Citizens Advocating for Roblar Rural Quality v. County of Sonoma CA1/5 ( 2014 )


Menu:
  • Filed 5/13/14 Citizens Advocating for Roblar Rural Quality v. County of Sonoma CA1/5
    NOT TO BE PUBLISHED IN OFFICIAL REPORTS
    California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
    publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication
    or ordered published for purposes of rule 8.1115.
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    FIRST APPELLATE DISTRICT
    DIVISION FIVE
    CITIZENS ADVOCATING FOR
    ROBLAR RURAL QUALITY,
    Plaintiff and Respondent,
    v.
    COUNTY OF SONOMA et al.,                                             A136877
    Defendants and Appellants;                                  (Sonoma County
    JOHN BARELLA et al.,                                                 Super. Ct. No. SCV-248943)
    Real Parties in Interest and
    Appellants.
    The County of Sonoma (County) certified a final environmental impact report
    (EIR) and granted necessary land use permits for an aggregate quarry (hereafter Quarry
    or Quarry Project). Citizens Advocating for Roblar Rural Quality (CARRQ), a nonprofit
    corporation, filed a petition for writ of mandate under the California Environmental
    Quality Act (CEQA) (Pub. Resources Code, § 21000 et seq.), challenging the County’s
    approvals. The trial court granted the petition in part, finding that failure to test or study
    potential water quality contamination from a neighboring landfill resulted in factual
    conclusions unsupported by substantial evidence; certain specified environmental
    mitigation measures were inadequate or constituted a prohibited deferral of mitigation;
    and evidence and analysis regarding the impact of widening an access road on an
    adjacent creek was inadequate.
    1
    The Quarry Project’s proponents, real parties in interest John Barella and the
    John E. Barella and Andrea M. Barella Trust (collectively Barella), are joined by the
    County in an appeal from the judgment. Barella contends that in granting the writ, the
    trial court improperly ignored substantial expert evidence, opinions, and studies
    supporting County’s actions and made improper de novo determinations. We reverse.
    I.     BACKGROUND
    On December 4, 2003, Barella submitted its application for the Quarry Project1 to
    the County seeking permits and rezoning for development of a hard rock aggregate mine
    on a 198.7 acre parcel located at 7601 Roblar Road in southern Sonoma County,
    approximately five miles west of the City of Cotati. The Quarry site is east of Roblar
    Road and is bounded to the north by an abandoned County landfill (Landfill). The
    Quarry Project contemplated development of a 65-acre quarry pit with mining and
    processing of approximately 570,000 cubic yards of aggregate material annually.2 The
    County determined that the Quarry Project was subject to the environmental review
    requirements of CEQA and the Sonoma County Permit and Resource Management
    Department prepared and circulated a draft EIR for comment from May to July 2008. A
    public hearing on the draft EIR was held on June 19, 2008. After response to public
    comment, a proposed final EIR was released on October 15, 2009.3 A public hearing on
    the final EIR was held before the County’s planning commission on December 17, 2009.
    As discussed in greater detail post, the North Coast Regional Water Quality Control
    1
    The application (entitled “Roblar Road Quarry Surface Mining and Reclamation
    Plan Application”) was originally submitted in the name of North Bay Construction, Inc,
    an entity owned by Barella.
    2
    The proposed location is designated as a priority site for aggregate production in
    the November 1994 “Sonoma County Aggregate Resources Management Plan and
    Environmental Impact Report,” a document Barella included in his April 26, 2013
    request for judicial notice. The document comprises part of the administrative record in
    this matter and we therefore grant the request. (Evid. Code, § 452.)
    3
    The draft and final EIR’s were prepared for the County by Environmental
    Science Associates and subconsultants including Miller Pacific Engineering Group
    (geology, soils, seismicity) and Balance Hydrologics, Inc. (hydrology, water quality).
    2
    Board (Regional Water Board), as a CEQA responsible agency, submitted a comment
    letter on December 15, 2009, questioning the adequacy of the final EIR’s assessment and
    mitigation of water quality impacts associated with the Landfill’s proximity to the
    Quarry. In response, Barella submitted a revised water management plan to the final
    EIR. The final EIR incorporated these changes, and was further revised to include
    additional mitigation measures. On April 1, 2010, the planning commission took
    additional comment on the proposed final EIR revisions, and voted to recommend that
    Sonoma County Board of Supervisors (Board of Supervisors) certify the final EIR, as
    revised, and approve the Quarry Project with conditions.
    After the initial recommendation to approve the final EIR, further surveys on the
    Quarry Project site found larvae of the California tiger salamander, a protected species
    under state and federal law. Analysis of California tiger salamander impacts and
    mitigation measures were revised and included in recirculated portions of the draft EIR.4
    The recirculated portions of the draft EIR were released for public comment on June 15,
    2010. On July 15, 2010, the planning commission held a public hearing on the
    recirculated portions of the draft EIR and, on September 16, 2010, held a public hearing
    to consider the associated responses to comments and the final EIR for the Quarry
    Project. The planning commission again recommended (unanimously) that the Board of
    Supervisors certify the final EIR, adopt a statement of overriding considerations, and
    approve the Quarry Project. The final EIR included the draft EIR and associated
    response to comments document, the “Revised Response to Comment HYD-1” and
    revised water management plan, and the recirculated portions of the draft EIR and
    associated response to comments document.
    At an October 19, 2010 public hearing, the Board of Supervisors received a staff
    report and accepted oral and written testimony. The Board of Supervisors then closed the
    public hearing, and tentatively approved the final EIR and what was designated as
    4
    The recirculated portions of the draft EIR also included an updated analysis of
    greenhouse gas emissions and mitigation measures addressing thresholds of significance
    recently adopted by the Bay Area Air Quality Management District.
    3
    “Modified Alternative 2” for the Quarry Project. The Board of Supervisors directed staff
    to prepare findings consistent with the board’s determinations, and continued the matter
    to the following December for final action. On December 14, 2010, the Board of
    Supervisors voted to certify the final EIR (Resolution No. 10-0902), as well as voted to
    adopt CEQA findings and a statement of overriding considerations, adopt a mitigation
    monitoring and reporting program and approve Modified Alternative 2 (Resolution No.
    10-0903).5
    On January 13, 2011, CARRQ filed the instant petition for writ of mandate
    challenging the Quarry Project approvals. After certification of the administrative record
    and briefing, the superior court issued a tentative ruling granting the writ in part on
    June 20, 2012. Oral argument was heard on June 22, and the court filed its statement of
    decision on August 2. The court found the final EIR deficient, and ordered the Quarry
    Project approvals vacated: “(1) On the basis that the failure to test or study the
    neighboring Landfill water quality for contamination has ‘. . . reached factual conclusions
    unsupported by substantial evidence.’ [Public Resources Code, §] 21168.5; [¶] (2) On
    the basis that the project description of the mitigation preserve is inadequate and, in some
    measure, constitutes a prohibited deferral of mitigation; [¶] (3) On the basis that the EIR
    fails to provide adequate analysis of the impacts or efficacy of the mitigation preserve;
    and [¶] (4) On the basis that the evidence and analysis regarding the impact of widening
    Roblar Road on Americano Creek and related mitigation measures is inadequate.” The
    court denied the petition on all other points.
    After responding to Barella’s objections and requests for clarification, the court
    entered judgment on October 10, 2012, and a peremptory writ of mandate issued on that
    date. This timely appeal followed.
    5
    The Board also approved entitlements specific to the Quarry Project, including a
    zone change to add a mineral resources overlay zone to the site, a use permit with a 20-
    year term for mining and recycling of asphalt, concrete and other materials, and a
    reclamation plan for the Quarry site.
