Nissho of California, Inc. v. Bond Safeguard Insurance , 163 Cal. Rptr. 3d 575 ( 2013 )


Menu:
  • Filed 10/22/13
    CERTIFIED FOR PUBLICATION
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    FOURTH APPELLATE DISTRICT
    DIVISION TWO
    NISSHO OF CALIFORNIA, INC.,
    Plaintiff and Appellant,                      E052746
    v.                                                    (Super.Ct.No. INC075909)
    BOND SAFEGUARD INSURANCE                              OPINION
    COMPANY,
    Defendant and Appellant.
    APPEAL from the Superior Court of Riverside County. Thomas A. Peterson
    (retired judge of the L.A. Super. Ct. assigned by the Chief Justice pursuant to art. VI, § 6
    of the Cal. Const.) and John G. Evans, Judges. Reversed in part, affirmed in part.
    Mordy Law Offices and Christopher R. Mordy for Plaintiff and Appellant.
    Voss, Cook & Thel, Francis T. Donohue III, Jessica T. Elmassian; Harris Beach
    and Bruce L. Maas for Defendant and Appellant.
    Robins, Kaplan, Miller & Ciresi, David C. Veis and Laura P. Nash for The Surety
    & Fidelity Association of America as Amicus Curiae on behalf of Defendant and
    Appellant.
    1
    Prior to entering into a Subdivision Improvement Agreement (SIA) with the City
    of Palm Springs (City) for the development of a private residential community called the
    Avalon Palm Springs Village project (Avalon), Suncal PSV, LLC (Suncal), the owner of
    the property in a joint venture partnership with Lehman Brothers, obtained a Maintenance
    and Warranty Bond, several faithful performance (FP) bonds, and seven labor and
    materials (L&M) bonds from defendant and appellant Bond Safeguard Insurance
    Company (Safeguard) to insure the project. Suncal and City then entered into a SIA
    which specifically required landscaping improvements to “offsite” areas bordering the
    project, which were owned by City.1 City required the landscaping for the “offsite” areas
    be bonded. Suncal had previously obtained a L&M bond for “Off-Site Landscaping &
    Traffic” in the amount of $566,200, representing 50 percent of the estimated cost of those
    improvements.
    Suncal entered into three separate contracts with plaintiff and appellant Nissho of
    California, Inc. (Nissho) for the landscaping of Avalon. One of those contracts, for
    $1,639,777.19, covered labor and materials for the “offsite” landscaping required in the
    SIA. Nissho completed a substantial portion of the work in the offsite contract but never
    received payment. On January 4, 2008, Nissho gave notice to Suncal and Safeguard that
    it had not been paid the sum of $896,963.53 for work performed on the offsite
    1   “Off-site improvements refer to improvements that are off of the property site
    itself,” i.e., “off-site landscaping refers to landscaping off the private property, for
    example on adjacent public property.”
    2
    landscaping contract. Attached to the letter were copies of both the FP and L&M “Off-
    Site Landscape & Traffic” bonds and the Maintenance and Warranty bond.
    Nissho filed suit against both Suncal and Safeguard seeking damages of
    $1,597,567.82 as against Suncal for breach of all three contracts and $909,986.96 as
    against Safeguard on the L&M bonds.2 After a bench trial, the court ruled in favor of
    Nissho in the amount of $1,041,148.55, permitting it to seek recompense against all the
    L&M bonds, regardless of their characterization. Nissho filed a motion for attorney fees,
    which the trial court denied. Safeguard appeals contending the trial court erred in
    awarding Nissho damages in excess of the L&M bond for “Off-Site Landscaping &
    Traffic” (the “Offsite Bond”). Nissho appeals maintaining it was entitled to an award of
    attorney fees. We reverse the judgment with respect to the trial court‟s award of damages
    to Nissho above the limit of the Offsite Bond. We affirm the judgment with respect to
    the trial court‟s denial of Nissho‟s motion for attorney fees.
    FACTUAL AND PROCEDURAL HISTORY
    Director of Public Works and City Engineer David Barakian, testified it was
    City‟s responsibility to make sure any proposed development was consistent with City‟s
    general plan as adopted by the city council. Barakian reviewed all plans for new
    developments in the city and had authority to accept or reject any proposed plans. If a
    2  At trial, Nissho also attempted to obtain remuneration against the L&M bonds
    for on-site work it had completed but for which it had not been paid. Suncal apparently
    filed for bankruptcy to which Nissho would, by all accounts, have been entitled to
    become a claimant. Additionally, Nissho‟s counsel conceded that as a licensed
    contractor, Nissho had resort to recover under a mechanic‟s lien on the work it performed
    on “on-site” areas.
    3
    developer was proposing a new development within the city, it was required to obtain
    security to pay for the improvements in case they were not completed by the developer;
    in this instance, the security consisted of bonds. The form of the bond was dictated or
    approved by the city attorney.
