Valley Commercial Contractors v. Windsor Walnut Creek Apt CA1/1 ( 2016 )


Menu:
  • Filed 2/11/16 Valley Commercial Contractors v. Windsor Walnut Creek Apt CA1/1
    NOT TO BE PUBLISHED IN OFFICIAL REPORTS
    California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
    publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication
    or ordered published for purposes of rule 8.1115.
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    FIRST APPELLATE DISTRICT
    DIVISION ONE
    VALLEY COMMERCIAL
    CONTRACTORS, L.P.,
    Plaintiff and Respondent,                                  A141069
    v.                                                                  (Contra Costa County
    WINDSOR WALNUT CREEK                                                Super. Ct. No. C 08-02958)
    APARTMENTS, LLC et al.,
    Defendants and Appellants.
    VALLEY COMMERCIAL
    CONTRACTORS, L.P. et al.
    A141661
    Plaintiffs and Appellants,
    v.                                                                  (Contra Costa County
    Super. Ct. No. C 08-02958)
    TARGIO PROPERTIES,
    Defendant and Appellant.
    In this construction dispute, defendants Windsor Walnut Creek Apartments, LLC
    (WWCA) and Windsor Capital Group, Inc. (WCG) appeal from the judgment after jury
    trial in favor of plaintiff Valley Commercial Contractors, L.P. (Valley). Defendant
    Tarigo Properties, LLC (Tarigo), joins WWCA’s appeal and has filed its own appeal
    challenging the interest rate the trial court applied to Valley’s mechanic’s lien. Valley
    cross-appeals from the court’s denial of its motion seeking cost of proof sanctions against
    WWCA based on that defendant’s denial of a request for admission. We reverse the
    judgment as to the interest rate on the mechanic’s lien. In all other respects, we affirm.
    FACTUAL AND PROCEDURAL BACKGROUND
    I. Construction Project Background
    A. The Parties and Their Associates
    WWCA is the former owner and developer of real property located at 2383 Main
    Street in the City of Walnut Creek (City). This case arises out of the construction of a
    125-unit apartment complex (Project) located on the property. The Project is a three-
    story wood frame structure over a concrete podium deck with two levels of subterranean
    parking. Patrick Nesbitt is the executive vice-president of WCG, which is a real estate
    development and management company. WWCA is a single purpose entity established
    by WCG for the development of the Project.
    Valley is a general contractor. As a general contractor, Valley’s job is to manage
    and coordinate the subcontractors who work on construction projects. Jeffrey DeWeese
    is Valley’s president, a position he has held since 1990. Between 1990 and 2005, Valley
    built over 50 commercial properties, including multi-family senior housing units, multi-
    story office buildings, skilled nursing facilities, and government buildings. Just prior to
    starting work on the Project, Valley began a five-story, structural steel office building
    over one level of underground parking. Valley had also recently built a 125,000-square-
    foot warehouse, and had substantially remodeled four 17-story residential towers. While
    Valley had constructed both concrete and wooden buildings, prior to 2005 it had not built
    a combined concrete and wooden structure.
    DeWeese first learned of the Project through a construction management firm
    called ProPM. ProPM was retained by WWCA in 2005. At that time, the Project was in
    the preconstruction stage.
    David Zainer is an owner’s representative who performs construction management
    services. Zainer first became aware of the Project in early 2005 when he met ProPM’s
    owner. Zainer eventually became a half-owner of ProPM. As the owner’s representative
    for the Project, Zainer’s job included reviewing change order requests. He also served as
    a mentor for Nesbitt.
    2
    Norman Harris is a licensed architect with a company called HDO Architects
    (HDO). In 2004, WWCA hired HDO to design the Project. HDO retained the assistance
    of two structural engineers, one for the concrete portion of the Project and one for the
    framing portion. Three design-build subcontractors were also under HDO’s supervision
    with respect to the design portion of their work, one each for mechanical, electrical, and
    plumbing (MEPs).
    B. Initial Stages of the Project
    The first phase of Harris’s work involved obtaining an entitlement from the City,
    which granted WWCA the right to build the apartment complex in advance of the
    submission of detailed drawings needed to secure a building permit. In 2005, he began
    preparing the working drawings for the Project. These drawings were compiled in the
    project manual, a book of about 500 pages that incorporated all of the Project’s plans and
    specifications. Harris substantially completed the initial set of drawings sometime in
    2005. The plans for the above-ground structure were not permitted until September
    2006.
    In September 2005, Valley and WWCA entered in to a written agreement
    (Construction Contract) in which Valley agreed to build the Project for the total price of
    $22,152,595. The Project was to be substantially completed in 20 months.1 Valley
    agreed to update the work schedule on a monthly basis or at appropriate intervals as
    required by the work conditions. Construction on the Project began in October 2005.
    John Correa served as Valley’s project manager. Dan Evans was Valley’s project
    engineer.
    II.      Project Delays
    Much of the testimony at trial was devoted to assigning responsibility for the
    many delays that occurred during the course of the Project’s construction. We view the
    evidence in the light most favorable to the judgment, accepting as true all evidence
    1
    As it turned out, the Project was not substantially completed until June 2009.
    3
    tending to support it. (See Bertero v. National General Corp. (1974) 
    13 Cal. 3d 43
    , 61
    (Bertero); Quigley v. McClellan (2013) 
    214 Cal. App. 4th 1276
    , 1278, fn. 1.)
    A. Delays in Obtaining City Permits
    Before the Construction Contract was signed, ProPM told Valley all permits for
    the Project had been obtained.2 This turned out not to be the case.3 Among the permits
    that had not been issued were the asphalt permits and the permit for the above-ground
    wooden structure. Five or six months into construction, the architectural plans for the
    wooden structure were still not finalized. During that time, the City was in the process of
    checking HDO’s plans and requesting additional information.
    In February 2006, Evans received a copy of the first plan check from the City.
    The document contained 109 comments. It is generally considered preferable to have
    plan checks done before work begins, so that any modifications or changes can be
    addressed ahead of construction. Based on this first plan check, Evans concluded the
    plans would require much more work before the City would issue a permit. Moreover,
    each of the City’s inquiries could potentially result in additions to the scope of the work.
    B. Weather-Related Delays
    In the winter of 2005, the weather was difficult to work in due to excessive rain,
    which made it hard to remove dirt from the site during the excavation stage. DeWeese
    understood that verified rain delays and delays caused by change orders would serve to
    extend the completion date set forth in the Construction Contract. However, Zainer did
    not always approve the rain days Valley requested. At trial, he acknowledged rain
    delayed the Project for many weeks. Valley initially requested 66 rain days. After
    2
    Zainer testified that he did not have time to undertake a detailed review of the
    architectural or structural plans prior to the start of construction. He did review the utility
    and soil plans, as well as the concrete structural plans, because these plans concerned the
    portion of the Project that was going to be built first. He did not take any steps to insure
    HDO’s plans for the above-ground structure were complete and final before the Project
    broke ground.
    3
    When the Construction Contract was signed, Nesbitt knew the architectural plans had
    not been finalized and that WWCA had not secured all the required permits.
    4
    reviewing the Valley’s daily field reports, Zainer determined only 40 rain days were
    justified.
    C. Concrete Podium Construction Delays
    After excavation was completed, the next major subcontractor involved in the
    Project was R&G Contractors (R&G), which was responsible for building the concrete
    podium. Initially, R&G’s work had been priced at $3 million out of the Project’s total
    cost. Valley had not selected R&G as the concrete subcontractor. Instead, WWCA
    directed Valley to use R&G. Valley had never worked with this subcontractor before.
    Beginning in August 2006, Evans was present on the job site, processing change
    orders needed to accommodate revisions being made by the structural concrete engineer.
    Several changes were made to the scope of R&G’s work. For example, columns were
    added to the podium. There were also changes made at the basement level and street
    level. A total of 11 structural concrete plan changes were made, the majority of which
    resulted in requests for information (RFI’s) made to HDO. Design changes had to be
    worked into the concrete pour schedule, and additional rebar had to be obtained.
    John Packwood worked for Valley as a project superintendent. He testified that
    “critical path” dates were missed, starting with the mass excavation stage. Critical path
    dates are important for maintaining a project’s schedule and completion date. R&G’s
    work was delayed as a result of design changes, bad weather, and manpower issues. For
    example, the many plan revisions created confusion. The delays to R&G’s work
    correspondingly caused delays to other subcontractors’ work.
    Ultimately, the concrete portion of the Project was delayed by three to four
    months. In addition to weather, a week or two of delay was caused by design revisions.
    The concrete also took longer to set than anticipated, adding another week or two. The
    employment of a dirt ramp at the excavation site caused at least four weeks of delay. The
    Project was adjacent to the Interstate 680 freeway, requiring Valley to obtain permits
    from Caltrans for traffic control. When trucks were needed to remove soil or access the
    site, permits for lane closures had to be obtained from the City. Sometimes these permits
    5
    would be denied due to weather or for other reasons, which caused delays in receiving
    scheduled drop-offs of materials.
    D. Design Coordination Delays
    Harris acknowledged at trial that as the lead architect it was his role to coordinate
    the Project’s design with the MEPs. As a general contractor, Valley is not licensed to
    design mechanical, electrical, or plumbing systems. Valley was never asked to
    coordinate planning between the MEPs and HDO. During the course of the Project’s
    construction, HDO issued 85 architectural supplemental instructions (ASI’s). HDO and
    the structural engineers were also responsible for submitting all ASI’s and plan revisions
    to the City for approval.4
    Much of the testimony concerning design coordination problems focused on the
    Project’s ventilation system. As late as February 2007, Valley was involved in meetings
    with HDO, the MEPs, and the structural engineer to finalize the ventilation system for
    dryers and restroom exhaust fans. These elements were designed to be ventilated through
    each flooring level and up to the roof deck though a system of chases and shafts. A shaft
    is a fire-rated, through-floor penetration that connects one floor to another and may
    continue through multiple floors. It is lined on the inside and outside with fire-rated
    sheetrock. In addition to providing ventilation, the shaft allows pipes and mechanical
    ductwork to be run from floor to floor. The chase leads to the shaft and may also enclose
    pipes, but it is not lined with sheetrock on the inside.
    The MEP’s design plans utilized the same shaft to run their infrastructure through
    the building. The meeting with Valley was called to address the fact that there was not
    enough room in the wall behind the washer and dryer to house the vents with their rated
    enclosures as well as the plumbing and electrical infrastructure. The mechanical design-
    build subcontractor generated the design for the ventilation system it installed in the
    Project. It then gave the design to HDO to work into the architectural plans. Due to
    4
    At one point in June of 2007, the City shut down the job site because it did not have a
    current set of plans reflecting the changes it had approved.
