Vought Construction Inc. v. Stock ( 2022 )


Menu:
  • Filed 10/24/22
    CERTIFIED FOR PUBLICATION
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    FIRST APPELLATE DISTRICT
    DIVISION FOUR
    VOUGHT CONSTRUCTION INC.,
    Plaintiff and Appellant,
    A164823
    v.
    JAY STOCK,                                 (Alameda County
    Super. Ct. No. RG 20067174)
    Defendant and Respondent.
    Vought Construction Inc. (Vought) appeals from a judgment following a
    bench trial on its claims against homeowner Jay Stock. Vought sought
    recovery of the balance due on his contract for the renovation of a house owned
    by Stock, additional compensation pursuant to a disputed change order, and
    penalties for the violation of a prompt-payment statute, Civil Code section
    8800 (section 8800). Stock did not dispute the unpaid amount Vought had
    earned for finished work under the terms of their agreement as modified by
    approved change orders, but he disputed the claim for additional
    compensation and asserted an offsetting claim for liquidated damages for
    delay. The court held that Vought was entitled to the undisputed balance due
    plus approximately half the disputed amount it claimed in additional
    compensation; that Stock was entitled to approximately half the amount he
    claimed as liquidated damages; and that Stock had not violated section 8800
    by withholding final payment pending resolution of the controversy. The court
    held that neither side had prevailed, so that neither was entitled to attorney
    1
    fees under section 8800 or to costs of suit under Code of Civil Procedure
    section 1032.
    We conclude that the trial court correctly ruled that the recent case of
    United Riggers & Erectors, Inc. v. Coast Iron & Steel Co. (2018) 
    4 Cal.5th 1082
    (United Riggers) did not prohibit Stock from temporarily withholding payment,
    and did not abuse its discretion in holding that neither party was the
    prevailing party for the purpose of awarding attorney fees under section 8800.
    However, Vought was the prevailing party for the purpose of recovering costs
    under Code of Civil Procedure section 1032.
    Factual and Procedural History
    In September 2019, Stock and Vought entered a modified form contract
    for a home renovation project. They replaced the form’s references to
    “architect” with “owner” because Stock’s architect had retired, and Stock
    intended to perform the project-administration role that the form provides will
    be performed by the project’s architect.
    The contract stated a “contract sum” of $374,000 1 to be paid in
    installments for the specified work. It required Vought to substantially
    complete the work by January 13, 2020, subject to potential adjustments. If
    Vought failed to complete the work by the adjusted date, Stock was entitled
    to $300 per day of delay as liquidated damages. Vought was required to
    submit a biweekly application for payment (AFP). Stock was to pay, within
    seven days of receiving an AFP, a sum calculated as follows: Determine the
    portions of the contract sum allocable to completed work and to materials and
    equipment procured, subtract payments already made, and subtract any
    1   Dollar amounts in this opinion are rounded to the nearest $1,000.
    2
    amount for which Stock had wholly or partly withheld 2 or nullified an AFP
    based on, inter alia, evidence that the project would not be completed by the
    deadline and that the unpaid contract balance would not cover liquidated
    damages due for delay. 3
    Over the course of the project, Stock approved eight change orders or
    other adjustments that raised the agreed contract sum by a total of $69,000,
    to $442,000. The parties also agreed to extend the substantial completion
    date to February 11, 2020.
    The problems arose from a “relatively small” component of the project
    that the court described as “installation of some fairly particular and involved
    railings that would match . . . ones that [Stock] already had on the interior of
    the home.” The court found that the railings were “sophisticated and
    complicated” and “required a significant amount of detail.” Further, “Stock
    was under the impression that these railings could be . . . purchased, ordered,
    2The contract referred to Stock having “withheld” or “nullified” AFPs
    because the original form provided for the contractor to submit AFPs to the
    architect, who would in turn either certify them to the owner for payment or
    withhold or nullify them if certain conditions were unmet.
