Castro v. City of Sacramento CA3 ( 2015 )


Menu:
  • Filed 10/9/15 Castro v. City of Sacramento CA3
    NOT TO BE PUBLISHED
    California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
    publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication
    or ordered published for purposes of rule 8.1115.
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    THIRD APPELLATE DISTRICT
    (Sacramento)
    ----
    ROBERT CASTRO, JR., et al.,                                                                  C064091
    Plaintiffs and Appellants,                                       (Super. Ct. No.
    34200800012385CUWMGDS)
    v.
    CITY OF SACRAMENTO et al.,
    Defendants and Respondents;
    IA SACRAMENTO HOLDINGS, L.L.C., et al.,
    Real Parties in Interest and
    Respondents.
    This is another chapter in the history of the litigation involving property once
    occupied by the Southern Pacific and Union Pacific Railroads in the City of Sacramento.
    As described in greater detail below, the long-vacant railyard property has been the
    subject of several redevelopment plans and amended redevelopment plans and multiple
    1
    lawsuits. The Richards Boulevard Redevelopment Plan (Richards Boulevard Plan),
    which encompassed the railyards as well as the industrial area surrounding Richards
    Boulevard, was adopted by the City of Sacramento (City) in 1990. Thereafter, in 2008,
    the Richards Boulevard Plan was amended to remove from the project area boundaries
    300 acres, reducing its size to 1,068 acres, and to change its name. The 300 acres
    removed from the plan, 245 acres of former railyard property along with approximately
    60 acres of downtown Sacramento property, became the subject of a new Railyards
    Redevelopment Plan (Railyards Plan). The City also approved a land use plan, the
    Railyards Specific Plan (Specific Plan), limited to the railyards. The City’s review of the
    Specific Plan environmental impact report (Specific Plan EIR) is the subject of separate
    litigation. (Sacramento Citizens Concerned About the Railyards v. City of Sacramento
    (Oct. 7, 2015, C065220 [nonpub. opn.] (Sacramento Citizens).)
    In this appeal, plaintiffs Robert Castro, Jr., Linda Powers, and Chris Rich
    (collectively, Castro) challenge the decision of defendants City and the Redevelopment
    Agency of the City of Sacramento (Agency) to amend the 1990 Richards Boulevard Plan
    to remove 300 acres from its boundaries and rename it the River District Redevelopment
    Plan (River District Plan). Castro also challenges the City’s adoption of the new
    Railyards Plan covering the 300 acres removed from the Richards Boulevard Plan.
    Castro argues (1) the environmental impact report for the Richards Boulevard Plan
    amendment and Railyards Plan (Redevelopment EIR) violated CEQA (California
    Environmental Quality Act; Pub. Resources Code, § 21000 et seq.) by improperly tiering
    from the Specific Plan EIR, (2) the Agency impermissibly segmented environmental
    review by certifying the Redevelopment EIR, and (3) the Redevelopment EIR failed to
    analyze and mitigate toxic air contaminants. We shall affirm the judgment.
    2
    FACTUAL AND PROCEDURAL BACKGROUND
    We begin, as all environmental sagas must, with the history leading up to the
    current imbroglio. The area at the center of this dispute includes over 200 acres of the
    former Union Pacific Railyards, an area developed in the late 1880’s.
    Richards Boulevard Plan
    In 1990 the City adopted the Richards Boulevard Plan for the Richards Boulevard
    Redevelopment Project Area (Richards Boulevard Project Area), which included the
    railyards area. However, the City’s efforts to develop the railyards area bore no fruit over
    the next 17 years. The City faced obstacles including lack of infrastructure,
    environmental contamination, issues of historic preservation, and the need to realign the
    area’s levee system.
    Based on these concerns, the City determined it could not develop the railyards
    area without a separate redevelopment project area limited to just the railyards. This
    separate project area would free the rest of the Richards Boulevard Project Area from the
    costs and other development constraints associated with developing the railyards.
    Amendment of the Richards Boulevard Plan
    In 2007 the Planning Commission of the City of Sacramento (Planning
    Commission) amended the boundaries of the Richards Boulevard Project Area and the
    preliminary plan therefor to exclude the railyards area. The amendment changed the title
    of the Richards Boulevard Plan to the River District Plan and removed from the Richards
    Boulevard Project Area the 300 acres proposed to be included in the new Railyards
    Redevelopment Project Area (Railyards Project Area). The River District Plan covers
    approximately 1,068 acres north of the new Railyards Project Area and consists of
    warehouse and distribution facilities. The Planning Commission designated the land
    within the boundaries of the railyards as the new Railyards Project Area.
    The Railyards Project Area consists of the 300 acres formerly within the Richards
    Boulevard Project Area. The Railyards Project Area is located within the Central City
    3
    Community Plan area of the City of Sacramento. Most of the Railyards Project Area is
    subject to the Specific Plan, but the boundaries of the 300-acre Railyards Project Area
    differ from the 244-acre Specific Plan area.1
    Under the Specific Plan, the 244 acres will become a diverse mixed-use
    development. The remaining approximately 60 acres of the Railyards Development Plan
    are not included in the Specific Plan. The 60 acres contain the United States Courthouse,
    the Sacramento County Jail, the Sacramento County Administration Building, and the
    Sacramento City Hall.
