Garcia Juarez Construction v. Monte Vista Water Dist. CA4/2 ( 2014 )


Menu:
  • Filed 1/14/14 Garcia Juarez Construction v. Monte Vista Water Dist. CA4/2
    NOT TO BE PUBLISHED IN OFFICIAL REPORTS
    California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
    publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication
    or ordered published for purposes of rule 8.1115.
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    FOURTH APPELLATE DISTRICT
    DIVISION TWO
    GARCIA JUAREZ CONSTRUCTION, INC.,
    Plaintiff and Appellant,                                            E054324
    v.                                                                           (Super.Ct.No. CIVRS1004326)
    MONTE VISTA WATER DISTRICT,                                                  OPINION
    Defendant and Respondent.
    APPEAL from the Superior Court of San Bernardino County. Barry L. Plotkin,
    Judge. (Retired judge of the San Bernardino Super. Ct. assigned by the Chief Justice
    pursuant to art. VI, § 6 of the Cal. Const.) Affirmed.
    Felahy Law Group, Allen B. Felahy and Oscar Ramirez for Plaintiff and
    Appellant.
    Robertson & Associates, Robert Nation and Alexander Robertson IV for
    Defendant and Respondent.
    1
    Garcia Juarez Construction, Inc., appeals from a judgment entered in favor of
    Monte Vista Water District following the grant of the water district’s motion for
    summary judgment.
    We hold that under the controlling authority, the parties’ moving and opposition
    papers establish that Garcia Juarez Construction (hereafter Garcia Juarez) failed to show
    the existence of a triable issue of material fact. Accordingly, we will affirm the
    judgment.
    BACKGROUND
    Monte Vista Water District (hereafter the water district) solicited bids for
    construction of a pipeline and a pressure relief station in the City of Montclair. Garcia
    Juarez submitted a bid for $311,800 and was awarded the contract for that amount, plus
    additional compensation due to changed conditions and/or extra work performed, if any.
    Garcia Juarez based its bid on the understanding that it would be permitted to store its
    equipment on site while it was engaged in work on the project. It alleged in its complaint
    that this is the industry standard.
    The contract executed by the parties required Garcia Juarez to obtain an
    encroachment permit from the City of Montclair. After the contract was executed, Garcia
    Juarez obtained the permit and learned that a term of the permit prohibited a contractor
    from storing its equipment on site, thus requiring it to mobilize and demobilize its
    equipment daily. Garcia Juarez notified the water district and requested extra
    compensation to cover the cost of doing so. The water district denied the request. The
    additional cost to Garcia Juarez was $66,671.71.
    2
    Garcia Juarez filed a claim for the additional compensation pursuant to
    Government Code section 910. The claim was denied, and Garcia Juarez filed a
    complaint for breach of contract and breach of warranty.
    The water district filed an answer to the complaint. Thereafter, it filed a motion
    for summary judgment. Garcia Juarez filed opposition. After hearing argument, the
    court granted the motion. Judgment was entered on July 1, 2011, and Garcia Juarez filed
    a timely notice of appeal on August 5, 2011.
    DISCUSSION
    SUMMARY JUDGMENT WAS PROPERLY GRANTED
    Standard of Review
    A defendant moving for summary judgment must show that one or more elements
    of a cause of action cannot be established, or that there is a complete defense to that cause
    of action. Once the defendant has met that burden, the burden shifts to the plaintiff to
    show that a triable issue of one or more material facts exists as to that cause of action or
    as to a defense to the cause of action. The plaintiff must set forth specific facts showing
    that a triable issue of material fact exists.1 (Code Civ. Proc., § 437c, subd. (p)(2).)
    We review an order granting summary judgment de novo. In performing our de
    novo review, we must view the evidence in a light favorable to the defendant as the
    losing party, liberally construing its evidentiary submission while strictly scrutinizing the
    plaintiff’s showing, and resolving any evidentiary doubts or ambiguities in the
    1 Garcia Juarez does not deny that the water district made a sufficient showing to
    cause the burden to shift to it.
    3
    defendant’s favor. (Saelzler v. Advanced Group 400 (2001) 
    25 Cal. 4th 763
    , 768-769.)
    Here, we conclude that the undisputed facts defeat both causes of action and that Garcia
    Juarez has not demonstrated the existence of a triable issue of material fact.
    Summary Judgment Was Properly Granted
    Garcia Juarez’s theory for both causes of action was that the water district had a
    duty to disclose that daily mobilization and demobilization would be required, but that it
    either intentionally failed to disclose that information or actively concealed it in order to
    induce lower bids. It contended in its opposition to the summary judgment motion that
    because the industry standard, as reflected in the Standard Specifications for Public
    Works Construction, generally referred to as the “Greenbook,” is that daily mobilization
    and demobilization is not required, the water district had a duty to inform bidders
    explicitly that under this contract, daily mobilization and demobilization would be
    required.
    Shortly before the water district filed its motion for summary judgment, the
    California Supreme Court issued its opinion in Los Angeles Unified School Dist. v. Great
    American Ins. Co. (2010) 
    49 Cal. 4th 739
    .2 In that case, the court addressed the question
    presented here: Under what circumstances may a contractor on a public works contract
