County of Butte v. Dept. of Water Resources ( 2018 )


Menu:
  • Filed 12/20/18
    CERTIFIED FOR PUBLICATION
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    THIRD APPELLATE DISTRICT
    (Yolo)
    ----
    COUNTY OF BUTTE,
    Plaintiff and Appellant,                       C071785
    v.                                              (Super. Ct. Nos. 144283,
    144282)
    DEPARTMENT OF WATER RESOURCES,
    Butte County
    Defendant and Respondent;
    STATE WATER CONTRACTORS, INC., et al.,
    Real Parties in Interest and Respondents.
    COUNTY OF PLUMAS et al.,
    Plaintiffs and Appellants,                  (Super. Ct. No.
    CVCV091258)
    v.
    Yolo County
    DEPARTMENT OF WATER RESOURCES,
    Defendant and Respondent;
    STATE WATER CONTRACTORS, INC., et al.,
    Real Parties in Interest and Respondents.
    1
    APPEAL from a judgment of the Superior Court of Yolo County, Daniel P.
    Maguire, Judge. Dismissed with directions.
    Bruce Alpert, County Counsel; Rossmann and Moore, Antonio Rossmann,
    Roger B. Moore, and Barton Lounsbury for Plaintiff and Appellant County of Butte.
    R. Craig Settlemire, County Counsel; Law Office of Roger B. Moore and Roger B.
    Moore; Law Offices of Michael B. Jackson and Michael B. Jackson for Plaintiffs and
    Appellants Plumas County and Plumas County Flood Control and Water Conservation
    District.
    E. Robert Wright for Friends of the River and the California Sportfishing
    Protection Alliance as Amicus Curiae on behalf of Plaintiffs and Appellants.
    Kamala D. Harris and Xavier Becerra, Attorneys General, Robert W. Byrne,
    Senior Assistant Attorney General, Randy L. Barrow, Deputy Attorney General,
    Deborah L. Barnes and Matthew J. Goldman, Deputy Attorneys General for Defendant
    and Respondent Department of Water Resources.
    The Sohagi Law Group, Margaret M. Sohagi and Philip A. Seymour; Duane Morris,
    Thomas M. Berliner and Jolie-Anne S. Ansley; Downey Brand, David R.E. Aladjem for
    Real Parties in Interest and Respondents Alameda County Flood Control & Water
    Conservation District, Zone 7, Kern County Water Agency, San Bernardino Valley
    Municipal Water District, Santa Clara Valley Water District, The Metropolitan Water
    District of Southern California, and State Water Contractors, Inc.
    The Department of Water Resources (DWR) applied to the Federal Energy
    Regulatory Commission (FERC or Commission) to extend its federal license to operate
    Oroville Dam and its facilities as a hydroelectric dam.1 The project is referred to as the
    Oroville Facilities Project (sometimes also Project or Settlement Agreement (SA)) by
    which the affected parties agree to the conditions for the extended license. “The SA
    includes Appendix A, which incorporates all of the . . . measures that the Settling Parties
    believe to be under FERC’s jurisdiction.”2 The objective of the Project is the continued
    1      The action does not concern the construction, repair, or replacement of the dam
    spillways, the need for which occurred during the pendency of this case.
    2     Throughout this opinion, all quotations are to the Draft Environmental Impact
    Report (DEIR) unless otherwise indicated.
    2
    operation of the Oroville Facilities for power generation and the implementation of
    conditions for the extended license.
    The plaintiffs brought this action in the superior court to stay the license procedure
    on the premise the environmental effects of relicensing the dam concern the operation of
    the dam and that jurisdiction to review the matter lies in the state courts pursuant to the
    California Environmental Quality Act (Pub. Resources Code, § 21000 et seq.; hereinafter
    CEQA).3 They claim that a CEQA document offered to support the DWR’s application
    to FERC failed to consider the impact of climate change on the operation of the dam for
    all the purposes served by the dam. The superior court dismissed the complaint on the
    ground that predicting the impact of climate change is speculative. The plaintiffs
    appealed.
    A federal license is required by the Federal Power Act (16 U.S.C. § 791a et seq.;
    hereinafter FPA) for the construction and operation of a hydroelectric dam. The license
    is issued by FERC. With one relevant exception, the FPA occupies the field of licensing
    a hydroelectric dam and bars review in the state courts of matters subject to review by
    FERC. (See, e.g., First Iowa Hydro-Electric Cooperative v. Federal Power Com. (1946)
    
    328 U.S. 152
    [
    90 L. Ed. 1143
    ] (First Iowa).) The reason is that a dual final authority with
    a duplicate system of state permits and federal licenses required for each project would be
    unworkable. In this case the duplicate authority involves the separate NEPA (National
    Environmental Protection Act) and CEQA reviews of the SA. (Ibid.)
