Travelers Casualty etc. v. Berger Foundation CA4/3 ( 2014 )


Menu:
  • Filed 9/25/14 Travelers Casualty etc. v. Berger Foundation CA4/3
    NOT TO BE PUBLISHED IN OFFICIAL REPORTS
    California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
    publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication
    or ordered published for purposes of rule 8.1115.
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    FOURTH APPELLATE DISTRICT
    DIVISION THREE
    TRAVELERS CASUALTY & SURETY
    COMPANY OF AMERICA,
    G049802
    Plaintiff and Appellant,
    (Super. Ct. No. INC085539)
    v.
    OPINION
    THE H.N. & FRANCES C. BERGER
    FOUNDATION,
    Defendant and Respondent.
    Appeal from a judgment of the Superior Court of Riverside County,
    Randall Donald White, Judge. Reversed.
    Anderson, McPharlin & Conners, Mark E. Aronson and Vanessa S. Davila
    for Plaintiff and Appellant.
    Hennelly & Grossfeld and Ronald K. Giller for Defendant and Respondent.
    *                  *                  *
    INTRODUCTION
    Travelers Casualty & Surety Company of America (Travelers) was
    substituted into this action as real party in interest to assert plaintiff Granite Construction
    Company’s (Granite) claim for foreclosure of a mechanic’s lien. Travelers appeals from
    the judgment entered after the trial court granted defendant The H.N. & Frances C.
    Berger Foundation’s (Berger) motion for summary judgment. We reverse. Triable issues
    of material fact exist as to whether Granite’s mechanic’s lien was effective under Civil
    1
    Code former section 3097. The trial court therefore erred by granting summary
    judgment. In our opinion, we address the most significant triable issues of material fact
    in parts III., IV., and V. of the Discussion section.
    SUMMARY OF THE PARTIES’ EVIDENCE
    In 2003, Berger, a charitable foundation, acquired a 446-acre tract of land
    in Palm Desert. Berger developed part of the property into a fully functional 240-acre
    golf course and chose not to develop the remainder of the property. Berger gifted the
    golf course to the Bob Hope Desert Classic golf tournament and sought a developer to
    purchase the remainder of the property.
    In September 2006, Desert Gold Ventures, LLC (Desert Gold), was
    interested in acquiring the property from Berger to develop a resort named the Delfino
    Resort. Part of Desert Gold’s plan was to contract with Granite, a contractor, to begin the
    development of the property by making improvements on the sides of Varner Road
    located on the property. At an unspecified date, but no later than November 7, 2006,
    Berger dedicated Varner Road to the County of Riverside (the County).
    1
    Title 15 of part 4 of division 3 of the Civil Code, addressing mechanic’s liens,
    was repealed as of July 1, 2012. (Stats. 2010, ch. 697, § 16.) All further statutory
    references are to former sections of the Civil Code unless otherwise specified.
    2
    Copies of e-mails exchanged between representatives of Granite, Desert
    Gold, and CalVest Industries (CalVest) (CalVest was later engaged to serve as
    construction manager of the project) included an e-mail by Attorney Sara D. Harris of
    Rutter Hobbs & Davidoff Incorporated (representing Desert Gold), dated September 26,
    2006, stating: “I spoke to the Berger Foundation’s attorney regarding the unlikely event
    the buyer does not acquire the property and whether the seller would assume the
    obligations of the ‘Owner’ under the Granite contract. The response from the Berger
    Foundation is ‘no’. They believe that the contract price is too high. Apparently, the
    Berger Foundation is acting as the contractor and retaining subcontractors to do the work
    on their portion of Varner Road. As stated in an email I received from the seller’s
    attorney, the Berger Foundation will ‘indicate to Granite that they are allowing the
    roadwork to commence prior to Desert Gold closing of the property but this could not
    involve any undertaking by the Foundation to honor Desert Gold’s contract with
    Granite.’ [¶] I will check with the Foundation’s counsel to see if the Berger Foundation
    will agree to assume the responsibility of paying Granite for any work performed on the
    property prior to date the Granite contract is terminated due [to] the failure of escrow to
    2
    close on the purchase of the property by Desert Gold.”
    In October 2006, Desert Gold entered into an agreement with Granite, in
    which Granite agreed to perform road and water improvement work along the
    approximately one-mile stretch of Varner Road (the Granite contract). The work
    included widening Varner Road from two lanes to six lanes (which required curb, gutter,
    asphalt, sidewalk, and storm drain work) and installing a 24-inch water line along the
    length of the road and a domestic water crossing underneath the road. The amount of the
    2
    Among raising a host of other evidentiary objections in support of its motion for
    summary judgment, Berger argued in the trial court that the e-mail exchange, cited ante,
    was unauthenticated and inadmissible. The trial court overruled all evidentiary
    objections. Berger does not argue on appeal that the trial court abused its discretion with
    regard to any evidentiary objection rulings.
