISCUSSION
    A.    CEQA
    CEQA “and the regulations implementing it (Cal. Code
    Regs., tit. 14, § 15000 et seq. [(CEQA Guidelines)]) embody
    California’s strong public policy of protecting the environment.
    ‘The basic purposes of CEQA are to: [¶] (1) Inform governmental
    17
    decision makers and the public about the potential, significant
    environmental effects of proposed activities. [¶] (2) Identify
    ways that environmental damage can be avoided or significantly
    reduced. [¶] (3) Prevent significant, avoidable damage to the
    environment by requiring changes in projects through the use of
    alternatives or mitigation measures when the governmental
    agency finds the changes to be feasible. [¶] (4) Disclose to the
    public the reasons why a governmental agency approved the
    project in the manner the agency chose if significant
    environmental effects are involved.’” (Tomlinson v. County of
    Alameda (2012) 
    54 Cal.4th 281
    , 285–286, fn. omitted.)
    “‘The foremost principle under CEQA is that the
    Legislature intended the act “to be interpreted in such manner as
    to afford the fullest possible protection to the environment within
    the reasonable scope of the statutory language.”’ [Citations.]
    ‘With narrow exceptions, CEQA requires an EIR whenever a
    public agency proposes to approve or to carry out a project that
    may have a significant effect on the environment. [Citations.]’
    [Citations.] The basic purpose of an EIR is to ‘provide public
    agencies and the public in general with detailed information
    about the effect [that] a proposed project is likely to have on the
    environment; to list ways in which the significant effects of such
    a project might be minimized; and to indicate alternatives to such
    a project.’ [Citations.] ‘Because the EIR must be certified or
    rejected by public officials, it is a document of accountability. If
    CEQA is scrupulously followed, the public will know the basis on
    which its responsible officials either approve or reject
    environmentally significant action, and the public, being duly
    informed, can respond accordingly to action with which it
    disagrees.’ [Citation.] The EIR ‘protects not only the
    18
    environment but also informed self-government.’” (Sierra Club v.
    County of Fresno (2018) 
    6 Cal.5th 502
    , 511–512, fn. omitted
    (Sierra Club).)
    “The standard of review in a CEQA case, as provided in
    sections 21168.5 and 21005, is abuse of discretion. . . . ‘[A]n
    agency may abuse its discretion under CEQA either by failing to
    proceed in the manner CEQA provides or by reaching factual
    conclusions unsupported by substantial evidence. [Citation.]
    Judicial review of these two types of error differs significantly:
    While we determine de novo whether the agency has employed
    the correct procedures, “scrupulously enforc[ing] all legislatively
    mandated CEQA requirements” [citation], we accord greater
    deference to the agency’s substantive factual conclusions. In
    reviewing for substantial evidence, the reviewing court “may not
    set aside an agency’s approval of an EIR on the ground that an
    opposite conclusion would have been equally or more reasonable,”
    for, on factual questions, our task “is not to weigh conflicting
    evidence and determine who has the better argument.”
    [Citation.]’ [Citation.]” (Sierra Club, supra, 6 Cal.5th at p. 512.)
    “‘Where an EIR is challenged as being legally inadequate, a
    court presumes a public agency’s decision to certify the EIR is
    correct, thereby imposing on a party challenging it the burden of
    establishing otherwise.’” (San Franciscans for Livable
    Neighborhoods v. City and County of San Francisco (2018) 
    26 Cal.App.5th 596
    , 613.)
    B.    Cumulative Impact Analysis
    The Alliance contends the trial court erred by finding that
    no cumulative impacts study on the stickleback was necessary for
    19
    the 2017 Recirculated EIR. “[S]ection 21083, subdivision (b),
    provides that the CEQA guidelines . . . should address a situation
    in which ‘[t]he possible effects of a project are individually limited
    but cumulatively considerable. As used in this paragraph,
    “cumulatively considerable” means that the incremental effects of
    an individual project are considerable when viewed in connection
    with the effects of past projects, the effects of other current
    projects, and the effects of probable future projects.’ ([] § 21083,
    subd. (b)(2),italics [removed].)” (Environmental Protection
    Information Center v. California Dept. of Forestry & Fire
    Protection (2008) 
    44 Cal.4th 459
    , 523.)