    4
    II.    DISCUSSION
    A.     CEQA Review Standard
    “ ‘The basic purposes of CEQA are to: [¶] (1) Inform governmental decision
    makers and the public about the potential, significant environmental effects of proposed
    activities. [¶] (2) Identify ways that environmental damage can be avoided or
    significantly reduced. [¶] (3) Prevent significant, avoidable damage to the environment
    by requiring changes in projects through the use of alternatives or mitigation measures
    when the governmental agency finds the changes to be feasible. [¶] (4) Disclose to the
    public the reasons why a governmental agency approved the project in the manner the
    agency chose if significant environmental effects are involved.’ (Cal. Code Regs., tit. 14,
    § 15002.)[6]” (Tomlinson v. County of Alameda (2012) 
    54 Cal. 4th 281
    , 285–286.)
    CEQA’s purpose is to compel government to make decisions with environmental
    consequences in mind. (Laurel Heights Improvement Assn. v. Regents of University of
    California (1988) 
    47 Cal. 3d 376
    , 393 (Laurel Heights I).)
    “In reviewing an agency’s compliance with CEQA in the course of its legislative
    or quasi-legislative actions, the courts’ inquiry ‘shall extend only to whether there was a
    prejudicial abuse of discretion.’ (Pub. Resources Code, § 21168.5.) Such an abuse is
    established ‘if the agency has not proceeded in a manner required by law or if the
    determination or decision is not supported by substantial evidence.’ [Citations.]”
    (Vineyard Area Citizens for Responsible Growth, Inc. v. City of Rancho Cordova (2007)
    
    40 Cal. 4th 412
    , 426–427, fns. omitted (Vineyard).) “Substantial evidence is defined as
    ‘enough relevant information and reasonable inferences from this information that a fair
    argument can be made to support a conclusion, even though other conclusions might also
    be reached.’ [Citations.]” (Association of Irritated Residents v. County of Madera
    (2003) 
    107 Cal. App. 4th 1383
    , 1391.) Under CEQA, “substantial evidence includes fact,
    6
    Guidelines for implementing CEQA are found under California Code of
    Regulations, title 14, section 15000 et seq.
    5
    a reasonable assumption predicated upon fact, or expert opinion supported by fact.”
    (Pub. Resources Code, § 21080, subd. (e)(1).)
    Our task is essentially identical to that of the trial court. (American Canyon
    Community United for Responsible Growth v. City of American Canyon (2006)
    
    145 Cal. App. 4th 1062
    , 1070.) Accordingly, “we review the agency’s actions directly and
    are not bound by the trial court’s conclusions. [Citations.]” (Friends of Lagoon Valley v.
    City of Vacaville (2007) 
    154 Cal. App. 4th 807
    , 816–817.) In that sense appellate judicial
    review under CEQA is de novo. 
    (Vineyard, supra
    , 40 Cal.4th at p. 427.) We must
    therefore independently determine whether the administrative record demonstrates any
    legal error by the County and whether it contains substantial evidence to support the
    County’s factual determinations. (Ibid.)
    A reviewing court “shall not exercise its independent judgment on the evidence
    but shall only determine whether the [agency’s] act or decision is supported by
    substantial evidence in light of the whole record.” (Pub. Resources Code, § 21168.) In
    determining whether an agency has prejudicially abused its discretion, “ ‘the power of the
    appellate court begins and ends with a determination as to whether there is any
    substantial evidence, contradicted or uncontradicted, which will support the [agency’s
    decision].’ ” (Western States Petroleum Assn. v. Superior Court (1995) 
    9 Cal. 4th 559
    ,
    571.) Our review for substantial evidence applies a deferential standard that is satisfied if
    “the record contains relevant information that a reasonable mind might accept as
    sufficient to support the conclusion reached.” (Great Oaks Water Co. v. Santa Clara
    Valley Water Dist. (2009) 
    170 Cal. App. 4th 956
    , 968.) We indulge all reasonable
    inferences from the evidence that would support the agency’s determinations. If more
    than one inference can be drawn from the evidence, “ ‘a reviewing court is without power
    to substitute its deductions’ ” for those of the agency. (Western States Petroleum Assn.,
    at p. 571.) “In reviewing for substantial evidence, the reviewing court ‘may not set aside
    an agency’s [decision] on the ground that an opposite conclusion would have been
    equally or more reasonable,’ for, on factual questions, our task ‘is not to weigh
    6
    conflicting evidence and determine who has the better argument.’ [Citation.]”
    
    (Vineyard, supra
    , 40 Cal.4th, at p. 435.)
    B.     Groundwater Issues
    CARRQ challenges the adequacy of the final EIR’s analysis of Quarry operations
    on groundwater flows, and possible release of contaminants from the adjacent Landfill.
    It contends that the final EIR acknowledged the risk that contaminants or pollutants from
    the Landfill could seep into the Quarry site as a result of mining operations, but that the
    County refused to conduct or allow testing of the Landfill to determine and disclose the
    risk posed to regional water quality.7 As a consequence, CARRQ argues, the County’s
    finding that the risks to groundwater would be less than significant lack substantial
    evidence support. “Without testing and associated analysis, the County was unable to
    understand the magnitude of the impact and to determine if there were feasible mitigation
    measures that could reduce this impact to an acceptable level.” CARRQ also argues that
    failure to test for contaminants in the Landfill resulted in the EIR failing to adequately
    describe, in good faith, the environmental setting of the Quarry Project as required by
    CEQA.
    Barella responds that CARRQ mischaracterizes the record and ignores, and fails to
    cite, evidence in support of the County’s findings. The burden is on the party challenging
    an EIR to show it is inadequate, and to affirmatively show no substantial evidence in the
    record supported the agency’s findings. (California Native Plant Society v. City of
    7
    The draft EIR also evaluated potential impacts of blasting operations from
    Quarry operations on the surrounding areas, including the Landfill. A hydrologist
    testified before the planning commission that, given the nature and density of subsurface
    bedrock fractures, blasting “would not influence the [underground water] flow regime . . .
    much farther than probably 20 or 30 feet from where the blast was, so from the edge of
    the Quarry, let’s say 20, 30 feet out, maybe even 50 feet. That’s still a short distance
    compared to the distance between the Quarry and the landfill itself and to Americano
    Creek as well.” The draft EIR concluded that proposed blasting would not impact the
    integrity of the landfill cells, landfill infrastructure, or the surrounding ground on the
    landfill property, and consequently would not in and of itself create or increase potential
    for movement of potential contaminants from the landfill cells offsite. CARRQ does not
    specifically challenge this finding on appeal.
    7
    Rancho Cordova (2009) 
    172 Cal. App. 4th 603
    , 626 (California Native Plant Society).)
    “As with all substantial evidence challenges, [a party] challenging an EIR for insufficient
    evidence must lay out the evidence favorable to the other side and show why it is lacking.
    Failure to do so is fatal. A reviewing court will not independently review the record to
    make up for [the challenging party’s] failure to carry his burden.” (Defend the Bay v.
    City of Irvine (2004) 
    119 Cal. App. 4th 1261
    , 1266.)
    The draft EIR found: “Excavation of the proposed quarry could cause
    groundwater which may contain contaminants to enter the quarry walls as seepage. In
    addition, groundwater from the on-site production wells proposed to be used for quarry
    operations may contain contaminants. Contaminated water could degrade water quality
    in Ranch Tributary and Americano Creek if not properly contained and treated prior to
    discharge. This would be a potentially significant impact.” In its approvals, the County
    found that the potential impact would be mitigated to a less than significant level by
    incorporation of Barella’s revised water management plan, implementation of specified
    mitigation measures, and implementation of an enhanced groundwater monitoring well
    system. The trial court agreed with CARRQ that the final EIR was rendered inadequate
    by a failure to test or study Landfill water quality and whether Quarry operations would
    change flow patterns and cause potentially contaminated water to flow from the Landfill
    to the Quarry and into waterways.
