Joshua v. San Francisquito Creek Joint Powers Authority CA1/2 ( 2022 )


Menu:
  • Filed 8/23/22 Joshua v. San Francisquito Creek Joint Powers Authority CA1/2
    NOT TO BE PUBLISHED IN OFFICIAL REPORTS
    California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
    publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or
    ordered published for purposes of rule 8.1115.
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    FIRST APPELLATE DISTRICT
    DIVISION TWO
    PETER JOSHUA,
    Plaintiff and Appellant,
    A163294
    v.
    SAN FRANCISQUITO CREEK                                                 (San Mateo County
    JOINT POWERS AUTHORITY, et                                             Super. Ct. No. 19CIV06305)
    al.,
    Defendants and Respondents.
    Appellant Peter Joshua filed an unsuccessful petition for a writ of
    mandamus alleging that the San Francisquito Creek Joint Powers Authority
    (SFCJPA) failed to comply with the California Environmental Quality Act
    (Pub. Res. Code, § 21000 et seq.) (CEQA) in preparing an Environmental
    Impact Report (EIR) in connection with a project to make certain
    improvements to protect from floods in the San Francisquito creek watershed
    (the project). He argues that the EIR failed to consider a reasonable range of
    alternatives to the project because certain alternatives were part of the
    SFCJPA’s overall program, that another alternative considered in the EIR
    was invalid because it did not lessen the environmental impacts of the
    project, and that the statement of overriding considerations adopted by the
    1
    SFCJPA failed to find certain of the alternatives infeasible. We reject the
    arguments, and we affirm.
    BACKGROUND
    Against a history of flooding, the SFCJPA developed the “San
    Francisquito Creek Flood Protection, Ecosystem Restoration, and Recreation
    Project Upstream of Highway 101.” And, following rigorous CEQA review,
    the project culminated in a lengthy EIR, which EIR provided an excellent
    background of the setting here. We thus begin with extensive quotation from
    that EIR:
    “San Francisquito Creek originates in the eastern foothills of the Santa
    Cruz Mountains and drains a watershed that is approximately 45 square
    miles in size, from Skyline Boulevard to San Francisco Bay. The watershed
    contains three reservoirs (Searsville, Lagunita, and Felt) and several
    tributary creeks, including Los Trancos, West Union, Alambique, Bear, and
    Corte Madera Creek as well as many smaller tributaries that drain into the
    creeks. San Francisquito Creek begins at the confluence of Corte Madera
    Creek and Bear Creek, just downstream of Searsville Dam, and flows
    through Stanford University and the communities of Menlo Park, Palo Alto,
    and East Palo Alto to San Francisco Bay. San Francisquito Creek represents
    the boundary between Santa Clara and San Mateo Counties and the cities of
    Menlo Park, Palo Alto, and East Palo Alto. The watershed’s 5-square-mile
    floodplain is located primarily within these cities.”
    “For this Program EIR, San Francisquito Creek is described in three
    reaches (Figure 1-2). Reach 1 extends from San Francisco Bay to the
    upstream side of U.S. Highway 101. SFCJPA has completed construction of
    improvements in Reach 1 following the completion of CEQA documentation
    in 2012. This Program EIR does not include proposed actions in Reach 1,
    2
    though the upstream end of Reach 1 may be traversed for construction access
    to a channel-widening site within Reach 2 (Site 5). Reach 2 extends from the
    upstream side of the frontage road to U.S. Highway 101 (West Bayshore
    Road) to the upstream side of the Pope-Chaucer Bridge. Reach 3 begins on
    the upstream side of the Pope-Chaucer Bridge and extends throughout the
    upper watershed.”
    “Flooding from the creek is a common occurrence, including twice
    within the past decade. The largest flow recorded since [record keeping]
    began in 1930 occurred in February 1998, when the creek overtopped its
    banks in several areas, affecting approximately 1,700 . . . propert[ies.]” That
    event is now considered by SFCJPA and the Corps to have been
    approximately “a 70-year flood, [relative] to the commonly referenced
    [standard of a] 100-year flood event.[1]”
    The EIR thus described the specific objectives of the project as follows:
    “Protect life, property, and infrastructure from floodwaters exiting the
    creek during flows up to 7,500 cubic feet per second (cfs), while minimizing
    impacts of the project on adjacent communities and the environment;
    “Enhance habitat within the project area, particularly interconnected
    habitat for threatened and endangered species;
    “Create new recreational opportunities and connect to existing bike and
    pedestrian corridors;
    “Minimize operational and maintenance requirements; and
    “Not preclude future actions to bring cumulative flood protection up to
    a 100-year flow event.”
