Takata Corp. v. Cal. Dept. of Corrections etc. CA1/3 ( 2015 )


Menu:
  • Filed 1/21/15 Takata Corp. v. Cal. Dept. of Corrections etc. CA1/3
    NOT TO BE PUBLISHED IN OFFICIAL REPORTS
    California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
    publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication
    or ordered published for purposes of rule 8.1115.
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    FIRST APPELLATE DISTRICT
    DIVISION THREE
    JON K. TAKATA CORPORATION,
    Plaintiff and Respondent,
    A136794
    v.
    CALIFORNIA DEPARTMENT OF                                             (Marin County
    CORRECTIONS AND                                                      Super. Ct. No. 1002716)
    REHABILITATION,
    Defendant and Appellant.
    Defendant California Department of Corrections and Rehabilitation (DCR)
    appeals from a judgment entered after the trial court granted in part and denied in part
    DCR’s motion for summary judgment/adjudication and granted in part, denied in part a
    motion for summary judgment/adjudication brought by plaintiff Jon K. Takata
    Corporation, doing business as Restoration Management Company (RMC), and found in
    favor of RMC after a court trial. DCR contends the judgment must be reversed because
    RMC’s claims were barred for failure to file a government claim in the manner
    prescribed by the Government Claims Act (Gov. Code, § 910 et seq.). We affirm the
    judgment.
    1
    FACTUAL AND PROCEDURAL BACKGROUND1
    In the fall of 2007, RMC learned that San Quentin State Prison (San Quentin) was
    soliciting bids for “emergency hazardous material clean-up services” to be performed at
    the prison. RMC and at least one other contractor submitted a bid and RMC was
    awarded the contract. RMC began performing the work in November 2007. On or about
    February 28, 2008, DCR and RMC entered into a contract in which they set forth in
    writing their agreement that RMC would clean up lead-containing dust that had
    accumulated in San Quentin’s four cell block buildings. The contract was a State of
    California form entitled “STANDARD AGREEMENT” and included a section for
    “Contract Disputes” that set forth a dispute resolution process for any disputes that arose
    relating to the contract. The contract provided that the term of the agreement was
    November 7, 2007 through June 30, 2008, and that the amount to be paid was $4.329
    million. RMC successfully completed the work and DCR paid RMC in full by
    remittance dated June 30, 2008.
    After RMC completed the work, one of its workers who had worked on the project
    filed a complaint with the Department of Industrial Relations (DIR) alleging that RMC
    should have paid—but did not pay—him prevailing wages for work removing old paint
    from walls contaminated with lead. DIR investigated the matter and determined the
    workers performed work that fit within the job classification of Lead Removal Worker
    and were therefore entitled to prevailing wages under Labor Code sections 1771 and
    1774. DIR found that RMC violated those statutes by not paying prevailing wages for
    the classification and issued a civil wage and penalty assessment (the assessment) against
    RMC on December 19, 2008, for a total amount of $765,150.82, consisting of back
    wages of $619,005.82 and a $146,145.00 penalty. In the assessment, DIR informed
    RMC of its right to a review with the Labor Commissioner and of the option of
    requesting a settlement meeting. RMC sought review of the assessment before the Labor
    Commissioner and also requested a settlement meeting.
    1
    The following facts are not in dispute.
    2
    Shortly after receiving the assessment, RMC, through its Chief Financial Officer
    Dave Glover, contacted Bob Sweeny, then-San Quentin State Prison’s Associate Warden
    of Business Services, to discuss the assessment. In an email dated February 2, 2009,
    Sweeny told Glover that he was going to contact “our legal division in Sacramento and
    the environmental compliance unit” and that he “look[ed] forward to meeting [Glover]
    and hopefully resolving this issue.” In an email to Sweeny dated July 31, 2009, Glover
    stated: “As you know, in order to avoid the potential of a significant increase to the
    prevailing wage liability we were facing, we agreed to settle with the DIR last month. As
    dictated by this resolution, we are now at the point where we need to fund.” Glover
    informed Sweeny that the agreed upon amount was “in the neighborhood of
    $750,000.00” and stated, “you were going to check with your team in regards to any
    allowance/indemnification/subsidy which San Quentin might be able to provide. As soon
    as you get a moment, can you call me with any information you have?” RMC then
    settled the matter with DIR on or about June 12, 2009, and paid an amount less than the
    full amount assessed ($736,711.84) by check dated August 3, 2009.