    EIR for the Railyards Plan
    Later in 2007 the Agency released a notice of preparation (NOP) of an EIR to
    evaluate the environmental impact of the Richards Boulevard Plan amendment and the
    Railyards Plan. The NOP described the proposed project as an amendment of the
    Richards Boulevard Plan and the adoption of a new Railyards Plan. It explained that the
    railyards portion of the Richards Boulevard Project Area would be deleted from the
    project area and be established as a separate redevelopment project area, the Railyards
    Project Area. The amendment would change the name of the Richards Boulevard Plan to
    the River District Plan.
    Amendment of the Richards Boulevard Plan would not require an EIR, but the
    new Railyards Plan would.
    1 Defendants and real parties in interest accuse plaintiffs of trying to create confusion
    between the City’s land use approval of the Specific Plan and its EIR, and the Agency’s
    separate and subsequent approval of the redevelopment plans and certification of the
    Redevelopment EIR. They emphasize that while the Specific Plan covers part of the
    Railyards Project Area, the Specific Plan and the redevelopment plans are distinct
    projects, governed by separate statutes, serving different purposes, and covering different
    geographical areas with potentially different environmental impacts.
    4
    The Specific Plan EIR
    In the summer of 2007 the City released the Specific Plan EIR for public review
    and comment. The Specific Plan replaced a prior railyards specific plan prepared by the
    ROMA Design Group and approved by the City in 1994 (the ROMA Plan) and allowed
    development different from that contemplated by the prior plan. The Specific Plan EIR
    covers the 244 acres in the Railyards Project Area and the environmental impacts of
    transforming the railyards property into a diverse mixed-use development that may
    include up to 2.4 million square feet of office space and approximately 12,500 residential
    units.
    The City certified the Specific Plan EIR in December 2007. Project approvals
    listed in the Specific Plan included “Approval of a Redevelopment Plan,” “Owner
    Participation Agreement” (OPA), and “Financing Plan.”2
    The Road to Litigation
    In October 2007 the Agency filed an NOP for the draft Redevelopment EIR and
    transmitted the NOP to local agencies to solicit comments. In December the City
    certified completion of the Specific Plan EIR for the 244-acre railyards property.
    In January 2008 the Agency filed a notice of availability of the draft
    Redevelopment EIR and distributed it to various agencies, organizations, and individuals.
    The draft Redevelopment EIR remained open for comment for 45 days. The Agency
    received relatively few comments on the draft Redevelopment EIR. The Agency revised
    2 An OPA is a contract between a property owner or developer and a redevelopment
    agency to permit redevelopment of property within a redevelopment project area that is
    owned by an entity other than the redevelopment agency. (Health & Saf. Code, § 33339.)
    The master OPA provides a framework for entering into subsequent, project-specific
    OPA’s, including the initial phase infrastructure OPA, which nevertheless stands as an
    independent document.
    5
    the draft Redevelopment EIR and addressed the comments. In April 2008 the Agency
    released the final Redevelopment EIR.
    In May 2008 the Agency certified completion of the Redevelopment EIR,
    approved the amendment to the Richards Boulevard Plan, approved the Railyards Plan,
    and adopted an implementation plan for the Railyards Redevelopment Project. The City
    Council of the City of Sacramento amended the Richards Boulevard Plan and approved
    the Railyards Plan in May 2008. The Agency also entered into a master OPA and an
    Initial Phase Infrastructure OPA with the developer of the railyards project.
    Castro filed a petition for a writ of mandate, challenging the Agency’s certification
    of the Redevelopment EIR.
    Trial Court Decision
    The trial court denied Castro’s petition a for writ of mandate. The court
    determined that the Specific Plan development project and the Railyards Plan project are
    separate and independent from each other for the purposes of CEQA. In addition, the
    court also rejected Castro’s contention that the Redevelopment EIR improperly tiered
    from the Specific Plan EIR. The court found the Redevelopment EIR reasonably
    responded to Castro’s contentions regarding the risks posed by toxic air contaminant
    (TAC) emissions.
    Castro filed a timely notice of appeal.
    DISCUSSION
    STANDARD OF REVIEW
    The Legislature intended CEQA to be interpreted to afford the fullest possible
    protection to the environment within the reasonable scope of the statute. The EIR
    provides the means of achieving this goal. It is an environmental alarm bell, alerting the
    public and its governmental representatives to environmental changes before they
    become irreversible. In addition, it provides the public with some assurance that the
    responsible agency has analyzed and considered the ecological impacts of its action. As
    6
    a document of accountability, the EIR allows the public to know the basis on which
    officials approve or reject environmentally significant action. Such knowledge allows the
    public to respond to official actions that impact the environment. (Laurel Heights
    Improvement Assn. v. Regents of University of California (1988) 
    47 Cal. 3d 376
    , 390-392
    (Laurel Heights).)
    When considering a challenge to the legal adequacy of an EIR, we presume an
    agency’s decision to certify the EIR is correct, placing the burden of establishing
    otherwise on the party challenging the EIR. (Sierra Club. v. City of Orange (2008)
    
    163 Cal. App. 4th 523
    , 530 (Sierra Club).) We must determine whether the agency abused
    its discretion by not proceeding in a manner required by law and whether the decision is
    supported by substantial evidence. We do not second-guess the correctness of the EIR’s
    environmental conclusions but consider only its sufficiency as an informational
    document. (Laurel 
    Heights, supra
    , 47 Cal.3d at p. 392.) We will not set aside an
    agency’s approval of an EIR on the ground that a different conclusion would have been
    more reasonable or equally compelling. (Citizens of Goleta Valley v. Board of
    Supervisors (1990) 
    52 Cal. 3d 553
    , 564.)