    3
    Granite contract was $8,225,000. Also in October, Desert Gold contracted with CalVest
    to provide Desert Gold construction management services at the project.
    Although Berger was still the owner of the property at the time Desert Gold
    and Granite entered into the Granite contract, Berger was not a party to that agreement.
    The record shows the normal chronology of events for a construction project of that kind
    did not occur because there was some time pressure in completing the Varner Road
    construction. The Bob Hope Desert Classic golf tournament, referred to by one witness
    as the “king of the desert,” was scheduled to be held on January 17, 2007. Varner Road,
    therefore, needed to be widened and otherwise improved to allow better public access to
    the event.
    On November 7, 2006, the County approved a final tract map of the
    property, which divided the property into lots A through C and 1 through 10. Varner
    Road was identified on the tract map as lot A; lot A adjoined various lots in the approved
    tract. The tract map also reflected that Berger had unconditionally dedicated lot A to the
    County.
    Granite’s accounting clerk, Kim George, prepared two preliminary 20-day
    notices, dated December 1, 2006. The preliminary 20-day notices identified Scripps
    Investments & Loans, Inc. (Scripps), as the lender, and Desert Gold as the
    “owner/reputed owner.” The notices also estimated $8,225,000 as the total price of labor,
    services, equipment, or materials under the Granite contract. George prepared the notices
    based on information Granite had received from CalVest and Desert Gold. George did
    not review any public records to confirm Granite’s information; it was not Granite’s
    practice to do so. An e-mail containing “preliminary notice information” (capitalization
    omitted), which Tim Reynolds of Granite had received from Michael Oliphant of
    CalVest, identified Desert Gold as the owner of the property. A document, on which
    Granite also relied, that had a Delfino Resort logo on it and was entitled “Preliminary
    4
    Lien Information Contact Information,” identified Berger and Scripps as the lenders, and
    Desert Gold as the owner.
    George had “no idea” why Berger was not identified on the request for
    preliminary notice information form that Granite had prepared for the purpose of
    identifying whom it would serve with a preliminary 20-day notice for the project.
    George thought it “odd” and “d[id]n’t make sense” that Berger was not listed on that
    document.
    Granite’s preliminary 20-day notices were thereafter served by certified
    mail to Scripps and Desert Gold, as confirmed by returned receipts, copies of which are
    contained in our record. It was not Granite’s practice to prepare declarations of service
    with regard to its service of preliminary 20-day notices. Berger was neither identified on,
    nor served with, the preliminary 20-day notices.
    On December 7, 2006, a grant deed transferring the property from Berger to
    Desert Gold was executed but was not recorded until January 4, 2007. In opposing
    Berger’s motion for summary judgment, Travelers did not dispute that Desert Gold
    acquired the property from Berger on January 4, 2007.
    Reynolds, Granite’s project manager and senior estimator, testified at his
    deposition that in the normal course of such improvement work on public land, Granite
    would obtain an encroachment permit from the County before it could begin work on
    Varner Road. Oliphant testified, however, that construction began on December 11,
    2006, before the County issued an encroachment permit on December 20, because
    “everybody,” including the County and Berger, was “pushing” to get the work done in
    time for the Bob Hope Desert Classic golf tournament. The improvements to Varner
    Road “were to benefit all of the lots” in the tract. Travelers issued payment and
    performance bonds for the road and water improvement work on Varner Road.
    Granite began the work by clearing and grading along Varner Road,
    removing a chain-link fence, and staking the area. Materials were staged and stored on
    5
    the premises for sewer and water lines. Reynolds testified at his deposition that Granite
    was not concerned whether Desert Gold owned the property before construction began
    because “the County wouldn’t let me go to work unless there was an agreement to work
    on that property.” Oliphant (employed by construction manager, CalVest) testified in his
    deposition that there was no agreement Desert Gold had to first acquire the property
    before construction began. He testified this was a “special circumstance” because work
    should not have begun until two weeks after the County had issued the December 20,
    2006 encroachment permit. He also testified construction proceeded “at owner’s risk.”
    At the commencement of the work on Varner Road, Berger’s president,
    Ron Auen, and Doug Vance, Berger’s vice-president of real estate, were seen at the
    property monitoring the work; they never objected to the work or told the workers to stop
    or leave. Vance contacted Cove Electric to mark Berger’s private underground fiber
    optic line before the commencement of construction. A portable water tower that held
    12,000 gallons of water was erected on the property for the project. The water tower was
    visible from parts of the freeway and Varner Road. Vance’s brother’s company, Dan’s
    Equipment, was a contractor in the commencement of work at the property; Dan’s
    Equipment supplied water and water trucks.
    Berger financed Desert Gold’s purchase of the property, and Berger thus
    became the beneficiary of a deed of trust encumbering lots 3, 4, 6 through 9, B, and C of
    the property. The trust deed was recorded on January 4, 2007. Berger intended that its
    trust deed would be first in priority. Berger would not have provided financing if it had
    not been secured by a first trust deed.