    On August 18, 2009, Glover sent Sweeny an email stating he had spoken with an
    attorney about the legal grounds for asserting and obtaining reimbursement of the
    settlement amount of $736,711.84 from San Quentin. Glover reported that under Labor
    Code sections 1773, 1773.2, and 1781, “public agencies, like San Quentin,” were
    required to “specify in the call for bids for the contract, in the bid specifications, and in
    the contract itself, what the general rate of per diem wages is and whether this job is a
    prevailing wage job, or not.” Citing legal authority, Glover further stated that a
    contractor is entitled to reimbursement from the public agency where the public agency
    fails to inform the contractor that the work to be performed is a prevailing wage job.
    Glover noted that San Quentin did not specify anywhere in its solicitation for bids,
    specifications, or contract that this was a prevailing wage job.
    On October 28, 2009, Ronald Peck, counsel for RMC, wrote to Kathy Harker,
    counsel for DCR, “concerning [RMC’s] claim against [DCR] for the sum of $740,000.00
    relating to increased wages and benefits they were required to pay as a result of work
    3
    performed by [RMC] that was later determined by [DIR] to be work for which prevailing
    wages were to be paid.” Peck reiterated the facts and legal grounds for seeking
    reimbursement of the amount RMC paid DIR in settlement of the assessment.
    Over the course of the next several months, Peck and Harker exchanged
    communications regarding RMC’s request for assessment, and Peck provided Harker
    with additional requested documents. On February 10, 2010, Peck stated that RMC was
    “anxious to resolve this matter one way or the other” and sent Harker a letter entitled
    “Amended and Restated Claim for Damages” in which he set forth in detail—and
    attached documents—relating to the claims RMC was asserting against DCR.
    On March 2, 2010, Harker wrote Peck to say that DCR’s investigation of RMC’s
    request for reimbursement was still ongoing. She added, “please understand that your
    client may have obligations to perfect its claim pursuant to Government Code section 910
    et seq. and any steps taken by [DCR] to evaluate your request within this department
    should not be considered a waiver of any defense available to [DCR] in another forum.”
    On March 4, 2010, Peck mailed a letter, a claim form, and a $25 fee to the
    California Victim Compensation and Government Claims Board (Claims Board) seeking
    reimbursement of the amount RMC paid in settlement of the assessment. Peck stated,
    “Claims and an Amended Claim were previously filed with the Department of
    Corrections on August 18, 2009, October 28, 2009 and February 10, 2010. We have been
    advised that they are still investigating the matter. [¶] Out of an abundance of caution,
    we are also filing a Claim with your office.” On March 5, 2010, Peck mailed an amended
    claim form to the Claims Board stating the same claim but seeking attorney fees and
    costs in addition to the amount paid for the assessment.
    On March 10, 2010, the Claims Board wrote to Peck, sating in part: “The claim
    does not include the date you were served with the complaint, which resulted in your
    claim for equitable indemnity. Please provide the exact date the complaint was served on
    you. If your claim was presented to the Board more than six months from the date of
    incident, it will be returned for not being presented within six months after the event or
    4
    occurrence as required by law. If the claim is not presented within the time allowed by
    law, no action will be taken.”
    On March 18, 2010, Peck wrote the Claims Board, stating: “In response to your
    request for additional information, there was no Complaint that resulted in our client’s
    claim for indemnity. [¶] Further, our client’s claim, although similar to an indemnity
    claim, is actually statutory. Labor Code § 1781 requires a State Agency, like San
    Quentin, to pay any increased costs incurred by a contractor (like [RMC]) as a result of a
    decision” by the [DIR].”2 Peck stated that “the Labor Commissioner initially asserted
    that this was a prevailing wage job on December 19, 2008” and that the claim was settled,
    and payment was made by RMC to DIR in August 2009.
    On March 29, 2010, the Claims Board denied RMC’s claim, stating in part,
    “Based on its review of your claim, Board staff believes that the court system is the
    appropriate means for resolution of these claims, because the issues presented are
    complex and outside the scope of analysis and interpretation typically undertaken by the
    Board.” The Claims Board stated it had considered the claim only to the extent it
    asserted allegations that arose from facts or events that occurred in the six months prior to
    the date it was presented to the Board. On May 11, 2010, the Claims Board issued a
    “corrected notice” in which it stated that because RMC’s claim “was filed more than one
    year from the date of the incident that is the basis of the claim, . . . it is too late for the
    Board to consider an application to present a late claim.” The Claims Board stated: “It
    has been determined that the date of the incident that is the basis of this claim is
    December 19, 2008. As such, this claim was filed more than one year from the date of
    incident.”