    We review the agency’s decision, not that of the trial court. (In re Bay-Delta etc.
    (2008) 
    43 Cal. 4th 1143
    , 1162.) When considering whether an agency followed the
    correct procedures, we conduct a de novo review. However, when reviewing an agency’s
    substantive factual conclusions, we afford the agency greater deference and employ the
    substantial evidence test. In reviewing the record for substantial evidence we do not
    reweigh the evidence. Instead, we focus on the adequacy, completeness, and good faith
    effort at full disclosure. (Sierra 
    Club, supra
    , 163 Cal.App.4th at p. 531; Association of
    Irritated Residents v. County of Madera (2003) 
    107 Cal. App. 4th 1383
    , 1390.)
    IMPROPER TIERING
    Castro contends the Agency violated CEQA by preparing the Redevelopment EIR,
    which Castro argues unnecessarily and confusingly replicated the Specific Plan EIR.
    7
    According to Castro, the Redevelopment EIR improperly tiered from the Specific Plan
    EIR. Castro contends the physical development described in the two EIR’s is the same,
    and in the Redevelopment EIR “virtually nothing new is added.”
    Tiering Under CEQA
    CEQA allows agencies to tier subsequent environmental analysis from prior EIR’s
    when feasible: “(a) The Legislature finds and declares that tiering of environmental
    impact reports will promote construction of needed housing and other development
    projects by (1) streamlining regulatory procedures, (2) avoiding repetitive discussions of
    the same issues in successive environmental impact reports, and (3) ensuring that
    environmental impact reports prepared for later projects which are consistent with a
    previously approved policy, plan, program, or ordinance concentrate upon environmental
    effects which may be mitigated or avoided in connection with the decision on each later
    project. . . .
    “(b) To achieve this purpose, environmental impact reports shall be tiered
    whenever feasible, as determined by the lead agency.” (Pub. Resources Code, § 21093.)3
    CEQA encourages agencies to tier environmental analyses that they prepare for
    separate but related projects, including development projects. Tiering can eliminate
    repetitive discussions of the same issues and focus the later EIR on the issues ripe for
    decision at each level of review. Tiering is appropriate when the sequence of analysis is
    from an EIR prepared for a general plan to an EIR for another plan of lesser scope, but
    the agency is not excused from adequately analyzing reasonably foreseeable significant
    environmental effects of the project. Nor does tiering justify an agency’s deferring such
    analysis to a later-tier EIR. However, the level of detail contained in a first-tier EIR need
    3 All further statutory references are to the Public Resources Code unless otherwise
    designated.
    8
    not be greater than that of the program being analyzed. (CEQA Guidelines, § 15152,
    subd. (b).)4
    Under section 21094, if an EIR has been prepared and certified for a plan, the
    agency for a later project shall examine significant effects of the later project on the
    environment via a tiered EIR. A subsequent EIR is not required to examine effects the
    agency determines were either (1) mitigated or avoided as a result of the prior EIR, or
    (2) examined in sufficient detail in the prior EIR to allow those effects to be mitigated or
    avoided through conditions of approval or by other means in connection with approval of
    the later project. (§ 21094, subd. (a)(1)-(a)(1)(B).)
    Although tiering is permissible in certain circumstances, CEQA requires an
    agency to analyze the project in its entirety to ensure all potential impacts related to the
    proposed project are properly considered. (Stanislaus Natural Heritage Project v.
    County of Stanislaus (1996) 
    48 Cal. App. 4th 182
    , 197-199 (Stanislaus Natural Heritage).)
    The prohibition against segmentation of a project serves to prevent dividing the project
    into smaller pieces, precluding meaningful and complete analysis of potential
    environmental impacts. However, environmental impacts of related projects may be
    analyzed separately when the projects are not dependent on one another. (Tracy First v.
    City of Tracy (2009) 
    177 Cal. App. 4th 912
    , 931-932 (Tracy First); Rio Vista Farm Bureau
    Center v. County of Solano (1992) 
    5 Cal. App. 4th 351
    , 370-373.)
    Discussion
    Castro contends the Redevelopment EIR violates CEQA since it analyzes the same
    physical development analyzed in the Specific Plan EIR. According to Castro and
    quoting from the draft Redevelopment EIR, “The Redevelopment EIR admits that it
    4 The Guidelines for Implementation of the California Environmental Quality Act are set
    forth in the California Code of Regulations, title 14, section 15000 et seq. (CEQA
    Guidelines).
    9
    evaluates no new physical project and includes no new environmental analysis from that
    provided in the two previous EIRs:
    “ ‘The Railyards Specific Plan/Richards Boulevard Area Plan (RSP/RBAP) EIR
    analyzed the impacts of redevelopment consistent with the RBAP, which encompasses
    the same area as the existing Richards Boulevard Redevelopment Project Area. The
    recently adopted Railyards Specific Plan (RSP) EIR analyzed the impacts of development
    consistent with the updated Railyards Specific Plan, which covers the majority of the
    Railyards Project Area. Therefore, this Program EIR tiers from both of these EIRs, and
    assumes the mitigation measures adopted and required for development within these
    specific plan areas are a part of the future development within the Project Areas. No
    land use changes are proposed as part of the Proposed Project.’ ”
    Castro contends the boundary change is not a project subject to CEQA, citing Simi
    Valley Recreation & Park Dist. v. Local Agency Formation Com. (1975) 
    51 Cal. App. 3d 648
    , 652, 662-666. Castro asserts, “A boundary change of a redevelopment plan and a
    change in the name of a redevelopment plan are not subject to CEQA. Therefore, the
    only ‘project’ subject to CEQA review is the [Specific Plan], and the Redevelopment EIR
    was unnecessary.”