    3    The contract states: “[T]he amount of each progress payment shall be
    computed as follows: [¶] .1 Take that portion of the Contract Sum properly
    allocable to completed Work . . . ; [¶] .2 Add that portion of the Contract Sum
    properly allocable to materials and equipment [procured and stored on site]
    . . . ; [¶] .3 Subtract the aggregate of previous payments made by the Owner;
    and [¶] .4 Subtract amounts, if any, for which the Homeowner has withheld
    or nullified [an AFP] as provided in Section 9.5 of AIA Document A201-2007.”
    Section 9.5 states that “The Architect may . . . withhold [an AFP] in whole or
    in part . . . to such extent as may be necessary in the Architect’s opinion to
    protect the Owner from loss for which the Contractor is responsible . . .
    because of [¶] * * * [¶] .6 reasonable evidence that the Work will not be
    completed within the Contract Time, and that the unpaid balance would not
    be adequate to cover actual or liquidated damages for the anticipated delay
    . . . .”
    3
    [and] installed, without a sophisticated set of . . . architectural drawings,
    because in his experience that had not been required for the work . . . done
    inside his house,” while Vought “did not have extensive experience with these
    railings and kept as a placeholder an amount . . . consistent with what they
    have used to price out other types of railing systems, which may have been
    possible to install without having detailed architectural drawings.”
    The court found that it was not until January 24, 2020—four months
    after work began in September 2019, and three weeks before the adjusted
    substantial completion date of February 11, 2020—that Vought confronted
    “the need to have [architectural] drawings and the need to get firm prices for
    the materials that it would take to make this installation,” and raised the
    issues with Stock. Because of ensuing delays in obtaining the requisite
    drawings and materials—exacerbated by the onset of the COVID-19
    pandemic—Vought was unable to finish installing the railings until August
    2020. Work on all other parts of the project was substantially complete and
    approved by inspectors by late May 2020.
    In April 2020, Vought sent Stock an AFP showing an updated contract
    sum of $73,000 then unpaid but did not request immediate payment. In May
    2020 Vought sent another AFP effectively identifying the same $73,000 as
    unpaid, valuing the work left to perform as $41,000, and demanding
    immediate payment of $32,000. Stock made no payment.
    In June 2020 Vought sent an AFP and a proposed $50,000 change order
    for the railings. The June AFP included the $50,000 and sought immediate
    payment of $78,000, equaling the difference (with minor variances) between
    the agreed, adjusted contract price of $437,000 (not including the unapproved
    $50,000 change order) and the payments to date of $363,000. Stock rejected
    the change order and made no payment.
    4
    In early July, Vought recorded a mechanic’s lien against the property
    for $78,000, and filed this action. On August 6, Vought sent an AFP with a
    proposed “change order” for $10,000 in “legal costs” and interest on unpaid
    progress payments. The AFP demanded payment of $142,000 (including the
    value of both unapproved change orders). Stock made no payment.
    On August 7, 2020, the project was completed. The work was
    satisfactory and priced by agreement at a value at least $73,000 more than
    Stock had paid, but Stock claimed he was entitled to withhold liquidated
    damages of $53,000. 4 Four months later, in December 2020, Stock paid Vought
    $20,000. At trial, Stock testified that “I realized I could [with]hold more than
    my liquidated damages claim, according to the law, but I didn’t want more
    than my liquidated damages claim.”
    In November 2021 the action proceeded to a four-day bench trial. The
    judge asked counsel to submit tables specifying “exactly where the parties
    agree and where they disagree about costs and expenses and payments.”
    Based on those tables and on the ensuing proceedings, the court made findings
    establishing that the undisputed difference between the agreed total price of
    the work and the amount already paid was $79,000 as of August 2020, and
    $59,000 as of December 2020. On Vought’s claim for $50,000 in additional
    compensation for the railings, the court found Vought entitled to $31,000.
    4 At oral argument, Vought pointed out that, in his August 13 email to
    Vought refusing to make further payment, Stock asserted only that he was
    entitled to liquidated damages of “$39,000.” The email in fact stated, “our
    contract stipulates that you will be obligated to pay liquidated damages of
    $300/day starting at the mutually agreed upon adjusted target completion
    date of 2/11/20. As of August 7, 2020, these damages total approximately
    $39,000” The $39,000 figure simply reflects an arithmetic error. August 7 is
    178 days after February 11, so Stock’s true claim as of August 13, 2020 was
    for 178 x $300, or $53,400.