    2
    Labor Code section 1781 provides in part: “(a)(1) Notwithstanding any other
    provision of law, a contractor may . . . bring an action . . . to recover from the body
    awarding a contract for a public work . . . any increased costs incurred by the contractor
    as a result of any decision by the body, the [DIR], or a court that classifies, after the time
    at which the body accepts the contractor’s bid . . . the work covered by the bid or
    contract as a ‘public work,’ . . . if that body, before the bid opening or awarding of the
    contract, failed to identify as a ‘public work’ . . . in the bid specification or in the contract
    documents that portion of the work that the decision classifies as a ‘public work.’ ”
    5
    On May 25, 2010, following denial of the claim, RMC filed this action pleading
    five causes of action. The first cause of action alleged a violation of Labor Code
    sections 17263 and 1781. The second cause of action sought equitable indemnity, and the
    third cause of action alleged negligence. The fourth cause of action alleged negligent
    nondisclosure, and the fifth cause of action alleged a “tort of another.” The complaint
    sought $736,711.84, attorney fees and costs including attorney fees under Labor Code
    section 1726, and interest. DCR demurred to the complaint, asserting that all five causes
    of action were barred for failure to file a government claim within one year of accrual of
    the causes of action, that the second though fifth causes of action were barred to the
    extent they sought reimbursement for attorney fees because the causes of actions for fees
    exceeded the scope of the government claim that was filed, and that the second through
    fifth causes action were non-statutory common law claims that could not be brought
    against the State of California.
    RMC responded to the demurrer by filing a first amended complaint. The first
    amended complaint dropped the third through fifth causes of action and alleged facts to
    show that RMC had timely filed a government claim. In its first cause of action, RMC
    alleged it paid a civil wage and penalty of $736,711.84 because DCR had failed to notify
    RMC as required by Labor Code sections 1726 and 1781 that the work required the
    payment of prevailing wages. In its second cause of action, RMC alleged that an
    authorized employee of DCR had negligently failed to identify the contract work as a
    “public work” in violation of the “Labor Code sections referred to above,” and that CDR
    was vicariously liable for the employee’s actions. The first amended complaint prayed
    for the same damages, interest, and fees that had been requested in the original complaint.
    3
    Labor Code section 1726, subdivision (c), provides that a contractor is entitled to
    attorney fees and costs in addition to reimbursement for wages and penalties where the
    public agency “affirmatively represented to the contractor in writing . . . that the work to
    be covered by the bid or contract was not a ‘public work,’ ” or where the public agency
    “received actual written notice from [DIR] that the work to be covered by the bid or
    contract is a ‘public work,’ and failed to disclose that information to the contractor before
    the bid opening or awarding of the contract.”
    6
    DCR demurred to the first amended complaint on substantially the same grounds as the
    demurrer to the original complaint, and the demurrer was overruled.
    The court stated in overruling the demurrer to the first amended complaint that the
    first and second causes of action were not barred as a matter of law for failure to comply
    with the government claims requirements. The court determined that RMC’s March
    2010 claim was timely because the first cause of action was not a claim for indemnity
    that accrued upon DIR’s presentation of the civil wage and penalty assessment, but rather
    was a violation of statute that accrued when RMC incurred increased costs in August
    2009. The court determined the second cause of action was authorized under
    Government Code, section 815.6, which imposes liability on a public entity for injuries
    caused by the entity’s failure to discharge a mandatory duty.
    DCR answered the first amended complaint on February 7, 2011. In its answer,
    DCR asserted as a first affirmative defense that the complaint and all causes of action
    were barred for failure to present a government claim within one year of accrual of the
    cause of action. Following discovery, both parties moved for summary judgment or
    adjudication. Both motions asked the trial court to decide as a matter of law whether the
    first and second causes of action were barred for failure to file a timely government claim
    within one year of accrual.
