Clews Land & Livestock, LLC v. City of San Diego ( 2018 )


Menu:
  • Filed 12/20/17; Certified for Publication 1/8/18 (order attached)
    COURT OF APPEAL, FOURTH APPELLATE DISTRICT
    DIVISION ONE
    STATE OF CALIFORNIA
    CLEWS LAND AND LIVESTOCK, LLC et                                    D071145
    al.,
    Plaintiffs and Appellants,
    (Super. Ct. No. 37-2015-00032905-
    v.                                                         CU-TT-CTL)
    CITY OF SAN DIEGO,
    Defendant and Respondent,
    JAN DUNNING et al.,
    Real Parties in Interest and
    Respondents.
    APPEAL from a judgment of the Superior Court of San Diego County,
    Timothy B. Taylor, Judge. Affirmed.
    Kevin K. Johnson and Jeanne L. MacKinnon for Plaintiffs and Appellants.
    San Diego City Attorney's Office and Glenn T. Spitzer for Defendant and
    Respondent.
    Schwartz Hyde & Sullivan, Kevin P. Sullivan; The Jon Corn Law Firm, Jonathan
    C. Corn and Arie L. Spangler for Real Parties in Interest and Respondents.
    Plaintiffs Clews Land and Livestock, LLC; Barbara Clews; and Christian Clews
    (collectively, CLL) appeal a judgment in favor of defendant City of San Diego (City) on
    CLL's petition for writ of mandate and complaint for declaratory and injunctive relief,
    violation of procedural due process, and equitable estoppel. CLL's petition and
    complaint challenged the City's approval of a project to build a private secondary school
    on land neighboring CLL's commercial horse ranch and equestrian facility and the City's
    adoption of a mitigated negative declaration (MND) regarding the project. The for-profit
    school, the Cal Coast Academy, is being developed by real parties in interest Jan
    Dunning, Cal Coast Academy RE Holdings, LLC, and the North County Center for
    Educational Development, Inc. (collectively, Cal Coast).
    CLL contends the court erred by denying its petition and resolving its remaining
    claims in favor of the City. It argues the City should not have adopted the MND because
    the Cal Coast Academy project would cause significant environmental impacts in the
    areas of fire hazards, traffic and transportation, noise, recreation, and historical resources,
    and because the MND identified new impacts and mitigation measures that were not
    included in the draft MND. CLL further argues the City should not have approved the
    project because it is situated in designated open space under the applicable community
    land use plan and because the City did not follow the provisions of the San Diego
    Municipal Code (SDMC) applicable to historical resources.
    The City and Cal Coast respond that CLL did not exhaust its administrative
    remedies because it failed to appeal the decision adopting the MND to the San Diego
    City Council. On the merits, the City and Cal Coast argue the project would not cause
    2
    any significant environmental impacts in the areas identified by CLL, the project is not
    inconsistent with the open space designation, and the City complied with the historical
    resources provisions of the SDMC.
    For reasons we will explain, we conclude CLL's challenge to the MND is barred
    because it did not exhaust its administrative remedies in proceedings before the City. In
    doing so, we reject CLL's argument that the City's process for administrative appeals—at
    least as implicated by this project—violates the California Environmental Quality Act
    (CEQA; Pub. Resources Code, § 21000 et seq.) 1 by improperly splitting the adoption of
    an environmental document (e.g., the MND) from the project approvals. We further
    conclude CLL's challenge to the MND fails on its merits, even assuming CLL had
    exhausted its administrative remedies. Finally, we conclude the City complied with all
    applicable requirements of the SDMC regarding historical resources and the City's
    approval of the project does not conflict with the open space designation because the
    project will be located on already-developed land. We therefore affirm the judgment.
    1      Further statutory references are to the Public Resources Code unless otherwise
    stated. The administrative guidelines adopted by the Secretary for Resources to
    implement CEQA (Cal. Code Regs., tit. 14, § 15000 et seq.) will be referred to as
    "Guidelines" followed by the section number. "We need not decide for purposes of this
    appeal whether the Guidelines are binding on the courts. At a minimum . . . the
    Guidelines are entitled to great weight so long as they are not clearly unauthorized or
    erroneous." (California Oak Foundation v. Regents of University of California (2010)
    
    188 Cal. App. 4th 227
    , 240, fn. 3.)
    3
    FACTUAL AND PROCEDURAL BACKGROUND
    The Project and Its Surroundings
    The project consists of a 5,340-square-foot school, divided into three classroom
    buildings under a single roof, on an approximately one-acre site. The school will have a
    maximum enrollment of 75 students, with 18 staff members. Along with the school, the
    project proposes construction of a 24-stall parking lot, landscaping, and removal of
    certain existing features on the site, including a concrete-filled swimming pool.
    A farmhouse at the site was built around 1900 and is a designated historical
    resource, part of the larger Mount Carmel Ranch (Historical Resources Board No. 391).
    Cal Coast currently uses the farmhouse as an administrative office, and it will continue to
    do so following project completion. Several older outbuildings exist at the site as well.
    The project will not affect the farmhouse or outbuildings, and the school's design
    incorporates features intended to ensure compatibility with the historic nature of the site.
    The site is adjacent to CLL's equestrian facility, the Clews Horse Ranch. The
    ranch consists of a 45-stall parking lot, corrals, stables, riding areas, a barn, a club house,
    and two or three single family homes. A riding ring abuts the project site. The ranch has
    facilities for over a hundred horses and a dozen cattle. Individuals come to the ranch to
    ride or participate in other equestrian activities. The ranch also holds a popular rodeo.
    The project site is situated at the end of Clews Ranch Road, a 1,650-foot private
    driveway that also provides access to the ranch. It is approximately 20 feet wide and has
    a posted speed limit of 10 miles per hour. Clews Ranch Road runs east-to-west and
    connects with Carmel Country Road. At that intersection, a public parking lot serves
    4
    recreational bicycle and hiking trails in the area. Clews Ranch Road is the sole vehicular
    accessway for both the project site and the ranch, although a dirt road runs westward
    from the site and connects with Carmel Creek Road. The project site sits on a bluff
    above State Route 56, a busy divided highway. Across the highway is a developed
    suburban area.
    The site lies within the "Neighborhood 8" portion of Carmel Valley, a designated
    community plan area within the City. Under the Carmel Valley Neighborhood 8 Precise
    Plan, the site is designated as open space. The site is zoned residential MF-1, which
    allows construction of multifamily dwellings up to a density of seven to fifteen units per
    acre. MF-1 zoning allows "by right" construction of primary and secondary schools. The
    site is also within the coastal zone. When the neighboring ranch was permitted in 2007,
    the City changed its zoning from multifamily residential to agricultural. The ranch is also
    designated open space.
    The City's Initial Study
    Cal Coast applied to the City for the approvals necessary to develop the project.
    In an initial study, City staff determined the project would not have a significant impact
    on any environmental factors, with the exception of "cultural resources," i.e.,
    archaeological and paleontological resources. Such resources may exist in the project
    area. However, City staff concluded the environmental impact would be less than
    significant if mitigation measures were adopted, including on-site monitoring during
    grading activities.
    5
    As relevant here, the initial study also assessed the project's potential impacts on
    historical resources, fire hazards, land use and planning, noise, recreation, and
    transportation and traffic. The initial study identified the farmhouse as a historical
    resource, but it determined that the project's effects on the farmhouse would be less than
    significant because the farmhouse and outbuilding structures would be maintained and
    because the school's design was consistent with the City's historical resource regulations.
    As to fire hazards, the initial study noted the project site was adjacent to native or
    naturalized vegetation in the Carmel Valley River Enhancement Program (CVREP) area
    along State Route 56. Based on its location, the project would be subject to brush
    management regulations. In addition, the project's design incorporated fire resistant
    materials and tempered glass windows. Based on these factors, the initial study
    concluded that the project would not "expose people or structures to a significant risk of
    loss, injury or death involving wildland fires." As to land use, the initial study
    determined the project was compatible with the community plan and permitted by the
    underlying multifamily residential zoning. As to noise, it found no environmental
    impact. The initial study noted that the project would not be a "permanent noise
    generating source" and "would not expose people to a substantial increase in temporary
    or periodic ambient noise levels." As to recreation, the initial study concluded the project
    would have no impact on recreational resources. And as to traffic and transportation, the
    initial study likewise found no impact. It determined that the project was consistent with
    the community plan and underlying zoning, would not cause any permanent increase in
    traffic, and would not result in inadequate emergency access.
    6
    The Draft MND and Public Comments
    Based on the initial study, City staff prepared a draft MND for the project. The
    draft MND described the proposed project (albeit as "three modular buildings" rather
    than a single building), identified the potential impact on cultural resources, and
    described the mitigation measures Cal Coast would adopt to lessen any such impact. The
    City's initial study was attached to the draft MND.
    Several interested parties submitted comments in response to the draft MND. Two
    Native American tribes wrote regarding cultural resources. City staff responded by
    pointing out the mitigation measures in the draft MND. The San Diego County
    Archaeological Society wrote to clarify the qualifications of any archaeological monitor.
    A consultant engaged by Cal Coast requested certain technical corrections, including
    changing the description of the project from "three modular buildings" to "a new single-
    story building."
    CLL submitted comments criticizing the use of an MND for the project. It
    contended the City was required to prepare an Environmental Impact Report (EIR).