    recover damages when the plans and specifications of a project are correct, but the
    2 The parties refer to this case as “Hayward” after the second defendant in that
    case, Hayward Construction Company. (See Los Angeles Unified School Dist. v. Great
    American Ins. 
    Co., supra
    , 
    49 Cal. 4th 739
    .) We shall short cite it as LAUSD v. Great
    American.
    4
    contracting public authority failed to disclose information in its possession that materially
    affected the cost of performance? (Id. at p. 744.)
    The court analyzed conflicting intermediate court opinions and concluded that a
    contractor “may be entitled to relief for a public entity’s nondisclosure in the following
    limited circumstances: (1) the contractor submitted its bid or undertook to perform
    without material information that affected performance costs; (2) the public entity was in
    possession of the information and was aware the contractor had no knowledge of, nor any
    reason to obtain, such information; (3) any contract specifications or other information
    furnished by the public entity to the contractor misled the contractor or did not put it on
    notice to inquire; and (4) the public entity failed to provide the relevant information. The
    circumstances affecting recovery may include, but are not limited to, positive warranties
    or disclaimers made by either party, the information provided by the plans and
    specifications and related documents, the difficulty of detecting the condition in question,
    any time constraints the public entity imposed on proposed bidders, and any unwarranted
    assumptions made by the contractor. The public entity may not be held liable for failing
    to disclose information a reasonable contractor in like circumstances would or should
    have discovered on its own, but may be found liable when the totality of the
    circumstances is such that the public entity knows, or has reason to know, a responsible
    contractor acting diligently would be unlikely to discover the condition that materially
    increased the cost of performance.” (LAUSD v. Great 
    American, supra
    , 49 Cal.4th at
    pp. 753-754, italics added.)
    5
    Garcia Juarez does not contend that the contract or the bidding documents
    affirmatively represented or suggested that it would be able to store its equipment at the
    site, nor does it point to any evidence that any representative of the water district told it
    that overnight storage would be permitted. Rather, it contends that because the bidding
    instructions provided by the water district did not instruct bidders to “look beyond the
    contract documents to familiarize themselves with all the local ordinances and
    requirements,” it did not obtain information concerning the city’s permit conditions until
    after it had been awarded the contract.
    Contrary to Garcia Juarez’s contentions, the bidding and contract documents
    unquestionably informed bidders that they were required to familiarize themselves with
    the permit requirements of the City of Montclair and to obtain all required permits:
    The Summary of the Work states, “The contractor shall comply with the all [sic]
    construction requirements of the Monte Vista Water District. Bonding fees and [the]
    inspection permit fee required by the district shall be paid by the contractor and shall
    include: [¶] 1. City of Montclair encroachment permit. . . .”3
    The General Provisions states, “Observing Ordinances. The contractor shall
    observe all the laws and ordinances of [the] city, county or state, where applicable, in
    relation to the obstruction of streets and driveways . . . .” The document further states,
    “The contractor shall comply with all permit requirements of the city and all other
    involved agencies, and all costs therefor shall be included in the prices bid.” The
    3 We have normalized the capitalization in the quoted portions of the contract and
    bidding documents. We have added italics for emphasis.
    6
    bidding instructions state, “Before submitting a bid, each bidder must (a) examine the
    contract documents thoroughly . . . (c) familiarize itself with federal, state and local laws,
    ordinance[s], rules and regulations that may in any manner affect cost, progress or
    performance of the work, [and] (d) study and carefully correlate bidder’s observations
    with the requirements of the contract document.”
    Both the bid form and the contract executed by Garcia Juarez contained an
    acknowledgement that it had familiarized itself with all laws and regulations “that in any
    manner may affect cost, progress, performance or furnishing the work.”
    Garcia Juarez admitted that the city’s General Permit Condition and Utility Trench
    Specifications provides, “There shall be no equipment or materials stored or stockpiled
    in [the] street right-of-way. Equipment and materials shall be removed from the street
    right-of-way when not in use and at the end of each working day, except as approved by
    the Department.” The encroachment permit apparently contains the same requirement.4
    Garcia Juarez admitted that the city’s permit requirements were readily available
    both at the city’s permit desk and on its Web site, but admitted both in its complaint and
    in its response to the water district’s statement of undisputed facts that it did not obtain
    the permit information until after its bid had been accepted and it had entered into the
    contract with the water district.
    These undisputed facts establish that Garcia Juarez was put on notice to ascertain
    the city’s permit requirements, to determine whether those requirements would affect the
    4 Neither party has cited to a page in the record where the encroachment permit
    appears, and we have not discovered it.
    7