    6
    HDO’s lack of coordination, the subcontractor had to redesign the ventilation shafts
    about five times, which resulted in delays. The early shaft designs were too small to
    accommodate everything that needed to go into the duct leading to the roof.
    The overall delay in finalizing the shaft’s design was significant. The design was
    the subject of a November 2005 meeting, yet it took another 18 months before HDO
    issued an ASI addressing the dimensions of the chase and the shaft’s fire rating. The
    specifications for constructing the shafts were issued by HDO in June 2007, which was
    some 20 months after Valley started working on the Project.5 Evans testified the City did
    not approved the new shaft design until December 2007. By the time the design was
    approved, the framing subcontractor had already been working on the Project for three or
    four months.6
    Valley’s expert witness, Joel Agnello, is an architect who specializes in forensic
    architectural consulting. He testified that MEPs normally prepare their designs and give
    them to the architect for review. The architect is in charge of the overall design and is
    responsible for coordinating all the designs that are contributed by others. In contrast, the
    actual construction of the project itself is coordinated by the general contractor.
    Agnello confirmed that it is better to have the final set of plans ready before a
    general contractor is retained. It is also preferable to have all permits secured prior to
    construction. In his opinion, it would have been very difficult to meet the schedule set
    forth in the Construction Contract due to the lack of clear direction from the Project’s
    design team. The design plans were poorly coordinated. This lack of coordination
    5
    Additional revisions had to be made because fire regulations had changed since the
    plans were originally drafted in 2005.
    6
    At one point during a walk-through while the framing was being done, Harris noted the
    structural engineer had drawn a joist right over the top of the shaft behind the washer and
    dryer. At trial, Harris acknowledged the working drawings did not reflect the correct
    placement of the shafts, which explains why the framing subcontractor ran joists straight
    through some of those shafts. As the units were being built, he advised Valley to cut the
    truss out. Harris testified that only two or three of the units had been framed at that point
    and the cost to correct the mistake was therefore limited. Valley paid for an additional
    subcontractor to make these fixes, hoping to be reimbursed later.
    7
    affected the construction, as evidenced by an excessive number of RFI’s. The design
    problems included the failure to “cloud” the working drawings to highlight the revisions
    being made, a lack of sufficient architectural details within the plans, and slow responses
    to design-related questions, all of which negatively impacted the construction schedule.
    E. Change Orders
    By 2006, the Project’s plans and design had been modified “across the board.”
    About $2 million was spent on change orders during Valley’s tenure. During the course
    of construction, 150 to 200 change orders were issued, each one involving RFI’s that
    required HDO to revise the working drawings. Evans testified that HDO and the
    structural engineers generally did not identify their revisions by clouding the plan
    changes or by providing an itemized list.7 This made it difficult for subcontractors to
    understand what changes were being made, which delayed getting change orders priced
    out.8
    The change order process was further aggravated by Zainer’s demand for
    excessive backup documentation before approving change orders.9 Zainer also
    sometimes refused to approve full payment for work that had already been done, putting
    Valley in the position of having to ask subcontractors to cut down their billing. Some
    subcontractors eventually refused to do any extra work on good faith, instead requiring
    final approval of change orders no matter how much this delayed the schedule.10 Valley
    7
    Harris admitted he ceased clouding his design revisions once construction started.
    8
    If a subcontractor had a problem following the plans during construction, he or she
    would ask Evans for clarification. If Evans could not answer the question, he would
    submit an RFI to HDO. Delays in responding to RFI’s slowed down the entire process.
    In the case of the proper method for attaching handrails, it took about seven months to
    resolve the issue after multiple RFI’s had been submitted.
    9
    Zainer would ask subcontractors to give a breakdown of labor, materials, and
    equipment, as well as copies of invoices for materials.
    10
    For example, R&G had to provide backup documentation for work it had already done
    to alter structural aspects of the podium, alterations that were driven by the concrete
    structural engineer. R&G subsequently refused to do change order work until it was paid
    for the work it had already done.
    8
    itself did not have the resources to advance the money for the additional work on its own.
    At one point every individual subcontractor had a change order that was denied by
    Zainer.
    Evans would have expected more cooperation and coordination on a job of this
    size. The lack of cooperation from the design professionals impacted Valley’s ability to
    do its job as a general contractor. For example, revisions to the Project’s waterproofing
    continued from July 2007 to May 2008. Changes were made to the plans that had not
    been a part of the original bidding, requiring the original waterproofing subcontractor to
    incorporate two years’ worth of changes into his submittal package to get Zainer’s
    approval. In the case of the HVAC contractor, the contractor’s entire submittal package
    was rejected by Zainer even though much of the package was fine. In general, the
    submittal process was not streamlined, which caused delays.
    F. Construction Consultant Testimony
    Benjamin Tipton worked as a construction consultant for major Bay Area
    construction lenders. He was hired by the banks that were financing the Project. He
    observed how the Project’s schedule was impacted by weather delays and design
    coordination issues. The lack of coordination between the City, design professionals, and
    contractors was an issue from very early on in this project. For example, at one point the
    mechanical design plans had the bathroom ventilation chase dimensions at 15.5 by 15.5
    inches, while HDO had drawn the dimensions at 12 by 12 inches. The structural plans
    also showed a joist running straight through where the ventilation was supposed to be.
    He concurred with the view that the architect is responsible for coordinating all the
    design professionals.
    Tipton would visit the site and attend the monthly meetings when the pay
    applications came in. During these meetings, Valley regularly discussed the impact the
    design plans would have on change orders. He saw five to seven pages of actual or
    potential change orders a month. These changes impacted the Project’s cost and
    9
    scheduling. Tipton always felt that Valley was acting in good faith with respect to its pay
    applications, and Zainer always approved them.11
    III.   The April 2008 Amendment to the Construction Contract
    A. Valley’s General Conditions Budget
    “General conditions” are expenses or costs incurred by a general contractor, such
    as for manpower, trailers, portable toilets, and cleanup. In the Construction Contract,
    Valley had originally budgeted $904,867 for its general conditions. The total actual
    expenditures for general conditions came to $2,206,443. The increase was due, in part, to
    the additional 10 to 11 months Valley worked beyond the 20-month period set forth in
    the Construction Contract. Valley’s costs also went up because it had to hire more people
    to address all the design issues that arose. In the Spring of 2008, Evans was still
    addressing problems caused by the issuance of so many change orders.12
    DeWeese testified that being “upside down” for over $1 million in general
    conditions made it difficult to make payroll and put a tremendous hardship on all aspects
    of his business. DeWeese eventually had several meetings with Ken Hassett, who was
    WCG’s vice-president for construction development. DeWeese wanted to work with
    Hassett because he felt Nesbitt did not have enough experience.
    B. The Amendment
    As a result of the discussions with Hassett, Valley executed a written agreement
    on April 22, 2008 (the Amendment) in which Valley agreed to accept a total of $840,000
    for the excess general conditions, spread over nine scheduled payments. DeWeese
    agreed to this deal even though he would end up losing about half a million dollars. The
    parties also agreed to extend the Project’s completion date to August 31, 2008. The first
    payment was to be made April 30, 2008. However, no payments were ever made.
    11
    Zainer testified that Valley was straightforward with their pay applications. He
    recommended payment of all their payment applications after revisions had been made.
    12
    By May 2008, over 400 RFI’s had been issued, along with various ASI’s, structural
    revisions, and plan revisions.
    10
    C. The Oris List
    Scott Layne owns Oris Group Consulting (Oris). WWCA contacted him about the
    Project in April 2008. He toured the Project, concluding the work was only 50 to 60
    percent completed at that time. His estimate accounted for defective work that he
    believed would take three to four months to correct. Oris later generated an itemized list
    of the existing defects for WWCA (Oris List). While Layne did not talk to any
    representative of Valley or ProPM, or to the architect or any designers, he concluded the
    Project would not be completed by August 2008. Oris eventually billed WWCA between
    $750,000 to $800,000 in consulting fees.
    Layne did not negotiate the Amendment but he was consulted on it. By May 8,
    2008, Layne was treating his task as a forensic litigation-type assignment. The first Oris
    List was provided to WWCA on May 19, 2008. Layne made a second site inspection on
    May 28, 2008. He testified that after a tour he met with DeWeese; however, at his
    deposition he said he did not recall if he met with anyone from Valley. While he claimed
    he provided Valley with a checklist to help it organize the issues that needed to be
    addressed, six days later he was advising Nesbitt on how to terminate Valley.13
    At trial, Layne opined that Valley did not properly manage the Project. “A big
    problem” was that the MEPs “were not coordinating their design/build functions with one
    another,” a deficiency that he attributed to Valley, not HDO. Layne testified that the
    design-build contractors were “subcontracted to the general contractor,” and that Valley
    was responsible for making sure that the design-build scopes of work of each of the
    subtrades was completed. He opined Valley fell below the standard of care because “the
    MEP contractors are responsible for providing solutions—design solutions to—to preset
    a functioning method of completing their scopes.”
    Layne also reviewed all the Project’s change orders and determined $412,187 in
    charges should not have been paid. On cross-examination, he admitted an owner is free
    13
    DeWeese did not consider the deficiencies described on the Oris List to be serious in
    nature. To his knowledge, no one apart from Nesbitt considered anything on the list to
    describe a serious construction deficiency.
    11
    to approve a change order for any reason or no reason at all. The change orders he
    examined were all approved, and had been paid five years before trial. Accounting for
    legitimate delays, Layne concluded the Project should have been substantially completed
    by August 30, 2007. He admitted that, assuming that the parties had mutually agreed
    extend the completion date to August 31, 2008, his hypothetical completion date would
    no longer apply.
    Zainer was critical of the many design revisions that occurred during the Project’s
    construction. In recommending that Nesbitt not sever the relationship with Valley, he
    noted Valley was already trying to fix existing defects. In a June 2008 e-mail message,
    Zainer informed WWCA that the Oris List was flawed and should not be relied on.14 He
    also stated: “We see no relevancy in unearthing resolved issues as a precedence for
    moving past this impasse. We are where we are, and the agreement that Ken Hassett
    forged with [Valley] on your behalf should have closed the book on those past issues and
    any delays that they caused.” Nesbitt disagreed that Valley should be kept on the project,
    and Zainer was eventually phased out.
