  • Filed 9/20/13
    CERTIFIED FOR PUBLICATION
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    SECOND APPELLATE DISTRICT
    DIVISION THREE
    HM DG, INC., et al.,                             B242540
    Plaintiffs and Respondents,              (Los Angeles County
    Super. Ct. No. BC475302)
    v.
    FARZAD ETEMAD AMINI AND
    POUNEH BEIZAI, Individually and as
    Trustees, etc.,
    Defendants and Appellants
    Appeal from an order of the Superior Court of Los Angeles County,
    Charles F. Palmer, Judge. Reversed with directions.
    Leo A. Schwarz for Defendants and Appellants.
    Law Offices of James J. Hevener and James J. Hevener for Plaintiffs and
    Respondents.
    _____________________
    INTRODUCTION
    Plaintiffs and Respondents HM DG, Inc. and Hassan Majd doing business as Majd
    Design Group (HMDG) sued Defendants and Appellants Farzad Etemad Amini and
    Pouneh Beizai (Defendants) in the superior court to recover allegedly unpaid progress
    payments under a construction contract for a high-end remodel of Defendants‘ home.
    After HMDG refused Defendants‘ demand to submit the dispute to arbitration,
    Defendants filed a petition to compel arbitration pursuant to an arbitration clause in the
    parties‘ contract. The trial court denied the petition, holding that Defendants failed to
    establish the existence of a valid arbitration agreement on the ground that the ―arbitration
    clause at issue is uncertain in that it does not specify before what agency o[r] person the
    matter will be arbitrated, [or] how the arbitrator will be selected, but merely sets for[th]
    alternative options for these terms.‖ The trial court also awarded HMDG its attorneys
    fees incurred in opposing the petition to compel arbitration. We reverse.
    Code of Civil Procedure section 1281.61 specifically contemplates the existence of
    an enforceable arbitration agreement even where the ―arbitration agreement does not
    provide a method for appointing an arbitrator . . . .‖ The statute further provides that
    ―[i]n the absence of an agreed method, or if the agreed method fails . . . , the court, on
    petition of a party to the arbitration agreement, shall appoint the arbitrator.‖ (Ibid.) As
    we shall explain, because the court has the power to appoint an arbitrator under section
    1281.6 when the parties fail to agree upon a method for appointment, we conclude that
    neither the absence of a definite method, nor the presence of ―alternative options,‖ for
    appointing an arbitrator renders an otherwise valid arbitration agreement unenforceable.
    As we find the agreement to arbitrate is valid, and that Defendants demanded
    arbitration in accordance with the subject arbitration clause, we will reverse the trial
    court‘s order. However, because the trial court did not reach the question of whether any
    1
    Unless otherwise specified, statutory references are to the Code of Civil
    Procedure.
    2
    other ground for denying the petition under section 1281.2 applies, we will remand the
    matter for the trial court to consider this issue.
    FACTUAL SUMMARY
    In early 2010, Defendants, husband and wife, approached HMDG about
    remodeling their home. After discussions regarding the project parameters, HMDG
    presented Defendants with a three page ―Project Proposal & Agreement‖ (Agreement).
    A clause entitled ―Arbitration Clause‖ located directly above the Agreement‘s
    signature line provides:
    ―In the event a dispute shall arise between the parties to this contract, it is
    hereby agreed that the dispute shall be referred to [one of the following
    choices: (1) designate a specific USA&M office or alternate service by
    agreement of the parties; (2) provide a method of selecting the arbitrator
    and suits of the hearing, such as ‘from the county wherein the
    manufacturing plant is located’; or for multi-jurisdictional disputes
    (3) insert ‘a USA&M office to be designated by USA&M National
    Headquarters’] for arbitration in accordance with the applicable United
    States Arbitration and Mediation Rules of Arbitration. The arbitrator’s
    decision shall be final and legally binding and judgment may be entered
    thereon.
    “Each party shall be responsible for its share of the arbitration fees in
    accordance with the applicable Rules of Arbitration. In the event a party
    fails to proceed with arbitration, unsuccessfully challenges the arbitrator’s
    award, or fails to comply with the arbitrator’s award, the other party is
    entitled to costs of suit, including a reasonable attorney’s fee for having to
    compel arbitration or defend or enforce the award.‖2 (Bracketed text and
    italics in original.)
