Bay Area Clean Environment v. Santa Clara Co. ( 2016 )


Menu:
  • Filed 8/31/16
    CERTIFIED FOR PUBLICATION
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    SIXTH APPELLATE DISTRICT
    BAY AREA CLEAN ENVIRONMENT,                        H040789
    INC.,                                             (Santa Clara County
    Super. Ct. No. 1-12-CV229236)
    Plaintiff and Appellant,
    v.
    SANTA CLARA COUNTY et al.,
    Defendants and Respondents;
    LEHIGH SOUTHWEST CEMENT
    COMPANY et al.
    Real Parties In Interest and
    Respondents.
    The Permanente Quarry (Quarry) is a 3,510-acre surface mining operation
    producing limestone and aggregate for the manufacture of cement, and is located in an
    unincorporated area of Santa Clara County. The Quarry has been in existence since
    1903, and is currently owned by Lehigh Southwest Cement Company and Hanson
    Permanente Cement (collectively “Lehigh”).
    At issue in this case is the Santa Clara County Board of Supervisors’ (County)
    2012 approval of a reclamation plan amendment for closing and reclaiming the Quarry’s
    mining operations over a 20-year period. The County approved the reclamation plan
    amendment following a review under the California Environmental Quality Act (CEQA)
    (Pub. Resources Code, § 21000, et seq.) and certification of an environmental impact
    report.
    Bay Area Clean Environment, Inc. (Bay Area) is a non-profit organization that
    represents residents of Santa Clara County. On July 26, 2013, Bay Area filed a petition
    for peremptory writ of mandate challenging the County’s approval of the reclamation
    plan amendment. Bay Area asserted claims under the Surface Mining and Reclamation
    Act (SMARA) (Pub. Resources Code, § 2710, et seq.) and CEQA.
    The trial court denied Bay Area’s writ petition, affirming the County’s approval of
    the reclamation plan amendment. Bay Area appeals the denial of the petition, arguing
    that the trial court erred in affirming the County’s decision, because the reclamation plan
    amendment does not comply with SMARA and CEQA.1
    STATEMENT OF THE FACTS AND CASE2
    The Quarry is located at the end of Permanente Road, which is the continuation of
    Stevens Creek Road in unincorporated Santa Clara County near the western border of the
    1
    The Towns of Los Altos Hills and Atherton, and the cities of Cupertino and Los
    Altos filed an application to file an amicus curiae brief in support of Bay Area. County
    requested leave to file an objection to the application. We granted County leave to file
    the objection, and deferred consideration of the application and the objection with the
    appeal. County’s objection to the application to file an amicus brief is overruled and the
    application is granted.
    2
    Bay Area filed a request for judicial notice that we deferred for consideration
    with the appeal. The first item that is the subject of Bay Area’s request is the fact that
    Midpeninsula Regional Open Space District brought an action against Santa Clara
    County alleging the same claims as were alleged in the trial court in this case.
    Midpeninsula filed a notice of appeal in this court in case number H040839 and later
    dismissed the appeal. We take notice of the action under Evidence Code section 452,
    subdivision (c).
    Bay Area’s request that we take judicial notice of information contained in the
    Federal Register about aquatic life is denied, because it is not properly noticeable under
    Evidence Code section 452.
    2
    city of Cupertino. Since 1903, the Quarry has been conducting a surface mining
    operation producing limestone and aggregate.
    In 1939, The Permanente Corporation (Permanente) purchased the Quarry
    property, which at that time consisted of approximately 1,300 acres. From the date of the
    original purchase in 1939, Permanente expanded the Quarry’s operations, opening new
    mining areas on the property, and acquiring adjacent land. By 2011, the Quarry had
    grown to 3,510 acres.
    The Quarry has a central pit where limestone and other rock are mined. There are
    two overburden3 storage areas surrounding the pit. The Quarry also contains a rock
    crushing area and administrative offices. The quarry operates within the upper portion of
    the Permanente Creek watershed. The creek flows east and borders the south side of the
    pit, then leaves the Quarry property and runs to the bay.
    The Quarry’s first reclamation plan was approved by the County in 1985, and was
    meant to be updated after a 25-year period. In 2006, the Department of Conservation
    found that the Quarry was in violation of SMARA, because the 1985 reclamation plan
    did not provide a solution for slope instability. In response to the Department of
    Conservation’s finding, the County issued a notice of violation to the Quarry in
    October 2006, ordering that the 1985 plan be amended to address slope instability, and to
    expand the boundaries to encompass all areas disturbed by mining.
    In addition to slope instability occurring in the Quarry, selenium levels
    downstream of the Quarry were discovered to be above normal levels. The elevated
    selenium levels could adversely affect aquatic life in the downstream areas. The
    selenium levels were the result of mining operations that caused limestone surfaces to be
    exposed to oxygen and water.
