Jefferson Street Ventures v. City of Indio , 236 Cal. App. 4th 1175 ( 2015 )


Menu:
  • Filed 4/21/15; pub. order 5/15/15 (see end of opn.)
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    FOURTH APPELLATE DISTRICT
    DIVISION THREE
    JEFFERSON STREET VENTURES, LLC,
    Plaintiff and Appellant,                            G049899
    v.                                             (Super. Ct. No. INC072101)
    CITY OF INDIO,                                          OPINION
    Defendant and Respondent.
    Appeal from a judgment of the Superior Court of Riverside County, John
    G. Evans, Judge. Reversed and remanded with directions.
    Manatt, Phelps & Phillips and Michael M. Berger for Plaintiff and
    Appellant.
    Richards, Watson & Gershon,
    Gregory M. Kunert and Saskia T. Asamura for Defendant and Respondent.
    Jefferson Street Ventures, LLC (Jefferson), appeals from a judgment in
    favor of the City of Indio (the City) in this combined petition for writ of administrative
    mandamus/inverse condemnation action. In 2007, the City conditioned approval of
    Jefferson’s 2005 application for development of a shopping center upon Jefferson leaving
    approximately one-third of its property undeveloped to accommodate the reconstruction
    of a major freeway interchange that was in the planning stages. The City intended to
    eventually acquire the development-restricted property through either eminent domain or
    negotiated purchase. But it could not acquire the property at the time Jefferson’s
    development application was approved due to funding constraints imposed by the
    byzantine planning and review process for the interchange that involved various local,
    state, and federal agencies, and which the City did not anticipate being complete for at
    least a few more years—as it turned out it was almost seven. When Jefferson’s
    development application was being approved, City staff explained the City could not
    allow development on the part of the site designated for the interchange because the City
    would incur additional costs for the property if and when it was later taken for the
    interchange.
    Jefferson sued the City contending the development restrictions were
    invalid because they constituted an uncompensated taking of its property. Following a
    hearing on the writ petition, the trial court found the development restrictions were
    permissible and denied the writ. Although the court originally declined to consider
    whether the facially valid development restrictions nonetheless amounted to an
    uncompensated taking, it subsequently granted the City’s motion for judgment on the
    pleadings on the inverse condemnation causes of action agreeing the ruling on the writ
    petition included a finding there was no compensable taking.
    On appeal, Jefferson contends: (1) the trial court erred by denying its
    petition for writ of administrative mandate because the City’s development restrictions
    constituted an uncompensated taking; and (2) regardless of the ruling on the mandamus
    2
    cause of action, the trial court erred by denying it a trial on its inverse condemnation
    claims. We agree with the former contention and conclude the restrictions constituted a
    de facto taking of the development restricted portion of Jefferson’s property and the trial
    court erred by denying Jefferson’s petition for writ of mandate.
    In Hensler v. City of Glendale (1994) 
    8 Cal. 4th 1
    , 7 (Hensler), our Supreme
    Court held a landowner alleging government action constitutes an uncompensated taking
    must first challenge the action by way of a writ of mandate so as to “afford the local
    entity the opportunity to rescind its action rather than pay compensation for a taking.” In
    this case, however, that option appears to now be foreclosed. While this appeal has been
    pending, responsibility for rights-of-way acquisition for the interchange project has been
    transferred to the County of Riverside (the County), and in February 2014, the County
    commenced a direct condemnation action to acquire the requisite portions of Jefferson’s
    property for construction of the interchange. The direct condemnation action will
    encompass many, if not all, of the damage claims Jefferson asserts against the City in this
    action. However, we cannot conclude this action is moot because the direct
    condemnation action has not proceeded to trial or final judgment. Accordingly, although
    we reverse and remand for further proceedings, we also direct the trial court to consider
    consolidation of this action with the direct condemnation action so as to avoid duplication
    of damages.
    FACTS & PROCEDURE
    The I-10/Jefferson Street Interchange Project
    Jefferson is the owner of a vacant 26.85-acre parcel of land located in the
    City (the Property). The Property is bounded by the I-10 freeway to the south,
    Jefferson Street to the west, and Varner Road, which curves around the property’s
    northern perimeter from Jefferson Street tapering down to the I-10 and then running
    parallel to the I-10 freeway. The Property is surrounded by mostly vacant land.
    3
    The I-10/Jefferson Street interchange was one of several I-10 interchanges
    in the Coachella Valley slated for reconstruction and enlargement to accommodate
    increasing population growth and development in the area. The reconstruction of the
    I-10/Jefferson Street interchange will require acquisition of rights-of-way including a
    portion of Jefferson’s property.
    Since the late 1990’s, numerous governmental agencies have been involved
    in studying, planning, and funding the I-10 interchange projects including the Federal
    Highway Administration (FHWA), the State of California, Department of Transportation
    (Caltrans), the County, the Coachella Valley Association of Governments, and the City.
    The City was originally designated as the responsible agency for the I-10/Jefferson Street
    interchange (hereafter the Interchange Project). Preparation of the requisite
    environmental studies for the Interchange Project began in 2001. Those studies had to
    meet requirements of both the National Environmental Policy Act of 1969 (NEPA,
    42 U.S.C. § 4321 et seq.; 49 C.F.R. §§ 1105.6, 1105.7), and the California Environmental
    Quality Act (CEQA, Pub. Resources Code, § 21000, et seq.; Cal. Code Regs., tit. 23,
    § 3775, et seq.). Acquisition of rights-of-way for the Interchange Project could not begin
    until all environmental review was complete and approved. As the City’s public works
    director explained to the city council in March 2007, the average time for a NEPA
    document on an interstate highway interchange project to wend its way through all the
    requisite federal and state agencies was about seven years. And as the City’s community
    development director explained in August 2007, state and federal funds could not be
    released until environmental review was complete and the City had no control over the
    federal environmental review process.
    There were three potential configurations for the Interchange Project
    identified by Caltrans—Alternatives 1, 2, and 3. Although some environmental studies
    were pointing to Alternative 1 as early as 2003, by November 2005, the City’s staff was
    designating Alternative 3 as the preferred configuration. However, as will be explained
    4
    anon, in 2007, the city council selected Alternative 1 as its preferred Interchange Project
    configuration.
    Jefferson’s Project
    At some point, Jefferson acquired the Property. In 2004, Jefferson began
    consulting with City staff on its development plans for the Property and on July 27, 2005,
    Jefferson submitted a proposal to the City for development of a retail shopping center on
    the entire 26.85-acre parcel.
    Jefferson’s development proposal, Project Master Plan No. 05-01-38
    (hereafter the PMP), was for about 20 buildings with a combined total square footage of
    248,600. It placed the largest buildings, including the proposed supermarket “anchor
    tenant,” along the I-10 perimeter of the Property facing towards Varner Road.
    A triangular area at the southeast end of the Property (where Varner Road tapers towards
    I-10 and then runs parallel to it) was not designated for buildings but as a drainage
    retention basin. The PMP contained an appendix addressing the proposed Alternative 3
    configuration for the Interchange Project, which would require acquisition of
    approximately 15 acres of the Property by the City, including the area most desirable for
    a supermarket.
    The City’s planning commission’s first public hearing on Jefferson’s
    project was set for May 10, 2006. City staff reported that although the original PMP was
    for the entire 26.85-acre site, Jefferson had revised its proposal in light of the Interchange
    Project and the City’s preference for Alternative 3, and the revised site plan and proposal
    was for 17.50 acres with 156,650 combined square feet of buildings. City staff
    recommended approval noting the PMP was consistent with the City’s general and
    specific plans and zoning ordinances. Staff recommended adoption of a mitigated
    negative declaration for the project under CEQA. However, before the planning
    commission meeting, Jefferson informed City staff it would not revise the PMP and
    wanted approval for the 26.85-acre project as submitted. The planning commission
    5
    hearing was continued numerous times while City staff and Jefferson worked through
    various issues.