    2
    ―USA&M‖ is an acronym for United States Arbitration and Mediation. The
    clause‘s reference to ―suits of the hearing‖ is an apparent typographical error. The
    parties agree that the clause should read ―situs of the hearing.‖
    3
    After reviewing the Agreement, which was prepared by HMDG, Defendants
    executed the Agreement without requesting any changes to the Arbitration Clause. Mr.
    Majd executed the Agreement on behalf of HMDG.
    In mid-2011, a dispute arose between HMDG and Defendants regarding the
    quality of the remodeling work, Defendants‘ requests to make substantial changes to the
    project‘s scope, and Defendants‘ alleged failure to make prompt progress payments as
    required by the Agreement. On July 9, 2011, HMDG made a proposal to resolve the
    dispute by having Defendants place funds sufficient to complete the remaining project
    items into an escrow account. Although HMDG‘s proposal contained numerous
    references to arbitration, no formal demand for arbitration was made. When Defendants
    refused the proposal, HMDG served a 10-day stop work order and recorded a mechanic‘s
    lien on the property.
    On December 15, 2011, HMDG filed a complaint against Defendants in the
    superior court, asserting claims for breach of contract, a common count for money due
    under the contract, foreclosure of mechanics lien, unjust enrichment, and violation of the
    prompt payment statute—Civil Code section 3260.1.
    On February 21, 2012, Defendants‘ counsel, Leo A. Schwarz, sent a letter to
    counsel for HMDG, James J. Hevener. Mr. Schwarz‘s letter reads, in pertinent part:
    ―Please accept this letter as defendants‘ demand that all of the claims
    raised by plaintiffs in their complaint in the Action, as well as the claims to
    be made by defendants, be arbitrated per the ‗Arbitration Clause‘ found on
    Page 3 of the June 24, 2010 ‗Project Proposal and Agreement‘. As
    USA&M, one of the designated potential arbitration providers, does not
    have a presence in Los Angeles County or the State of California, we
    propose that the parties avail themselves to Option No. 2 of the Arbitration
    Clause, where a method of selecting the arbitrator is provided. Defendants
    propose that: (1) the matter be heard by a retired judge with substantial
    construction and home improvement contract experience; (2) each party
    select two neutral such judges, with each party allowed to strike one of the
    4
    other party‘s selections; (3) the arbitrator is then randomly selected from
    the remaining two judges; (4) the California arbitration rules (C.C.P.
    [§] 1281 et seq.) be adopted as the rules of arbitration; (5) the terms set
    forth in the second paragraph of the Arbitration Clause remain in effect;
    and (6) the Action will be stayed pending the Arbitrator‘s award, however,
    defendants‘ right to seek expungement of the mechanic‘s lien prior to the
    arbitration hearing shall not be stayed.‖ (Underscoring omitted.)
    The next day, February 22, 2012, Mr. Hevener wrote back to Mr. Schwarz that
    HMDG found ―[the] proposal unreasonable and not required by the Project Proposal and
    Agreement.‖ Mr. Hevener‘s letter continued: ―Please proceed with filing your
    responsive pleading today. [¶] My client remains open to discussing settlement of this
    dispute including a reasonable process for alternative dispute resolution.‖
    On February 22, 2012, Defendants filed a petition to compel arbitration pursuant
    to the Agreement‘s Arbitration Clause. The petition was supported by Defendants‘
    declarations and a declaration by their attorney, attaching the Agreement, Mr. Schwarz‘s
    letter demanding arbitration, and Mr. Hevener‘s response.
    On June 13, 2012, after a hearing on Defendants‘ petition, the trial court issued an
    order denying the petition and awarding HMDG attorney fees in the amount of $2,430.
    In pertinent part, the court‘s order states: ―[D]efendants have failed to meet their burden
    of proving the existence of a valid arbitration agreement. Specifically, the arbitration
    clause at issue is uncertain in that it does not specify before what agency o[r] person the
    matter will be arbitrated, [or] how the arbitrator will be selected, but merely sets for[th]
    alternative options for these terms. At most the agreement provides that these questions
    are to be resolved in the future which . . . ‗gives rise to no legal obligation until such
    future agreement.[‘] Moreover, defendants‘ demand for arbitration itself reflects that
    there was a lack of mutual consent insofar as it proposes terms nowhere set forth in the
    putative arbitration agreement.‖ The trial court‘s order states no other ground for
    denying Defendants‘ petition.