    3        The plaintiffs rely on CEQA case authority to stay the relicensing procedure
    pending state judicial review of the DWR’s approval of the project. (Santiago County
    Water Dist. v. County of Orange (1981) 
    118 Cal. App. 3d 818
    , 829 (Santiago County).)
    Plaintiff Butte County requested that the state court “[e]njoin DWR’s project until and
    unless respondent [DWR] lawfully approves the project in the manner required by CEQA
    . . . .” Plaintiff County of Plumas requested that: “Respondents and real parties in
    interest . . . suspend all activity under the certification that could result in any change or
    alteration in the physical environment until respondent has taken actions that may be
    necessary to bring the certification into compliance with CEQA.”
    3
    The exception to preemption lies with the state’s authority to impose more
    stringent water quality conditions on the license than federally required pursuant to
    section 401 (33 U.S.C. § 1341; hereinafter section 401) of the Clean Water Act4 (33
    U.S.C. § 1251 et seq.).5 In California the authority to establish the conditions is vested in
    the state water pollution control board (now State Water Resources Control Board
    (SWRCB)). (Wat. Code, § 13160 et seq.) The conditions must be set forth in a
    certificate to be incorporated in the license.6 The environmental predicate for the
    certificate is set forth in Appendix A of the SA in both NEPA and CEQA reviews of the
    conditions for the license. To avoid duplication of federal and state environmental
    reviews, the jurisdiction to review the conditions lies with FERC.
    Oroville Dam was completed in 1968 as part of the State Water Project (SWP). It
    blocks access to 66.9 miles of high-quality habitat for anadromous fish (salmon &
    steelhead). FERC licenses are conditioned on the adoption of a plan for the “adequate
    protection, mitigation, and enhancement of fish and wildlife . . . and for other beneficial
    public uses, including irrigation, flood control, water supply, and recreational and other
    purposes . . . .” (16 U.S.C. § 803(a)(1).) The Feather River Fish Hatchery was built to
    4       The Clean Water Act provides: “Any applicant for a Federal license or permit to
    conduct any activity including, but not limited to, the construction or operation of
    facilities, which may result in any discharge into the navigable waters, shall provide the
    licensing or permitting agency a certification from the State in which the discharge
    originates or will originate, or, if appropriate, from the interstate water pollution control
    agency having jurisdiction over the navigable waters at the point where the discharge
    originates or will originate, that any such discharge will comply with the applicable
    provisions of sections 301, 302, 303, 306, and 307 of this Act [33 U.S.C. §§ 1311, 1312,
    1313, 1316, 1317].” (33 U.S.C. § 1341(a)(1).)
    5      The formal name of the Clean Water Act is the Federal Water Pollution Control
    Act.
    6       References to a certificate is to the law generally, references to the “Certificate”
    are to the SWRCB certificate issued December 15, 2010. (State Water Resources
    Control Board, Order WQ 2010-0016 (Dec. 15, 2010).)
    4
    compensate for the loss of spawning grounds resulting from the construction of Oroville
    Dam.
    The DWR proposes, in fulfillment of the environmental requirements of section
    803 of title 16 of the United States Code, that new measures be taken to improve the
    conditions of fish and wildlife affected by the presence of the dam. The measures include
    a commitment by DWR to develop plans to enhance, protect, restore, and/or create
    habitat within the FERC boundary to be set forth in a certificate. These plans, referred to
    as the “New Project License,” are subject to CEQA environmental review when
    implemented.7 The DWR has selected a federal alternative procedure, an SA, for the
    fulfillment of its obligations. The SA involves the agreement of the parties affected by
    the extended license.
    We shall conclude that the plaintiffs cannot challenge the environmental
    sufficiency of the SA in the state courts because jurisdiction to review the matter lies with
    FERC and plaintiffs did not seek federal review as required by 18 Code of Federal
    Regulations part 4.34(i)(6)(vii) (2003). Moreover, the plaintiffs did not challenge and
    could not challenge the SWRCB Certificate itself in their pleadings because it did not
    exist at the time this action was filed. The extended license issues upon the filing of a
    certificate and that cannot be delayed beyond one year from the date of a request for the
    certificate. “Section 401(a)(1) requires that a State ‘act on a request for certification[]
    within a reasonable period of time (which shall not exceed one year) after receipt of such
    request,’ or else ‘the certification requirements of this subsection shall be waived . . . .’ ”
    (Alcoa Power Generating Inc. v. FERC (D.C. Cir. 2011) 
    643 F.3d 963
    , 972.) It is only
    after the issuance of the license that the Certificate may be implemented.
    7       A project under CEQA is defined as a physical change in the environment. Public
    Resources Code section 21065 defines “ ‘Project’ ” as: “an activity which may cause
    either a direct physical change in the environment, or a reasonably foreseeable indirect
    change in the environment . . . .”
