Save North Petaluma River and Wetlands v. City of Petaluma ( 2022 )


Menu:
  • Filed 11/14/22; certified for publication 12/13/22 (order attached)
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    FIRST APPELLATE DISTRICT
    DIVISION THREE
    SAVE NORTH PETALUMA RIVER
    AND WETLANDS et al.,
    Petitioners and Appellants,                     A163192
    v.                                                      (Sonoma County
    CITY OF PETALUMA et al.,                                Super. Ct. No. SCV-266157)
    Respondents,
    J. CYRIL JOHNSON INVESTMENT
    CORPORATION,
    Respondent and Real Party in
    Interest.
    This is a mandate proceeding to review an agency’s decision for
    compliance with the California Environmental Quality Act (CEQA) (Pub.
    Resources Code, § 21000 et seq.1) At issue is the decision of the City of
    Petaluma (the City) to certify the environmental impact report (EIR) for a
    180-unit apartment complex in Petaluma proposed by real party in interest J.
    Cyril Johnson Investment Corporation (JCJIC). Save North Petaluma River
    1     All further statutory references are to this code unless otherwise
    indicated.
    1
    and Wetlands and Beverly Alexander (petitioners) appeal the trial court’s
    decision upholding the City’s certification of the EIR. We shall affirm.
    Factual and Procedural Background
    In 2003, JCJIC proposed the development of a 312-unit apartment
    complex called the “Sid Commons Apartment Project,” which would be
    located in Petaluma on roughly 15.45 acres of vacant land along the
    Petaluma River at the northern end of Graylawn Avenue (the Project). The
    site of the Project includes grasses, wetlands, oaks, and other vegetation. In
    July 2007, the City published the “Notice of Preparation” for the Project. The
    environmental consultant expected that a Draft EIR could be completed in
    approximately five months.
    In May 2008, shortly after the City began work on the Draft EIR, the
    City adopted General Plan 2025.2 To conform to General Plan 2025, JCJIC
    submitted its Project application as a smaller 278-unit complex and also
    revised the Project to include river terracing.
    In October 2015, the City began meeting with regulatory agencies to
    solicit their input on the Project. After conducting site visits, the California
    Department of Fish and Wildlife, the Regional Water Quality Control Board,
    and the National Oceanic and Atmospheric Administration Fisheries Service
    2     General Plan 2025 included the following revisions to the previous
    General Plan: (1) increase of the allowable residential density at the site;
    (2) addition of Policy 1-P-2, providing for infill development at equal or higher
    density and intensity than surrounding uses; (3) addition of the Project Site
    to the Land Inventory of Opportunity Sites in the Housing Element of the
    General Plan; (4) addition of Policy 8-P-30, which requires the set back of
    new development at least 200 feet from the centerline of the Petaluma River;
    and (5) addition of Policy 8-P-28, which called for the “ ‘construction of a flood
    terrace system to allow the [Petaluma] River to accommodate a 100-year
    storm event within a modified River channel, to the extent feasible given
    existing physical and natural constraints.’ ”
    2
    all provided feedback on the issues they believed the EIR should address. In
    view of General Plan 2025 and the agency feedback, a “Habitat Mitigation
    Monitoring Plan” was created in order to: address habitat replacement and
    mitigation for impacts caused by the general plan’s requirement for river
    terracing; preserve existing native riparian “ ‘high value’ ” habitat where
    practicable; increase the acreage of aquatic habitat within the Project site;
    increase the functions and values of the existing habitat; and improve flood
    capacity of the Petaluma River. The monitoring plan was incorporated into
    the “Biological Resources” chapter of the Draft EIR.
    On March 1, 2018, the City published the Draft EIR for public review
    and comment. JCJIC provided various consultant studies regarding
    environmental impacts, including a March 2004 report by Wetlands Research
    Associates, Inc. (WRA) of so-called “Special Status Species” (the 2004 WRA
    Special Status Species Report or the 2004 WRA Report). In April 2018, the
    Planning Commission considered the Draft EIR and took public comment
    that included concerns from neighboring residents regarding traffic impacts
    to Graylawn Avenue and neighboring streets, impacts to the floodplain, and
    decreased quality of life for the neighborhood. The commission provided
    feedback on the Draft EIR and offered comments to address the intense
    density of the Project and to provide for an appropriate buffer between the
    Project and the riparian corridor.
    On May 21, 2018, the City Council held a hearing on the Draft EIR.
    City staff and the EIR consultant presented the Draft EIR, summarized the
    public comment, and reported on the outcome of the Planning Commission
    hearing. The council considered the public comment, which reiterated
    concerns about the impact of increased traffic on neighboring streets and
    decreased quality of life for the neighborhood. Commenters were also
    3
    concerned about impacts to flooding, the floodplain, hydrology, wetlands, the
    Petaluma River, wildlife, trees, and access to the proposed river trail. City
    Council members provided comment and requested supplemental
    documentation, noting concerns about the hydrology analysis, noise
    modeling, and traffic data. Although the council authorized preparation of a
    final EIR, a majority of its members expressed a preference for a refined
    concept that would reduce density, minimize traffic impacts, provide an
    enhanced buffer between the proposed development and the riparian
    corridor, and minimize impacts to mature trees and wetland features.
    In October 2019, the City issued its “Response to Comments/Final
    Environmental Impact Report” (Final EIR). In response to the significant
    environmental conclusions raised in the Draft EIR and the comments from
    public agencies and the public, JCJIC proposed a revised version of the
    Project that would further reduce the proposed complex from 278 units to 205
    units; reduce the height of certain residential buildings from three to two
    stories; increase building setback from the Petaluma River; and implement a
    “Traffic Calming Plan” on Graylawn and Jess Avenues. The Final EIR
    analyzed these revisions and concluded they eliminated or reduced several of
    the potential significant impacts identified in the Draft EIR for the original
    plan. Although the Planning Commission voted to recommend that the City
    Council certify the EIR, it did not recommend approval of necessary zoning
    amendments.
    On January 8, 2020, JCJIC submitted another reduced version of the
    Project with 180 units in mostly three-story buildings except for the two-story
    buildings in the areas adjacent to existing single-family homes (the Second
    4
    Revision).3 Among other things, these changes were intended to reduce the
    building footprint and increase the setback from the Petaluma River;
    preserve two wetlands near the river and avoid development in the River
    Plan Corridor; and preserve additional trees with a flood terrace design
    adjustment. The changes would also reduce flood impacts and result in a
    further 12 percent reduction in vehicle trips.
