Vascos Excavation Group v. Gold CA2/5 ( 2022 )


Menu:
  • Filed 12/21/22 Vascos Excavation Group v. Gold CA2/5
    NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS
    California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions
    not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion
    has not been certified for publication or ordered published for purposes of rule 8.1115.
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    SECOND APPELLATE DISTRICT
    DIVISION FIVE
    VASCOS EXCAVATION GROUP,                                             B315205
    LLC,
    (Los Angeles County
    Plaintiff and Appellant,                                   Super. Ct. No. 20STCV01372)
    v.
    ROBERT GOLD,
    Defendant and Respondent.
    APPEAL from an order of the Superior Court of
    Los Angeles County, Timothy P. Dillon, Judge. Affirmed.
    Law Office of Daniel M. O’Leary and Daniel M. O’Leary for
    Plaintiff and Appellant.
    The Law Offices of Abdulaziz, Grossbart & Rudman and
    Bruce D. Rudman for Defendant and Respondent.
    Plaintiff and appellant Vascos Excavation Group, LLC
    (Vascos), a contractor, prevailed in an arbitration against its
    client, defendant and respondent Robert Gold. After finding that
    Vascos was not duly licensed because its responsible managing
    employee (RME) did not meet the criteria required by law, the
    trial court granted Gold’s petition to vacate the arbitration award
    on the ground the arbitrator exceeded her powers.
    Vascos makes two main arguments on appeal. It first
    contends the trial court misapplied the burden of proof regarding
    whether Vascos was a duly licensed contractor. We reject this
    argument. The trial court correctly determined that Vascos had
    the burden of proof on this issue.
    Vascos also argues the trial court erroneously denied it an
    evidentiary hearing. In the trial court, however, Vascos did not
    seek an evidentiary hearing. It instead argued that such a
    hearing was not authorized by law. Vascos therefore forfeited the
    issue on appeal.
    BACKGROUND
    In June 2019, Vascos and Gold executed a written
    agreement. Under the contract, in exchange for monetary
    compensation, Vascos was required to perform certain
    excavation, grading, and concrete work at Gold’s property in
    Pacific Palisades. The contract included an arbitration clause.
    A dispute arose between Vascos and Gold regarding the
    amount Gold owed under the contract. Vascos recorded a
    mechanics lien and then, in January 2020, filed a complaint in
    superior court against Gold to enforce the lien.
    Gold did not file an answer to the complaint. Instead, he
    filed a petition to compel arbitration. Vascos responded by filing
    a notice of non-opposition to the petition and serving Gold with a
    2
    demand for arbitration with the American Arbitration
    Association (AAA) pursuant to AAA’s Construction Industry
    Arbitration Rules and Mediation Procedures (Construction
    Arbitration Rules). The court then entered an order compelling
    the parties to arbitrate.
    AAA advised counsel for both sides that it would apply the
    Construction Arbitration Rules and assigned the matter to
    arbitrator Marcia Haber Kamine. Gold corresponded with the
    arbitrator but did not file an answer to Vascos’ demand for
    arbitration.
    The arbitrator held a four-day hearing in October 2020.
    After both parties rested, Gold argued that Vascos was barred
    from seeking compensation because it was not a duly licensed
    contractor. The arbitrator re-opened the arbitration for the
    limited purpose of giving Vascos an opportunity to prove it had a
    valid license.
    Vascos filed a certified copy of its license, showing its
    license was current and that John Matthew Welch was its RME.
    On the RME issue, Vascos filed a declaration by Victor Montes,
    the project manager at Gold’s property. Montes attached a
    “snippet” of two videos that purportedly show Welch at the
    construction site on June 29 and August 10, 2020. These videos
    are not in the record.
    In January 2021, the arbitrator issued an interim award,
    finding that Vascos was entitled to recover $111,440.29 in
    damages and penalties. In the interim award, the arbitrator
    found: “The evidence of Mr. Welch’s participation was his
    attendance at the job site on at least one occasion, and that he
    worked remotely from his home in his capacity as RME. Working
    remotely would allow Mr. Welch to make administrative
    3
    decisions. For this reason, the challenge to his RME status is
    over ruled.” The arbitrator issued a final award in February
    2021, adopting the relevant portions of her interim award.
    In March 2021, Gold filed a petition to vacate arbitration
    award in the superior court. Vascos opposed the petition and
    asked the court to confirm the arbitration award.