    5
    ISSUES PRESENTED
    In this appeal, we must decide whether the subject Arbitration Clause constitutes a
    valid arbitration agreement, notwithstanding the presence of multiple alternative methods
    for selecting an arbitrator in the clause. We also will address HMDG‘s contention that
    the presence of these alternatives in the Arbitration Clause establishes that there was no
    mutual consent to arbitrate. Finally, we will address HMDG‘s contention that
    Defendants‘ demand for arbitration was defective because it included proposals that did
    not strictly conform to the terms of the Arbitration Clause.
    Based on a plain reading of section 1281.6, we conclude that the Arbitration
    Clause is both valid and establishes the parties‘ mutual consent to arbitrate,
    notwithstanding the clause‘s various options for selecting an arbitrator. We also
    conclude that Defendants‘ demand for arbitration was consistent with the terms of the
    Arbitration Clause. Accordingly, we will reverse the order denying Defendant‘s petition.
    However, because the trial court did not reach other potential grounds for denying the
    petition under section 1281.2, we will remand the matter for the court to consider these
    issues.
    DISCUSSION
    A.     Section 1281.6 Makes Clear that the Parties Need Not Agree Upon a
    Specific Method for Appointing an Arbitrator to Form a Binding
    Arbitration Agreement
    In denying Defendants‘ petition to compel arbitration, the trial court determined
    that the Arbitration Clause was not ―a valid arbitration agreement‖ because the clause
    ―does not specify before what agency o[r] person the matter will be arbitrated, [or] how
    the arbitrator will be selected, but merely sets for[th] alternative options for these terms.‖
    The court‘s conclusion assumes the premise that an arbitration agreement must identify a
    specific arbitrator or specify a single method for selecting an arbitrator in order to be
    valid. That premise, as we shall explain, is contrary to a plain reading of section 1281.6
    and, thus, cannot support the trial court‘s denial of Defendants‘ petition to compel
    arbitration.
    6
    As our resolution of this issue rests on the interpretation of a statute and the
    application of that statute to undisputed facts—in this case, section 1281.6 and the terms
    of the written Arbitration Clause—the issue is subject to this court‘s independent or de
    novo review. (People ex rel. Lockyer v. Shamrock Foods Co. (2000) 
    24 Cal.4th 415
    ,
    432; International Engine Parts, Inc. v. Feddersen & Co. (1995) 
    9 Cal.4th 606
    , 611; City
    of Saratoga v. Hinz (2004) 
    115 Cal.App.4th 1202
    , 2012.)
    We begin with the well-settled canons of statutory construction. ―In statutory
    construction cases, our fundamental task is to ascertain the intent of the lawmakers so as
    to effectuate the purpose of the statute. [Citation.] ‗We begin by examining the statutory
    language, giving the words their usual and ordinary meaning.‘ [Citations.] If the terms
    of the statute are unambiguous, we presume the lawmakers meant what they said, and the
    plain meaning of the language governs. [Citations.]‖ (Estate of Griswold (2001)
    
    25 Cal.4th 904
    , 910–911 (Estate of Griswold), quoting Day v. City of Fontana (2001)
    
    25 Cal.4th 268
    , 272.)
    Section 1281.6 states: ―If the arbitration agreement provides a method of
    appointing an arbitrator, that method shall be followed. If the arbitration agreement does
    not provide a method for appointing an arbitrator, the parties to the agreement who seek
    arbitration and against whom arbitration is sought may agree on a method of appointing
    an arbitrator and that method shall be followed. In the absence of an agreed method, or if
    the agreed method fails or for any reason cannot be followed, or when an arbitrator
    appointed fails to act and his or her successor has not been appointed, the court, on
    petition of a party to the arbitration agreement, shall appoint the arbitrator.‖ (Italics
    added.)
    A plain reading of section 1281.6 yields only one reasonable interpretation—that
    the validity of an arbitration agreement is not contingent upon the agreement identifying
    a specific arbitrator or specifying a particular method for appointing an arbitrator.