    Among other things, CLL argued that potential impacts on historical resources, fire
    hazards, noise, and transportation and traffic should be studied in an EIR. CLL believed
    the draft MND's treatment of historical resources was inadequate without a
    comprehensive survey of the project site. It further believed the draft MND did not
    adequately consider the hazards to students and teachers from wildfires, especially given
    the limited access to the project site. CLL contended the draft MND ignored the impact
    of noise on the Clews Horse Ranch and alleged the project "create[d] a real threat to the
    7
    viability of the ranch as [a] place to board and train horses." (A ranch creditor also wrote
    to complain that approval of the project would "impair[] the ability of Clews Ranch to
    realize its economic potential and therefore impairs the security of [his] loan.") Finally,
    CLL argued the project's use of Clews Ranch Road would overburden the easement held
    by the project site over the road.
    A ranch client submitted comments that echoed CLL's concerns regarding noise.
    The individual noted the ranch's riding area was very close to the project site. He alleged
    construction activities at the project site had caused "loud, unanticipated noise, or
    blowing plastic sheets" that caused him and other riders to be thrown from their horses.
    He further alleged that Clews Ranch Road could not handle additional traffic and had
    numerous blind spots. He believed additional traffic would endanger horses and riders
    that use the road. As to the latter concerns, City staff responded that the dimensions,
    alignment, and surfacing of the road had been reviewed by City engineering,
    transportation, and fire personnel, who determined it was adequate to serve both the
    school and the ranch. City staff noted Cal Coast had proposed to use a shuttle bus service
    to transport students to the school from the public parking lot at the intersection of Clews
    Ranch Road and Carmel Country Road, thereby reducing traffic on Clews Ranch Road.
    CLL engaged a fire safety consultant, Van Collingsworth, to submit additional
    comments regarding fire hazards related to the project. Collingsworth concluded the
    project had significant adverse fire safety impacts that required preparation of an EIR.
    He noted the project site was within a Very High Fire Hazard Severity Zone and a flood
    plain. Collingsworth identified a large number of questions regarding fire safety that he
    8
    alleged went unanswered in the draft MND. These questions revolved around topics such
    as the project's design and construction standards, the evacuation plan for the school, first
    responder response times and capabilities, and brush management guidelines.
    Collingsworth also provided general information regarding the vulnerability of structures
    and people to wildfires, the strength and intensity of expected wildfires, the impact of
    drought conditions on fire behavior, and the safety of firefighters and other emergency
    personnel. He expressed concern that Clews Ranch Road would be inadequate to
    evacuate the school in addition to the animals and people at the ranch. Finally, he
    asserted without citation that "[t]raffic is already constrained and gridlocked during
    commuter hours on and offsite under current conditions."
    City staff reviewed Collingsworth's comments and did not believe he had raised
    any significant environmental impacts. The fire marshal had reviewed the project and
    found it complied with City fire codes. Similarly, an outside consultant engaged by Cal
    Coast had prepared a wildfire analysis in response to Collingsworth's comments. The
    consultant identified no significant impacts regarding fire safety. Cal Coast also
    submitted a brush management plan and a fire protection and emergency evacuation plan,
    which described two evacuation routes (one eastward and one westward) in the event of
    an emergency.
    City staff identified several project design features that reduced the potential for
    fire hazard impacts, including fire resistant building materials, brush removal, a new
    water line and fire hydrant serving the project site, and an annually reviewed evacuation
    plan. They described the contents of the school's evacuation plan, including exit routes
    9
    east along Clews Ranch Road to Carmel Country Road and west along a dirt road to
    Carmel Creek Road. City staff noted the school intended to close on red flag warning
    days out of an abundance of caution. For fires that might originate at the school, City
    staff noted among other things that the project will incorporate interior sprinklers that
    successfully suppress 98 percent of fires.
    Cal Coast engaged a consultant to prepare an analysis of potential noise impacts
    caused by the project. The consultant reported that school would be in session from 8:30
    a.m. until 2:00 p.m., with morning and lunch breaks. No physical education classes
    would be on site, and the school would not use bells or other alarms (except for fire
    alarms). Given the proximity of State Route 56, approximately 200 feet from the project
    site, the consultant found the average ambient noise level at the site was approximately
    60 decibels. The consultant identified the loudest likely noise generated by students and
    faculty at the school as laughter, which has a level of approximately 88 decibels. It
    modeled a worst-case scenario, where the laughter was continuous over a one-hour
    period, and the weighted average noise levels ranged between 38 and 49 decibels at the
    receivers in the model. Because these levels were less than the observed noise level at
    the site, the consultant concluded the project's noise impact would not exceed levels that
    would disturb sensitive wildlife under the City's noise significance determination
    thresholds.
    The Final MND and Public Comments
    After receiving the comments and reports described above, City staff prepared a
    final MND for the project. The final MND incorporated Cal Coast's requested change to
    10
    the project description, as well as new information from the reports and analyses prepared
    by Cal Coast. For example, City staff changed their conclusion regarding emergency
    access to the project from "no impact" to "less than significant impact" and added detail
    regarding the City's review of emergency access to the school. After review by the San
    Diego Fire Department, City staff determined the school met its emergency access
    requirements. This determination was supported by Cal Coast's fire consultant, who
    concluded that the project would not expose people or structures to a significant risk of
    loss, injury, or death from wildland fires. The final MND confirmed, however, that "the
    physical scope of the project, project impacts, proposed mitigation measures and
    conclusions of the [MND] are not affected by the revisions."
    After City staff prepared the final MND, the Carmel Valley Community Planning
    Board (CVCPB) considered the project. Christian Clews is a member of the CVCPB, but
    he recused himself from its consideration of the project. Several board members
    expressed concern about the multifamily residential zoning of the project site and
    expressed their desire to have open space there. The project was put to a vote by the
    board. The vote failed, with five in favor, four opposed, and two abstentions. Nine votes
    were required to support the project.
    The board chair subsequently wrote to the City to describe the "unusual dilemma"
    the project posed to the board. He wrote that the site's multifamily residential zoning
    seemed incompatible with the community plan, which designated the site as open space.
    (For this reason, the chair abstained from the vote.) The chair stated that he personally
    did not object to a school at the site because it appeared to be an acceptable use of the
    11
    protected area. But other board members expressed concern that the school's use of the
    site would not be compatible with the horse ranch next door. The chair believed further
    study of the issue was needed. Other board objections included concerns over the impact
    of noise and traffic on the horse ranch, the impact of the school's operation on the public
    parking lot that would be used by the school's shuttle buses, the impact of development
    on the rural setting and nearby recreational trails, the severity of fire hazards and the
    adequacy of evacuation routes, and the general sense that "many issues still could use
    more detailed and guaranteed solutions."
    CLL submitted additional comments objecting to allegedly significant changes to
    the project and demanding recirculation of the MND. CLL also argued that the City had
    not complied with its historical resource regulations. Collingsworth submitted additional
    comments as well that criticized the project's brush management and evacuation plans.
    He also rebutted the City's responses to comments on the draft MND.
    Proceedings Before the Hearing Officer
    The City scheduled a public hearing on the project before a City hearing officer.
    In a report to the hearing officer, City staff recommended the project be approved in full,
    i.e., the final MND be adopted and permits for coastal development and site development
    be issued. The report described the current site conditions, the proposed project, and the
    governing community plan. It noted the site was within an area of designated open
    space, but it concluded that the project was consistent with the community plan's open
    space policies because the new development did not extend beyond previously developed
    12
    and disturbed areas. After hearing speakers for and against approval, the hearing officer
    approved the project and adopted the MND.
    The public hearing notice stated, "The decision of the Hearing Officer is final
    unless appealed to the Planning Commission," and "The decision made by the Planning
    Commission is the final decision by the City." It then advised, "The adoption of [an
    MND] may be appealed to the City Council after all other appeal rights have been
    exhausted. All such appeals must be filed by 5:00 PM within ten (10) business days from
    the date of the Planning Commission's certification/adoption of the environmental
    document."
    At the time of the hearing, the City published Information Bulletin 505, a guide to
    the City's appeal procedure under the SDMC. The City divides its procedures for
    approving development applications into different numbered processes. (SDMC,
    § 112.0501.) The City handled the project at issue here under Process Three. The
    bulletin stated, "Process Two and Three permit decisions are appealable to the Planning
    Commission. Process Four permit decisions are appealable to the City Council. Appeals
    of Environmental Determinations may be made after all project appeal rights have been
    exhausted." It further stated, "All appeals must be made in accordance with the
    procedures listed in Chapter 11, Article 2, Division 5. All appeals must be made no later
    than close of business, within ten (10) business days of the original decision date (Process
    Three and Four) . . . ." The bulletin specified the filing location for "Process Two and
    Three Decisions Appealable to the Planning Commission" as the City's Development
    Services Department, and the filing location for "Process Four Decisions and
    13
    Environmental Determinations Appealable to the City Council" as the City Clerk's
    Office. 2
    Appeal to the Planning Commission
    CLL appealed the hearing officer's decision to the Planning Commission on a City
    form, DS-3031. CLL selected "Process Three Decision - Appeal to the Planning
    Commission" as the "Type of Appeal." It filed the form with the City's Development
    Services Department. It did not select "Environmental Determination - Appeal to City
    Council" or file the form with the City Clerk's Office.
    CLL identified numerous grounds for appeal. It contended the hearing officer's
    findings under CEQA and in the final MND were not supported, including in the areas of
    traffic and transportation, noise, hazards, and cultural resources. It also contended the
    project's approval conflicted with the City's historical resource regulations and the
    Carmel Valley Neighborhood 8 Precise Plan.