    5
    Accordingly, this court has no jurisdiction of the cause tendered. We shall return
    the case to the trial court with an order to dismiss the complaint for lack of subject matter
    jurisdiction.8
    DISCUSSION9
    A. The Oroville FERC Project and its Multiple Uses
    The Oroville FERC Project No. 2100 is located on the Feather River in the Sierra
    Nevada foothills in Butte County, California. The Oroville Facilities were constructed
    between 1961 and 1968 as part of the SWP, a water storage and delivery system of
    reservoirs, aqueducts, power plants, and pumping plants designed to provide flood
    control and to store and distribute water to supplement the needs of urban and agricultural
    water users in both northern and southern California. The Oroville Dam is the largest
    earthen dam in the United States. The Oroville Facilities Project is operated for power
    generation, water quality improvement in the Sacramento–San Joaquin Delta, recreation,
    fish and wildlife enhancement, and flood management. The dam is designed to access
    8       The court advised the parties that its tentative view was that the relicensing of the
    Oroville Dam and Oroville Facilities Project is preempted by the FPA and implementing
    regulations (e.g., 18 C.F.R. §§ 4.34, 385.602 (2003)) and that jurisdiction over a
    challenge to the issuance of the license lies with FERC. Accordingly, the case should be
    returned to the superior court with directions to dismiss the action for lack of federal
    subject matter jurisdiction. We invited the parties to submit supplemental briefs in
    response to our advice. They did so and agreed that the case was subject to federal law
    except for the environmental program contained in a certificate prepared by the SWRCB.
    The plaintiffs then sought to challenge the environmental predicate for the Certificate
    setting forth the state’s more stringent water quality provisions on the ground it also fails
    to consider climate change. The challenge cannot succeed because the Certificate did not
    exist at the time the case was filed and the program required by the Certificate cannot be
    challenged until it is implemented by the DWR. That has not occurred because
    implementation is dependent upon the filing of the Certificate. Accordingly, there is no
    issue regarding the implementation of the Certificate to review on appeal.
    9      The facts and procedure regarding the subject of jurisdiction appear at relevant
    points in the Discussion.
    6
    the waters of Lake Oroville at different depths to allow control of the temperature of the
    water discharged from the dam. The only physical change to the existing dam is the
    opening of a water valve to access the cold water at the bottom of Lake Oroville.10
    The Oroville Facilities include facilities and operations to help protect and
    enhance fish and wildlife species and their habitat. Many of the existing environmental
    programs implemented within the Oroville Facilities Project boundary are cooperatively
    managed or are based on agreements with other agencies such as the Department of Fish
    and Game and the United States Fish and Wildlife Service. This includes operation and
    maintenance of facilities such as the Feather River Fish Hatchery and the Oroville
    Wildlife Area and implementation of measures developed in consultation with interested
    parties to protect species that are listed under the Federal Endangered Species Act and/or
    the California Endangered Species Act.
    As an integral part of the SWP, water stored in Lake Oroville is released from the
    Oroville Facilities to meet a variety of statutory, contractual water supply, flood
    management, and environmental commitments. These contractual, flood management,
    fishery, water quality, and other environmental obligations are defined in numerous
    operating agreements that specify timing, flow limits, storage amounts, and/or constraints
    on water releases. The relicensing of the operation of the dam is consistent with these
    existing commitments and no changes to the contractual obligations or to the general
    pattern of these releases are anticipated.
    The Oroville Facilities are also important components of the Sacramento River
    Flood Control Project, the flood management system for areas along the Feather and
    Sacramento rivers downstream of Oroville Dam. The Oroville Facilities provide flood
    protection benefits to Oroville, other portions of Butte County, Marysville, Yuba City,
    10      The water valve permits access to cooler water from the bottom of Lake Oroville
    that is fed by the Feather River, which flows through a tunnel built during the
    construction of the dam to convey water from the river around the site of the dam.
    7
    other portions of Yuba and Sutter counties, and many smaller communities downstream
    to Sacramento. The use of the dam to control floods is governed by federal regulations
    issued by the U.S. Army Corps of Engineers. The Oroville Facilities also provide
    protection to 283,000 acres of developed agricultural lands and a variety of transportation
    and other public utility infrastructure. Pursuant to section 204 of the federal Flood
    Control Act of 1958, flood control operations at Oroville are governed by the rules and
    regulations prescribed by the Secretary of the Army. The Proposed Project is consistent
    with existing U.S. Army Corps of Engineers flood management objectives.