    At some unspecified point in time, Desert Gold stopped making payments;
    Berger foreclosed on its trust deed and reacquired the property. Desert Gold apparently
    disappeared from the picture.
    On February 11, 2008, Granite stopped performing under the Granite
    contract because it had not been paid. As Granite was listed on the encroachment permit,
    6
    the County required Granite to conduct some continuing maintenance on the
    uncompleted work to make sure the area remained safe until the work was completed.
    On February 22, 2008, Granite served a second preliminary 20-day notice,
    this time on Berger, which identified Berger as the lender. The notice contained a
    $2,480,129.49 estimate for the total price of additional labor, equipment, and materials
    needed for the project. No proof of service was prepared.
    On January 15, 2009, Granite recorded a mechanic’s lien that encumbered
    the property now owned, once again, by Berger.
    PROCEDURAL HISTORY
    I.
    GRANITE’S FIRST AMENDED COMPLAINT
    In April 2009, Granite commenced this action to, inter alia, foreclose on its
    mechanic’s lien. Granite’s first amended complaint, which is the operative complaint in
    this case, contained a claim for breach of contract against Desert Gold; two claims for
    common counts against Desert Gold; a claim for foreclosure of the mechanic’s lien
    against Desert Gold, Berger, Top Finance of Arizona, LLC, Dynamic Finance of
    Arizona, LLC, CalVest, P.M. 10, Inc., Earth Systems Southwest, and GR Underground,
    Inc.; a claim for action on a payment bond against Travelers and the County; and a claim
    for violation of Insurance Code section 790.03, subdivision (h) and California Code of
    Regulations, title 10, section 2695.10 against Travelers.
    As to the claim for foreclosure of the mechanic’s lien, the first amended
    complaint alleged that pursuant to section 3097, within 20 days after first furnishing
    labor, services, equipment, and materials to the jobsite, Granite provided a preliminary
    20-day notice. The first amended complaint further alleged: “On January 15, 2009,
    plaintiff’s certified Notice of Claim of Lien in the sum of $5,716,455.33 was duly
    recorded,” and that “[s]aid recordation was within thirty (30) days of recordation of
    7
    Notice of Completion and within ninety (90) days since completion of the work of
    improvements or cessation of labor thereon. On or about April 16, 2009, defendant,
    Travelers Casualty and Surety Company of America, partially reduced the above
    referenced mechanics’ lien to $2,794,779.92.”
    II.
    TRAVELERS SUBSTITUTES IN AS PLAINTIFF AS TO GRANITE’S FORECLOSURE
    OF MECHANIC’S LIEN CLAIM; GRANITE DISMISSES ALL CAUSES OF ACTION
    OTHER THAN FORECLOSURE OF MECHANIC’S LIEN CLAIM.
    In April 2010, Travelers filed a motion for an order substituting Travelers
    in place of Granite as to Granite’s cause of action for foreclosure of its mechanic’s lien.
    Travelers’s moving papers explained that Granite and Travelers entered into a settlement
    agreement in which, inter alia, Granite assigned its claim for foreclosure on the
    mechanic’s lien to Travelers. In September 2010, the trial court granted Travelers’s
    motion and ordered that Travelers, as assignee of Granite, “is hereby substituted in as the
    real party in interest in place of Granite as to the operative Complaint’s fourth cause of
    action for foreclosure of mechanic’s lien.” (Some capitalization omitted.) In April 2011,
    Granite filed a request for dismissal of all causes of action contained in the first amended
    complaint except for the fourth cause of action for foreclosure of the mechanic’s lien.
    The court clerk entered the dismissal accordingly.
    III.
    THE TRIAL COURT DENIES TRAVELERS’S FIRST MOTION FOR
    SUMMARY ADJUDICATION.
    In March 2011, Travelers filed a motion for summary adjudication as to the
    foreclosure of the mechanic’s lien claim, on the ground: “Travelers is entitled to
    judgment in its favor as to the fourth cause of action for foreclosure of mechanic’s lien as
    Granite: (1) supplied a preliminary notice; (2) timely recorded a mechanics lien; and
    (3) has priority over the deeds of trust held by the lenders which were recorded after the
    8
    commencement of work of improvement on the subject real property.” (Some
    capitalization omitted.)
    The trial court denied the motion for summary adjudication, stating triable
    issues of material fact existed as to the following: “Whether Travelers paid and
    discharged the entire debt of Granite; whether subrogation of Granite[’]s rights to
    Travelers would work an injustice as to Berger[;] whether Granite stopped work as early
    as February 2008 (which would indicate that the mechanics lien was recorded too late
    pursuant to Civ. Code 3115); whether Granite[’]s work stopped on January 31 2009
    (which would indicate that Granite recorded the mechanics lien prematurely on
    January 15 2009 in violation of Civ. Code 3115); whether Granite commenced work on
    October 20 2006; and the reasonable value of the work and materials.”