    In a report to the Planning Commission, City staff recommended that CLL's
    appeal be denied. After recounting the conditions at the site and the description of the
    project, the report addressed the issues identified by CLL's appeal. The report noted that
    an MND had been adopted by the hearing officer, but no appeal had been filed
    challenging that environmental determination. The report stated that the time to appeal
    had expired 10 business days after the hearing officer's decision, so any issues based on
    2      As we will discuss in detail below, the parties dispute the accuracy of the
    descriptions of the City's appeal procedure in Information Bulletin 505 and the public
    hearing notice.
    14
    CEQA or the MND had been waived. The report rejected CLL's contention that the City
    failed to comply with its historical resources regulations. The project would maintain the
    existing historic farmhouse, and the new construction was consistent with the
    farmhouse's aesthetics. Based on these facts, the project was consistent with federal
    standards for historical resource preservation and did not require a site development
    permit under the City's historical resource regulations. (A site development permit was
    required, however, based on its location in the Carmel Valley community plan area.) The
    report further rejected CLL's contention that the project conflicted with the community
    plan's open space designation for reasons previously discussed.
    CLL objected to the report's characterization of its appeal. In correspondence with
    City staff, CLL argued it had appealed the hearing officer's environmental determination,
    as evidenced by its statement of the grounds of appeal. CLL claimed it was not required
    to appeal the environmental determination to the City Council until its other appeals had
    been exhausted, i.e., after the Planning Commission rendered its decision. City staff
    responded that CLL was welcome to present its argument to the Planning Commission.
    At the Planning Commission's first hearing on the project, a commissioner asked
    the deputy city attorney present about the scope of CLL's appeal. The attorney responded
    that CLL had not properly appealed the hearing officer's environmental determination
    because it had not indicated on its appeal form that it was pursuing an appeal of that
    determination. She explained, "Had [the appropriate box] been checked, this appeal
    would be set before the City Council and would not be heard before this body." Later in
    the hearing, a commissioner expressed sympathy with CLL's position, finding it clear that
    15
    CLL attempted to appeal both the permit approvals and the environmental determination.
    She requested that the appeal be returned to City staff and calendared before the City
    Council. The deputy city attorney responded that the appeal procedures are laid out in
    the SDMC, and it would be impossible to transfer the appeal to the City Council. The
    commissioner further requested that the City's appeal form and information bulletin be
    revised to reflect the correct procedures. The attorney said they would follow-up on the
    commissioner's request. After hearing numerous speakers for and against the project,
    including both fire experts, the Planning Commission trailed consideration of the project
    to its next meeting.
    At the next meeting, the commissioners questioned Cal Coast, CLL, and their
    representatives. However, the Planning Commission was unable to reach the four-vote
    threshold to act on the project. The vote on a motion to approve the project and deny
    CLL's appeal was three in favor and two opposed, with two not voting. Consideration of
    the project was trailed again to a future meeting.
    When the Planning Commission considered the project a third time, a motion to
    approve the project and deny CLL's appeal prevailed on a vote of four in favor, two
    opposed, and one not voting. The Planning Commission's decision was memorialized in
    a resolution granting a coastal development permit and site development permit for the
    project. The resolution and permits included extensive findings regarding the project and
    its compliance with the City's land use policies.
    16
    Attempted Appeal to the City Council
    CLL attempted to file an appeal of the Planning Commission's decision to the City
    Council. CLL used a redesigned form DS-3031 that identified the "Type of Appeal" as
    either "Appeal of the Project" or "Appeal of the Environmental Determination." The
    various City processes, and the body to which the appeal was made, were no longer
    identified on the form. CLL indicated it was appealing both the project and the
    environmental determination. As grounds for its appeal, CLL identified various
    environmental impacts it believed required preparation of an EIR, including
    transportation and traffic, fire hazards, land use and planning, noise, and historical
    resources. CLL also contended, among other things, that the MND should have been
    recirculated because the final MND contained significant revisions to the project and
    additional mitigation measures. To justify its appeal, CLL referenced language in the
    public hearing notice and information bulletin that purported to authorize an appeal of an
    environmental determination after all other appeal rights had been exhausted.
    The City rejected CLL's appeal. In its rejection letter, the City stated that CLL's
    appeal challenging the environmental determination was untimely under the SDMC. The
    Planning Commission's approval of permitting for the project was final and not
    appealable.
    Appeal to the California Coastal Commission
    CLL then appealed to the California Coastal Commission. CLL argued, among
    other things, that the project was inconsistent with the City's Local Coastal Program
    (LCP). To support its argument, CLL pointed to the community plan's designation of the
    17
    area as open space and the historic status of the farmhouse at the site. CLL claimed the
    City failed to analyze the effect of the project on the functions of the open space,
    including the benefits of the CVREP recreation areas, and failed to follow its historical
    resource regulations. CLL also claimed the project would expose its horse ranch and
    users of nearby trails to increased fire hazards because of inadequate evacuation routes.
    Coastal Commission staff assessed CLL's appeal and found it raised no substantial
    issue. The staff's report concluded the project was consistent with the LCP. The report
    rejected CLL's open space argument because the site had already been developed and
    disturbed, and it found the City had complied with its historical resource regulations. It
    further noted, "Fire safety and evacuation is not a[n] LCP issue; however, the
    development complies with all fire-related requirements including brush management
    and building design." The report referenced a number of project elements that would
    address fire hazards and fire safety.
    The Coastal Commission's staff report concluded, "[T]here is strong and legal
    support for the City's determination that the proposed development is consistent with the
    certified LCP. . . . The extent and scope of the development is minor." At a public
    hearing, the Commission agreed with the report and found no substantial issue.
    Superior Court Proceedings
    CLL then filed the instant petition for writ of mandate and complaint for
    declaratory and injunctive relief, violation of procedural due process and equitable
    estoppel. The operative first amended petition and complaint alleged that the MND was
    improperly adopted because the project would have significant environmental impacts in
    18
    the areas already discussed above and because the final MND had significant new
    material that required recirculation. The petition and complaint repeated CLL's
    contentions that the community plan's open space designation prohibited the project and
    that the City failed to follow its historical resource regulations. The petition and
    complaint also challenged the City's appeal procedures. It alleged that the procedures did
    not comply with CEQA because they segregated environmental determinations from
    project approvals. It further alleged that the City did not provide adequate notice of the
    appellate procedures, thereby violating state law, the SDMC, and CLL's constitutional
    right to procedural due process. Finally, the petition and complaint alleged that the City
    should be equitably estopped from claiming that CLL had not adequately appealed
    adoption of the MND because the public hearing notice and other documents inaccurately
    described the appeal procedures.
    After briefing and argument, the trial court denied the petition and rejected CLL's
    claims. The court concluded CLL failed to exhaust its administrative remedies in City
    proceedings by failing to properly appeal the hearing officer's environmental
    determination. It found the City was not estopped from asserting a defense based on
    administrative exhaustion and that the City's appeal procedure did not violate CEQA.
    Even if the defense did not apply, the court was unpersuaded that adoption of the MND
    was unjustified. The court explained, "The court agrees with the City and [Cal Coast]
    that much of what motivated petitioners' objection to the building of the school next door
    has nothing to do with environmental concerns. Petitioners just do not want the academy
    as a neighbor because they feel it will affect them adversely from an economic
    19
    perspective." The court did not believe there was a fair argument that the project would
    significantly impact the environment. It stated, "The dominant neighbor of the proposed
    academy is [State Route] 56, hardly an environmentally sensitive area. The building
    proposed is small (5340 sq. ft. in a single story), and it will be unoccupied more days and
    hours than not. It strikes the court that requiring an expensive, time-consuming, and
    likely to be challenged EIR for this modest project, which is about the size of a large
    home, would be overkill." The court found CLL's remaining arguments unpersuasive and
    entered judgment accordingly. CLL appeals.
    DISCUSSION
    I
    CEQA Overview
    "CEQA was enacted to advance four related purposes: to (1) inform the
    government and public about a proposed activity's potential environmental impacts; (2)
    identify ways to reduce, or avoid, environmental damage; (3) prevent environmental
    damage by requiring project changes via alternatives or mitigation measures when
    feasible; and (4) disclose to the public the rationale for governmental approval of a
    project that may significantly impact the environment." (California Building Industry
    Assn. v. Bay Area Air Quality Management Dist. (2015) 
    62 Cal. 4th 369
    , 382 (CBIA).)
    CEQA primarily advances these purposes through its requirement that a state or
    local agency prepare an EIR before pursuing or approving any project falling within
    CEQA's scope that may have a significant impact on the environment. (§§ 21100,
    subd. (a), 21151, subd. (a).) "An [EIR] is an informational document which, when its
    20
    preparation is required . . . , shall be considered by every public agency prior to its
    approval or disapproval of a project." (§ 21061.)
    " 'If the agency's initial study of a project produces substantial evidence supporting
    a fair argument the project may have significant adverse effects, the agency must
    (assuming the project is not exempt from CEQA) prepare an EIR.' " (Save the Plastic
    Bag Coalition v. City of Manhattan Beach (2011) 
    52 Cal. 4th 155
    , 171 (Save the Plastic
    Bag).) "If, on the other hand, '[t]here is no substantial evidence, in light of the whole
    record . . . that the project may have a significant effect on the environment,' the agency
    may adopt a negative declaration." (Ibid.)