    On July 28, 2021, the trial court entered an order granting
    1
    Gold’s petition to vacate the arbitration award. The trial court
    found Vascos failed to meet its burden of proving that Welch was
    a bona fide RME and, consequently, failed to show that Vascos
    was a duly licensed contractor at the time it provided Gold with
    construction services.
    Vascos timely appealed.
    DISCUSSION
    I.    The Trial Court Did Not Misapply the Burden of
    Proof
    A.    An Arbitration Award Issued Pursuant to an
    Unenforceable Contract May be Vacated
    The trial court compelled an arbitration in this case
    pursuant to an arbitration clause in the contract between the
    parties. The Legislature has enacted a comprehensive statutory
    scheme regulating arbitration in furtherance of a “ ‘strong public
    policy in favor of arbitration as a speedy and relatively
    inexpensive means of dispute resolution.’ ” (Moncharsh v. Heily
    & Blase (1992) 
    3 Cal.4th 1
    , 9 (Moncharsh).)
    1
    The trial court also denied Vascos’ request to
    “partially correct” the award to grant Vascos attorney fees.
    Vascos does not make any argument on appeal regarding this
    issue.
    4
    Generally, an arbitration award is final. (See Moncharsh,
    
    supra,
     3 Cal.4th at p. 9.) “The scope of judicial review of
    arbitration awards is extremely narrow because of the strong
    public policy in favor of arbitration and according finality to
    arbitration awards.” (Ahdout v. Hekmatjah (2013) 
    213 Cal.App.4th 21
    , 33 (Ahdout).)
    A trial court may vacate an arbitration award only on
    certain, enumerated grounds. (Code Civ. Proc., § 1286.2.) One
    ground is that the arbitrator exceeded his or her powers. (Id. at
    § 1286.2, subd. (a)(4).) “[T]he power of the arbitrator to
    determine the rights of the parties is dependent upon the
    existence of a valid contract under which such rights might
    arise.” (Loving & Evans v. Blick (1949) 
    33 Cal.2d 603
    , 610
    (Loving & Evans).)
    In Loving & Evans, an unlicensed contractor prevailed in
    an arbitration against its client. Our Supreme Court held the
    trial court erred in confirming the arbitration award because the
    underlying contract was illegal. (Loving & Evans, supra, 33
    Cal.2d at pp. 614–615.) Since Loving & Evans, the courts have
    repeatedly upheld the rule that arbitration awards issued
    pursuant to illegal or unenforceable contracts must be vacated.
    (See, e.g., All Points Traders, Inc. v. Barrington Associates (1989)
    
    211 Cal.App.3d 723
    , 738 [unlicensed real estate broker];
    Lindenstadt v. Staff Builders, Inc. (1997) 
    55 Cal.App.4th 882
    , 893
    (Lindenstadt) [unlicensed real estate broker]; Richey v.
    AutoNation, Inc. (2015) 
    60 Cal.4th 909
    , 917 [“judicial review may
    be warranted when a party claims that an arbitrator has
    enforced an entire contract or transaction that is illegal”];
    Sheppard, Mullin, Richter & Hampton, LLP v. J-M
    5
    Manufacturing Co. (2018) 
    6 Cal.5th 59
    , 73–75 (Sheppard Mullin)
    [violation of attorney professional responsibility rules].)
    While the California Supreme Court has “identified limits”
    to the Loving & Evans exception to arbitral finality, it has
    “not questioned the continued validity” of the exception.
    (Sheppard Mullin, supra, 6 Cal.5th at p. 75.) “[T]he basic
    premise of Loving & Evans is that an agreement to arbitrate is
    invalid and unenforceable if it is made as part of a contract that
    is invalid and unenforceable because it violates public policy.”
    (Sheppard Mullin, at pp. 78–79.)
    B.    The Trial Court and This Court Review the Issue of
    Illegality/Unenforceability De Novo
    “Whether a contract is entirely illegal, and therefore
    unenforceable, is an issue ‘for judicial determination upon the
    evidence presented to the trial court, and any preliminary
    determination of the legality by the arbitrator . . . should not be
    held to be binding upon the trial court.’ ” (Sheppard Mullin,
    supra, 
    6 Cal.5th 59
     at pp. 74–75 [quoting Loving & Evans];
    accord Ahdout, supra, 213 Cal.App.4th at p. 33.)
    We review the trial court’s decision regarding whether an
    arbitrator exceeded his or her powers de novo. (Haworth v.
    Superior Court (2010) 
    50 Cal.4th 372
    , 382; Ahdout, supra, 213
    Cal.App.4th p. 33.)