    Our analysis begins with the presumption that the County’s decision is correct,
    and CARRQ bears the burden of proving the contrary. (San Diego Citizenry Group v.
    County of San Diego (2013) 
    219 Cal. App. 4th 1
    , 11–12.) We conclude that substantial
    evidence supports the final EIR finding.
    1.     Landfill Conditions
    The Landfill is located adjacent to and north of the Quarry site. The closest waste
    cell in the Landfill is approximately 400 feet away from the Quarry site. The Landfill
    was operated as an open burn pit from 1956 through 1967. Between 1967 and 1971, it
    was operated as a sanitary landfill by Sonoma County, using a landfill technique known
    as trench filling. During the time the Landfill site was operated as a burn pit and sanitary
    8
    landfill, it received primarily residential and commercial waste, along with minor
    agricultural waste. The City of Santa Rosa reopened the landfill in 1972 for disposal of
    demolition debris along the top of the lowest waste disposal unit, and then covered it with
    soil. Operations were terminated in 1973 and no additional waste has been accepted
    since that time, but extensive grading, drainage improvements, and revegetation have
    occurred at the Landfill site.
    Three main pads in the Landfill step up the slope from Roblar Road. The lowest
    and northernmost pad contains two waste cells and is situated at approximately 200 feet
    above sea level. A middle pad containing a single waste cell is located at approximately
    270 feet above sea level. The upper and southernmost pad contains a single waste cell
    and is at approximately 350 feet above sea level. The Landfill is unlined and leachate8
    which percolates through the site is removed from the Landfill via an onsite leachate
    collection system, and transported to an offsite treatment plant. Leachate from the
    Landfill is routinely tested for potential hazardous constituents. Testing reports indicated
    that the leachate does not contain chemical constituents at levels considered hazardous
    waste under title 27 of the California Code of Regulations.
    In 1991, three groundwater monitoring wells (R-l, R-2 & R-3) were installed on
    Landfill property as part of the County’s solid waste water quality assessment test
    (SWAT) for the Landfill.9 A SWAT monitoring program for the Landfill focused on
    potential migration pathways for surface water and groundwater, and included sampling
    and analysis for halogenated and volatile organic compounds, pesticides, PCB’s, and
    metals. A 1992 report to the County showed that toluene was the only volatile organic
    compound detected (in monitoring well R-l) at a concentration slightly above the
    laboratory method detection limit. Toluene was not detected again in the subsequent
    8
    Leachate is a “liquid formed by the drainage of liquids from waste or by the
    percolation or flow of liquid through waste. It includes any constituents extracted from
    the waste and dissolved or suspended in the fluid.” (Cal. Code Regs., tit. 27, § 20164.)
    9
    Testing of surface water quality at the Landfill is performed by the Sonoma
    County Department of Transportation and Public Works, and quarterly reports are
    submitted to the Regional Water Board.
    9
    sampling events under the SWAT. The report concluded that “ ‘there has been little or
    no impact to water quality and the environment from past landfill operations, and there is
    no indication of leachate leaving the site boundaries.’ ” The sampling and analysis done
    between 2004 and 2008 confirmed the presence in well R-1 of low, dissolved
    concentrations of a volatile organic compound (cis-l,2-Dichloroethene), a chemical
    commonly found in chemical cleaning products, and the organic compound vinyl
    chloride. While the levels of each were at or slightly over the laboratory method
    detection limits, they were again in all cases below applicable state and federal water
    quality objectives for drinking water.
    The most recent analysis of groundwater chemistry data collected from the
    Landfill monitoring wells was contained in a July 2009 groundwater monitoring report
    prepared for the County by Pacific Geoscience. The data was compared against primary
    and secondary maximum contaminant levels (MCL’s) set by both the United States
    Environmental Protection Agency and the State of California. None of the samples
    exceeded the available MCL’s for general chemistry. Groundwater collected from
    monitoring well R-l met or exceeded primary MCL’s set by the State of California for
    chromium and secondary MCL’s for iron and manganese, and as previously noted, was
    negative for volatile organic compounds with the exception of cis-l,2-Dichloroethene.
    Groundwater from well R-2 exceeded state secondary MCL’s for iron and manganese.
    The samples from wells R-l and R-2 were found to be “not dissimilar to a typical
    drinking water in terms of its major ions.” Metals data from well R-3 in some samples,
    however, exceeded primary or secondary MCL’s for arsenic, barium, chromium, iron,
    manganese, mercury and nickel.
    2.     Existing Quarry Project Site Conditions
    In January 2007, during geotechnical analysis of the Quarry Project, three new
    groundwater monitoring wells (MW-l, MW-2 & MW-3) were installed roughly in line
    between the Landfill and proposed Quarry footprint. The new wells served as “sentry
    wells” and were located to serve as boundary monitoring points to monitor groundwater
    quality and detect whether any pollutants were migrating from the Landfill to the Quarry
    10
    site. Five quarterly monitoring reports were completed for the County by consultant
    Advanced GeoEnvironmental, Inc. from February 2007 through March 2008. The
    groundwater monitoring program included sampling and analysis of groundwater for
    water chemistry (e.g., pH, alkalinity, hardness, and TDS), salts, organochlorine
    pesticides, PCB’s, semivolatile organic compounds, and trace metals. Laboratory
    analysis of samples collected showed low concentrations of volatile organic compounds,
    which were in all cases below applicable state and federal water quality objectives for
    drinking water.
    3.     Migration of Groundwater from the Landfill
    Subsurface exploration determined that the groundwater resides in three different
    geologic zones, and the Landfill and Quarry sites are situated in different watersheds. A
    ridgeline and a hydrogeological divide (the Ranch Tributary watershed divide) exists
    between the Landfill, north of the divide, and the Quarry site, south of the divide. A
    calibrated groundwater flow model was developed for the Quarry site and Landfill by
    consultant Geomega Inc. (Geomega). Results from the groundwater model showed that a
    groundwater divide would consistently be present between all levels of the Landfill and
    the Quarry, preventing groundwater and leachate originating at the Landfill from flowing
    to the Quarry under any scenario, and that under all conditions groundwater beneath the
    Landfill would flow northward towards Americano Creek and not to the Quarry site.10
    Geomega also calculated the result of what it termed a hypothetical “worst case”
    scenario, assuming that groundwater beneath the Landfill could flow to the Quarry site,
    and that groundwater discharging along the entire north side of the Quarry originated
    beneath the Landfill. In that event, groundwater flowing from the lower levels of the
    Landfill (the areas of wells R-1 & R-3), concentrations of metals and volatile organic
    compounds would be diluted below detection limits when reaching the quarry pit and any
    groundwater from the Landfill impacted by leachate “would be acceptable for all
    10
    The draft EIR concluded that the Ranch Tributary watershed divide would shift
    somewhat north of its existing location as a result of Quarry excavation.
    11
    constituents and would be either at background levels or below MCL[’]s provided by
    both [United States Environmental Protection Agency] and the State of California” and
    “would not exceed state and federal drinking water standards.”
    4.     Regional Water Board Comments
    As noted ante, the Regional Water Board submitted comments to the circulated
    final EIR on December 15, 2009. The Regional Water Board expressed concern with two
    significant potential impacts of the Quarry Project.11 The first was with the adequacy of
    mitigation measures for impacts to surface waters, with discharge of excess flows of
    groundwater and storm water. The second concern was the identification of heavy metals
    and other pollutants in groundwater at levels exceeding ground and surface water quality
    objectives. The Regional Water Board said that it was “not convinced by the
    documentation provided that excavation and draining of groundwater will not result in
    the movement of pollutants in the aquifer, thereby causing the degradation of water
    quality.” More specifically, the comment questioned the adequacy of the hydrologic
    investigation of the Landfill site for leachate or groundwater impacts. The comment
    concluded that “the [final EIR] falls short of outlining a clear path to avoid groundwater
    impacts to receiving waters.”