    At the January 10, 2007, planning commission hearing, City staff explained
    various governmental agencies were still trying to agree on the Interchange Project
    alignment that worked for all the parties and by this time Jefferson was expressing a
    preference for Alternative 1 as the least damaging to its project. The City’s community
    development director and the planning commissioners lamented that Jefferson was caught
    up in a lengthy process involving numerous state and federal agencies, with
    environmental problems and other issues concerning the Interchange Project that still
    were not resolved. The city attorney reported the City had just recently received a letter
    from Caltrans on behalf of FHWA advising the City that NEPA environmental work had
    to be completed before the City could move forward on the Interchange Project. The
    public hearing on the PMP was continued to February 14, 2007, and then to March 14,
    2007.
    On March 7, 2007, the city council held a noticed public hearing to
    consider staff’s recommendation to approve Alternative 1 for the Interchange Project as
    the City’s preferred configuration. The city manager explained the I-10 interchanges had
    been funded and defunded due to budget problems and urged a decision be made
    immediately as to the preferred alternative so funding was not lost again. The draft
    environmental impact report still had to be circulated to the public and reviewed by
    FHWA, the Federal Transportation Administration (FTA) and at least 15 other
    agencies—a process staff hoped might be completed in another two and one-half years.
    Additionally, Caltrans would have to approve the locally preferred alternative.
    Jefferson’s principal, Charles Ellis, advised the city council that Alternative
    1 was the least onerous for its project and urged the city council to approve Alternative 1.
    The City approved Alternative 1 for the Interchange Project, and authorized staff to
    6
    solicit proposals to complete construction drawings for the interchange based on
    Alternative 1.
    On March 14, 2007, the planning commission held its final hearing on the
    PMP. The staff report explained the City had approved Alternative 1 for the
    Interchange Project, which reduced the developable area of Jefferson’s property to
    approximately 17.1 acres. Therefore, there must be a condition to approval of the PMP
    that before building permits were issued, Jefferson must submit a revised plan providing
    for the building envelope for the development to be revised to accommodate the
    Alternative 1 configuration for the Interchange Project. There was some discussion
    during the meeting during which Jefferson’s project planner explained about how the
    project might be revised to fit a 17-acre site. Ellis indicated Jefferson was “reluctantly”
    modifying its PMP (i.e., to accommodate the Alternative 1 alignment for the Interchange
    Project), with the understanding the City would be paying Jefferson just compensation
    for the property being taken for the Interchange Project. The planning commission
    adopted a proposed resolution recommending the city council approve the PMP subject to
    staff’s recommended conditions.
    On July 18, 2007, the city council held its first hearing on the PMP. The
    community development director explained the approval would allow Jefferson to
    proceed immediately with development of a 17-acre project, on a site with an as yet
    unknown configuration, and if the Interchange Project did not eventually get funded (and
    built), Jefferson could come back and build out the rest of the Property.
    Ellis advised the city council that Jefferson did not agree to approval of
    only a 17-acre project. He reiterated that Jefferson’s project had been in the planning
    process since August 2004 and it had submitted the PMP to the City for approval in
    January 2005. It was still not clear to him the City would in fact ever condemn the
    nine acres the City wanted removed from the proposed development (hereafter referred to
    as the Alternative 1 Acreage). Ellis stated he understood the quandary the City was in—
    7
    by declaring the Alternative 1 Acreage unbuildable it was effectively taking Jefferson’s
    property now, but the City had to rely on third parties to pay for that taking and it was
    unknown if and when that would happen. Accordingly, Ellis stated Jefferson did not
    agree with the staff recommendation to approve only a 17-acre project and it was asking
    for immediate approval of the full 26.85-acre development described by the PMP.
    The community development director again explained the City intended to
    implement the Interchange Project as quickly as possible, but it would not approve
    construction in the proposed rights-of-way only to then have to demolish the buildings
    and relocate tenants in the future. By conditioning approval as proposed, Jefferson could
    still come back and build out the entirety of the Property if the Interchange Project did
    not get funded or built. The community development director reiterated that Jefferson
    would be compensated at fair market value for any land acquired for the Interchange
    Project at such time as rights-of-way were acquired.
    Ellis reiterated Jefferson wanted an “unequivocal commitment” from the
    City that if only a 17-acre project was approved now, the City would compensate it for
    the Alternative 1 Acreage. Ellis explained it was not commercially reasonable to build
    out a 17-acre project and then at some time in the future come back and try to develop the
    remaining acreage that would be “locked in the rear” (between the 17 acres approved for
    construction and the freeway) if the Interchange Project was never built. The community
    development director explained the City could not give commitments beyond the
    assurances staff had already given—the City could not commit to buying the property if
    in fact the Interchange Project was never built. The hearing was continued to August 15,
    2007.
    On August 15, 2007, City staff continued to recommend approval of the
    PMP with the condition it be revised to exclude the Alternative 1 Acreage and a two-acre
    temporary no-build area for construction of the Interchange Project. Jefferson continued
    to assert its position that it wanted approval of the PMP for the entire 26.85-acre parcel
    8
    and a guarantee of just compensation for “a fully entitled site.” City staff again explained
    that if Jefferson was allowed to develop the entire site prior to construction of the
    Interchange Project, the City would incur additional condemnation costs for demolition
    of buildings and relocation of tenants. Staff again observed the environmental clearances
    for the Interchange Project had not been completed and the property could not be
    acquired until environmental clearance was obtained. The community development
    director and the city manager both reiterated the City had every intention of proceeding
    with the Interchange Project, but it was stuck in the federal approval process. The
    city attorney confirmed the City was committed to paying just compensation for any
    eventual taking of Jefferson’s property for the Interchange Project. But he also noted
    there was “so much uncertainty with . . . respect to the interchange . . . .” The city
    attorney observed that until the federal and state environmental analysis were completed,
    the City would not know “where the landscape lay” and thus there simply was not
    enough information to pay Jefferson for any property taken. After an unidentified
    speaker at the hearing commented that even though Alternative 1 had been selected as the
    preferred configuration, that did not mean Caltrans or federal authorities would agree
    with that decision; council members agreed with that assessment. One council member
    explained, the City was 95 percent certain Alternative 1 would be the alignment, so by
    prohibiting building in the Alternative 1 envelope, the City was trying to carve out the
    area that would realistically be available for development. And even if the City was
    “slightly wrong” about the exact property that would be taken for the Interchange Project
    most of the Alternative 1 Acreage would get purchased at some point in the future.
    At the conclusion of the hearing, the city council approved
    Ordinance No. 1151, and adopted a mitigated negative declaration, approving the PMP.
    The ordinance contained two factual findings in support of approval of the PMP: (1) The
    PMP was consistent with the goals and policies of the City’s general plan; and (2) The
    PMP was consistent with the City’s zoning ordinances and met the requirements of the
    9
    specific plan for the area. The ordinance made approval of the PMP subject to various
    conditions including the following: condition No. 6, “Prior to the issuance of any
    building permits, five corrected copies of the [PMP] shall be submitted to the [City’s
    community development director] for review, approval, and filing as the final document
    for the project, and shall include a revised plan [that] shall provide for a building
    envelope as permitted for the site under the provisions of the Jefferson Street Interchange
    Alternative 1[;]” and condition No. 10, “An approximate 2.1 acre ‘Temporary No-Build
    Area’ shall be reserved in the southeastern portion [i.e., the triangular area the PMP
    designates as a drainage retention basin] of the site to the satisfaction of the [p]ublic
    [w]orks [d]irector which shall prohibit construction in this area until completion of
    the . . . Interchange Project. Upon completion of the interchange project this area may be
    developed.”
    The Current Litigation
    Jefferson did not revise its PMP or seek building permits for its project. It
    filed the instant action, a combined petition for writ of mandate and complaint for
    damages for inverse condemnation, on November 7, 2007. The complaint alleged the
    City had improperly conditioned approval of the PMP upon Jefferson’s leaving the
    Alternative 1 Acreage undeveloped, plus a temporary no build area of two acres for a
    temporary off-ramp (hereafter the Temporary No-Build Area), to accommodate the
    proposed Interchange Project without paying Jefferson just compensation.