    C.    The Requirements of the CSLL
    The purpose of the Contractors State License Law (CSLL;
    Bus. & Prof. Code, § 7000 et seq.)2 is to protect the public from
    2
    Unless otherwise stated, all future statutory
    references are to the Business and Professions Code.
    6
    incompetent and dishonest contractors who provide building and
    construction services. (Manela v. Stone (2021) 
    66 Cal.App.5th 90
    ,
    102; Hydrotech Systems, Ltd. v. Oasis Waterpark (1991) 
    52 Cal.3d 988
    , 995 (Hydrotech).) To further that goal, the CSLL “imposes
    strict and harsh penalties for a contractor’s failure to maintain
    proper licensure.” (MW Erectors, Inc. v. Niederhauser
    Ornamental & Metal Works Co., Inc. (2005) 
    36 Cal.4th 412
    , 418
    (MW Erectors).)
    Under the CSLL, a contractor may not maintain any
    action, legal or equitable, to recover compensation for the
    “performance of any act or contract” unless the contractor was
    duly licensed “at all times during the performance of that act or
    contract.” (§ 7031, subd. (a).)
    A limited liability company (LLC) like Vascos may qualify
    for a license through the qualification of certain individuals
    affiliated with the company, including an RME. (§ 7068, subd.
    (b)(4).) If an RME is disassociated with an LLC, and is not
    replaced within 90 days of the disassociation date, the company’s
    license is automatically suspended. (§ 7068.2, subd. (a); Buzgheia
    v. Leasco Sierra Grove (1997) 
    60 Cal.App.4th 374
    , 387
    (Buzgheia).)
    An RME must satisfy two basic requirements. The
    individual must be (1) a “bona fide employee” of the LLC and (2)
    “actively engaged” in the work for which the LLC has a license.
    (§ 7068, subd. (c)(1).) “Bona fide employee” of the LLC means an
    employee who is “permanently employed.” (§ 7068, subd.
    (c)(2)(A).) “ ‘Actively engaged’ means working 32 hours per week,
    or 80 percent of the total hours per week that the [LLC’s]
    business is in operation, whichever is less.” (§ 7068, subd.
    (c)(2)(B).)
    7
    An RME “shall be responsible for exercising supervision
    and control of their employer’s or principal’s construction
    operations to secure compliance” with the CSLL and related
    regulations. (§ 7068.1, subd. (a).)
    D.    The Trial Court’s Order Was Correct
    Section 7031, subdivision (d) provides: “If licensure or
    proper licensure is controverted, then proof of licensure pursuant
    to this section shall be made by production of a verified certificate
    of licensure from the Contractors State License Board which
    establishes that the individual or entity bringing the action was
    duly licensed in the proper classification of contractors at all
    times during the performance of any act or contract covered by
    the action. Nothing in this subdivision shall require any person
    or entity controverting licensure or proper licensure to produce a
    verified certificate. When licensure or proper licensure is
    controverted, the burden of proof to establish licensure or proper
    licensure shall be on the licensee.”
    Vascos suggests that it met its burden of demonstrating it
    had a valid license by producing a copy of its certificate and had
    no further burden to prove that it was properly licensed because
    defendant did not meet its burden of proving that the RME was a
    sham. We disagree. Indeed, the court in Buzgheia rejected the
    argument made by the contractor in that case that it “had no
    burden other than to produce the license certificate.” (Buzgheia,
    supra, 60 Cal.App.4th at p. 389.) Instead, the court found that
    “production of the certificate is necessary, but insufficient if the
    point is controverted.” (Ibid.)
    A party sued by a corporate contractor may also challenge
    the contractor’s license on the ground that the RME is a “sham.”
    (Buzgheia, supra, 60 Cal.App.4th at p. 385.) “If the RME was a
    8
    sham, the contractor is barred from recovery because [it] is, in
    effect, acting outside the license, just like a specialty contractor
    who labors at a task for which he or she has no expertise nor
    license.” (Id. at p. 386.) The contractor has the burden of proof
    on the issue of whether it has a bona fide RME. (Id. at p. 389;
    Jeff Tracy, Inc. v. City of Pico Rivera (2015) 
    240 Cal.App.4th 510
    ,
    516–518 (Jeff Tracy, Inc.).)