    Moreover, if an arbitration agreement that ―does not provide a method for appointing an
    arbitrator‖ is valid [§ 1281.6], then it follows that an agreement which provides multiple
    alternative methods for appointing an arbitrator also is valid, even though it does not
    7
    specify a particular method for appointment. Indeed, even where the parties are unable to
    agree upon a specific method for appointing an arbitrator, section 1281.6 provides a
    solution to ensure a party‘s contractual right to arbitrate is enforced. In such instances,
    section 1281.6 provides that ―the court, on petition of a party to the arbitration agreement,
    shall appoint the arbitrator.‖
    Consistent with our plain reading of section 1281.6, we hold that the presence of
    multiple alternative methods for selecting an arbitrator in the Arbitration Clause does not
    render the clause invalid or unenforceable.3 The trial court erred in finding that
    Defendants failed to meet their burden of establishing the existence of a valid arbitration
    agreement.
    B.     The Arbitration Clause Establishes the Parties’ Mutual Consent to
    Arbitrate
    HMDG contends that the presence of ―options for key terms such as selection of
    the specific Office of USA&M [that] would administer the arbitration and provide the
    associated arbitration rules, how the arbitrator would be selected, and the location for the
    arbitration hearing‖ demonstrates that there was ―no meeting of the minds‖ or mutual
    3
    We hold this interpretation follows from a plain reading of section 1281.6. But
    even were we to view the statutory language as ambiguous with respect to an arbitration
    agreement that provides numerous options for appointing an arbitrator, we would reach
    the same conclusion. Where statutory language is susceptible of more than one possible
    interpretation, ―we ‗ ― ‗select the construction that comports most closely with the
    apparent intent of the Legislature, with a view to promoting rather than defeating the
    general purpose of the statute, and avoid an interpretation that would lead to absurd
    consequences.‘ ‖ ‘ [Citation.]‖ (Estate of Griswold, supra, 25 Cal.4th at p. 911.) Section
    1281.6 is part of a ―detailed statutory scheme,‖ through which ―the Legislature has
    expressed a ‗strong public policy in favor of arbitration as a speedy and relatively
    inexpensive means of dispute resolution.‘ [Citations.]‖ (Moncharsh v. Heily & Blase
    (1992) 
    3 Cal.4th 1
    , 9.) The statute plainly contemplates a valid and enforceable
    arbitration agreement, even where the parties have failed to specify a method for
    appointing an arbitrator. Given the strong public policy favoring arbitration, it would be
    an absurd consequence to hold that an agreement that provides no method for appointing
    an arbitrator is valid, while an agreement that provides multiple alternative methods for
    appointing an arbitrator is invalid.
    8
    consent to arbitrate. We disagree. Contrary to HMDG‘s contention, the plain language
    of the Arbitration Clause, combined with the parties‘ signatures directly under the clause,
    establishes the parties‘ mutual consent to submit their disputes to ―arbitration in
    accordance with the applicable United States Arbitration and Mediation Rules of
    Arbitration‖ and to be bound by the ―arbitrator‘s decision.‖~(CT 38)~ The presence of
    options regarding the method for selecting an arbitrator or the location of the arbitration
    hearing do not negate that clear intention.
    ―Contract formation requires mutual consent, which cannot exist unless the parties
    ‗agree upon the same thing in the same sense.‘ ‖ (Bustamante v. Intuit, Inc. (2006)
    
    141 Cal.App.4th 199
    , 208 (Bustamante), quoting Civ. Code, § 1580; see also Civ. Code,
    §§ 1550, 1565.) ― ‗Mutual assent is determined under an objective standard applied to
    the outward manifestations or expressions of the parties, i.e., the reasonable meaning of
    their words and acts, and not their unexpressed intentions or understandings.‘
    [Citations.]‖ (Bustamante, at p. 208.) ―Where the existence of a contract is at issue and
    the evidence is conflicting or admits of more than one inference, it is for the trier of fact
    to determine whether the contract actually existed. But if the material facts are certain or
    undisputed, the existence of a contract is a question for the court to decide.‖ (Ibid.;
    Robinson & Wilson, Inc. v. Stone (1973) 
    35 Cal.App.3d 396
    , 407 [―the question whether
    the contract . . . is sufficiently definite and certain in its essential terms to give rise to a
    legal obligation is a question of law‖].) Because HMDG‘s contention rests on the
    language of the Arbitration Clause, and the presence of ―options for key terms‖ in the
    clause, we review the issue as a question of law, without deference to purported factual
    determinations made by the trial court.4
    4
    The trial court stated in its order that ―defendants‘ demand for arbitration itself
    reflects that there was a lack of mutual consent insofar as it proposes terms nowhere set
    forth in the putative arbitration agreement.‖ HMDG contends this was a ―key factual
    determination[ ]‖ and urges us to review the question of mutual consent under the
    substantial evidence standard. As we have explained, because the trial court‘s purported
    factual determination is, like HMDG‘s mutual consent argument, based entirely upon the
    terms of the Arbitration Clause, the issue is subject to our independent review.