    The first cause of action for a writ of mandate under Code of Civil
    Procedure sections 1094.5 and 1085, alleged the findings made on August 15, 2007 (i.e.,
    that the PMP was consistent with the City’s general plan, specific plan, and zoning
    ordinances), supported approval of the PMP as originally submitted. Therefore, Jefferson
    alleged the City had no authority to condition approval of the PMP on leaving any
    portion of the Property undeveloped. The complaint’s inverse condemnation causes of
    action contained allegations of a regulatory taking and a forced dedication of private
    10
    property bearing no nexus to the impact of the proposed project; unreasonable pre-taking
    conduct and unreasonable delay; severance damage to the remainder of Jefferson’s
    property; and unlawful development conditions. In its prayer for relief, Jefferson sought
    issuance of a peremptory writ of mandate commanding the City to approve the PMP as
    submitted, i.e., for the development of the full 26.85 acres. In the event a writ was not
    issued, Jefferson sought just compensation for a taking of its property, damages for the
    City’s unreasonable precondemnation delay and conduct, plus costs and attorney fees.
    The trial court stayed the inverse condemnation causes of action until the mandamus
    cause of action was tried
    Jefferson filed its opening brief on the writ of mandate in April 2009. It
    raised two issues. First, it contended that by conditioning approval of the PMP upon
    leaving the Alternative 1 Acreage undeveloped to accommodate the Interchange Project
    plus the two-acre Temporary No-Build Area, the City was illegally regulating land use to
    depress land value for future acquisition. In making this argument, Jefferson cited to
    statements made by City staff cautioning against allowing Jefferson to build in the
    proposed rights-of-way area because it could result in the City incurring costs relating to
    demolition of those buildings and tenant relocation if and when that property was
    condemned. Jefferson also argued the conditions constituted an unlawful exaction/forced
    dedication of its property.
    Following a hearing on the petition for writ of administrative mandamus,
    the trial court issued its statement of decision denying the writ. The court found there
    was no evidence the City acted in excess of its jurisdiction because its police power
    necessarily included the authority to plan for major infrastructure improvements and
    there was no evidence Jefferson was denied a fair hearing. Turning to the specific
    arguments Jefferson made, the trial court found the record did not support a finding the
    City was acting so as to depress the value of property to be taken, or to coerce Jefferson
    into accepting a particular price for its property if it was ever condemned. There was no
    11
    change in the zoning and “[a]ll that can be said is that the City restricted [Jefferson’s]
    right to build on a portion of its property until such time as the proposed interchange
    plans were accepted or rejected.” The court specifically stated it was not deciding in the
    mandamus proceeding whether the development restrictions effected a compensable
    taking or were an unlawful exaction observing “whether or not the City requires you to
    keep that land fallow, that you’re entitled to compensation, that’s not before me.
    [¶] . . . [¶] [T]hat issue is not one I’m deciding. I’m not making that decision based on
    your writ.” The trial court entered a judgment on the mandamus cause of action on
    June 30, 2009, but later clarified it was an interlocutory judgment only.
    On August 16, 2011, the City filed a motion for judgment on the pleadings
    under Code of Civil Procedure section 438 as to the remaining inverse condemnation
    causes of action. The City argued the trial court’s ruling denying the writ of mandate
    barred Jefferson’s takings claims. Jefferson opposed the motion noting the trial court
    specifically did not decide the takings issue, and it was entitled to present substantive
    argument and evidence on its takings claim.
    The trial court initially denied the City’s motion for judgment on the
    pleadings, stating that in deciding the mandamus cause of action it had not considered
    whether the restrictions on development resulted in a taking. It set the matter for further
    briefing “on the limited issue of whether Jefferson[’s] writ encompassed the [takings
    claim] . . . and how the court should proceed from this point.” Following receipt of the
    supplemental briefing, the trial court vacated its prior order denying the motion for
    judgment on the pleadings and entered a new order granting the motion for judgment on
    the pleadings. The trial court stated in its minute order that its ruling in the City’s favor
    on the administrative mandamus cause of action constituted a finding the City’s actions
    did not constitute a taking, and therefore Jefferson’s inverse condemnation causes of
    action were meritless “[on] their face.”
    12
    Judgment was entered on January 12, 2012, in favor of the City, and
    Jefferson filed a notice of appeal.
    REQUESTS FOR JUDICIAL NOTICE/POSTJUDGMENT EVENTS
    The City’s First Request for Judicial Notice
    On February 28, 2013, the City filed its first request for judicial notice,
    which we deferred for decision with the merits of the appeal. The City requested we take
    judicial notice of the administrative record submitted to the trial court on May 5, 2009, in
    advance of the trial on the petition for writ of mandate. (Evid. Code, §§ 452, 459.)
    Jefferson agrees we should take judicial notice of the administrative record, and we grant
    that request.
    The City also requested we take judicial notice of a city council agenda
    report dated October 20, 2009, that was not part of the administrative record and
    post-dates the trial court’s ruling denying the petition for writ of mandate, but which
    provides some pertinent background concerning the history of the Interchange Project.
    Jefferson opposes the request. We deny the request for judicial notice of the October 20,
    2009, city council agenda report as this document was not part of the administrative
    record. (See Architectural Heritage Assn. v. County of Monterey (2004) 
    122 Cal. App. 4th 1095
    , 1112 (Architectural Heritage Assn.) [appellate court would not consider extra-
    administrative record evidence].)
    The City’s Second Request for Judicial Notice
    On September 17, 2014, this court granted the City’s unopposed second
    request for judicial notice filed August 14, 2014, of public documents regarding events
    concerning the Property that have transpired since the trial court entered judgment in this
    case. We took judicial notice of the December 28, 2011, “Cooperative Agreement”
    between the City, Caltrans, and the County concerning the Interchange Project, which is a
    public record. Pursuant to the Cooperative Agreement, the County has become the
    responsible agency for construction of the Interchange Project and has assumed all
    13
    responsibility for acquisition of rights-of-way for the project “including all eminent
    domain activities.”
    We also took judicial notice of the February 11, 2014, eminent domain
    complaint filed by the County against Jefferson, and various entities owning utility and
    roadway easements on the Property, to acquire the necessary rights-of-way for the
    Interchange Project. (County of Riverside v. Jefferson Street Ventures, LLC et al.
    (Riverside County Super. Ct., Case No. PSC1400798, hereafter the County
    Condemnation Action.) The legal description of the property to be condemned includes
    the fee simple interest in a 6.277-acre parcel (which the City states is within the footprint
    of the Alternative 1 alignment for the Interchange Project), a .093-acre road easement, a
    .152-acre slope easement, and a 3.457-acre temporary construction easement.
    In a stipulation filed with this court on April 18, 2014, Jefferson agreed it
    has not challenged the County’s right to take the land that is the subject of the County
    Condemnation Action, and the issues pending resolution in the County Condemnation
    Action relate to just compensation for the taking. That stipulation also refers to a second
    condemnation action filed by the City concerning a small amount of property being
    acquired by the City for improvement of the Jefferson Street/Varner Road intersection.
    (City of Indio v. Jefferson Street Ventures, LLC et al. (Riverside County Super. Ct., Case
    No. PSC1400896, hereafter the City Condemnation Action.)
    The City’s Third Request for Judicial Notice
    On October 27, 2014, the City filed a third request for judicial notice of
    additional court documents, which we deferred for decision with the merits of the appeal.
    Jefferson opposes the request. The documents include Jefferson’s motion for leave to file
    a first amended answer in the County Condemnation Action filed on October 14, 2014.
    In that motion, Jefferson seeks to amend its answer to include claims for
    precondemnation damages and to clarify the basis for its claim for severance damages.
    Jefferson also states the factual basis for its claim for precondemnation damages
    14
    (damages for unreasonable precondemnation activity) are the same facts that underlie this
    writ of mandate/inverse condemnation action. The City also asks us to take judicial
    notice of Jefferson’s motion to consolidate the County Condemnation Action and the City
    Condemnation Action filed on October 16, 2014, because the two actions involve parts of
    the same subject property owned by the same defendant, the same parties, and the same
    project. The final document of which the City requests judicial notice is the substitution
    of attorneys filed by Jefferson in the County Condemnation Action on October 16, 2014,
    substituting in new counsel in the condemnation actions. We grant the City’s request for
    judicial notice of these documents because they are court records and relevant to the
    issues in this case.
    The City’s Fourth Request for Judicial Notice
    On March 6, 2015, after oral argument in this appeal was heard, but before
    the matter was taken under submission, the City filed a fourth request for judicial notice.