    B. Federal Preemption
    With one relevant exception, the FPA occupies the field of licensing a
    hydroelectric dam and bars environmental review of the federal licensing procedure in
    the state courts. (First 
    Iowa, supra
    , 
    328 U.S. 152
    ; California v. FERC (1990) 
    495 U.S. 490
    [
    109 L. Ed. 2d 474
    ]; cf. Sayles Hydro Ass’n v. Maughan (9th Circ. 1993) 
    985 F.2d 451
    ; Karuk Tribe of Northern California v. California Regional Water Quality Control
    Bd., North Coast Region (2010) 
    183 Cal. App. 4th 330
    .)
    The lead case is First Iowa. A state license issued for a hydroelectric dam
    bypassed the federal licensing system and was enforced in the state courts. The Supreme
    Court held that the federal law preempted the state law and barred its application in the
    state courts. The court explained that under the FPA “there is a separation of those
    subjects which remain under the jurisdiction of the states from those subjects which the
    Constitution delegates to the United States and over which Congress vests the Federal
    Power Commission with authority to act. To the extent of this separation, the Act
    establishes a dual system of control. The duality of control consists merely of the
    division of the common enterprise between two cooperating agencies of government,
    each with final authority in its own jurisdiction. . . . A dual final authority, with a
    duplicate system of state permits and federal licenses required for each project, would be
    unworkable. . . . [For that reason] [s]ection 9(c) [of the FPA] permits the Commission to
    8
    secure from the [state] applicant ‘[s]uch additional information as the Commission may
    require.’ This enables it to secure, in so far as it deems material, such parts, or all of the
    information that the respective States may have prescribed in state statutes as a basis for
    state action.” (First 
    Iowa, supra
    , 328 U.S. at pp. 167-169, italics added, italics omitted,
    fns. omitted.) Here that would include the CEQA document in Appendix A of the SA
    that is the predicate environmental study for the Certificate. Otherwise, First Iowa says,
    the federal law would vest in a state, a veto power over a federal project. “Such a veto
    power easily could destroy the effectiveness of the [FPA]. It would subordinate to the
    control of the State the ‘comprehensive’ planning which the Act provides . . . .” (Id. at
    p. 164.) For the same reasons a state cannot delay a FERC license by issuing a certificate
    beyond one year of a request for a certificate.
    Thus, pursuant to First Iowa, the state review of the environmental information
    within the jurisdiction of FERC and contained in the CEQA document cannot be used to
    delay the issuance of the license.
    C. The Clean Water Act Exception
    The exception to federal jurisdiction is found in section 401 of the Clean Water
    Act. (33 U.S.C. § 1341.) FERC requires that every application for a federal license that
    may result in the discharge of pollutants into navigable waters, including pollutants from
    the discharge of water from a dam, must provide FERC with a certificate that the Project
    has complied with the state law that regulates the pollution of water. (33 U.S.C. § 1341;
    S.D. Warren Co. v. Maine Bd. of Environmental Protection (2006) 
    547 U.S. 370
    [
    164 L. Ed. 2d 625
    ]; Wat. Code, § 13160 et seq.). The term pollution includes the temperature
    and flow of water that impacts the lives of fish in the water below the dam.
    Before FERC can issue a new license to DWR, the SWRCB must first issue a
    water quality certificate pursuant to section 401 of the Clean Water Act and the Porter-
    Cologne Act, Water Code section 13160 et seq. However, as noted, the state, including
    its courts, cannot delay the issuance of a certificate beyond one year from the date of a
    9
    request to issue a certificate. In issuing its water quality certification, the SWRCB
    certifies that the Proposed Project will comply with specified provisions of the Clean
    Water Act, including water quality standards that are developed pursuant to state law and
    in satisfaction of Clean Water Act section 303 (33 U.S.C. § 1313). Preparation and
    certification of an Environmental Impact Report under the terms of CEQA and directed
    to the environmental effects of the state’s more stringent water quality law is required
    before the SWRCB can take action. This DEIR is intended to fulfill that purpose, and
    considers three alternatives: the No-Project Alternative, the Proposed Project (SA), and
    the FERC Staff Alternative described in the FERC Draft Environmental Impact
    Statement (DEIS).
    The SA contains appendices. It provides that the CEQA “program” in Appendix
    A is subject to amendment by the SWRCB to comply with the state’s more stringent
    clean water law pursuant to section 401 of the federal Clean Water Act. The “amended
    program” is set forth in a certificate issued by the SWRCB as conditions to the FERC
    license to be implemented when imposed after the license is issued. “Preparation and
    certification of an EIR under the terms of CEQA is required before the SWRCB can take
    action.” The DEIR provides that when the “amended program” in the Certificate is
    implemented (i.e., constructed) the implementation may be subject to CEQA review in
    the state courts.