    3
    Overburden in mining is the “material overlying a deposit of useful geological
    materials or bedrock.” (Merriam-Webster 10th Collegiate Dict. (2001) p. 826.)
    3
    In April 2007, Lehigh filed an application to amend the 1985 reclamation plan.
    Since that time, three amendment applications have been filed. The 2007 and 2010
    amendments included proposals to open new mining areas to replace the reclaimed pit.
    Specifically, the 2010 amendment proposed the creation of a new pit in an area south of
    Permanente Creek, called the South Quarry. The July 2011 application that is the subject
    of this appeal did not in include the South Quarry proposal, and superseded all earlier
    applications.
    The County issued a draft environmental impact report for public review on
    December 23, 2011. The County set a 60-day review period, ending February 21, 2012.
    The County Planning Commission held five workshops to receive public input and
    comment. In May 2012, the County published the final environmental impact report that
    consisted of the draft as well as public comments and revisions to the draft. At the
    June 7, 2012 meeting, the Planning Commission approved the reclamation plan
    amendment, certified the final environmental impact report, and made CEQA findings.
    Following an appeal of the County Planning Commission’s action, the County
    reviewed the reclamation plan amendment. On June 26, 2012, the County voted to
    approve the reclamation plan amendment and certify the environmental impact report. In
    doing so, the County found that the reclamation plan amendment was designed to protect
    water quality and was consistent with SMARA and County ordinances. The County also
    found that the reclamation plan amendment would achieve compliance with all applicable
    water standards and the 5.0 micrograms per liter selenium standard. The County found
    that the potential impacts of excess selenium runoff during the 20-year period of
    reclamation were significant and unavoidable, because the effectiveness of the mitigation
    measures during that period was uncertain. Finally, based on information provided by
    water-quality experts, the County found that a water treatment facility was not feasible
    4
    because the technology for such a facility would be unproven and the costs were
    disproportionately high.4
    On July 26, 2012, Bay Area filed a petition for writ of mandate in the Santa Clara
    County Superior Court, asserting claims under SMARA and CEQA. On
    November 29, 2012, the Midpeninsula Regional Open Space District (Midpeninsula) also
    filed suit alleging CEQA claims. The two actions were consolidated for hearing and on
    September 13, 2013, the court affirmed the County’s approval of the reclamation plan
    amendment. A consolidated judgment was entered denying both petitions for writ of
    mandate. Midpeninsula filed a notice of appeal in this court on February 27, 2014, and
    Bay Area filed its notice on March 3, 2014.
    Midpeninsula settled its dispute with Lehigh, and dismissed its appeal on August
    20, 2014. Bay Area proceeds with this appeal.
    DISCUSSION
    On appeal, Bay Area asserts that in approving the reclamation plan amendment for
    the Quarry, the County violated SMARA and CEQA. Bay Area also argues that the trial
    court erred in allowing the County to augment the administrative record.
    SMARA Claims
    Bay Area argues that the County abused its discretion when it determined that the
    reclamation plan amendment satisfied SMARA regulatory standards for water quality and
    wildlife habitat. (Pub. Resources Code, § 2710, et seq.) The reclamation plan
    amendment in this case was designed to reclaim all of the land affected by mining
    operations in the Quarry and would occur over a 20-year period.
    4
    Bay Area filed a motion to strike portions of the County’s brief that included
    information regarding Lehigh’s implementation of a water treatment system to reduce
    selenium levels. This information was not part of the administrative record and was not
    considered by the County. Bay Area’s motion to strike page 19 in the final paragraph
    beginning, “These protections . . .” through the end of the paragraph on page 20, and
    page 25, last line, parenthetical phrase “(which is now in operation)” is granted.
    5
    SMARA was enacted in 1975 to implement a comprehensive surface mining and
    reclamation policy, which would, among other objectives, prevent or minimize adverse
    environmental effects and eliminate residual public health and safety hazards generally
    attendant to surface mining. (Pub. Resources Code, § 2712.) Also in 1975, the County
    amended its mining ordinance to require mine operators to periodically obtain a
    certificate of compliance. A certificate of compliance verifies that existing mining
    operations comply with permit conditions, County ordinances, and federal and state
    statutes. (Santa Clara County Code, §§ 16.54.020, 16.54.100.) In 1987, SMARA was
    amended to require existing mining operations without approved reclamation plans to
    submit proposed reclamation plans by March 31, 1998 for approval by the lead agency.
    (Pub. Resources Code, § 2770, subds. (a), (b).) “Reclamation” is land treatment that
    minimizes the adverse effects of mining operations so that mined lands may be reclaimed
    to a usable condition. (Pub. Resources Code, § 2733.)
    Approval of a reclamation plan under SMARA is reviewed for abuse of discretion
    pursuant to Code of Civil Procedure section 1094.5. (Hansen Bros. Enterprises, Inc. v.