    In its ruling on the issue of whether a timely government claim was filed, the trial
    court stated: “Judge Adams concluded in her December 2010 order on demurrer that:
    ‘The first cause of action is not a claim for indemnity that accrued upon presentation of
    the civil wage and penalty assessment by the [DIR], but rather a violation of statute that
    accrued when [RMC] “incurred” increased costs.’ Based on the plain wording of Labor
    Code, section 1781, subdivision (a)(1), along with other authorities noted by the parties,
    this court agrees with Judge Adams’s conclusion. If [RMC] had filed a government
    claim based on the DIR’s initial notification, it would have appeared premature—given
    [RMC’s] responsibility of avoiding or reducing any assessment through an administrative
    appeal. The undisputed facts show that [RMC] only ‘incurred’ increased costs [on]
    August 3, 2009 . . . Thus, [RMC’s] claim filed in March 2010 was timely.” The court
    7
    also addressed RMC’s arguments that it was exempt from the claims filing requirements,
    that RMC had substantially complied with any claims filing requirements, and that DCR
    was estopped from raising the defense. The court expressed an opinion on each of those
    claims but determined they were “merely alternative arguments,” and that in any event,
    involved material facts so that they could not be resolved by way of a motion for
    summary judgment.
    The trial court granted DCR’s motion for summary adjudication as to RMC’s
    second cause of action (negligence), and the matter proceeded to court trial solely on the
    merits of whether RMC was entitled to recovery under Labor Code section 1781.4 After
    trial, the court found in favor of RMC and ordered DCR to pay $736,711.84, plus seven
    percent interest per annum to accrue from August 3, 2009 (the date RMC paid the
    settlement to DIR) through the date of judgment. The court awarded RMC costs of suit
    as the prevailing party.
    DISCUSSION
    DCR contends the judgment must be reversed because RMC’s action was barred
    for failure to file a government claim in the manner prescribed by the Government
    Claims Act (the Act).5 We reject the contention.
    1. Summary Judgment
    We review summary judgment rulings de novo to determine whether the moving
    party has met its burden of persuasion that there is no triable issue as to any material fact
    and that the moving party is entitled to judgment as a matter of law. When the defendant
    is the moving party, the defendant must show either: (1) the plaintiff cannot establish one
    4
    In its first cause of action, RMC also sought attorney fees and costs under Labor
    Code section 1726. Because RMC did not allege facts sufficient to state a claim for
    violation of Labor Code section 1726, i.e., that DCR affirmatively misrepresented or
    recklessly failed to disclose that the work was a “public work,” the trial court allowed the
    first cause of action to proceed to trial only as to RMC’s Labor Code section 1781 claim.
    5
    DCR does not dispute that it was required—and failed—to inform RMC that the
    contract was for a public works project for which prevailing wages were due. DCR also
    does not challenge the trial court’s determination on the merits of RMC’s claim that
    RMC was entitled to reimbursement under Labor Code section 1781.
    8
    or more elements of a cause of action, or (2) there is a complete defense. If that burden
    of production is met, the burden shifts to the plaintiff to show the existence of a triable
    issue of fact with respect to that cause of action or defense. (Aguilar v. Atlantic Richfield
    Co. (2001) 
    25 Cal. 4th 826
    , 850; Code Civ. Proc., § 437c, subds. (c) & (o)(2).)
    In deference to the strong public policy favoring a trial on the merits, appellate
    courts are bound by the same principles governing the trial court’s determination: the
    moving party’s papers are strictly construed and the opposing party’s papers are liberally
    construed. All doubts as to the propriety of granting the motion (whether there is any
    issue of material fact) are to be resolved in favor of the party opposing the motion, i.e., by
    a denial of summary judgment. (Lonicki v. Sutter Health Central (2008) 
    43 Cal. 4th 201
    ,
    206; Faust v. California Portland Cement Co. (2007) 
    150 Cal. App. 4th 864
    , 877
    [“[S]ummary judgment cannot properly be affirmed unless a contrary view would be
    unreasonable as a matter of law in the circumstances presented”].) The proper
    interpretation of a statute and the application of the statute to undisputed facts are
    questions of law. (Lozada v. City and County of San Francisco (2006) 
    145 Cal. App. 4th 1139
    , 1148–1149.)