    Developers were required to obtain bonds for both FP and L&M. FP bonds
    ensured that if the developer refused or was unable to complete the project City could
    recover the costs for the improvements it deemed necessary. L&M bonds “cover the
    costs of labor and materials of vendors and subcontractors employed by the developer in
    performance” of the contract. A Maintenance and Warranty bond covered improvements
    for a one-year period after the city accepted the improvements. Suncal asked City if it
    could break up the securities by category of the work to be performed.
    Between October 27, and 30, 2006, Suncal obtained from Safeguard FP bonds
    totaling $17,385,000 or 100 percent of the estimated cost for the proposed works of
    improvement. On the same dates, Suncal obtained from Safeguard seven L&M bonds
    totaling $8,692,500, or 50 percent of the estimated construction costs. The L&M bonds
    were enumerated and valued as follows: (1) Domestic Water $1,635.452; (2) Storm
    Drain $244,250; (3) Sanitary Sewer System $1,566,350; (4) AC Pavement $2,035,000;
    (5) Aggregate Base $892,675; (6) Curb & Gutter/Flatwork $1,762.575; and (7) Offsite
    Landscaping & Traffic $566,200. Suncal additionally acquired a Maintenance and
    Warranty of Improvements bond in the amount of $169,860. The offsite landscaping
    4
    improvements were proposed by Suncal in order that the surrounding public areas would
    match the on-site landscaping of the development.3
    Todd Rohm, an independent insurance agent working for Rohm Insurance Agency
    signed the Offsite Bond as attorney-in-fact for Safeguard. It was on a city bond form.
    Rohm testified separate bonds, rather than a single bond, were issued because it would
    narrow the scope of the work performed allowing the principal, Suncal, to obtain releases
    from City under the individual bonds so that it would not continue to be liable for the
    total amount of improvements yet to be constructed. Thus, if the curbs and gutters,
    landscaping, and streets were completed, Suncal could be released by City for liability for
    the completed works while remaining liable only for those yet to be completed. The SIA
    was entered into by the parties on December 18, 2006. Rohm testified “It‟s very typical
    that the bonds have to be prepared and included within the agreements and submitted all
    at one time and then the—the agreement is often times signed at a later date when
    everything is provided, security included, the bond security.”
    Moreover, renewal premiums were required to be paid on all the bonds, so it
    would be less costly for a developer to have separate bonds, some of which might be
    completed and released, than it is to have one large bond that must continue to be
    renewed until the entire project is completed. Once the work secured by a particular
    bond is signed off and accepted by the city, the bond is exonerated and the principal no
    3  Suncal “wanted to . . . take the landscaping . . . that had been there for years, and
    to change it at their expense, to have new landscaping put in in that area that better fit the
    type of landscaping they were putting in elsewhere . . . .”
    5
    longer is required to pay premiums on that bond. Furthermore, if a claim is made on a
    single L&M bond, the claimant could obtain an award for the entire amount of the bond
    to the exclusion of all other subcontractors, laborers, or suppliers who could potentially
    also make claims against the same bond; thus, bonds separately designated for divergent
    areas of work would make it more likely that any particular subcontractor could obtain
    recompense against the bond if the developer became unable to pay.
    Each category of bond issued covered only work performed within the purview of
    that bond. Construction estimates were created to enumerate what work would be
    covered by each particular bond. Those estimates determined what entities could recover
    for any particular type of work designated under the separately characterized bonds. Any
    work not performed on those worksheets would not be covered by that bond. Carol
    Templeton, an Engineering Associate for City who was involved in the SIA and the bond
    calculations for Avalon, testified the bond amounts were assessed using the amounts in
    the bond worksheets. She obtained the amount for the Offsite Bond by obtaining
    estimates from two subcontractors for the total amount of the work required; the amounts
    were doubled to provide a “cushion” in case City had to perform the work itself. There
    was no requirement that Suncal‟s contractors or subcontractors pay prevailing wages for
    any of the project‟s work, including the offsite landscaping.
    Marcus Fuller, the Assistant Director of Public Works and Assistant City Engineer
    for City who prepared and reviewed all the bonds in the Avalon project, testified none of
    the landscape improvements were ever accepted by City. He testified it is unusual for
    City to require landscaping bonds for such projects; City only required landscaping bonds
    6
    in the Avalon project for offsite areas that City would later be required to maintain. City
    did not require that landscaping in on-site areas, areas which would be within the
    community and not on City land, be bonded. Nonetheless, even though the bonds
    covered offsite areas belonging to City, the bonds were “not bonds associated with public
    work projects.”
    Nabu Kato, the owner and founder of Nissho, testified he provided estimates to
    Suncal for the landscaping work on Avalon. His estimates did not include prevailing
    wages. Nissho subsequently signed contracts with Suncal for the landscaping work.
    Kato defined offsite work as any work conducted on land that would eventually be turned
    over either to the homeowners‟ association or City.