    5
    On Stock’s claim for liquidated damages, the court found that, no later
    than 30 days after Vought began work—that is, by October 18, 2019—it should
    have begun to investigate what it would have to do to timely procure and
    install the railings. The court thus found that 98 of the 178 days’ total delay,
    from October 18, 2019, to January 24, 2020, were attributable to Vought, that
    none of the delay after January 24 was attributable to Vought, and that
    neither party “really controlled the outcome” after that date. The court thus
    awarded Stock $29,000 on his cross-claim for liquidated damages (98 days at
    $300/day).
    As of one week after the completion date of August 7, 2020, the court
    thus held, the true unpaid balance—taking into account both the undisputed
    claims and the disputed claims as resolved at trial—was $81,000. After
    Stock’s $20,000 payment in December 2020, the unpaid balance was $61,000.
    The court awarded Vought contractual interest at 1.5 percent per month on a
    balance of $81,000 from August 14 to December 4, 2020, and on a balance of
    $61,000 from that date onward. It found that each party had acted
    unreasonably in part, but in good faith, in withholding or demanding greater
    payment, and each had prevailed in part. It requested further briefing on the
    issue of attorney fees.
    At a hearing four weeks later the court stated that it “has a fair amount
    of discretion in determining which party is the prevailing party,” and
    considering the case “in its totality,” the court held that “neither party is the
    prevailing party.” 5 It ruled that “fees under Section 8800 are not appropriate
    because there was . . . a good faith dispute between the parties as to what
    5The day before that hearing, Vought filed a request for a written
    statement of decision, which the court orally denied as untimely because not
    made within 10 days of its oral ruling at the end of trial on November 10 (see
    Cal. Rules of Court, rule 3.1590).
    6
    needed to be paid.” The court confirmed that it had read United Riggers, on
    which Vought relied, without indicating how it found the case distinguishable.
    Following the hearing, the court signed a proposed order and judgment.
    The order states that “both parties have partially prevailed on claims asserted
    in their respective complaints, but neither . . . is the prevailing party.” It
    awarded Vought $61,000 plus $17,000 in interest; it awarded neither party
    attorney fees or costs.
    Vought made several postjudgment filings challenging the trial judge’s
    rulings, all of which were addressed by a different judge. In all respects
    relevant to the issues on appeal, the court declined to disturb the trial judge’s
    rulings and struck Vought’s cost bill. 6 Vought filed a timely notice of appeal
    from the judgment and from the appealable postjudgment orders.
    DISCUSSION
    1. Standards of Review
    Vought’s opening brief made four main contentions: (1) that Stock
    violated section 8800 as a matter of law; (2) that also as a matter of law
    Vought is the prevailing party under Code of Civil Procedure section 1032
    and therefore the prevailing party for purposes of attorney fees under
    section 8800; (3) that delays due to Stock’s bad-faith performance of his role as
    architect bar his liquidated damages claim; and (4) that the court erred in
    6
    Vought filed a motion to vacate the judgment and enter a new one
    awarding remedies for a violation of section 8800 and a motion for a new trial
    based on, inter alia, the court’s failure to find such a violation, its award of
    excessive liquidated damages, and its refusal to issue a statement of decision.
    Vought also filed a memorandum of costs and, after Stock moved to strike the
    memorandum, an opposition contending that Vought was the prevailing party
    entitled to costs as a matter of law under Code of Civil Procedure section 1032.
    The court denied Vought’s motions to vacate the judgment and for a new trial
    and granted Stock’s motion to strike the costs memo.
    7
    failing to order foreclosure of the mechanic’s lien. 7 We review all four issues
    de novo. The first two attack only legal conclusions based on undisputed
    factual findings. (Westfour Corp. v. California First Bank (1992) 
    3 Cal.App.4th 1554
    , 1558.) Similarly, whether the undisputed evidence compelled a finding
    that Stock caused more than 80 days of delay is a legal issue we decide in the
    first instance. (Estes v. Eaton Corp. (2020) 
    51 Cal.App.5th 636
    , 651.) And,
    while an action to enforce a mechanic’s lien sounds in equity (Burton v.