    Agnello reviewed the 52 items on the Oris List and concluded only six or seven of
    them had any validity. Even these were minor issues. The majority of the items Oris
    classified as either incomplete or incorrect were in the process of being repaired or had
    been redesigned. The list did not provide justification for WWCA to withhold payment.
    He opined Valley was entitled to $1.3 million in additional general conditions.
    D. The Stop Work Notices
    On June 19, 2008, WWCA issued a stop work notice. Evans stopped all new
    work, but continued correcting defective items. The next day Valley received an
    additional notice that all work must stop. Evans closed down work on the site. At this
    point, the Project was 80 percent complete.
    14
    Harris was not consulted about hiring Oris and was not asked to respond to the Oris
    List.
    12
    DeWeese testified that he never abandoned the Project, while Nesbitt took the
    position that Valley had done so. DeWeese explained that he pulled everyone off the job
    on June 23, 2008, in response to the stop work notices. He decided not to engage in
    further negotiations with WWCA because he had just engaged in a series of such
    meetings. He believed further meetings would be pointless. The stop work notices were
    never retracted, but if WWCA had rescinded them, DeWeese would have returned to the
    Project.
    E. Valley’s Mechanics Lien
    On August 27, 2008, Valley recorded a lien on the property in the amount of
    $1,198,980.45. The amount owed for general conditions was used as the basis for
    Valley’s lien.15
    F. WWCA’s Side of the Contract Dispute
    Nesbitt testified that WWCA changed general contractors in 2008 because Valley
    “was way behind schedule, and we were way over budget at that point.” He also said,
    “Valley ultimately ended up abandoning the job, so we really had no other choice.” He
    first considered terminating Valley in March 2008, when DeWeese reported Valley had
    exhausted its general condition budget. He acknowledged WWCA did not make any
    payments under the Amendment. He said he did not pay because DeWeese had agreed to
    document Valley’s progress before receiving payment.
    The first installment payment of $72,000 was due on April 30, 2008. When asked
    how much progress he expected Valley to have made between the April 22, 2008 signing
    and April 30, Nesbitt said: “To us, the hurdle there was we needed verification that
    completion of August 31 was possible.” In his view, on April 30 he would receive a bill
    and then he would have time to verify whether the work had been done. The
    Construction Contract allowed WWCA 20 days for payment, and Nesbitt thought he
    15
    Julie Young, a project manager for Valley, determined how much money Valley was
    owed in general conditions for the Project using a construction industry accounting
    system called Timberline.
    13
    could follow that same procedure even though the Amendment does not contain a similar
    provision.
    On cross-examination, Nesbitt acknowledged it was Hassett’s job to determine
    The Project’s percentage of completion. In his deposition, Nesbitt testified that Hassett
    made a determination that Valley had not met the percentage of completion targets for
    May or June 2008. However, Hassett testified at his deposition that he never made any
    such determination. Layne advised Nesbitt to stop paying Valley, yet Nesbitt signed the
    Amendment six days after receiving that advice. By May 8, 2008, WWCA was already
    contemplating litigation against Valley.
    While Nesbitt was on a “litigation path,” he also envisioned a “completion path”
    for Valley, notwithstanding his failure to abide by the terms of the Amendment. Rather
    than paying Valley the first $72,000 installment payment, he planned to use the money to
    pay salaries and consulting fees, including Oris’s consulting fees. Valley was to get
    whatever was left over. He wanted to present this plan to DeWeese at a meeting after the
    stop work notice was issued. At trial, he admitted his proposal was inconsistent with the
    Amendment. He also maintained Valley had “abandoned” the project, while admitting he
    never recalled the stop work notice.
    On June 23, 2008, DeWeese told Nesbitt that Valley was in dire financial straits
    and expressed his view that Nesbitt was not honoring the Amendment. He offered to
    return to the Project if Nesbit paid the amounts that were past due. Nesbitt denied he
    intended to terminate Valley’s contract by issuing the stop work notices. He invited
    DeWeese to a meeting on June 30, 2008, but DeWeese did not show up.
    G. Post-Termination Construction
    Robert Putnam is a general contractor with Michael Roberts Constrution, Inc.
    (MRC). He contacted Nesbitt in June 2008 after he became aware that work on the
    project had apparently ceased. After MRC got the job, Putnam recommended that
    14
    WWCA hire the same subcontractors who had worked under Valley.16 MRC was shown
    the Oris List after it started the Project. Putnam considered the Oris List in projecting the
    scope of MRC’s work, including setting aside allowances for correcting the listed items.
    Not everything on the list actually required repair. Eventually, MRC filed a mechanic’s
    lien on the Project to protect its rights and the rights of subcontractors that had worked
    under MRC. Putnam had to notify 11 subcontractors that WWCA was withholding their
    retentions. He did not agree with that decision. Eventually MRC’s lien was released.
    H. Tarigo
    Dylan Skerrett works for the Tarigo family. In 2011 he was seeking to purchase a
    commercial property on behalf of the Tarigo family. He made an offer to purchase the
    completed Project. At no time before he made the offer did anyone tell him there were
    any construction defects. The final purchase price was $46,950,000.
    Skerrett was never given the Oris List. Nor was he told WWCA had any reports
    detailing construction defects. The property information sheet included language in
    which WWCA declared it had no actual knowledge of any material physical defects in
    the property. Skerrett did not believe he had an affirmative duty to ask for any defect
    lists, because the purchase contract did ask WWCA to provide all copies of reports
    pertaining to the property. WWCA offered to purchase the property back after he
    became aware of the undisclosed documents. Tarigo declined the offer.
    IV.    Litigation Commences
    On November 25, 2008, Valley filed a complaint against WWCA and WCG for
    breach of contract and to foreclose on the mechanic’s lien. The complaint alleged
    defendants had breached both the Construction Contract and the Amendment. Valley
    requested judgment on the Construction Contract in the amount of $1,198,980.45, plus
    lost profits and other damages as well as interest, costs, and attorney fees. As to the
    16
    Tipton continued attending the monthly meeting and observed that change orders were
    occurring with the same frequency as when Valley had been the general contractor.
    When the job was completed, Tipton concluded the Project’s construction was “very
    excellent.”
    15
    breach of the Amendment, the complaint sought $840,000 in damages, plus additional
    lost profits and other damages, together with interest and costs.
    On March 5, 2009, WWCA filed a cross-complaint against Valley alleging causes
    of action for breach of contract, negligence, negligent misrepresentation, conversion, and
    for an accounting.17 WWCA alleged Valley’s performance was deficient, forcing
    WWCA to issue a stop work notice, after which Valley allegedly abandoned the job.
    WWCA alleged it then terminated Valley for cause in August 2008.
    V.     Jury’s Verdict
    On September 3, 2013, the jury unanimously found in favor of Valley on its claim
    for breach of the Amendment. By an 11 to one vote, it found Valley’s damages to be in
    the amount of $840,000. By a nine to three vote the jury also found in favor of Valley on
    its quantum meruit claim in the amount of $1,058,916.12. The jury found against
    WWCA on its claim for breach of contract by a vote of 11 to one.
    On December 16, 2013, WWCA filed a motion for new trial. The trial court
    denied the motion, and judgment was entered on November 21, 2013.
    DISCUSSION
    I.     Juror Misconduct
    WWCA claims several of the jurors committed prejudicial misconduct. We set
    forth the facts surrounding the misconduct and the trial court’s responsive measures.
    On August 2, 2013, WWCA’s attorneys informed the trial court that juror No. 12
    had sent Nesbitt a Facebook friend invitation. The judge noted she had observed the
    juror smiling at Nesbitt while he was testifying. The judge interviewed juror No. 12 and
    excused her. An alternate juror was sworn in. The judge then learned juror No. 12 had
    17
    On August 26, 2013, WWCA agreed to dismiss the fraud-based claims in the
    operative cross-complaint. On August 27, 2013, the trial court granted Valley’s motion
    for nonsuit on the negligence claim.
    16
    made inappropriate comments to other female jurors during a restroom break.18 The
    judge decided to interview each of the female jurors in chambers regarding this incident.
    A. First Round of Interviews
    Juror No. 2 revealed that during a recess, juror No. 12 told juror No. 5 that she did
    not know why the trial was continuing because the matter should have settled. Jurors
    Nos. 2 and 5 explained to her that both sides were entitled to present their positions.
    Juror No. 2 did not recall if juror No. 12 indicated which side she was leaning towards.
    She also reported jurors Nos. 12 and 5 had engaged in a discussion about how the
    evidence of damages might be presented, and had speculated that a mechanic’s lien had
    delayed escrow when Tarigo bought the property.
    Juror No. 4 also heard juror No. 12 say she had made up her mind early on and
    knew what she was going to do, and revealed that other jurors had also been making
    comments about the trial. This included “[j]ust about everybody.” One juror had stated
    that “[Valley] deserved their money,” but juror No. 4 could not remember who it was.
    She also said she had gone to dinner with another juror who talked about the case “a
    lot.”19 She heard some conversation “almost every day,” but conceded she was “coming
    from a place where we should say nothing.”
    18
    The judge reportedly learned from court staff of juror No. 12’s remarks in the women’s
    restroom.
    19
    We have read the reporter’s transcript carefully and we disagree with WWCA’s
    characterization of this “Dinner Revelation” as including that the two jurors “specifically
    discussed ultimate conclusions.” The passage it cites to in the record does not even
    pertain to the dinner, but rather to conversations that occurred when the jurors were
    “outside the court [¶] . . . [¶] [s]ometimes right as [they were] leaving.” Additionally, the
    discussions did not include ultimate conclusions: “THE COURT: So is it basically just
    commenting? Did they say, well, that person is obviously lying or they’re a terrible
    witness? [¶] JUROR NO. 4: No. But—no. I can’t say—that’s a more swaying type of
    thing. It will be a personal comment about the person, you know. It would be a personal
    comment.” WWCA relies on this same passage in asserting that juror No. 4 stated that
    jurors were discussing witness credibility. In fact, the passage shows she denied jurors
    were having such discussions.
    17
    Juror No. 5 reported the jurors had joked about some aspects of the trial, and had
    commented on its length. Juror No. 12 complained numerous times about how long the
    trial was taking and how it was disrupting her life.20 Juror No. 5 had also heard
    comments about “theatrics” during the trial, and complaints that the proceeding was
    “dragging.” But she had not heard anyone say they had already made up their mind.
    Juror No. 6 had not heard jurors say they had already made up their minds.
    However, jurors did discuss the personalities and mannerisms of the lawyers.