    9
    HMDG‘s contention regarding the purported lack of mutual consent is largely
    disposed of by our earlier analysis of section 1281.6. As explained, section 1281.6 makes
    clear that the absence of a specified method for appointing an arbitrator neither
    invalidates an arbitration agreement nor negates the parties‘ clearly expressed intent to
    submit their disputes to arbitration. Accordingly, HMDG‘s argument that mutual consent
    is lacking because the Arbitration Clause did not specify ―the specific Office of USA&M
    [that] would administer the arbitration‖ or ―how the arbitrator would be selected‖ is
    without merit.
    For much the same reason, we are not persuaded by HMDG‘s contentions
    regarding the purported options related to the ―associated arbitration rules‖ and ―the
    location of the arbitration hearing.‖ We view these matters as part and parcel with the
    appointment of an arbitrator—that is, for example, if the parties were to elect to appoint
    an American Arbitration Association (AAA) arbitrator, that appointment would entail
    arbitration in a AAA forum under AAA rules. Thus, under section 1281.6, the absence of
    a specified forum or set of rules in an arbitration clause does not invalidate the agreement
    to arbitrate. Rather, in the absence of such provisions, ―the parties to the agreement who
    seek arbitration and against whom arbitration is sought may agree on a method of
    appointing an arbitrator‖—including the forum and rules that will govern the
    arbitration—or, if the parties cannot agree, ―the court, on petition of a party to the
    arbitration agreement, shall appoint the arbitrator.‖ (§ 1281.6.)
    HMDG contends that ―arbitration rules and forum are material terms of an
    agreement to arbitrate‖ and, thus, must be specified in the agreement to establish mutual
    consent. This contention goes too far and is not supported by the authorities cited by
    HMDG. On the contrary, the authorities HMDG cites implicitly recognize the conclusion
    we reach.
    10
    In support of its contention, HMDG cites Martinez v. Master Protection Corp.
    (2004) 
    118 Cal.App.4th 107
    , 121 (Martinez) for the proposition that ― ‗ ―[a]n agreement
    to arbitrate before a particular forum is as integral a term of a contract as any other, which
    courts must enforce.‖ ‘ [Citations.]‖ The arbitration clause in Martinez ―require[d] that
    the arbitration be conducted in accordance with specific procedures promulgated by the
    AAA . . . .‖ (Id. at p. 120.) The plaintiff ―submitted his claims to the AAA, but [AAA]
    refused to conduct a hearing.‖ (Ibid.) The trial court nevertheless ordered the parties to
    arbitrate, and ―appointed another arbitrator‖ pursuant to section 1281.6. (Martinez, at
    p. 120.) The Martinez court reversed. As the court correctly concluded, ―[s]ection
    1281.6 does not permit the trial court to choose an alternative forum when the chosen
    forum refuses to hear the case.‖ (Id. at p. 121.) That conclusion follows from the plain
    language of section 1281.6: ―If the arbitration agreement provides a method of
    appointing an arbitrator, that method shall be followed.‖ But this does not mean, as
    HMDG contends, that section 1281.6 is inapplicable where the parties have provided a
    list of alternative methods for selecting an arbitrator and forum. Indeed, Martinez
    implicitly recognizes, as we do, that the selection of an arbitral forum is part and parcel
    with the appointment of an arbitrator. (See Martinez, at p. 120 [rejecting contention that
    trial court properly appointed a non-AAA arbitrator with the proviso that AAA rules be
    followed on ground that the ―requirement for resolution of the present dispute ‗in
    accordance with‘ pertinent AAA procedures means that the arbitration must take place
    before that designated agency, that is, in an AAA forum‖ before an AAA arbitrator].)