    5.     Barella’s Revised Water Management Plan
    To allow staff response to the comment and to questions by planning
    commissioners following the December 17, 2009 public hearing, further public hearing
    on the final EIR was scheduled for February 4, 2010, and then continued to April 1, 2010.
    After consulting with the County and the Regional Water Board, Barella submitted a
    revised water management plan in March 2010, prepared by CSW/Stuber-Stroeh
    Engineering Group, Inc. and PES Environmental, Inc., and incorporating Geomega’s
    11
    CARRQ cites, inter alia, the letter as evidence that the mitigation measures
    proposed by Barella were inadequate to reduce the environmental impacts to a less than
    significant level. Pointing to evidence of a disagreement with other agencies is not
    enough to carry the burden of showing a lack of substantial evidence to support the City’s
    finding. (California Native Plant 
    Society, supra
    , 172 Cal.App.4th at p. 626.)
    12
    flow modeling. The revised water management plan expanded the management of water
    resources for the project and provided that all precipitation, seepage, and process water
    from the Quarry site would no longer be discharged to surface waters, but would be
    captured and conveyed to sediment control basins for testing, treatment if required, and
    reuse onsite. The onsite treatment system was also modified to address Regional Water
    Board concerns about treatment of metals. Only surface water runoff occurring outside
    the Quarry footprint would be discharged to the adjacent Ranch Tributary or Americano
    Creek, and the revised water management plan would maintain “baseline” surface water
    conditions in the both the Ranch Tributary and Americano Creek. Barella further
    proposed an expanded monitoring well network. A “Revised Master Response HYD-1”
    dealing with hydrology and water quality issues was prepared and incorporated in the
    final EIR. The Regional Water Board found the revised water management plan had
    “largely addressed the Regional Water Board comments.”
    At the continued public hearing on April 1, 2010, the planning commission
    considered the final EIR including the revised water management plan, and heard
    testimony from Geomega hydrologist Bill Linderfelt, Ph.D. The planning commission
    determined that the final EIR, as revised, adequately characterized existing groundwater
    flow and groundwater quality on the Landfill and Quarry sites, appropriately and
    conservatively assessed potential water quality impacts associated with the Quarry
    Project development, and prescribed adequate mitigation to reduce potential impacts to
    less than significant. The planning commission found that the revised water management
    plan assured that the project would not result in degradation of groundwater and surface
    water quality and recommended approval and certification of the final EIR. On
    December 14, 2010, the Board of Supervisors approved certification of the final EIR.
    They found that potential discharge of contaminated water to Ranch Tributary and
    American Creek would be mitigated to a less than significant level by incorporation of
    the revised water management plan and the mitigation measures required by it, and by
    13
    implementation of an enhanced groundwater monitoring well system proposed by
    Barella.12
    6.     Analysis
    CARRQ focuses its challenge to these findings on the failure of the County to
    conduct or permit additional testing within the waste cells of the Landfill. CARRQ
    insists that the final EIR is deficient because “no one knows what type of contaminants
    are in the Landfill and at what concentrations these contaminants may be found within
    the Landfill because the interior of the Landfill has never been tested . . . .”13 (Boldface
    omitted.) But the issue is not what contaminants might be present within the interior of
    the Landfill. Rather, the question is what contaminants are at risk for release from the
    Landfill by virtue of the Quarry Project. “CEQA does not require a lead agency to
    conduct every recommended test and perform all recommended research to evaluate the
    impacts of a proposed project. The fact that additional studies might be helpful does not
    mean that they are required. [Citations.]” (Association of Irritated Residents v. County
    of 
    Madera, supra
    , 107 Cal.App.4th at p. 1396; see also Gray v. County of Madera (2008)
    
    167 Cal. App. 4th 1099
    , 1115 [“additional testing is required only if the initial testing is
    insufficient”].)
    12
    PES Environmental, Inc. (Sept. 27, 2010) Work Plan for Installation of
    Additional Groundwater Monitoring Wells, Roblar Road Quarry.
    13
    As CARRQ notes, the County declined to permit additional testing in the
    Landfill footprint. At the public hearing on October 19, 2010, a member of the Board of
    Supervisors asked staff why further studies and analysis that Barella was apparently
    willing to conduct were not done and included in the final EIR. The response was that:
    “The applicant came to the Department of Public Works seven months ago. I think it was
    in the springtime. After that they met with the regional board and asked if they could
    come on to the landfill and do some analysis. And they had a two- or or three-page
    laundry list of all the things that the regional board staff wanted to look at which was akin
    to the full characterization that we did out at the center of the disposal site, which is an
    active landfill. And we—staff, you know, we’re not really interested in opening up the
    landfill for a full characterization that would cost $700,000 to study and you never know
    what you were going to get with that.”
    14
    The risk identified in the draft and final EIR’s was the possibility of seepage of
    potentially contaminated groundwater from the Landfill into the Quarry site, and the
    concern that “[c]ontaminated water could degrade water quality in Ranch Tributary and
    Americano Creek if not properly contained and treated prior to discharge.” CARRQ
    points to no other identified risk that Landfill contaminants, of whatever nature, would be
    released as a consequence of the Quarry’s operations.14 The data considered by the
    County in reaching its conclusion that any environmental risks would be mitigated to less
    than significant included groundwater monitoring data from the Landfill site for a period
    of more than a decade; groundwater modeling prepared by qualified experts confirming
    that a geological divide existed, and would continue to exist, between the Landfill and the
    Quarry Project site; and the revised water management plan providing that all
    precipitation, seepage, and process water from the Quarry Project site would be contained
    and treated onsite, with only surface water runoff from outside the Quarry footprint
    discharged into Ranch Tributary or the Americano Creek.
    In applying the substantial evidence standard, we accord great deference to the
    administrative agency’s substantive factual conclusions. 
    (Vineyard, supra
    , 40 Cal.4th at
    p. 435.) Further, we are required to “ ‘resolve reasonable doubts in favor of the
    administrative finding and decision.’ [Citation.]” (Laurel Heights 
    I, supra
    , 47 Cal.3d at
    p. 393.)
    We reiterate that our task is “not to weigh conflicting evidence and determine who
    has the better argument when the dispute is whether adverse effects have been mitigated
    or could be better mitigated.” (Laurel Heights 
    I, supra
    , 47 Cal.3d at p. 393.) We “may
    not set aside an agency’s approval of an EIR on the ground that an opposite conclusion
    would have been equally or more reasonable. [Citation.]” (Ibid.) Here, there is “enough
    14
    As discussed ante, CARRQ does not challenge here the final EIR conclusion
    that proposed explosive blasting in Quarry operations would not impact the integrity of
    the Landfill cells, Landfill infrastructure, or the surrounding ground on the Landfill
    property, and would not in and of itself create or increase potential for movement of
    potential contaminants from the Landfill cells offsite.
    15
    relevant information and reasonable inferences from this information that a fair argument
    can be made to support [the County’s] conclusion, even though other conclusions might
    also be reached.” (See Cal. Code Regs., tit. 14, § 15384, subd. (a).)
    C.     Roblar Road Mitigation Measures
    CARRQ complains that the final EIR failed to analyze what it terms the “last-
    minute decision” to route gravel truck traffic beside the Americano Creek, and that
    substantial evidence does not support the County’s finding that any impacts on
    Americano Creek from required roadway improvements on Roblar Road would be
    reduced to less than significant levels. We again disagree.