    Juror No. 11 recalled juror No. 12 stating early on that the case was going on too
    long and that she had already made up her mind. Juror No. 11 walked away and did not
    think any other juror had heard the comment. During the trial, juror No. 12 would make
    comments like “[w]hat the fuck do we need to know this for?” She would also send text
    messages and check her Facebook account during trial.
    Juror No. 8 did not remember juror No. 12 making comments in the restroom. She
    did recall juror No. 12 saying something about how one of the subcontractor witnesses
    had said, “I don’t recall” too much. When juror No. 8 heard comments by other jurors,
    she would try to shut down the conversations.
    An alternate juror had heard comments expressing frustration with the lawyers.
    This juror may have heard juror No. 12 state that she had made up her mind, though she
    did not indicate which side she favored.21 After interviewing the female jurors, the trial
    court concluded the jury had not been tainted by anything juror No. 12 had said.
    20
    Once again, we disagree with WWCA’s claim that juror No. 5 said juror No. 12
    repeated “on ‘numerous’ occasions that the trial should be over and/or she had already
    made up her mind.” The transcript reveals the opposite: “THE COURT: For instance,
    did you overhear [Juror No. 12] say anything about she’d made up her mind or anybody
    else say that? Why don’t we just stop here, I’ve made up my mind? [¶] JUROR NO. 5:
    “I don’t think I’ve heard that. . . . [¶] I just know she wanted it to be over. . . . [¶] But I
    didn’t hear her distinctly say, I made up my mind.”
    21
    WWCA’s claim that juror No. 12 must have been siding with Valley “because only
    Valley’s witnesses had testified early on in the trial” is pure speculation.
    18
    B. WWCA’s Motion for Mistrial and Second Round of Interviews
    On August 5, 2013, Windsor filed a motion for mistrial. Valley opposed, arguing
    that a properly given admonishment would cure any existing prejudice. The trial court
    elected to conduct a second round of interviews with the jurors, including the male jurors.
    Juror No. 4 identified her dinner companion as juror No. 1, and she described his
    comments about the case. He had said that his notes were not good “ ‘but I think I’m
    getting this.’ ” He appeared to have “feelings” about the case, but she could not recall
    any specifics. She also divulged that juror No. 5 turned to her in the jury box at some
    point during the presentation of Valley’s case and said something to the effect that Valley
    and the other contractors “need to be paid.” Juror No. 4 thought a number of jurors spoke
    to each other, but she did not know what they had said. However, she did not think jurors
    were deliberating. Juror No. 12 had been the most outspoken juror. Juror No. 4 had tried
    to avoid her, and did not think any other jurors had been swayed by her comments.
    The court reinterviewed juror No. 5 regarding the statement that the contractors
    “need to be paid.” She denied making the statement. She admitted her opinion had gone
    back and forth during trial, but said she had not yet made up her mind. She did mention
    that she had driven by the Windsor Apartments and told her husband (who is a
    contractor) that her case concerned the building, but did not discuss the case with him.
    Juror No. 1 acknowledged he had dinner with a juror but said they did not talk
    about the trial.22 He believed all the jurors were open-minded, and that no one had
    decided the case. Juror No. 5 complained a lot about the hardship of being on the jury
    but had not discussed the trial itself.
    Two other jurors had not heard anyone directly or indirectly say which side should
    win or that Valley and the subcontractors should get paid. Another juror said the jurors
    commented on personality quirks observed during the trial, but not matters that would
    affect their decision. A male juror had “heard certain things where I think some people
    22
    While WWCA argues juror No. 1 “was clearly being untruthful with the court” in
    denying he had told juror No. 4 that Valley should get paid, Juror No. 4 never reported
    that he specifically told her Valley should recover.
    19
    found some witnesses more credible than others,” though this point had not been
    discussed “elaborately.” He did recall juror No. 1 said he did not feel Packwood was as
    credible as some of the other witnesses.
    C. Denial of Motion for Mistrial
    Following these additional interviews, the trial court denied WWCA’s motion for
    mistrial. The court concluded there had not been “repeated and pervasive misconduct.”
    While “there was probably discussion that shouldn’t have taken place, . . . as far as
    discussing the case or forming opinions, I think that we have dismissed the juror who was
    problematic here,” referring to juror No. 12. WWCA’s counsel then advocated for
    excusing juror No. 5. The court disagreed, noting juror No. 5 said her opinion vacillated
    both ways depending on the testimony she was hearing at the time. After denying
    WWCA’s motion, the court strongly admonished the jury to avoid any more discussions
    about the case until deliberations.
    D. Although Juror Misconduct Occurred, the Misconduct Was Not Prejudicial
    Jury misconduct is a ground for a new trial. (Code Civ. Proc., § 657, subd. (2).)
    Discussing the case with other jurors, or forming and expressing an opinion prior to
    deliberations is generally considered to be misconduct. (City of Pleasant Hill v. First
    Baptist Church (1969) 
    1 Cal. App. 3d 384
    , 429.) “Once misconduct occurs, it raises a
    presumption of prejudice that can be rebutted by an affirmative evidentiary showing that
    prejudice does not exist, or by a reviewing court’s examination of the entire record to
    determine whether there is a reasonable probability of actual harm to the complaining
    party resulting from the misconduct. [Citation.] In reviewing the trial court’s ruling on a
    new trial motion, we accept the trial court’s credibility determinations if they are
    supported by substantial evidence, including all favorable inferences that may be drawn
    from the evidence. Whether prejudice arose is a mixed question of law and fact subject
    to our independent review.” (Karlsson v. Ford Motor Co. (2006) 
    140 Cal. App. 4th 1202
    ,
    1232.)
    20
    We conclude the trial court did not err in denying WWCA’s motions for mistrial
    and new trial.23 Preliminarily, there is no question that juror No. 12 engaged in
    misconduct before she was dismissed by the trial court. It also appears she improperly
    revealed early in the trial that she was biased towards one side, although she did not
    explicitly disclose which side she favored. Several other jurors were exposed to her
    remarks. However, as soon as her misconduct came to light, she was immediately
    removed from the jury and replaced by an alternate juror. The remaining jurors were
    interviewed extensively. Based on these interviews, the trial court concluded they had
    not been influenced by the excluded juror. To the extent other jurors had discussed the
    case, these discussions were limited to matters not pertaining to the merits, such as the
    attorneys’ mannerisms. Importantly, deliberations did not occur until approximately one
    month after juror No. 12’s removal, minimizing any influence her expressed views might
    have had on any of the remaining jurors. Additionally, the record contains no evidence
    of any subsequent juror misconduct.
    The record does suggest a few jurors may have commented on some witnesses’
    credibility before juror No. 12 was removed. While the evidence on this point was
    conflicting, particularly as to whether juror No. 1 and juror No. 5 had expressed
    favoritism towards Valley, nothing in the record supports WWCA’s broad contention that
    the jury “wantonly abandoned its sworn duty to remain unbiased and unprejudiced.”
    The misconduct also was not prejudicial. (Cal. Const., art. VI, § 13; Hasson v.
    Ford Motor Co. (1982) 
    32 Cal. 3d 388
    , 417.) The testimony as to the breach of the
    Amendment was not sharply in conflict. It was uncontested that the contract was valid
    and that WWCA did not make any of the required installment payments. The primary
    defenses for not adhering to the terms of the contract were that the original Construction
    Contract allowed WWCA to use delays as justification for withholding payment and that
    Valley had abandoned the job. WWCA also attempted to show that defective
    23
    WWCA appears to have analytically lumped together the trial court’s rulings denying
    its mistrial motion and denying its subsequent new trial motion. Because both rulings
    raise virtually the same issues, we will discuss them in combination.
    21
    construction was responsible for causing delays. While the Project was not completed on
    time, the jury could reasonably have attributed most of the delays to the design
    professionals’ failure to coordinate their plans, and to other factors that were outside of
    Valley’s control. The evidence also suggested WWCA intended to fire Valley even as it
    negotiated the terms of the Amendment.24
    Importantly, the alleged instances of misconduct occurred more than a month prior
    to deliberations. The offending juror responsible for the vast majority of the improper
    conduct was removed without delay, and the jury was strongly admonished to refrain
    from any discussion of matters involving the case. Shortly after that juror was removed,
    all the remaining jurors informed the court that they had not been influenced by her
    comments. They also attested that they had not prejudged the case and affirmed they
    could remain open-minded until all the evidence was presented. There is no evidence to
    contradict the trial court’s assessment that the jurors properly conducted their
    deliberations. Our review of the record confirms the trial court’s view that removal of
    juror No. 12 was enough corrective action to ensure a fair trial.
    Contrary to WWCA’s claim, Rufo v. Simpson (2001) 
    86 Cal. App. 4th 573
    (Rufo)
    does not suggest a different result. In Rufo, the appellate court found the trial court had
    not abused its discretion in denying a mistrial after removing a juror who had failed to
    disclose that her daughter had worked for one of the prosecutors in the defendant’s prior
    criminal trial. (Id. at p. 613.) The juror was removed after two and one-half days of
    deliberation. (Id. at p. 612.) The appellate court concluded the defendant had failed to
    demonstrate why the removal of the offending juror was not sufficient to remedy the
    harm in that particular case: “When juror misconduct is discovered before a verdict is
    reached, the trial court has a choice among several remedies, one of which is to discharge
    the offending juror and replace the juror with an alternate. [Citations.] Ordinarily the
    less drastic remedy is preferable to requiring a whole new trial; the remedy of mistrial is
    24
    We also note the vote of the jury was not close, as it was unanimous in favor of Valley
    on its claim for breach of the Amendment. It also found against WWCA on its claim for
    breach of contract against Valley by a vote of 11 to one.
    22
    for those rare cases where the trial court in its discretion concludes the misconduct of the
    juror has already caused such irreparable harm that only a new trial can secure for the
    complaining party a fair trial.” (Rufo, at p. 613.)
    Significantly, the Rufo court noted “the offending juror was not included among
    the 12 jurors who rendered the verdict after being instructed to begin deliberations anew.
    In the absence of any evidence that the offending juror’s previous temporary participation
    in deliberations tainted the other jurors, this record wholly rebuts the presumption of
    prejudice . . . .” 
    (Rufo, supra
    , 86 Cal.App.4th at p. 613.) Here, the potential taint is even
    more attenuated as the offending juror was removed some five weeks before
    deliberations.