    1 The 100-year flood is considered to have a 1 percent chance of
    occurring in any given year.
    3
    The EIR explained how the SFJCPA evaluated the project and various
    alternatives to it, including the following regarding how the process began
    with a list of 17 potential projects:
    “For the past two decades, members of the public, local agency staff
    members, and the U.S. Army Corps of Engineers have been analyzing the
    capital improvements necessary to protect communities within the flood-
    prone Reach 2 of San Francisquito Creek, upstream of U.S. Highway 101.
    The three fundamental approaches to providing flood protection—contain,
    detain, or bypass—with the specific alternatives proposed for analysis,
    include:
    “Enable the creek to contain higher flows during storms by removing
    constrictions or raising the height of the creek bank in the floodplain area
    (Alternatives 2, 5, 6, 7, 8, 10, 11, 12, and 17),
    “Temporarily detain or store portions of high flows during storms
    through one or more floodwater detention facilities in Reach 3 (Alternatives
    3, 9, 13, and 16), and/or
    “Remove a portion of the high flows immediately upstream of Reach 2,
    route that portion of the flow through the flood-prone area in an
    underground bypass channel, and deposit this water at a location in the creek
    that can safely convey it to San Francisco Bay (Alternatives 4, 14, and 15).”
    The SFJCPA went on to screen the 17 alternatives as follows:
    “Alternatives 2 through 17 were evaluated using a two-round approach.
    In Round 1 (Table 2-1), alternatives were evaluated for their ability to meet
    the project objectives. None of the alternatives would preclude future actions
    to bring cumulative flood protection up to a 100-year flood event and
    therefore this objective was not evaluated. Alternatives that could not
    4
    achieve project objectives were excluded from further consideration (i.e.,
    screened out). The alternatives that could potentially meet project objectives
    were subject to feasibility evaluation in Round 2 (Table 2-2).”
    “The previous screening process examined how well each of the 17
    alternatives met the project objectives, and then the cost, and logistical and
    technical feasibility, of the remaining alternatives.
    “The following alternatives advanced through this screening process:
    “Alternative 2: Replace the Pope-Chaucer Bridge and Widen Channel
    Downstream.
    “Alternative 3: Construct One or More Detention Basins.
    “Alternative 5: Replace the Pope-Chaucer Bridge and Construct
    Floodwalls Downstream.
    “As described below, these alternatives were grouped according to the
    reaches in which they primarily occur, then re-organized and renamed. This
    EIR analyzes Alternative 3 (from this point forward referred to separately as
    the Former Nursery Detention Basin Alternative and the Webb Ranch
    Detention Basin Alternative) at a programmatic level because, in concert
    with the alternatives proposed in Reach 2, they would help to the overall
    objective of protecting people and property from water resulting from at least
    a 100-year event by increasing the conveyance and/or detention of water.
    Additionally, this EIR conducts a more detailed project level analysis for
    Alternative 2 and Alternative 5 to enable the implementation of the first
    phase of work immediately upstream of the highway to allow the creek to
    contain (and thus protect communities there from) flows up to the 1998 flood
    event level. These alternatives also advance local priorities of enhancing
    creek habitat and recreational opportunities.”
    5
    “Within Reach 2, Alternatives 2 and 5 advanced for full analysis in the
    EIR. Alternative 2 was renamed the Channel Widening Alternative, and
    Alternative 5 was renamed the Floodwalls Alternative. Both alternatives
    include replacing the Pope-Chaucer Bridge and widening the channel
    immediately upstream of U.S. Highway 101 (Site 5) to align the channel with
    the recently completed modifications to the bridge at the highway’s West
    Bayshore frontage road. Where Alternatives 2 and 5 differ is in how they
    achieve flood protection between those two locations. The Channel Widening
    Alternative would involve primarily creek channel widening, replacing
    decades-old sacked concrete walls with more vertical, architecturally treated
    soil nail walls or sheet pile walls. The Floodwalls Alternative would involve
    construction of floodwalls at the top of the creek’s banks. Finally, both
    alternatives would include construction of creekside parks and aquatic
    habitat enhancements and potentially creekside parks (Figures 2-1 and 2-2).”
    “Within Reach 3, Alternative 3 advanced for full analysis in the
    Program EIR. Alternative 3 was split into two alternatives, each
    representing one of the two potential detention basin sites. The potential
    detention basin at the previous site of Boething plant nursery is called the
    Former Nursery Detention Basin Alternative and the potential detention
    basin at Webb Ranch is called the Webb Ranch Detention Basin Alternative.”