    In Jeff Tracy, Inc., the defendant argued the plaintiff
    contractor could not recover compensation because it had a sham
    RME. The trial court denied the contractor’s request for a jury
    trial on the issue pursuant to Code of Civil Procedure section 597,
    which permits non-jury trials on special defenses. The Court of
    Appeal reversed, holding that the contractor’s licensure—
    including its satisfaction of the RME requirements—is an
    element of its breach of contract claim. (Jeff Tracy, Inc., supra,
    240 Cal.App.4th at p. 518.)
    A plaintiff, of course, has the burden of proof with respect
    to each element of its causes of action. (Evid. Code, § 500.)
    In Buzgheia, the defendants argued the plaintiff contractor
    could not prevail because his company had a sham RME. The
    trial court instructed the jury the contractor’s presentation of a
    certificate of licensure shifted the burden of proof on the issue of
    licensure to the defendants. (Buzgheia, supra, 60 Cal.App.4th at
    p. 383.) The Court of Appeal held this instruction was erroneous
    because the contractor’s burden “included the burden of proving
    compliance with the RME requirements.” (Id. at p. 393.)
    Similarly, in the present case, Vascos’ presentation of a
    certificate of licensure did not end the inquiry or shift the burden
    of proof. As the trial court correctly determined, Vascos had the
    burden of proof on the issue of whether its purported RME,
    9
    Welch, was bona fide. This is because Vascos’ licensure through
    a bona fide RME is an element of its cause of action.
    Vascos did not meet its burden. It presented no evidence
    showing Welch was a “permanent” employee of the company.
    Vascos also failed to present any evidence that Welch worked 32
    hours per week, or 80 percent of the total hours per week that the
    company’s business was in operation.
    The only evidence in the record on this issue is a
    declaration by project manager Victor Montes.3 Although Montes
    states that he attaches videos purporting to show Welch at Gold’s
    property, the videos are not in the record. In any case, even
    assuming Welch was at the project site on two occasions as
    Vascos claims, this falls far short of showing Welch was a bona
    fide RME.
    The trial court correctly noted that “Vascos could have
    easily submitted a declaration from Welch establishing that he
    was a bona fide RME.” Vascos could have met its burden, the
    trial court stated, with a “five sentence declaration” from Welch.
    We agree with the trial court’s observation. The burden on
    Vascos was not high, yet it failed to meet it.
    Vascos argues it never had the burden on the issue of
    licensure because the issue was not “controverted” by Gold within
    the meaning of section 7031, subdivision (d). We disagree.
    3
    The parties make different assertions about the
    evidence presented to the arbitrator regarding the RME issue.
    There was no court reporter at the arbitration hearing and very
    little of the evidence the arbitrator considered is in the record.
    From our perspective, “if it is not in the record, it did not
    happen.” (Protect Our Water v. County of Merced (2003) 
    110 Cal.App.4th 362
    , 364.)
    10
    “[A] defendant’s answer containing a general denial of the
    material allegations of the contractor’s claim [citation] is
    sufficient to ‘controvert’ the contractor’s allegation of licensure,
    and thus invokes the requirement of section 7031, subdivision
    (d) . . . .” (Advantec Group, Inc. v. Edwin’s Plumbing Co., Inc.
    (2007) 
    153 Cal.App.4th 621
    , 624.) Here, though Gold did not file
    an answer in court, he did controvert Vascos’ licensure at the
    arbitration.
    The AAA Construction Arbitration Rules provide that the
    parties may proceed under “Regular Track” or “Fast Track”
    procedures.4 Pursuant to stipulation of the parties, the arbitrator
    applied the Fast Track Procedures in this case.
    Section F-2 of the Fast Track Procedures provides: “If an
    answer or counterclaim is to be filed, it shall be filed within seven
    calendar days after notice of the filing of the demand is sent by
    the AAA. All other requirements of Section R-4 apply.”
    Section R-4(c)(i) of the Regular Track Procedures, in turn,
    provides: “A respondent may file an answering statement with
    the AAA within 14 calendar days after notice of the filing of the
    demand is sent by the AAA. . . . If no answering statement is
    filed within the stated time, the respondent will be deemed to
    deny the claim.”
    In the present case, while Gold did not file an answering
    statement, he was “deemed” to deny Vascos’ allegations,
    including its allegation that it was a duly licensed contractor.
    Gold also argued in his closing arbitration brief that Vascos was
    4
    The Fast Track Procedures are in the record. We
    take judicial notice of the remainder of the Construction
    Arbitration Rules. (Evid. Code, §§ 452, subd. (h), 459, subd. (a).)