    IV.
    THE TRIAL COURT DENIES BERGER’S MOTION FOR SUMMARY JUDGMENT ON THE
    GROUND TRIABLE ISSUES OF MATERIAL FACT EXISTED AS TO WHETHER BERGER
    HAD KNOWLEDGE OF THE COMMENCEMENT OF THE VARNER ROAD IMPROVEMENT
    WORK AND WHETHER BERGER CAUSED THAT WORK TO COMMENCE.
    In November 2011, Berger filed a motion for summary judgment as to the
    foreclosure of the mechanic’s lien claim on the grounds, “there is no triable issue of fact
    and that Berger is entitled to a judgment as a matter of law as to the foreclosure of
    mechanics’ lien claim because under Civil Code Section 3128, the mechanics’ lien that
    Travelers seeks to enforce did not attach to the property that it purports to encumber. The
    mechanics’ lien did not attach to the property because Berger owned the property when
    work commenced and did not cause the work to be done.”
    On February 14, 2012, the trial court denied the motion for summary
    judgment on the ground, “[t]riable issues of fact exist as to whether the Berger
    Foundation had knowledge of commencement of the offsite improvement work and
    whether it caused the work to commence.”
    9
    V.
    THE TRIAL COURT GRANTS BERGER’S MOTION FOR SUMMARY JUDGMENT;
    TRAVELERS APPEALS.
    In January 2012, Berger filed a motion for summary judgment on the
    ground, “there is no triable issue of fact and that Berger is entitled to a judgment as a
    matter of law as to the foreclosure of mechanics’ lien cause of action. The mechanics’
    lien that Travelers seeks to enforce is invalid because Granite did not serve Berger with a
    20-day preliminary notice as required by Civil Code Sections 3097, 3097.1 and 3114.”
    The trial court granted Berger’s motion for summary judgment on the
    ground, “Granite failed to serve Berger with a 20 day preliminary notice as required
    (Civil Code 3097 3097.1 and 3114). Granite was not exempt from this requirement on
    the grounds that it had a direct contract with the reputed owner of the property[,] that
    there was an implied contract between Berger and Granite[,] or that Granite acted in good
    faith.” The court overruled the parties’ evidentiary objections; neither party challenges
    the court’s ruling on any evidentiary objections in this appeal.
    In May 2012, judgment was entered in favor of Berger and against
    Travelers as the real party in interest to Granite’s claim. Travelers appealed.
    DISCUSSION
    I.
    STANDARD OF REVIEW
    We review orders granting summary judgment de novo. (Saelzler v.
    Advanced Group 400 (2001) 
    25 Cal.4th 763
    , 767; Village Nurseries v. Greenbaum
    (2002) 
    101 Cal.App.4th 26
    , 35.) A motion for summary judgment is properly granted if
    the moving papers establish there is no triable issue of material fact and the moving party
    is entitled to judgment as a matter of law. (Code Civ. Proc., § 437c, subd. (c); Aguilar v.
    Atlantic Richfield Co. (2001) 
    25 Cal.4th 826
    , 843.)
    10
    II.
    SUMMARY OF THE APPLICABLE LAW GOVERNING PRELIMINARY 20-DAY
    NOTICES AND MECHANIC’S LIENS
    “A mechanic’s lien is a claim against the real property, which may be filed
    if a claimant has provided labor or furnished materials for the property and has not been
    paid. (Kim v. JF Enterprises (1996) 
    42 Cal.App.4th 849
    , 854 . . . .) The mechanic’s lien
    derives from the California Constitution and ‘courts have uniformly classified the
    mechanics’ lien laws as remedial legislation, to be liberally construed for the protection
    of laborers and materialmen.’” (Brewer Corp. v. Point Center Financial, Inc. (2014) 
    223 Cal.App.4th 831
    , 839, quoting Connolly Development, Inc. v. Superior Court (1976) 
    17 Cal.3d 803
    , 826-827.)
    A mechanic’s lien “is effected by the filing of a claim of lien within certain
    time limitations (§§ 3115, 3116) and by meeting other statutory requirements.” (Kim v.
    JF Enterprise (1996) 
    42 Cal.App.4th 849
    , 854.) Under section 3097, “[s]ervice of a
    preliminary 20-day notice is required to enforce a mechanic’s lien or stop notice claim.
    [Citations.] A preliminary notice must be served within 20 days after the claimant has
    begun providing labor, services, equipment, or material for which a mechanic’s lien or
    stop notice claim will be made. [Citation.] The Legislature imposed the notice
    requirement to alert property owners and lenders ‘to the fact that the property or funds
    involved might be subject to claims arising from contracts to which they were not parties
    and would otherwise have no knowledge.’ [Citation.] The Legislature intended ‘to exact
    strict compliance with the preliminary notice requirement.’ [Citations.]” (Brewer Corp.
    v. Point Center Financial, Inc., supra, 223 Cal.App.4th at p. 847.)