    On February 3, 2020, the City Council held a hearing on whether to
    certify the EIR based on the Second Revision and approve the zoning
    amendments. A City staff memo prepared for this hearing thoroughly
    detailed the history of the Project, including the Planning Commission’s
    consideration of the Final EIR and JCJIC’s appeal of the commission’s denial
    of the proposed zoning amendments; the comments received on the Draft and
    Final EIRs; the extent of JCJIC’s public outreach to better understand and
    respond to neighborhood concerns; and the multiple revisions JCJIC made to
    the Project in response to comments. The staff report concluded that the
    changes in the Second Revision reduced impacts, reduced conflicts regarding
    tree protection and wetlands preservation, and addressed the concerns that
    had caused the Planning Commission to deny the zoning amendments. It
    also noted the Second Revision was within the range of alternatives
    addressed in the EIR and would not result in new or more substantial
    impacts compared to prior versions.
    Meanwhile, earlier that afternoon, petitioners submitted a letter to the
    City Council challenging numerous aspects of the Project’s CEQA review. As
    relevant here, petitioners disputed the adequacy of the EIR’s special status
    3    The Project site could have accommodated up to 282 units under the
    Land Inventory referenced in the revised General Plan.
    5
    species analysis and challenged the EIR’s failure to analyze emergency
    evacuations.
    After several hours of deliberation and public comment, the City
    Council voted to certify the EIR and to overturn the Planning Commission’s
    denial of zoning amendments. The council subsequently approved the zoning
    amendments by ordinance on February 24, 2020.
    Petitioners filed a petition for writ of mandate challenging the
    adequacy of the EIR on a number of grounds, including the two raised here.
    The trial court held a hearing and thereafter denied the petition in a detailed
    45-page decision. After entry of judgment, petitioners timely appealed.
    Discussion
    A. CEQA Standard of Review
    “CEQA is a comprehensive scheme designed to provide long-term
    protection to the environment.” (Mountain Lion Foundation v. Fish & Game
    Com. (1997) 
    16 Cal.4th 105
    , 112.) “With narrow exceptions, CEQA requires
    an EIR whenever a public agency proposes to approve or to carry out a project
    that may have a significant effect on the environment.” (Laurel Heights
    Improvement Assn. v. Regents of University of California (1988) 
    47 Cal.3d 376
    , 390 (Laurel Heights).) The fundamental purpose of an EIR is “to provide
    public agencies and the public in general with detailed information about the
    effect which a proposed project is likely to have on the environment; to list
    ways in which the significant effects of such a project might be minimized;
    and to indicate alternatives to such a project.” (§ 21061.) As such, the EIR is
    an informational document that functions as “the primary means of achieving
    the Legislature’s considered declaration that it is the policy of this state to
    ‘take all action necessary to protect, rehabilitate, and enhance the
    environmental quality of the state.’ (§ 21001, subd. (a).)” (Laurel Heights, at
    6
    p. 392; see generally Guidelines, § 15003, subd. (a)4 [“EIR requirement is the
    heart of CEQA”].)
    The EIR serves as a “document of accountability” because it requires
    certification or rejection by the responsible public officials. (Laurel Heights,
    supra, 47 Cal.3d at p. 392.) “If CEQA is scrupulously followed, the public will
    know the basis on which its responsible officials either approve or reject
    environmentally significant action, and the public, being duly informed, can
    respond accordingly to action with which it disagrees.” (Ibid.) Although
    perfection in preparing the EIR is not required, the agency must reasonably
    and in good faith discuss a project in detail sufficient to enable the public to
    discern the “ ‘analytic route’ ” that the “ ‘agency traveled from evidence to
    action.’ ” (Id. at p. 404; see Guidelines, § 15151; San Franciscans for Livable
    Neighborhoods v. City and County of San Francisco (2018) 
    26 Cal.App.5th 596
    , 614.)
    In a mandate proceeding to review an agency’s decision for compliance
    with CEQA, our role is to determine the EIR’s sufficiency as an informative
    document; we do not pass upon the correctness of the agency’s environmental
    determinations. (Laurel Heights, supra, 47 Cal.3d at p. 392.) Like the trial
    court, we “review the administrative record to determine whether the agency
    prejudicially abused its discretion.” (Save Our Peninsula Committee v.
    Monterey County Bd. of Supervisors (2001) 
    87 Cal.App.4th 99
    , 116–117 (Save
    Our Peninsula).) For purposes of CEQA, an abuse of discretion “is
    established if the agency has not proceeded in a manner required by law or if
    the determination or decision is not supported by substantial evidence.”
    4    All references to “Guidelines” are to the state CEQA Guidelines, which
    implement the provisions of CEQA and are set forth in the California Code of
    Regulations, title 14, section 15000 et seq.
    7
    (§ 21168.5; see Sierra Club v. State Bd. of Forestry (1994) 
    7 Cal.4th 1215
    ,
    1236.)
    CEQA regulations define substantial evidence as “enough relevant
    information and reasonable inferences from this information that a fair
    argument can be made to support a conclusion, even though other conclusions
    might also be reached.” (Guidelines, § 15384, subd. (a).) Whether a fair
    argument can be made requires an examination of “the whole record before
    the lead agency.” (Ibid.) Substantial evidence includes “facts, reasonable
    assumptions predicated upon facts, and expert opinion supported by facts”
    (Guidelines, § 15384, subd. (b)), but cannot be established by “[a]rgument,
    speculation, unsubstantiated opinion or narrative, evidence which is clearly
    erroneous or inaccurate, or evidence of social or economic impacts which do
    not contribute to or are not caused by physical impacts on the environment”
    (Guidelines, § 15384, subd. (a)).
    The substantial evidence standard requires that we “ ‘resolve
    reasonable doubts in favor of the administrative finding and decision’ ” and
    refrain from weighing conflicting evidence and second guessing agency
    determinations that a project’s adverse effects are or are not sufficiently
    mitigated. (Laurel Heights, supra, 47 Cal.3d at pp. 392–393.) It is the
    burden of the project opponents to prove the EIR is legally inadequate. (Save
    Our Peninsula, supra, 87 Cal.App.4th at p. 117.)
    On appeal, petitioners contend the trial court erred and abused its
    discretion in upholding the City’s certification of the EIR because, in their
    view, the EIR failed to properly analyze the Project’s impacts on special
    status species and on public safety in the event of an evacuation. We address
    these claims in order.