    A negative declaration is "a written statement briefly describing the reasons that a
    proposed project will not have a significant effect on the environment and does not
    require the preparation of an environmental impact report." (§ 21064.) An MND is "a
    negative declaration prepared for a project when the initial study has identified
    potentially significant effects on the environment, but (1) revisions in the project plans or
    proposals made by, or agreed to by, the applicant before the proposed negative
    declaration and initial study are released for public review would avoid the effects or
    mitigate the effects to a point where clearly no significant effect on the environment
    would occur, and (2) there is no substantial evidence in light of the whole record before
    the public agency that the project, as revised, may have a significant effect on the
    environment." (§ 21064.5.)
    21
    II
    Exhaustion of Administrative Remedies
    "The exhaustion of administrative remedies doctrine 'bars the pursuit of a judicial
    remedy by a person to whom administrative action was available for the purpose of
    enforcing the right he seeks to assert in court, but who has failed to commence such
    action and is attempting to obtain judicial redress where no administrative proceeding has
    occurred at all; it also operates as a defense to litigation commenced by persons who have
    been aggrieved by action taken in an administrative proceeding which has in fact
    occurred but who have failed to "exhaust" the remedy available to them in the course of
    the proceeding itself. [Citation.] As our Supreme Court has stated it: 'In brief, the rule is
    that where an administrative remedy is provided by statute, relief must be sought from
    the administrative body and this remedy exhausted before the courts will act.' [Citation.]
    The rule is a jurisdictional prerequisite in the sense that it 'is not a matter of judicial
    discretion, but is a fundamental rule of procedure laid down by courts of last resort,
    followed under the doctrine of stare decisis, and binding upon all courts.' " (Citizens for
    Open Government v. City of Lodi (2006) 
    144 Cal. App. 4th 865
    , 874 (Citizens for Open
    Government).)
    For example, if the administrative proceeding includes a right to appeal an
    allegedly improper action, a plaintiff must generally pursue that administrative appeal in
    order to exhaust his or her administrative remedies. " 'If some reasonable administrative
    remedy, such as the right to appeal the action of a planning commission, were afforded to
    challenge such improper action the doctrine of administrative remedies would bar suit by
    22
    litigants who failed to employ it.' " (Tahoe Vista Concerned Citizens v. County of Placer
    (2000) 
    81 Cal. App. 4th 577
    , 590 (Tahoe Vista); see Sea & Sage Audubon Society, Inc. v.
    Planning Com. (1983) 
    34 Cal. 3d 412
    , 417-418.) 3
    Because this exhaustion requirement depends on the availability of a remedy
    within the administrative proceeding, we must examine the procedures applicable to the
    proceeding. " 'Consideration of whether such exhaustion has occurred in a given case
    will depend upon the procedures applicable to the public agency in question.' " (Tahoe
    
    Vista, supra
    , 81 Cal.App.4th at p. 591.)
    "We apply a de novo standard of review to the legal question of whether the
    doctrine of exhaustion of administrative remedies applies in a given case." (Citizens for
    Open 
    Government, supra
    , 144 Cal.App.4th at p. 873.) We likewise review de novo the
    trial court's interpretation of the applicable provisions of the SDMC. (Save Our Heritage
    Organisation v. City of San Diego (2015) 
    237 Cal. App. 4th 163
    , 174.)
    3       This exhaustion requirement is separate from, and in addition to, the requirements
    under CEQA that (1) any grounds for noncompliance with CEQA must be presented to
    the public agency before its decision and (2) a prospective plaintiff must object to
    approval of the project in order to have standing to seek judicial remedies. (§ 21177,
    subds. (a) & (b).) Cal Coast and the City proffer defenses based on these requirements as
    well, but we need not consider them because we reject CLL's contentions on the merits in
    the following sections. Although courts have described section 21177 as "codif[ying] the
    doctrine of exhaustion of administrative remedies for CEQA" (Citizens for Open
    
    Government, supra
    , 144 Cal.App.4th at p. 875), it does not cover every circumstance
    where the doctrine applies. (See Tahoe 
    Vista, supra
    , 81 Cal.App.4th at p. 590
    ["Notwithstanding the Legislature's expressed intent, section 21177 is not properly
    speaking an exhaustion of administrative remedies statute."].) Section 21177 does not
    apply here, for example, where the plaintiff raises a ground for noncompliance before a
    public agency's decision but does not pursue available administrative procedures to
    challenge that decision.
    23
    As noted, the City has established five "decision processes" to handle applications
    for permits, maps, and other planning decisions. (SDMC, § 112.0501.) The City applied
    its "Process Three" to Cal Coast's application. Under Process Three, an application may
    be approved, conditionally approved, or denied by a hearing officer at a public hearing.
    (Id., § 112.0505.) The hearing officer must comply with CEQA's environmental review
    and certify or adopt the appropriate environmental document (e.g., negative declaration,
    MND, or EIR). (Id., § 128.0311, subd. (a).) The hearing officer's decision may be
    appealed to the Planning Commission within 10 business days by filing an application
    with the City Manager. (Id., § 112.0506.) The Planning Commission may affirm,
    reverse, or modify the decision being appealed. (Id., § 112.0506, subd. (f).)
    The SDMC contains a separate section describing the procedure for environmental
    determination appeals. (SDMC, § 112.0520.) The SDMC defines an "environmental
    determination" as "a decision by any non-elected City decisionmaker, to certify an
    environmental impact report, adopt a negative declaration or mitigated negative
    declaration, or to determine that a project is exempt from [CEQA] . . . ." (Id.,
    § 113.0103.) The procedure for environmental determination appeals applies regardless
    of the decision process adopted by the City: "Notwithstanding other provisions of this
    Code, any person may appeal an environmental determination not made by the City
    Council." (Id., § 112.0520, subd. (a), italics omitted.) An environmental determination
    appeal must be filed with the City Clerk within 10 business days of either "the date of
    posting of the Notice of Right to Appeal Environmental Determination" or "the date of a
    24
    decision by a Hearing Officer or the Planning Commission to adopt or certify an
    environmental document." (Id., § 112.0520, subd. (b).)
    The City Council may grant or deny the appeal. (Id., § 112.0520, subd. (e).) If the
    City Council denies the appeal, it will "approve the environmental determination and
    adopt the CEQA findings and statement of overriding considerations of the previous
    decision-maker, where appropriate." (Id., § 112.0520, subd. (e)(2), italics omitted.) If
    the City Council grants the appeal, it will set aside the environmental determination and
    return it to City staff for reconsideration. (Id., § 112.0520, subd. (e)(2), (f)(2).) "The
    Planning Director shall reconsider the environmental determination . . . and prepare a
    revised environmental document as appropriate, in consideration of any direction from
    the City Council." (Id., § 112.0520, subd. (f)(2), italics omitted.) During this time, "[t]he
    lower decision-maker's decision to approve the project shall be held in abeyance. The
    City Council shall retain jurisdiction to act on the revised environmental document and
    associated project at a subsequent public hearing." (Id., § 112.0520, subd. (f)(1).)
    At the subsequent hearing, the City Council has the power to consider the revised
    environmental document and the associated project. "At a subsequent hearing, the City
    Council shall again consider the environmental determination and associated projects,
    and may take action as follows: [¶] (A) Certify or adopt the environmental document;
    adopt CEQA findings and statement of overriding considerations as appropriate; and
    affirm the previous decision to approve the associated project; [¶] (B) Certify or adopt
    the environmental document; adopt CEQA findings and statement of overriding
    considerations as appropriate; condition and approve the associated project as modified;
    25
    or [¶] (C) Find that the environmental document is insufficient, in which case the
    document shall not be certified. The associated project shall be denied and the decision
    shall be deemed the final administrative action." (SDMC, § 112.0520, subd. (f)(3), italics
    omitted.)
    Taken together, these provisions establish a bifurcated appeals procedure for
    Process Three decisions made by a hearing officer. While a hearing officer's "decision"
    may be appealed to the Planning Commission within 10 business days (SDMC,
    § 112.0506, subd. (b)), any environmental determination by the hearing officer must
    simultaneously be appealed to the City Council within the same period (id., § 112.0520,
    subd. (b)(2)). As a result of this bifurcation, an appeal to the Planning Commission
    covers only the nonenvironmental project approvals (e.g., permits), while an appeal to the
    City Council covers the environmental determination. If the City Council grants the
    appeal, however, it may consider the non-environmental project approvals as well.
    The sequencing and interaction of these two appeals is unclear, but we need not
    delve further into City procedure in order to resolve the dispute before us. CLL filed
    only an appeal of the hearing officer's decision to the Planning Commission. It did not
    file an appeal of the hearing officer's environmental determination. It therefore did not
    avail itself of the City's administrative appeals procedure that was available to address
    CLL's objections to the hearing officer's adoption of the MND. CLL did not exhaust its
    26
    administrative remedies regarding the MND, and it may not now bring a judicial action
    challenging it. (See Tahoe 
    Vista, supra
    , 81 Cal.App.4th at p. 592.) 4
    CLL argues its failure to appeal the hearing officer's environmental determination
    is excused because the City's bifurcated appeal procedures are invalid under CEQA. (See
    California Clean Energy Committee v. City of San Jose (2013) 
    220 Cal. App. 4th 1325
    ,
    1346 (California Clean Energy).) CEQA requires the person or persons responsible for
    approving a project (the "decisionmaking body" in CEQA parlance) also be responsible
    for complying with CEQA's environmental review (e.g., by certifying an EIR, adopting a
    negative declaration or MND, or determining that the project is exempt). (See
    Guidelines, §§ 15025, subd. (b), 15356.) Assuming authority is properly delegated
    within the public agency, the decisionmaking body may be an unelected official or
    commission. (California Clean Energy, at p. 1336 & fn. 3.) If the decisionmaking body
    is unelected, however, the decisionmaking body's compliance with CEQA must be
    appealable to the agency's elected decisionmaking body, if any. (§ 21151, subd. (c);
    Guidelines, §§ 15061, subd. (e), 15074, subd. (f), 15090, subd. (b).)