    cost of its performance of the contract, and to incorporate them into the price it bid on the
    contract.
    Garcia Juarez contends, however, that triable issues of fact exist as to the
    misleading nature of the contract and bidding documents for several reasons. First, it
    asserts that the water district knew that it is the standard in the industry not to obtain a
    permit before being awarded the contract. Nevertheless, it admits that it could have
    obtained the city’s permit requirements before submitting its bid. It also appears to
    contend that it reasonably assumed that the Greenbook, which states the industry standard
    is not to require daily mobilization and demobilization, would govern the contract.
    However, the Conditions of the Contract provides that “permits from other agencies as
    may be required by law” would take precedence over the Greenbook in resolving
    conflicts resulting from “errors, discrepancies, ambiguities, or inconsistencies” in any of
    the contract documents. Finally, Garcia Juarez contends that the contract documents
    were intentionally misleading because the permit requirements of the California
    Department of Transportation were physically included in the document but the city’s
    permit requirements were not provided. This fact is not sufficient to raise a genuine
    triable issue of fact, however, because the bidding and contract documents repeatedly
    alerted bidders that additional permits might apply and expressly informed bidders that
    they were required to obtain the city’s encroachment permit.
    A reasonable contractor acting diligently would have obtained the readily
    available information as to the city’s permit requirements. Because Garcia Juarez failed
    to do so, its own negligence, rather than any error or omission by the water district, was
    8
    responsible for the additional expenses it incurred in performing its obligations under the
    contract. Accordingly, its two causes of action fail as a matter of law, pursuant to
    LAUSD v. Great 
    American, supra
    , 49 Cal.4th at pages 753 through 754.
    Garcia Juarez contends, however, that LAUSD v. Great 
    American, supra
    , 
    49 Cal. 4th 739
    , is inapposite because in that case, the court “struck a balance between two
    innocent parties.” It states, “There was no finding in [that case] that the public entity had
    knowledge of the condition encountered by the contractor for which additional payment
    was requested.” It asserts that in this case, the water district “had full knowledge of the
    restrictions which caused additional cost to” Garcia Juarez and intentionally failed to
    disclose that information.
    We disagree that LAUSD v. Great 
    American, supra
    , 
    49 Cal. 4th 739
    , applies only if
    both parties are ignorant of the condition which adversely affected the contractor or if
    both are “innocent” parties. As the court pointed out, an action for intentional or
    negligent misrepresentation cannot be maintained against a public entity, and a contractor
    which asserts that the public entity mislead it into making an inappropriately low bid has
    a cause of action only for breach of contract. (Id. at p. 748 & fn. 3, citing and discussing
    Gov. Code, § 818.8 [governmental immunity for misrepresentation].) Accordingly, the
    public entity’s intent to conceal material facts, or its lack of intent to do so, is irrelevant,
    as is its status as an “innocent” party. (LAUSD v. Great American, at p. 745 [contractor
    is entitled to recover regardless of any showing of a fraudulent intent to conceal material
    facts].) As explained by another court, “Under general principles of contract and tort
    law, a party who conceals or fails to disclose material information to another is liable for
    9
    fraud. In the public construction contract context, however, the conduct of a public
    agency which would otherwise amount to a tortuous [sic] misrepresentation is treated as a
    breach of contract. The underlying theory is that providing misleading plans and
    specifications constitutes a breach of the implied warranty of correctness. [Citation.]”
    (Howard Contracting, Inc. v. G.A. MacDonald Construction Co. (1998) 
    71 Cal. App. 4th 38
    , 55 (Howard).) Accordingly, the water district’s intent in omitting an express
    statement that overnight storage of the equipment would not be permitted is irrelevant.5
    We reject Garcia Juarez’s contention that the controlling authority in this case is
    not LAUSD v. Great American but 
    Howard, supra
    , 
    71 Cal. App. 4th 38
    . The portion of
    Howard which deals with concealment of material facts by a public agency in soliciting
    bids for a public works project is consistent with the holding in LAUSD v. Great
    American that a public entity “may not be held liable for failing to disclose information a
    reasonable contractor in like circumstances would or should have discovered on its own,
    but may be found liable when the totality of the circumstances is such that the public
    entity knows, or has reason to know, a responsible contractor acting diligently would be
    unlikely to discover the condition that materially increased the cost of performance.”
    (LAUSD v. Great 
    American, supra
    , 49 Cal.4th at p. 754.)
    5  For this reason, we also reject Garcia Juarez’s contention that there is a triable
    material issue of fact as to the water district’s “affirmative fraudulent intent to conceal”
    this information. We also reject Garcia Juarez’s assertion that the test formulated in
    LAUSD v. Great American “is framed as an alternative to having to prove an affirmative
    fraudulent intent to conceal.” It is not an alternative, because, as the opinion makes clear,
    fraudulent intent is irrelevant in a breach of contract action. (See LAUSD v. Great
    