    8
    B. The EIR Properly Analyzed Impacts to Special Status
    Species
    CEQA regulations contemplate that the physical conditions existing
    when a Notice of Preparation is published “will normally constitute the
    baseline physical conditions” used to describe the environmental setting and
    to determine the significant effects of a proposed project. (Guidelines,
    § 15125, subd. (a).) Knowledge of the baseline conditions is “critical to the
    assessment of environmental impacts,” and special emphasis is “placed on
    environmental resources that are rare or unique to that region and would be
    affected by the project.” (Guidelines, § 15125, subd. (c).) When an EIR
    contains an inadequate description of the environmental setting for a project,
    “a proper analysis of project impacts [is] impossible.” (Galante Vineyards v.
    Monterey Peninsula Water Management Dist. (1997) 
    60 Cal.App.4th 1109
    ,
    1122 [invalidating EIR containing only passing references to surrounding
    viticulture]; see Friends of the Eel River v. Sonoma County Water Agency
    (2003) 
    108 Cal.App.4th 859
    , 873–875.)
    Here, the Notice of Preparation was issued in July 2007. As the
    administrative record documents, the EIR contains a 70-page analysis
    addressing potential impacts to biological resources on the Project site,
    including special status species. The biological resources section of the EIR
    was prepared by Booker Holton, an expert biologist, who investigated the
    Project site following the Notice of Preparation and relied on a number of
    sources—including the 2004 WRA Special Status Species Report, site visits,
    various state and federal plant and wildlife databases, input from regulatory
    agencies, arborist reports, vegetation mapping, and environmental
    communities mapping of the site—to support his analysis.
    As defined in the EIR’s biological resources section, special status
    species are “plants and animals legally protected under state and federal
    9
    endangered species acts or other regulations, or those species that the
    scientific community considers sufficiently rare to qualify for such listing.”
    Based on WRA’s June 2009 mapping of seven different habitat types on the
    Project site,5 the EIR detailed the following information concerning the
    possible presence of special status plants and animals, and offered analyses
    concerning the impact of Project activities on such species and the effect of
    recommended mitigation measures.
    1. Special Status Plant Species
    The EIR described the existing conditions of the Project site as follows:
    “No special status plants have a moderate or high potential to occur on the
    Project site. This determination was based on the habitat types present on
    the site, the known habitat requirements for those special status plants
    potentially occurring in the general area, and the results of previous surveys
    of the property. Furthermore, the highly disturbed nature of the site would
    indicate that none are likely to be present.” (Fn. omitted.)
    In its impact analysis, the EIR concluded “the potential for the Project
    to result in adverse impacts on special status plant species is less than
    significant.” In so concluding, the EIR explained: “Potential special status
    plant habitats in the Project area were evaluated in 2008 and cross-
    referenced with [the California Natural Diversity Database] and [the
    California Native Plant Society] lists of special status plants potentially
    present in the region. Based on the habitat types present and other
    knowledge of the site, special status plant species were determined to have
    either low potential for being present, or were determined to be not present
    at the Project site.”
    5     The seven habitats are: non-native grassland; valley oak woodland;
    riparian woodland; mixed woodland; seasonal wetlands; Petaluma River
    (waters of the U.S.); and detention basin.
    10
    In light of this assessment, mitigation measures for the protection of
    special status plants were deemed unnecessary and none was recommended.
    2. Special Status Birds
    The EIR described “a moderate to high potential of occurrence for
    several special status bird species to occur in the Project area.” According to
    the EIR, special status species that were likely to forage and/or nest in the
    types of habitats located on the Project site included white-tailed kite, Allen’s
    hummingbird, loggerhead shrike, salt marsh common yellowthroat,
    California Ridgeway’s rail, and California black rail. Another state
    endangered/federal threatened species that “may be present” on the site
    included the yellow-billed cuckoo, while other “state Species of Special
    Concern” that “could nest” in the Project site grasslands included “long-eared
    owl, Purple martin, yellow warbler, yellow-breasted chat, yellow-billed
    cuckoo, and Northern harrier.”
    In analyzing the Project’s impact, the EIR concluded: “Based on
    existing habitat conditions, there is a moderate to high potential for
    occurrence of four special status bird species and raptors to occur at the
    Project site.” Specifically, “[t]rees along the Petaluma River could provide
    suitable nesting habitat, and grasslands on the site provide suitable foraging
    habitat for the White-Tailed Kite, a [California Department of Fish and
    Wildlife] fully protected species. The Allen’s Hummingbird, a [U.S. Fish and
    Wildlife Service] Species of Conservation Concern, are common breeding
    species in riparian and scrub habitats, and may breed at the Project site
    along Petaluma River. Grasslands and adjacent shrubs and riparian trees
    within the Project site provide suitable foraging and nesting habitat for
    Loggerhead Shrike, a [California Department of Fish and Wildlife] Species of
    Special Concern and a federal Species of Conservation Concern. Salt marsh
    11
    common yellowthroat, a federal Species of Conservation Concern and a
    [California Department of Fish and Wildlife] Species of Concern, may nest
    along Petaluma River in emergent vegetation or willows. Furthermore, the
    oak and riparian woodlands that exist on three sides of the Project site also
    provides suitable nesting habitat for several raptor species. [¶] Potentially
    significant impacts to these bird species include nest and/or young
    abandonment, resulting from grading or construction disturbance.”
    Additionally, the impact analysis determined that “[w]hile project site
    surveys did not find habitat suitable for area bat species, the 2017 arborist
    study noted two trees with cavities” that “may provide suitable roosting
    habitat for some bat species such as the pallid bat.”
    The EIR then recommended two measures “[t]o address the potential
    for Project-related grading and construction activities to affect special status
    bird species.” The first mitigation measure called for pre-construction
    nesting surveys of trees in the Project site in the event grading or
    construction is “scheduled during the nesting season of migratory birds
    (February 1 through August 30)” and for implementation of specified
    protection measures overseen by a qualified biologist in the event any active
    nest is found. The second mitigation measure recommended pre-construction
    tree roost surveys by a qualified biologist and other measures to protect bats
    during all tree removal and vegetation management activities on the Project
    site. The EIR determined these mitigation measures would “prevent harm to
    special status bird and bat species” and would mitigate impacts to such
    species “to a level of less than significant.”