    It asks us to take judicial notice of a Riverside County Board of Supervisors agenda
    report dated January 26, 2015, showing County approval of the construction contract for
    the Interchange Project. Jefferson opposes the request. We deny the request for judicial
    notice of the January 26, 2015, report because it was not part of the administrative record
    (Architectural Heritage 
    Assn., supra
    , 122 Cal.App.4th at p. 1112), and we do not find it
    useful in resolving the issues before us.
    DISCUSSION
    On appeal, Jefferson contends the conditions the City imposed on approval
    of the PMP precluding development on the Alternative 1 Acreage and the Temporary
    No-Build Area constituted an unconstitutional taking, and therefore, the trial court erred
    by denying its petition for writ of administrative mandate. Additionally, Jefferson
    contends the trial court erred by denying it an evidentiary hearing on its inverse
    condemnation claims. We agree the restrictions constituted an uncompensated taking of
    the property on which development was prohibited by the City.
    15
    1. General Principles of Takings Law
    We begin with some legal background on takings jurisprudence and inverse
    condemnation. The state and federal Constitutions guarantee real property owners “just
    compensation” when their land is taken for a public use. (Cal. Const., art. I, § 19; U.S.
    Const., 5th Amend.; Lingle v. Chevron U.S.A. Inc. (2005) 
    544 U.S. 528
    , 537 (Lingle);
    Kavanau v. Santa Monica Rent Control Bd. (1997) 
    16 Cal. 4th 761
    , 773; Shaw v. County
    of Santa Cruz (2008) 
    170 Cal. App. 4th 229
    , 259 (Shaw).) This constitutional guarantee is
    “‘designed to bar [g]overnment from forcing some people alone to bear public burdens
    which, in all fairness and justice, should be borne by the public as a whole.’ [Citation.]”
    (Penn Central Transp. Co. v. New York City (1978) 
    438 U.S. 104
    , 123 (Penn Central).)
    “[A]n ‘inverse condemnation’ action may be pursued when the state or
    other public entity improperly has taken private property for public use without following
    the requisite condemnation procedures [or] takes other action that effectively circumvents
    the constitutional requirement that just compensation be paid before private property is
    taken for public use.” (Customer Co. v. City of Sacramento (1995) 
    10 Cal. 4th 368
    , 377,
    fn. omitted.)
    “‘The paradigmatic taking requiring just compensation is a direct
    government appropriation or physical invasion of private property’—a categorical
    taking.” 
    (Shaw, supra
    , 170 Cal.App.4th at p. 260.) “When property is damaged, or a
    physical invasion has taken place, an inverse condemnation action may be brought
    immediately because an irrevocable taking has already occurred.” 
    (Hensler, supra
    ,
    8 Cal.4th at p. 13; see Hurwitz v. City of Orange (2004) 
    122 Cal. App. 4th 835
    , 847-848.)
    Additionally, “‘government regulation of private property may, in some
    instances, be so onerous that its effect is tantamount to a direct appropriation or ouster—
    and . . . such “regulatory takings” may be compensable under the Fifth Amendment.’
    [Citation.] The United States Supreme Court has recognized ‘that a regulation of
    property that “goes too far” may effect a taking of that property, though its title remains
    16
    in private hands. In such a case, the property owner may bring an inverse condemnation
    action, and if it prevails, the regulatory agency must either withdraw the regulation or pay
    just compensation. [Citation.] Even if the agency withdraws the regulation, the property
    owner may have a right to just compensation for the temporary taking while the
    regulation was in effect. [Citation.]’” 
    (Shaw, supra
    , 170 Cal.App.4th at p. 260.)
    “Two categories of regulatory action will generally be deemed per se
    compensable takings. First, where government requires an owner to suffer a ‘permanent
    physical invasion’ of his property for such things as cable lines, it must provide just
    compensation. [Citations.] Second, where the government action does not result in any
    physical invasion of the property, the action will still be considered a taking if the
    regulation deprives the owner of ‘all economically beneficial or productive use of [the]
    land.’ [Citations.] ‘[T]he government must pay just compensation for such “total
    regulatory takings,” except to the extent that “background principles of nuisance and
    property law” independently restrict the owner’s intended use of the property.’
    [Citation.]” 
    (Shaw, supra
    , 170 Cal.App.4th at pp. 260-261.)
    Takings challenges outside the above per se compensable categories (those
    that do not involve a physical invasion or that leave the property owner with some
    economically beneficial use of the property), may nonetheless go “too far” and be
    compensable when the regulation substantially interferes with the ability of a property
    owner to make economically viable use of, derive income from, or satisfy reasonable,
    investment-backed profit expectations with respect to the property. 
    (Lingle, supra
    ,
    544 U.S. at pp. 538-539, citing Penn 
    Central, supra
    , 438 U.S. at p. 124.) And a
    condition imposed on a property owner for land use approval will go “too far” when there
    is no “essential nexus” between the permit condition and a legitimate state interest
    (Nollan v. California Coastal Commission (1987) 
    483 U.S. 825
    , 837 (Nollan)), or the
    17
    condition is not “roughly proportional” to the impact it seeks to address (Dolan v. City of
    Tigard (1994) 
    512 U.S. 374
    , 385 (Dolan)).1
    “A ‘temporary’ taking of real property by the government is compensable
    on the same constitutional basis as a permanent taking. For purposes of the just
    compensation provisions of the Fifth Amendment, there is no difference between a
    temporary taking that denies a landowner all use of his property, and a permanent taking.
    Temporary physical invasions should be assessed according to a case specific factual
    inquiry. Similarly, whether a temporary regulation constitutes a taking involves an ad
    hoc consideration of relevant circumstances. The duration or delay resulting from
    governmental regulations is one of the factors a court must consider in determining the
    severity of burden of a regulation. Also relevant is the degree to which the invasion is
    intended or a foreseeable result of authorized governmental action. So too are the
    character of the property at issue and the owner’s reasonable investment-backed
    expectations. The severity of the interference is also considered.” (11 Miller & Starr,
    Cal. Real Estate (3d ed. 2014) § 30:30, pp. 30-146 to 30-147, fns. omitted.)
    A landowner claiming that application of government regulations effects a
    taking of a property interest cannot sue directly on an inverse condemnation cause of
    action unless administrative and judicial remedies have been exhausted. 
    (Hensler, supra
    ,
    8 Cal.4th at pp. 13-14.) This requirement is jurisdictional and not a matter of judicial
    1             Under the Nollan/Dolan test, a public entity may require an uncompensated
    exaction, such as an easement, as a condition of a development permit only where there is
    “‘rough proportionality’” between the condition and the burden the development places
    on a public interest. 
    (Dolan, supra
    , 512 U.S. at p. 391.) Jefferson argues there was no
    rational nexus, or rough proportionality, between its proposed shopping center project
    and the expansion of the I-10/Jefferson Street interchange—the interchange expansion
    was to accommodate the regional population growth and was not necessitated by its
    shopping center. Because we conclude there was a de facto taking of the
    Alternative 1 Acreage and the Temporary No-Build Area, we need not also consider
    whether the development restriction constitutes an unlawful exaction.
    18
    discretion. (Tahoe Vista Concerned Citizens v. County of Placer (2000) 
    81 Cal. App. 4th 577
    , 589.)
    “[A] claim that the application of governmental regulations effects a taking
    of a property interest is not ripe until the government entity charged with implementing
    the regulations has reached a final decision regarding the application of the regulations to
    the property at issue.” (Williamson County Reg’l Planning Comm’n v. Hamilton Bank
    (1985) 
    473 U.S. 172
    , 186.) This is because until there has been a “final, definitive
    position” as to how the regulations will be applied to the land, a court cannot determine
    the extent of the economic impact, a factor that bears on the question whether a
    compensable taking has occurred. (Id. at p. 191.)
    Even if the administrative decision is final, the exhaustion requirement also
    affords the governmental entity the opportunity to rescind or modify the ordinance or
    regulation or to exempt the property from the allegedly invalid restriction once it has
    been judicially determined the proposed application of the regulation will constitute a
    compensable taking. 