    Alan v. Superior Court (2003) 
    111 Cal.App.4th 217
     (Alan), like Martinez,
    recognizes that a court cannot invoke section 1281.6 to make an appointment that is
    inconsistent with the forum and set of rules required by the parties‘ agreement. The
    arbitration clause at issue in Alan provided: ― ‗[A]ny arbitration … shall be conducted
    before an arbitration panel convened by the [NYSE] or the [NASD]. . . . Such arbitration
    shall be governed by the rules of the organization convening the panel.‘ ‖ (Alan, at
    p. 224, italics added by Alan.) Because it viewed the designated arbitral forums and rules
    to be ―an integral part‖ of the parties‘ agreement to arbitrate, the Alan court rejected the
    11
    argument that a court could simply appoint another arbitrator under section 1281.6 when
    the designated organizations refused to hear the dispute. (Alan, at p. 224.) However, the
    court did not hold, as HMDG contends, that the presence of choices regarding the forum
    and rules—i.e., ― ‗an arbitration panel convened by the [NYSE] or the [NASD]‘ ‖ and
    ― ‗governed by the rules of the organization convening the panel‘ ‖—invalidated the
    agreement.
    Here, notwithstanding the presence of options for selecting an arbitrator, the
    arbitration forum and the USA&M rules to be applied, a plain reading of the Arbitration
    Clause clearly evidences the parties‘ intention to submit their disputes to arbitration. The
    Arbitration Clause unequivocally states: ―In the event a dispute shall arise between the
    parties to this contract, it is hereby agreed that the dispute shall be referred to [one of
    three choices for appointing an arbitrator] . . . for arbitration in accordance with the
    applicable United States Arbitration and Mediation Rules of Arbitration. The arbitrator‘s
    decision shall be final and legally binding and judgment may be entered thereon.‖
    (Bracketed text added, italics omitted.) No more was required to form a binding
    agreement to arbitrate. (See Cheng-Canindin v. Renaissance Hotel Associates (1996)
    
    50 Cal.App.4th 676
    , 687-688 [―although arbitration can take many procedural forms, a
    dispute resolution procedure is not an arbitration unless there is a third party decision
    maker, a final and binding decision, and a mechanism to assure a minimum level of
    impartiality with respect to the rendering of that decision‖].)
    C.     Defendants Properly Demanded Arbitration in Accordance with the
    Arbitration Clause and Section 1281.2
    Subject to exceptions that are not properly before us,5 section 1281.2 provides
    that: ―On petition of a party to an arbitration agreement alleging the existence of a
    5
    Notwithstanding the existence of an agreement to arbitrate, section 1281.2,
    subdivision (c) authorizes the trial court to refuse to enforce the arbitration agreement
    or stay the arbitration proceeding ―[i]f the court determines that a party to the arbitration
    is also a party to litigation in a pending court action or special proceeding with a third
    party as set forth under subdivision (c) . . . .‖ In its opposition to Defendants‘ petition
    to compel arbitration, HMDG argued that the petition should be denied under
    12
    written agreement to arbitrate a controversy and that a party thereto refuses to arbitrate
    such controversy, the court shall order the petitioner and the respondent to arbitrate the
    controversy if it determines that an agreement to arbitrate the controversy exists . . . .‖
    The statute does not explicitly require the petitioning party to establish that a proper
    demand for arbitration was made. Nevertheless, a ―necessary implication‖ of the
    language requiring ― ‗the existence of a written agreement to arbitrate a controversy and
    that a party thereto refuses to arbitrate such controversy‘ . . . is that a request or demand
    for arbitration under the written agreement to arbitrate has been made and refused.‖
    (Mansouri v. Superior Court (2010) 
    181 Cal.App.4th 633
    , 641, italics added (Mansouri),
    quoting § 1281.2.)
    Having determined that Defendants established the existence of a valid arbitration
    agreement, we turn to HMDG‘s contention that Defendants failed to make a proper
    demand for arbitration. HMDG contends that the February 21, 2012 letter from
    Defendants‘ attorney did not meet the standard articulated in Mansouri because the letter
    included proposed ―terms to which [HMDG] had not agreed.‖ As HMDG‘s contention
    turns upon undisputed evidence—i.e., the contents of the February 21, 2012 letter and the
    written Arbitration Clause—we review the issue de novo. (Mooney v. County of Orange
    (2013) 
    212 Cal.App.4th 865
    , 872.)
    subdivision (c) because HMDG had filed a cross-complaint in a related superior court
    action filed by one of its subcontractors concerning work performed on Defendants‘
    home. Because the trial court found that Defendants failed to establish the existence of
    a valid arbitration agreement, the court did not reach this issue. Accordingly, we will
    remand this matter for the trial court to consider the application of subdivision (c), which
    may require the court to make factual determinations and exercise its discretion in
    accordance with section 1281.2. The trial court also may consider other statutory
    defenses raised by HMDG, such as waiver under section 1281.2, subdivision (a).