    Board of Supervisors (1996) 
    12 Cal. 4th 533
    , 543.) We consider all reasonable inferences
    from the administrative record in favor of the agency. (Evid. Code, § 664; Norris v. State
    Personnel Bd. (1985) 
    174 Cal. App. 3d 393
    , 396.)
    Water Quality
    SMARA’s water quality provisions state the following: “(a) Surface mining and
    reclamation activities shall be conducted to protect on-site and downstream beneficial
    uses of water in accordance with the PorterCologne Water Quality Control Act, Water
    Code section 13000, et seq., and the Federal Clean Water Act, 33 U.S.C. section 1251, et
    seq. (b) The quality of water, recharge potential, and storage capacity of ground water
    aquifers which are the source of water for domestic, agricultural, or other uses dependent
    on the water, shall not be diminished, except as allowed in the approved reclamation
    6
    plan. (c) Erosion and sedimentation shall be controlled during all phases of construction,
    operation, reclamation, and closure of a surface mining operation to minimize siltation of
    lakes and watercourses, as required by the Regional Water Quality Control Board or the
    State Water Resources Control Board. (d) Surface runoff and drainage from surface
    mining activities shall be controlled by berms, silt fences, sediment ponds, revegetation,
    hay bales, or other erosion control measures, to ensure that surrounding land and water
    resources are protected from erosion, gullying, sedimentation and contamination. Erosion
    control methods shall be designed to handle runoff from not less than the 20 year/1 hour
    intensity storm event.” (Cal. Code of Reg., tit. 14, § 3706.)
    The County found that the reclamation plan amendment met the standards for
    water quality as set forth in SMARA. In making this finding, the County relied on a
    hydrologic investigation prepared by Golder Associates that was contained within the
    reclamation plan amendment itself. The investigation stated different types of water
    sampling, laboratory analysis and testing, and included the collection of water samples in
    Permanente Creek and other nearby creeks, groundwater sampling from Quarry wells,
    and field “wall wash” tests.
    In addition to the investigation report, the reclamation plan amendment also
    contained a water quality report that was prepared by Strategic Engineering & Science,
    Inc., a company specializing in water analysis. The report contained analysis of water
    data that had been collected by Golder, and provided a prediction of future water quality
    if the reclamation plan amendment were to be implemented. The report projected that the
    strategies stated in the reclamation plan amendment would amount to the water quality
    meeting acceptable standards. The specific reclamation strategies included backfilling of
    the Quarry pit and placing non-limestone on the exposed areas of limestone which would
    reduce the amount of the Quarry’s release of selenium. In addition, the Quarry’s release
    of selenium would be reduced by mixing organic matter into the backfill.
    7
    Bay Area concedes that when completed, the reclamation plan amendment would
    meet the requirements of California Code of Regulations, Title 14, sections 3706 and
    3710. However, Bay Area argues that during the 20-year interim period of the
    reclamation activities, water quality downstream of the Quarry would deteriorate because
    there would be an increase in selenium contamination in Permanente Creek. Specifically,
    Bay Area asserts that during the interim period, selenium-containing limestone and
    overburden would be deposited in and moved around within the Eastern Mineral Storage
    Area and the Quarry pit. According to Bay Area, the continued degradation of water
    quality due to selenium contamination during the interim period would violate SMARA.
    Bay Area’s argument that the reclamation activities would cause further water
    contamination and would violated SMARA is inconsistent with the provisions of
    SMARA itself. Specifically, California Code of Regulations, Title 14, section 3706,
    subdivision (b) provides that water quality may be affected if it is necessary to complete a
    reclamation plan. Here, according to SMARA, the County had discretion to allow
    reclamation actions that were necessary to achieve compliance with federal and state
    water laws, including potential additional selenium deposits in the water. This
    occurrence as a result of the reclamation activities does not mean that the reclamation
    plan amendment violates SMARA.
    Here, the record supports the County’s finding that the reclamation plan
    amendment complies with SMARA with regard to water quality. The County did not
    abuse its discretion.
    Wildlife Habitat
    In addition to water quality, Bay Area also argues that the reclamation plan
    amendment does not comply with SMARA’s standards for preservation of wildlife
    habitat. California Code of Regulations, Title 14, section 3703, subdivision (b) provides:
    “Wildlife habitat shall be established on disturbed land in a condition at least as good as
    8
    that which existed before the lands were disturbed by surface mining operations, unless
    the proposed end use precludes its use as wildlife habitat or the approved reclamation
    plan establishes a different habitat type than that which existed prior to mining.”
    The California red-legged frog (frog) is protected under the Federal Endangered
    Species Act, and lives in Permamente Creek downstream of the Quarry pit and the
    eastern mineral storage area. The frog was found in the lower segment of the creek
    outside of the reclamation plan amendment’s boundary in 1997. The frog has remained
    confined to this area since its discovery.
    Bay Area argues that the reclamation plan amendment does not comply with the
    wildlife provisions of SMARA, because it does not specifically mention the frog. In
    addition, Bay Area asserts that the reclamation plan amendment does not protect the frogs
    that are located downstream of the Quarry from selenium released by the reclamation
    work itself.