    Stressing it was deprived of a fair trial because at least one juror (juror No. 5) had
    formulated and communicated “an opinion about the ultimate question in the case before
    the close of evidence,” when she allegedly said the contractors “need to get paid,”
    WWCA relies on Andrews v. County of Orange (1982) 
    130 Cal. App. 3d 944
    , 957–958
    (Andrews). It also relies on Deward v. Clough (1966) 
    245 Cal. App. 2d 439
    (Deward).
    Those cases are distinguishable.
    In Andrews, the appellate court reversed the denial of a motion for new trial and
    found the plaintiffs in an eminent domain proceeding had been deprived of a fair trial by
    reason of jury misconduct. 
    (Andrews, supra
    , 130 Cal.App.3d at p. 968.) While multiple
    acts of juror misconduct occurred, the reviewing court observed that certain incidences of
    misconduct, while not trivial, “may not have been of sufficient gravity to have deprived
    plaintiffs of a fair trial . . . .” (Id. at p. 957.) These lesser incidents included a juror who
    remarked, “S.O.S.—same old shit,” during one of the field trips to inspect the plaintiffs’
    homes. This same juror commented that one of the houses was not worth $90,000
    because “his house which was better was not worth that much.” (Id. at p. 957, fn. 10.)
    Another juror admitted she talked to her husband about the trial, but said she neither
    sought nor received his view of the case. During deliberations, she also commented that
    a realtor told her it was not unusual for a house to be on the market for several months.
    (Ibid.)
    23
    It was only when combined with multiple “serious acts of misconduct” committed
    by another juror that these lesser acts became prejudicial. 
    (Andrews, supra
    ,
    130 Cal.App.3d at p. 957.) These serious acts included: (1) commenting during a field
    trip that the plaintiffs’ case was “a big farce,” after another juror reportedly commented
    that the plaintiffs already had enough money; (2) during deliberations, reporting that a
    real estate broker had told him that the $20,000 markdown on a plaintiff’s house was not
    unusual; (3) talking for more than a half hour about “starter generator noise,” even
    though no evidence had been presented on starter generator noise; and (4) repeatedly
    separating himself from the other jurors. (Andrews, at pp. 957–959.) The appellate court
    also deemed the juror’s prejudgment of the case resulted in prejudice, emphasizing that
    several nine-to-three votes awarded zero damages, with this juror having voted in the
    majority. (Id. at p. 959.)
    The misconduct in the present case is more akin to the lesser acts of misconduct
    discussed in the Andrews case. 
    (Andrews, supra
    , 
    130 Cal. App. 3d 944
    .) Assuming juror
    No. 5 did at one point say that the contractors “need to be paid,” this misconduct does not
    rise to the same level as the juror in Andrews who said the plaintiffs’ case was “a big
    farce.” Andrews is also distinguishable in that there is no evidence here of any
    misconduct occurring during deliberations. Unlike the situation in Andrews, here the
    most problematic juror was removed well before deliberations occurred.25 Further, most
    of the jury’s votes in this case were not close. The only nine-to-three vote involved the
    award of quantum meruit recovery, which is not at issue in this case as Valley elected to
    pursue the remedy of contract damages. Other than the fact that it was not the prevailing
    party, WWCA does not put forth any specific argument that the jurors’ voting patterns
    support its argument of prejudice.
    In Deward, the Court of Appeal found the denial of a new trial motion was error
    where juror misconduct was clearly proved and resulted in an unfair trial. (Deward,
    25
    While WWCA contends that the failure of the jurors to report misconduct on the part
    of the other jurors is an independent ground for reversing the judgment, it cites to no
    cases so 
    holding. 24 supra
    , 245 Cal.App.2d at pp. 441–442.) On the last day of trial before arguments had
    been completed and the jury instructed, as the jurors came out of the courtroom and
    headed for the jury room but found it locked, one juror said to several others: “ ‘ “I don’t
    see why they don’t open up the jury room now. We could bring in a verdict already.” ’ ”
    The jurors who were present all laughed. (Id. at p. 445.) The reviewing court held that
    the statement showed that the juror had prejudged the case; that this “was misconduct and
    it was serious.” (Id. at p. 444.) The court concluded that the misconduct resulted in an
    unfair trial and that the failure of the trial court to grant a new trial was prejudicial error.
    (Id. at p. 442.)
    WWCA argues that juror No. 5’s alleged statement that the contractors “need to be
    paid” was “a clear case of a juror violating his oath by pre-judging the case and
    expressing that opinion to other jurors.” However, unlike the case in 
    Deward, supra
    ,
    
    245 Cal. App. 2d 439
    , the evidence was conflicting as to whether the statement was made
    at all. Additionally, the offending statement was made more than a month before
    deliberation, whereas the statement in Deward was made on the last day of trial. Finally,
    we note that all the jurors were questioned by the judge and WWCA offers no persuasive
    evidence that they lied to the judge about what had occurred, or about whether any of the
    communications had influenced them.26 In sum, while misconduct did occur, the record
    falls short of showing that any of the jurors decided the case based on anything other than
    the evidence presented. Accordingly, we do not ascertain resulting prejudice.
    We also disagree with WWCA’s claim that the trial court made inappropriate
    comments reflecting a bias in favor of Valley. However, we need not address this issue
    further as it does not appear this claim was properly raised below. On that basis, WWCA
    has forfeited the issue on appeal. (See People v. Samuels (2005) 
    36 Cal. 4th 96
    , 114
    26
    While it is true that the jurors did not take the initiative to inform the court of any
    communications as required by Code of Civil Procedure section 1209, subdivisions (a)(6)
    and (a)(11), defendant does not cite to a case holding that mistrial is the appropriate
    sanction for such a failure.
    25
    [“Failure to raise the issue of judicial conduct at trial waives claims of statutory or
    constitutional error.”].)
    II.       The Verdict Award Is Not Excessive
    WWCA claims the verdict of $840,000 to Valley is “impermissibly excessive
    because it provides for a windfall to Valley.” We are not persuaded.
    “The amount of damages is a fact question, committed first to the discretion of the
    jury and next to the discretion of the trial judge on a motion for new trial. [Citations.]
    All presumptions favor the trial court’s ruling, which is entitled to great deference
    because the trial judge, having been present at trial, necessarily is more familiar with the
    evidence and is bound by the more demanding test of weighing conflicting evidence
    rather than our standard of review under the substantial evidence rule. [Citations.] [¶]
    We must uphold an award of damages whenever possible [citation] and ‘can interfere on
    the ground that the judgment is excessive only on the ground that the verdict is so large
    that, at first blush, it shocks the conscience and suggests passion, prejudice or corruption
    on the part of the jury.’ [Citations.] [¶] In assessing a claim that the jury’s award of
    damages is excessive, we do not reassess the credibility of witnesses or reweigh the
    evidence. To the contrary, we consider the evidence in the light most favorable to the
    judgment, accepting every reasonable inference and resolving all conflicts in its favor.”
    (Westphal v. Wal-Mart Stores, Inc. (1998) 
    68 Cal. App. 4th 1071
    , 1078.)
    WWCA correctly observes the award represents the amount the jury believed
    Valley would have earned had it been permitted to continue working under the
    Amendment. It then asserts the award is contrary to law because the amounts outlined
    under the contract were for general conditions, not profit. It bases this assertion on
    evidence that general conditions are used to pay employee salaries, equipment rental, and
    other fixed amounts. It thus concludes Valley was not entitled to any damages for
    general conditions expenses that were to have been paid after the stop work notices
    issued.
    On a motion for new trial claiming excessive damages or insufficient evidence
    (Code Civ. Proc., § 657, subds. 5 & 6), the trial court sits as an independent trier of fact.
    26
    (Lane v. Hughes Aircraft Co. (2000) 
    22 Cal. 4th 405
    , 412.) If the motion is granted, we
    apply a “highly deferential standard” (id. at p. 409), upholding all factual determinations
    with “the same deference that an appellate court would ordinarily accord a jury’s factual
    determinations” (id. at p. 412); pertinent evidentiary conflicts place the new trial order
    “beyond review” (id. at p. 416). A denial of the motion, on the other hand, requires
    deference to the jury verdict, as in any claim of insufficient evidence. We affirm if any
    substantial evidence, contradicted or uncontradicted, supports the judgment. (Western
    States Petroleum Assn. v. Superior Court (1995) 
    9 Cal. 4th 559
    , 571; see Bertero, supra,
    (1974) 13 Cal.3d at p. 64 [damages are excessive “ ‘. . . where the recovery is so grossly
    disproportionate as to raise a presumption that it is the result of passion or prejudice’ ”];
    Hilliard v. A. H. Robins Co. (1983) 
    148 Cal. App. 3d 374
    , 414 [trial court’s determination
    on motion for a new trial on the issue of excessive damages is usually upheld].)
    Damages for breach of contract are measured as the amount that will compensate
    the plaintiff for the detriment caused by the breach. (Civ. Code, § 3300.) WWCA’s brief
    does not cite to any cases holding that a contractor may never recover as a measure of
    damages the full amount of general conditions owed under a construction contract.
    Additionally, DeWeese testified he initially asked for $1.3 million to make him whole for
    general conditions Valley had already incurred.27 He also testified that even with the
    Amendment, Valley still stood to lose at least $500,000.28 As Valley notes, the effect of
    the Amendment was to make Valley whole for special damages that WWCA prevented
    Valley from recovering due to its issuance of the stop work notice.29
    27
    The mechanic’s lien Valley filed was for approximately $1.1 million, but Valley’s
    project manager Julie Young determined Valley was actually owed $1.3 million.
    28
    The $840,000 sum consisted of payment towards current general conditions of
    $360,000 and prior general conditions of $480,000.
    29
    Special damages for breach of contract are limited to losses that were either actually
    foreseen (see, e.g., Dallman Co. v. Southern Heater Co. (1968) 
    262 Cal. App. 2d 582
    , 586
    [in contract negotiations, supplier was put on notice that its failure to perform would
    result in lost profits]) or were “reasonably foreseeable” when the contract was formed.
    (Applied Equipment Corp. v. Litton Saudi Arabia Ltd. (1994) 
    7 Cal. 4th 503
    , 515.) Here,
    27
    It is undisputed that WWCA had made no payments under the Amendment. Thus,
    accepting “every reasonable inference and resolving all conflicts” in Valley’s favor, the
    jury’s award of $840,000 to Valley is not excessive.
    III.   Evidentiary Rulings
    WWCA claims the trial court erred by improperly excluding certain evidence, and
    by limiting the testimony of various key witnesses. It also claims the court allowed the
    admission of highly prejudicial evidence having little or no probative value. We address
    these allegations in turn, and conclude they lack merit.