    The trial court considered the relationship between the two EIR’s and found: “The
    project described and evaluated in the [Specific Plan] EIR and the project described and
    evaluated in the Redevelopment EIR are separate and independent, though
    complementary, projects. The [Specific Plan] EIR concerns the development of land uses
    on the 244 acre [Specific Plan] site by the City under the State Planning and Zoning Law,
    the City of Sacramento General Plan, and the [Specific Plan]. The Redevelopment EIR
    concerns the Agency’s actions under the Community Redevelopment Law to divide the
    [Richards Boulevard Plan] Area, establish separate plans for the redevelopment of the
    1,068 acre [River District Plan] Area and the 300 acre [Railyards Plan] Area, and approve
    10
    a Master OPA and an Initial Phase [Infrastructure] OPA with the Developer for the
    elimination of blight.
    “The Agency’s planned redevelopment activities to eliminate blight in the [River
    District Plan] Area and in the [Railyards Plan] Area, where the [Specific Plan] site is
    located, began well before the [Specific Plan] was conceptualized, are not limited to
    [Specific Plan] implementation, and are distinct from the City’s land use planning
    activities to develop the [Specific Plan].” The court also noted: “[T]he tax increment
    funding provided under the Initial Phase [Infrastructure] OPA is a redevelopment activity
    undertaken pursuant to the [Railyards Plan] project which may facilitate but which does
    not add any component to and is not part of the [Specific Plan] development project.”
    CEQA requires an agency to prepare an EIR for any project it determines may
    have a significant impact on the environment. (CEQA Guidelines, § 15002, subd. (f)(1).)
    CEQA defines a project as any activity that may have a potential for resulting in a direct
    or indirect physical change in the environment. (CEQA Guidelines, §§ 15002, subd. (d),
    15378, subd. (a).)
    Here, approximately 60 acres of the Railyards Project Area lie outside the area
    subject to the Specific Plan. The amendment to the Richards Boulevard Plan modifies
    the boundaries of the Richards Boulevard Project Area and creates a new redevelopment
    plan for the Railyards Project Area. The Agency’s initial study identified potentially
    significant impacts stemming from the project, including impacts to the view corridors on
    I Street, 4th Street, 7th Street, 9th Street, and 10th Street.
    These potential impacts include aesthetics, light, and glare and were not part of the
    Specific Plan EIR but instead are analyzed in the Redevelopment EIR. The
    Redevelopment EIR ultimately concluded the potential impacts to the view corridors
    were less than significant.
    Castro rejects any argument that the Redevelopment EIR includes a broader scope
    of analysis than the Specific Plan EIR, contending the Redevelopment EIR does not
    11
    analyze a project other than the Specific Plan. According to Castro, the Specific Plan
    EIR provided an identical analysis of light and glare in the view corridors but provided a
    more comprehensive evaluation of these aesthetic issues. As for the additional acreage
    included in the Redevelopment EIR, Castro contends “the 60 downtown acres are of no
    consequence for CEQA purposes, and as a practical matter the boundaries of the
    [Specific Plan] and [Railyards] Plan are the same.” Tellingly, Castro provides no support
    for this assertion.
    Castro also contends the Redevelopment EIR improperly tiered from the Specific
    Plan EIR since “[n]o additional level of detail is provided in the Redevelopment EIR
    because it is not of ‘lesser scope’ than the [Specific Plan] EIR.” In addition, Castro
    argues, “The Agency’s use of tiering also violates CEQA because the Redevelopment
    Project is broader and more general in nature than the [Specific Plan].”
    The trial court found the concept of tiering in CEQA did not preclude the
    Redevelopment EIR from using the impact analysis in the Specific Plan EIR for the same
    infrastructure: “The impacts to be analyzed in the Redevelopment EIR for the funding of
    that infrastructure under the Initial Phase [Infrastructure] OPA would be substantially the
    same as the impacts that were analyzed in the [Specific Plan] EIR for development of the
    infrastructure.” Moreover, the trial court could “conceive of no reason for the
    Redevelopment EIR to duplicate the impact analysis already produced by the [Specific
    Plan] EIR to the extent that it covers the impacts of developing the same infrastructure.”
    Under section 21094, if a prior EIR has been prepared and certified for a program
    or plan, the lead agency for a later project that meets the requirements of section 21094
    “shall examine significant effects of the later project upon the environment by using a
    tiered environmental impact report.” The agency must determine that the later project is
    (1) consistent with the program, plan, policy, or ordinance covered by the prior EIR;
    (2) consistent with applicable local land use plans and zoning of the city, county, or city
    12
    and county in which the subsequent project would be located; and (3) is not subject to
    section 21166. (§ 21094, subd. (b)(1)-(2).)
    Here, the Redevelopment EIR is a program EIR related to the prior EIR, is
    consistent with applicable land use plans and zoning, and is not subject to section 21166.