    Although the Alliance contends that the trial court
    “misconstrued” CEQA Guidelines section 15130, subdivision
    (a)(1), and asserts the error requires de novo review on appeal, at
    bottom, it challenges the court’s factual finding that “[s]ince the
    Chloride Compliance Project will not reduce water flow in the
    River, there are no cumulative impacts to resolve.” According to
    the Alliance, “[t]he record before the Court is otherwise”; and, it
    cites in support the notice of preparation from the 2016 Recycled
    Water SEIR, in which the District stated that “‘[t]he production
    and disposal of brine produced at Valencia [water reclamation
    plant] would reduce discharge to the [River].’” A notice of
    preparation, however, is not a factual finding. Rather, it is the
    means by which the lead agency provides notice to “all
    responsible agencies and the state Office of Planning and
    Research. These agencies then have 30 days to specify the scope
    and content of information to be included. ([] § 21080.4; [CEQA
    Guidelines], § 15082.) With this input, the lead agency prepares
    a draft EIR ([] § 21100) and circulates it for public review and
    comment ([] § 21091; [CEQA Guidelines], § 15087).” (Tuolumne
    20
    Jobs & Small Business Alliance v. Superior Court (2014) 
    59 Cal.4th 1029
    , 1038.) The factual finding by the District, as set
    forth in the 2017 Recirculated EIR, is that the Chloride
    Compliance Project would not reduce the quantity of wastewater
    discharge into the River and thus would not impact any special
    status species. Specifically, the District found that: “The
    separation of the Recycled Water Project from the Chloride
    Compliance Project would eliminate the potential diversion of
    approximately 5 [million gallons per day] from the [Valencia
    water reclamation plant] discharge to the [River]. The combined
    discharge from the [Valencia and Saugus water reclamation
    plants] would remain essentially at the current rate of 18 [million
    gallons per day]. As a result, the Chloride Compliance Project
    would not impact any special-status species or their habitat
    within the [River] because the discharge conditions would be
    essentially the same as current conditions.” When, as here,
    substantial evidence supports the District’s conclusions, we defer
    to the agency’s factual findings. (Sierra Club, supra, 6 Cal.5th at
    p. 512.)
    We next consider the Alliance’s related argument that the
    District was nonetheless required to conduct a cumulative impact
    study because the Recycled Water Project was “a reasonably
    foreseeable” future project. (Laurel Heights Improvement Assn. v.
    Regents of University of California (1988) 
    47 Cal.3d 376
    , 396.)
    “[M]ere awareness of proposed expansion plans or other proposed
    development does not necessarily require the inclusion of those
    proposed projects in the EIR. Rather, these proposed projects
    must become ‘probable future projects.’ (CEQA Guidelines,
    § 15130(b)(1)(A).)” (Gray v. County of Madera (2008) 
    167 Cal.App.4th 1099
    , 1127 (Gray).) “‘[P]robable future projects’ can
    21
    be interpreted as reasonably probable future projects. . . .