    (Hensler, supra
    , 8 Cal.4th at p. 13.) As Hensler explains: “If the
    alleged taking is a ‘regulatory taking,’ i.e., one that results from the application of zoning
    laws or regulations which limit development of real property, . . . the owner must afford
    the state the opportunity to rescind the ordinance or regulation or to exempt the property
    from the allegedly invalid development restriction once it has been judicially determined
    that the proposed application of the ordinance to the property will constitute a
    compensable taking. The owner may do so, where appropriate, by a facial challenge to
    the ordinance, but in most cases must seek a variance if that relief is available and then
    exhaust other administrative and judicial remedies. The facial challenge may be through
    an action for declaratory relief [citation]. The latter, an ‘as applied’ challenge to the
    development restrictions imposed by the administrative agency, may be properly made in
    a petition for writ of ‘administrative’ mandamus to review the final administrative
    decision (Code Civ. Proc., § 1094.5) and that action may be joined with one for inverse
    19
    condemnation. A declaratory relief action also may be joined with an action in inverse
    condemnation. [Citation.] Damages for the ‘taking’ may be sought in an administrative
    mandamus action (Code Civ. Proc., § 1095), or, if the plaintiff seeks a jury trial, in the
    joined inverse condemnation action. [Citations.] The owner ‘may not, however, elect to
    sue in inverse condemnation and thereby transmute an excessive use of the police power
    into a lawful taking for which compensation in eminent domain must be paid.’
    [Citation.] Compensation must be paid for a permanent taking only if there has been a
    final judicial determination that application of the ordinance or regulation to the property
    is statutorily permissible and constitutes a compensable taking. Even then the state or
    local entity has the option of rescinding its action in order to avoid paying compensation
    for a permanent taking.” 
    (Hensler, supra
    , 8 Cal.4th at pp. 13-14.)
    As the Court of Appeal explained in Patrick Media Group, Inc. v.
    California Coastal Com. (1992) 
    9 Cal. App. 4th 592
    , 608 (Patrick Media), “the essential
    underpinning of the challenge is the invalidity of the administrative action. The
    gravamen of a challenge based upon inverse condemnation is that the administrative
    action was invalid insofar as it did not provide for payment of compensation. [Citation.]”
    (See also Mola Development Corp. v. City of Seal Beach (1997) 
    57 Cal. App. 4th 405
    , 414
    (Mola) [“Hensler made this point clear. The court required a ‘prepayment judicial
    determination’ that a regulation is excessive and constitutes a taking in order to give a
    city the opportunity to change its mind before being compelled to pay damages”].)
    2. Petition for Writ of Administrative Mandate
    Here, Jefferson joined its inverse condemnation causes of action with a
    petition for writ of mandate, which was ruled upon first by the trial court and denied.
    Accordingly, we consider first Jefferson’s contention the trial court erred by denying its
    petition for writ of mandamus.2
    2             For the first time on appeal, the City contends Jefferson has not exhausted
    its administrative remedies in that it cannot satisfy the ripeness requirement. The City’s
    20
    “Judicial review of most public agency decisions is obtained by a
    proceeding for a writ of ordinary [Code of Civil Procedure section 1085] or
    administrative [Code of Civil Procedure section 1094.5] mandate. [Citations.] The
    applicable type of mandate is determined by the nature of the administrative action or
    decision. [Citation.]” (McGill v. Regents of the University of California (1996)
    
    44 Cal. App. 4th 1776
    , 1785.) Typically, quasi-legislative or ministerial acts are reviewed
    by ordinary mandate, and quasi-judicial acts are reviewed by administrative mandate.
    (Ibid.)
    Although Jefferson did not specify below (or on appeal) which type of
    mandate it sought, the trial court’s statement of decision on the writ of mandate indicated
    it applied the standards for administrative mandamus. Generally “[t]he grant of a land
    use permit . . . is an adjudicatory act. A proceeding under Code of Civil Procedure
    section 1094.5 is the exclusive remedy for judicial review of the . . . administrative action
    of local level agencies in these circumstances. [Citations.]” (Saad v. City of Berkeley
    (1994) 
    24 Cal. App. 4th 1206
    , 1211.)
    argument is made in passing only and consists of three short sentences found in the
    conclusion of its response to a different argument. The City states that because Jefferson
    never submitted a site plan for a 17-acre project, it failed to obtain a final decision as to
    “‘the type and intensity of development legally permitted’” which “renders the entire
    lawsuit unripe.” The argument is devoid of any reasoned legal analysis. Although a
    jurisdictional issue, such as ripeness, may be raised for the first time on appeal (see
    Environmental Defense Project of Sierra County v. County of Sierra (2008)
    
    158 Cal. App. 4th 877
    , 885; Farm Sanctuary, Inc. v. Department of Food & Agriculture
    (1998) 
    63 Cal. App. 4th 495
    , 501, fn. 5), it is not an appellate court’s job to develop
    arguments for the parties. In view of the City’s failure to present any reasoned legal
    analysis of the point, we deem the contention waived. (See Badie v. Bank of America
    (1994) 
    67 Cal. App. 4th 779
    , 784-785 [appellant must present relevant legal authority and
    reasoned argument on each point made]; Mansell v. Board of Administration (1994) 
    30 Cal. App. 4th 539
    , 545-546 [it is not the proper function of Court of Appeal to search the
    record on behalf of appellants or to serve as “backup appellate counsel”]; Kim v.
    Sumitomo Bank (1993) 
    17 Cal. App. 4th 974
    , 979 [appellate court not required to consider
    points not supported by citation to authorities or record].)
    21
    The trial court’s inquiry in administrative mandamus “‘extend[s] to the
    questions whether the [agency] has proceeded without, or in excess of, jurisdiction;
    whether there was a fair trial; and whether there was any prejudicial abuse of discretion.’
    (Code Civ. Proc., § 1094.5, subd. (b).) Abuse of discretion is established if the [agency]
    has not proceeded in the manner required by law, the order or decision is not supported
    by the findings, or the findings are not supported by the evidence. (Code Civ. Proc.,
    § 1094.5, subd. (b).)” (Kifle-Thompson v. State Bd. of Chiropractic Examiners (2012)
    
    208 Cal. App. 4th 518
    , 523.) On appeal, we do not “undertak[e] a review of the trial
    court’s findings or conclusions. Instead, ‘we review the matter without reference to the
    trial court’s actions. In mandamus actions, the trial court and appellate court perform the
    same function. . . .’ [Citations.]” (Friends of the Old Trees v. Department of Forestry &
    Fire Protection (1997) 
    52 Cal. App. 4th 1383
    , 1393.)
    As explained above, “the essential underpinning of the challenge is the
    invalidity of the administrative action. The gravamen of a challenge based upon inverse
    condemnation is that the administrative action was invalid insofar as it did not provide
    for payment of compensation. [Citation.]” (Patrick 
    Media, supra
    , 9 Cal.App.4th at
    p. 608.)
    Jefferson contends the conditions imposed on approval of the PMP
    prohibiting indefinitely the development of the Alternative 1 Acreage and the Temporary
    No-Build Area—11 acres,3 which is over one-third of its property—to preserve that
    3               At oral argument the City suggested nine acres was the combined total of
    the Alternative 1 Acreage and the Temporary No-Build Area, but in their briefs both
    parties represent nine acres was the amount of property needed for the Alternative 1
    alignment for the Interchange Project, and the Temporary No-Build Area was an
    additional approximately two acres. Thus, for our purposes here, we will refer to the
    Alternative 1 Acreage and the Temporary No-Build Area, as having a combined total of
    approximately 11 acres. We note, however, the designated Temporary No-Build Area,
    likely had little if any practical impact on the size of Jefferson’s project as it was
    designated by Jefferson from the outset as an unbuildable drainage retention basin.
    22
    property for possible future rights-of-way for the Interchange Project was an invalid
    taking. We agree. As Jefferson points out, the PMP fully satisfied all the City’s
    requirements for development of the Property. The only findings contained in
    Ordinance No. 1151 approving the PMP were that the PMP was consistent with the
    City’s general plan, the applicable specific plan, and complied with the City’s zoning
    ordinances. There is nothing in the record suggesting Jefferson’s project caused or
    contributed to the need for the Interchange Project—as City staff consistently observed,
    the Interchange Project was needed to accommodate and promote regional growth and
    was viewed by the City “not as an interchange, but as our economic development
    opportunity, because it is a major interchange.”