    A. Packwood’s Testimony
    WWCA asserts the court prevented it from introducing statements by Packwood
    that purportedly would have shown Valley “repeatedly breached its contract” and
    “performed its work in bad faith in several instances.” The two statements were: (1) that
    DeWeese told him to stop preparing daily field reports for WWCA, and (2) that Correa
    instructed Packwood to install joists in the shafts even after HDO instructed Valley not
    to, so that Valley could charge WWCA to remove them.
    In its argument, WWCA does not cite to any point in the trial transcript in which
    Packwood was prevented from testifying that he was instructed by DeWeese to stop
    preparing daily field reports. However, in the brief’s statement of facts WWCA states:
    “On or about July 17, 2013, the trial court prevented [WWCA] from obtaining certain
    testimony from [Packwood] relating to conversations he had with [DeWeese and Correa],
    regarding Windsor’s claims of Valley’s bad faith conduct and its defective construction.”
    WWCA cites to testimony during Packwood’s cross-examination in which he
    twice was asked questions that called for hearsay. He first testified he had sent the
    reports to WWCA only when asked, and that Correa (not DeWeese) had told him not to
    send them on a daily basis. WWCA’s counsel then asked: “And did he tell you why he
    didn’t want ownership to get the daily field reports?” Valley’s counsel made a hearsay
    WWCA was aware of Valley’s position that it had already expended funds for general
    conditions and the Amendment was intended, in part, to allow Valley the opportunity to
    recover a significant portion of these expenditures.
    28
    objection, which was sustained. At this point, WWCA’s counsel did not argue for any
    exception to the hearsay rule. The second citation in WWCA’s brief is irrelevant.
    Confusingly, there is neither an objection nor a ruling at the cited page.30
    WWCA later raised the issue with the trial court outside the presence of the jury,
    arguing that the party admission exception applied. Evidence Code section 1222 states:
    “Evidence of a statement offered against a party is not made inadmissible by the hearsay
    rule if: [¶] (a) The statement was made by a person authorized by the party to make a
    statement or statements for him concerning the subject matter of the statement; and [¶]
    (b) The evidence is offered either after admission of evidence sufficient to sustain a
    finding of such authority or, in the court’s discretion as to the order of proof, subject to
    the admission of such evidence.” The court ruled the question called for hearsay, was not
    relevant, was not an admission, and called for speculation. The court offered that
    WWCA’s counsel could ask Correa what he had said to Packwood if Correa came to
    testify. Correa did not testify at trial.
    “[A]n appellate court applies the abuse of discretion standard of review to any
    ruling by a trial court on the admissibility of evidence, including one that turns on the
    hearsay nature of the evidence in question. [Citations].” (People v. Waidla (2000)
    
    22 Cal. 4th 690
    , 725.) We agree that the evidence WWCA sought is not relevant.
    WWCA overstates the impact of the excluded testimony, arguing “[h]ad this evidence
    been admitted, the jury would have seen that Valley repeatedly breached its contract with
    [WWCA] and performed its work in bad faith in several instance.” This argument is
    difficult to follow, as WWCA does not cite to any contractual provision requiring Valley
    to send daily field reports.
    Even if the trial court abused its discretion by excluding the testimony, we
    conclude the error was not prejudicial. “The burden is on the appellant in every case to
    30
    WWCA also cites to Packwood’s posttrial declaration attached to its motion for new
    trial. In the declaration, he states that “Correa told me, ‘[t]hey [Windsor] don’t need to
    know what’s going on up here, and I don’t pay you to prepare and send these DFR’s to
    them . . . . If they want to know what’s happening, they’re going to have to pay for it.”
    29
    show that the claimed error is prejudicial; i.e., that it has resulted in a miscarriage of
    justice.” (Cucinella v. Weston Biscuit Co. (1954) 
    42 Cal. 2d 71
    , 82; see Cal. Const.,
    art. VI, § 13; Evid. Code, § 354.) In its reply brief, WWCA claims the excluded
    testimony “would have showed the jury that Valley was not keeping records of its
    progress and was not being truthful with Windsor regarding the work that was being
    done, the percentage of work completed, and the status of the corrections being made.”
    This is also an overstatement. The evidence WWCA sought to introduce did not prove
    Valley misrepresented the progress of its work, only that it was disinclined to prepare
    WWCA with daily reports. Accordingly, we conclude the error, if any, was harmless.
    As to the placement of joists in the shafts, WWCA does not cite to the transcript
    where this evidence was supposedly excluded, relying instead on Packwood’s posttrial
    declaration. In its reply brief it also cites to testimony that it claims shows Packwood
    “was prevented from testifying about Valley’s instructions to ignore what the architect
    said and continue framing units that had problems with joists running through the dryer
    vent shafts.” (Italics added.) He actually testified that he was instructed by Correa to
    continue framing because a fix would occur at a later date if one ever did occur.
    WWCA’s counsel did not ask any more questions about the conversation. Consequently,
    WWCA’s claim that the trial court prevented it from introducing testimony that “Valley
    wanted to charge [WWCA] to remove [the joists]” is unsupported by the record.
    B. Exclusion of the Opinions of WWCA’s Architect
    The trial court ruled that Harris could not offer opinion testimony because he had
    not been properly disclosed as an expert witness. On cross-examination, Harris
    acknowledged he had never been designated as an expert witness. He also affirmed he
    was unable to attribute any of the Project’s delays to defective construction. WWCA
    claims Harris was improperly prohibited from testifying as to his observations and
    opinions of Valley’s work with respect to such matters as his “serious concerns” about
    the framing and “problematic” conditions involving the concrete. The trial court
    sustained Valley’s objections to such testimony on the grounds that it constituted
    impermissible expert opinion.
    30
    WWCA first asserts that Harris was giving testimony as a fact witness, not an
    expert, because he was testifying about his own observations, conclusions, and actions
    regarding Valley’s work. It is established that “ ‘[t]he need for pretrial discovery is
    greater with respect to expert witnesses than it is for ordinary fact witnesses
    [because] . . . . [¶] . . . the other parties must prepare to cope with witnesses possessed of
    specialized knowledge in some scientific or technical field. They must gear up to cross-
    examine them effectively, and they must marshal the evidence to rebut their opinions.’ ”
    (Bonds v. Roy (1999) 
    20 Cal. 4th 140
    , 147.) We conclude the trial court properly
    prohibited Harris from testifying as to his opinions on the quality of Valley’s work,
    notwithstanding the fact that he was also a percipient witness. (See Province v. Center
    for Women’s Health & Family Birth (1993) 
    20 Cal. App. 4th 1673
    , 1681–1684 [percipient
    witness not listed as an expert improperly permitted to testify as to expert medical
    opinion], disapproved on other grounds in Heller v. Norcal Mutual Ins. Co. (1994)
    
    8 Cal. 4th 30
    , 41.)
    WWCA relies on Schreiber v. Estate of Kiser (1999) 
    22 Cal. 4th 31
    (Schreiber) for
    the proposition that nonexpert witnesses may give opinions over matters to which they
    have personal knowledge. That case is not on point. In Schreiber, the Supreme Court
    held that a treating physician does not become a “retained” expert within the meaning of
    Code of Civil Procedure section 2034, subdivision (a)(2) (requiring the submission of an
    expert witness declaration) whenever such a physician gives opinion testimony.
    (Schreiber, at pp. 35–36.) Unlike the present case, in Schreiber the treating physicians
    had been designated as expert witnesses. (Id. at p. 34.)
    Alternatively, WWCA asserts Harris was qualified to offer expert testimony
    because he was designated as a nonretained expert by Valley in each of its expert witness
    designations and WWCA had reserved its right to call any experts listed by Valley.
    However, Valley points out that it subsequently withdrew the nonretained experts in its
    amended disclosure. In its reply brief, WWCA contends Harris could nevertheless offer
    expert testimony at trial because Valley did not withdraw its designation until after
    WWCA reserved its rights and after he had been deposed. However, the case it relies on,
    31
    Powell v. Superior Court (1989) 
    211 Cal. App. 3d 441
    , is inapposite because it did not
    address the utilization of experts after a designation has been withdrawn. In sum,
    WWCA has failed to demonstrate error in the exclusion of the proffered testimony.
    C. Limitation of Putnam’s Testimony
    WWCA also claims the trial court erred in sustaining Valley’s objections to
    Putnam’s testimony regarding the cost to complete the framing after MRC took over the
    Project in October 2008. It asserts the testimony was relevant to show the costs to
    remedy Valley’s allegedly defective work, as well as to challenge Valley’s credibility
    regarding its position that it had completed 100 percent of the framing. The trial court
    sustained Valley’s objection to testimony based on relevance. Valley’s counsel also
    noted that Putnam had not been designated as an expert witness and therefore he could
    not identify what caused the need to make corrections to the framing. For example,
    damage could have occurred because the framing was exposed to the weather for some
    months before MRC took over the Project. Additional framing work could also have
    been prompted by City inspections and design changes.
    In yet another posttrial declaration submitted along with WWCA’s motion for a
    new trial, Putnam declared that MRC had charged “a total of $504,865 to remedy all of
    the items on the Oris defect list as well as other non-conforming work that MRC found in
    the field.” Given the state of the evidence at the time of Putnam’s testimony, including
    an apparent lack of expert testimony as to how much of MRC’s charges were attributable
    to Valley’s faulty work, we cannot say the trial court abused its discretion in excluding
    the proffered testimony.31
    D. Exclusion of Notice to Cure
    At trial, WWCA attempted to introduce an August 1, 2008 letter prepared by its
    trial counsel as evidence that a notice to cure was issued to Valley. WWCA directs us to
    31
    WWCA argues that all the framing costs were due to Valley’s breaches and “ultimate
    abandonment of the Project in June 2008.” (Italics added.) As we must view the
    evidence in a light most favorable to the verdict, we cannot agree with WWCA’s
    characterization of Valley’s conduct.
    32
    a portion of the reporter’s transcript taken during Nesbitt’s testimony. It appears that by
    this time, the trial court had already sustained Valley’s objection to the admission of the
    letter. Regardless of whether the letter was admissible, WWCA fails to show its
    exclusion was prejudicial.
    On June 20, 2008, WWCA issued the last of the stop work notices, directing
    Valley to immediately cease all work. While WWCA claims the notice to cure was
    evidence that it “made an attempt to get Valley to comply with its contractual obligations
    before terminating Valley, it is indisputable that the notice was sent after WWCA
    imposed this final stop work notice. The August 1, 2008 letter contains no language
    recalling the stop work notice and it does not purport to be a return to work notice. It is
    thus unclear how Valley could have complied with its “contractual obligations” after
    receiving the letter.32 Accordingly, the letter is not relevant as to whether Valley was in
    breach of contract.