    [P]rojects that are undergoing environmental review are
    reasonably probable future projects. [Citation.] We conclude
    that any future project where the applicant has devoted
    significant time and financial resources to prepare for any
    regulatory review should be considered as probable future
    projects for the purposes of cumulative impact.” (Gray, supra,
    167 Cal.App.4th at pp. 1127–1128.)
    In support of its contention that the Recycled Water Project
    was reasonably foreseeable, the Alliance cites to the District’s
    statement that it “anticipates that [the Water Agency] will take
    primary responsibility for watershed management planning,
    including consideration, planning and implementation of any
    recycled water reuse opportunities, and that to the extent [the
    Water Agency] decides to proceed with any projects, [the Water
    Agency] will act as lead agency in any such efforts.” We disagree
    with the Alliance’s characterization of this statement. At best, it
    reflects that the Water Agency would be the lead agency on any
    future project involving recycled water reuse if the Water Agency
    decided to proceed with such a project. The statement does not,
    on its own, render the Recycled Water Project reasonably
    foreseeable. Nor does the record demonstrate that the Recycled
    Water Project has undergone any environmental review by the
    Water Agency; or that the Water Agency will proceed with the
    Recycled Water Project as currently defined, that is, by diverting
    treated wastewater produced from the Chloride Compliance
    Project toward the local communities. On this record, whether
    the Recycled Water Project will proceed is speculative, and CEQA
    does not require a cumulative impacts analysis. (Gray, supra,
    167 Cal.App.4th at pp. 1127–1128.)
    22
    C.    Piecemealing
    The Alliance also argues that the District conducted an
    improper piecemealing of the Project. “‘CEQA broadly defines a
    “project” as “an activity which may cause either a direct physical
    change in the environment, or a reasonably foreseeable indirect
    physical change in the environment, and . . . [¶] . . . [¶] . . . that
    involves the issuance to a person of a lease, permit, license,
    certificate, or other entitlement for use by one or more public
    agencies.” [Citation.] [¶] The statutory definition is augmented
    by the [CEQA] Guidelines . . . , which define a “project” as “the
    whole of an action, which has a potential for resulting in either a
    direct physical change in the environment, or a reasonably
    foreseeable indirect physical change in the environment . . . .”’
    [Citation.]” (Banning Ranch Conservancy v. City of Newport
    Beach (2012) 
    211 Cal.App.4th 1209
    , 1220 (Banning Ranch).)
    “Accordingly, ‘CEQA forbids “piecemeal” review of the significant
    environmental impacts of a project.’ [Citation.] Agencies cannot
    allow ‘environmental considerations [to] become submerged by
    chopping a large project into many little ones—each with a
    minimal potential impact on the environment—which
    cumulatively may have disastrous consequences.’ [Citation.]”
    (Id. at p. 1222.)
    We agree with the trial court that any argument of
    piecemealing related to the Recycled Water Project has been
    rendered moot by the District’s decision not to proceed with the
    Recycled Water Project. “‘California courts will decide only
    justiciable controversies. [Citations.] The concept of
    justiciability is a tenet of common law jurisprudence and
    23
    embodies “[t]he principle that courts will not entertain an action
    which is not founded on an actual controversy . . . .” [Citations.]
    Justiciability thus “involves the intertwined criteria of ripeness
    and standing. A controversy is ‘ripe’ when it has reached, but has
    not passed, the point that the facts have sufficiently congealed to
    permit an intelligent and useful decision to be made.” [Citation.]
    But “ripeness is not a static state” [citation], and a case that
    presents a true controversy at its inception becomes moot “‘if
    before decision it has, through act of the parties or other cause,
    occurring after the commencement of the action, lost that
    essential character’” [citation].’ [Citation.] Stated differently,
    moot cases ‘are “[t]hose in which an actual controversy did exist
    but, by the passage of time or a change in circumstances, ceased
    to exist.” [Citation.]’ [Citation.]” (Parkford Owners for a Better
    Community v. County of Placer (2020) 
    54 Cal.App.5th 714
    , 722.)
    We review a finding of mootness de novo. (Wilson & Wilson v.
    City Council of Redwood City (2011) 
    191 Cal.App.4th 1559
    , 1582.)
    As discussed, piecemealing violates CEQA because it has
    the potential to disguise the cumulative impact of a project by
    chopping it into smaller projects. (Banning Ranch, supra, 211
    Cal.App.4th at p. 1222.) However, if one of those smaller projects
    has been rejected from the project as a whole, the question of
    piecemealing becomes moot. (See § 21080, subd. (b)(5) [“This
    division [referring to CEQA] does not apply to any of the
    following activities: [¶] . . . [¶] Projects which a public agency
    rejects or disapproves”].) Here, there is no longer an actual
    controversy that the Recycled Water Project will have a
    cumulative impact with the Chloride Compliance Project because
    the two components will proceed independently of each other
    24
    (and, in the case of the Recycled Water Project, may not proceed
    at all). Thus, the question of piecemealing is moot.
    Even if we were to consider the merits of the Alliance’s
    argument, we find no piecemealing. We independently determine
    whether improper piecemealing is occurring. (Banning Ranch,
    supra, 211 Cal.App.4th at p. 1224.)