    3. Special Status Fish, Reptile, and Amphibian Species
    Citing the California Natural Diversity Database, the EIR reported
    that three special status fish species—Sacramento splittail, Central
    12
    California Coast ESU steelhead trout, and Chinook salmon—are “known or
    are suspected to occur in the reach of the Petaluma River that runs along the
    northeastern edge of the Project site.”
    The EIR additionally addressed the possible presence of the California
    Red-Legged Frog and the Western Pond Turtle, stating: “The assessment of
    existing conditions determined that special status species habitat is unlikely
    to occur on the uplands portion of the site that is proposed for development.”
    Specifically, the uplands development portion provides “low potential” for
    these species due to lack of “suitable aquatic habitat” for the turtle species
    and “no suitable breeding habitat” for the frog species. However, the EIR
    cited “[California Natural Diversity Database] 2013” in reporting recorded
    occurrences of the frog species “within a three-mile radius of the site” and
    cited the 2004 WRA Special Status Species Report for its conclusion that
    “turtles may occasionally nest near the Project boundary.”
    In discussing the potential impacts of the Project on these special
    status species, the EIR reported that the “Project’s proposed construction of a
    river terrace expanding the banks of the River, as directed by the General
    Plan, may result in both direct and indirect adverse effects.” In particular,
    grading of the floodway terrace adjacent to the river and trimming and
    clearing of vegetation along the riverbank “could result in the removal of
    habitat for California red-legged frog and Western pond turtle.” Such Project
    activities could also result in “degradation of special status fisheries habitat.”
    Specifically, “[u]nintentional introduction of sediment into the water from
    erosion or runoff has the potential to affect steelhead, green sturgeon and/or
    the Sacramento splittail’s feeding rates and growth, increase mortality, cause
    behavioral avoidance, and reduce macro-invertebrate prey populations,”
    while unintended introduction into the water of petrochemicals associated
    13
    with grading equipment “could injure or kill these fish populations and/or
    their macro-invertebrate prey populations.”
    To address these impacts, the EIR made the following
    recommendations. JCJIC “shall obtain all required authorizations from the
    U.S. Army Corps, the [Regional Water Quality Control Board], the California
    Department of Fish and Wildlife, and other regulatory agencies with
    jurisdiction (as applicable) . . . . Copies of applicable permits shall be
    obtained by the Project applicant and provided to the City of Petaluma prior
    to grading, and the Project applicant shall implement all avoidance and
    minimization measures as required by these agency authorizations.” For
    example, the EIR explained, such agency permits and approvals would be
    required before any dredged or fill material could be discharged into the
    Petaluma River, and the Project applicant would be required to comply with
    any terms and conditions imposed by the agencies for protection of Central
    California Coast steelhead trout and other fish.
    In addition to all the avoidance and mitigation measures required by
    the regulatory agencies, the EIR recommended the following four additional
    mitigation measures to provide further protection: (1) to the extent feasible,
    grading in the river area and vegetation removal must be limited to specific
    dates in order to “avoid potential impacts to anadromous fish species and
    nesting birds” and to avoid interference with “adult spawning migrations or
    the outmigration of smolts”; (2) requiring a “qualified [U.S. Fish and Wildlife
    Service]-approved biologist” to “conduct pre-construction surveys of all
    ground disturbance areas within suitable habitats in the Project site to
    determine if California red-legged frogs and Western pond turtles are
    present” within 48 hours of the start of grading operations; (3) requiring the
    biologist to work with the resource agencies to determine whether and to
    14
    what extent relocation and/or exclusion buffers would be appropriate in the
    event the special status frog or turtle species are detected; and
    (4) implementing best management practices prior to and during
    construction, as required and/or approved by the resource agencies, to protect
    special status species and habitats, including active oversight and monitoring
    of activities by a [U.S. Fish and Wildlife Service]-approved biologist with
    “stop-work authority.”
    According to the EIR, implementation of all identified mitigation
    measures “would reduce potential impacts of the proposed Project on special
    status species and sensitive habitats to a level of less than significant. It is
    anticipated that once construction of the Petaluma River terrace and the
    [Habitat Mitigation Monitoring Plan] is complete, habitat for these species
    will be restored and possibly increased as a result.”
    4. Analysis
    As the foregoing reflects, the EIR’s discussion of special status plant
    and animal species drew not only from the 2004 WRA Special Status Species
    Report, but also from information of the site’s environmental conditions
    obtained by experts who conducted subsequent evaluations and site visits.6
    After describing the habitats existing on the Project site, the EIR identified—
    based on cross-referencing such habitats with the habitats of the special
    status species listed in state and federal plant and animal databases and also
    6     Apparently, the 2004 WRA Report did not include a survey for special
    status species on 6.24 acres of the Project site, including the Petaluma River
    and the riparian habitat along the river. The EIR, however, incorporated the
    Habitat Mitigation Monitoring Plan as an appendix to address the concern
    that the river terracing component of the Project “will unavoidably impact
    certain biological resources along the Riverbanks including riparian and oak
    woodland habitat.” The EIR incorporated the information from the
    monitoring plan as part of its special status species analysis.
    15
    based on other site-specific information—the special status species that occur
    or might occur on the site and be impacted by the Project. All this resulted in
    the EIR’s discussion of 11 special status animals with moderate to high
    potential for occurrence on the Project site—including six bird species, three
    fish species, one frog species, and one turtle species—plus the potential for
    roosting on the site by some bat species. Thus, not only did the EIR base its
    analysis on “facts, reasonable assumptions predicated upon facts, and expert
    opinion supported by facts” (Guidelines, § 15384, subd. (b)), but it amply
    demonstrated the “ ‘analytic route’ ” from such evidence to the action
    recommended and ultimately taken. (Laurel Heights, supra, 47 Cal.3d at
    p. 404.)
    Petitioners challenge the EIR as deficient because: (1) the City never
    investigated the Project’s baseline conditions as of 2007 when the Notice of
    Preparation was published, and the record contains no evidence of studies or
    surveys for special status species at that point in time; (2) substantial
    evidence does not support the EIR’s discussion of baseline conditions for
    special status species; and (3) absent accurate and complete information on
    the environmental setting, the EIR could not and did not adequately analyze
    or mitigate the Project’s impacts on protected species. We are not persuaded.