    Section 3097 provided in relevant part: “‘Preliminary 20-day notice
    (private work)’ means a written notice from a claimant that is given prior to the recording
    of a mechanic’s lien, prior to the filing of a stop notice, and prior to asserting a claim
    against a payment bond, and is required to be given under the following circumstances:
    11
    [¶] (a) Except one under direct contract with the owner . . . , every person who furnishes
    labor, service, equipment, or material [to a work of improvement] . . . shall, as a
    necessary prerequisite to the validity of . . . a notice to withhold, cause to be given to the
    owner or reputed owner, to the original contractor, or reputed contractor, and to the
    construction lender, if any, or to the reputed construction lender, if any, a written
    preliminary notice as prescribed by this section. [¶] (b) Except the contractor . . . , all
    persons who have a direct contract with the owner and who furnish labor, service,
    equipment, or material [to a work of improvement] . . . shall, as a necessary prerequisite
    to the validity of . . . a notice to withhold, cause to be given to the construction lender, if
    any, or to the reputed construction lender, if any, a written preliminary notice as
    prescribed by this section.” Section 3095 defined the term “‘[o]riginal contractor’” as
    “any contractor who has a direct contractual relationship with the owner.”
    “Although a mechanic’s lien itself is not recorded until after the completion
    of the work in question (§§ 3115, 3116), with certain exceptions, a claimant must serve a
    ‘preliminary notice’ not later ‘than 20 days after the claimant has first furnished labor,
    service, equipment, or materials to the jobsite.’ (§§ 3097, 3097, subd. (d).) A
    preliminary 20-day notice is ‘a necessary prerequisite to the validity of any claim of lien
    . . . .’ (§ 3097, subd. (a).) ‘A claimant shall be entitled to enforce a lien only if he has
    given the preliminary 20-day notice (private work) in accordance with the provisions of
    Section 3097, if required by that section, and has made proof of service in accordance
    with the provisions of Section 3097.1.’ (§ 3114.) Strict compliance with section 3097 is
    required. (Truestone, Inc. [v.] Simi West Industrial Park II (1984) 
    163 Cal.App.3d 715
    ,
    721 . . . .)” (Kim v. JF Enterprises, supra, 42 Cal.App.4th at p. 855.)
    Here, Travelers sought to foreclose on Granite’s mechanic’s lien to recover
    money for the services and materials provided by Granite in its construction work on
    Varner Road, which was property owned by the County, a public entity. Although “[a]
    mechanics lien is not available against public property,” even when a private developer
    12
    performs construction on public property, “[p]rivate property that is directly adjacent to
    and benefited by public works, such as streets, storm drains, and curbs, also can be
    subject to a mechanics lien on a public works project.” (Cal. Mechanics Liens and
    Related Construction Remedies (Cont.Ed.Bar 4th ed. 2013) § 4.5, pp. 319, 320, citing
    North Bay Construction, Inc. v. City of Petaluma (2006) 
    143 Cal.App.4th 552
     and
    Sukut-Coulson, Inc. v. Allied Canon Co. (1978) 
    85 Cal.App.3d 648
    .)
    Furthermore, section 3128 authorized the attachment of liens to adjacent
    property: “The liens provided for in this chapter shall attach to the work of improvement
    and the land on which it is situated together with a convenient space about the same or so
    much as may be required for the convenient use and occupation thereof, if at the
    commencement of the work or of the furnishing of the materials for the same, the land
    belonged to the person who caused such work of improvement to be constructed, but if
    such person owned less than a fee simple estate in such land then only his interest therein
    is subject to such lien, except as provided in Section 3129.” (See Forsgren Associates,
    Inc. v. Pacific Golf Community Development LLC (2010) 
    182 Cal.App.4th 135
    , 150.)
    The parties do not dispute that Granite’s mechanic’s lien, if otherwise valid, could attach
    to the property adjacent to Varner Road.
    III.
    ALTHOUGH GRANITE DID NOT HAVE A DIRECT CONTRACTUAL RELATIONSHIP WITH
    BERGER, AND DID NOT SERVE BERGER WITH A PRELIMINARY 20-DAY NOTICE IN
    2006, A TRIABLE ISSUE OF MATERIAL FACT EXISTS AS TO WHETHER BERGER HAD
    ACTUAL KNOWLEDGE OF THE COMMENCEMENT OF THE CONSTRUCTION SO AS TO
    EXCUSE GRANITE FROM THAT REQUIREMENT.
    It is undisputed Granite did not serve Berger, as owner of the property
    adjacent to Varner Road or in any capacity, with a preliminary 20-day notice at the
    commencement of the construction in December 2006. “Section 3097, subdivision (a)
    creates two exceptions to the preliminary notice requirement. No notice is required from:
    (1) ‘one under direct contract with the owner’, or (2) one performing actual labor for
    13
    wages.” (Kim v. JF Enterprises, supra, 42 Cal.App.4th at p. 855.) “The rationale for
    excepting those under direct contract with the owner from serving a preliminary notice is
    that ‘the owner is generally apprised of potential lien claims by those with whom he deals
    directly, whereas it is difficult for him to learn of potential liens by those not under direct
    contract. [Citation.]’ [Citation].” (Ibid.)