    As described in Banning Ranch, supra, 
    211 Cal.App.4th 1209
    , there are two lines of cases where courts have found
    improper piecemealing: “First, there may be improper
    piecemealing when the purpose of the reviewed project is to be
    the first step toward future development. . . . [¶] And there may
    be improper piecemealing when the reviewed project legally
    compels or practically presumes completion of another action.”
    (Id. at p. 1223.) “On the other hand, two projects may properly
    undergo separate environmental review (i.e., no piecemealing)
    when the projects have different proponents, serve different
    purposes, or can be implemented independently.” (Ibid.)
    On this record, we find that the District did not engage in
    piecemealing. The two objectives of the Chloride Compliance
    Project as stated in the 2017 Recirculated EIR are compliance
    with the Chloride TMDL order and use of an existing industrial
    facility to dispose of the resulting brine. Under the Chloride
    Compliance Project, the District will discharge the treated
    wastewater produced from the Chloride Compliance Project into
    the River. The Recycled Water Project, by contrast, would
    increase the distribution of recycled water for use by local
    municipalities by diverting the treated wastewater that would
    have otherwise been discharged into the River. In other words,
    the Recycled Water Project involves the end-product of the
    Chloride Compliance Project. Accordingly, the Recycled Water
    25
    Project is not necessary for the Chloride Compliance Project to
    proceed as stated in the 2017 Recirculated EIR. Thus, the
    Chloride Compliance Project can be implemented without the
    Recycled Water Project.
    D.    Project Alternatives
    Finally, we consider the Alliance’s argument that the trial
    court erred by purportedly finding that its challenges to the
    alternatives analysis in the 2017 Recirculated EIR were subject
    to collateral estoppel. Our review of the record demonstrates
    that the court did not reject the Alliance’s alternatives argument
    on collateral estoppel grounds. The Alliance raised three
    arguments regarding project alternatives below. Specifically, it
    argued that: (1) the 2013 EIR’s project alternative analysis was
    “outdated” because the deadline for complying with the Chloride
    TMDL order was extended and the 2013 EIR’s analysis therefore
    required updating; (2) the 2017 Recirculated EIR failed to
    analyze reasonable alternatives to separation of the Recycled
    Water Project from the Chloride Compliance Project; and (3) the
    2017 Recirculated EIR failed to identify the preferred project
    alternative. On appeal, the Alliance does not challenge the trial
    court’s rulings on its first and third arguments. And, contrary to
    the Alliance’s contention, the court expressly found that the
    doctrine of collateral estoppel did not bar the Alliance from
    “challenging alternatives to the separation of the Chloride
    Compliance Project from the Recycled Water Project.” The court
    instead rejected the Alliance’s argument on mootness grounds.
    The Alliance has failed to raise any challenge to the court’s
    mootness ruling and has therefore forfeited any argument on
    26
    appeal. (See Golden Door Properties, LLC v. County of San Diego
    (2020) 
    50 Cal.App.5th 467
    , 555 [“And even in a CEQA case, ‘“[t]he
    most fundamental rule of appellate review is that an appealed
    judgment or order is presumed to be correct.” [Citation.] It is the
    appellant who bears the burden of overcoming that
    presumption’”].)7
    7      To the extent the Alliance argues that the doctrine of
    collateral estoppel did not bar it from challenging the District’s
    failure to consider alternatives to the Chloride Compliance
    Project, that is, alternatives to removing chloride from the
    treated wastewater, it did not make any such challenge in the
    trial court. “We do not consider new matters raised for the first
    time on appeal.” (Citizens Opposing a Dangerous Environment v.
    County of Kern (2014) 
    228 Cal.App.4th 360
    , 380, fn. 16.)
    27
    IV. DISPOSITION
    The judgment denying the Affordable Clean Water
    Alliance’s petition for writ of mandate is affirmed. The Santa
    Clarita Valley Sanitation District of Los Angeles County is
    entitled to costs on appeal.
    NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS
    KIM, J.
    We concur:
    BAKER, Acting P. J.
    MOOR, J.
    28
    

Document Info

Docket Number: B303831M

Filed Date: 2/16/2022

Precedential Status: Non-Precedential

Modified Date: 2/16/2022