    1.     Roblar Road and Proposed Haul Routes
    Roblar Road is a two-lane major rural collector road that provides direct access to
    the Quarry Project site. A traffic study for the EIR estimated that production from the
    Quarry would generate between 151 and 240 truckloads of material per day, or 302 to
    480 one-way truck trips. This was projected to increase the percentage of average daily
    truck traffic on Roblar Road west of project site from an existing 8 percent to an
    estimated 19 percent (an 11 percent increase), and on Roblar Road east of the Quarry site,
    from an existing 9 percent to an estimated 14 percent (a 5 percent increase). Roblar Road
    currently has approximately 10-foot wide traffic lanes, with portions as narrow as 8.5–9.0
    feet (less than the current County standard of 12 feet), and minimal or no paved shoulders
    (less than the current County standard of six feet). Americano Creek is a regional creek
    running adjacent to Roblar Road in the immediate vicinity of the Quarry site. Americano
    Creek crosses Roblar Road three times, and follows closely and roughly parallel to
    Roblar Road for several hundred feet in the vicinity of the Quarry site.
    Mitigation measures E.3a and E.4a of the draft EIR recommended improvement of
    Roblar Road along its approximate six and one-half mile length (as well as other
    connecting roads) to meet current County road design standards, including two 12-foot
    wide vehicle travel lanes, two six-foot wide shoulders, and associated striping and
    signage to meet Class II bike facilities. The draft EIR noted that construction of the
    roadway improvements would also result in potential secondary environmental impacts.
    16
    The secondary impacts resulting from implementation of offsite transportation mitigation
    measures were analyzed separately. The draft EIR recognized that the required offsite
    improvements would mitigate Quarry Project impacts, and provide a beneficial effect on
    the movement of large vehicles, cars and bicyclists on haul routes, but that construction
    and implementation of these offsite transportation improvements would also result in
    their own potentially significant temporary and long-term environmental impacts on land
    use and agricultural resources, geology and soils, hydrology and water quality, hazardous
    materials, biological resources, transportation and circulation, air quality, noise,
    aesthetics and cultural resources. It discussed the “likely range of potential
    environmental impacts,” but noted that “[a] detailed analysis of the specific off-site
    impacts cannot be completed until and if design work was undertaken that would provide
    information on the specific alignment and structural improvements that may be required
    along Roblar . . . Road[] to accommodate the proposed widening. If the proposed
    roadway improvements were pursued, subsequent detailed environmental analysis and
    County approval would be required.”
    An alternative haul route suggested by Barella (Alternative 2) was included in the
    draft EIR and was considered by the Sonoma County Permit and Resource Management
    Department to be the “environmentally superior alternative” due to reduced secondary
    impacts associated with the improvements to Roblar Road (and other access roads)
    otherwise required as project mitigation. Under this alternative, all Quarry truck traffic
    would use two new temporary private off-road segments through other property adjacent
    to the Quarry site (Access Road 1 & Access Road 2), and reduced the extent of
    improvements to Roblar Road, as well as various other existing public roads. No project
    haul trucks would use Roblar Road east of the Quarry Project site. Alternative 2,
    however, required construction of Access Road 1 across a County agricultural preserve
    and open space district conservation easement and conflicted with the Williamson Act’s15
    15
    The Williamson Act (Gov. Code, § 51200 et seq.) empowers local governments
    to establish “agricultural preserves” consisting of lands devoted to agricultural and other
    compatible uses.
    17
    agricultural restrictions in other respects. Consequently, in a memorandum to the Permit
    and Resource Management Department dated October 19, 2010, Environmental Science
    Associates suggested a modification to Alternative 2 that would no longer require
    construction of Access Road 1, with all trucks entering and exiting the Quarry site via the
    originally proposed access point on Roblar Road (Modified Alternative 2). The Modified
    Alternative 2 resulted in a requirement that a total approximate 1.6-mile segment of
    Roblar Road be improved to current County road design standards—an additional 0.6
    miles over what would be required in proposed Alternative 2, but significantly less than
    that required under the original proposal addressed in the draft EIR and its recirculated
    portions. County staff review found that Modified Alternative 2 would not result in any
    new significant or substantially more severe environmental impacts than already analyzed
    in the draft EIR and its recirculated portions, and that no additional environmental review
    was required. Barella also submitted evidence from his engineers that the roadway
    improvements under Modified Alternative 2 could be constructed within the boundaries
    of an existing County right of way.
    At the October 19, 2010 public hearing, the Board of Supervisors approved
    Modified Alternative 2, which Barella characterizes as a “hybrid” of the haul route
    proposed by Alternative 2 and that originally proposed, including the driveway
    configuration entering the Quarry site. The County found that Modified Alternative 2
    would not result in any new construction impacts associated with offsite transportation
    improvements that were not already evaluated in the EIR (section V; impact E.8) and,
    although Modified Alternative 2 would result in an additional 0.6 mile of public road
    improvements, the offsite improvements required for Modified Alternative 2 would be
    substantially less than the originally proposed project. In approving the hybrid haul
    route, the County found that it would avoid potentially significant land use and
    agricultural resource impacts associated with the implementation of offsite mitigation
    transportation improvements, and that any associated environmental impacts, including
    any impacts to jurisdictional waters, wetlands and riparian habitat, would be mitigated to
    less than significant levels with the required conditions of approval.
    18
    2.     Project Components and Secondary Environmental Impacts
    The parties first disagree about the level of scrutiny required for environmental
    impacts associated with the offsite transportation improvements. Barella argues that the
    required Roblar Road improvements are mitigation measures generating secondary
    impacts, which are not required to be described by an EIR in as great detail as the
    primary impacts caused by the project components.16 CARRQ insists that the widening
    of Roblar Road is an integral aspect of the project as a whole, requiring complete
    analysis, since the “Quarry development and operations are contingent upon roadway
    widening.”17 (See Tuolumne County Citizens for Responsible Growth, Inc. v City of
    Sonora (2007) 
    155 Cal. App. 4th 1214
    (Tuolumne).) We agree with Barella that Tuolumne
    is distinguishable.
    The issue in Tuolumne was whether failure to analyze certain road realignment
    improvements required as a condition of approval for a home improvement shopping
    center resulted in improper segmenting of a “single CEQA project.” 
    (Tuolumne, supra
    ,
    155 Cal.App.4th at p. 1218.) The City of Sonora did not include the detailed road
    improvement plans in a mitigated negative declaration prior to public circulation, and
    undertook a separate CEQA review of the road improvements. The court found that the
    offsite road realignment improvements were treated improperly as a completely “separate
    and independent” project. (Id. at pp. 1221, 1227–1228.) Contrary to CARRQ’s
    assertion, that is not what occurred here. The secondary environmental impacts of the
    offsite mitigation measures, including widening of access roadways, were catalogued and
    discussed in significant detail. Among potential impacts noted were vegetation removal,
    shallow excavation and grading along the alignment of the road widening improvements,
    16
    “If a mitigation measure would cause one or more significant effects in addition
    to those that would be caused by the project as proposed, the effects of the mitigation
    measure shall be discussed but in less detail than the significant effects of the project as
    proposed. [Citation.]” (Cal. Code Regs., tit. 14, § 15126.4, subd. (a)(1)(D).)
    17
    To the extent that CARRQ suggests that development and operation of the
    Quarry would not be physically possible without widening of Roblar Road, the record
    fails to support that contention.
    19
    increased creek sedimentation during construction and the possibility of accidental
    release of contaminants (e.g., fuels and lubricants) during construction, and temporary
    and/or permanent disturbance of seasonal wetlands and jurisdictional waters in the
    vicinity of Americano Creek. Mitigation measures E.8a–E.8p and E.9 were specifically
    proposed to address these secondary impacts. Further, Tuolumne did not consider the
    application of California Code of Regulations, title 14, section 15126.4. subdivision
    (a)(1)(D). Barella correctly observes that the fact that a mitigation measure is mandated
    by a lead agency as a condition of project approval cannot thereby transform the measure
    into an integral project component. The implementing guidelines require that all
    mitigation measures be fully enforceable “through permit conditions, agreements, or
    other legally binding instruments.” (Cal. Code Regs., tit. 14, § 15126.4, subd. (a)(2).)