    4      CLL claims that its appeal from the Planning Commission's decision was
    sufficient to appeal the environmental determination to the City Council. CLL relies on
    the SDMC provision governing the timing of environmental determination appeals,
    which must be filed "[w]ithin 10 business days from the date of a decision by a Hearing
    Officer or the Planning Commission to adopt or certify an environmental document."
    (SDMC, § 112.0520, subd. (b), italics added.) But, under the City's Process Three, it was
    the hearing officer who adopted the environmental document, not the Planning
    Commission. CLL therefore had 10 business days from the hearing officer's decision to
    appeal the environmental determination. The later Planning Commission decision on
    nonenvironmental matters did not reset the time to appeal.
    27
    The City's procedure, at least as relevant here, complies with these requirements.
    Under Process Three, the hearing officer has the authority to approve the project and
    comply with CEQA's environmental review. (SDMC, §§ 112.0505, 128.0311, subd. (a).)
    The hearing officer is therefore the City's decisionmaking body under the Guidelines.
    And, because the hearing officer is unelected, the City's procedures allow an appeal of the
    hearing officer's environmental determination to the City's elected City Council. (SDMC,
    § 112.0520.) CLL simply did not avail itself of that procedure.
    CLL relies on California Clean 
    Energy, supra
    , 
    220 Cal. App. 4th 1325
    , but it is
    inapposite. In that case, the local agency had delegated the authority to comply with
    CEQA's environmental review to its planning commission. (Id. at p. 1337.) This
    delegation was improper because the planning commission did not have the authority to
    approve the project at issue. (Id. at pp. 1338, 1340.) The planning commission's
    purported certification of a final EIR for the project was therefore unauthorized by
    CEQA, and the plaintiff's challenge to that certification was not barred by its failure to
    appeal the planning commission's environmental decision. (Id. at p. 1346.) Here, the
    hearing officer's adoption of an MND for the project was procedurally proper, since the
    hearing officer also had the authority to approve the project. California Clean Energy
    does not apply.
    The other authorities CLL cites confirm that the hearing officer's adoption of the
    MND was procedurally proper because he was the City's decisionmaking body for the
    project. (See POET, LLC v. State Air Resources Bd. (2013) 
    218 Cal. App. 4th 681
    , 731
    ["For an environmental review document to serve CEQA's basic purpose of informing
    28
    governmental decision makers about environmental issues, that document must be
    reviewed and considered by the same person or group of persons who make the decision
    to approve or disapprove the project at issue."]; Kleist v. City of Glendale (1976) 
    56 Cal. App. 3d 770
    , 778 ["The state guidelines require that the decision-making body or
    administrative official having final approval authority over a project involving a
    substantial effect upon the environment review and consider an EIR before taking action
    to approve or disapprove the project."]; see also El Morro Community Assn. v. California
    Dept. of Parks & Recreation (2004) 
    122 Cal. App. 4th 1341
    , 1349-1350 ["Guidelines,
    section 15356 specifically defines the '[decisionmaking] body' as 'any person or group of
    people within a public agency permitted by law to approve or disapprove the project at
    issue.' "].) The City's procedure establishing an appeal to the City Council to challenge
    the hearing officer's adoption of the MND was likewise proper. (See Vedanta Society of
    So. California v. California Quartet, Ltd. (2000) 
    84 Cal. App. 4th 517
    , 527-528.) CLL
    was required to pursue this appeal in order to exhaust its administrative remedies.
    CLL argues that the City's appeal procedures are inadequate because the Planning
    Commission has authority over project approvals but not the environmental
    determination. But this alleged inadequacy does not affect the validity of the hearing
    officer's environmental determination, so it provides no excuse for CLL's failure to
    appeal that determination. (Cf. California Clean 
    Energy, supra
    , 220 Cal.App.4th at p.
    1346.) In addition, it is unclear on the current record which procedure would have
    applied had CLL properly appealed the environmental determination. During the first
    Planning Commission meeting below, a deputy city attorney told the commissioners,
    29
    "Had [the appropriate box] been checked, this appeal would be set before the City
    Council and would not be heard before this body."
    CLL also argues the City Council is not a "decisionmaking body" because project
    approval under Process Three progresses from the hearing officer to the Planning
    Commission. (SDMC, § 112.0506.) No independent appeal to the City Council, separate
    from an environmental determination, is authorized. (Ibid.) The Planning Commission's
    decision is final. In CLL's view, the City Council is therefore not a "person or group of
    people within a public agency permitted by law to approve or disapprove the project at
    issue." (Guidelines, § 15356.) If the City grants the environmental determination appeal,
    however, it has such authority. (SDMC, § 112.0520, subd. (f).) Neither CEQA nor the
    Guidelines require that a local agency's elected decisionmaking body accept appeals
    regarding every project approval, separate and apart from environmental review. They
    require only that the environmental determination be appealable. (§ 21151, subd. (c);
    Guidelines, §§ 15061, subd. (e), 15074, subd. (f), 15090, subd. (b).) The City's
    procedures allow exactly that.
    CLL further claims its failure to appeal should be excused based on inaccurate
    descriptions of the City's appeal process in the public hearing notice for Cal Coast's
    project and the City's Information Bulletin 505. The public hearing notice misstated the
    procedure for an environmental determination appeal by implying that the appeal should
    occur after the Planning Commission considered the project: "The adoption of [an MND]
    may be appealed to the City Council after all other appeal rights have been exhausted.
    All such appeals must be filed by 5:00 PM within ten (10) business days from the date of
    30
    the Planning Commission's certification/adoption of the environmental document."
    Under the SDMC, the appeal to City Council for a Process Three project does not occur
    "after all other appeal rights have been exhausted;" it occurs simultaneously with the
    appeal to the Planning Commission. And, while the notice's reference to an appeal
    "within ten (10) business days of the Planning Commission's certification/adoption of the
    environmental document" may be applicable to other projects (see, e.g., SDMC,
    § 112.0507 [describing the City's Process Four]), it is not accurate under the Process
    Three procedures the City applied to this project because the time to appeal ran from the
    hearing officer's adoption of the environmental document. The City's information
    bulletin, which was referenced in the public hearing notice, states that appeals must be
    made in accordance with the SDMC and does not describe the specific procedures, except
    to state, "Appeals of Environmental Determinations may be made after all project appeal
    rights have been exhausted." Again, this statement incorrectly describes the sequencing
    of the project and environmental determination appeals under Process Three, which must
    be pursued simultaneously.
    CLL primarily frames its argument based on these inaccuracies as one of improper
    notice under CEQA. This framing does not fit the facts here. The authorities CLL cites
    discuss the failure to comply with CEQA's requirement that an "alleged grounds for
    noncompliance" with CEQA be presented to a public agency under section 21177,
    subdivision (a). (See Temecula Band of Luiseno Mission Indians v. Rancho Cal. Water
    Dist. (1996) 
    43 Cal. App. 4th 425
    , 433-435 (Temecula Band); McQueen v. Board of
    Directors (1988) 
    202 Cal. App. 3d 1136
    , 1150-1151 (McQueen).) This requirement "does
    31
    not apply to any alleged grounds for noncompliance with this division for which there
    was no public hearing or other opportunity for members of the public to raise those
    objections orally or in writing prior to the approval of the project, or if the public agency
    failed to give the notice required by law." (§ 21177, subd. (e).) In McQueen, the court
    held that an inaccurate and misleading project description is "tantamount to a lack of
    notice" under CEQA, thus excusing the plaintiff's failure to raise a noncompliance issue
    early in the public agency's consideration of the project. 
    (McQueen, supra
    , at p. 1150.)
    Temecula Band agreed with McQueen's interpretation of the statute, but it distinguished
    McQueen on the facts. (Temecula 
    Band, supra
    , at p. 434.) While the project description
    was inaccurate and misleading, as in McQueen, the project was clarified at a subsequent
    public hearing. (Ibid.) The plaintiff failed to object after that clarification, despite an
    opportunity to do so, and therefore its failure to raise a noncompliance issue was not
    excused. (Ibid.)
    CLL's failure to appeal is not a failure to raise a noncompliance issue under
    section 21177. McQueen and Temecula Band therefore have little relevance to the
    administrative exhaustion issue here. And, even taken on their own terms, these
    authorities stand only for the proposition that a plaintiff should be excused from failing to
    raise a noncompliance issue where a misleading project description—or complete lack of
    notice—has misled a plaintiff into believing there is no noncompliance issue at all.
    (§ 21177, subd. (e); Temecula 
    Band, supra
    , 43 Cal.App.4th at p. 434.) It does not apply
    where the public agency has accurately provided notice of a public hearing, but it
    misstates the applicable procedures to appeal the decision made at that hearing.
    32
    Instead, a plaintiff's remedy in this situation is to prevent the public agency from
    invoking an administrative exhaustion defense through equitable estoppel. (See Shuer v.