    11
    not duly licensed because Welch was not a bona fide RME. After
    Gold made this argument, Vascos was given an opportunity to
    present evidence on the issue at the arbitration.
    Vascos’ contention that Gold did not controvert its licensure
    claim elevates form over substance. This argument also fails to
    account for the public policy underlying section 7031. The shield
    against the “evil targeted by section 7031” is undermined if the
    RME is sham. (Buzgheia, supra, 60 Cal.App.4th at p. 387.)
    “Because of the strength and clarity of this policy, it is well
    settled that section 7031 applies despite injustice to the
    unlicensed contractor.” (Hydrotech, 
    supra,
     52 Cal.3d at p. 995.)
    Moreover, there are sound public policy reasons for placing
    the burden on the contractor rather than the consumer under
    these circumstances. “The contractor will (or should) have
    knowledge of how he has utilized the RME. The contractor will
    (or should) have greater access to evidence, namely his own
    records, including payroll records, timesheets, the names of other
    employees who can testify to the activities of the RME and so
    forth. The ‘most desirable result in terms of public policy in the
    absence of proof’ that a contractor complied with the licensing
    laws, including the RME provisions thereof, is that the contractor
    who evades the law should be barred from court. [Citations].”
    (Buzgheia, supra, 60 Cal.App.4th at p. 390.)
    Vascos argues that the trial court should have given
    “deference” to the arbitrator’s findings and that “[t]he Arbitration
    Award created a presumption of proper licensure.” As we have
    explained, however, this position has been repeatedly rejected by
    the courts. “A party seeking confirmation [of an arbitration
    award] cannot be permitted to rely upon the arbitrator’s
    conclusion of legality for the reason that paramount
    12
    considerations of public policy require that this vital issue be
    committed to the court’s determination whenever judicial aid is
    sought.” (Loving & Evans, supra, 33 Cal.2d at p. 614; accord
    Lindenstadt, supra, 
    55 Cal.App.4th 892
    –893 [holding trial court’s
    failure to review issue of illegality de novo was error]; Sheppard
    Mullin, supra, 6 Cal.5th at pp. 74–75 [affirming Loving & Evans
    rule].)
    Vascos’ reliance on MW Erectors is misplaced. There, the
    California Supreme Court held that “the CSLL does not
    automatically void all contracts entered by unlicensed
    contractors.” (MW Erectors, 
    supra,
     36 Cal.4th at p. 440.) In
    particular, the court held, “if fully licensed at all times during
    contractual performance, a contractor is not barred from
    recovering compensation for the work solely because he or she
    was unlicensed when the contract was executed.” (Id. at p. 419.)
    MW Erectors did not involve judicial review of an
    arbitration award and stated nothing about the issue here,
    namely the burden of proof on the issue of a contractor’s
    licensure. Further, the trial court’s decision is consistent with
    MW Erectors because there is no evidence that Vascos was a duly
    licensed contractor at any time, including when it performed its
    obligations under the contract.
    Vascos’ citation to Templo Calvario Spanish Assembly of
    God v. Gardner Construction Corp. (2011) 
    198 Cal.App.4th 509
    (Templo Calvario) is also unpersuasive. In Templo Calvario, an
    arbitrator ruled a consumer could disgorge fees it paid an
    unlicensed contractor. Citing MW Erectors, the court held the
    CSLL did not prohibit a consumer from arbitrating a dispute
    “simply because the contractor was unlicensed at the time of the
    13
    signing of the construction contract.” (Templo Calvario, supra,
    198 Cal.App.4th at p. 519.)
    The present case is factually distinguishable from Templo
    Calvario. Instead of a consumer seeking disgorgement from an
    unlicensed contractor, an unlicensed contractor is attempting to
    recover from a consumer. The Templo Calvario court expressly
    recognized this distinction. It noted that the CSLL and MW
    Erectors barred a contractor from “initiating any affirmative
    arbitration claim” and “bringing suit or using the courts to collect
    compensation of its work while unlicensed.” (Templo Calvario,
    supra, 198 Cal.App.4th at p. 519.)
    Vascos unconvincingly cites dicta in Tempo Calvario. The
    Templo Calvario court stated that MW Erectors “effectively”
    overruled Loving & Evans “on the issue of whether a contract
    entered into by an unlicensed contractor is automatically ‘ “illegal
    and void.” ’ ” (Templo Calvario, supra, 198 Cal.App.4th at p.