    While the reclamation plan amendment does not itself mention the frog, the record
    in this case shows that a study of wildlife species was appended to the reclamation plan
    amendment entitled “Biological Resources Assessment,” which included a description of
    the frog’s habitat and results of surveys tracking the location of the frog within the
    vicinity of the Quarry. The assessment stated that because the frog was not found within
    the reclamation plan amendment boundaries, it would not be directly affected by the
    reclamation activities. However, the assessment also provided protective measures such
    as pre-construction surveys and daytime only work to limit the potential risk of harming
    the frog if it swam upstream into Permanente Creek.
    In addition, the environmental impact report analyzed the potential selenium
    impact to aquatic wildlife downstream of the creek, including the frog. The report
    recommended measures to mitigate the effect of the selenium runoff. These measures
    included the study and design of a water treatment facility and water protection measures.
    9
    However, the report concluded that the impacts of selenium discharge to aquatic life
    downstream of the Quarry as a result of reclamation activities were significant and
    unavoidable, because the effectiveness of the proposed mitigation measures was
    unknown.
    In its June 26, 2012 findings, the County adopted the information in the
    environmental impact report, and imposed new water protections as suggested in the
    report, and concluded that the selenium runoff impacts were significant and unavoidable.
    Contrary to Bay Area’s assertion, the record supports the conclusion that impacts
    of the reclamation activities on the frog as a result of reclamation activities were
    considered by the County, and were mitigated to the extent possible under the
    circumstances. The County’s conclusion that the reclamation plan amendment ultimately
    protected the frog and its habitat is supported by the record. The record shows that the
    reclamation plan will reduce the selenium levels in Permanente Creek and will ultimately
    improve the conditions for the frog. The reclamation plan amendment also adopted the
    provisions of the environmental impact report to restrict work near the creek and to
    conduct pre-construction surveys of the area so that the frog would not be directly
    affected by the reclamation.
    Office of Mining Reclamation’s Statements Related to SMARA
    Bay Area argues that the statements of the Office of Mining Reclamation to the
    Department of Conservation that the reclamation plan amendment complied with
    SMARA were not substantial evidence to support the County’s findings in this case.
    The Department of Conservation is a state agency that oversees the administration
    of SMARA in reclamation plans. (See Dept. of Conservation v. El Dorado County
    (2005) 
    36 Cal. 4th 971
    , 988-989.) The Department of Conservation reviews all new and
    amended reclamation plans. (Pub. Resources Code, § 2774, subds. (c) & (d).) In its
    10
    regulatory role, the Department of Conservation is permitted to appeal and comment at a
    public hearing to review a reclamation plan. (Id.)
    Here, based on the statements of the Office of Mining Reclamation, the
    Department of Conservation made a formal determination that the reclamation plan
    amendment complies with the standards set forth in SMARA, including those for water
    quality and wildlife habitat. (Code of Regulations, tit. 14, §§ 3703, 3706.) The
    Department of Conservation’s conclusion that the reclamation plan amendment complied
    with SMARA constitutes substantial evidence upon which the County relied in its
    findings.
    Conclusion on the SMARA Claims
    We find that the County did not abuse its discretion when it determined that the
    reclamation plan amendment satisfied SMARA’s regulatory standards for water quality
    and wildlife habitat. (Pub. Resources Code, §§ 2710, et seq.) In addition, the statements
    of the Office of Mining Reclamation were properly considered by the County and
    provided substantial evidence to support the County’s findings.
    CEQA Claims
    Bay Area asserts that the environmental impact report for the reclamation plan
    amendment violates the provisions of CEQA. Specifically, Bay Area argues that the
    environmental impact report does not state a sufficient cumulative impact analysis, and
    that the County’s CEQA findings supporting certification of the report are not supported
    by substantial evidence.
    “A public agency must prepare an [environmental impact report] or cause an
    [environmental impact report] to be prepared for any project that it proposes to carry out
    or approve that may have a significant effect on the environment. (Pub. Resources Code,
    §§ 21100, subd. (a), 21151, subd. (a); Guidelines, § 15064, subd. (a)(1).) The
    [environmental impact report] must describe the proposed project and its environmental
    11
    setting, state the objectives sought to be achieved, identify and analyze the significant
    effects on the environment, state how those impacts can be mitigated or avoided, and
    identify alternatives to the project, among other requirements. (Pub. Resources Code,
    §§ 21100, subd. (b), 21151; Guidelines, §§ 15124, 15125.)
    “The agency must notify the public of the [draft environmental impact] report,
    make the draft [environmental impact report] and all documents referenced in it available
    for public review, and respond to comments that raise significant environmental issues.
    (Pub. Resources Code, §§ 21091, subds. (a), (d), 21092; Guidelines, §§ 15087, 15088.)