    Sosinsky (1988) 
    203 Cal.App.3d 562
    , 572), Stock does not claim that the court’s
    failure to order foreclosure rests on a discretionary application of equitable
    principles, so we review de novo whether its findings compel relief. In
    supplemental briefing, the parties have agreed, as do we, that the standard
    for “prevailing party” status under Code of Civil Procedure section 1032 does
    not govern the “prevailing party” analysis for purposes of attorney fees
    pursuant to section 8800, and that we review for abuse of discretion the trial
    court’s determination that no party prevailed for this purpose. (James L.
    Harris Painting & Decorating, Inc. v. West Bay Builders, Inc. (2015)
    
    239 Cal.App.4th 1214
    , 1221–1222 (Harris Painting).)
    2. The Findings Do Not Establish a Violation of Section 8800
    Section 8800 states, “(a) Except as otherwise agreed in writing . . . , the
    owner shall pay the direct contractor, within 30 days after notice demanding
    7
    Vought also challenges the denial of its new trial motion, arguing that
    its request for a statement of decision was timely (see fn. 5, ante) and that
    failure to issue a timely requested statement mandates a new trial. (Wallis v.
    PHL Assocs., Inc. (2013) 
    220 Cal.App.4th 814
    , 826–827.) But as the trial court
    observed in denying Vought’s motion, any such error would warrant relief only
    if it were prejudicial. (F.P. v. Monier (2017) 
    3 Cal.5th 1099
    , 1102.) Vought
    does not dispute the need to show prejudice but makes no attempt to do so; it
    has thus forfeited the issue.
    8
    payment pursuant to the contract is given,[8] any progress payment due as to
    which there is no good faith dispute between them. . . . [¶] (b) If there is a
    good faith dispute between the owner and direct contractor as to a progress
    payment due, the owner may withhold from the progress payment an amount
    not in excess of 150 percent of the disputed amount.” As discussed below, an
    owner who violates the statute is liable for penalties, costs, and attorney fees.
    (§ 8800, subd. (c).)
    Vought contends that section 8800 did not allow Stock to withhold the
    $79,000 progress payment undisputedly earned and unpaid in August 2020
    based on his disputed claim for liquidated damages and the disputed change
    orders. Vought relies on United Riggers, supra, 
    4 Cal.5th 1082
    , which involved
    a dispute between a direct contractor (contractor) and a subcontractor under a
    parallel prompt-payment statute, Civil Code section 8814. That statute
    governs retention payments from contractors to subcontractors, but the
    analysis in United Riggers applies to all prompt payment statutes, including
    section 8800. 9
    In United Riggers, the subcontractor did work that was undisputedly
    satisfactory, complete, and valued at a certain price, and it also asserted
    8
    The contract here altered the default rule of section 8800 by requiring
    progress payments within seven days of receipt of AFPs. Neither party
    disputes that the payment due within seven days of Stock’s receipt of the
    August 6 AFP constituted a “progress payment” for purposes of section 8800.
    9   Civil Code section 8814 “is one of a series of provisions meant to
    ensure timely payment to contractors and subcontractors. To the extent
    possible, statutes relating to the same class of things, and sharing the same
    purpose or object, should be harmonized and construed similarly. [Citations.]
    . . . This interpretive principle applies to the prompt payment statutes
    [citations], which were largely modeled on each other and designed to
    accomplish the same end in a series of closely related contexts.” (United
    Riggers, supra, 4 Cal.5th at p. 1090.)
    9
    disputed claims for additional payment based on proposed change orders.
    (United Riggers, supra, 4 Cal.5th at p. 1086.) Because of the disputed change
    orders, the contractor refused to pay the subcontractor the amount
    undisputedly due, and the subcontractor sued for penalties, costs, and fees
    under Civil Code section 8814. (Ibid.) United Riggers resolved an ambiguity in
    section 8814, determining that the statute does not permit a contractor to
    withhold payment based on any good faith dispute, but only based on disputes
    regarding the specific payment due. (Id. at p. 1089; see § 8800, subd. (b)
    [permitting withholding “[i]f there is a good faith dispute between the owner
    and direct contractor as to a progress payment due”].) The court relied on the
    remedial purpose of prompt-payment statutes, and noted that permitting
    contractors to withhold payment based on any dispute would give them a
    windfall—an interest-free loan of the amount not in dispute. Such an
    interpretation would enable a contractor to “chill the assertion of legitimate
    claims for additional compensation.” (United Riggers, supra, at pp. 1092–
    1093.) Thus, the contractor was not entitled to withhold the amount
    admittedly due because of a dispute as to whether an additional amount was
    due.