    (See Rosenthal v. Great Western Fin. Securities Corp. (1996) 
    14 Cal.4th 394
    , 413.)
    13
    We conclude the February 21, 2012 letter was a demand ―pursuant to and under
    the terms of [the parties‘] written arbitration agreement‖ as required by section 1281.2.
    (Mansouri, supra, 181 Cal.App.4th at p. 641, italics omitted.) The letter states, in no
    uncertain terms: ―Please accept this letter as defendants‘ demand that all of the claims
    raised by plaintiffs in their complaint in the Action, as well as the claims to be made by
    defendants, be arbitrated per the ‗Arbitration Clause‘ found on Page 3 of the June 24,
    2010 ‗Project Proposal and Agreement‘.‖
    In arguing that the letter improperly demanded arbitration in variance with the
    parties‘ agreement, HMDG focuses on the letter‘s next two sentences, in which
    Defendants ―propose that the parties avail themselves to Option No. 2 of the Arbitration
    Clause‖ and ―propose‖ six additional points concerning the arbitration and pending civil
    action. While it is true, as HMDG contends, that two of the proposed points did not
    ―strictly [track] the parties‘ actual agreement,‖ this does not undermine the operative
    demand for arbitration.6 Those points were, as Defendants labeled them, ―proposals,‖
    and HMDG was invited to negotiate those points consistent with ―Option No. 2 of the
    Arbitration Clause.‖7 The operative demand, however, offered no room for negotiation—
    it made specific reference to the Arbitration Clause and demanded that the claims be
    submitted to arbitration pursuant to ―the ‗Arbitration Clause‘ found on Page 3 of the June
    24, 2010 ‗Project Proposal and Agreement‘.‖
    6
    As quoted in the factual summary, most of Defendants‘ proposed points concerned
    the method for selecting an arbitrator. Defendants, however, also proposed that ―the
    California arbitration rules (C.C.P. [§] 1281 et seq.) be adopted as the rules of
    arbitration‖—a proposal that does not strictly track the Arbitration Clause‘s requirement
    ―for arbitration in accordance with the applicable United States Arbitration and
    Mediation Rules of Arbitration.‖ Defendants also proposed that the court action be
    stayed pending the arbitrator‘s award, except with respect to Defendants‘ ―right to seek
    expungement of the mechanic‘s lien.‖ Because the Arbitration Clause does not
    contemplate that there will be a court action, it naturally makes no provision for the trial
    court to retain some aspect of a case that is sent to arbitration.
    7
    As set forth in the factual summary, Option No. 2 of the Arbitration Clause states
    that the parties may ―provide a method of selecting the arbitrator and [situs] of the
    hearing . . . .‖
    14
    This clear invocation of the Arbitration Clause, coupled with the negotiable nature
    of the proposed terms, distinguishes Defendants‘ demand for arbitration from the demand
    that the court found to be defective in Mansouri, supra, 
    181 Cal.App.4th 633
    . In
    Mansouri, the plaintiff and defendant entered into an arbitration agreement providing for
    arbitration before a three-person panel. (Id. at p. 637.) Prior to filing a petition to compel
    arbitration, the plaintiff wrote a letter to defendant demanding that she agree to submit to
    ―binding arbitration before a single arbitrator, unilaterally preselected by the [plaintiff].‖
    (Ibid.) ―The letter indicated that if [defendant] did not agree, the [plaintiff] would file ‗a
    court action for injunctive and declaratory relief and attorneys fees to enforce [her]
    compliance.‘ ‖ (Italics omitted.) The Mansouri court held that the plaintiff ―failed to
    show it requested that [defendant] arbitrate pursuant to and under the terms of [their
    written arbitration agreement]‖ as required by section 1281.2. (Id. at p. 642.) The court
    based its conclusion on the following defects in the purported demand for arbitration:
    ―The letter made no reference to the arbitration provision of the [parties‘ agreement], did
    not offer the three-person form of arbitration set forth in [the arbitration provision], and
    did not inform [defendant] that a petition to compel arbitration would be filed if she
    refused.‖ (Id. at p. 637.)