    These claims are premised largely on the assumption that the
    information in the 2004 WRA Special Status Species Report provided an
    inadequate basis for evaluating the Project’s impact on special status species
    because the report preceded the 2007 Notice of Preparation by three years
    and was based on a site assessment conducted in 2001. As a preliminary
    matter, we reject any suggestion that the 2004 report was based solely on a
    2001 site survey. Notably, Appendix A to the report contained information
    reflecting a comprehensive assessment of the potential presence of special
    16
    status plant and animal species on the Project site based on WRA’s review of
    the U.S. Fish and Wildlife Service “Official Species Lists for Cotati USGS
    Quad (2004),” the California Department of Fish and Game “Natural
    Diversity Data Base (2003),” “searches of the Cotati USGS Quad and
    surrounding 9 Quads,” and the California Native Plant Society “electronic
    inventory (2004).” And apart from the 2004 WRA Report, the EIR indicated
    its analysis included updated database reviews in 2008, 2010, and 2013, and
    was based on information gathered from site visits in 2009, 2016,7 and 2017.
    Petitioners insist that a study conducted at the time of the Notice of
    Preparation is indispensable for setting the appropriate special status species
    baseline. But they cite no authority suggesting that CEQA is violated where,
    as here, the EIR’s analysis on the topic was drawn from site visits, studies,
    and habitat evaluations that were undertaken both before and after the
    Notice of Preparation. Petitioners do not contend the EIR’s description of the
    existing conditions and habitats on the undeveloped Project site was
    incomplete or otherwise flawed for purposes of assessing the presence of
    special status species. As the California Supreme Court has explained,
    “[n]either CEQA nor the CEQA Guidelines mandates a uniform, inflexible
    rule for determination of the existing conditions baseline.” (Communities for
    a Better Environment v. South Coast Air Quality Management Dist. (2010) 
    48 Cal.4th 310
    , 328; see Save Our Peninsula, supra, 87 Cal.App.4th at p. 125
    [“the date for establishing baseline cannot be a rigid one”].) Agencies enjoy
    the discretion to decide, in the first instance, how to realistically measure the
    existing physical conditions without the proposed project (Communities for a
    Better Environment, at p. 328), and the selection of a baseline will be upheld
    7      JCJIC’s appellate briefing represents that this site visit actually
    occurred in 2015 and that the EIR’s reference to 2016 was a typographical
    error.
    17
    when supported by substantial evidence (e.g., Citizens for East Shore Parks v.
    State Lands Com. (2011) 
    202 Cal.App.4th 549
    , 562–563; Cherry Valley Pass
    Acres & Neighbors v. City of Beaumont (2010) 
    190 Cal.App.4th 316
    , 336–337).
    The record here demonstrates that substantial evidence supports the EIR’s
    analysis of the special status species that were subject to the Project’s impact.
    Indeed, petitioners point to no evidence that the biological conditions
    existing on the Project site in 2007 differed from those in 2004 when WRA
    conducted its cross-referencing study, or in later years when updated plant
    and wildlife databases were consulted. For example, no special status plant
    species were reported in a 2008 evaluation of the plant habitats in the Project
    area, or in a March 2009 vegetation mapping of the Project site, or in a June
    2009 biological communities mapping.8 This was consistent with the 2004
    WRA Report’s account that no special status plants had ever been observed
    on the Project site.9 The information in the EIR also aligned with the
    information contained in the 2008 EIR for General Plan 2025, which
    encompassed the Project site and featured its own analysis of special status
    plant and animal species for the broader Petaluma area.
    Moreover, when experts and regulatory agencies brought new
    information to JCJIC’s attention, JCJIC responded by working with experts
    and City staff to ensure that the EIR addressed such matters. Consequently,
    the EIR addresses several special status species that were not mentioned in
    the 2004 WRA Report. For example, in 2015 the City and regulatory
    8     Petitioners suggest the March 2009 vegetation mapping and the June
    2009 biological communities mapping are not in the EIR or in the record.
    That is inaccurate.
    9     The administrative record contains a September 7, 2004, document in
    which WRA elaborated that “surveys conducted by Jones and Stokes in 1997
    for the Corona Reach Specific Plan (which included the present Sid Commons
    project area) resulted in no special status plants observed.”
    18
    agencies alerted JCJIC of the need for additional evidence regarding on-site
    fish species. This prompted an analysis that ultimately resulted in the EIR’s
    evaluation that the Project’s grading and construction activities could result
    in adverse effects to three fish species and inclusion of recommendations to
    mitigate such effects.10 Additionally, a 2017 arborist study noted two trees
    with cavities that may provide suitable roosting habitat for some bat species,
    which led to the EIR’s inclusion of recommended mitigation measures to
    protect bats during all tree removal and vegetation management activities on
    the Project site.
    Despite a professed concern that the EIR inadequately addressed the
    Project’s impact on plants and wildlife, petitioners suggest the foregoing
    information is irrelevant because, among other things, no additional special
    status species studies were conducted and because studies post-dating 2007
    have no bearing on the site conditions existing in 2007. But again,
    petitioners do not challenge the accuracy or completeness of the EIR’s
    description of the Project site’s existing biological and habitat conditions; nor
    do they point to anything indicating that such conditions were materially
    different in 2007 for purposes of a special status species analysis. “The fact
    that additional studies might be helpful does not mean that they are
    required.” (Association of Irritated Residents v. County of Madera (2003) 
    107 Cal.App.4th 1383
    , 1396; Guidelines, § 15204, subd. (a).) And, if anything, the
    EIR’s inclusion of the post-2007 information indicates that the EIR was
    prepared with an eye toward “completeness” and “a good faith effort at full
    disclosure.” (Guidelines, § 15151.)
    10    Nothing in the record indicates continued concern on the part of the
    regulatory agencies after the EIR addressed the identified informational
    gaps.
    19
    Contrary to petitioners’ contention, San Joaquin Raptor/Wildlife
    Rescue Center v. County of Stanislaus (1994) 
    27 Cal.App.4th 713
     does not
    compel a different conclusion. There, the EIR for a housing project was found
    inadequate and misleading because it understated the significance of the
    adjacent San Joaquin River, ignored a nearby wetland wildlife preserve, and
    did not address whether wetland areas were on the project site, despite
    comment letters flagging such concerns. (Id. at pp. 722–729.) Here, in
    contrast, there is no evidence that the EIR omitted or inaccurately described
    the material aspects of the biological conditions on or near the Project site,
    and the EIR expressly took into account important information concerning
    nearby habitats.