    In this case the Certificate includes an amendment to set water temperature
    requirements for the fish hatchery as required by a 1983 agreement between DWR and
    the Department of Fish and Game. It mandates that the water temperature of discharged
    water be lowered by a specified amount “[a]fter facility modifications [required by the
    Certificate], but no later than 10 years after [issuance of the] license.” “Because of the
    importance of the river valve [(that permits taking water from the deepest and coolest
    parts of Lake Oroville)] for temperature control” the Certificate also requires that “a
    10
    timeline be submitted within six months of license issuance that includes the steps
    necessary to finalize the repair or refurbishment of the river valve.”
    D. The Relicensing Procedure
    The federal law provides for an alternative licensing procedure (ALP). We note
    that the federal administrative regulation does not refer to CEQA. (See 18 C.F.R.
    § 4.34(i)(6)(vii) (2003).) The purpose of the ALP is to “resolv[e] all issues that have or
    could have been raised by the Parties in connection with FERC’s order issuing a New
    Project License . . . .” The ALP “combine[s] into a single process the pre-filing
    consultation process, the environmental review process under the National Environmental
    Policy Act and administrative processes associated with the [federal] Clean Water Act
    and other statutes, . . .” (18 C.F.R. § 4.34(i)(2)(i) (2003).) The SA provides that these
    requirements are incorporated in the license as conditions of the license.
    The ALP substitutes the environmental report, normally required in an application
    to FERC, with a “Preliminary Draft Environmental Assessment (PDEA).” “The ALP is
    intended to expedite the licensing process by combining the prefiling consultation and
    federal and State environmental review process into a single process.” After DWR
    submitted its draft license application and draft PDEA the stakeholders continued to
    negotiate and ultimately developed the SA, which was signed by 52 parties and adopted
    by DWR as the Proposed Project and submitted to FERC.
    The SA includes “[t]he cooperative scoping of environmental issues (including
    necessary scientific studies), the analysis of completed studies” and “[t]he preparation of
    a [PDEA] . . . .” (18 C.F.R. § 4.34(i)(4)(ii) & (iii) (2003).) The purpose of the SA is to
    “resolve[] all issues that may arise in the issuance of all permits and approvals associated
    with the issuance of the New Project License, including . . . . Section 401 Certification,
    [National Environmental Policy Act] and CEQA.” The SA includes two appendices
    11
    which mark the line between federal (Appendix A) and state (Appendix B)11 jurisdiction.
    In its federal NEPA environmental impact statement for the Project, FERC evaluated
    only Appendix A of the SA.
    Thus, in keeping with First Iowa, Appendix A of the SA sets out the matters
    subject to federal jurisdiction. The potentially confusing aspect of the procedure is the
    presence of a lengthy CEQA document. It serves two purposes. It provides the
    underlying environmental studies supporting both the FERC application (PDEA) and the
    state’s more stringent clean water law. The environmental matter set forth in the SA is
    reviewable by FERC for purposes of the PDEA and by the SWRCB as a predicate for the
    state’s more stringent water quality conditions.
    That is all that is required for issuance of the FERC license. As noted, the
    implementation of the clean water rules is potentially subject to further CEQA review.
    The program contained in the Certificate provides for further studies and implementation
    of the state’s more stringent clean water law rules after the issuance of the FERC license.
    Thus the program in Appendix A fulfills two functions. (1) It provides the state’s
    environmental information to meet FERC’s requirements (PDEA). (2) It supplies the
    environmental information from which the SWRCB develops the state’s clean water law
    in a certificate.
    “[T]he SA was submitted to FERC on March 24, 2006, as supplemental
    information to support the license application that DWR filed in January 2005 for
    consideration as future license conditions to the Oroville license for the next 50 years.”
    “The objective of the Proposed Project is the continued operation and maintenance
    of the Oroville Facilities for electric power generation, including implementation of any
    11     Appendix B contains agreements by the parties that are not required by federal law
    including the contribution of money to construct the new facilities. No issue regarding
    Appendix B has been tendered.
    12
    terms and conditions [(adopted by the SWRCB)] to be considered for inclusion in a new
    FERC hydroelectric license.” (Italics added.)
    In this case “[t]he SA includes a commitment by DWR to develop, in consultation
    with stakeholders, a number of plans to enhance, protect, mitigate, restore, and/or create
    habitat within the FERC Project boundary. It also requires that DWR complete a number
    of studies and conduct monitoring to guide future decisions and activities. While these
    . . . will likely lead to future actions that would be subject to CEQA environmental
    review prior to implementation . . . [they] do not result in a physical change to the
    environment and thus are not ready for project-specific CEQA analysis at this time.”12
    “The SA includes Appendix A, which incorporates all of the protection,
    mitigation, and enhancement . . . measures that the Settling Parties believe to be under
    FERC’s jurisdiction in Proposed License Articles, and Appendix B, which includes all of
    the PM&E measures and other agreements that the Settling Parties believe to be outside
    of FERC’s jurisdiction or that are commitments made by parties other than DWR.”