    CARRQ’s suggested interpretation and application of Tuolumne would effectively
    eliminate any distinction between primary and secondary environmental impacts and
    make every mitigation requirement a “project component.”
    3.     Substantial Evidence in Support of Findings
    CARRQ argues that the final EIR contained no evidence of either the extent or
    nature of the impacts of the roadway widening on Americano Creek or the efficacy of the
    mitigation measures, and simply set forth conclusions without requisite analysis. We
    read the administrative record differently.
    Exhibit A to the Board of Supervisor’s resolution certifying the final EIR included
    discussion of the secondary impacts resulting from implementing offsite transportation
    improvements and the related mitigation measures described in section IV.E
    (“Transportation and Traffic”) of the draft EIR. With respect to Americano Creek, the
    draft EIR discussed potentially significant secondary hydrology and water quality issues
    arising from implementation of offsite transportation improvements, including increases
    in sedimentation, the potential need for new or modified storm drains or culverts where
    roadway crossings occurred, or potential accidental release of construction related
    hazardous materials to soil and/or storm water. While noting that analysis of specific
    offsite impacts could not be completed until design work for the exact alignment and
    20
    structural improvements of the proposed widening was undertaken, and that subsequent
    detailed environmental analysis and County approval would be required, the draft EIR
    assessed the likely range of anticipated environmental impacts, and preliminary
    mitigation measures to reduce those potential environmental impacts. Vegetation
    removal, shallow excavation and grading along the new roadway alignment were
    identified as likely impacts. Mitigation measure E.8b, reflecting “current engineering
    practice and the accepted standard of care to mitigate potential impacts from unique
    geological conditions along the roadway alignments” required that grading and
    construction specifications for the roadway widening “implement best management
    practices . . . to reduce or eliminate soil erosion during construction” and incorporation of
    such measures into a storm water pollution prevention plan for the proposed roadway
    widening (required as mitigation measure E.8c).18 Mitigation measure E.8b required a
    “design level geotechnical investigation . . . to identify site specific geologic conditions
    and geotechnical constraints and develop adequate engineering design criteria and
    remedies to reduce the potential for slope instability from cutting and filling of adjacent
    slopes along the roadway alignments.” The draft EIR considered secondary impacts on
    biological resources and found that mitigation measures identified to mitigate potential
    impacts to biological resources from the proposed Quarry Project (including
    jurisdictional waters and wetlands impacts), would also be relevant and applicable for
    mitigating impacts associated with the roadway widening improvements. Mitigation
    measure E.8e required Barella to conduct a formal wetland delineation in accordance
    with the 1987 Corps of Engineers Wetlands Delineation Manual and have it verified by
    the U.S. Army Corps of Engineers. Wetland permits and compliance with the Clean
    Water Act were required if the Corps of Engineers determined that any jurisdictional
    waters were impacted. Barella was further required to compensate for the loss of any
    jurisdictional wetlands.
    18
    Storm water pollution prevention plans are defined under the federal Clean
    Water Act (33 U.S.C. § 1251 et seq.) and National Pollutant Discharge Elimination
    System (33 U.S.C. §1342; 40 C.F.R. § 122.26 (2013).)
    21
    CARRQ contends that recognition that further detailed analysis would be required
    under specific roadway improvement plans and designs constitutes improper deferral of
    mitigation. “Impermissible deferral of mitigation measures occurs when an EIR puts off
    analysis or orders a report without either setting standards or demonstrating how the
    impact can be mitigated in the manner described in the EIR. [Citations.]” (City of Long
    Beach v. Los Angeles Unified School Dist. (2009) 
    176 Cal. App. 4th 889
    , 915–916.)
    Deferral of mitigation measure selection is permissible, however, “ ‘for kinds of
    impacts for which mitigation is known to be feasible, but where practical considerations
    prohibit devising such measures early in the planning process . . . , the agency can
    commit itself to eventually devising measures that will satisfy specific performance
    criteria articulated at the time of project approval. Where future action to carry a project
    forward is contingent on devising means to satisfy such criteria, the agency should be
    able to rely on its commitment as evidence that significant impacts will in fact be
    mitigated. [Citations.]’ [Citation.]” (Sacramento Old City Assn. v. City Council (1991)
    
    229 Cal. App. 3d 1011
    , 1028–1029.) “ ‘[T]he details of exactly how mitigation will be
    achieved under the identified measures can be deferred pending completion of a future
    study.’ [Citations.] . . . [¶] Furthermore, a condition requiring compliance with
    regulations is a common and reasonable mitigation measure, and may be proper where it
    is reasonable to expect compliance. [Citations.]” Oakland Heritage Alliance v. City of
    Oakland (2011) 
    195 Cal. App. 4th 884
    , 906; 
    id. at pp.
    889, 907–910 [no improper
    mitigation deferral where, prior to project commencement, final design parameters for
    site improvements required review and approval by registered geotechnical engineer and
    city agency for compliance with codes, ordinances and policies]; see also California
    Native Plant 
    Society, supra
    , 172 Cal.App.4th at pp. 621–623 [appropriate to defer
    analysis of exact location of offsite habitat replacement where nothing in record
    suggested “offsite mitigation measures the [c]ity proposed were not feasible or that the
    [c]ity had not fully committed to implementing those measures”]; Gentry v. City of
    Murrieta (1995) 
    36 Cal. App. 4th 1359
    , 1394–1396 [no improper deferral where
    mitigation conditions would be “subject to a host of specific performance criteria
    22
    imposed by various ordinances, codes, and standards, as well as other mitigation
    conditions”].)
    We find the identification and discussion of potential secondary environmental
    impacts to be sufficient under the standards of California Code of Regulations, title 14,
    section 15126.4, subdivision (a)(1)(D), and we find substantial evidence in the record to
    support the conclusion reached by the County that any such impacts could be mitigated to
    less than significant levels. Again, we do “ ‘not pass upon the correctness of the EIR’s
    environmental conclusions, but only upon its sufficiency as an informative document.’
    [Citation.]” (Laurel Heights 
    I, supra
    , 47 Cal.3d at p. 392.)
    D.     Offsite Mitigation Preserve
    Surveys identified the presence of the California red-legged frog (CRLF), a special
    status protected species on the Quarry Project site. After the April 2010 initial planning
    commission recommendation to approve the final EIR, further surveys on the project site
    found larvae of the California tiger salamander (CTS), also a protected species under
    state and federal endangered species acts. Analysis of CTS impacts and mitigation
    measures were revised and included in recirculated portions of the draft EIR.19 The
    recirculated portions of the draft EIR determined that the Quarry Project would result in
    the permanent loss of CTS and CRLF breeding habitat (impact D.11). Proposed
    mitigation measures included requiring that Barella consult with the United States
    Federal Wildlife Service (USFWS) under section 7 of the federal Endangered Species
    Act of 1973 to define the necessary mitigation to compensate for the unavoidable impacts
    to the CTS and its habitat and obtain a “Biological Opinion” for the project. Barella was
    also required to apply for a California “State Incidental Take Permit” under section 208l,
    subdivision (b) of the Fish and Game Code if the state Department of Fish and Game
    determined that the federal authorization under the Biological Opinion was not consistent
    with the requirements of the California Endangered Species Act (Mitigation measure
    19
    As noted ante, the recirculated portions of the draft EIR also included an
    updated analysis of greenhouse gas emissions and mitigation measures addressing
    thresholds of significance adopted by the Bay Area Air Quality Management District.