    The agency also must consult with and obtain comments from other agencies affected by
    the project and respond to their comments. (Pub. Resources Code, §§ 21092.5, 21104,
    21153; Guidelines, § 15086.) It must prepare a final [environmental impact report]
    including any revisions to the draft [environmental impact report], the comments received
    from the public and other agencies, and responses to comments. (Guidelines, §§ 15089,
    subd. (a), 15132.)
    “An agency may not approve a project that will have significant environmental
    effects if there are feasible alternatives or feasible mitigation measures that would
    substantially lessen those effects. (Pub. Resources Code, §§ 21002, 21002.1, subd. (b);
    Guidelines, § 15021, subd. (a)(2); [citation].) An agency may find, however, that
    particular economic, social, or other considerations make the alternatives and mitigation
    measures infeasible and that particular project benefits outweigh the adverse
    environmental effects. (Pub. Resources Code, § 21081, subds. (a)(3), (b); Guidelines,
    § 15091, subd. (a)(3).) Specifically, an agency cannot approve a project that will have
    significant environmental effects unless it finds as to each significant effect, based on
    substantial evidence in the administrative record, that (1) mitigation measures required in
    or incorporated into the project will avoid or substantially lessen the significant effect;
    (2) those measures are within the jurisdiction of another public agency and have been
    12
    adopted, or can and should be adopted, by that agency; or (3) specific economic, legal,
    social, technological, or other considerations make the mitigation measures or
    alternatives identified in the [environmental impact report] infeasible, and specific
    overriding economic, legal, social, technological, or other benefits outweigh the
    significant environmental effects. (Pub. Resources Code, §§ 21081, 21081.5; Guidelines,
    §§ 15091, subds. (a), (b).) A finding that specific overriding project benefits outweigh
    the significant environmental effects (Pub. Resources Code, § 21091, subd. (b)) is known
    as a statement of overriding considerations. (Guidelines, § 15093.)
    “Thus, a public agency is not required to favor environmental protection over
    other considerations, but it must disclose and carefully consider the environmental
    consequences of its actions, mitigate adverse environmental effects if feasible, explain
    the reasons for its actions, and afford the public and other affected agencies an
    opportunity to participate meaningfully in the environmental review process. The
    purpose of these requirements is to ensure that public officials and the public are aware of
    the environmental consequences of decisions before they are made.” (Federation of
    Hillside & Canyon Assns. v. City of Los Angeles (2004) 
    126 Cal. App. 4th 1180
    , 1197-
    1198, fns. omitted.)
    CEQA depends on the environmental impact report. “An environmental impact
    report is an informational document” the purpose of which “is to provide public agencies
    and the public in general with detailed information about the effect which a proposed
    project is likely to have on the environment; to list the ways in which the significant
    effects of such a project might be minimized; and to indicate alternatives to such a
    project.” (Pub. Resources Code, § 21061) According to our Supreme Court, “The
    purpose of an [environmental impact report] is to give the public and government
    agencies the information needed to make informed decisions, thus protecting ‘ “not only
    the environment but also informed self-government.” ’ [Citation.] The [environmental
    13
    impact report] is the heart of CEQA, and the mitigation and alternatives discussion forms
    the core of the [environmental impact report].” (In re Bay-Delta Etc. (2008) 
    43 Cal. 4th 1143
    , 1162.)
    Once the environmental impact report has been adopted, the scope of judicial
    scrutiny proceeds along two paths. “ ‘Section 21168.5 [of the Public Resources Code]
    provides that a court’s inquiry in an action to set aside an agency’s decision under CEQA
    “shall extend only to whether there was a prejudicial abuse of discretion. Abuse of
    discretion is established if the agency has not proceeded in a manner required by law or if
    the determination or decision is not supported by substantial evidence.” As a result of
    this standard, “The court does not pass upon the correctness of the [environmental impact
    report’s] environmental conclusions, but only upon its sufficiency as an informative
    document.” [Citation.]’ [Citations.] ‘We may not set aside an agency’s approval of an
    [environmental impact report] on the ground that an opposite conclusion would have
    been equally or more reasonable.’ [Citation.] [¶] ‘An appellate court’s review of the
    administrative record for legal error and substantial evidence in a CEQA case, as in other
    mandamus cases, is the same as the trial court’s: The appellate court reviews the
    agency’s action, not the trial court’s decision; in that sense appellate judicial review
    under CEQA is de novo.’ [Citation.]” (In re Bay-Delta 
    Etc., supra
    , 
    43 Cal. 4th 1143
    ,
    1161-1162.)
    “The agency is the finder of fact and a court must indulge all reasonable inferences
    from the evidence that would support the agency’s determinations and resolve all
    conflicts in the evidence in favor of the agency’s decision. [Citation.] ‘ “Technical
    perfection is not required; the courts have looked not for an exhaustive analysis but for
    adequacy, completeness and a good-faith effort at full disclosure.” ’ [Citation.] ‘A
    court’s task is not to weigh conflicting evidence and determine who has the better
    argument when the dispute is whether adverse effects have been mitigated or could be
    14
    better mitigated. We have neither the resources nor scientific expertise to engage in such
    analysis, even if the statutorily prescribed standard of review permitted us to do so.’