    E. Admission of Allegedly Prejudicial Evidence
    WWCA claims the trial court erred in allowing Valley to elicit testimony from
    several witnesses revealing that MRC and certain subcontractors had not been paid their
    final retention. It asserts this testimony served no relevant purpose and should have been
    excluded because it was highly prejudicial. It also asserts the court wrongly allowed
    evidence of the sale price of the finished building. We find no error.
    As to the first point, WWCA provides numerous citations to the reporter’s
    transcript concerning the unpaid retentions,33 but concedes in its reply brief that the only
    32
    Nesbitt testified he was aware that in order for Valley to return to the job he needed to
    issue a return to work notice. He conceded he never did so.
    33
    For example, the waterproofing subcontractor testified he was never told his work was
    deficient. By the time he ceased working on the Project, he was owed approximately
    $150,000. He was never paid. WWCA also did not pay the mechanical subcontractor’s
    retentions even though all of its work passed City inspection. A drywall company’s work
    also always passed City inspection. It received a stop work notice in May 2008. At that
    time, it was owed $196,748. The company returned to the Project about four months
    later. WWCA did not make payments. MRC terminated it because the company’s owner
    refused to increase his manpower. At the time of trial, he was owed $236,000.
    33
    time it objected to this evidence at trial was during Putnam’s testimony. As to all the
    other instances, WWCA failed to preserve this issue for appeal. (See Evid. Code, §§ 353,
    354; and see People v. Rogers (1978) 
    21 Cal. 3d 542
    , 548.) By the time Putnam testified,
    the jury had already heard testimony that some subcontractors had not been paid.34
    Therefore, even if the trial court erred in allowing Putnam’s testimony, WWCA was not
    prejudiced thereby.
    The problem with WWCA’s challenge to the sale price evidence is that the only
    “testimony” WWCA claims was improperly admitted is not testimony at all, but rather is
    the opening statement of Valley’s counsel. Notably, WWCA did not interpose any
    objections to the statement. The jury was also read CACI No. 3925, which expressly
    advises that arguments of counsel are not evidence and that the verdict must be based on
    the testimony of witnesses and other evidence.35 We find no error.
    IV.    Inclusion of WCG as a Judgment Debtor
    On July 25, 2013, WCG moved for a nonsuit, arguing that it was not an owner of
    the Project. Valley’s counsel responded that WCG is specifically referenced in the
    Amendment. He moved to amend Valley’s complaint to conform to proof. The nonsuit
    motion was deferred and the motion to amend was granted. On appeal, WCG claims the
    reference to it in the Amendment must be deemed a typographical error because it was
    not a contracting party to the original Construction Contract. It contends judgment was
    improperly entered against WCG.
    The Amendment itself specifies that it is an “AGREEMENT BETWEEN
    WINDSOR CAPITAL GROUP, INC. AND VALLEY COMMERCIAL
    CONTRACTORS, L.P.” Nesbitt signed the Amendment and testified that he was the
    executive vice-president of WCG. He also offered testimony indicating that WCG
    34
    Contrary to WWCA’s brief, the testimony at trial was that MRC was paid its final
    retention.
    35
    WWCA’s related claim that the trial court “prevented” Nesbitt from testifying as to the
    true costs WWCA incurred finds no support in the record. (See Cal. Rules of Court, rule
    8.204(a)(1)(C); and see Myers v. Trendwest Resorts, Inc. (2009) 
    178 Cal. App. 4th 735
    ,
    745 [appellant’s responsibility on appeal to accurately cite the record].)
    34
    viewed itself as a party to the agreements with Valley. This contradicts the claim that the
    reference to WCG was “clearly a mere typographical error.”
    Regardless, the doctrine of invited error applies here. “Under the doctrine of
    invited error, a party may not complain of the giving of a particular instruction that he or
    she individually or jointly requested. [Citations.] This rule is designed to prevent one
    whose conduct induces or invites the commission of error by the trial court from later
    taking advantage of it.” (Demkowski v. Lee (1991) 
    233 Cal. App. 3d 1251
    , 1257.) The
    jury instructions presented to the trial court after nine weeks of trial were jointly
    submitted by the parties. CACI No. 300 is the predicate for all of the contract damages
    instructions and expressly instructs the jury that Valley entered into a contract and an
    amendment with both WWCA and WCG. We disagree with WCG’s contention that the
    doctrine should not apply because this jury instruction was “non-substantive.”
    Relying on Demkowski v. 
    Lee, supra
    , 233 Cal.App.3d at p. 1257, WWCA claims
    the doctrine of invited error “was not meant to provide a litigant with a windfall in the
    event of a scrivener’s error.” Once again, the authority is not on point. In that case, the
    defendant did not object to the jury instruction. However, she did object to the verdict
    forms adopted by the court, claiming they permitted a double recovery against her.
    (Ibid.) Here, WCG did not object to the relevant instructions or verdict forms.
    Accordingly, the argument has been waived.
    V.     Award of Prejudgment Interest
    The jury awarded Valley $370,944 in prejudgment interest based on the
    progressive payments owed to it under the terms of the Amendment. WWCA claims
    Valley is not entitled to receive any prejudgment interest under Civil Code section 3287.
    It asserts the trial court erred in awarding such interest because the amount Valley claims
    it was owed is uncertain. It argues that the only certain amounts owed to Valley were
    limited to the installment payments scheduled to occur prior to the stop work notice. The
    trial court expressly rejected this argument. We review the trial court’s prejudgment
    interest award for legal error. (Pierotti v. Torian (2000) 
    81 Cal. App. 4th 17
    , 27–28.)
    35
    The purpose of prejudgment interest is to compensate the prevailing party for the
    loss of money during the period before the judgment is entered. (Wisper Corp. v.
    California Commerce Bank (1996) 
    49 Cal. App. 4th 948
    , 958.) Civil Code section 3287,
    subdivision (a) states, in pertinent part: “A person who is entitled to recover damages
    certain, or capable of being made certain by calculation, . . . is entitled also to recover
    interest thereon . . . .” “The test for recovery of prejudgment interest under [Civil Code]
    section 3287, subdivision (a) is whether ‘defendant actually know[s] the amount owed or
    from reasonably available information could the defendant have computed that
    amount.’ ” (Cassinos v. Union Oil Co. (1993) 
    14 Cal. App. 4th 1770
    , 1789.) “ ‘ “A
    dispute as to the price agreed, or as to the amount of work done or its cost, will not
    prevent the allowance of interest. . . . Where the data necessary to determine the amount
    due are supplied to the debtor by an invoice or statement, he will be charged with interest
    for failure to pay.” ’ ” (Conderback, Inc. v. Standard Oil Co. (1966) 
    239 Cal. App. 2d 664
    , 690.)
    The jury here evidently chose the $840,000 figure for damages on the breach of
    contract claim because that was the amount WWCA failed to pay under the Amendment.
    The trial court noted the contract “stated the amounts due and the dates the amounts were
    due, and those were the amounts awarded by the jury. Nothing more is needed to show
    ‘damages certain, or capable of being made certain by calculation, and the right to
    recover which is vested in the person upon a particular day.’ ” We agree and find no
    error.
    VI.      Rate of Prejudgment Interest
    As part of the judgment entered on November 21, 2013, Valley was authorized to
    foreclose the mechanic’s lien it recorded upon the Project, which is under Tarigo’s
    ownership. The total award was $1,198,980.45, comprised of $840,000 for WWCA’s
    breach of contract and $318,980.45 in prejudgment interest. The trial court later
    increased the prejudgment interest award to $370,944 to account for the fact that the
    judgment was entered later than had been anticipated. The interest rate was calculated at
    36
    a rate of 8 percent “under [Valley’s] agreement with defendants and Civil Code Sections
    3287 and 3289.”
    In its separate brief filed in this appeal, Tarigo argues that the prejudgment interest
    rate of 8 percent should be reduced to 7 percent based on Palomar Grading & Paving,
    Inc. v. Wells Fargo Bank, N.A. (2014) 
    230 Cal. App. 4th 686
    (Palomar), an opinion issued
    after the trial court’s ruling. In Palomar, the appellate court held that the constitutional
    default rate of 7 percent should apply to prejudgment interest on a mechanic’s lien as
    applied to noncontracting, innocent owners. (Id. at pp. 689–690.)
    Valley asserts Tarigo is precluded from contesting the 8 percent prejudgment
    interest rate by the doctrines of waiver and invited error. It also asserts the instant case is
    “readily distinguished from Palomar.” The issue was not waived. Because Palomar was
    a case of first impression 
    (Palomar, supra
    , 230 Cal.App.4th at p. 689) and was decided
    after the judgment appealed from, Tarigo cannot be faulted for having failed to raise the
    interest rate issue below. Similarly, while it is true that Tarigo concurred with the 8
    percent figure in the proceeding below, it did not invite any error.
    In 
    Palomar, supra
    , 
    230 Cal. App. 4th 686
    , a general contractor had contracted with
    two subcontractors who were not paid for substantial portions of their work. The
    landowners never entered a contract with the two subcontractors. 
    (Palomar, supra
    ,
    230 Cal.App.4th at pp. 688–689.) The appellate court held that prejudgment interest on a
    mechanic’s lien should not be calculated based on rates applicable to breach of contract
    where, as here, the innocent property owner was not a party to the contract or a
    participant in its breach. Rather, under such circumstances, “it is the constitutional
    default rate that should apply to prejudgment interest on a mechanic’s lien . . . .” (Id. at
    p. 690.) As the court explained, the default rate of interest prescribed by the Constitution
    in Article XV, section 1, sets the interest rate at 7 percent for the “ ‘forbearance of any
    . . . things in action.’ ” The court noted that “[t]hings in action obviously include the
    right to foreclose on a mechanic’s lien,” and found that as to noncontracting, innocent
    owners, the constitutional default rate applied, rather than the 10 percent rate specified by
    37
    Civil Code section 3289, subdivision (b), that otherwise would have applied.36 (Palomar,
    at pp. 689–690.)
    We concur with the reasoning in 
    Palomar, supra
    , 
    230 Cal. App. 4th 686
    . Like the
    landowner in that case, Tarigo was not a party to any of the underlying contracts. The
    judgment is reversed insofar as it provides for a rate of prejudgment interest at 8 percent
    and is remanded for a recalculation at the rate of 7 percent.