    The Redevelopment EIR tiers from the Richards Boulevard Plan EIR and the Specific
    Plan EIR. In addition, the Agency found the Redevelopment EIR would not change any
    land uses analyzed in the Specific Plan EIR. Section 21166 applies when the subsequent
    project is not different from the previous project.
    Castro also argues the Redevelopment EIR improperly tiered from the Specific
    Plan EIR because the Redevelopment EIR is broader and more general than the Specific
    Plan EIR. In support, Castro quotes CEQA Guidelines section 15152, subdivision (b):
    “ ‘Tiering is appropriate when the sequence of analysis is from an EIR prepared for a
    general plan, policy, or program to an EIR or negative declaration for another plan,
    policy, or program of lesser scope, or to a site-specific EIR or negative declaration.’ ”
    The trial court rejected this argument, noting the statutory definition “does not,
    and should not, preclude the use in the Redevelopment EIR of the impact analysis in the
    [Specific Plan] EIR for the same infrastructure. . . . The court can conceive of no reason
    for the Redevelopment EIR to duplicate the impact analysis already produced by the
    [Specific Plan] EIR . . . .” Nor can we. Under the CEQA Guidelines, tiering “can
    eliminate repetitive discussions of the same issues and focus the later EIR or negative
    declaration on the actual issues ripe for decision at each level of environmental
    review. . . . Tiering does not excuse the lead agency from adequately analyzing
    reasonably foreseeable significant environmental effects of the project and does not
    justify deferring such analysis to a later tier EIR or negative declaration. However the
    level of detail contained in the first tier EIR need not be greater than that of the program,
    plan, policy or ordinance being analyzed.” (CEQA Guidelines, § 15152, subd. (b).)
    13
    Castro’s arguments to the contrary notwithstanding, the Redevelopment EIR did not
    violate CEQA in tiering from the Specific Plan EIR.5
    IMPROPER SEGMENTATION
    Castro contends that because the physical components of the railyards project are
    addressed in the Specific Plan EIR, there are no additional project components to be
    analyzed in the Redevelopment EIR. Since the Railyards Plan was prepared solely to
    provide funding for the Specific Plan, it was part of the “whole of the action” that makes
    up the railyards project. Therefore, the Agency’s certification of the Redevelopment EIR
    is an impermissible segmentation of environmental review. In support, Castro cites
    Citizens for a Megaplex-Free Alameda v. City of Alameda (2007) 
    149 Cal. App. 4th 91
    ,
    106.)
    The trial court disagreed, finding the purpose of the Railyards Plan is to make tax
    increment funding available to the developer under the Initial Phase Infrastructure OPA
    for the construction of certain public facilities on the Specific Plan site. According to the
    court, “[T]ax increment funding provided under the Initial Phase OPA is a redevelopment
    activity undertaken pursuant to the Railyards Redevelopment Plan project which may
    facilitate but which does not add any component to and is not part of the [Specific Plan]
    development project. Thus the tax increment funding does not add to the [Specific Plan]
    development project or its impacts on the physical environment and need not be analyzed
    together with the [Specific Plan] project for purposes of CEQA. The [Specific Plan]
    development project and the [Railyards Plan] project are separate and independent from
    each other for purposes of CEQA.”
    Castro disagrees, arguing the Agency prepared the Railyards Plan solely to fund
    the Specific Plan. Castro reasons: “Although the [Railyards] Plan and the Specific Plan
    5 Since we find no impropriety in the Redevelopment EIR’s tiering from the Specific
    Plan EIR, we need not address Castro’s arguments concerning prejudice.
    14
    have different functions and arise from a different statutory framework, they have a
    common purpose to develop the Railyards in accordance with the [Specific Plan].”
    CEQA requires an agency to analyze the project in its entirety to ensure all
    potential environmental impacts related to the proposed action are properly considered.
    CEQA’s prohibition against segmentation strives to prevent an agency from dividing a
    single project into smaller pieces and stymieing a complete analysis of potential
    environmental impacts. (Stanislaus Natural 
    Heritage, supra
    , 
    48 Cal. App. 4th 182
    ; Tracy
    
    First, supra
    , 177 Cal.App.4th at pp. 931-932.) Environmental impacts of related projects
    may be analyzed separately when the projects are not dependent on one another. (Del
    Mar Terrace Conservancy, Inc. v. City Council (1992) 
    10 Cal. App. 4th 712
    , 732-735.)
    In the present case, the Specific Plan project and the redevelopment project have
    different purposes and cover different areas. The Specific Plan project covers the
    development of 244 acres within the Richards Boulevard Project Area. In contrast, the
    redevelopment project consists primarily of two parts: (1) amending the boundaries of
    the Richards Boulevard Project Area and renaming the Richards Boulevard Plan, which
    covers 1,068 acres, and (2) creating a Railyards Project Area, covering 300 acres.
    As the trial court pointed out, the project described in the Specific Plan EIR and
    the project described in the Redevelopment EIR are separate and independent, though
    complementary, projects. The Agency provided two objectives for the Redevelopment
    Plan: “To enable the Railyards Area to be developed in accord with the new adopted
    Specific Plan and to provide support and assistance to that development as feasible,
    necessary and appropriate” and “[t]o protect the remaining Richards Boulevard (River
    District) Project Area from the costs and other development constraints particularly
    affecting the Railyards Area.” These objectives go beyond merely procuring funds for
    the Railyards Project Area.