    [Citation.] ‘[T]he relevant inquiry here is not whether the record establishes compliance
    but whether the record contains evidence [the agency] failed to comply with the
    requirements of its . . . regulatory program. In the absence of contrary evidence, we
    presume regular performance of official duty. (Evid.Code, § 664.)’ ” (Gilroy Citizens
    for Responsible Planning v. City of Gilroy (2006) 
    140 Cal. App. 4th 911
    , 918-919.) Every
    court “presumes a public agency’s decision to certify the [environmental impact report] is
    correct, thereby imposing on a party challenging it the burden of establishing otherwise.”
    (Sierra Club v. City of Orange (2008) 
    163 Cal. App. 4th 523
    , 530.)
    Legal error, in the form of failure to comply with CEQA, is reviewed
    independently, but all factual determinations are reviewed according to the substantial
    evidence standard. (Vineyard Area Citizens for Responsible Growth, Inc. v. City of
    Rancho Cordova (2007) 
    40 Cal. 4th 412
    , 426-427, 435.) “The substantial evidence
    standard is applied to conclusions, findings and determinations. It also applies to
    challenges to the scope of an [environmental impact report’s] analysis of a topic, the
    methodology used for studying an impact and the reliability or accuracy of the data upon
    which the [environmental impact report] relied because these types of challenges involve
    factual questions.” (Bakersfield Citizens for Local Control v. City of Bakersfield (2004)
    
    124 Cal. App. 4th 1184
    , 1198.)
    A substantial evidence challenge is subject to an important proviso: “As with all
    substantial evidence challenges, an appellant challenging an [environmental impact
    report] for insufficient evidence must lay out the evidence favorable to the other side and
    show why it is lacking. Failure to do so is fatal. A reviewing court will not
    independently review the record to make up for appellant’s failure to carry his burden.”
    (Defend the Bay v. City of Irvine (2004) 
    119 Cal. App. 4th 1261
    , 1266.)
    15
    Cumulative Impact of the Reclamation Plan Amendment
    Bay Area asserts that the environmental impact report for the reclamation plan
    amendment was inadequate, because it failed to address the cumulative impact of the new
    South Quarry pit that had previously been proposed to replace the reclaimed pit.
    Specifically, Bay Area argues that the reclamation plan amendment implicitly relies on
    the establishment of a new pit in the South Quarry to replace the reclaimed North Quarry
    pit, and the new pit was not included in the reclamation plan or considered in the
    environmental impact report.
    Bay Area cites the primary objectives of the reclamation plan amendment, which
    were to “maintain a local, reliable, and economic source of cement-grade limestone and
    to continue operations of the existing quarry.” (Emphasis omitted.) Bay Area asserts that
    the only way to achieve the stated objective was to open a new quarry pit to replace the
    one being reclaimed.
    Bay Area notes that the 2010 comprehensive plan amendment that immediately
    preceded the approved 2011 reclamation plan amendment included an application for a
    use permit for a new South Quarry pit. Bay Area theorizes that in order for Lehigh to
    achieve quick approval of the reclamation plan amendment so that it could continue to
    supply cement to California public agencies, it removed the application for a use permit
    for South Quarry pit from the reclamation plan amendment.
    Bay Area argues that the new quarry pit was a reasonably foreseeable future
    project, and it should have been included in the environmental impact report in order to
    comply with CEQA. Bay Area makes this argument based in part on the concept that
    segmentation of proposed projects should be avoided. “Segmentation” refers to the
    division of a project into pieces, thereby avoiding review of the physical impact of the
    project as a whole. “A public agency may not divide a single project into smaller
    individual projects in order to avoid its responsibility to consider the environmental
    16
    impacts of the project as a whole.” (Sierra Club v. West Side Irrigation Dist. (2005) 
    128 Cal. App. 4th 690
    , 698.) “CEQA mandates that environmental considerations do not
    become submerged by chopping a large project into many little ones, each with a
    potential impact on the environment, which cumulatively may have disastrous
    consequences.” (Burbank-Glendale-Pasadena Airport Authority v. Hensler (1991) 
    233 Cal. App. 3d 577
    , 592.) “A project under CEQA is the whole of an action which has a
    potential for resulting in a physical change in the environment, directly or ultimately, and
    includes the activity which is being approved and which may be subject to several
    discretionary approvals by governmental agencies.” (Ibid.)