    2. Government Claims Act
    a. Applicability to Section 1781 Actions
    Government Code section 905 provides that subject to certain exceptions, “all
    claims for money or damages against local public entities” must be presented to the
    responsible public entity before a lawsuit is filed. Claims for personal injury and
    property damage must be presented within six months after accrual; all other claims must
    be presented within a year. (Gov. Code, § 911.2.) Failure to present a timely claim bars
    suit against the entity. (Gov. Code, § 945.4; State of California v. Superior Court
    (Bodde) (2004) 
    32 Cal. 4th 1234
    , 1239.) The purpose of the claims statutes is “to provide
    the public entity sufficient information to enable it to adequately investigate claims and to
    settle them, if appropriate, without the expense of litigation. [Citations.] It is well-settled
    that claims statutes must be satisfied even in face of the public entity’s actual knowledge
    of the circumstances surrounding the claim.” (City of San Jose v. Superior Court (1974)
    9
    
    12 Cal. 3d 447
    , 455.) The claims statutes also “enable the public entity to engage in fiscal
    planning for potential liabilities and to avoid similar liabilities in the future.” (Baines
    Pickwick Ltd. v. City of Los Angeles (1999) 
    72 Cal. App. 4th 298
    , 303; Minsky v. City of
    Los Angeles (1974) 
    11 Cal. 3d 113
    , 123.)
    Although the parties spend the majority of their appellate briefs addressing the
    timeliness of RMC’s March 4, 2010 claim with the Claims Board, they also present some
    argument relating to the issue of whether the Act even applied to RMC’s cause of action
    for a violation of Labor Code section 1781 (Section 1781). DCR asserts the Act applied
    because claim filing requirements “are broadly construed to apply to any and all claims
    for money or damages” and a claim for reimbursement under Section 1781 is a “claim for
    money or damages.” RMC asserts it was not required to file under the Act for a violation
    of Section 1781, “which by definition is a government claim,” and provides for the right
    to reimbursement “[n]otwithstanding any other provision of law.” RMC also asserts that
    even if the Act generally applies to Section 1781 actions, it did not apply in this case
    because the contract the parties entered into contained an alternative dispute resolution
    process, and the Act “authorizes a state agency . . . to substitute a contractual claim
    procedure as an alternative to the statutory claims procedure set forth in [the Act].” RMC
    further asserts that even if the Act applied, it applied only to the “prevailing wages”
    portion—and not the “penalties” portion—of the assessment because Government Code
    section 905, subdivision (k), specifically excludes “penalties” from the definition of
    “money or damages.” We express no opinion on these arguments and need not—and
    therefore will not—decide whether the Act applies to Section 1781 claims generally, or
    whether it applied in this particular case, because even assuming the Act applied, we
    conclude that RMC satisfied its obligation under the Act by filing a timely claim with the
    Claims Board.
    b. Timeliness of RMC’s Claim
    The Act requires that, for actions for injury to person or property for money or
    damages, the plaintiff must present a claim to the Claims Board “not later than six
    months after the accrual of the cause of action.” (Gov. Code, § 911.2, subd. (a).) “A
    10
    claim relating to any other cause of action shall be presented . . . not later than one year
    after the accrual of the cause of action.” (Ibid.) The parties do not dispute—and we
    agree—that the one year period applies to RMC’s Section 1781 claim because the
    damage suffered by RMC was not an injury to person or property. (Gov. Code, § 810.8
    [“injury” is defined as “death, injury to a person, damage to or loss of property, or any
    other injury that a person may suffer to his person, reputation, character, feelings or
    estate”].) The dispositive question, therefore, is when the Section 1781 claim “accrued.”
    Government Code section 901 provides in pertinent part: “[T]he date of accrual of
    a cause of action to which a claim relates is the date upon which the cause of action
    would be deemed to have accrued within the meaning of the statute of limitations which
    would be applicable thereto if there were no requirement that a claim be presented to and
    be acted upon by the public entity before an action could be commenced thereon.
    However, the date upon which a cause of action for equitable indemnity or partial
    equitable indemnity accrues shall be the date upon which a defendant is served with the
    complaint giving rise to the defendant’s claim . . . against the public entity.”
    Here, because RMC’s action was based on a statutory right to reimbursement
    under Section 1781, and was not an action for “equitable indemnity” as DCR asserts6, the
    cause of action accrued on “the date upon which the cause of action would be deemed to
    have accrued” under Section 1781. (Gov. Code, § 901.) The court held in K.J. v.