    The holding in United Riggers has no application here, to a good faith
    dispute over an amount that would reduce, rather than increase, the net
    amount otherwise due. The court stated that withholding is permitted “when
    payment would result in the [payee] receiving more than the minimum
    amount both sides agree is due.” However, a payor may not withhold a
    payment “that is simply part of that undisputed minimum amount” merely
    because “a dispute has arisen over whether additional amounts over and above
    the [payment due] might also be owed.” (United Riggers, supra, 4 Cal.5th at
    pp. 1097–1098; id. at p. 1085 [“Controversies concerning unrelated work or
    10
    additional payments above the amount both sides agree is owed will not excuse
    delay”].) A payor, in short, “must be able to present a good faith argument for
    why all or a part of the withheld monies themselves are no longer due.” (Id. at
    p. 1098.)
    Thus, Stock was not prohibited from withholding the $79,000 otherwise
    due based on his good faith claim for liquidated damages, which gave him “a
    good faith argument for why all or a part of the withheld monies themselves
    [were] no longer due.” (United Riggers, supra, 4 Cal.5th at p. 1098.) Although
    Stock claimed only $53,000 in liquidated damages, section 8800 authorized
    him to withhold 150 percent of that amount, slightly more than the $79,000
    otherwise undisputedly due Vought as of August 14, 2020. 10
    Vought’s contention that the dispute over liquidated damages was not a
    dispute “as to [the] progress payment due,” as required by subdivision (b) of
    section 8800, 11 is thus at odds with the purpose of section 8800 and the
    decision in United Riggers. Moreover, the contention disregards the language
    of the contract (see fn. 3, ante), which explicitly provides that approval of an
    AFP may be withheld based on “reasonable evidence that the Work will not be
    completed within the Contract Time, and that the unpaid balance would not
    10 The statute’s 150 percent authorization reflects a recognition that the
    value of an owner’s offsetting claim will often be uncertain, as when the claim
    is for defective workmanship. (United Riggers, supra, 4 Cal.5th at p. 1097.)
    As applied here, however, the 150 percent authorization seems at odds with
    the purpose of the statute, since there was no uncertainty that $53,400 was
    the maximum possible setoff to which Stock could be entitled. Indeed, Stock
    testified, “I realized I could [with]hold more than my liquidated damages
    claim, according to the law, but I didn’t want more than my . . . claim.”
    Nevertheless, the statute is explicit and unconditional.
    11
    Section 8800, subdivision (b) permits withholding “[i]f there is a good
    faith dispute between the owner and direct contractor as to a progress
    payment due.”
    11
    be adequate to cover actual or liquidated damages for the anticipated delay
    . . . .”
    Vought contends that section 15.1.3 of the contract, entitled
    “Continuing Contract Performance,” required Stock to pay the amount
    claimed despite his offsetting claim for liquidated damages. Section 15.1.3
    states that “Pending final resolution of a claim, except as otherwise agreed in
    writing or as provided in Section 9.7 or Article 14,[12] the Contractor shall
    proceed diligently with performance of the Contract and the Owner shall
    continue to make payments in accordance with the Contract Documents.”
    But as noted (see fn. 3, ante), section 9.5 of the contract states that “The
    Architect may . . . withhold [an AFP] in whole or in part to such extent as
    may be necessary . . . to protect the Owner from loss . . . because of [¶] . . .