    23
    D.11a). Mitigation for impacts to CTS habitat were further required to be consistent with
    CTS mitigation identified in a 2005 Santa Rosa Plain Conservation Strategy and in a
    USFWS 2007 Programmatic Biological Opinion.20 Mitigation measure D.11b required
    construction of a replacement pond for a pond to be lost on the Quarry site, and
    translocation of CTS larvae to the new pond under the direction of the USFWS and
    Department of Fish and Game. A habitat mitigation plan would be determined by the
    USFWS based on the findings issued in the project-specific Biological Opinion,
    including location of the replacement pond, pond size, and hydrology. The County found
    that any impacts on CTS habitat would be mitigated to a less than significant level by the
    implementation of mitigation measures D.1la and D.11b and incorporated those measures
    into the conditions of approval for the project.21
    On July 21, 2010, Barella made a request to the Sonoma County Agricultural
    Preservation and Open Space District (District) to clarify or amend a recorded
    conservation easement on property adjacent to the Quarry site. Barella sought to utilize
    the adjacent property as a preserve for CTS and CRLF by expanding the size of an
    existing stock pond and constructing an additional stock pond for use by the two special-
    status species. On December 14, 2010 (the date of final EIR certification), the Board of
    Supervisors, acting in their capacity as the Board of Directors of the District, approved a
    resolution interpreting the conservation easement to permit establishment of the CTS and
    CRLF mitigation preserve on this adjacent land (Resolution No. 10-0925).
    CARRQ contends that the final EIR is inadequate because it did not describe,
    analyze or even mention the site of its proposed protected species mitigation preserve,
    precluding the County from determining if the mitigation measures were feasible.
    CARRQ further argues that omission of Barella’s proposal for creation of the mitigation
    20
    USFWS Programmatic Biological Opinion for U.S. Army Corps of Engineers
    (2007) Permitted Projects that May Affect California Tiger Salamander and Three
    Endangered Plant Species on the Santa Rosa Plain, California (Corps File No. 223420N).
    21
    The agencies responsible for the Santa Rosa Plain Conservation Strategy had
    previously concluded that compliance with the interim mitigation guidelines in the
    strategy would be sufficient to mitigate significant effects to listed species.
    24
    preserve on the adjacent open space land constituted a failure to proceed in the manner
    required by law.
    1.     Location of the Mitigation Preserve
    We address this issue first, since the parties disagree about the impact of prior
    related litigation (Tresch v. County of Sonoma Agricultural Preservation & Open Space
    Dist. Bd. of Directors (Jan. 4, 2013, A133472) (Tresch) [nonpub. opn.]).22 Petitioners in
    Tresch, including CARRQ, sought a writ of mandate in the Sonoma County Superior
    Court requiring the District, inter alia, to set aside approval of Resolution No. 10-0925—
    alleging violation of CEQA and seeking preparation of a new EIR for the Quarry Project.
    The trial court sustained the District’s demurrer to the CEQA cause of action without
    leave to amend on the ground that the District’s adoption of Resolution No. 10-0925 did
    not constitute approval of a project within the meaning of CEQA. Barella contends that
    Tresch has already determined that the proposed mitigation preserve is not part of the
    Quarry Project, and the CARRQ is barred by the doctrine of collateral estoppel from
    arguing otherwise. CARRQ insists that Tresch has “no bearing on this appeal.”
    “Collateral estoppel is one of two aspects of the doctrine of res judicata. In its
    narrowest form, res judicata ‘ “precludes parties or their privies from relitigating a cause
    of action [finally resolved in a prior proceeding].” ’ [Citation.] But res judicata also
    includes a broader principle, commonly termed collateral estoppel, under which an issue
    ‘ “necessarily decided in [prior] litigation [may be] conclusively determined as [against]
    the parties [thereto] or their privies . . . in a subsequent lawsuit on a different cause of
    action.” ’ [Citation.] [¶] Thus, res judicata does not merely bar relitigation of identical
    claims or causes of action. Instead, in its collateral estoppel aspect, the doctrine may also
    preclude a party to prior litigation from redisputing issues therein decided against him,
    even when those issues bear on different claims raised in a later case.” (Vandenberg v.
    Superior Court (1999) 
    21 Cal. 4th 815
    , 828, italics omitted.) “Collateral estoppel . . . is
    22
    Barella was named in the underlying petition for writ of mandate as a real party
    in interest. We grant Barella’s request that we take judicial notice of this decision.
    (Evid. Code, §§ 452, subd. (a), 459; Cal. Rules of Court, rule 8.1115(b)(1).)
    25
    intended to preserve the integrity of the judicial system, promote judicial economy, and
    protect litigants from harassment by vexatious litigation. [Citation.]” (Id. at p. 829.) The
    doctrine is applied “ ‘only if several threshold requirements are fulfilled. First, the issue
    sought to be precluded from relitigation must be identical to that decided in a former
    proceeding. Second, this issue must have been actually litigated in the former
    proceeding. Third, it must have been necessarily decided in the former proceeding.
    Fourth, the decision in the former proceeding must be final and on the merits. Finally,
    the party against whom preclusion is sought must be the same as, or in privity with, the
    party to the former proceeding. [Citations.]’ [Citation.]” (Hernandez v. City of Pomona
    (2009) 
    46 Cal. 4th 501
    , 511.)
    CARRQ appears to dispute only the identity of issues in the two proceedings.
    CARRQ insists that Tresch only held that the District was not required to analyze
    Resolution No. 10-0925 permitting use of land subject to the conservation easement
    under CEQA, and that “[t]he issue here is whether the County . . . was required to
    analyze the use of the mitigation preserve on [conservation easement] land, as it was
    clearly proposed in conjunction with the [Quarry] Project.” (Italics omitted.)
    CARRQ is correct that the reviewing court in Tresch rejected appellants’ claim
    that Resolution No. 10-0925 was itself a CEQA project, since it only established that
    creation of the mitigation preserve is permissible in principle under the existing terms of
    the conservation easement, and neither required nor permitted any specific action or any
    physical change to the adjacent property. “All it does is confirm that the terms of the
    [conservation easement] do not preclude the possibility that the Preserve, in some form,
    could be established on the [adjacent] property.” 
    (Tresch, supra
    , A133472.)
    But similar to the argument CARRQ makes here with respect to the Roblar Road
    mitigation measures, appellants in Tresch also argued that the District’s adoption of
    Resolution No. 10-0925 required compliance with CEQA, in part because the mitigation
    26
    activity allowed under this resolution is an integral component of the Quarry Project.23
    CARRQ ignores the fact that the underlying petition in Tresch sought not only vacation
    of Resolution No. 10-0925, but an order requiring preparation of a new EIR for the
    Quarry Project. The Tresch court expressly rejected appellants’ assertion that Resolution
    No. 10-0925 was an integral part of the Quarry Project, finding that the mitigation
    conditions of the final EIR left it up to the federal and state agencies involved to
    determine what mitigation efforts will be needed in regard to the protected species.
    “Nothing in [the final EIR conditions of approval] makes establishment of the Preserve
    inevitable, or (in the words of the CEQA [implementing guidelines]) ‘commits the
    [District . . . ] to a definite course of action in regard to’ mitigating the Quarry’s impact
    on the protected species. ([Cal. Code Regs., tit. 14], § 15352.) [¶] . . . Thus, the
    conditions of the EIR for the Quarry neither included nor relied upon the District’s
    interpretation of the [conservation easement] to permit the Preserve. Moreover, nothing
    in the record suggests that Barella cannot satisfy the conditions of the EIR as to the
    protected species without creating the Preserve, if there are other means of sufficiently
    mitigating the Quarry’s effect on the protected species. Thus, both legally and as a
    practical matter, it is possible for the Quarry [P]roject to go forward even if the Preserve
    is never created.” 
    (Tresch, supra
    , A133472.)
    Thus, the issue of whether the site of the proposed protected species mitigation
    preserve was required to be included in the Quarry Project final EIR was adjudicated in
    Tresch and could not be revisited, either in the trial court or here. This is necessarily
    dispositive of CARRQ’s claim that the County failed to proceed in the manner required
    by law in this respect.