    Petitioners’ other authorities are likewise unavailing. In Madera
    Oversight Coalition, Inc. v. County of Madera (2011) 
    199 Cal.App.4th 48
    (Madera Oversight Coalition), the Notice of Preparation was issued in 2006
    but the EIR’s traffic analysis included references to three different baselines,
    one of which was a future baseline using traffic conditions forecast for the
    year 2025. (Id. at pp. 59, 92–93.) After holding that lead agencies have no
    discretion to adopt a baseline that uses conditions predicated to occur on a
    date subsequent to an EIR’s certification (id. at pp. 89–90, 92), the Court of
    Appeal remanded the matter with instructions to grant the petition for writ
    of mandate as to the EIR’s traffic analysis because of its failure to clearly
    identify the baseline used in analyzing the project’s impacts (id. at pp. 107–
    108).11 In Save Our Peninsula, supra, 
    87 Cal.App.4th 99
    , the court rejected
    11    The California Supreme Court disapproved Madera Oversight
    Coalition, supra, 
    199 Cal.App.4th 48
    , insofar as it held “an agency may never
    employ predicted future conditions as the sole baseline for analysis of a
    project’s environmental impacts.” (Neighbors for Smart Rail v. Exposition
    Metro Line Construction Authority (2013) 
    57 Cal.4th 439
    , 457.)
    20
    an EIR’s baseline estimate of a property’s water usage that relied on “a
    ‘standard water demand factor for irrigated pastureland,’ ” because
    substantial evidence did not show the property was in fact irrigated
    pastureland. (Id. at p. 122.) Finally, in County of Amador v. El Dorado
    County Water Agency (1999) 
    76 Cal.App.4th 931
    , the EIR for a project to
    provide additional water for consumptive use was found inadequate for
    purposes of determining the project’s impacts because, among other things, it
    failed to adequately describe the baseline environment and historical
    operations for pre-project water distribution. (Id. at pp. 941, 954–955.)
    Unlike the EIRs in those cases, the EIR here did not purport to measure
    impacts based on conditions that did not exist on the Project site or on
    conditions that were forecasted to exist at some point in the distant future.
    And as discussed, there is no indication that the site conditions documented
    in the instant EIR were incorrectly or incompletely described for purposes of
    a special status species analysis.
    Petitioners also contend the EIR’s references to studies and site visits
    did not constitute substantial evidence supporting its special status species
    analysis because such studies and visits were not included in the
    administrative record and were not otherwise adequately documented, e.g.,
    the names of the participants and descriptions of what took place are not
    disclosed in the record. But the CEQA Guidelines make clear that factual
    information in the EIR itself “may constitute substantial evidence in the
    record to support the agency’s action on the project if its decision is later
    challenged in court.” (Guidelines, §15121, subd. (c); see Karlson v. City of
    Camarillo (1980) 
    100 Cal.App.3d 789
    , 801 [“EIRs constitute evidence”].)
    Moreover, section 15148 of the Guidelines provides: “Preparation of EIRs is
    dependent upon information from many sources, including engineering
    21
    project reports and many scientific documents relating to environmental
    features. These documents should be cited but not included in the EIR. The
    EIR shall cite all documents used in its preparation including, where
    possible, the page and section number of any technical reports which were
    used as the basis for any statements in the EIR.” (Italics added.)
    Here it is unclear from the record whether the site visits cited in the
    EIR resulted in the type of documents contemplated by section 15148 of the
    Guidelines. But even assuming that to be the case, the EIR need not include
    all the reports used in its preparation. (Guidelines, § 15148.) Thus, an
    agency’s failure to disclose a consultant’s memo or to provide a
    comprehensive summary of its underlying assumptions and data does not
    necessarily render an EIR inadequate. And while “ ‘we must ensure strict
    compliance with the procedures and mandates of [CEQA],’ ” we also must
    remain “mindful of the purposes of the statute in deciding how strict to be in
    interpreting the Guidelines.” (El Morro Community Assn. v. California Dept.
    of Parks & Recreation (2004) 
    122 Cal.App.4th 1341
    , 1354 (El Morro).) In this
    case, the EIR’s analysis incorporated the information gleaned from the site
    visits and databases and generally identified the source and date of such
    information.
    Moreover, the City provided an extended public review and comment
    period for the Draft EIR from March 1 to May 21, 2018, affording petitioners
    an ample opportunity to request the background details of the identified site
    visits. In El Morro, supra, 
    122 Cal.App.4th 1341
    , for example, when the
    petitioner complained of the draft EIR’s failure to specifically reference each
    of its supporting technical reports, the agency responded with a list of the
    reports and advised the petitioner the reports were available for public
    review in the agency’s office. (Id. at p. 1353.) Here, however, petitioners first
    22
    raised their complaint just hours before the City Council’s February 3, 2020,
    hearing on the Final EIR, which did not allow the City to respond in a similar
    manner.
    In sum, petitioners fail to show that the EIR was rendered legally
    inadequate simply because no special status species analysis was conducted
    in 2007. (See Save Our Peninsula, supra, 87 Cal.App.4th at p. 117.) As the
    EIR explains, its special status species analysis was drawn from site visits,
    studies, and habitat evaluations that were undertaken both before and after
    the Notice of Preparation, and there is no indication the analysis was flawed
    due to material changes in the on-site habitats over the time period at issue.
    Thus, the EIR’s analysis and the information upon which it relied allowed for
    intelligent decisionmaking concerning the Project’s impacts on the identified
    special status bird and bat species that might forage, roost, or nest on the
    site, as well as its impacts on special status fisheries habitat and on special
    status turtle and frog species.
    Having rejected the claimed inadequacy of the EIR’s special status
    species analysis, we reject petitioners’ further contention that the EIR could
    not and did not offer recommendations that would adequately mitigate the
    Project’s impacts on these protected species.
    C. The EIR Properly Analyzed Public Safety Impacts Relating
    to Emergencies
    In accordance with CEQA, CEQA Guidelines, the City’s plans and
    policies, and agency and professional standards, the EIR acknowledged the
    Project’s impact would be considered significant if the Project would, as
    indicated in Appendix G of the Guidelines,12 “[i]mpair implementation of or
    12    Appendix G of the Guidelines contains a sample checklist of
    environmental considerations that lead agencies may use to assess a project’s
    impact.
    23
    physically interfere with an adopted emergency response plan or emergency
    evacuation plan.” (Italics added.)