    The City’s primary rationale for removing 11 acres from the otherwise
    developable site was that it planned to acquire all or some of the development-restricted
    property for construction of the Interchange Project and if development of that property
    was permitted, the City could incur additional costs for the buildings and relocation of
    tenants. Moreover, whether the Interchange Project ultimately would be built, and its
    precise location, was still not decided. As the city manager observed in 2007, the I-10
    interchanges had been funded and defunded due to state budget problems. The City
    would not have funds for rights-of-way acquisition until all state and federal
    environmental reviews were completed—a process that might be completed in a few
    years. The final configuration of the Interchange Project was not known—Caltrans might
    not accept the City’s recommendation for Alternative 1.
    “The principles which affect the parties’ rights in an inverse condemnation
    suit are the same as those in an eminent domain action. [Citations.]” (Breidert v.
    Southern Pac. Co. (1964) 
    61 Cal. 2d 659
    , 663, fn. 1.) As this court observed in Chhour v.
    Community Redevelopment Agency (1996) 
    46 Cal. App. 4th 273
    , 279-280, “‘[I]t is well
    established that condemnation and inverse condemnation are merely different forms of
    the same limitation on governmental power. [Citations.]’ [Citation.] Principles
    23
    applicable to eminent domain proceedings apply, where appropriate, to suits in inverse
    condemnation. [Citations.]” (See also People ex rel. Dept. of Transportation v.
    Diversified Properties Co. III (1993) 
    14 Cal. App. 4th 429
    , 441, fn. 3 (Diversified
    Properties) [distinction between direct condemnation and inverse condemnation of no
    significance “[i]nsofar as the constitutional mandate of just compensation is concerned].)
    Therefore, we find guidance from both direct and inverse condemnation cases.
    In a direct condemnation action, a de facto taking occurs when there was a
    “‘physical invasion or direct legal restraint’” prior to the statutory valuation date in which
    case the property is valued as of that date. (Klopping v. City of Whittier (1972) 
    8 Cal. 3d 39
    , 46 (Klopping).)4 Diversified 
    Properties, supra
    , 
    14 Cal. App. 4th 429
    , a direct
    condemnation case, considered a de facto taking claim in factual circumstances similar to
    those in this case. In Diversified Properties, a developer bought a 17.38-acre parcel in
    the City of Rancho Cucamonga intending to build a commercial shopping center on the
    property. While escrow was still open, the developer learned a three-acre portion of the
    property was designated by the state for potential freeway rights-of-way. The developer
    closed escrow after being advised by the state that if development was imminent, and
    there was confirmation from the city that but for the need to protect the state’s proposed
    rights-of way, development of the property would be approved, the state would be able to
    purchase the rights-of way. (Id. at pp. 437-438.) The developer submitted development
    4               In Klopping, the Supreme Court differentiated claims for precondemnation
    damages from claims for a de facto taking, explaining precondemnation damages result
    when a public entity engages in precondemnation conduct short of a de facto taking
    causing adverse economic impact to private property resulting from precondemnation
    delay and/or unreasonable conduct. 
    (Klopping, supra
    , 8 Cal.3d at pp. 51-52.) “[W]hen
    the condemner acts unreasonably in issuing precondemnation statements, either by
    excessively delaying eminent domain action or by other oppressive conduct, our
    constitutional concern over property rights requires that the owner be compensated. This
    requirement applies even though the activities which give rise to such damages may be
    significantly less than those which would constitute a de facto taking of the
    property. . . . ” (Ibid.)
    24
    plans to the city, which, as required by the city, excluded from the otherwise developable
    area the three-acre proposed for freeway rights-of-way plus an additional
    one and one-half acres potentially needed for a reconstruction of the freeway interchange.
    (Id. at p. 438.) Then, in April 1986, the city formally requested the state “exercise its
    protective acquisition’ authority” to purchase “the four and one-half acres ‘set aside’
    from [the developer’s] larger parcel[,]” property which otherwise would have been
    developable. (Id. at p. 439.) After a year, the state had still not initiated condemnation
    proceedings leaving the four and one-half acres undevelopable. Another year and a half
    passed before the state finally made an offer to purchase the property, which the
    developer rejected. (Id. at p. 439.) The developer filed an inverse condemnation action
    against the state, which it ultimately agreed to dismiss when the state filed its direct
    condemnation action. The trial court ruled there had been a de facto taking of the
    developer’s property by the state due to the direct interference with its right to develop its
    property. (Id. at pp. 439-440.)
    In affirming the trial court’s de facto taking ruling, the Diversified
    Properties court began with the rule that “governmental regulation of the development of
    land rises to the level of a ‘taking’ if it ‘denies an owner economically viable use of his
    land.’ [Citation.]” (Diversified 
    Properties, supra
    , 14 Cal.App.4th at p. 441, fn. omitted,
    quoting Agins v. Tiburon (1980) 
    447 U.S. 255
    , 260; see Lucas v. South Carolina Coastal
    Council (1992) 
    505 U.S. 1003
    , 1015, 1019.) The court concluded the state, as the
    condemning agency, was liable for the de facto taking that occurred long before the direct
    condemnation action was filed because the development restrictions imposed by the city
    precluded the property owner from realizing any economic value from the subject
    25
    property (the four and one-half acres of the property owner’s 17.385-acre parcel)5 and the
    state had a direct hand in causing those development restrictions: “(1) The [c]ity and the
    [s]tate ‘cooperated’ with each other with respect to the nondevelopment of [the subject]
    property within and along the [s]tate’s proposed freeway route . . . ; (2) the [s]tate knew
    that the [c]ity had deprived [the property owner] of virtually all right to develop the
    subject property and that this development restriction rendered the subject property
    virtually unmarketable; (3) the [s]tate knew that the [c]ity’s restrictions on the
    development of the subject property were based solely on the fact that the property was
    located within the proposed freeway route; and (4) the [s]tate had no intention of actually
    condemning the subject property for many years (although it was arguably willing to buy
    the property at an earlier date if an agreeable purchase price could be negotiated).” (Id. at
    p. 442, fn. omitted, italics added.) Despite the fact the subject property was otherwise
    developable and “it would still be several more years before the [s]tate needed to need to
    condemn the subject property for freeway construction . . . the [s]tate merely ‘sat back’
    and allowed the [c]ity, by way of its development restrictions, to ‘bank’ the subject
    property for the [s]tate—presumably so that the [s]tate could, at a later date, condemn the
    subject property in an undeveloped (and, consequently, less costly) condition.” (Id. at
    p. 443.)
    Diversified Properties relied on Jones v. People ex rel. Dept. of
    Transportation (1978) 
    22 Cal. 3d 144
    , 151 (Jones), an inverse condemnation case in
    which a taking was similarly found based on the prohibition of development of property
    solely to preserve it for future acquisition for public use. In Jones, “‘plaintiffs bought
    5              The Diversified Properties court was not persuaded by the fact that
    development restriction did not apply to all the property: “While it is true that not all of
    [the property owner’s] larger parcel was ‘taken’ by the [s]tate, it is also true that all of the
    subject parcel was ‘taken’ by the [s]tate and it is the inverse condemnation of the subject
    parcel that we are here concerned with.” (Diversified 
    Properties, supra
    , 14 Cal.App.4th
    at p. 444, fn. 6.)
    26
    property with frontage on Fair Oaks Boulevard, intending to subdivide, with access from
    the boulevard to the subdivision. The [state] announced plans to construct a freeway
    which would cross plaintiffs’ property and cut off access from Fair Oaks Boulevard.