    After trial, the parties agreed the primary dispute between Nissho and Safeguard
    was not whether Nissho could and should recover money from one of the bonds, but
    which bond or bonds and up to what amount. Safeguard contended Nissho was limited to
    recovering the $566,200 for work under the Offsite Bond. In fact, Safeguard conceded
    Nissho‟s work was “covered by the [Offsite Bond]”; Nissho “did landscape work[,]
    [t]hey‟re entitled to recover under that bond up to $566,000”; it simply contested
    Nissho‟s ability to reach the other L&M bonds. Nissho argued it could recover for all its
    work, both offsite and on-site, under all the L&M bonds.
    The court entered judgment in favor of Nissho in the amount of $1,041,148.55
    plus costs and interest from January 2008. The court found Nissho had provided work in
    the amount of $1,041,148.55. The court further found, “The SIA only requires that a
    security instrument (singular) be provided for L&M. Therefore, SunCal and Safeguard
    7
    contracted to split the L&M requirement into seven separate bonds. No subcontractor
    was a party to this agreement. Thereby, Safeguard contracted with Suncal to limit it[]s
    own liability to the detriment of the subcontractors.” Thus, “The court finds that
    Safeguard is liable to Nissho up to an amount not exceeding $8.6 million.” The court
    additionally awarded Nissho recovery of interest dating back to the date of its claim
    because the court found Nissho was not limited to the amount of the L&M landscape
    bond. Finally, the court tentatively found Nissho was not entitled to recover attorney fees
    because insufficient evidence established the L&M bonds were public works payment
    bonds. Thus, the fact that some of the areas would come under the control of City did not
    alter the private nature of the agreement at the time it was signed.
    Nissho later filed a motion for attorney fees as a direct obligee of the bond. The
    court denied the motion, expositing, “[Nissho] as the prevailing party is not entitled to
    attorneys fees under the Labor and Materials Bonds [Government Code section] 66499.2
    or Civ[il] Code [sections] 3082 et seq. The purpose of the Labor and Material Bonds
    involved here is to protect . . . City . . . by providing for payment to the contractors
    subcontractors[,] laborers[,] materialmen[,] and all other persons employed in the
    performance of the work of improvement[,] for materials furnished or labor thereon of
    any kind. The bonds are not designed to establish a fund for payment of breach of
    contract damages beyond the reasonable amount of materials or labor provided. Even if
    the contract between Suncal . . . and Nissho . . . provided for attorneys fees to the
    prevailing party the court would reach the same decision.”
    8
    DISCUSSION
    A.     INTRODUCTION
    “„The Subdivision Map Act is “the primary regulatory control” governing the
    subdivision of real property in California.‟ [Citation.] It has three principal goals: „to
    encourage orderly community development, to prevent undue burdens on the public, and
    to protect individual real estate buyers.‟ [Citation.] It „seeks “to encourage and facilitate
    orderly community development, coordinate planning with the community pattern
    established by local authorities, and assure proper improvements are made, so that the
    area does not become an undue burden on the taxpayer.”‟ [Citation.]” (Pacific Palisades
    Bowl Mobile Estates, LLC v. City of Los Angeles (2012) 
    55 Cal. 4th 783
    , 798-799.)
    “To accomplish its goals, the Subdivision Map Act sets suitability, design,
    improvement, and procedural requirements (e.g., Gov. Code, §§ 66473 et seq., 66478.1 et
    seq.). It also allows local governments to impose supplemental requirements of the same
    kind (e.g., id., §§ 66475 et seq., 66479 et. seq.). [Citation.] Further, „[t]he Act vests the
    “[r]egulation and control of the design and improvement of subdivisions” in the
    legislative bodies of local agencies, which must promulgate ordinances on the subject.‟
    [Citation.] The local entity‟s enforcement power is directly tied to its power to grant or
    withhold approval of a subdivision map. Thus, „[o]rdinarily, subdivision under the Act
    may be lawfully accomplished only by obtaining local approval and recordation of a
    tentative and final map . . . .‟ [Citation.]” (Pacific Palisades Bowl Mobile Estates, LLC
    v. City of Los Angeles, supra, 55 Cal.4th at p. 799.)
    9
    “By the enactment of this article, the Legislature intends to accomplish . . . the
    following objective[]: [¶] . . . [¶] (c) To ensure that local agencies have maximum
    discretion . . . in the imposition of conditions on any approvals occurring subsequent to
    the approval or conditional approval of the vesting tentative map . . . .” (Gov. Code,
    § 66498.9)4 Whenever the furnishing of security is required it shall be in any form of
    security which is acceptable to the local agency including one or more bonds by one or
    more authorized corporate sureties. (§ 66499, subd. (a)(1)(5).)
    “A surety is „one who promises to answer for the debt, default, or miscarriage of
    another, or hypothecates property as security therefor.‟ [Citation.] A surety bond is a
    „“written instrument executed by the principal and surety in which the surety agrees to
    answer for the debt, default, or miscarriage of the principal.”‟ [Citation.] In suretyship,
    the risk of loss remains with the principal, while the surety merely lends its credit so as to
    guarantee payment or performance in the event that the principal defaults. [Citation.] In
    the absence of default, the surety has no obligation. [Citation.]” (Cates Construction,
    Inc. v. Talbot Partners (1999) 
    21 Cal. 4th 28
    , 38.)