    VII.     WWCA’s Motion to Tax Costs
    WWCA claims the trial court abused its discretion in awarding Valley virtually all
    of its costs ($1,364,188.84 out of $1,404,051.55), asserting Valley failed to provide
    admissible evidence to support the vast majority of its claimed costs. Specifically,
    WWCA challenges the awards for deposition costs, service of process, and witness fees.
    It claims Valley failed to provide the proper documentary support for these alleged costs,
    and contends several charges were unreasonable and not permitted under Code of Civil
    Procedure section 1033.5. It also argues that many of the costs sought by Valley were
    discretionary, and not reasonable or necessary.
    On January 29, 2014, Valley’s attorney, William S. Kronenberg, prepared a
    declaration in support of Valley’s opposition to the motion to tax costs. In his
    declaration, he noted that the number of individual expenses and costs incurred on
    Valley’s behalf could not be examined without an undue expenditure of time and without
    partially waiving attorney-client and attorney work product privileges. He indicated his
    firm had lodged unredacted invoices reflecting all of the expenses and costs for the trial
    court’s in camera inspection.
    On February 11, 2014, the trial court held a hearing on WWCA’s motion to tax
    costs.
    On March 18, 2014, the trial court filed its order after hearing. As to the
    deposition costs, service of process, and witness fees, the court overruled all of WWCA’s
    36
    Civil Code section 3289, subdivision (b), provides: “If a contract entered into after
    January 1, 1986, does not stipulate a legal rate of interest, the obligation shall bear
    interest at a rate of 10 percent per annum after a breach.”
    38
    objections. With respect to the witness fees, the court stated: “Mr. Kronenberg’s
    declaration states an adequate basis and provides acceptable documentation for this item.
    It is noted that Valley as both plaintiff and defendant is entitled pursuant to CCP 998 to
    recover expert witness costs pre- and post-settlement offer, since it achieved a more
    favorable outcome than the CCP 998 offer.”
    As the prevailing party, Valley had the right to recover costs. (Code Civ. Proc.,
    § 1032, subd. (b).) The burden of proof on a motion to tax costs depends upon the nature
    of the costs being challenged. “If the items appearing in a cost bill appear to be proper
    charges, the burden is on the party seeking to tax costs to show that they were not
    reasonable or necessary. On the other hand, if the items are properly objected to, they are
    put in issue and the burden of proof is on the party claiming them as costs.” (Ladas v.
    California State Auto. Assn. (1993) 
    19 Cal. App. 4th 761
    , 774.) All of the costs at issue in
    this appeal are specifically recoverable by statute. WWCA therefore had the burden of
    proving them unreasonable and/or unnecessary. We review the trial court’s decision on
    appeal for abuse of discretion. (Bender v. County of Los Angeles (2013) 
    217 Cal. App. 4th 968
    , 990.)
    While WWCA raises numerous allegations as to Valley’s alleged failure to
    provide backup documentation to support the majority of its costs, WWCA does not does
    not deny that the trial court conducted an in camera review of Valley’s privileged
    supporting documentation, thereafter concluding the costs were reasonable and
    justifiable. WWCA did not request a statement of decision from the court, nor did it
    cause a transcript of the hearing on the issue to be prepared. “All intendments and
    presumptions are indulged to support [the trial court’s order] on matters as to which the
    record is silent, and error must be affirmatively shown.” (Denham v. Superior Court
    (1970) 
    2 Cal. 3d 557
    , 564.) WWCA has failed to demonstrate error.
    VIII. Nonsuit on WWCA’s Negligence Cause of Action
    Finally, WWCA contends the trial court erred in granting Valley’s nonsuit as to its
    negligence cause of action.
    39
    On August 26, 2013, Valley renewed a motion for nonsuit that the trial court had
    previously deferred upon ruling. The parties orally argued their respective positions
    regarding the merits of the nonsuit motion, and WWCA also submitted a written brief on
    the issue for the court’s consideration.
    On August 27, 2013, the trial court granted the motion for nonsuit. The court did
    not make a record of its rationale for granting the nonsuit, and WWCA did not request
    such a record.
    “A nonsuit in a jury case or a directed verdict may be granted only when
    disregarding conflicting evidence, giving to the plaintiffs’ evidence all the value to which
    it is legally entitled, and indulging every legitimate inference which may be drawn from
    the evidence in plaintiffs’ favor, it can be said that there is no evidence to support a jury
    verdict in their favor.” (Elmore v. American Motors Corp. (1969) 
    70 Cal. 2d 578
    , 583.)
    Nonsuit is appropriate where the plaintiff’s proof raises nothing more than speculation,
    suspicion, or conjecture. (Helm v. K.O.G. Alarm Co. (1992) 
    4 Cal. App. 4th 194
    , 198,
    fn. 1.)
    In reviewing a grant of nonsuit, the appellate court evaluates the evidence in the
    light most favorable to the plaintiff. (Nally v. Grace Community Church (1988)
    
    47 Cal. 3d 278
    , 291.) The judgment of nonsuit will be affirmed if a judgment for the
    defendant is required as a matter of law, after resolving all presumptions, inferences and
    doubts in favor of the plaintiff. (Ibid.) The review of a grant of nonsuit is de novo.
    (Saunders v. Taylor (1996) 
    42 Cal. App. 4th 1538
    , 1541–1542.)
    The parties agree that the trial court’s decision to grant the nonsuit motion was
    based on its finding that WWCA had not offered sufficient evidence of causation.
    WWCA argues causation could have been shown by evidence of the costs to repair the
    construction defects that allegedly occurred under Valley’s watch, evidence that the court
    “erroneously excluded.” The evidence WWCA cites to includes the testimony from
    Putnam that we have already found was properly excluded.
    The problem here, which we have already discussed above, is that there was no
    admissible evidence as to the cost of repairs attributable to Valley, as opposed to costs
    40
    that were incurred to remediate weather damage or design flaws. It was uncontroverted
    at trial that only some of the repairs were related to poor workmanship by Valley’s
    subcontractors. The rest was attributable to weather, plan corrections, new designs, and
    the costs spent to complete the Project itself. Because WWCA failed to isolate the
    charges attributable to Valley, the motion for nonsuit was properly granted.
    IX.    Denial of Valley’s Motion for Attorney Fees
    Valley cross-appeals from the trial court’s ruling denying its motion for attorney
    fees. The motion was based on WWCA’s alleged failure to reasonably admit a request
    for admission. Code of Civil Procedures section 2033.420 (section 2033.420) at
    subdivision (a) provides: “If a party fails to admit the genuineness of any document or the
    truth of any matter when requested to do so under this chapter, and if the party requesting
    that admission thereafter proves the genuineness of that document or the truth of that
    matter, the party requesting the admission may move the court for an order requiring the
    party to whom the request was directed to pay the reasonable expenses incurred in
    making that proof, including reasonable attorney’s fees.”
    The trial court’s ruling on a section 2033.420 motion is reviewed for an abuse of
    discretion. (Miller v. American Greetings Corp. (2008) 
    161 Cal. App. 4th 1055
    , 1066.)
    “The determination of whether ‘there were no good reasons for the denial,’ whether the
    requested admission was ‘of substantial importance,’ and the amount of expenses to be
    awarded, if any, are all within the sound discretion of the trial court. [Citation.] By
    contrast, if the trial court exercises its discretion and determines that the requirements of
    the statute exist, reasonable expenses must be awarded. [Citation.] On appeal, the trial
    court’s decision will not be reversed unless the appellant demonstrates that the lower
    court abused its discretion.” (Brooks v. American Broadcasting Co. (1986)
    
    179 Cal. App. 3d 500
    , 508.)37
    37
    We disagree with Valley’s contention that we must review this issue under the de novo
    standard of review.
    41
    On appeal, Valley contests the trial court’s ruling with respect to its request for
    admission No. 1. This request asked WWCA to “[a]dmit propounding party is not liable
    to responding party for breach of contract as alleged in responding party’s second
    amended cross-complaint’s first cause of action.” WWCA unequivocally denied the
    request. Reiterating that the jury ultimately found Windsor’s denial was wrong and that
    Valley did not breach the contract, Valley asserts the court erred as a matter of law in
    denying its right to attorney fees.
    Subdivision (b) of section 2033.420 provides: “The court shall make this order [to
    pay reasonable expenses] unless it finds any of the following: [¶] (1) An objection to the
    request was sustained or a response to it was waived under Section 2033.290. [¶] (2) The
    admission sought was of no substantial importance. [¶] (3) The party failing to make the
    admission had reasonable ground to believe that that party would prevail on the matter.
    [¶] (4) There was other good reason for the failure to admit.” “In evaluating whether a
    ‘good reason’ exists for denying a request to admit, ‘a court may properly consider
    whether at the time the denial was made the party making the denial held a reasonably
    entertained good faith belief that the party would prevail on the issue at trial.’ ” (Laabs v.
    City of Victorville (2008) 
    163 Cal. App. 4th 1242
    , 1276.)
    As the trial court noted in its ruling, at the point at which this request was served,
    more than two years before trial, WWCA had reasonable grounds to believe it would
    prevail on its cross-claim that Valley had breached the initial 2005 Agreement by failing
    to complete the Project in a timely and workmanlike manner. While Valley quarrels with
    this finding, we cannot say that WWCA acted in bad faith in pursuing its cross-claim.
    Indeed, it would be unreasonable to expect WWCA to admit such a request in the
    beginning stages of litigation and effectively forfeit its right to present evidence and have
    42
    its claim decided by a jury.38 Accordingly, we find no abuse of discretion in the court’s
    denial of attorney fees for Valley’s cost-of-proof.39
    DISPOSITION
    The judgment is reversed as to the interest rate on the mechanic’s lien. The matter
    is remanded for the calculation of interest on the mechanic’s lien at the legal rate of
    7 percent. In all other respects, the judgment is affirmed. The parties shall bear their
    own costs on appeal.
    38
    We need not address WWCA’s additional argument that Valley failed to present
    competent evidence to establish its costs-of-proof.
    39
    Valley requests a “voluntary partial dismissal of its severable cross-appeal of the trail
    court’s February 11, 2014 and March 18, 2014 post-judgment orders on costs in this
    case.” Not surprisingly, WWCA does not oppose the request. The balance of Valley’s
    cross-appeal is dismissed.
    43
    _________________________
    DONDERO, J.
    We concur:
    _________________________
    HUMES, P.J.
    _________________________
    BANKE, J.
    A141069/A141661
    44