    “In general, SA Appendix A includes a commitment by DWR to develop, in
    consultation with stakeholders, numerous environmental plans and programs. These
    environmental plans and programs would improve fish spawning and rearing habitat to
    complement FESA anadromous fish species recovery programs, support the Feather
    River Fish Hatchery, provide additional habitat for waterfowl, provide protection for
    terrestrial FESA species, monitor water quality in project waters, improve habitat for
    warmwater fish species and improve the coldwater fishery in Lake Oroville, and provide
    new management direction for the [Oroville Wildlife Area].”
    A dispute concerning “required [environmental] studies,” tendered by an entity
    “participating” in the ALP, is subject to federal administrative review before FERC. (18
    12     The review of the proposed implementation of the changes made by the SWRCB
    in the Certificate is the only point at which CEQA applies to the licensing procedure.
    13
    C.F.R. § 4.34 (i)(6)(vii) (2003).) Plaintiffs, as participants in the SA, tendered a dispute
    regarding “required studies” but failed to seek relief before FERC. Accordingly, they
    failed to exhaust their federal administrative remedies. The SA also contains Appendix
    B, which sets forth agreements by the parties not required by federal law. No such
    agreement is at issue in this case.
    E. The New Project License
    Although the Oroville Facilities Project that is subject to licensing is the SA, the
    project subject to environmental review is referred to in Appendix A as the “New Project
    License.” It is subject to review before FERC because the applicants of the SA
    “participat[e] in the alternative pre-filing consultation process.”13 As the CEQA
    document explains, this project, does “not . . . include any annual license extending the
    original license” for the dam. Rather, it sets forth the environmental proposals that
    physically condition the new license. For this reason, it does not include the
    environmental effects of the operation of the dam but only the environmental effects of
    the projects encompassed by the New Project License, i.e, the projects listed in the
    Certificate.
    A source of confusion is the classification of the overall project subject to the
    FERC license as the Oroville Dam and Oroville Facilities Project. However, the project
    subject to environmental review in this case is not the existing dam and facilities but the
    project to further mitigate the loss of habitat caused by the construction of the dam, and
    that is referred to as the New Project License. This project would increase the habitat
    along the lower reaches of the Feather River, open a water valve to access colder water at
    13     Title 18 Code of Federal Regulations part 4.34(i)(6)(vii) (2003) provides in
    relevant part: “Any potential applicant, resource agency, Indian Tribe, citizens’ group, or
    other entity participating in the alternative pre-filing consultation process may file a
    request with the Commission to resolve a dispute concerning the alternative process
    (including a dispute over required studies) . . . .” (Italics added.)
    14
    the bottom of Lake Oroville to meet hatchery temperature requirements, improve the
    spawning of fish by channel and gravel improvement plans, and regulate the flow of
    water from the dam.14 Only the implementation of the conditions set forth in the
    Certificate relating to the state’s clean water law, some of them to be completed years
    after the license is issued, is subject to independent CEQA review in the state courts.
    There is an extensive CEQA document (DEIR) in the record and it is this
    document that the plaintiffs rely on in their CEQA challenge. It serves two purposes.
    First, it satisfies the state’s obligation to provide environmental information to FERC. It
    is used “to evaluate the potential effects of implementing the SA as new license terms
    and conditions for the continued operation of the hydroelectric component of the Oroville
    Facilities.” That, however, is reviewable before FERC as general conditions for the
    operation of the dam.
    The federal law has its own means of review of contested issues in the settlement
    process. Under 18 Code of Federal Regulations part 385.602(h)(1)(i) (2003), if FERC
    determines that any offer of settlement is contested by any party, the Commission may
    decide the merits of the issues if the record contains substantial evidence upon which to
    base a reasoned decision or it determines there is no genuine issue of material fact.15 (18
    C.F.R. § 385.602(h)(1)(i) (2003).)
    14     Insofar as the implementation of the changes made by the SWRCB to the “New
    Project License” (Appendix A) are subject to CEQA analysis it is programmatic. (Pub.
    Resources Code, §§ 21093, 21094.) The CEQA “program” is set forth in Appendix A as
    the environmental predicate for the Certificate. As noted, the CEQA “program” set forth
    in Appendix A is subject to federal administrative review before FERC pursuant to
    NEPA. (18 C.F.R. § 4.34(i)(6)(vii) (2003).)
    15    If the Commission determines that the record does not contain substantial
    evidence, the Commission has the option to take other action which the Commission
    determines to be appropriate. (18 C.F.R. § 385.602(h)(1)(ii)(B) (2003).)