    And so the EIR went to fully analyze 5 potential projects: the
    statutorily-required “No-Project” alternative, the Channel Widening
    Alternative, the Floodwalls Alternative, and two detention basin alternatives:
    the Former Nursery Detention Basin Alternative and the Webb Ranch
    Detention Basin Alternative. Based on this analysis, the EIR deemed the
    Channel Widening Alternative the “Preferred Project,” and adopted the
    6
    following statement of overriding considerations recommending that it be
    approved:
    “In light of the environmental, social, economic, and other
    considerations identified below and supported by the substantial evidence in
    the EIR, the SFCJPA chooses to approve the proposed project because, in its
    view, such benefits substantially outweigh the significant and unavoidable
    adverse environmental effects. The following statements identify the reasons
    why, in the SFCJPA’s judgment, the benefits of the project outweigh the
    significant and unavoidable effects. Each of the overriding considerations set
    forth below constitutes a separate and independent ground for finding that
    the benefits of the project outweigh its significant adverse environmental
    effects and is an overriding consideration warranting approval:
    “1. The proposed project would restore San Francisquito Creek to its
    natural capacity throughout the project reach; this improved hydrologic
    functioning provides long-term benefits to aquatic species.
    “2. The proposed project would restore aquatic habitat by installing
    permanent woody debris, boulders, pools, and other features to
    approximately 1,800 linear feet of the channel at widening sites and the
    Pope-Chaucer Bridge. These elements, together with the improvements in
    hydrologic function in the project reach, will provide long-term benefits to
    salmonids and other aquatic species.
    “3. The proposed project will provide flood protection benefits to over
    4,000 homes, businesses, and schools in the San Francisquito Creek
    floodplain. Although implementation of this project by itself will not
    completely remove the affected area from the FEMA 100-year flood zone, it
    will protect life, property, and infrastructure from the largest recorded flood
    7
    flow and reduce damages during higher flows. Thus, it is a key piece of
    SFCJPA’s long-term comprehensive flood protection strategy.
    “4. The proposed project will create recreational opportunities by
    connecting the new features to existing bike and pedestrian corridors and
    potentially constructing two creekside parks.
    “In summary, in consideration of the existing flood risks along San
    Francisquito Creek associated with lack of adequate capacity in the Creek
    channel, and the analysis of project outcomes presented in the Final EIR,
    SFCJPA finds that the economic, social, and environmental benefits of
    meeting the project’s goals and objectives outweigh the significant and
    unavoidable noise and cumulative air quality impacts associated with the
    project’s construction.”
    At a public meeting on September 26, 2019, the SFCJPA certified
    the EIR, adopted the statement of overriding considerations, and
    approved the project.
    On October 24, Joshua filed a petition for writ of mandamus
    challenging that approval, alleging a single cause of action for alleged
    violations of CEQA.
    The petition came on for hearing on March 25, 2021, at the conclusion
    of which the trial court took the matter under submission. On June 4, the
    trial court issued an order denying the writ petition in its entirety.
    Judgment was entered on July 9, from which        Joshua filed a notice of
    appeal.
    DISCUSSION
    Applicable Law
    “As a general proposition, CEQA depends on the EIR. ‘An
    environmental impact report is an informational document,’ the purpose of
    8
    which ‘is to provide public agencies and the public in general with detailed
    information about the effect which a proposed project is likely to have on the
    environment; to list ways in which the significant effects of such a project
    might be minimized; and to indicate alternatives to such a project.’ (Pub.
    Resources Code, § 21061.)[2] According to our Supreme Court: ‘The purpose
    of an EIR is to give the public and government agencies the information
    needed to make informed decisions, thus protecting “ ‘not only the
    environment but also informed self-government.’ ” [Citation.] The EIR is the
    heart of CEQA, and the mitigation and alternatives discussion forms the core
    of [an] EIR.’ (In re Bay–Delta Etc. (2008) 
    43 Cal.4th 1143
    , 1162.)” (Tiburon
    Open Space Committee v. County of Marin (2022) 
    78 Cal.App.5th 700
    , 724–
    725 (Tiburon Open Space).)
    “The judicial attitude to EIRs is deferential. ‘A court’s task is not to . . .
    determine who has the better argument when the dispute is whether adverse
    effects have been mitigated or could be better mitigated. We have neither the
    resources nor [the] scientific expertise to engage in such analysis . . . .’