    Castro also argues that, under the analysis in Laurel 
    Heights, supra
    , 47 Cal.3d at
    p. 396, “an EIR must include an analysis of the environmental effects of future expansion
    15
    or other action if: (1) it is a reasonably foreseeable consequence of the initial project; and
    (2) the future expansion or action will be significant in that it will likely change the scope
    or nature of the initial project or its environmental effects.” Castro contends the
    Railyards Redevelopment Project was a foreseeable consequence of the Specific Plan and
    would change the scope of the initial project by adding the tax increment financing
    element.
    However, Castro fails to explain how the Agency’s decision to amend the
    Richards Boulevard Plan was a foreseeable consequence of the City’s adoption of the
    Specific Plan. Nor does Castro explain how the action of removing the Railyards Project
    Area from the larger Richards Boulevard Project Area impacts or changes the nature of
    the land use entitlements approved in the Specific Plan.
    Castro alleges improper segmentation “[b]ecause the physical components of the
    Redevelopment Project are addressed in the [Specific Plan] EIR, there were no additional
    Project components to be analyzed in the Redevelopment EIR. The Railyards
    Redevelopment Plan was prepared solely to provide funding for the [Specific Plan] and
    was therefore part of the ‘whole of the action’ that comprises the Railyards Project.”
    Again, the stated objectives of the Redevelopment EIR are not merely to provide a
    funding mechanism for the project.6
    ANALYSIS OF TAC EMISSIONS
    Castro argues the Redevelopment EIR fails to analyze and mitigate for TAC
    emissions. TAC’s, or toxic air contaminants, are airborne substances that are hazardous
    to health, causing acute and chronic adverse health effects. The California Air Resources
    Board has identified diesel particulate matter (DPM) as a TAC. The railyards are
    exposed to DPM from local freeway diesel truck traffic and diesel trucks operating on the
    6 Since we find no improper segmentation under CEQA, we need not address Castro’s
    claims of prejudice.
    16
    site, diesel-powered locomotives using rail lines that cross the property, and diesel
    emissions from vehicles that would use the Sacramento Intermodal Transportation
    Facility (SITF) proposed for the project site. According to Castro, the Redevelopment
    EIR failed to set forth a legally acceptable standard of significance for TAC’s, no
    substantial evidence supports the standard of significance adopted, and the TAC
    evaluation is inadequate.
    Standards of Significance
    CEQA defines a threshold of significance: “Each public agency is encouraged to
    develop and publish thresholds of significance that the agency uses in the determination
    of the significance of environmental effects. A threshold of significance is an identifiable
    quantitative, qualitative or performance level of a particular environmental effect, non-
    compliance with which means the effect will normally be determined to be significant by
    the agency and compliance with which means the effect normally will be determined to
    be less than significant.” (CEQA Guidelines, § 15064.7, subd. (a).)
    The lead agency determines whether an environmental impact is significant and
    also determines the corresponding threshold of significance. In exercising this discretion
    the agency may rely on threshold of significance data developed by experts, and may also
    rely on a regulatory agency. (Napa Citizens for Honest Government v. Napa County Bd.
    of Supervisors (2001) 
    91 Cal. App. 4th 342
    , 362-363 (Napa Citizens); California Native
    Plant Society v. City of Rancho Cordova (2009) 
    172 Cal. App. 4th 603
    , 625-626 (Native
    Plant Society).)
    Thresholds of significance do not automatically determine whether an
    environmental impact will be significant. Instead, they serve as a marker to determine
    whether a particular impact will normally be determined to be significant or less than
    significant. (Protect the Historic Amador Waterways v. Amador Water Agency (2004)
    
    116 Cal. App. 4th 1099
    , 1108-1109.)
    17
    1.     Redevelopment EIR’s Standard of Significance
    Preliminarily, Castro faults the Redevelopment EIR for adopting a standard of
    significance for TAC’s that finds significance if “[t]he project would substantially
    increase the risk of exposure to TACs.” Castro argues this is not an acceptable
    qualitative standard of significance and is “impermissibly vague.” According to Castro,
    the EIR was required to provide a meaningful standard for TAC’s as expressed as an
    increase in the number of cancer cases per million or another metric that is acceptable in
    the scientific community.
    Here, the Sacramento Metropolitan Air Quality Management District (Air District)
    is the regulatory agency responsible for TAC emissions in the Railyards Project Area.
    However, the Air District does not have a threshold of significance to recommend on
    TAC emissions. As stated in the foreword to the Air District’s “Recommended Protocol
    for Evaluating the Location of Sensitive Land Uses Adjacent to Major Roadways,” this
    document “does not provide an acceptable cancer risk level or a regulatory threshold;
    therefore it does not establish which projects are acceptable and which are not. Local
    land use jurisdictions retain all authority and decide after considering all relevant factors
    whether the project is appropriate.”
    As the trial court noted, the Specific Plan EIR, which the Redevelopment EIR
    incorporates, applied the same qualitative standard of significance to the results obtained
    by two health risk assessments (HRA) prepared by the Environ Corporation to evaluate
    TAC’s. The court determined: “The EIR used a qualitative rather than a quantitative
    standard because there is no established risk from exposure to TACs from mobile
    sources; it is very difficult to set a risk standard from mobile sources; and the existing
    ambient TAC risk within the [Specific Plan] area already exceeds the TAC risk from
    stationary sources, an increase of 10 cancer cases per million people, and would not be
    helpful in measuring whether the TAC emissions from mobile sources project would
    impact the risk of exposure to TACs in the [Specific Plan] area.”