    15
    Second, the DEIR provides an analysis for the preparation of a “water quality
    certification for the Proposed Project from the [SWRCB] under Section 401 of the
    [federal] Clean Water Act.” The primary purpose of the DEIR is “to identify . . . any
    potential . . . environmental impacts that may result from implementation of” the New
    Project License. It provides for environmental studies that support the changes made by
    the SWRCB in the Certificate. To the extent that CEQA applies to the Certificate it is to
    the proposed implementation of the changes by the SWRCB. (See 33 U.S.C. § 1341(d).)
    Appendix A also functions as a PDEA, an “analysis required under [the federal] NEPA in
    support of relicensing.”
    In this respect the state laws are not a part of relicensing and cannot be used to
    delay relicensing by resort to the state courts. The SA is clear that the purpose of the SA
    is to “resolv[e] all issues that have or could have been raised by the Parties in connection
    with FERC’s order issuing a New Project License . . . .” “[I]t is the Parties’ intention that
    this [SA] also resolves all issues that may arise in issuance of all permits and approvals
    associated with the issuance of the New Project License, including but not limited to . . .
    CWA [Clean Water Act] Section 401 Certification, NEPA and CEQA.”
    Although “[t]he DEIR analyzes the potential impacts of implementing the SA
    including all its appendices, as DWR’s proposed project, the matters subject to
    environmental review by the state required to obtain an extended license include only the
    matters in Appendix A. The state’s environmental information provided in Appendix A,
    which is expressly made subject to federal jurisdiction, satisfies the state’s environmental
    obligation with respect to the federal license. It also provides the environmental
    information in support of the programmatic portion of the New Project License which is
    the environmental predicate for review of the “program” by the SWRCB for compliance
    with the state’s more stringent clean water law.
    The program set forth in the “New Project License” was submitted to the SWRCB
    for its review pursuant to the California Clean Water Act. (Porter-Cologne Act, Wat.
    16
    Code, § 13160 et seq.) The changes made to the program are set forth in a certificate
    (adopted December 15, 2010, two years after the filing of this action). The Certificate
    has not been filed with FERC because of the pendency of this action.16 The CEQA
    document asserts only that the changes made to the program by the SWRCB in the
    Certificate are subject to CEQA review in the state courts when implemented after the
    Certificate is submitted to FERC and the license issued.
    Neither the program subject to the SWRCB review, nor the Certificate by which
    SWRCB exercises its section 401 authority to implement the provisions of Appendix A
    are the subject of plaintiffs’ petition. Because the plaintiffs’ petition was filed in the state
    court two years before the SWRCB adopted the Certificate, no issue is tendered
    concerning the changes the Certificate makes to the program, and no action under CEQA
    to review the changes can be filed in a state court until after the license is issued and the
    changes implemented. As a consequence, they have not tendered a question of how the
    CEQA part of the section 401 review meshes with the non-CEQA part of the licensing
    process.
    F. The Parties’ Status
    The plaintiffs participated extensively in the ALP but refused to sign the SA. As a
    consequence, they are not parties to the SA and have no procedural rights pursuant to its
    internal review procedures in Appendix B of the SA to dispute the agreement of the
    parties.17 Nor did the plaintiffs seek administrative review of the New Project License
    before FERC as required by 18 Code of Federal Regulations part 4.34(6)(vii) (2003).
    16     The plaintiffs rely on CEQA case authority to stay the relicensing procedure
    pending state judicial review of the DWR’s approval of the project. (Santiago 
    County, supra
    , 118 Cal.App.3d at p. 829.)
    17     The internal review procedures apply to matters agreed to by the parties that are
    not subject to FERC review, such as the provision of funds to carry out the agreements.
    As noted, no such issue is tendered in this action.
    17
    Instead, on August 21, 2008, they filed a CEQA complaint for a writ of mandate in the
    state superior court challenging the environmental effects of climate change on the
    operation of the dam and facilities for all the purposes served by the SWP. It is the
    propriety of the appeal from the judgment of the superior court in that action that we
    consider.
    The plaintiffs argue that the SA applies only to entities that have signed the SA as
    parties. That is true, but the source of the plaintiffs’ contractual rights, if any, is the SA.
    There is one remedy for which status as a party is not required, and it is a federal remedy
    for the violation of the environmental requirements of federal law. “Any . . . entity
    participating in the alternative pre-filing consultation process may file a request with the
    Commission to resolve a dispute concerning the alternative process (including a dispute
    over required studies) . . . .” (18 C.F.R. § 4.34(i)(6)(vii) (2003), italics added.) The
    plaintiffs participated extensively in the pre-filing consultation process and tendered
    essentially the same climate change argument and supporting data for consideration by
    the SA in their opening brief as CEQA claims, but refused to sign the SA as a party.
    Since the plaintiffs are not parties to the SA and did not utilize its administrative process
    they have no rights under the SA and cannot challenge the provisions of the SA relating
    to Appendix B.