    “„[A] surety on an official bond undertakes no liability for anything which is not
    within the letter of his contract. The obligation is strictissimi juris; that is, he has
    consented to be bound only within the express terms of his contract and his liability must
    be found within that contract or not at all. [Citation.] “Where a surety bond is given
    pursuant to the requirements of a particular statute, the statutory provisions are
    4   All further statutory references are to the Government Code unless indicated.
    10
    incorporated into the bond.” [Citation.]‟ [Citation.]” (Schmitt v. Insurance Co. of North
    America (1991) 
    230 Cal. App. 3d 245
    , 258.) “The surety‟s obligation is strictly construed
    so as not to impose a burden not contained in or clearly inferable from the language of
    the contract. [Citations.]” (Airlines Reporting Corp. v. United States Fidelity &
    Guaranty Co. (1995) 
    31 Cal. App. 4th 1458
    , 1464.)
    “„In general, a surety bond is interpreted by the same rules as other contracts.
    That is, we seek to discover the intent of the parties, primarily by examining the words
    the parties have chosen giving effect to the ordinary meaning of those words.‟” (Amwest
    Sur. Ins. Co. v. Patriot Homes, Inc. (2005) 
    135 Cal. App. 4th 82
    , 86-87.) “[I]f the trial
    court‟s interpretation [was] based solely on an examination of the contract, the
    interpretation of the contract is a question of law and this court will independently review
    the validity of the trial court‟s construction. [Citation.] However, if the trial court [was]
    presented with conflicting extrinsic evidence to aid in the interpretation of the contract, „a
    reasonable construction of the agreement by the trial court which is supported by
    substantial evidence will be upheld. [Citations.]‟ [Citations.]” (Lugosi v. Universal
    Pictures (1979) 
    25 Cal. 3d 813
    , 852.)
    “It long has been settled in California that where a bond incorporates another
    contract by an express reference thereto, „the bond and the contract should be read
    together and construed fairly and reasonably as a whole according to the intention of the
    parties.‟ [Citations.] To ascertain the nature and extent of the liability to which the
    surety has bound itself, courts must „examine the language of the undertaking by the light
    of the [construction] agreement, faithful performance of the terms of which it
    11
    guarantees.‟ [Citations.] As a general rule, „[t]he obligation of a surety must be neither
    larger in amount nor in other respects more burdensome than that of the principal . . . .‟
    [Citation.]” (Cates Construction, Inc. v. Talbot Partners, supra, 21 Cal.4th at pp. 39-40.)
    Here, the parties agree that although there was no express reference to the L&M bonds in
    the SIA, the parties intended the SIA to incorporate the L&M bonds.
    B.     NISSHO WAS LIMITED TO RECOVERING AGAINST THE PENAL
    SUM ENUMERATED IN THE OFFSITE BOND IN THE AMOUNT OF
    $566,200
    Safeguard contends Nissho was limited to recovering against the amount
    enumerated in the Offsite Bond. We agree.
    Here, the court resorted to the consideration of evidence extrinsic to the SIA and
    the bond agreements. As such, we may consider such evidence in determining whether
    its interpretation of the SIA was supported by substantial evidence. Considering the
    uncontradicted parole evidence of the SIA adduced below, we hold Nissho was limited to
    recover only in an amount no greater than the penal sum specified in the Offsite Bond.
    First, section 66499 et seq. clearly provide for the legality of obtaining separate
    bonds to furnish security for projects such as the SIA. Section 66499, subdivision (a)(1)
    allows for a “[b]ond or bonds by one or more duly authorized corporate sureties.”
    Section 66499.2, which dictates the form of any L&M bond issued under the statutes,
    provides “A bond or bonds by one or more duly authorized corporate sureties for the
    security of laborers and material suppliers shall be in substantially the following form[.]”
    12
    Thus, the issuance of multiple L&M bonds for a development project was clearly
    envisioned under the statutory scheme.
    Second, it is notable all the Avalon security bonds were issued more than a month
    prior to the execution of the SIA. All the bonds were issued between October 27, and 30,
    2006. The SIA was not signed until December 6, 2006, at which time City had already
    accepted Nissho‟s provision of security, which the parties agree was incorporated into the
    SIA. Thus, the parties to the SIA clearly intended the provision of multiple L&M bonds
    to be acceptable.
    The evidence adduced below established City consented to the issuance of
    separate securities characterized by the work to be performed. City was approached prior
    to issuance of the securities with a request that City permit Suncal to obtain separate
    securities. City was intimately involved in determining the amounts of the bonds through
    the use of bond worksheets and contractor estimates specifically delineated by the type of
    work to be performed; thus, not only was City aware that separate bonds would issue, it
    aided Suncal in determining their scope. The security bonds were on forms supplied and
    approved by City. City reviewed the adequacy of the bonds prior to entering into the
    SIA. Thus, City exercised its statutorily invested “maximum discretion” in approving the
    SIA with separate security bonds. (§ 66498.9, subd. (c).)