    18
    Interestingly, Castro does not address or even cite these findings. Instead, Castro
    focuses on a letter from the Air District dated April 25, 2008. In the letter, the Air
    District criticized the Specific Plan EIR’s analysis of TAC emissions, stating the analysis
    used in the EIR was outdated and could not be approved at the present time. The letter
    states: “The Air District contends that without a complete analysis of the impact of
    various sources of TACs on the proposed project, it is not accurate to say there will not
    be a ‘substantial increase in the risk.’ ” The Air District also recommended that the
    “proponents perform a site-specific Health Risk Assessment.”
    Subsequently, the Air District on May 2, 2008, sent a letter stating: “[I]t is the
    District’s understanding that the Draft and Final EIRs have analyzed air quality and
    toxics impacts based on the information now known. Because this is a program-level
    EIR, it is understood that more specific information will become available in the future as
    actual projects are identified and that impacts will be reanalyzed for significance prior to
    approval of individual projects. The District concurs with this approach.”
    In its April 25, 2008, letter the Air District expressed concerns about the
    qualitative standard of significance and the methodology used. However, less than a
    month later, the Air District accepted the TAC analysis in the Redevelopment EIR,
    reasoning that it was sufficient for a program-level analysis based on limited information
    about projects in the River District Plan and the portion of the Railyards Plan not covered
    in the Specific Plan. The Air District also explained that it concurred in the methodology
    used in the Specific Plan EIR to assess TAC impacts, but that the methodology was
    constantly evolving and future projects might be required to use a different or modified
    analytical approach. Although Castro attempts to undermine the impact of the May 2,
    2008, letter, the letter provides evidence the Air District accepted the EIR’s TAC analysis
    despite its earlier misgivings.
    19
    Castro also argues that the health risks posed by TAC’s can only be quantitatively
    discussed. In support, Castro cites Berkeley Keep Jets Over the Bay Com. v. Board of
    Port Cmrs. (2001) 
    91 Cal. App. 4th 1344
    (Berkeley Keep Jets).
    In Berkeley Keep Jets, the plaintiffs challenged an agency’s lack of substantive
    analysis of TAC’s. The appellate court found the agency’s TAC analysis defective, in
    part because the EIR stated the health effects of TAC’s were unknown. In addition, the
    agency relied on outdated information in assessing TAC impacts. (Berkeley Keep 
    Jets, supra
    , 91 Cal.App.4th at pp. 1366-1367.) The Agency also failed to research available
    approved protocols to assess the risks associated with mobile TAC emissions. According
    to the court, the agency failed to make “any reasonable conscientious effort . . . to collect
    additional data or to make further inquiries of environmental or regulatory agencies
    having expertise in the matter.” (Id. at p. 1370.) For all these reasons, the court
    concluded the agency must meaningfully attempt to quantify the amount of mobile-
    source emissions that would be emitted during normal operations and determine whether
    those emissions would result in significant health impacts. (Id. at p. 1371.)
    The court in Berkeley Keep Jets did not hold that TAC risks can only be examined
    quantitatively, not qualitatively. Instead, the court considered the woefully inadequate
    discussion of TAC’s in that case and found it wanting. No such egregious gap in analysis
    appears in the present case. Here, the Specific Plan EIR referenced Air District and Air
    Resources Board documents in analyzing TAC impacts. The Specific Plan EIR also
    calculated train and vehicle emissions quantitatively and performed a screening HRA.
    The Agency reviewed the Specific Plan EIR’s TAC analysis and included it in the
    Redevelopment EIR. The Redevelopment EIR did not run afoul of CEQA in employing
    a qualitative standard of significance in analyzing TAC emissions and their
    environmental impact.
    20
    2.     Substantial Evidence
    Castro argues the record does not contain substantial evidence supporting the
    Redevelopment EIR’s TAC standard of significance. According to Castro, the record is
    devoid of any evidence that an expert in air quality formulated the standard of
    significance or any evidence supporting the standard of significance. Under CEQA, we
    must uphold an EIR if there is any substantial evidence in the record to support the
    agency’s decision that the EIR is adequate and complies with CEQA. (Defend the Bay v.
    City of Irvine (2004) 
    119 Cal. App. 4th 1261
    , 1265; National Parks & Conservation
    Assn. v. County of Riverside (1999) 
    71 Cal. App. 4th 1341
    , 1357.)
    Castro argues experts “denigrated” the Redevelopment EIR’s standard of
    significance, and the EIR’s failure to rebut this criticism denotes a lack of substantial
    evidence. According to Castro, the rejection of the standard of significance by the Air
    District’s expert and other experts “shifts the burden of proof to the Agency to justify
    adopting the standard,” a burden the Agency failed to meet.
    However, disagreement by other agencies or experts over an agency’s
    determination that mitigation measures will reduce an adverse impact does not show that
    insufficient evidence supports the determination. The burden is on Castro to
    affirmatively show there was no substantial evidence in the record, not simply that other
    experts disagreed with the analysis. (Native Plant 
    Society, supra
    , 172 Cal.App.4th at
    p. 626.)