    American, supra
    , 49 Cal.4th at pp. 745, 748 & fn. 3; see also 
    Howard, supra
    , 71
    Cal.App.4th at p. 50.)
    10
    In Howard, the city was found in breach of contract in part because it failed to
    disclose limitations on the project which it anticipated would be required by permits to be
    issued by federal agencies. (
    Howard, supra
    , 71 Cal.App.4th at p. 50.) The city argued
    that the permits disclosed the agencies’ intent to impose restrictions on disposal of
    excavated material and on access to the project, and that if the plaintiff had examined the
    permits, it would have learned of the adverse effect of those restrictions on the cost and
    time required to complete the project. (Id. at p. 55.) The court held, however, that the
    contract “did not specifically direct bidders to examine the permits issued by the
    regulatory agencies.” Moreover, “since no permits were issued until after the bid
    submission date, no permits existed for bidders to review.” (Id. at p. 56, italics added.)
    Finally, the court held, since the city bore responsibility for obtaining the project permits,
    “bidders were reasonably entitled to assume that the [c]ity would inform them of any
    permit requirements or restrictions adversely affecting their ability to perform work on
    the project.” (Ibid.)
    Here, in contrast, bidders were informed that the City of Montclair’s permit
    requirements would apply and that they would need to obtain the city’s encroachment
    permit. They were also informed that any permits required by law would supersede the
    Greenbook if there was a conflict between the two. The information as to the city’s
    permit requirements was readily available. Because the water district gave notice
    sufficient to put bidders on inquiry as to the city’s permit requirements, no bidder could
    claim that it exercised due diligence in formulating its bid if it failed to ascertain the
    impact the city’s permit requirements might have on its performance of the contract.
    11
    We also reject Garcia Juarez’s contention that the water district is “rely[ing] on
    generic disclaimers to insulate itself for its failure to disclose and concealment of the
    conditions.” Garcia Juarez does not explain what it means by “generic disclaimer,” nor
    does it cite any language in the contract or bidding documents which allegedly constitutes
    such a disclaimer. Further, although it cites 
    Howard, supra
    , 
    71 Cal. App. 4th 38
    in this
    context, it does not cite any specific portion of that case which discusses disclaimers. We
    need not consider perfunctory arguments which are not supported either by citation to the
    record or by legal argument and authority. (See People v. Weaver (2001) 
    26 Cal. 4th 876
    ,
    986-987; Duarte v. Chino Community Hospital (1999) 
    72 Cal. App. 4th 849
    , 856 [Fourth
    Dist., Div. Two].) Accordingly, we deem the contention waived.
    DISPOSITION
    The judgment is affirmed. Monte Vista Water District is awarded costs on appeal.
    NOT TO BE PUBLISHED IN OFFICIAL REPORTS
    McKINSTER
    J.
    We concur:
    HOLLENHORST
    Acting P. J.
    RICHLI
    J.
    12
    

Document Info

Docket Number: E054324

Filed Date: 1/14/2014

Precedential Status: Non-Precedential

Modified Date: 4/18/2021