    County of San Diego (2004) 
    117 Cal. App. 4th 476
    , 487 ["We find, however, that the sum
    total of county's actions . . . negligently led [the plaintiff] to conclude that she had no
    administrative recourse. That being the case, county is estopped from asserting in its
    demurrer that [the plaintiff] failed to exhaust her administrative remedies."]; see also
    Feduniak v. California Coastal Com. (2007) 
    148 Cal. App. 4th 1346
    , 1372 ["[C]ourts will
    not hesitate to estop the government from asserting a procedural barrier, such as the
    statute of limitations or a failure to exhaust remedies, as a defense to claims against it,
    where the government's affirmative conduct caused the claimant's failure to comply with
    the procedural requirement."]; J.H. McKnight Ranch, Inc. v. Franchise Tax Bd. (2003)
    
    110 Cal. App. 4th 978
    , 991; but see Park Area Neighbors v. Town of Fairfax (1994) 
    29 Cal. App. 4th 1442
    , 1449-1450 [equitable estoppel inapplicable to representations on
    matters of law; inaccurate statements did not excuse failure to exhaust administrative
    remedies].) CLL pursued a claim for equitable estoppel in the trial court, but it was
    unsuccessful. CLL has not raised any claim of error regarding equitable estoppel in this
    court. Its failure to exhaust administrative remedies therefore may not be excused on that
    basis.
    III
    Adoption of the MND
    Although we have found that CLL failed to exhaust its administrative remedies
    regarding the City's adoption of an MND for the project, we will nonetheless consider
    33
    CLL's substantive arguments as an alternative ground for our decision. CLL primarily
    argues the hearing officer should not have adopted the MND because the record
    demonstrated a fair argument that the project may have a significant effect on the
    environment that would not be mitigated. CLL contends the City was therefore required
    to prepare an EIR for the project.
    An EIR must be prepared "[i]f there is substantial evidence, in light of the whole
    record before the lead agency, that the project may have a significant effect on the
    environment . . . ." (§ 21080, subd. (d).) " 'May' means a reasonable possibility."
    (Pocket Protectors v. City of Sacramento (2004) 
    124 Cal. App. 4th 903
    , 927 (Pocket
    Protectors).)
    " 'Environment' means the physical conditions which exist within the area which
    will be affected by a proposed project, including land, air, water, minerals, flora, fauna,
    noise, objects of historic or aesthetic significance." (§ 21060.5.) " 'Significant effect on
    the environment' means a substantial, or potentially substantial, adverse change in the
    environment." (§ 21068.) "An economic or social change by itself shall not be
    considered a significant effect on the environment. A social or economic change related
    to a physical change may be considered in determining whether the physical change is
    significant." (Guidelines, § 15382; see § 21082.2, subd. (c).)
    "[S]ubstantial evidence includes fact, a reasonable assumption predicated upon
    fact, or expert opinion supported by fact." (§ 21080, subd. (e)(1).) "Substantial evidence
    is not argument, speculation, unsubstantiated opinion or narrative, evidence that is clearly
    inaccurate or erroneous, or evidence of social or economic impacts that do not contribute
    34
    to, or are not caused by, physical impacts on the environment." (§ 21080, subd. (e)(2).)
    "The existence of public controversy over the environmental effects of a project shall not
    require preparation of an environmental impact report if there is no substantial evidence
    in light of the whole record before the lead agency that the project may have a significant
    effect on the environment." (§ 21082.2, subd. (b).) "Relevant personal observations of
    area residents on nontechnical subjects may qualify as substantial evidence . . . .
    [Citations.] So may expert opinion if supported by facts, even if not based on specific
    observations as to the site under review." (Pocket 
    Protectors, supra
    , 124 Cal.App.4th at
    p. 928.)
    The agency does not weigh the potential effect on the environment if substantial
    evidence supports both the preparation of an EIR and the opposite. "[I]f a lead agency is
    presented with a fair argument that a project may have a significant effect on the
    environment, the lead agency shall prepare an EIR even though it may also be presented
    with other substantial evidence that the project will not have a significant effect."
    (Guidelines, § 15064, subd. (f)(1); see No Oil, Inc. v. City of Los Angeles (1974) 
    13 Cal. 3d 68
    , 75.) For example, "[i]f there is disagreement among expert opinion supported
    by facts over the significance of an effect on the environment, the Lead Agency shall
    treat the effect as significant and shall prepare an EIR." (Guidelines, § 15064, subd. (g).)
    "The fair argument standard creates a 'low threshold' for requiring an EIR, reflecting a
    legislative preference for resolving doubts in favor of environmental review." (Preserve
    Poway v. City of Poway (2016) 
    245 Cal. App. 4th 560
    , 576.)
    35
    The hearing officer's "decision to issue a negative declaration in connection with
    [the project] is reviewed for 'prejudicial abuse of discretion,' which 'is established if the
    agency has not proceeded in a manner required by law or if the determination or decision
    is not supported by substantial evidence.' " (Save the Plastic 
    Bag, supra
    , 52 Cal.4th at
    p. 171, quoting § 21168.5.) " 'In reviewing the adoption of [a negative declaration], our
    task is to determine whether there is substantial evidence in the record supporting a fair
    argument that the Project will significantly impact the environment; if there is, it was an
    abuse of discretion not to require an EIR. [Citation.] " 'Whether a fair argument can be
    made is to be determined by examining the entire record.' " [Citation.]' [Citation.]
    'Although our review is de novo and nondeferential, we must give the lead agency the
    benefit of the doubt on any legitimate, disputed issues of credibility.' " (Joshua Tree
    Downtown Business Alliance v. County of San Bernardino (2016) 1 Cal.App.5th 677, 684
    (Joshua Tree).)
    As the appellant, CLL bears the burden of identifying in the record substantial
    evidence of a fair argument that the project may have a significant effect on the
    environment that would not be mitigated. (See Citizens for Responsible and Open
    Government v. City of Grand Terrace (2008) 
    160 Cal. App. 4th 1323
    , 1332.) CLL
    contends the project may have significant effects in the areas of fire hazards, traffic and
    transportation, noise, recreation, and historical resources.
    For reasons we will explain, CLL has not made a sufficient showing here. The
    project at issue is relatively modest and located on already-developed land. The record
    does not reflect any fair argument that the project may have a significant effect on the
    36
    environment that would not be mitigated. We will address each of the areas CLL
    identifies in turn. 5
    Fire Hazards
    A project may have a significant effect on the environment by increasing the risk
    of fire hazards, including wildfires. Here, however, CLL has not shown the project
    would have any significant effect on fire hazards in the area. The project meets all
    applicable fire codes, the project site is already developed, and CLL's large commercial
    horse ranch already operates on the neighboring parcel. The area already sees vehicular
    and pedestrian traffic. CLL has not shown any of the project's activities have a
    reasonable possibility of significantly increasing the risk of fire hazards. Indeed, by
    incorporating a new water line and fire hydrant, the project appears to increase fire safety
    in the area.
    CLL focuses on the location of the project in a Very High Fire Hazard Severity
    Zone (see Gov. Code, § 51178) and the risk to persons and property from potential
    wildfires in the area. CLL's focus is misplaced. As our Supreme Court has explained,
    "we must distinguish between requirements that consider the environment's effects on a
    project and those that contemplate the project's impacts on the existing environment."
    
    (CBIA, supra
    , 62 Cal.4th at p. 388.) Only the latter impacts are valid under CEQA. It is
    5     CLL's opening brief presents its argument that there was substantial evidence in
    chronological order, identifying in turn bits of evidence in the City's initial study,
    comments to the draft and final MND, and testimony before the hearing officer and at the
    Planning Commission. Presenting this information chronologically, rather than by topic,
    makes our review of CLL's argument more difficult and lessens its persuasive value.
    37
    proper to evaluate "a project's potentially significant exacerbating effects on existing
    environmental hazards—effects that arise because the project brings 'development and
    people into the area affected.' " (Ibid.) But considering existing environmental hazards,
    unchanged by the project, are not proper under CEQA. "CEQA generally does not
    require an analysis of how existing environmental conditions will impact a project's
    future users or residents." (Id. at p. 386.) 6
    CLL argues the project will inhibit the ability of people and, at the ranch, animals
    to evacuate in the event of a wildfire. CLL points to the alleged "inability to timely and
    safely evacuate 95 school personnel and students in conjunction with [CLL's] 135 horses
    and 15 cattle, ranch personnel, clients and trailers through the narrow Clews Ranch
    Road." But Clews Ranch Road is 20 feet wide and only 1,650 feet long. Complaints
    about its inadequacy are speculative. The project will also have an alternate evacuation
    route westward along a dirt road, and it intends to operate only part of the year and will
    close on red flag warning days. The inherent difficulty in evacuating "135 horses and 15
    cattle, ranch personnel, clients and trailers" already exists and will not be significantly
    affected by the project. Viewing the record as a whole, there is no fair argument that the
    project will materially affect evacuation routes in the area.
    CLL relies on the comments submitted by its fire safety expert, Van
    Collingsworth. His comments consist largely of general observations regarding fire
    6      CEQA provides for exceptions to this general rule in certain specific contexts,
    including school construction projects near hazardous waste disposal sites or freeways.
    (§ 21151.8, subd. (a)(3)(B); see 
    CBIA, supra
    , 62 Cal.4th at p. 391.) Very High Fire
    Hazard Severity Zones are not included.
    38
    hazards not tied to the project, questions about the project, and topics allegedly
    unaddressed or inadequately addressed in the MND and project materials. His general
    observations cannot, in and of themselves, create a fair argument without some nexus
    with the project itself. His questions about the project and the topics allegedly
    unaddressed or inadequately addressed also cannot create a fair argument without some
    showing that those questions and topics refer to a potentially significant effect on the
    environment that the project may create. Collingsworth also focuses on the effect of the
    environment on the project (students and faculty at the school), rather than the effect of
    the project on the environment, which is incorrect for the reasons we have already
    discussed. Collingsworth's remaining comments are conclusory, speculative, or
    otherwise unsupported. They are likewise insufficient.