    Arcadia Unified School Dist. (2009) 
    172 Cal. App. 4th 1229
    , 1239: “ ‘The date of accrual
    of a cause of action marks the starting point for calculating the claims presentation
    6
    DCR asserts that the “special rule” for accrual of equitable claims set forth in
    Government Code section 901 applies because RMC’s Section 1781 cause of action was
    essentially an equitable indemnity claim. DCR states that because an equitable indemnity
    cause of action accrues when “a defendant is served with the complaint giving rise to the
    defendant’s claim,” the Section 1781 cause of action accrued on December 19, 2008,
    when the original assessment was served. We disagree. Although Section 1781
    embodies an indemnity principle, it provides a statutory right to reimbursement without
    the weighing of equities, and is not an “equitable indemnity” action. Moreover, even if it
    were to be considered an equitable indemnity action, we would conclude that the original
    assessment issued on December 19, 2008, was not a final assessment, and cannot be
    analogized to a civil complaint.
    11
    period. [Citations.] “The general rule for defining the accrual of a cause of action sets
    the date as the time ‘when, under the substantive law, the wrongful act is done,’ or the
    wrongful result occurs, and the consequent ‘liability arises.’ [Citation.] In other words, it
    sets the date as the time when the cause of action is complete with all of its elements
    [citations]—the elements being generically referred to by sets of terms such as
    ‘wrongdoing’ or ‘wrongful conduct,’ ‘cause’ or ‘causation,’ and ‘harm’ or ‘injury’
    [citations].” (Norgart [v. Upjohn Co. (1999) 
    21 Cal. 4th 383
    ,] 397 . . .; see also Mosesian
    v. County of 
    Fresno, supra
    , at p. 500 [“A cause of action normally accrues when under
    the substantive law the wrongful act is done and the liability or obligation arises, that is,
    when action may be brought”].) “A cause of action accrues for purposes of the filing
    requirements of the Tort Claims Act on the same date a similar action against a nonpublic
    entity would be deemed to accrue for purposes of applying the relevant statute of
    limitations.” (John R. [v. Oakland Unified School Dist. (1989) 
    48 Cal. 3d 438
    ,] 444,
    fn. 3 . . . accord, Santee v. Santa Clara County Office of Education (1990)
    
    220 Cal. App. 3d 702
    , 708.)’ ”
    As noted, Section 1781, subdivision (a)(1), provides in part that a contractor may
    “bring an action . . . to recover from the body awarding a contract for a public
    work . . . any increased costs incurred by the contractor as a result of any decision by the
    body, the [DIR], or a court that classifies, after the time at which the body accepts the
    contractor’s bid . . . , the work covered by the bid or contract as a ‘public work,’ . . . if
    that body, before the bid opening or awarding of the contract, failed to identify as a
    ‘public work’ . . . in the bid specification or in the contract documents that portion of the
    work that the decision classifies as a ‘public work.’ ” Section 1781, subdivision (c)(2),
    defines “increased costs” as including “[L]abor cost increases required to be paid to
    workers” for prevailing wages and “[P]enalties” for which the contractor is actually
    liable.
    Thus, in this case, to prove the elements of Section 1781, RMC was required to
    show that: (1) DCR, “the body awarding a contract for a public work”; (2) failed to
    identify the work as a “public work” “in the bid specification or in the contract
    12
    documents” “before the bid opening or awarding of the contract”; (3) the work was
    determined by DCR, DIR, or the court, to be a “public work” “after the time at which
    [DCR] accept[ed] [RMC’s] bid”; and (4) RMC “incurred” “increased costs” in the form
    of wages and penalties “as a result” of that determination. Until those elements could be
    established, RMC did not have a Section 1781 claim, and any statutory claim filing
    period had not yet commenced. (See K.J. v. Arcadia Unified School 
    Dist., supra
    ,
    172 Cal.App.4th at pp. 1238–1239.)
    On the issue of when RMC incurred “increased costs,” DCR asserts that RMC
    incurred the costs when DIR served the assessment on December 19, 2008. RMC asserts
    the action accrued when it “paid” the wages and penalties on August 3, 2009, or at the
    earliest in June 2009, when “final determination was made” and it became “liable” or
    “required to pay” $736.711.84 in wages and penalties. We conclude the action accrued
    when the assessment became final and RMC became liable for paying the wages and
    penalties.
    Section 1742, which sets forth the review process for DIR assessments, provides
    that a contractor who receives an assessment may obtain administrative review of that
    assessment “within 60 days after service of the assessment. If no hearing is requested
    within 60 days after service of the assessment, the assessment shall become final.” (Lab.