    The plaintiffs alleged that the SA did not consider the impact of global climate
    change on DWR’s continued operation of the existing dam and facilities for the purposes
    served by the SWP. They argue that “[c]limate change will almost certainly affect the
    project’s ability to meet water supply, water temperature, water quality, flood
    management, and recreational requirements, thus severely impacting human populations
    and ecosystems.”18 A project subject to CEQA review involves the environmental
    18     In their initial briefing, the plaintiffs challenged the project description as
    “truncated,” as failing to include all the uses to which water from the dam would be put
    pursuant to the SWP. These are referred to as “project operations.” The plaintiffs argue:
    18
    consequences of a physical change in the environment. Since no physical changes are
    planned for the dam itself,19 other than the reopening of the water valve, the plaintiffs
    assume the project subject to environmental review is the DWR’s operation of the dam as
    part of the SWP.
    The plaintiffs do not claim that, given climate change, the environmental measures
    in Appendix A would cause an environmentally harmful physical change in the
    environment, since Appendix A is designed to ameliorate environmental harms caused by
    the existing dam. Rather, they claim that the impact of climate change on the continued
    operation of the dam would affect the DWR’s ability to carry out the purposes served by
    the SWP.
    The respondents reply that the impact of climate change on the operation of the
    dam is too speculative to require consideration under CEQA. The superior court agreed
    and entered a judgment in favor of the respondents. This is the posture in which the
    appellate case was initially briefed.
    The operation of the existing dam and facilities, however, is not the project subject
    to environmental review. The project subject to review is labeled the New Project
    License and expressly does “not . . . include any annual license extending the original
    “Climate change will almost certainly affect the project’s ability to meet water supply,
    water temperature, water quality, flood management, and recreational requirements, thus
    severely impacting human populations and ecosystems. DWR’s own report discusses
    several impacts but never analyzes them in light of climate change due to the EIR’s
    erroneous assumption of stationarity.” (Fn. omitted.) “ ‘[R]eservoirs will likely
    experience changes in the rate and timing of inflow. Changes in reservoir operations and
    reduced annual storage in snowpack could result in less water being available in the
    summer and fall to meet Delta outflow and salinity requirements.’ ”
    It is true that changes in the earth’s climate could affect the temperature or flow of
    water to the new environmental project, but as noted, any such argument must be made
    when the project in the Certificate is implemented.
    19     See footnote 1, ante.
    19
    license . . . .” The New Project License does include new spawning grounds for
    anadromous fish and changes in the temperature and flow of water from the dam to
    improve the spawning and survivability of the fish. It is subject to review by the
    SWRCB for compliance with California’s clean water laws.
    The parties were likely misled by the lengthy CEQA document in the record that
    includes a CEQA review of the environmental consequences of relicensing the existing
    dam. From this premise the plaintiffs argue that DWR should have considered the
    project subject to environmental review as the environmental impact of climate change
    on the operation of the dam and facilities, as part of the SWP, and that, as a result, the
    DWR failed to consider the consequences of climate change on the operation. It was on
    this basis that the plaintiffs claimed the decision to approve the project and issue the
    license should be stayed pending a state court resolution of their CEQA claims.
    (Santiago 
    County, supra
    , 118 Cal.App.3d at p. 829.)
    The plaintiffs’ primary mistake is that the project subject to environmental review
    by the state is not the dam and facilities as built, but the project to further mitigate the
    loss of habitat caused by construction of the dam in 1967, increasing the habitat along the
    lower reaches of the Feather River, opening a water valve to access colder water at the
    bottom of Lake Oroville to meet hatchery temperature requirements, improving the
    spawning of fish by channel and gravel improvement plans, and regulating the flow of
    water from the dam.
    The correct view of the project tenders questions of federal administrative and
    substantive law applicable to the relicensing of a hydroelectric dam and its facilities.
    DISPOSITION
    The plaintiffs cannot challenge the environmental sufficiency of the program in
    Appendix A because review of that program lies with FERC and they did not seek review
    as required by 18 Code of Federal Regulations part 4.34(i)(6)(vii) (2003). The plaintiffs
    20
    cannot challenge the environmental predicate to the Certificate contained in the CEQA
    document because that is subject to review by FERC. The plaintiffs cannot challenge the
    Certificate because it did not exist when this action was filed, and they cannot challenge
    the changes made by the SWRCB in the Certificate until they are implemented. For these
    reasons the parties have not tendered a federal issue over which this court has state
    CEQA jurisdiction. Accordingly, we shall dismiss the appeal with directions to the trial
    court to vacate its judgment and dismiss the action for lack of subject matter jurisdiction.
    Costs are awarded to respondents. (Cal. Rules of Court, rule 8.278(a)(1), (2).)
    /s/
    Blease, J.
    We concur:
    /s/
    Raye, P. J.
    /s/
    Hull, J.
    21