    [¶] . . . reasonable evidence that the Work will not be completed within the
    Contract Time, and that the unpaid balance would not be adequate to cover
    actual or liquidated damages for the anticipated delay . . . .” 13 Vought
    contends that section 9.5 authorized Stock at most to withhold the amount of
    his liquidated damages claim, not 150 percent of that amount. However,
    section 8800, subdivision (b) states that “If there is a good faith dispute
    between the owner and direct contractor as to a progress payment due, the
    owner may withhold from the progress payment an amount not in excess of
    150 percent of the disputed amount.” That provision creates a statutory right,
    which the contract does not purport to restrict or waive, to withhold up to
    Section 9.7 governs the contractor’s right to stop work upon a failure
    12
    of payment, and article 14 concerns termination or suspension of the
    contract. Neither is relevant here.
    The August AFP for $142,000 included $59,000 in disputed and
    13
    unapproved change orders and was “withheld” in full by Stock acting as
    architect. The trial court correctly held that the undisputed contract balance
    when Stock withheld payment was $79,000.
    12
    150 percent of a disputed amount from a progress payment if there is a good
    faith dispute as to that progress payment. Section 9.5 of the contract makes
    clear that a good faith dispute as to liquidated damages qualifies as a dispute
    “as to a progress payment due,” triggering the owner’s statutory right to
    withhold 150 percent of the disputed amount.
    In short, the trial court properly held that Stock did not violate section
    8800 by withholding payment of the amount due Vought pending resolution
    of his claim for liquidated damages.
    2.    The trial court had the discretion to determine which, if either,
    party prevailed for the purpose of awarding attorney fees under
    section 8800, subdivision (c).
    Section 8800, subdivision (c) states, “In an action for collection of the
    amount wrongfully withheld, the prevailing party is entitled to costs and a
    reasonable attorney’s fee.” Arguing that the definition of “prevailing party” in
    section 1032 controls, Vought’s opening and reply briefs contend it is the
    prevailing party because it secured a “net monetary recovery.” However, the
    definition in section 1032, discussed below, does not govern the meaning of
    the term in other statutory provisions that authorize an award of attorney
    fees. (DeSaulles v. Community Hospital of Monterey Peninsula (2016)
    
    62 Cal.4th 1140
    , 1147; Duff v. Jaguar Land Rover of North America, LLC
    (2022) 
    74 Cal.App.5th 491
    , 504.) Indeed, Stock arguably was the prevailing
    party here because the court correctly held that he did not violate section
    8800 by withholding less than 150 percent of the disputed amount of
    liquidated damages. However, we agree with the trial court that it had the
    discretion to determine which, if either, party prevailed.
    The court’s discretion was recognized in Brawley v. J.C. Interiors, Inc.
    (2008) 
    161 Cal.App.4th 1126
    , 1137. As the court there explained, “Unlike
    section 1032, . . . [the prompt-payment statute] contains no definition of the
    13
    term ‘prevailing party.’ ‘[C]ourts in cases involving . . . statutes which provide
    that the prevailing party “shall” recover attorney fees also have concluded
    that a court has the discretion to find there is no prevailing party, even
    though the statute does not expressly say so. [Citations] The determination of
    whether there is to be a prevailing party is to be made “on a practical level”
    after considering what each party accomplished via the litigation.” ’ ” (Ibid.)
    The court in Harris Painting, supra, 239 Cal.App.4th at page 1220, adopted
    that approach. 14
    Vought now contends that the court abused its discretion in failing to
    find it the prevailing party based on a practical evaluation of the “litigation
    as a whole” (Harris Painting, supra, 239 Cal.App.4th at p. 1223). Vought
    notes its net monetary recovery, the court’s finding that it was not reasonable
    for Stock to withhold for four months the $20,000 he admitted was
    “uncontested”, and the purpose of prompt-payment statutes (see United
    Riggers, supra, 4 Cal.5th at p. 1092 [“State policy strongly supports liberally
    construing this law for the benefit of those it is intended to protect”]). While
    those factors might support an award of fees, they are counterbalanced by the
    court’s finding that each party acted in good faith, if at times unreasonably;
    Vought’s failure to prove that Stock violated section 8800; and that both
    parties recovered approximately half of what they sought. On this record, the
    14
    Harris Painting and Brawley both involved other prompt-payment
    statutes, but those statutes had fee provisions essentially identical to section
    8800, subdivision (c). (See Harris Painting, supra, 239 Cal.App.4th at
    p. 1219, quoting Bus. & Prof. Code, § 7108.5, subd. (c) [“[i]n any action for the
    collection of funds wrongfully withheld, the prevailing party shall be entitled
    to his or her attorney’s fees and costs”]; Brawley v. J.C. Interiors, Inc., supra,
    161 Cal.App.4th at p. 1137, quoting Civ. Code, former § 3260, subd. (g)
    [same].)