    Third, contrary to the court‟s ruling, it was undisputed below that Suncal, not
    Safeguard, requested issuance of separate securities. Thus, contrary to the court‟s
    characterization, Safeguard did not attempt “to limit it[]s own liability to the detriment of
    the subcontractors.” Indeed, Safeguard did only what was requested of it: issue separate
    13
    securities in amounts and characterizations of the work to be performed as designated by
    Suncal and City. Since, as discussed ante, the bonds were on City forms and in amounts
    determined by City and Suncal based on subcontractor estimates, it is difficult to assign
    nefarious intent to Safeguard for doing exactly what was asked of it.
    Fourth, it is entirely consistent with a reading of the SIA that Suncal would have
    Safeguard issue separately denominated L&M bonds limited to the work therein
    described. Nissho maintains the SIA‟s provision that, “A Security Instrument
    guaranteeing the payment to contractors, subcontractors, and other persons furnishing
    labor, materials, and/or equipment („Labor and Materials Security Instrument‟) with
    respect to the Works of Improvement in an amount equal to $8,692,500 equal to 50% of
    the estimated construction cost,” required Safeguard to issue one L&M bond in the
    amount of 50 percent of all estimated construction costs, from all of which it was entitled
    to seek remuneration. Likewise, Nissho argues language in each of the L&M bonds
    reading, “for materials furnished or labor thereon of any kind” allowed it to disregard the
    characterization of each bond since it provided work that would fall within the broad
    definition “of any kind.” (Italics added.) The clear intent of those provisions was to
    provide adequate security for the entire project in the SIA and the categories of
    improvements denominated in the separate L&M bonds. The fact that Suncal had
    Safeguard issue separate bonds securing disparate facets of the project comes well within
    that intent. (Lunardi v. Great-West Life Assurance Co. (1995) 
    37 Cal. App. 4th 807
    , 820.)
    14
    Whether Suncal obtained one security instrument or several, the bonds obtained by
    Suncal from Safeguard covered the amounts and work required by the SIA, City, and
    Government Code sections 66499 et seq. (Civ. Code § 1650; County of Kern v.
    California Dept. of Health Services (2009) 
    180 Cal. App. 4th 1504
    , 1513-1514.) City
    chose to limit the L&M bonds to 50 percent of the estimated costs of the improvements to
    be performed by the contractors, subcontractors, laborers, materialmen, and suppliers.
    The Offsite Bond in the amount of $566,200 represented 50 percent of all
    estimated offsite landscaping and traffic improvements. The amount of the bond was
    determined primarily from cost estimates provided by Nissho itself. Moreover, the
    estimates that provided the base amount for the Offsite Bond were doubled to provide a
    “cushion” in case City had to perform the work. This is, presumably, because once City
    had to undertake the work, it would become a public works project requiring City to pay
    prevailing wages. Thus, because the Offsite Bond included amounts for non-landscape
    work and doubled the construction estimates for all work performed under its aegis, the
    bond could not be construed as limiting any subcontractor‟s potential recovery under the
    bond in the event Suncal defaulted, particularly Nissho, which participated in the
    computation of the bond‟s amount. Indeed, because Nissho‟s offsite landscaping contract
    with Suncal amounted to $1,639,777.19, Nissho was at least on constructive notice that
    its contract amount twice exceeded the Offsite Bond and, therefore, it would be unable to
    recover even half the value of its work from the bond should Suncal default.
    15
    Fifth, Nissho presumably had knowledge of both the SIA and the bonds before it
    bid on or accepted award of the offsite landscaping contract with Suncal. As noted ante,
    Nissho had provided construction estimates, which served as the basis for the amount of
    the Offsite Bond. The incorporated bonds and bond worksheets were attached to the SIA,
    which was recorded in the county recorder‟s office. Kato testified Nissho began
    landscaping in 1984. Over its ensuing 20-plus-year history, Nissho expanded to the point
    where it had four regional offices operating in Chula Vista, Temecula, Palm Springs, and
    Vista, California. Nissho specialized in multiple large projects of up to 800,000 acres
    with 14,000 home sites.
    Under these circumstances, it is reasonable to conclude Nissho knew that under
    section 66499.3, subdivision (b), City was able to require that Suncal provide L&M
    bonds limiting Nissho‟s recovery in the event of Suncal‟s default to only 50 percent of
    the work it completed or 50 percent of the total work conducted on the project. Thus,
    Nissho was effectively on notice it could not rely on the entirety of all the L&M bonds
    for recovery in the event of Suncal‟s default. Nissho complains, “The net effect of . . .
    Safeguard‟s [bond] headers, if they are enforceable, is that contractors such as [Nissho]
    cannot be paid the full value of their work and labor.” Section 66499.3, subdivision (b)
    permits City to limit recovery for subcontractors to 50 percent of the work provided. City
    elected to require only the minimum amount of coverage required by statute.