    (Laurel Heights [Improvement Assn. v. Regents of University of California
    (1988)] 
    47 Cal.3d 376
    , 393.) It follows that courts ‘do not require technical
    perfection or scientific certainty.’ (Sierra Club v. County of Fresno (2018)
    
    6 Cal.5th 502
    , 515.)
    2  “Statutory references are to this code unless otherwise indicated. . . .
    We will abbreviate citations to the regulations promulgated by the Secretary
    of the Natural Resources Agency found in title 14 of the California Code of
    Regulations beginning at section 15000, as ‘Guidelines’ which, we have noted,
    ‘are binding upon all state and local agencies in applying CEQA.’
    (Schellinger Brothers v. City of Sebastopol (2009) 
    179 Cal.App.4th 1245
    , 1256,
    fn. 12.)”
    9
    “The scope of judicial scrutiny proceeds along two paths.
    ‘ “Section 21168.5 provides that a court’s inquiry in an action to set aside an
    agency’s decision under CEQA ‘shall extend only to whether there was a
    prejudicial abuse of discretion. Abuse of discretion is established if the
    agency has not proceeded in a manner required by law or if the
    determination or decision is not supported by substantial evidence.’ As a
    result of this standard, ‘The court does not pass upon the correctness of the
    EIR’s environmental conclusions, but only upon its sufficiency as an
    informative document.’ [Citation.]” [Citation.] “We may not set aside an
    agency’s approval of an EIR on the ground that an opposite conclusion would
    have been equally or more reasonable.” [Citation.] [¶] “An appellate court’s
    review of the administrative record for legal error and substantial evidence in
    a CEQA case, as in other mandamus cases, is the same as the trial court’s:
    The appellate court reviews the agency’s action, not the trial court’s decision;
    in that sense appellate judicial review under CEQA is de novo.” [Citation.]’
    (In re Bay–Delta Etc., supra, 
    43 Cal.4th 1143
    , 1161–1162.)
    “ ‘The agency is the finder of fact and a court must indulge all
    reasonable inferences from the evidence that would support the agency’s
    determinations and resolve all conflicts in the evidence in favor of the
    agency’s decision. . . . “A court’s task is not to weigh conflicting evidence and
    determine who has the better argument when the dispute is whether adverse
    effects have been mitigated or could be better mitigated. We have neither the
    resources nor scientific expertise to engage in such analysis, even if the
    statutorily prescribed standard of review permitted us to do so.” [Citation.]
    “[T]he relevant inquiry here is not whether the record establishes compliance
    but whether the record contains evidence [the agency] failed to comply with
    the requirements of its . . . regulatory program. In the absence of contrary
    10
    evidence, we presume regular performance of official duty. (Evid. Code,
    § 664.)” ’ (Gilroy Citizens for Responsible Planning v. City of Gilroy (2006)
    
    140 Cal.App.4th 911
    , 918–919.)
    “Every court ‘presumes a public agency’s decision to certify the EIR is
    correct, thereby imposing on a party challenging it the burden of establishing
    otherwise.’ (Sierra Club v. City of Orange (2008) 
    163 Cal.App.4th 523
    , 530.)
    Conversely, courts refuse to presume administrative error, still less that it is
    prejudicial. (§ 21005, subd. (b).) In fact, ‘errors in the CEQA . . . process
    which are insubstantial or de minimis are not prejudicial.’ (Environmental
    Protection Information Center v. California Dept. of Forestry & Fire Protection
    (2008) 
    44 Cal.4th 459
    , 486; see Neighbors for Smart Rail v. Exposition Metro
    Line Construction Authority (2013) 
    57 Cal.4th 439
    , 463 [‘Insubstantial or
    merely technical omissions are not grounds for relief’].)
    “Legal error, in the form of failure to comply with CEQA, is reviewed
    independently, but all factual determinations are reviewed according to the
    substantial evidence standard. ‘The substantial evidence standard is applied
    to conclusions, findings and determinations. It also applies to challenges to
    the scope of an EIR’s analysis of a topic, the methodology used for studying
    an impact and the reliability or accuracy of the data upon which the EIR
    relied because these types of challenges involve factual questions.’
    (Bakersfield Citizens for Local Control v. City of Bakersfield (2004)
    
    124 Cal.App.4th 1184
    , 1198.)” (Tiburon Open Space, supra, 78 Cal.App.5th
    at pp. 727–728, fn. omitted.)