    Code, § 1742, subd. (a), italics added.) Subdivision (b) provides that if the contractor
    makes a timely request for administrative review, “a hearing shall be commenced within
    90 days before the director . . . [¶] Within 45 days of the conclusion of the hearing, the
    director shall issue a written decision affirming, modifying, or dismissing the assessment.
    The decision of the director shall consist of a notice of findings, findings, and an
    order . . . Within 15 days of the issuance of the decision, the director may reconsider or
    modify the decision to correct an error, except that a clerical error may be corrected at
    any time.” (Id., subd. (b).) Subdivision (c) sets forth the means by which a contractor
    may seek review by way of a petition for a writ of mandate with the superior court, and
    provides that the director’s decision becomes final if no petition for a writ of mandate is
    filed within 45 days of service of the decision. (Id., subd. (c).)
    13
    Here, even though DIR’s original assessment of December 19, 2008, placed RMC
    on notice that there may be an issue concerning the failure to pay prevailing wages, it was
    not until RMC filed a request for a review with the Labor Commissioner and request for a
    settlement meeting, and a final assessment was made in June 2009—in this case, by way
    of a settlement—that RMC was liable for wages and penalties, and in what amount. We
    conclude that the date the assessment became final was the date RMC incurred
    “increased costs” within the meaning of Section 1781. (See Civ. Code, § 2778
    [providing that in the context of a claim for indemnity under a contract, “the person
    indemnified is entitled to recover upon becoming liable,” italics added].) Thus, RMC’s
    claim with the Claims Board, filed March 4, 2010, was timely, within the applicable one
    year limitation for filing a government claim under the Act.
    Relying on cases involving malpractice actions against accountants for faulty tax
    advice, DCR asserts the Section 1781 cause of action accrued when RMC received the
    original December 19, 2008 assessment: “Case law establishing the accrual date of
    actions for injuries caused by tax assessments provides an instructive analogy here, the
    rule being that the accrual date of an action triggered by a tax assessment is the date when
    the government issues the tax assessment and notifies the taxpayer of the deficiency.”
    (Citing, e.g., Moonie v. Lynch (1967) 
    256 Cal. App. 2d 361
    , 364.) Moonie v. Lynch, and
    related cases, however, actually support RMC’s position and our conclusion.
    In International Engine Parts, Inc. v. Feddersen & Co. (1995) 
    9 Cal. 4th 606
    , 608,
    the Supreme Court addressed the issue of when a cause of action against an accountant
    for malpractice “accrues” for purposes of the statute of limitations. The Supreme Court
    rejected the Court of Appeal’s determination that the action accrued upon receipt of an
    assessment by the Internal Revenue Services (IRS), which was “preliminary” in nature,
    and approved Moonie v. 
    Lynch, supra
    , 
    256 Cal. App. 2d 361
    , in which the Court of Appeal
    “employed a different measure” and held “that actual injury in accountant malpractice
    cases occurs on final tax deficiency assessment.” (International Engine Parts, Inc. v.
    Feddersen & 
    Co., supra
    , 9 Cal.4th at p. 608, italics added.) The Supreme Court noted
    that the initial notice merely informed the client that his accountant “may [have caused]
    14
    imposition of tax deficiencies.” (Ibid.) The Supreme Court held that such “potential
    liability” could not amount to actual harm and the accrual of a malpractice claim against
    the accountant until the final deficiency tax assessment issued. In so holding, the court
    noted, “The foregoing rule both conserves judicial resources and avoids forcing the client
    to sue the allegedly negligent accountant for malpractice while the audit is pending. It
    also avoids requiring the client to allege facts in the negligence action that could be used
    against him or her in the audit, without first allowing the accountant to correct the error
    (or mitigate the consequences thereof) during the audit process.” (Id. at p. 620.)
    Similarly, here, the “potential liability” RMC faced upon issuance of the original
    assessment of December 19, 2008, did not amount to actual harm and the accrual of a
    Section 1781 claim against DCR. The above malpractice cases therefore do not support
    DCR’s position.
    DISPOSITION
    The judgment is affirmed. Jon K. Takata Corporation, doing business as
    Restoration Management Company, shall recover its costs on appeal.
    15
    _________________________
    McGuiness, P.J.
    We concur:
    _________________________
    Pollak, J.
    _________________________
    Jenkins, J.
    16