    In Kim v. JF Enterprises, supra, 42 Cal.App.4th at page 856, the appellate
    [3]
    court explained: “Section 3129         states that every work of improvement constructed,
    labor performed or materials furnished ‘with the knowledge of the owner’ shall be held to
    have been ‘constructed, performed, or furnished at the instance of such owner . . . .’ This
    statute creates a presumption that, where the owner has knowledge of the construction
    work on its property, the work is done at the instance of the owner and hence ‘under
    direct contract with the owner’ within section 3097. [Citation.]” (Italics added.)
    Therefore, “‘[w]here a noncontracting owner has actual knowledge of the
    improvements being made to his property and fails to avail himself of the mode of
    exempting his interest from liability for the work provided by . . . section 3094 . . . , he is
    estopped to deny that the work was done at his instance and request. [Citation.] Under
    3
    Section 3129 provided in full: “Every work of improvement constructed upon
    any land and all work or labor performed or materials furnished in connection therewith
    with the knowledge of the owner or of any person having or claiming any estate therein
    shall be held to have been constructed, performed, or furnished at the instance of such
    owner or person having or claiming any estate therein and such interest shall be subject to
    any lien recorded under this chapter unless such owner or person having or claiming any
    estate therein shall give a notice of nonresponsibility pursuant to Section 3094.”
    Section 3094 defined “‘[n]otice of nonresponsibility’” as a “written notice, signed and
    verified by a person owning or claiming an interest in the site who has not caused the
    work of improvement to be performed, or his agent,” and which contains specified
    information set forth in the statute. The notice of nonresponsibility must be provided
    “[w]ithin 10 days after the person claiming the benefits of nonresponsibility has obtained
    knowledge of the work of improvement” and “shall be posted in some conspicuous place
    on the site.” (§ 3094.) There is no evidence any party provided a notice of
    nonresponsibility in this case.
    14
    such circumstances the claimant has a “direct contract with the owner” for the purposes
    of . . . section 3097 . . . and consequently is not required to give the notice prescribed
    therein. [Citations.]’ [Citation.]” (Kim v. JF Enterprises, supra, 42 Cal.App.4th at
    p. 856.)
    The appellate court in Kim v. JF Enterprises, supra, 42 Cal.App.4th at
    page 859, rejected the plaintiffs’ argument that the owners’ constructive knowledge was
    sufficient to excuse the plaintiffs’ compliance with section 3097. The court concluded,
    “only where the owner has actual knowledge of the construction is a claimant excused
    from serving a preliminary notice.” (Kim v. JF Enterprises, supra, at p. 859.)
    In granting Berger’s motion for summary judgment on the ground Granite
    failed to serve Berger with a preliminary 20-day notice, the trial court stated in part,
    “Granite was not exempt from this requirement on the grounds that it had a direct
    contract with the reputed owner of the property[,] that there was an implied contract
    between Berger and Granite[,] or that Granite acted in good faith.”
    Granite, however, produced evidence in opposition to Berger’s motion for
    summary judgment that would support a finding Berger had actual knowledge of the
    construction work along Varner Road, thereby triggering the presumption the work was
    done at the instance of Berger and “‘under direct contract with’” Berger. (Kim v. JF
    Enterprises, supra, 42 Cal.App.4th at p. 856.) By virtue of this evidence, Berger may be
    estopped from arguing the requirements of the statute were not met. That evidence
    includes: (1) the e-mails, dated September 26, 2006, documenting Berger’s reluctance, as
    expressed by one of its attorneys, to become a party to the Granite contract, and, thus,
    Berger’s awareness of discussions leading up to the Granite contract; (2) testimony that
    the commencement of work on Varner Road was expedited at “everybody’s” insistence,
    including Berger’s, with the goal of facilitating public access to the Bob Hope Desert
    Classic golf tournament to be held on January 17, 2007; (3) testimony regarding the
    presence of Berger executives, Auen and Vance, at the commencement of work on
    15
    Varner Road and frequent visits monitoring the progress of the work; (4) Vance’s
    assistance in marking a fiber optic line to facilitate construction on Varner Road; (5) the
    visible grading and staging activities on Varner Road and adjoining property; (6) the
    erection of a 12,000-gallon portable water tower on the property for use in construction
    efforts, which was visible from parts of the freeway and Varner Road itself; and, to a
    lesser extent, (7) Vance’s brother’s role at the commencement of construction activities
    as a contractor providing water supply services to facilitate construction on the property
    adjoining Varner Road.