    23
    The Tresch appellants also contended that to not consider Resolution No. 10-
    0925 as part of the Quarry Project would allow Barella to establish the preserve without
    ever complying with CEQA, and that Resolution No. 10-0925 had a reasonably
    foreseeable indirect impact on the environment due to the possibility that its adoption
    would set a precedent for the District to interpret other conservation easements to permit
    use of the underlying land for the benefit of commercial projects.
    27
    2.     Sufficiency of the Mitigation Analysis
    CARRQ is not precluded by collateral estoppel from challenging the adequacy of
    the mitigation analysis for the protected species measures contained in the final EIR, an
    issue not considered in Tresch. CARRQ contends that even if the mitigation preserve
    were not required for the Quarry Project to go forward, it was still contemplated as a part
    of the Quarry Project, and should have at least been analyzed as a mitigation measure or
    alternative. CARRQ further argues that the EIR deficiently addressed the actual
    mitigation measures relating to the take of endangered species and that the mitigation
    measures are improperly vague.
    In this instance, Barella may be correct that CARRQ failed to exhaust its
    administrative remedies. As Barella points out, CARRQ’s objections to the mitigation
    preserve, as reflected in the administrative record, challenged the creation of a mitigation
    bank on the adjacent parcel as a violation of the a conservation easement on that property
    prohibiting “any nonagricultural commercial or industrial activity or use” on those lands.
    (See 
    Tresch, supra
    , A133472.) CARRQ did not appear to raise any environmental
    impact issues with respect to the mitigation preserve, nor did it directly challenge the
    sufficiency of the species protection mitigation measures in the administrative
    proceedings. To challenge findings in an EIR, the basis for alleged noncompliance must
    be presented to the agency orally or in writing during the public comment period or prior
    to the close of the public hearing. (Pub. Resources Code, § 21177, subd. (a).) “ ‘The
    purpose of the rule of exhaustion of administrative remedies is to provide an
    administrative agency with the opportunity to decide matters in its area of expertise prior
    to judicial review. [Citation.] The decisionmaking body “ ‘is entitled to learn the
    contentions of interested parties before litigation is instituted.’ ” ’ [Citation.]”
    (California Native Plant 
    Society, supra
    , 172 Cal.App.4th at p. 616.) “ ‘Exhaustion of
    administrative remedies is a jurisdictional prerequisite to maintenance of a CEQA
    action.’ [Citation.]” (State Water Resources Control Bd. Cases (2006) 
    136 Cal. App. 4th 674
    , 791–792; Resource Defense Fund v. Local Agency Formation Com. (1987)
    
    191 Cal. App. 3d 886
    , 894 [failure to present issue at administrative level precludes
    28
    judicial review], disapproved on other grounds in Voices of the Wetlands v. State Water
    Resources Control Bd. (2011) 
    52 Cal. 4th 499
    , 539.)
    Even assuming, however, that the comments submitted by CARRQ are adequate
    to preserve a challenge here, we would reject the claim on the merits. The final EIR
    recognized the impacts to two protected species, both during Quarry development and
    operation, and from a permanent loss of habitat on the Quarry site. CARRQ focuses only
    on mitigation measures relating to habitat loss, specifically mitigation measure D.11a,
    complaining that the requirement for consultation with federal and state wildlife
    authorities fails to identify the criteria which will apply to the habitat replacement, or
    what evidence would support a conclusion that “these undefined measures will be
    sufficient to mitigate the significant effects of the project on these listed species.”
    CARRQ contends that this constitutes an improper deferral of mitigation.
    Formulation of mitigation measures should not be deferred until some future time.
    (Cal. Code Regs., tit. 14, § 15126.4, subd. (a)(1)(B).) But mitigation measures are not
    “deferred” if the agency recognizes the potential environmental effects and articulates
    specific performance criteria for mitigation of those effects. (Gentry v. City of 
    Murrieta, supra
    , 36 Cal.App.4th at pp. 1394–1396 [applicant required to submit improvement
    plans, grading plans, and a final map for approval, that would be “subject to a host of
    specific performance criteria imposed by various ordinances, codes, and standards, as
    well as other mitigation conditions”].) “Furthermore, a condition requiring compliance
    with regulations is a common and reasonable mitigation measure, and may be proper
    where it is reasonable to expect compliance. [Citations.]” (Oakland Heritage Alliance v.
    City of 
    Oakland, supra
    , 195 Cal.App.4th at p. 906.)
    California Native Plant Society presented circumstances similar to those before us.
    A residential and commercial development project was determined to have a significant
    environmental impact in loss of vernal pool tadpole shrimp habitat. (California Native
    Plant 
    Society, supra
    , 172 Cal.App.4th at p. 610.) Mitigation measures included requiring
    the applicant to create an offsite vernal pool and seasonal wetland habitat “ ‘to ensure no
    net loss in wetland habitat acreage, values and functions.’ ” (Id. at p. 612.) The project
    29
    opponent argued the EIR violated CEQA because it “ ‘failed to describe . . . where off-
    site vernal pool and wetland creation [would] occur, or how such activities may affect
    these undescribed off-site environments.’ ” (Id. at p. 614.) The opponent also contended
    a city had “ ‘unlawfully deferred development and adoption of mitigation measures until
    after project approval’ by failing to describe where the offsite mitigation might occur and
    failing to analyze or disclose the impacts of that mitigation[,]” and that a finding that the
    mitigation measures “would reduce the impact of the [p]roject on these habitats to less
    than significant, was not supported by the evidence.” (Ibid.) Rejecting a claim that the
    city had deferred mitigation, the Court of Appeal held that “when a public agency has
    evaluated the potentially significant impacts of a project and has identified measures that
    will mitigate those impacts, the agency does not have to commit to any particular
    mitigation measure in the EIR, as long as it commits to mitigating the significant impacts
    of the project. . . . [¶] . . . The [c]ity did not defer a determination of whether the [p]roject
    would have a significant impact on the vernal pool and seasonal wetland habitats or defer
    the identification of measures calculated to mitigate that impact. Rather, the [c]ity
    determined the impact the [p]roject would have—habitat loss—and identified a specific
    measure to mitigate that impact—preservation or creation of replacement habitat offsite
    in a specific ratio to the habitat lost as a result of the [p]roject. . . . [T]he agency was
    entitled to rely on the results of a future study to fix the exact details of the
    implementation of the mitigation measures the agency identified in the EIR.” (Id. at
    pp. 621–622.)
    The County did exactly that here. It identified the environmental impact—habitat
    loss for two protected species—and it required replacement of lost habitat in a manner
    compliant with federal and state law. The conditions of approval require identification of
    replacement habitat, in a ratio “not less than 1:1,” for the protected species in accordance
    with a Biological Opinion to be obtained in consultation with the USFWS, as well as
    compliance with the California Endangered Species Act. A site-specific habitat
    mitigation plan would be determined by the USFWS based on the findings issued in the
    Biological Opinion, and CTS larval relocation was required to be conducted under the
    30
    direction of the USFWS and Department of Fish and Game. Moreover, the habitat
    mitigation for the CTS was required to be consistent with existing CTS mitigation
    measures identified in the 2005 Santa Rosa Plain Conservation Strategy and 2007
    USFWS Programmatic Biological Opinion. CARRQ fails to meet its burden to show that
    the final EIR is inadequate in this respect.
    We find the contested conclusions of the final EIR to be supported by substantial
    evidence, and the final EIR to be sufficient as an information document. (San Joaquin
    Raptor Rescue Center v. County of Merced (2007) 
    149 Cal. App. 4th 645
    , 653.)
    III.   DISPOSITION
    The judgment granting the petition for writ of mandate is reversed. The matter is
    remanded to the trial court with instructions to deny the petition. Barella shall recover
    costs on appeal.
    _________________________
    Bruiniers, J.
    We concur:
    _________________________
    Jones, P. J.
    _________________________
    Simons, J.
    31