    The range of alternatives included in an EIR must be “potentially
    feasible alternatives that will foster informed decisionmaking and public
    participation.” (Guidelines, § 15126, subd. (a).) “An EIR shall describe a
    range of reasonable alternatives to the project . . . which would feasibly attain
    11
    most of the basic objectives of the project but would avoid or substantially
    lessen any of the significant effects of the project, and evaluate the
    comparative merits of the alternatives.” (Ibid.; see Preservation Action
    Council v. City of San Jose (2006) 
    141 Cal.App.4th 1336
    , 1350.)
    “ ‘Both the California and the federal courts have further declared that
    “[t]he statutory requirements for consideration of alternatives must be judged
    against a rule of reason.” ’ ([Citizens of] Goleta [Valley v. Board of Supervisors
    (1990)] 52 Cal.3d [553,] 565.) We uphold an agency’s selection of alternatives
    unless it is ‘manifestly unreasonable’ or inclusion of an alternative does not
    ‘[contribute to] a reasonable range of alternatives.’ (Ibid.)” (Bay Area
    Citizens v. Ass’n of Bay Area Governments (2016) 
    248 Cal.App.4th 966
    , 1018.)
    The rule of reason “requires the EIR to set forth only those alternatives
    necessary to permit a reasoned choice” and to “examine in detail only the
    ones that the lead agency determines could feasibly attain most of the basic
    objectives of the project.” (Guidelines, § 15126.6, subd. (f).)
    The Detention Basin Alternatives Are Not Invalid
    Joshua’s first argument is that the detention basin alternatives are
    “not valid” because they are not stand-alone projects but rather “future
    components of the overall Program and SFCJPA strategy,” pointing to certain
    acknowledgements in the record that the projects in Reach 2 would
    “complement” or work “in concert” with the detention basin proposals in
    Reach 3. We reject the argument.
    First, Joshua is simply wrong that the detention basin alternatives
    could not have been stand-alone projects. It was plainly possible to build
    detention basin facilities in Reach 3 without also completing the project.
    Indeed, the draft EIR notes that the “detention basins at Searsville, Webb
    Ranch, and the former plant nursery represent potentially feasible
    12
    alternatives that would, as a stand-alone project, provide real flood
    protection.” A December 19, 2016 revised notice of preparation for the draft
    EIR explained: “In its Draft EIR, the SFCJPA will evaluate the No Action
    alternative and four other alternatives, each of which could be implemented
    as a stand-alone project to meet the objectives listed above.” And a March 6,
    2017 letter from the California Department of Fish and Wildlife to the
    SFCJPA stated: “Each of the Project alternatives is intended to be a stand-
    alone project that could be implemented subsequent to the existing Project to
    provide greater flood protection in the future.” Finally, the EIR itself
    expressly acknowledges that either detention basin alternative “could be
    implemented as a stand-alone project with no downstream improvements, or
    as a complementary project after downstream improvements are made.” In
    short, the record amply supports the conclusion the detention basin
    alternatives were stand-alone projects.
    Joshua also argues that the EIR in this case does not provide an
    “accurate, stable, and finite project description” (County of Inyo v. City of Los
    Angeles (1977) 
    71 Cal.App.3d 185
    , 193), because, as his brief puts it, the EIR
    “analyz[es] options that are components of the current Project, rather than
    alternatives to the Project.” Not so. The EIR provides a 47-page description
    of the project and its impacts, including clearly defining the “[m]ajor
    elements” of the Project as “Replacing Pope-Chaucer Bridge,” “Downstream of
    that bridge, widening the Creek channel and replacing the wooden
    University Avenue Bridge parapet extension,” “Enhancing habitat within the
    project area,” and “Creating new recreational opportunities and connect to
    existing bike and pedestrian corridors.” The project is also clearly defined as
    the channel widening alternative from the first round of alternative selection.
    In short, despite the EIR’s occasional suggestion that the project’s goals could
    13
    be complemented or supplemented by the detention basin alternatives in
    Reach 3, the EIR does not fail to provide an accurate or stable project
    description.
    Tuolumne County Citizens for Responsible Growth, Inc. v. City of
    Sonora (2007) 
    155 Cal.App.4th 1214
    , cited by Joshua, is not to the contrary.