    Berger argues some of the deposition testimony of witnesses, which was
    produced by Travelers in opposition to the motion for summary judgment, was
    inconsistent and vague regarding timing of events and personal knowledge. For example,
    Oliphant testified at his deposition, as follows: “[W]hen we started on December 14, Ron
    Auen and Doug Vance were on the property every day during our improvements. So
    they—they never objected and said, ‘You guys have to stop, leave. We don’t want you
    to’—‘We don’t want you to not work—or work here,’ any—any of that. They were quite
    helpful.” Oliphant also testified “the Bergers” were on the jobsite “quite often” early in
    the morning as Auen was “an early bird, and so he came out early throughout the entire
    process.” Oliphant testified that his own schedule did not “always coincide to the early
    visits” and so he did not see Auen every time he came; Oliphant’s superintendent,
    however, told him that he saw Auen numerous times. Oliphant stated that he could not
    recall if he personally saw Auen and Vance onsite between December 11, 2006 and
    January 4, 2007.
    Oliphant also offered inconsistent testimony regarding the issue of Vance’s
    assistance in marking the fiber optic line. At one point in his deposition, Oliphant
    testified that immediately before construction began, he requested Vance’s assistance in
    marking the fiber optic line near the work on Varner Road to make sure it was not hit
    when digging began. He asked Vance, “can you mark out your fiberoptic line for us
    16
    because we are going to start.” Oliphant also testified he did not “actually recall the
    conversation to get that line demarked.” On the other hand, Vance testified at his
    deposition that he discussed the fiber optic line with Oliphant after the line had been
    damaged.
    Berger argues that although evidence shows a portable water tower was
    erected, no evidence shows when the tower was erected. Similarly, sometimes vague and
    inconsistent deposition testimony was presented as to the timing of the arrival of
    construction materials and equipment.
    That Oliphant and other witnesses provided sometimes inconsistent and
    vague deposition testimony does not render their testimony ineligible to create a triable
    issue of material fact as to Berger’s actual knowledge of the commencement of
    construction on Varner Road. It is the province of the jury to reconcile conflicting
    testimony offered by Oliphant and other witnesses and to weigh credibility.
    We have reviewed all of the evidence cited by the parties in support and in
    opposition to Berger’s motion for summary judgment. It would strain credulity to
    conclude that, as a matter of law, a reasonable jury could not find that Berger had an
    actual awareness of the commencement of construction on or along Varner Road in
    December 2006. Consequently, a triable issue of material fact exists as to whether
    Berger had actual knowledge of the construction of Varner Road, which would thereby
    excuse Granite’s failure to serve Berger with a preliminary 20-day notice under
    section 3097. Summary judgment must be reversed on this ground alone.
    IV.
    A TRIABLE ISSUE OF MATERIAL FACT EXISTS REGARDING WHETHER GRANITE
    SERVED DESERT GOLD WITH A PRELIMINARY 20-DAY NOTICE AS THE
    REPUTED OWNER OF THE PROPERTY.
    Section 3097, subdivision (a) required that a claimant serve a preliminary
    20-day notice on “the owner or reputed owner” of the property. The term “reputed,”
    17
    whether used to refer to the owner or the construction lender, for purposes of
    section 3097, is “a person or entity reasonably and in good faith believed by the
    claimant” to be the actual owner or construction lender. (Kodiak Industries, Inc. v. Ellis
    (1986) 
    185 Cal.App.3d 75
    , 87.) “The test is an objective one and a claimant must be
    deemed to possess sufficient information about a reputed lender when a reasonable
    person, given the claimant’s information, would have been led to believe in good faith”
    that a putative owner was the actual owner. (Ibid.) “[T]he information on which a
    reasonable claimant should rely must be cloaked with sufficient indicia of reliability—
    such as statements from the owner, general contractor, or lender itself or their agents—so
    as to distinguish this information from a mere guess or some ill-founded conjecture.”
    (Ibid.)
    Here, the trial court’s minute order granting summary judgment also stated
    Granite was not exempt from the preliminary 20-day notice requirement on the ground it
    had “acted in good faith.” Presumably, the court’s statement was in response to Granite’s
    argument that Granite, by serving Desert Gold on December 1, 2006, with a preliminary
    20-day notice, had discharged its obligation under section 3097 by serving the reputed
    owner of the property with that notice.
    The record shows the ordinary course of preparing for and commencing
    construction on the project was disturbed because of the collective goal of all those
    involved to have Varner Road widened and otherwise improved by the start of the Bob
    Hope Desert Classic golf tournament on January 17, 2007. Consequently, the Granite
    contract was entered into before the grant deed was executed transferring the property to
    Desert Gold, and construction began pursuant to the Granite contract before that grant
    deed was recorded in January 2007.
    The evidence shows that, in December 2006, the parties appeared to operate
    under the premise that Desert Gold’s acquisition of the property was a foregone
    conclusion. Despite their knowledge, Auen and Vance did not interfere with the
    18
    construction activities on Varner Road, and the County did not stop construction
    activities that occurred before the issuance of an encroachment permit. (Oliphant
    testified at his deposition that a transportation inspector from the County was out on the
    site every day and the inspector did not “red tag” the project or issue a stop notice.)