    Sixth, the court‟s judgment did not differentiate between Nissho‟s on-site and
    offsite work. On the contrary, the court‟s judgment aggregated the three separate
    contracts Nissho entered into with Suncal and noted Nissho had performed $1,041,148.55
    16
    worth of work on the aggregated contracts, the exact amount it awarded Nissho. Thus,
    the court erroneously permitted Nissho to recover against the bonds for its on-site work.
    Although Nissho sought recovery against the bonds for both its on-site and offsite work,
    the undisputed testimony below established that only its offsite work was covered by the
    Offsite Bond. Thus, only offsite landscaping was bonded and the court‟s award of
    recovery against the bonds for on-site work performed by Nissho was error.
    Seventh and finally, treatment of all the L&M bonds as one singular bond while
    disregarding each bond‟s limitations with regard to the type of work characterized therein
    would ignore the intent of the actual parties to the bonds and the legal requirement that
    bonds be strictly construed to limit the surety‟s obligations to those expressly specified.
    Here, Safeguard was presented with bonds by Suncal on City forms, in language written
    by City, based upon language required by statute, in amounts based upon estimates
    provided by subcontractors, and with characterizations of the work to be performed
    provided by City and Suncal. Safeguard issued the bonds as they were presented to it.
    Nissho invokes former Civil Code section 3226 providing, “Any bond given pursuant to
    the provisions of this title will be construed most strongly against the surety and in favor
    of all persons for whose benefit such bond is given . . . .” Assuming arguendo the bonds
    issued in this case were “given pursuant to the provisions of” that title, we still fail to see
    how they could be interpreted to allow Nissho, a landscaper, to recover against bonds
    specifically limited to work on domestic water, storm drains, sanitary sewer system, AC
    pavement, aggregate base, and/or curb and gutter/flatwork. Moreover, Nissho‟s
    argument below that “since . . . Safeguard had the opportunity to make any changes that
    17
    they felt were appropriate, then it has to be interpreted most strongly against them,” is
    belied by the statutory requirements for the language contained in the bonds.
    Government Code section 66499.2 dictates the language of the bond and, as testified to at
    trial, the language of the bonds was on City forms approved by City; thus, Safeguard had
    no opportunity to make changes to the language of the bonds and construing it against the
    “drafter,” here either City or the Legislature, would not inure to Nissho‟s benefit.
    In conclusion, we hold in consequence of the uncontradicted parole evidence
    adduced below, insufficient evidence supported the trial court‟s interpretation of the SIA
    to require a single security instrument. Thus, Nissho was limited to recovering against
    the Offsite Bond in the amount of $566,200 for its offsite work only. We therefore
    reverse the court‟s judgment awarding Nissho $1,041,148.55 against all the L&M bonds.
    Since the trial court failed to distinguish amounts Nissho expended in its offsite and on-
    site work, the matter must be remanded for a determination of whether Nissho expended
    work valued up to or above the penal sum of $566,200 designated in the Offsite Bond.
    To the extent it did, judgment should be entered in Nissho‟s favor in the maximum
    amount of $566,200.
    C.     NISSHO‟S RECOVERY OF INTEREST
    The trial court ruled Nissho would be allowed to recover interest dating back to
    the date of its initial claim because it was not limited to recovery against the penal sum of
    $566,200 designated in the Offsite Bond. Thus, because Nissho could seek recovery
    against all the L&M bonds with an aggregate value of $8,692,500, and Nissho had only
    recovered $1,041,148.55 against those bonds, sufficient additional bond funds were
    18
    available to permit Nissho to recoup interest. On appeal, Safeguard requests that, to the
    extent we hold Nissho was limited to recovering the penal sum of $566,200 designated in
    the Offsite Bond, we determine whether Nissho could recover interest above and beyond
    the sum specified in that bond.
    In the first instance, we decline to make such a determination because we believe
    the question is not ripe for review. (Vandermost v. Bowen (2012) 
    53 Cal. 4th 421
    , 461
    [“„The ripeness requirement, a branch of the doctrine of justiciability, prevents courts
    from issuing purely advisory opinions. [Citation.] It is rooted in the fundamental
    concept that the proper role of the judiciary does not extend to the resolution of abstract
    differences of legal opinion‟”].) The trial court did not make a determination of whether,
    if Nissho had recovered up to the amount limited by the bond, Nissho could recover
    additional funds for interest. Second, since the trial court made no determination of
    whether the value of Nissho‟s work performed on the offsite contract equaled or
    exceeded the limits of the Offsite Bond, that determination must be made before any
    determination on interest can be made. Thus, on remand we direct the trial court to
    determine both the amount Nissho may recover for offsite work performed against the
    limits of the Offsite Bond and, if it equals or exceeds that amount, whether Nissho can
    recover an additional amount for interest.
    D.     ATTORNEY FEES
    Nissho contends that as the prevailing party in the action below, it was statutorily
    entitled to an award of attorney fees. Safeguard maintains there was no statutory basis
    for awarding Nissho attorney fees and, therefore, the trial court‟s denial of Nissho‟s
    19
    motion for attorney fees was based on a correct interpretation of the statutory law. We
    agree with Safeguard.