    CLL has not shown that there is a fair argument that the project's effect on the fire
    hazards in the environment, including as a consequence of bringing additional people into
    the area, may be significant. The City therefore was not required to prepare an EIR on
    this basis.
    Traffic and Transportation
    A project may have a significant effect on the environment by increasing traffic or
    impeding transportation. Various comments from the public argued the project here
    would create an unreasonable traffic situation on Clews Ranch Road. They claimed that
    the road could not support the estimated 117 additional daily trips caused by the project
    because the road was narrow, "may create conflicts for two-way traffic," and was used by
    pedestrians and horses as well. Barbara Clews and others contended that there were also
    39
    "blind corners" on the road. As to the last comment, it appears contradicted by the actual
    condition of the road, which is only 1,650 feet long and largely straight. On direct issues
    of credibility, we must defer to the hearing officer. (See Joshua 
    Tree, supra
    , 1
    Cal.App.5th at p. 684.) The remaining comments are insufficient to create a fair
    argument that the project may have a significant impact on traffic and transportation.
    Clews Ranch Road was 20 feet wide and allowed two-way traffic. It had supported
    traffic to and from CLL's large commercial horse ranch and the project site, including
    during special events, without incident.
    The factual situation here is far different from the situation in Keep Our
    Mountains Quiet v. County of Santa Clara (2015) 
    236 Cal. App. 4th 714
    , which CLL cites.
    In that case, an initial report by the California Department of Transportation found there
    would be " 'significant impacts to the operations and traffic movements to the site
    entrances' and 'might impede [Summit Road] in both directions because of numerous
    vehicles making right and left-turns into the site.' " (Id. at p. 725.) The road leading to
    the project site was winding and very narrow (under 10 feet at one point), with 39 blind
    curves. (Id. at p. 727.) The accident rate was twice the statewide average. (Id. at pp.
    726-727.) No such facts were developed here.
    The commenters' predictions of significant impacts alone are insufficient absent
    specific facts in the record supporting a fair argument. " '[I]n the absence of a specific
    factual foundation in the record, dire predictions by nonexperts regarding the
    consequences of a project do not constitute substantial evidence.' " (Joshua 
    Tree, supra
    ,
    1 Cal.App.5th at p. 690.) CLL has not shown that there is a fair argument that the
    40
    project's effect on traffic and transportation may be significant. The City was not
    required to prepare an EIR on this basis.
    Noise
    A project may have a significant effect on the environment through the noise it
    generates. (See Oro Fino Gold Mining Corp. v. County of El Dorado (1990) 
    225 Cal. App. 3d 872
    , 882 [noise generated by gold mine's drilling rig].) Several commenters
    associated with CLL's horse ranch predicted significant noise impacts because noises
    from school activities could disrupt ranch operations. For example, one commenter
    described incidents in which construction noise at the project site had frightened horses
    and caused them to throw their riders. But the possibility that noise will impact the horse
    ranch's operations is insufficient. "Under CEQA, the question is whether a project will
    affect the environment of persons in general, not whether a project will affect particular
    persons." (Mira Mar Mobile Community v. City of Oceanside (2004) 
    119 Cal. App. 4th 477
    , 492.) The noise likely generated by the school (children laughing and playing, cars
    driving, doors closing, etc.) is insignificant in the context of the environment as a whole,
    especially given the project's location near a busy highway, State Route 56, and CLL's
    large ranch.
    Even if the noise generated by the school adversely impacted the ability of the
    ranch to continue operation as a viable business, the impact on the ranch alone would be
    insufficient to support preparation of an EIR. The fact that a project may affect another
    business's economic viability is not an effect covered by CEQA unless it results in a
    change in the physical environment (e.g., urban decay). (Joshua 
    Tree, supra
    , 1
    41
    Cal.App.5th at p. 685.) CLL has not shown that there is a fair argument that the project's
    effect on noise in the environment may be significant. The City was not required to
    prepare an EIR on this basis.
    Recreation
    A project may have a significant effect on the environment if it reduces available
    recreation activities. The project here will use a public parking lot serving nearby trails
    as a pick-up and drop-off point for its shuttles. Commenters believed the school's use of
    the parking lot would leave little room for other users. For example, the CVCPB
    expressed concern that "[u]nresolved operational issues such as the drop-off and pickup
    location may impact traffic flow on Carmel Country Road and [the location] may be
    inadequate for the added use beyond much needed parking for the heavily used CVREP
    public trails." Speculation by commenters such as the CVCPB is not substantial
    evidence, and it is insufficient to support a fair argument that the project may have a
    significant impact on recreation. (Joshua 
    Tree, supra
    , 1 Cal.App.5th at p. 690.) CLL has
    not shown the City was required to prepare an EIR on this basis.
    Historical Resources
    A project may have a significant effect on the environment if it affects historical
    resources. The project here would not alter the historic farmhouse on the site or its
    outbuildings, and the architecture of the new school on the property is consistent with the
    farmhouse's aesthetic. CLL claims the City should have undertaken additional study of
    the project's impact on the broader Mount Carmel Ranch historical resource, but such
    criticism is mere rhetoric without facts supporting such an impact. CLL has not shown
    42
    that there is a fair argument that the project's effect on historical resources may be
    significant. The City was not required to prepare an EIR on this basis. We will address
    the City's compliance with its historical resource regulations in part IV, post.
    IV
    Recirculation of the MND
    To achieve the public notice purposes of CEQA, an MND must be recirculated if
    it is substantially revised after its release but prior to adoption. (Guidelines, § 15073.5,
    subd. (a).) A substantial revision includes the circumstances where "[a] new, avoidable
    significant effect is identified and mitigation measures or project revisions must be added
    in order to reduce the effect to insignificance," or "[t]he lead agency determines that the
    proposed mitigation measures or project revisions will not reduce potential effects to less
    than significance and new measures or revisions must be required." (Guidelines,
    § 15073.5, subd. (b)(1)-(2).) Recirculation is not required where "[n]ew project revisions
    are added in response to written or verbal comments on the project's effects identified in
    the proposed negative declaration which are not new avoidable significant effects";
    "[m]easures or conditions of project approval are added after circulation of the negative
    declaration which are not required by CEQA, which do not create new significant
    environmental effects and are not necessary to mitigate an avoidable significant effect";
    or "[n]ew information is added to the negative declaration which merely clarifies,
    amplifies, or makes insignificant modifications to the negative declaration." (Guidelines,
    § 15073.5, subd. (c)(2)-(4).)
    43
    CLL contends the school's shuttle bus plan and its intent to close on red flag
    warning days, which were added to the project after the MND was circulated, constitute
    new mitigation measures that required recirculation. We disagree. These plans were
    purely voluntary, so they cannot constitute mitigation measures. (Guidelines, § 15126.4,
    subd. (a)(2).) And CLL has not shown they were added to the project to reduce
    significant effects on the environment for the reasons discussed above. Moreover,
    additional information about the project's design and layout, its evacuation plan, and its
    brush management plan, which were also added after circulation, were clarifying and
    amplifying in nature and did not make substantial revisions to the project. (See
    Guidelines, § 15126.4, subd. (c)(4).) Recirculation was not required.
    V
    Historical Resource Regulations
    CLL contends the City failed to follow its historical resource regulations (SDMC,
    § 143.0201 et seq.) and the Historical Resources Guidelines of the City's Land
    Development Manual (HRG). To succeed, CLL must establish a prejudicial abuse of
    discretion, i.e., it must show that the City's actions were "arbitrary, capricious, in excess
    of its jurisdiction, entirely lacking in evidentiary support, or without reasonable or
    rational basis as a matter of law." (Sierra Club v. County of Napa (2004) 
    121 Cal. App. 4th 1490
    , 1497 (Sierra Club).) "A prejudicial abuse of discretion is established
    if the agency has not proceeded in a manner required by law, if its decision is not
    supported by findings, or if its findings are not supported by substantial evidence in the
    record." (Ibid.; see § 21168.5)
    44
    CLL advances two interrelated arguments in an attempt to show the City did not
    proceed as required by law: (1) the historical resource regulations require the City to
    apply its "Process Four" to the project, which would involve review by the City's
    Historical Resources Board, and (2) the regulations require the City to analyze the effect
    of the project on Mount Carmel Ranch, the broader historical resource of which the
    project site's historic farmhouse is a part.
    The City's historical resource regulations apply whenever historical resources,
    including designated historical resources, are present at a project site. (SDMC,
    § 143.0210, subd. (a)(1).) The City must proceed under Process Four for certain types of
    development when a designated historical resource is present. (Id., § 126.0502, subd.
    (d)(1).) The types of development that require Process Four are subdivisions, single or
    multiple unit residential developments, commercial or industrial developments, public
    works projects, and any developments that deviate from the historical resources
    regulations. (Ibid.) The historical resources regulations similarly require Process Four
    for subdivisions, single or multiple unit residential developments, commercial or
    industrial developments, public works projects (other than capital improvement program
    projects), land use plans, and any developments that deviate from the historical resources
    regulations (other than capital improvement program projects). (Id., § 143.0210, subd.
    (e)(2).)