    Unlike the demand in Mansouri, Defendants‘ February 21, 2012 letter
    (1) demanded arbitration pursuant to ―the ‗Arbitration Clause‘ found on Page 3 of the
    June 24, 2010 ‗Project Proposal and Agreement‘ ‖; (2) proposed ―that the parties avail
    themselves to Option No. 2 of the Arbitration Clause‖ for selecting an arbitrator; and
    (3) advised that Defendants would ―file [a] motion to compel arbitration‖ if HMDG
    rejected the demand to arbitrate. HMDG rejected the demand and instructed Defendants
    to ―proceed with filing your responsive pleading . . . .‖ There was a ―demand for
    arbitration under the parties‘ arbitration agreement and a refusal to arbitrate under the
    agreement.‖ (Mansouri, supra, 181 Cal.App.4th at p. 640.)
    15
    Finally, insofar as HMDG refused to negotiate a method for selecting an arbitrator
    pursuant to one of the options set forth in the Arbitration Clause, we observe that the trial
    court was authorized to appoint an arbitrator pursuant to section 1281.6. As discussed,
    section 1281.6 provides that ―[i]n the absence of an agreed method, or if the agreed
    method fails or for any reason cannot be followed, . . . the court, on petition of a party to
    the arbitration agreement, shall appoint the arbitrator.‖ That appointment must be made
    in a manner consistent with one of the options set forth in the Arbitration Clause. (Ibid.
    [―If the arbitration agreement provides a method of appointing an arbitrator, that method
    shall be followed.‖].) However, because Option No. 2 allows for essentially any ―method
    of selecting the arbitrator and [situs] of the hearing,‖ this is not a case in which
    appointing an arbitrator in a manner consistent with the parties‘ agreement would be
    impossible if the parties are ultimately unable to agree upon a method.8
    Defendants met their burden under section 1281.2 of showing a valid written
    agreement to arbitrate a controversy; a demand to arbitrate such controversy pursuant to
    and under the terms of the written arbitration agreement; and the refusal to arbitrate such
    controversy pursuant to and under the terms of the written arbitration agreement.
    (Mansouri, supra, 181 Cal.App.4th at p. 641.) Accordingly, we will reverse the order
    denying Defendants‘ petition to compel arbitration and remand the matter for the trial
    court to consider whether any defense or exception under section 1281.2 applies.
    8
    The instant case is thus different from Alan, supra, 
    111 Cal.App.4th 217
     and
    Martinez, supra, 
    118 Cal.App.4th 107
     where the appellate courts held that section 1281.6
    did not authorize the trial courts to appoint an arbitrator in a manner inconsistent with the
    parties‘ arbitration agreements. As discussed above, in both Alan and Martinez, the
    parties‘ agreements identified specific arbitration service providers that were to arbitrate
    their disputes. (See Alan, at p. 224 [― ‗[A]ny arbitration . . . shall be conducted before an
    arbitration panel convened by the [NYSE] or the [NASD]‘ ‖]; Martinez, at p. 120
    [agreement ―require[d] that the arbitration be conducted in accordance with specific
    procedures promulgated by the AAA‖].) In both cases, the specified arbitration service
    providers would not hear the parties‘ disputes and, hence, the trial court was unable to
    follow the ―method of appointing an arbitrator‖ provided by the parties‘ agreements.
    (§ 1281.6.) Given the flexibility of Option No. 2 of the Arbitration Clause, that
    circumstance is not present here.
    16
    DISPOSITION
    The order denying the petition to compel arbitration is reversed. The award of
    $2,430 in attorney fees to HMDG is vacated. The case is remanded with directions to
    conduct additional proceedings, which are consistent with the views expressed herein.
    Defendants shall recover their costs in connection with this appeal.
    CERTIFIED FOR PUBLICATION
    HEESEMAN, J.
    We concur:
    CROSKEY, Acting P. J.
    KITCHING, J.
    Judge of the Los Angeles Superior Court, assigned by the Chief Justice pursuant to
    article VI, section 6 of the California Constitution.