    The EIR surveyed the applicable regulatory landscape and highlighted
    the City’s adoption of the “2013 California Fire Code,” which incorporates the
    “2012 Edition of the International Fire Code.” The EIR identified the
    following emergency-related code provisions relevant to the proposed Project:
    “D103.3—Turning Radius. The minimum turning radius shall be
    determined by the Fire Code Official or as approved by local standards.
    [¶] D103.4—Dead Ends. Dead-end fire apparatus access roads in excess of
    one hundred fifty feet (150’) (45.720 m) shall be provided with width and
    turnaround provisions in accordance with the local agency requirements for
    public streets or as approved by local standards. [¶] D106.1—Projects
    Having More Than Fifty (50) Dwelling Units. Multiple-family
    residential projects having more than fifty (50) dwelling units shall be
    provided with two (2) separate and approved fire apparatus access roads.”
    In view of these code provisions, the Draft EIR had proposed emergency
    access to the Project site via existing Graylawn Avenue, with EVA
    (Emergency Vehicle Access) at Bernice Court and the creation of an at-grade
    crossing over railroad tracks (the Shasta Avenue extension). But the Final
    EIR proposed to eliminate the at-grade rail crossing in response to concerns
    that the crossing “would substantially increase roadway hazards and hazards
    for emergency vehicles accessing the Project site” and generate other
    undesirable impacts and complications. Instead, the Final EIR explained
    that “[t]wo driveway connections are proposed to connect the Project to
    Graylawn Avenue” and, as proposed in the Draft EIR, Bernice Court would
    provide “a secondary means of emergency access to the site.” The Bernice
    Court connection would provide emergency vehicle access “designed to meet
    24
    all fire apparatus, turning radius and turnaround requirements of the
    Petaluma Fire Code.”
    Significantly, the EIR reported that “[t]he Petaluma Fire Department
    has reviewed this proposed EVA route and found it to provide acceptable
    emergency access to the site.” Moreover, the EIR explained, the “EVA design
    shall also meet additional recommendations of the City Fire Marshal to
    prohibit parking and other obstructions, and to ensure that the Bernice Court
    EVA is continuously available for emergency use (e.g., bollards, red curb or
    red pavement striping, no-parking signage, etc.). Final EVA design
    measures, including specific design details demonstrating these requirements
    will be provided and reviewed pursuant to the [Site Plan and Architectural
    Review] process and subject to review and approval by the Fire Marshal.” In
    light of this analysis, the EIR determined the public safety/emergency access
    impacts of the Project were “Less than Significant.” All this amply supported
    the EIR’s conclusion that the Project would not “[i]mpair implementation of
    or physically interfere with an adopted emergency response plan or
    emergency evacuation plan.” (Guidelines, Appendix G, italics added.)
    Notably, petitioners fail to identify any other adopted emergency
    response or emergency evacuation plans that required EIR analysis. Instead,
    they cite to a CEQA guideline providing that an EIR “should evaluate any
    potentially significant direct, indirect, or cumulative environmental impacts
    of locating development in areas susceptible to hazardous conditions (e.g.,
    floodplains, coastlines, wildfire risk areas), including both short-term and
    long-term conditions, as identified in authoritative hazard maps, risk
    assessments or in land use plans addressing such hazards areas.”
    (Guidelines, § 15126.2, subd. (a).) In petitioners’ view, the EIR was legally
    deficient because it omitted an analysis of egress and evacuation safety even
    25
    though numerous current and former neighbors of the site submitted public
    comment sharing their experiences with flooding and grass fires in the area.
    Petitioners also cite to Professor Thomas Cova’s submission of a one-
    page letter less than a week before the City Council’s February 3, 2020,
    hearing on the Final EIR. In his letter, Professor Cova described himself as a
    “National Evacuation Expert” and opined that the Project may have
    significant public safety impacts in the event residents moving into the
    planned Sid Commons Apartments and residents from the neighboring Oak
    Creek Apartments have to evacuate from hazardous events such as “flooding
    along the Petaluma River, earthquakes, fire or a railway hazardous materials
    spill.” Noting that all such residents will be forced to use the same street for
    evacuations, Professor Cova called for further study of the impact of
    additional development.
    Even assuming, generously, that the submissions from the public and
    from Professor Cova provided evidence of a potential public safety impact as
    contemplated in section 15126.2 of the CEQA Guidelines, we may not
    reweigh conflicting evidence, and such submissions provide no basis for
    setting aside the City’s certification of the EIR. (See Laurel Heights, supra,
    47 Cal.3d at p. 393.) Rather, petitioners bear the burden of proving the EIR
    is legally inadequate. (Save Our Peninsula, supra, 87 Cal.App.4th at p. 117.)
    Our review of the EIR and administrative record discloses no cause for
    reversal. Case law establishes that an agency may rely on the expertise of its
    staff to determine that a project will not have a significant impact. (Gentry v.
    City of Murrieta (1995) 
    36 Cal.App.4th 1359
    , 1379–1380 [upholding
    sufficiency of agency’s initial study].) Here, a City staff memo prepared for
    the February 3, 2020, hearing corroborated the public safety analysis in the
    EIR. In addressing public concern that “floodwaters within Graylawn and
    26
    Jess Avenues would interfere with evacuation in the event of a 100-year
    flood,” the staff memo highlighted the point that the “Project does not propose
    any development within the regulatory floodplain of the Petaluma River. All
    development associated with the Sid Commons Apartment Project, including
    access roads and infrastructure are located outside of the 100-year
    floodplain.” This analysis was consistent with a FEMA floodplains mapping
    featured in the Final EIR showing that key access roadways were located
    outside the 100-year floodplain.13
    The staff memo also reflected information from the City’s Assistant
    Fire Chief, who serves as “emergency operations manager for the City’s
    Emergency Operations Center.” According to the memo, the Assistant Fire
    Chief confirmed that “the Fire Department does not have significant flood or
    fire access/egress concerns with development above the 100-year floodplain at
    the site. He stated that if Graylawn Avenue were to be impacted by
    13     The staff memo noted in more detail that the FEMA mapping had
    differed from the hydrology maps presented in the Draft EIR which showed
    “inundation of the Graylawn Avenue street section in a 100-year flood event,”
    and that this discrepancy generated a Planning Commission “query
    regarding the depth of floodwaters anticipated on Graylawn Avenue.” The
    memo then explained that subsequent conversations between the City
    Engineer and the hydrologist who prepared the modeling work on behalf of
    the City “led to the finding that the project modeling (FEIR Figures 4-3
    through 4-8) did not account for recent completion of the Payran area flood
    work and its impact of removing from the floodplain the area that FEMA
    designates as Zone A99 on its current mapping (FEIR Figure 4-2).” As
    explained in the Final EIR, “[t]he A99 designation is for areas that have
    received substantial flood improvements, but where flood control projects are
    not yet complete or not yet accounted for in FEMA mapping.” Thus, the staff
    memo concluded, “consistent with the FEMA mapping, Graylawn and Jess
    Avenues, as well as properties within the A99 Zone remain outside of the 100-
    year floodplain, both in the current condition and after the upstream
    terracing and cumulative upstream terracing with detention directed by the
    General Plan.” (Italics added.)