    14
    court did not exceed the bounds of reason in concluding that neither was a
    prevailing party entitled to recover its attorney fees. 15
    3. Vought is the prevailing party entitled to recover its costs
    under Code of Civil Procedure section 1032.
    Subdivision (a)(4) of Code of Civil Procedure section 1032 defines the
    prevailing party for the purpose of recovering routine costs in a civil action.
    “ ‘Prevailing party’ includes the party with a net monetary recovery, a
    defendant in whose favor a dismissal is entered, a defendant where neither
    plaintiff nor defendant obtains any relief, and a defendant as against those
    plaintiffs who do not recover any relief against that defendant. If any party
    recovers other than monetary relief and in situations other than as specified,
    the ‘prevailing party’ shall be as determined by the court . . . .” (Ibid.)
    Vought is unquestionably “the party with a net monetary recovery,”
    specified in the first sentence. It recovered $61,000, plus interest. “It is clear
    from the statutory language that when there is a party with a ‘net monetary
    recovery’ (one of the four categories of prevailing party), that party is entitled
    to costs as a matter of right; the trial court has no discretion to order
    [otherwise].” (Michell v. Olick (1996) 
    49 Cal.App.4th 1194
    , 1198.)
    In rejecting Vought’s claim that it was the prevailing party under
    subdivision (a)(4) of Code of Civil Procedure section 1032, the judge hearing
    the matter stated, “[The trial judge] made specific fact-findings that went
    beyond a mere judgment for monetary relief in favor of one party or the other.
    . . . [A]mong those findings, [the trial judge] determined that neither side was
    a ‘prevailing party.’ [This] finding was entirely consistent with [a court’s]
    discretion under Code of Civil Procedure section 1032(a)(4) . . . .” The court
    did not cite, nor has Stock, any authority holding that a party “recovers other
    15   The parties’ contract did not include an attorney-fee provision.
    15
    than monetary relief,” conferring discretion on the court under the second
    sentence of subdivision (a)(4) to determine the prevailing party, merely by
    securing favorable findings or reducing the setoff claimed by the opposing
    party. Such does not constitute “relief” under subdivision (a)(4). Only Vought
    secured a monetary recovery, albeit for less than the full amount it sought.
    Vought therefore was the prevailing party entitled to costs as a matter of law
    because it secured a “net monetary recovery,” and the court lacked discretion
    to rule otherwise.
    Thus, the court erred in striking Vought’s cost memorandum, and the
    matter must be remanded for the trial court to consider any objections to the
    specific amounts requested.
    4. The Evidence Did Not Compel a Different Finding as to Delay.
    As noted, the project’s completion was delayed by 178 days, from
    February 11 to August 7, 2020. The court found 98 days of that delay due to
    Vought’s failure to investigate how it would complete the railings installation
    until January 24, 2020, or 128 days after work on the project began. The court
    found that the contractor should have begun to address the issue within
    30 days of starting work. Vought now contends that “[b]ecause Stock himself
    delayed the project and made it impossible to finish by the February 2020
    target,” the court was required to dismiss his liquidated damages claim.
    Vought cites expert testimony that the contract called for Stock to
    perform the role of architect; that the contract did not include complete design
    drawings for the railings; that Vought could not have installed the railings
    with the information available on February 15, 2020; and that once
    architectural drawings were available, it was necessary to generate shop
    drawings to fabricate the railings. Vought also contends that Stock added a
    new scope of work to the project “in January 2020” that involved tiling the
    stairs, which affected the design of the railings to be attached to those stairs;
    16
    that Stock did not deliver a tiling design until February 25; and that he did
    not sign a change order for the tiling until March 13.