    “„“On review of an award [or denial] of attorney fees after trial, the normal
    standard of review is abuse of discretion. However, de novo review of such a trial court
    order is warranted where the determination of whether the criteria for an award of
    attorney fees [has] been satisfied [pursuant] to statutory construction and a question of
    law.”‟ [Citation.]” (Heritage Pacific Financial, LLC v. Monroy (2013) 
    215 Cal. App. 4th 972
    , 1003.) The “American rule” requires that “unless expressly provided in contract or
    statute, each party to a litigation must pay its own attorney fees. [Citations]” (Serpa v.
    California Surety Investigations, Inc. (2013) 
    215 Cal. App. 4th 695
    , 709.)
    Section 66499.4 provides, “As a part of the obligation guaranteed by the security
    and in addition to the face amount of the security, there shall be included costs and
    reasonable expenses and fees, including reasonable attorneys‟ fees, incurred by the local
    agency in successfully enforcing the obligation secured.” (Italics added.) Likewise, as
    mirrored in the bonds issued in this case, the language required by section 66499.2
    provides, “that the surety will pay the same in an amount not exceeding the amount
    hereinabove set forth, and also in case suit is brought upon this bond, will pay, in addition
    to the face amount thereof, costs and reasonable expenses and fees, including reasonable
    attorney‟s fees, incurred by county (or city) in successfully enforcing this obligation, to
    be awarded and fixed by the court, and to be taxed as costs and to be included in the
    judgment therein rendered.” Since, Nissho is not a local agency or municipality, it
    20
    cannot recover attorney fees according to the Subdivision Map Act pursuant to which the
    bonds and SIA were executed in the instant case.
    Nonetheless, Nissho argues it is entitled to an award of attorney fees pursuant to
    former Civil Code section 3250, which provided, “An action on the payment bond may
    be maintained separately from and without the filing of an action against the public entity
    by whom the contract was awarded or any officer thereof. In any action, the court shall
    award to the prevailing party a reasonable attorney‟s fee, to be taxed as costs.” (Since
    renumbered Civ. Code, § 9564 [eff. July 1, 2012].) Former Civil Code section 3250 was
    part of former Title 15 which required a payment bond when a contractor was “awarded a
    contract by a public entity.” (Former Civ. Code, § 3247, subd. (a)) “„Public work‟
    means any work of improvement contracted for by a public entity.” (Former Civ. Code,
    § 3100.)
    A “„Public entity‟ means the state, Regents of the University of California, a
    county, city, district, public authority, public agency, and any other political subdivision
    or public corporation in the state.” (Former Civ. Code, § 3099.) Public works projects
    require a bond in an amount “not less than one hundred percent of the total amount
    payable by the terms of the contract.” (Former Civ. Code, § 3248, subd. (a).)
    We agree with the trial court‟s tentative determination that “the evidence is
    insufficient to establish that these were public works payment bonds. The fact that the
    outer perimeter (the landscaping) of the subdivision may some day [sic] come under the
    management of . . . City . . . as to maintenance, cannot alter the status existing at the time
    the agreement was signed. There appears to be no other basis for awarding attorney
    21
    fees.” Indeed, Fuller testified the bonds issued in the Avalon project were, “not bonds
    associated with public work projects.” Public works projects would have required the
    payment of prevailing wages. It was Suncal, not City‟s, determination to landscape the
    offsite areas so they would match the landscaping of the on-site areas. City did not
    require payment of prevailing wages on the offsite landscape work. However, the
    amounts calculated from contractor estimates were doubled for purposes of specifying
    the amount of the bonds in case the City ended up contracting for the work itself upon
    Suncal‟s default. Only in such circumstances where City itself was directly contracting
    for the work would it have become a public works project requiring the payment of
    prevailing wages. Thus, Nissho was not entitled to recover attorney fees under former
    Civil Code section 3250 because it was not engaged in a public works project.
    Nissho exposits two cases in support of its proposition that its offsite work
    qualified as public works projects entitling it to attorney fees. In Granite Construction
    Co. v. American Motorists Ins. Co. (1994) 
    29 Cal. App. 4th 658
     (Granite), a sub-
    subcontractor in a new subdivision performed work for which it was not paid. The
    original contractor and subcontractor filed for bankruptcy. The surety refused payment.
    The sub-subcontractor filed suit against the surety and won a motion for summary
    judgment and award of attorney fees. (Id. at p. 661.) The surety appealed, contending
    the sub-subcontractor had not timely filed a requisite public works preliminary bond
    notice and was not entitled to attorney fees. (Id. at pp. 661-662.) The court of appeal
    affirmed the trial court‟s judgment. (Id. at p. 662.)