    27
    floodwaters in the future, tall/heavy vehicles and boats would be available for
    rescue/evacuations. Additionally, the area is not in the City’s ‘High Fire
    Severity Zone’ where large rapid fire development potential exits [sic]. While
    there are empty fields nearby that could pose a hazard of fire spread, he
    notes, these areas are on level ground with light fuels and any fire in the
    fields or spread to any structures nearby would likely require an evacuation
    of only impacted buildings, not the entire complex. The Fire Marshal’s
    acceptance of the EVA at Bernice Court as the second point of access will
    provide adequate access in the case of an emergency.”14 (Italics added.)
    Relying on Sierra Watch v. County of Placer (2021) 
    69 Cal.App.5th 86
    ,
    petitioners characterize the City staff memo as a post-EIR analysis that is
    insufficient to remedy the EIR’s omission of a required public safety
    discussion of evacuation impacts. Sierra Watch involved an EIR for a new
    resort with 850 lodging units, 30,000 square feet of commercial space, over
    3,000 parking spaces, and housing for up to 300 employees on approximately
    94 acres in Olympic Valley near Lake Tahoe. (Id. at p. 92.) There, the
    petitioner challenged the adequacy of the EIR because, among other things,
    its discussion of the environmental setting did not sufficiently acknowledge
    the proximity and uniqueness of Lake Tahoe. (Id. at p. 96.) The Court of
    Appeal agreed, observing that the EIR “offered only one parenthetical
    reference to Lake Tahoe” without addressing the lake’s importance, its
    characteristics, or its current condition. (Ibid.) Nor did the EIR consider the
    impact of the project’s generation of an additional 23,842 vehicle miles
    traveled (VMT) per day on the clarity of the lake and the air quality of the
    14   Although petitioners are correct that the City staff memo does not
    mention when the Assistant Fire Chief made his statements to staff, the
    administrative record contains documentation that the statements were
    made in an email to staff dated January 14, 2020.
    28
    lake basin. (Id. at pp. 97–102.) Although the county eventually analyzed the
    impact of the additional VMT a few days before certifying the EIR (id. at
    p. 102), the Court of Appeal concluded the analysis came far too late to
    permit informed decisionmaking (id. at p. 103).
    Sierra Watch offers no parallel to the situation here. As recounted
    above, the EIR identified the relevant provisions in the City’s emergency
    response plan and took into account specific information about the Project
    site and the actual threat of flood or fire at the site. Drawing from such
    information, the EIR then considered whether the Project would “[i]mpair
    implementation of or physically interfere with an adopted emergency
    response plan or emergency evacuation plan” (Guidelines, Appendix G, italics
    added) and concluded it would not. This was sufficient to demonstrate the
    analytic route from specific underlying evidence to the ultimate conclusion.
    (Laurel Heights, supra, 47 Cal.3d at p. 404.) Moreover, even though the City
    had not adopted an emergency evacuation plan, the City staff memo
    acknowledged the public concern over potential flood or fire evacuations.
    Staff spoke with the City’s Assistant Fire Chief and reported his assurance
    that the City Fire Department did not have significant flood “access/egress
    concerns” because the proposed development was situated above the 100-year
    floodplain and because “tall/heavy vehicles and boats would be available for
    rescue/evacuations” in the event of future floodwaters on Graylawn Avenue.
    The memo also documented the City’s Assistant Fire Chief’s confirmation
    that the Fire Department had no significant fire-related “access/egress
    concerns” because the area was not within the City’s “ ‘High Fire Severity
    Zone’ ” where large rapid fire development potential exists. Thus, the staff
    memo provides additional evidence supporting the City’s certification of the
    EIR.
    29
    In short, petitioners have not met their burden of proving any
    inadequacy of the EIR with regard to its analysis of public safety impacts
    relating to emergencies. (Save Our Peninsula, supra, 87 Cal.App.4th at
    p. 117.)
    Disposition
    The judgment is affirmed. Costs on appeal are awarded to real party in
    interest.
    _________________________
    Fujisaki, J.
    WE CONCUR:
    _________________________
    Tucher, P.J.
    _________________________
    Rodríguez, J.
    Save N. Petaluma Rivers & Wetlands et al. v. City of Petaluma (A163192)
    30
    Filed: 12/13/22
    CERTIFIED FOR PUBLICATION
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    FIRST APPELLATE DISTRICT
    DIVISION THREE
    SAVE NORTH PETALUMA RIVER
    AND WETLANDS et al.,
    Plaintiffs and Appellants,          A163192
    v.                                         (Sonoma County
    CITY OF PETALUMA et al.,                   Super. Ct. No. SCV-266157)
    Defendants and Respondents;
    J. CYRIL JOHNSON INVESTMENT
    CORPORATION,
    Real Party in Interest and
    Respondent.
    BY THE COURT:
    The written opinion which was filed on November 14, 2022, has now
    been certified for publication pursuant to rule 8.1105(b) of the California
    Rules of Court, and is ordered published in the official reports.
    Date:__December 13, 2022_______            ____TUCHER, P.J.____________P.J.
    Trial Court:   Sonoma County Superior Court
    Trial Judge:   Hon. Arthur A. Wick
    Counsel:       Lozeau/Drury, Rebecca L. Davis and Brian B. Flynn for
    Plaintiffs and Appellants.
    Jarvis Fay, Rick William Jarvis, Christine L. Crowl; Eric
    W. Danly, City Attorney and Jordan Green, Assistant
    City Attorney for Defendants and Respondents.
    Reuben Junius & Rose, Matthew David Visick and Sabrina
    Saba Eshaghi for Real Party in Interest and Respond-
    ent.
    

Document Info

Docket Number: A163192

Filed Date: 12/13/2022

Precedential Status: Precedential

Modified Date: 12/13/2022