    Reynolds testified that he would have been fired if he had not believed there was an
    agreement in place providing a developer’s ownership of the property before construction
    began. CalVest and Desert Gold provided Granite with information that Desert Gold was
    the owner of the property for purposes of the preliminary 20-day notices.
    On the other hand, however, Granite was on notice that Berger was the
    original owner of the property but did not confirm ownership of the property when
    construction commenced. Consequently, we conclude a triable issue of material fact
    exists as to whether Granite, by serving Desert Gold as the reputed owner of the property,
    had acted reasonably and in good faith. Therefore, the motion for summary judgment
    failed on this ground, in addition to and independent of the ground, discussed ante, that a
    triable issue of material fact exists as to Berger’s actual knowledge.
    In light of our reversal of summary judgment due to the existence of triable
    issues of material fact, we do not need to also address Berger’s argument regarding the
    legal effect of Granite’s failure to prepare proofs of service for the preliminary 20-day
    4
    notices it served, as required by section 3114. Berger argues that Granite’s preliminary
    20-day notices would not be effective unless Granite prepared proofs of service. Without
    citing to supportive legal authority other than the statute itself, Berger suggests a
    contractor that provided labor, services, and materials under a construction contract, and
    complied with all the preliminary 20-day notice statutory requirements, except for the
    4
    Section 3114 provided: “A claimant shall be entitled to enforce a lien only if he
    has given the preliminary 20-day notice (private work) in accordance with the provisions
    of Section 3097, if required by that section, and has made proof of service in accordance
    with the provisions of Section 3097.1.”
    19
    requirement it must also prepare a proof of service, forfeits the right to recover amounts
    due under a construction contract through a mechanic’s lien. We do not agree the
    Legislature intended such an automatic and absolute forfeiture of the mechanic’s lien
    remedy to such a contractor in light of the remedial nature of the mechanic’s lien statutes,
    which the California Supreme Court has held must be “liberally construed for the
    protection of laborers and materialmen.” (Connolly Development, Inc. v. Superior Court,
    supra, 17 Cal.3d at pp. 826-827.) In any event, the trial court’s minute order granting
    Berger’s motion for summary judgment does not suggest the court relied on Granite’s
    failure to prepare proofs of service as a basis for its ruling.
    Because we reverse summary judgment, we also do not need to address
    whether a triable issue of material fact exists regarding who owned the property at the
    time construction commenced for the purpose of the preliminary 20-day notice
    requirement. Travelers argues that Desert Gold became the owner of the property on
    December 7, 2006, when the grant deed was executed, though not yet recorded, which
    argument, Berger contends, is forfeited for failure to raise it in the trial court. (See Civ.
    Code, § 1217 [“An unrecorded instrument is valid as between the parties thereto and
    those who have notice thereof.”].)
    V.
    THE TRIAL COURT’S MINUTE ORDER DOES NOT ADDRESS THE EFFECT OF THE
    PRELIMINARY 20-DAY NOTICE GRANITE SERVED ON BERGER IN FEBRUARY 2008.
    On February 22, 2008, Granite prepared a preliminary 20-day notice that
    identified Berger as “lender/surety” (capitalization omitted) and stated a $2,480,129.49
    estimate for the total price of additional labor, equipment, and materials needed for the
    project. The record contains a copy of the notice and a certified mail return receipt, but
    does not contain a proof of service for that notice.
    The trial court’s minute order does not address the effect, if any, that
    February 2008 notice to Berger had on the viability of the foreclosure on the mechanic’s
    20
    lien claim. Section 3097, subdivision (d) provided in part: “If labor, service, equipment,
    or materials have been furnished to a jobsite by a claimant who did not give a preliminary
    notice, that claimant shall not be precluded from giving a preliminary notice at any time
    thereafter. The claimant shall, however, be entitled to record a lien, file a stop notice, and
    assert a claim against a payment bond only for labor, service, equipment, or material
    furnished within 20 days prior to the service of the preliminary notice, and at any time
    thereafter.”
    Granite produced evidence that it continued work on the project until
    February 11, 2008, less than 20 days before service of the preliminary 20-day notice
    served on Berger. Therefore, a triable issue of material fact exists regarding the viability
    of the mechanic’s lien to recover labor, service, equipment, or materials furnished within
    20 days prior to service of the preliminary 20-day notice and any work thereafter
    completed by Granite.
    DISPOSITION
    The judgment is reversed. Appellant shall recover costs on appeal.
    FYBEL, J.
    WE CONCUR:
    O’LEARY, P. J.
    MOORE, J.
    21
    

Document Info

Docket Number: G049802

Filed Date: 9/25/2014

Precedential Status: Non-Precedential

Modified Date: 10/30/2014