    22
    We find Granite distinguishable for several reasons. First, Granite fails to
    establish the factual predicate for determination in this case as to whether the streets
    paved and sealed by the sub-subcontractor were on-site or offsite improvements and
    whether they were required by the municipality. In fact, the surety‟s argument that the
    sub-subcontractor failed to timely serve a public works preliminary bond notice assumes
    the project was a public work required by the municipality. This differs from the instant
    case in which Suncal required the offsite landscaping, and no public works preliminary
    bond notice was apparently required. Second, the Granite court indicated it was limiting
    its analysis to the bond‟s provision for attorney fees. (Granite, supra, 29 Cal.App.4th at
    p. 667, fn. 7.) However, that provision, like the ones in the bonds at issue in this case,
    limited attorney fees to the municipality. (Id. at p. 668.) Thus, Granite did not abide by
    its own analytical framework.
    Third, Granite provided no analysis of the competing statutory provisions for
    attorney fees with respect to subdivision improvements; thus, there was no indication as
    to whether the project at issue, like Avalon, would come within the purview of the
    Subdivision Map Act, which does not provide a statutory basis for attorney fees for
    subcontractors. Fourth, the surety in Granite did not contest the categorization of the
    sub-subcontractor‟s work as a public work and did not challenge its entitlement to
    attorney fees; rather, the surety challenged only the timeliness of sub-subcontractor‟s
    service of the public works preliminary bond notice and its entitlement to attorney fees
    prior to initiation of suit against the surety. Thus, because the court did not consider
    whether the sub-subcontractor‟s performance was a public work or whether it was
    23
    entitled to attorney fees after initiation of the suit, its holding is, at best, weak dictum for
    the proposition that subcontractors are always entitled to attorney fees upon successful
    suit against a surety.
    In California Paving & Grading Co., Inc. v. Lincoln General Ins. Co. (2012) 
    206 Cal. App. 4th 36
     (California Paving), the developer entered into a SIA with a municipality
    that required, as a condition of its approval, the developer install all public improvements
    required by the final map. The City required a 50 percent L&M bond for the public
    improvements. The developer contracted with a general contractor for construction of
    the improvements. (Id. at p. 38.) The general contractor subcontracted for the paving
    and asphalt work. The subcontractor performed the work but was never paid. The
    subcontractor filed suit against the developer and the general contractor, but both filed for
    bankruptcy. The subcontractor then filed suit against the surety. (Id. at p. 39.)
    The surety demurred contending the subcontractor had failed to file suit within the
    statutory timeframe. (California Paving, supra, 206 Cal.App.4th at pp. 39-40.) The
    subcontractor countered that, “the improvements for which the bond was issued are
    subdivision improvements, not a public work within the meaning of the Civil Code
    sections. Therefore, the payment bond is not a public works payment bond and the
    statute of limitations set forth in [former Civil Code] section 3249 does not apply to this
    action.” The trial court sustained the demurrer. (Id. at p. 40.)
    The appellate court reversed, holding the “subdivision improvement work
    constituted a public work within the meaning of [Civil Code] section 3100 because it
    constituted a „work of improvement contracted for by a public entity.‟” (California
    24
    Paving, supra, 206 Cal.App.4th at p. 43.) Indeed, the SIA and contract between the City
    and the developer “expressly required [the developer], at its „own cost and expense, to
    construct and install all public improvements required in and adjoining and covered by
    the final map.‟” (Ibid.) The general contractor then contracted with the subcontractor
    “„to furnish labor, services, equipment and materials required pursuant to the prime
    contract for the construction of the PUBLIC IMPROVEMENTS.‟” (Ibid.)
    Nissho fails to cite any provision in either the SIA or the contracts between it and
    Suncal where any of the contracted work was designated as a “public improvement.”
    This is a dispositive difference between the instant case and California Paving where the
    words “public improvements” in the various contracts and agreements were emphasized.
    Moreover, here, Suncal and City did not enter into any direct contract with one another,
    unlike in California Paving. Thus, City was not a party to any construction contract
    executed by Suncal, the general contractor, or Nissho. Finally, unlike in California
    Paving with respect to the street paving and asphalt work, City did not require the offsite
    landscaping performed by Nissho as a condition for approval of the SIA. Rather, Suncal
    proposed the offsite landscaping to which City acquiesced. Therefore, the offsite
    landscaping was not a public works improvement and Nissho was not entitled to an
    award of attorney fees.
    DISPOSITION
    The judgment awarding Nissho $1,041,148.55 plus costs and interest from January
    2008 is reversed. The matter is remanded with directions to the trial court to determine
    what amount of damages Nissho may recover up to the penal limit of $566,200 on the
    25
    Offsite Bond. The trial court is further directed to determine whether Nissho may
    recover costs and interest if the inclusion of such further costs exceeds the penal amount
    of the Offsite Bond. The trial court‟s judgment denying Nissho‟s motion for attorney
    fees is affirmed. Defendant and appellant Bond Safeguard Insurance Company is
    awarded its costs on appeal.
    CERTIFIED FOR PUBLICATION
    MILLER
    J.
    We concur:
    RAMIREZ
    P. J.
    McKINSTER
    J.
    26