    According to Castro, the lack of expert input on the Redevelopment EIR’s
    standard of significance constitutes a dearth of substantial evidence. Castro also faults
    the EIR for failing to provide the qualifications of the individuals who prepared the EIR.
    However, Castro fails to cite any authority requiring expert input in the determination of
    the threshold of significance applied in an EIR. Instead, an agency may rely on
    regulating agencies or an EIR preparer. (Eureka Citizens for Responsible Government v.
    City of Eureka (2007) 
    147 Cal. App. 4th 357
    , 369; Napa 
    Citizens, supra
    , 91 Cal.App.4th at
    21
    pp. 361-363.) Here, the Agency and City relied on the EIR preparers of both the Specific
    Plan EIR and the Redevelopment EIR, with input from the Air District and the Air
    Resources Board, in developing the TAC analysis. Substantial evidence supports the
    Redevelopment EIR’s determination of the applicable standard of significance for TAC
    emissions.
    Adequacy of TAC Evaluation
    Castro contends the record does not support the Redevelopment EIR’s conclusion
    that TAC emissions would be less than significant. Castro argues the lack of a site-
    specific HRA renders the Redevelopment EIR inadequate.
    “The determination of whether a project may have a significant effect on the
    environment calls for careful judgment on the part of the public agency involved, based
    to the extent possible on scientific and factual data.” (CEQA Guidelines, § 15064,
    subd. (b).) According to Castro, the full extent of the Specific Plan EIR analysis is a
    screening HRA, which included potential health risks from DPM’s from the freeway, rail
    lines, and the SITF. Castro argues the lack of a site-specific HRA in the Redevelopment
    EIR, which incorporated the Specific Plan EIR, “is an omission of information from the
    EIR necessary for public review of the Project’s impacts and informed decision-making.”
    This failure to include relevant information violates CEQA.
    We disagree. In order to evaluate the health impacts from exposure to DPM,
    Environ Corporation prepared two HRA’s, which were incorporated into the Specific
    Plan EIR. A screening HRA evaluated the potential cancer risk from DPM emissions
    from mobile sources including the freeway, train emissions, and emissions from the
    SITF. The HRA followed the Air District’s “Recommended Protocol for Evaluating the
    Location of Sensitive Land Uses Adjacent to Roadways.” The HRA also utilized data
    from a traffic study by Dowling Associates to evaluate potential risk to any homes built
    nearby. The HRA concluded the cancer risk for residences 200 feet or more from the
    freeway was less than the criteria in the Air District protocol and therefore no site-
    22
    specific HRA was necessary. In addition, the HRA determined the cancer risk from
    DPM’s from trains was less than the evaluation criterion wherever the residences would
    be located, and a site-specific HRA was not recommended.
    The other HRA evaluated the cancer risk to the community from chemicals that
    could become airborne from soil disturbance and DPM emissions from construction
    equipment used on contaminated sites. The HRA utilized computer modeling and
    guidance from the California and United States Environmental Protection Agencies, and
    applied the National Contingency Plan target cancer risk levels. The HRA concluded the
    health risk to the community surrounding the Specific Plan area from soil and DPM
    emissions during construction was less than the National Contingency Plan target risk
    levels for airborne soil chemicals and slightly higher than 10 in one million for DPM
    emissions. The DPM levels would likely be reduced through various mitigation
    measures.
    Substantial evidence supports the Redevelopment EIR’s conclusion that TAC
    emissions would be less than significant. In addition, the Redevelopment EIR explained
    why no site-specific analysis was performed.
    Subsequent Projects
    Finally, Castro contends the record includes no factual basis for the
    Redevelopment EIR’s conclusion that “ ‘[e]xposure of sensitive receptors to TACs
    through the build-out of planned land uses in the Project Areas would be less than
    significant.’ ” According to Castro, the Agency admitted there would be no requirement
    for all subsequent residential development in the Specific Plan to complete any analysis
    of TAC impacts. Our review of the record proves otherwise.
    The Redevelopment EIR identifies itself as a “Program EIR.” The Redevelopment
    EIR states: “This Program EIR provides a project area-wide environmental analysis and
    framework for subsequent approvals pursuant to adoption and implementation of the
    Proposed Project. As individual activities pursuant to the redevelopment plans are
    23
    proposed, the Agency will examine the individual activities to determine whether their
    effects have been fully evaluated in this Program EIR, and if not, what additional steps
    should be taken. Additional environmental review for the public and private activities or
    undertakings pursuant to or in furtherance of the Proposed Project would be required if
    any of the conditions outlined in [CEQA] Guidelines Sections 15162 or 15163 were to
    occur.”
    In addition, in response to comments from the Air District, the Redevelopment
    EIR states “all future discretionary projects throughout both Project Areas must be
    independently assessed by the City against the adequacy of existing environmental
    documentation,” and “there are more current [Air District] mitigation measures that
    would apply to future development projects.” The Redevelopment EIR contemplates
    subsequent environmental review of TAC emissions for future development.7
    DISPOSITION
    The judgment is affirmed. The Agency shall recover costs on appeal.
    RAYE              , P. J.
    We concur:
    NICHOLSON             , J.
    HULL                  , J.
    7  Castro argues extensively that should we find the Specific Plan EIR invalid in a
    companion case, the Redevelopment EIR should also be decertified. Since we do not
    find the Specific Plan EIR invalid in the companion case, we need not address this
    contention. (Sacramento 
    Citizens, supra
    , C065220.)
    24
    