    The record contains no support for Bay Area’s assertion that the County
    segmented the review of the reclamation plan amendment. The application for a use
    permit for the South Quarry was withdrawn before the final iteration of the reclamation
    plan amendment was subjected to the environmental impact report. The new pit (if it
    were a subsequent project) would not change the scope of the nature of the reclamation of
    the North Quarry pit or the reclamation’s environmental effects. (See Laurel Heights
    Improvement Assoc. of San Francisco, Inc. v. The Regents of the University of California
    (1988) 
    47 Cal. 3d 376
    , 396.) The reclamation plan amendment in this case is a stand-
    alone project and does not require approval of a future project, such as the South Quarry
    pit for reclamation of the North Quarry to occur.
    City of Antioch v. City Council (1986) 
    187 Cal. App. 3d 1325
    (City of Antioch),
    relied upon by Bay Area, is distinguishable. In that case, the project at issue was an
    infrastructure system on four parcels of undeveloped land, which was designed to serve
    subsequent development on the land. It was conceded that the sole and exclusive purpose
    of the infrastructure development at issue was “to provide a catalyst for further
    development in the immediate area.” (Id. at p. 1337.) The court addressed the question
    of whether a negative declaration was a sufficient environmental document for this
    17
    project. It found that an environmental impact report must be prepared since it was
    reasonably certain that development would follow, even though permits had not been
    applied for. The infrastructure by itself had no independent utility and served no purpose
    other than to facilitate development at that site. By issuing the permit for the first stage
    of the development, the agency had committed itself to the second phase. Therefore, the
    court concluded, “[c]onstruction of the roadway and utilities cannot be considered in
    isolation from the development it presages.” (Id. at p. 1336.)
    In contrast to City of Antioch, here the reclamation plan amendment is not a first
    phase in a larger development. It is the complete process by which the North Quarry will
    be reclaimed, and does not require approval of other future projects to be completed.
    In sum, the environmental impact report sufficiently reviewed the project
    proposed in the reclamation plan amendment, and did not omit to review a possible
    replacement quarry pit.
    Adequacy of the County’s CEQA Findings to Support Certification
    Bay Area argues that the County’s findings supporting certification of the
    environmental impact report were insufficient, because they were not supported by
    substantial evidence. Specifically, Bay Area asserts that the findings are insufficient
    because they do not state that the impacts of the plan on the frog were significant and
    unavoidable, or that the impact could be adequately mitigated. In addition, Bay Area
    argues that the statement of overriding considerations was deficient because it did not
    address the significant impacts on the frog.
    Impact 4.4-4 is entitled “Project activities could result in adverse negative effects
    on special status aquatic organisms. (Less than significant impact).” (Emphasis in
    original.) The Impact states “[The frog] is the only special status aquatic species of
    concern in the Study Area. However, no [frogs] have been found during surveys in the
    Project Area. Upland migration habitat for [the frog] is not present in the Project Area,
    18
    preventing significant movements of this species in the Project Area [record citation].
    [¶] Consequently, it is considered unlikely for the species to occur in the Project Area and
    therefore no direct impacts to special status aquatic species would be expected to result
    from Project activities.”
    With regard to the direct impacts on the frog from reclamation activities, the
    environmental impact report states that the impacts were less than significant. This
    conclusion is supported by substantial evidence in the record. Most notably, the evidence
    of less than significant impact is demonstrated by the facts that support the finding that
    the plan complies with SMARA.5 Under CEQA, additional findings regarding mitigation
    of impact are required only when the findings show a significant impact. (Pub.
    Resources Code, § 21081; Cal. Code Regs., tit. 14, § 15091.) If the direct potential
    impacts are less than significant, no additional findings are required. Here, in Impact 4.4-
    4, the environmental impact report concluded that the direct potential impacts of the
    reclamation plan on the frog were less than significant. As a result, contrary to Bay
    Area’s assertion, additional findings regarding Impact 4.4-4 were not required.
    (Environmental Protection Information Center v. California Dept. of Forestry and Fire
    Protection (2008) 
    44 Cal. 4th 459
    , 522; Mira Mar Mobile Community. v. City of
    Oceanside (2004) 
    119 Cal. App. 4th 477
    , 492-493.)
    To the extent Bay Area is referring to the indirect potential impacts to the frog
    from reclamation activities, Impact 4.4-5 of the environmental impact report discusses
    the risks to aquatic life, of which the frog is included, from excess selenium runoff in the
    downstream areas. The report states that the potential impact is significant and
    unavoidable. Consistent with the requirements of CEQA, Impact 4.4-5 also states the
    5
    Bay Area also asserts that the findings are insufficient because they rely in part
    on a conclusion that the reclamation plan amendment does not violate SMARA. As
    
    stated supra
    , the County properly found that the reclamation plan amendment satisfied
    the provisions of SMARA.
    19
    mitigation measures that would be applicable, including interim storm water control and
    sediment management, and an interim storm water monitoring plan in the eastern
    material storage area of the Quarry. These specific mitigation measures are described in
    detail in the environmental impact report. These statements of the indirect impacts to the
    frog are supported by substantial evidence in the record and comply with the CEQA
    requirements.