    Pursuant to provisions of the Streets and Highway Code, the [state] entered into a
    freeway agreement with the county to reroute or close streets which would intersect with
    the freeway, and further providing that no road could be opened into or connected with a
    freeway without permission of the state . . . . The county refused to approve plaintiffs’
    subdivision map because of the state’s freeway requirements. [¶] The Supreme Court
    held that plaintiffs were entitled to recover damages against the state because its actions
    substantially impaired their access. [Citation.]” (Diversified 
    Properties, supra
    ,
    14 Cal.App.4th at pp. 442-443.)
    In finding compensation was required for denying access to—and hence the
    ability to develop—the property, Jones observed, “if the only acts of which plaintiffs
    complain were the adoption of the route, the designation of their land for future
    acquisition, and the purchase of some of the properties along the right of way, there
    would be no such direct and special interference with plaintiffs’ rights as to justify an
    action in inverse condemnation. [P]lanning and construction of a freeway requires a
    substantial period of time, and a holding that announcement of the plan for the freeway
    results in inverse condemnation of properties designated for ultimate acquisition would
    result in the forced purchase by the state of large amounts of property which might never
    be used and would severely hamper the government’s ability to make needed
    improvements in the highway system. The need for flexibility in planning, changing the
    design of, or even abandoning a proposal for a highway militates against the theory that
    an action for inverse condemnation lies for the general effects of such conduct. [¶] Here,
    however, the state went further. It effectively denied plaintiffs the right to subdivide their
    land by depriving them of the access required for subdivision. Although it was the
    county which refused to approve plaintiffs’ subdivision map providing for access from
    27
    Fair Oaks Boulevard, the reason given for the refusal was the freeway agreement with the
    state and the provision of section 100.2 of the Streets and Highways Code that no road
    could be opened into a freeway without permission of the [state].” 
    (Jones, supra
    ,
    22 Cal.3d at p. 152.) In other words, once the state’s expressed desire to acquire the
    plaintiffs’ property in the future resulted in denial of land use approvals, a taking
    occurred. (See Taper v. City of Long Beach (1982) 
    129 Cal. App. 3d 590
    , 614-615
    [finding of de facto taking supported by evidence city rejected property owner’s
    development application because city intended to acquire property for public park]; see
    also Simpson v. City of North Platte (Neb. 1980) 
    292 N.W.2d 297
    , 301 [requiring
    developer to dedicate land for future unscheduled public use unrelated to burdens
    imposed by developer’s project nothing more than “a ‘land banking’ operation” in
    violation of takings clause].)
    Here, as in Diversified Properties, the City conditioned approval of
    development upon the Alternative 1 Acreage and Temporary No-Build Area remaining
    undeveloped to preserve that acreage for future acquisition for public use. At public
    hearings, the City staff repeatedly stated the City should not allow development on the
    property so as to avoid additional costs (e.g., for relocation of tenants and demolition of
    buildings) at such time as it was ready to acquire the property. We agree with Jefferson
    the conditions were imposed to “‘bank’” the otherwise developable property so it could
    potentially be condemned at some unknown time in the future “in an undeveloped (and,
    consequently, less costly) condition.” (Diversified 
    Properties, supra
    , 14 Cal.App.4th at
    p. 443.) And applying the reasoning of Diversified Properties, the condition effected an
    uncompensated taking of the Alternative 1 Acreage and the Temporary No-Build Area,
    and therefore, the trial court erred by denying Jefferson’s petition for writ of mandate.
    The City contends prohibiting development on the Alternative 1 Acreage
    was not a taking because the condition did not deprive Jefferson all use of its property—
    28
    Jefferson received approval to proceed with development of the remaining 17 acres.
    Thus, it argues Jefferson has not been denied all beneficial use of its land.
    We are not unmindful that “‘Taking’ jurisprudence does not divide a single
    parcel into discrete segments and attempt to determine whether rights in a particular
    segment have been entirely abrogated. In deciding whether a particular governmental
    action has effected a taking, [courts] focus[] rather both on the character of the action and
    on the nature and extent of the interference with rights in the parcel as a whole . . . .”
    (Penn 
    Central, supra
    , 438 U.S. at pp. 130-131.) But in this case, it is the City that has
    divided the Property into discrete segments.
    It is without dispute that under all applicable land use regulations,
    Jefferson’s entire property was developable and the PMP it submitted was in full
    compliance with those regulations. The City precluded Jefferson from building on a
    substantial portion of the Property so as to preserve it in an undeveloped state for possible
    future acquisition by the City for the Interchange Project. It would exalt form over
    substance to conclude because some of the Property could be built upon, there was no
    taking of the remainder declared undevelopable. Here Jefferson has been denied all
    beneficial use of the Alternative 1 Acreage and the Temporary No-Build Area on which
    no development is permitted, just as in Diversified Properties where the city prohibited
    development on the four and one-half acres of the developer’s 17-acre property the state
    identified as needed for freeway. (Diversified 
    Properties, supra
    , 14 Cal.App.4th at
    p. 444, fn. 6.) Thus this case is analogous to Twain Harte Associates, Ltd. v. County of
    Tuolumne (1990) 
    217 Cal. App. 3d 71
    , 77-79, in which the county carved out 1.7 acres
    from the property owner’s 8.5-acre lot zoned light commercial, and rezoned it as open
    space, effectively preventing any development thereon. The county argued that for
    taking purposes the 1.7-acre plot must be considered within the entire 8.5-acre parcel,
    6.8 acres of which had already been developed with a shopping center. The court held
    29
    whether there was a taking of the 1.7 acres was not dependent on the treatment of the
    entire parcel as a whole. (Id. at p. 87.)
    The City also contends prohibiting development of the Alternative 1
    Acreage and the Temporary No-Build Area was appropriate because the City was barred
    by federal law from acquiring the necessary rights-of-way until all environmental reviews
    were complete and the final configuration of the Interchange Project was approved. The
    City cites Lathan v. Brinegar (9th Cir. 1974) 
    506 F.2d 677
    , and Lathan v. Volpe (9th Cir.
    1971) 
    455 F.2d 1111
    , and those opinions’ discussions of the complex procedures
    involved in construction of federally funded highways and at what stage in the process
    rights-of way can be bought. We find little relevance to that argument as the issue before
    us is whether the City improperly denied Jefferson’s application for development of the
    property so as to keep it undeveloped (and thus less costly) for that future acquisition if
    and when it occurs.
    In sum, we conclude here that the conditions imposed by the City in
    approving the PMP were invalid because they constituted an uncompensated de facto
    taking of the Alternative 1 Acreage and the Temporary No-Build Area. Therefore, the
    trial court should have granted Jefferson’s petition for writ of mandamus.6
    We cannot, however, agree with Jefferson’s assertion the conditions
    effected a taking of its entire 26.85-acre property. Jefferson describes the conditions as
    creating a completely unidentifiable “floating no-build” area affecting its entire property
    rendering “any development on any portion [or the property] . . . ephemeral and
    impossible.” To the contrary, the area on which development was restricted, i.e., the
    Alternative 1 Acreage, was delineated on various Caltrans-generated schematics. Those
    6             In view of this conclusion, the trial court erred by granting the City’s
    motion for judgment on the pleadings on the remaining inverse condemnation causes of
    action given that the sole basis for granting the motion was Jefferson’s failure to prevail
    on the mandamus cause of action.
    30
    schematics showed the footprint of each alternative for the Interchange Project. The City
    initially expressed a preference for the Alternative 3 configuration and Jefferson’s PMP
    included an appendix demonstrating the impact of that alternative on its project and
    submitted revised site plan showing how the project could be reconfigured if
    Alternative 3 was selected. Jefferson, however, advocated for the selection of
    Alternative 1 because it was the configuration that would be least disruptive to its project,
    and the City selected Alternative 1 as the preferred configuration. At the final planning
    commission hearing on the PMP, Jefferson’s project planner discussed how the project
    might be modified to accommodate the Alternative 1 configuration, and Ellis indicated
    Jefferson would reluctantly modify the PMP to accommodate the Alternative 1
    configuration so long as Jefferson was going to be compensated for the acreage excluded
    from the PMP. There was no suggestion Jefferson did not understand what acreage the
    City was excluding from development—it was the acreage shown on the schematics as
    the Alternative 1 configuration.
    Similarly, the Temporary No-Build Area was identified in the ordinance
    approving the PMP as 2.1 acres on the southeastern portion of the site—a location that
    corresponds to the unbuildable drainage retention basin area designated in the PMP. The
    City then conditioned approval of the PMP upon Jefferson revising the building envelope
    for the project to conform to the Alternative 1 configuration (i.e., no development on the
    Alternative 1 Acreage). Although it is true that at the time the PMP was approved, the
    City would not have known the precise description of the land that would ultimately be
    taken for the Interchange Project, what is at issue here is the property that it excluded
    from Jefferson’s development application. Jefferson cannot claim it did not know what
    property that was.