    The common flaw in these arguments is that they concern conduct by
    Stock that occurred largely or entirely after, and was causally unrelated to,
    the 98-day period from October 18, 2019, to January 24, 2020, during which
    the court found that Vought unreasonably failed to begin addressing the
    railings issue. The court found all delay after January 24, 2020 to be the fault
    of neither party. Even if Vought’s evidence compelled a finding that all the
    post-January 24 delay was the fault of Stock, that would not undermine the
    finding that Vought’s 98-day delay in beginning to address the railings issue
    delayed the project’s ultimate completion by 98 days.
    Vought contends that Peter Kiewit Sons’ Co. v. Pasadena City Junior
    College Dist. (1963) 
    59 Cal.2d 241
     compels dismissal of Stock’s cross-claim.
    That case held that where late completion of a project “was caused by matters
    beyond [a contractor]’s control and was entirely excusable,” liquidated
    damages were unavailable. (Id. at p. 244.) But the court here found the late
    completion due partly to matters within Vought’s control, and thus only
    partly excusable. Vought also cites Howard J. White, Inc. v. Varian Associates
    (1960) 
    178 Cal.App.2d 348
    , which upheld dismissal of a liquidated damages
    claim on similar grounds, but there, too, the court did not attribute any of the
    delay to the contractor (id. at p. 355). The trial court here correctly held that
    Vought was not relieved of the obligation to pay liquidated damages for the
    delay that it caused even though it was not responsible for the entire delay.
    5. Vought Is Entitled to Foreclosure of Its Mechanic’s Lien
    The court did not resolve Vought’s cause of action to foreclose on its
    mechanic’s lien. Vought contends the court erred in failing to adjudge a lien
    on the property in the sum of $78,241.57 plus interest, and to order
    17
    foreclosure, as Stock raised no defense to the lien. 16 Stock responds that the
    judgment is for a lesser amount ($77,870.70) than the requested lien. But if a
    lien is excessive in amount, absent evidence of fraud the court should simply
    order it reduced to the amount due. (Basic Modular Facilities, Inc. v.
    Ehsanipour (1999) 
    70 Cal.App.4th 1480
    , 1485.)
    Vought proved the elements of a cause of action to foreclose on a
    mechanic’s lien: the fact that its labor, services, and materials were used in a
    work of improvement, the reasonable value of its contribution, and the date
    the work was complete. (Basic Modular Facilities, Inc. v. Ehsanipour¸ supra,
    70 Cal.App.4th at p. 1485.) It is entitled to a judgment ordering foreclosure
    on the lien—subject, of course, to Stock’s right of redemption (Civ. Code,
    § 2903) and to Vought’s duty to credit against the lien any payment received
    pursuant to its personal judgment against Stock (id., § 8468, subd. (b)).
    DISPOSITION
    The judgment is affirmed insofar as it awards Vought the principal
    sum of $61,105.45 plus contractual prejudgment interest through
    December 10, 2021 ($16,765.25). The order striking Vought’s cost
    memorandum is reversed. The matter is remanded so that the trial court may
    award Vought contractual prejudgment interest through the date of entry of
    a revised judgment, award it routine litigation costs pursuant to Code of Civil
    Procedure section 1032, subdivision (a)(4), and order foreclosure on Vought’s
    mechanic’s lien. Vought shall recover its costs of the proceedings in this court.
    16 Stock contended below that the lien was unenforceable because it had
    been recorded prematurely in July 2020, before the substantial completion
    date of August 7, 2020. The trial court did not find the lien unenforceable for
    that reason, and Stock does not renew that argument on appeal.
    18
    POLLAK, P. J.
    WE CONCUR:
    BROWN, J.
    GOLDMAN, J.
    19
    Trial court:                Alameda County Superior Court
    Trial judge:                Honorable Noel Wise and Michael Markman
    Counsel for plaintiff and   Mark N. White
    appellant:
    Counsel for defendant and   LEPERA + ASSOCIATES, PC
    respondent:                 Joseph A. Lepera
    Patrick A. Hormillosa
    Donel R. Lopez
    20
    

Document Info

Docket Number: A164823

Filed Date: 10/24/2022

Precedential Status: Precedential

Modified Date: 10/24/2022