    Finally, Bay Area argues that the statement of overriding considerations was
    defective because it did not specifically direct significant impacts to the frog. However,
    as discussed above, the finding that there was a less than significant impact on the frog
    from the reclamation activities is supported by substantial evidence. As a result, CEQA
    does not require a statement of overriding considerations because the potential direct
    impacts to the frog were found to be less than significant. (Cal. Code Regs., tit. 14,
    § 15093.)
    Augmentation of the Administrative Record
    Bay Area argues that the trial court erred in granting Lehigh’s motion to augment
    the administrative record to include an e-mail exchange between Dr. Mark Jennings, a
    herpetologist who conducted studies and contributed reports about the frog during the
    environmental review process, and David Johnston of the California Department of Fish
    and Wildlife. The e-mail discussed inconsistencies in Jennings’s prior reports about his
    observation of the frog in Pond 13, which is within the boundaries of the reclamation plan
    amendment.
    In his 2006 and 2007 reports, Jennings stated that the frog inhabited Pond 13, a
    location farther upstream from where it had ever been previously found, and within the
    boundaries of the reclamation plan amendment. In subsequent reports, however,
    Jennings did not include any reference to the frog being located in Pond 13.
    20
    Jennings sent an e-mail to Johnston in 2009, stating that he had erred in his 2007
    report when he said that he had observed the frog in Pond 13. Jennings opined that the
    error was likely the result of a typographical mistake in the numbering of the map of the
    Quarry. Jennings further reiterated to Johnston that he had never observed the frog in
    Pond 13, and that this was consistent with what he had told Johnston in the field.
    The contents of the administrative record, are governed by Public Resources Code
    section 21167.6, subdivision (e), which states: “The record of proceedings shall include,
    but is not limited to, all of the following items . . . .” Subdivision (e) includes 11
    categories of material that must be included in the administrative record. (Madera
    Oversight Coal. , Inc. v. County of Madera (2011) 
    199 Cal. App. 4th 48
    , 63, disapproved
    on other grounds in Neighbors for Smart Rail v. Exposition Metro Line Const. Authority
    (2013) 
    58 Cal. 4th 439
    .)
    In the present case, the e-mail exchange falls within subdivision (e)(10) of the
    Public Resources Code section 21167.6, which states that an administrative record
    includes “any other written materials relevant to the respondent public agency’s
    compliance with this division or to its decision on the merits of the project, including the
    initial study, any drafts of any environmental document, or portions thereof, that have
    been released for public review, and copies of studies or other documents relied upon in
    any environmental document prepared for the project and either made available to the
    public during the public review period or included in the respondent public agency’s files
    on the project, and all internal agency communications, including staff notes and
    memoranda related to the project or to compliance with this division.”
    Here, the e-mail exchange was properly part of the administrative record. Jennings
    wrote the e-mail in 2009, and that e-mail was communicated to the firm that prepared the
    biological resources assessment for the environmental review process. The draft
    environmental impact report relied on the biological resource assessment in stating its
    21
    findings. Evidence of the presence or absence of the frog in the reclamation area that was
    relied upon by the firm completing the biological study for the environmental review
    process falls within the parameters of Public Resources Code section 21167.6,
    subdivision (e) for inclusion in the administrative record.
    Conclusion on the CEQA Claims
    We find that the County properly certified the environmental impact report and
    approved the reclamation plan amendment in compliance with CEQA. The County’s
    findings regarding the direct and indirect environmental impacts from the reclamation
    plan amendment were sufficient under CEQA. Finally, the administrative record
    properly included information about the location of the frog relevant to the reclamation
    area boundaries.
    DISPOSITION
    The order denying Bay Area’s petition for writ of mandate is affirmed.
    22
    ______________________________________
    RUSHING, P.J.
    WE CONCUR:
    ____________________________________
    PREMO, J.
    ____________________________________
    ELIA, J.
    Bay Area Clean Environment, Inc. v. Santa Clara County et al.
    H040789
    23
    Trial Court:                                    Santa Clara County Superior Court
    Superior Court No.: 1-12-CV229236
    Trial Judge:                                    The Honorable Joseph Huber
    Attorneys for Plaintiff and Appellant           Stuart M. Flashman
    Bay Area Clean Environment, Inc.:
    Attorneys for Defendants and Respondents        Office of the County Counsel
    Santa Clara County et al.:
    Orry P. Korb
    Elizabeth G. Pianca
    Harrison, Temblador, Hungerford &
    Johnson
    Mark D. Harrison
    Sean K. Hungerford
    Attorneys for Amicus Curiae:                    Babak Naficy
    Towns of Los Altos and Atherton and the
    Cities of Cupertino and Los Altos:
    Bay Area Clean Environment, Inc. v. Santa Clara County, et al.
    H040789
    24
    

Document Info

Docket Number: H040789

Filed Date: 8/31/2016

Precedential Status: Precedential

Modified Date: 8/31/2016