    Having concluded the conditions imposed by the City in approving the
    PMP were invalid because they effected an uncompensated taking of the Alternative 1
    Acreage and the Temporary No-Build Area, and the trial court should have granted
    31
    Jefferson’s petition for writ of mandamus, we must turn to the appellate remedy. That
    requires us to turn back to 
    Hensler, supra
    , 
    8 Cal. 4th 1
    , and face the elephant in the room:
    the pending County Condemnation Action.
    
    Hensler, supra
    , 
    8 Cal. 4th 1
    , 14, requires a property owner alleging that
    government action constitutes an uncompensated taking must first challenge the
    development restriction by way of a writ of mandate so as to prevent the property owner
    from unilaterally “transmut[ing] an excessive use of the police power into a lawful taking
    for which compensation in eminent domain must be paid.’ [Citation.] Compensation
    must be paid for a permanent taking only if there has been a final judicial determination
    that application of the ordinance or regulation to the property is statutorily permissible
    and constitutes a compensable taking. Even then the state or local entity has the option of
    rescinding its action in order to avoid paying compensation for a permanent taking.” In
    other words, a prepayment judicial determination that the development restriction
    constitutes a taking is required “in order to give a city the opportunity to change its mind
    before being compelled to pay damages.” 
    (Mola, supra
    , 57 Cal.App.4th at p. 414.) In
    this case that would mean the City must either approve Jefferson’s PMP without the
    conditions precluding development on the Alternative 1 Acreage and the Temporary
    No-Build Area, or it must pay compensation for the taking. But the County
    Condemnation Action has effectively taken the former option off the table, leaving only
    the issue of determining just compensation for the Alternative 1 Acreage and the
    Temporary No-Build Area.
    As noted above, we have taken judicial notice of the December 28, 2011,
    Cooperative Agreement between the City, Caltrans, and the County pursuant to which the
    County has become the responsible agency for construction of the Interchange Project,
    and has assumed all responsibility for acquisition of rights-of-way for the Interchange
    Project “including all eminent domain activities.” We have also taken judicial notice of
    the eminent domain complaint filed by the County in February 2014 in the County
    32
    Condemnation Action and additional documents filed by Jefferson in the County
    Condemnation action including: (1) its motion to file an amended answer in which it
    indicates it will be seeking damages for the same precondemnation conduct that underlie
    this writ of mandate/inverse condemnation action; and (2) its motion to consolidate the
    County Condemnation Action with the City Condemnation Action by which the City is
    acquiring an additional part of Jefferson’s property for improvement of the Jefferson
    Street/Varner Road intersection. Jefferson has previously stipulated in this court that it
    does not challenge the County’s or the City’s right to take and the issues pending
    resolution in those actions relate to just compensation for the taking.
    We invited the parties to file supplemental letter briefs addressing the effect
    of the County Condemnation Action on the present case. The City argues the County
    Condemnation Action renders the present appeal moot because Jefferson will now obtain
    just compensation in the direct condemnation action. It contends that if this appeal is not
    dismissed as moot, Jefferson will pursue duplicative damages against the City and the
    County for the same property taken, severance damages to the remainder, damages for
    delay in instituting a direct condemnation action, and “attorneys fees, and the like.”
    “‘It is well settled that an appellate court will decide only actual
    controversies and that a live appeal may be rendered moot by events occurring after the
    notice of appeal was filed. We will not render opinions on moot questions or abstract
    propositions, or declare principles of law which cannot affect the matter at issue on
    appeal. [Citation.]’” (Indio Police Command Unit Association v. City of Indio (2014)
    
    230 Cal. App. 4th 521
    , 538; People v. Gregerson (2011) 
    202 Cal. App. 4th 306
    , 321 [“‘“[A]
    case becomes moot when court ruling can have no practical effect or cannot provide the
    parties with effective relief”’”].)
    We do not agree with the City that the County’s institution of a direct
    condemnation action renders this action moot. Condemnation actions can be abandoned
    in whole or in part “any time after the filing of the complaint and before the expiration of
    33
    30 days after final judgment . . . .” (Code Civ. Proc., § 1268.510, subd. (a).)
    Red Mountain, LLC v. Fallbrook Public Utility Dist. (2006) 
    143 Cal. App. 4th 333
    , 356
    (Red Mountain), applying the rules set forth in 
    Klopping, supra
    , 
    8 Cal. 3d 39
    , explains
    “that as between a[n] . . . eminent domain action and an inverse condemnation action
    involving the same property, the case that proceeds to judgment first is res judicata as to
    issues common to both actions and bars recovery in the other action of any damages that
    were or could have been recovered in the action that proceeded to judgment first.
    [Citation.]” And it is not clear the County Condemnation Action encompasses all of the
    Alternative 1 Acreage, which the City prohibited Jefferson from developing.
    Moreover, any concerns about double recovery may appropriately be
    handled and avoided by consolidating this case with the County Condemnation Action
    cases on remand. (Code Civ. Proc., § 1048, subd. (a) [consolidation of actions pending in
    same court that involve common questions of law or fact ]; see Red 
    Mountain, supra
    ,
    143 Cal.App.4th at p. 357 [inverse condemnation action and eminent domain action
    consolidated and proceeded to judgment together].) Indeed, consolidation appears
    particularly appropriate in this case—the cases are in the same court, involve the same
    property, and many (if not all) of the same damages. Although the County is not before
    us in this action, it has stepped into the City’s shoes to become the responsible agency for
    the constructing Interchange Project responsible for all eminent domain activities—which
    as a practical matter limits the City’s options on remand—and Jefferson has already
    sought consolidation of the County Condemnation and the City Condemnation Action
    bringing all the parties before the same court in those actions as well. (See People ex rel.
    Department of Public Works v. Chevalier (1959) 
    52 Cal. 2d 299
    , 307-308 [trial court
    properly consolidated separate eminent domain actions by state and city pertaining to
    same freeway project].)
    34
    DISPOSITION
    The City’s request for judicial notice filed February 28, 2013, is granted as
    to the four-volume administrative record lodged with this court and denied as to
    Exhibit A, the Indio City Council Agenda Report dated October 20, 2009. The City’s
    request for judicial notice filed October 27, 2014, is granted. The City’s request for
    judicial notice filed March 6, 2015, is denied.
    The trial court’s judgment is reversed and the matter is remanded to the
    trial court with directions to grant appellant’s petition for writ of mandate and conduct
    further proceedings in accordance with this opinion to determine just compensation for
    the Alternative 1 Acreage and the Temporary No-Build Area, which proceedings should
    include considering consolidation of this action with the pending County Condemnation
    Action (Riverside County Super. Ct., Case No. PSC1400798) and the pending City
    Condemnation Action (Riverside County Super. Ct., Case No. PSC1400896). Appellant
    is awarded its costs on this appeal.
    O’LEARY, P. J.
    WE CONCUR:
    BEDSWORTH, J.
    FYBEL, J.
    35
    Filed 5/15/15
    CERTIFIED FOR PUBLICATION
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    FOURTH APPELLATE DISTRICT
    DIVISION THREE
    JEFFERSON STREET VENTURES, LLC,
    Plaintiff and Appellant,                            G049899
    v.                                              (Super. Ct. No. INC072101)
    CITY OF INDIO,                                          ORDER GRANTING REQUEST
    FOR PUBLICATION
    Defendant and Respondent.
    The Law Offices of Palmieri, Tyler, Wiener, Wilhelm & Waldron, the Law
    Offices of Matteoni O’Laughlin & Hechtman, and the Law Offices of Jenny & Jenny
    have requested that our opinion filed April 21, 2015, be certified for publication. It
    appears that our opinion meets the standards set forth in California Rules of Court, rule
    8.1105(c). The request is GRANTED.
    The opinion is ordered published in the Official Reports.
    O’LEARY, P. J.
    WE CONCUR:
    BEDSWORTH, J.
    FYBEL, J.
    36