    Even if these requirements apply, the historical resource regulations contain
    certain exemptions. (SDMC, § 143.0220; see 
    id., §§ 126.0502,
    subd. (d)(1), 143.0210,
    subd. (e).) One of these exemptions covers "[a]ny development that proposes minor
    45
    alterations or improvements consistent with [SDMC] Section 143.0250, subdivision (a),
    to a designated historical resource, or any historical building or historical structure
    located within a historical district, or any new construction within a historical district that
    will enhance, restore, maintain, repair, or allow adaptive reuse of the resource and which
    will not adversely affect the special character or special historical, architectural,
    archaeological, or cultural value of the resource when all feasible measures to protect and
    preserve the historical resource are included in the development proposal consistent with
    the Secretary of Interior's Standards and Guidelines." (Id., § 143.0220, subd. (a), italics
    omitted.)
    In the report to the Planning Commission for the project, City staff explained that
    the project falls within this exemption because it is new construction that is consistent
    with the Secretary of the Interior's Standards and Guidelines, the HRG, and the historical
    resource regulations. In arguing that Process Four applies, CLL does not address the
    substance of this exemption. It merely criticizes the City's reliance on the exemption as a
    post hoc rationalization. Such criticism is insufficient without a showing that Process
    Four should have been applied. "The decisions of the agency are given substantial
    deference and are presumed correct. The parties seeking mandamus bear the burden of
    proving otherwise, and the reviewing court must resolve reasonable doubts in favor of the
    administrative findings and determination." (Sierra 
    Club, supra
    , 121 Cal.App.4th at p.
    1497.)
    CLL also criticizes the City for not complying with the requirements of the
    historical resource regulations and the HRG, particularly the absence of any detailed
    46
    analysis of the project's effect on the Mount Carmel Ranch, the broader historical
    resource of which the project site's historic farmhouse is a part, or of the project's Area of
    Potential Effect. Again, CLL's criticism is insufficient. Inadequate explanation
    regarding compliance is not the same as noncompliance. (See Sierra 
    Club, supra
    , 121
    Cal.App.4th at p. 1497.)
    CLL's further contention that a recommendation of the Historical Resources Board
    was required is incorrect; such a recommendation is only required under Process Four.
    (SDMC, § 126.0504, subd. (b)(2).) And its contention that approval of Cal Coast's
    project should have been handled under the same procedures as the prior approval of its
    commercial horse ranch is unpersuasive. The mere fact that CLL complied with different
    procedures does not show that Cal Coast should be held to those procedures. CLL has
    not shown the City erred.
    VI
    Consistency with the Carmel Valley Neighborhood 8 Precise Plan
    CLL argues that the project conflicts with the Carmel Valley Neighborhood 8
    Precise Plan (Precise Plan) adopted by the City. The Precise Plan "provides development
    guidelines for the Neighborhood 8 portion of Carmel Valley, a designated community
    plan area within the City[.]" "The Neighborhood 8 Precise Plan also functions as a
    component in the development implementation process . . . . The precise plan constitutes
    one of a series of steps in the City approval of development projects in Neighborhood 8.
    The Carmel Valley Community Plan provides guidelines, proposals and concepts for the
    future development of the entire Carmel Valley community. The precise plan is used by
    47
    the individual neighborhoods, within the larger Carmel Valley Plan context, to determine
    how the specific development unit will take shape. It is the precise plan's role to address
    issues such as development density, road alignments and community facility sites. The
    adopted precise plans then become the basis for reviewing subsequent development
    plans, subdivisions, and other permits within their respective development units." While
    subordinate to the City's General Plan and the Carmel Valley Community Plan, the
    Precise Plan guides development in the same way for projects within its area of concern.
    The most recent Precise Plan, issued in 2012, designates the project site as open
    space. In their report to the hearing officer, City staff identified the site as designated
    natural open space. The report explained, however, that development on the site was
    consistent with the Precise Plan because the area had already been disturbed: "The
    project site has been previously disturbed by the prior construction of several concrete
    pads void of any structures, several accessory buildings, a swimming pool and the
    historic residential structure. These improvements are or were dispersed throughout the
    property. The proposed school building is located in an area on the site which was
    previously developed with a swimming pool which has since been capped and covered
    with a concrete pad. New drive aisles and parking areas would be located in areas of
    previous disturbance and are either covered in concrete/asphalt/gravel or are existing
    unpaved driveways and/or parking areas. The project design limits new development to
    previously developed and disturbed areas in conformance with the Precise Plan's Open
    Space policies." In the report to the Planning Commission following CLL's appeal, City
    48
    staff reiterated their analysis and found no inconsistency between the project and the
    Precise Plan.
    The site development permit issued by the Planning Commission confirms that the
    project site "is designated Open Space by the Precise Plan." But it explained, "The
    proposed Project will be developed on previously disturbed land and will not impact or
    develop on existing undisturbed open space and [the Multi-Habitat Planning Area] land."
    It therefore found that the project would not "adversely affect the applicable land use
    plan." 7
    Any local land use or development decision, including approval of the project at
    issue here, must be consistent with the applicable general plan and its constituent
    elements. (Orange Citizens for Parks and Recreation v. Superior Court (2016) 2 Cal.5th
    141, 153 (Orange Citizens).) We review the City's finding that the project is consistent
    with the Precise Plan for abuse of discretion. (Id. at p. 154.) "A city's determination that
    a development approval is consistent with its general plan has been described by some
    courts as 'adjudicatory' [citation] and by others as 'quasi-legislative' [citation]. Where a
    consistency determination involves the application of a general plan's established land
    use designation to a particular development, it is fundamentally adjudicatory. In such
    7       Curiously, the City and Cal Coast in their joint respondents' brief take the position
    that the project site is not designated open space. They rely on an earlier 1990 Precise
    Plan and baldly assert that "any later designation of the site as 'open space' would have
    been a factual error." This assertion contradicts the City's position in the approved site
    development permit and the repeated analyses of City staff. While we need not explore
    the consequences of such inconsistency in this appeal, since an alternative ground exists
    on which to reject CLL's challenge, it is troubling.
    49
    circumstances, a consistency determination is entitled to deference as an extension of a
    planning agency's ' "unique competence to interpret [its] policies when applying them in
    its adjudicatory capacity." ' [Citation.] Reviewing courts must defer to a procedurally
    proper consistency finding unless no reasonable person could have reached the same
    conclusion." (Id. at pp. 154-155.) "The party challenging a city's determination of
    general plan consistency has the burden to show why, based on all of the evidence in the
    record, the determination was unreasonable." (San Diego Citizenry Group v. County of
    San Diego (2013) 
    219 Cal. App. 4th 1
    , 26.)
    CLL focuses on the project's site's multifamily residential (MF-1) zoning and
    contends that zoning is inconsistent with an open space designation. While "[a] zoning
    ordinance that conflicts with a general plan is invalid at the time it is passed" (Lesher
    Communications, Inc. v. City of Walnut Creek (1990) 
    52 Cal. 3d 531
    , 544), the City's
    zoning decision is not at issue here. The multifamily residential zoning was implemented
    prior to the latest Precise Plan's open space designation. The Precise Plan contemplated a
    change in the site's zoning from multifamily residential to open space, but it appears this
    change has not occurred.
    The issue here is whether the project is consistent with the Precise Plan's open
    space designation. CLL does not persuasively address the reasoning behind the City's
    consistency determination, which was based on previous development at the site. CLL
    references the general concern for open space, natural vistas, and recreation described in
    the Precise Plan and similar documents, but it does not explain how the City abused its
    discretion in finding that the development of the school at issue here would be consistent
    50
    with the objectives of the open space designation. (CLL's claim that the CVREP trails
    would be affected by the project's use of the trailhead parking lot has been addressed and
    rejected above.)
    The City could reasonably conclude that the project was consistent with the
    Precise Plan and its open space designation because the proposed school will be built on
    already developed land, next to a large commercial horse farm, and will be consistent
    with the historic nature of the site. (See Orange 
    Citizens, supra
    , 2 Cal.5th at p. 157
    [" '[S]tate law does not require perfect conformity between a proposed project and the
    applicable general plan.' "].) CLL's bare assertion that further evaluation was needed is
    insufficient.
    VII
    Site Development Permit Findings
    CLL contends, based on its previous arguments, that the City's findings in the site
    development permit are not supported by the evidence. We find that contention
    unpersuasive for the reasons we have already discussed with respect to CLL's specific
    arguments above.
    51
    DISPOSITION
    The judgment is affirmed.
    McCONNELL, P. J.
    WE CONCUR:
    HUFFMAN, J.
    AARON, J.
    52
    Filed 1/8/18
    CERIFIED FOR PUBLICATION
    COURT OF APPEAL, FOURTH APPELLATE DISTRICT
    DIVISION ONE
    STATE OF CALIFORNIA
    CLEWS LAND AND LIVESTOCK, LLC et                  D071145
    al.,
    Plaintiffs and Appellants,
    v.                                        (Super. Ct. No. 37-2015-00032905-
    CU-TT-CTL)
    CITY OF SAN DIEGO,
    Defendant and Respondent,                    ORDER CERTIFYING OPINION
    FOR PUBLICATION
    JAN DUNNING et al.,
    Real Parties in Interest and
    Respondents.
    THE COURT:
    The opinion filed December 20, 2017 was not certified for publication. It
    appearing the opinion meets the standards for publication specified in California Rules of
    Court, rule 8.1105(c), the requests pursuant to California Rules of Court, rule 8.1120(a)
    for publication are GRANTED.
    IT IS HEREBY CERTIFIED that the opinion meets the standard for publication
    specified in California Rules of Court, rule 8.1105(c); and
    ORDERED that the words "Not to Be Published in the Official Reports" appearing
    on page 1 of said opinion be deleted and the opinion herein be published in the Official
    Reports.
    McCONNELL, P. J.
    Copies to: All parties