    520.) Addressing this comment, the Ahdout court stated that
    “even if Templo Calvario correctly interprets the state of the law,
    the decision does not affect the outcome here.” (Ahdout, supra,
    213 Cal.App.4th at p. 39, fn. 8.)
    The same is true in this case. Nothing in MW Erectors or
    Templo Calvario changes our analysis. Further, as explained
    ante, after MW Erectors, Templo Calvario, and Ahdout were
    decided, the California Supreme Court endorsed the continued
    validity of Loving & Evans, though it noted the decision has been
    limited in certain respects that do not change the outcome here.
    (See Sheppard Mullin, supra, 6 Cal.5th at pp. 75–79.)
    The trial court applied the correct burden of proof and
    reached the right result. Vascos did not meet its burden of
    proving it was a duly licensed contractor through a bona fide
    14
    RME. The arbitration award therefore must be vacated because
    the arbitrator exceeded her powers.
    II.   Vascos’ Request for an Evidentiary Hearing
    In his petition to vacate the arbitration award, Gold asked
    for an order permitting “very limited discovery to determine the
    existence of documents proving full-time employment of John
    Matthew Welch from June to November 2019, including: (a)
    payroll records with cancelled checks; (b) worker’s compensation
    employee reports; and (c) payroll tax returns.” (Italics omitted.)
    Gold also requested the trial court to conduct an evidentiary
    hearing with live witness testimony on whether Welch was a
    bona fide RME.
    In its opposition to Gold’s petition, Vascos objected to
    permitting discovery and holding an evidentiary hearing. Vascos
    argued that “Gold’s request for what would effectively be a new
    court trial on the issue of licensure is legally unsupported and
    unsupportable.” According to Vascos, the trial court only had
    authority, at most, to conduct “a de novo review of the available
    evidence to the trial court at the time of review.” (Italics and bold
    omitted.) Vascos asserted an evidentiary hearing would be an
    inappropriate “fishing expedition” that “is clearly not supported
    by law.”5
    Now, on appeal, Vascos argues that it “should have been
    given notice and an opportunity to present evidence of the bona
    5
    In support of his request for an evidentiary hearing,
    Gold cited Ahdout, supra, 213 Cal.App.4th at pp. 39–40 and
    Lindenstadt, supra, 55 Cal.App.4th at p. 893, fn. 8. Vascos
    argued Ahdout and Lindenstadt did not support Gold’s position.
    We do not reach this issue.
    15
    fides of its responsible managing employee prior to the trial
    court’s ruling.” The trial court, Vascos contends, “erred by not
    setting an evidentiary hearing.”
    Gold argues Vascos “waived” a request for an evidentiary
    hearing and is judicially estopped from contending it was
    deprived of an evidentiary hearing.
    A.    Waiver/Forfeiture
    “It is axiomatic that a party may not complain on appeal of
    rulings to which it acquiesced in the lower court.” (Porterville
    Citizens for Responsible Hillside Development v. City of
    Porterville (2007) 
    157 Cal.App.4th 885
    , 912 (Porterville).)
    Although “waiver” and “forfeiture” are often used
    interchangeably to describe a party’s failure to raise an issue in
    the trial court, the two terms should be differentiated. (In re
    Stier (2007) 
    152 Cal.App.4th 63
    , 74.) “ ‘ “ ‘Whereas forfeiture is
    the failure to make the timely assertion of a right, waiver is the
    “intentional relinquishment or abandonment of a known right.”
    [Citations.]’ [Citation.]” [Citation.]’ ” (Ibid.) Forfeiture is “the
    correct legal term to describe the loss of the right to raise an
    issue on appeal due to the failure to pursue it in the trial court.”
    (Ibid.; accord Porterville, at p. 912.)
    Vascos forfeited on appeal any argument that the trial
    court should have conducted an evidentiary hearing because it
    did not ask for one in the trial court. To the contrary, Vascos
    successfully opposed such a hearing.
    B.    Judicial Estoppel
    Because we conclude Vascos forfeited its argument that the
    trial court denied it an evidentiary hearing, we do not reach the
    16
    issue of whether Vascos is judicially estopped from making that
    argument.
    DISPOSITION
    The July 28, 2021, order of the superior court is affirmed.
    Respondent Robert Gold is awarded his costs on appeal.
    NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS
    TAMZARIAN, J. *
    We concur:
    BAKER, Acting P.J.
    KIM, J.
    *
    Judge of the Los Angeles County Superior Court, assigned
    by the Chief Justice pursuant to article VI, section 6 of the
    California Constitution.
    17