    There, the city planning commission approved the proposed home
    improvement center on the condition that the project proponents also perform
    a road realignment. (Id. at pp. 1219–1220.) The court concluded that
    because the “project cannot be completed and opened legally without the
    completion of the road realignment,” the road realignment and the home
    improvement center were one project for the purposes of CEQA. (Id. at
    pp. 1227–1231; see id. at p. 1229 [“ ‘Courts have considered separate
    activities as one CEQA project and required them to be reviewed together
    where . . . both activities are integral parts of the same project [Citation]’
    [Citation]”].) Such is plainly not the case here, where the project was neither
    legally nor practically conditioned on the detention basin alternatives in
    Reach 3—indeed, the EIR expressly stating the opposite, calling the
    detention basin alternatives “stand-alone” projects.3
    3 For similar reasons, we find unavailing Joshua’s reliance on cases
    holding that “[a] public agency is not permitted to subdivide a single project
    into smaller individual sub-projects in order to avoid the responsibility of
    considering the environmental impact of the project as a whole. ‘The
    requirements of CEQA “cannot be avoided by chopping up proposed projects
    into bite-size pieces which, individually considered, might be found to have no
    significant effect on the environment or to be only ministerial.” [Citation.]’
    (Topanga Beach Renters Assn. v. Department of General Services (1976)
    
    58 Cal.App.3d 188
    , 195–196.)” (Orinda Assn v. Bd. of Supervisors (1986)
    
    182 Cal.App.3d 1145
    , 1171.) Such is not the case here, where the project was
    clearly defined and the detention basin alternatives expressly acknowledged
    to be stand-alone projects.
    14
    Joshua Has Failed to Exhaust Administrative Remedies With
    Respect to His Argument Regarding the Floodwalls Alternative
    Joshua’s next argument is that the floodwalls alternative is “invalid”
    because it does not lessen the environmental impact of the project—instead,
    the EIR concluded that “[t]he Floodwalls Alternative would have impacts
    similar to the proposed project but over a much greater area along and at the
    top of the creek banks. Therefore, this alternative would have greater
    impacts overall than the proposed project.”
    Joshua has failed to demonstrate that he exhausted his administrative
    remedies with respect to this argument.
    “ ‘In brief, the rule [of the exhaustion of administrative remedies] is
    that where an administrative remedy is provided by statute, relief must be
    sought from the administrative body and this remedy exhausted before the
    courts will act.’ [Citation.] The rule is a jurisdictional prerequisite in the
    sense that it ‘is not a matter of judicial discretion, but is a fundamental rule
    of procedure laid down by courts of last resort, followed under the doctrine of
    stare decisis, and binding upon all courts.’ [Citations.]” (Citizens for Open
    Government v. City of Lodi (2006) 
    144 Cal.App.4th 865
    , 874, quoting
    Abelleira v. District Court of Appeal (1941) 
    17 Cal.2d 280
    , 292.)
    Section 21177 addresses the exhaustion of remedies in CEQA cases. It
    provides that no action or proceeding may be brought alleging non-
    compliance with CEQA unless (1) the alleged grounds for noncompliance
    “were presented to the public agency orally or in writing by any person
    during the public comment period provided by this division or before the close
    15
    of the public hearing on the project before the issuance of the notice of
    determination” and (2) the person bringing the action “objected to the
    approval of the project orally or in writing during the public comment period
    provided by this division or before the close of the public hearing on the
    project before the filing of notice of determination.” (§ 21177, subds. (a), (b).)
    “The rationale for the rule is that an agency is entitled to learn the
    contentions of interested parties before litigation arises, so it will have an
    opportunity to address the contentions and perhaps render litigation
    unnecessary. (Mani Brothers Real Estate Group v. City of Los Angeles (2007)
    
    153 Cal.App.4th 1385
    , 1394.) To advance this purpose an interested party
    must present the exact issue to the administrative agency that is later
    asserted during litigation or on appeal. (Ibid.) General objections,
    generalized references or unelaborated comments will not suffice. (Porterville
    Citizens for Responsible Hillside Development v. City of Porterville (2007)
    
    157 Cal.App.4th 885
    , 910.) ‘ “[T]he objections must be sufficiently specific so
    that the agency has the opportunity to evaluate and respond to them.”
    [Citation.]’ (Id. at p. 909.)” (Hagopian v. State of California (2014)
    
    223 Cal.App.4th 349
    , 371.)
    The petitioner bears the burden of demonstrating exhaustion of
    administrative remedies. (Evans v. City of San Jose (2005) 
    128 Cal.App.4th 1123
    , 1136.) And we employ a de novo standard of review when determining
    whether the exhaustion of administrative remedies doctrine applies. (Ibid.)
    Joshua’s only argument that he exhausted his administrative remedies
    with respect to his challenge to the floodwalls alternative is that it is
    somehow encompassed within his argument the EIR did not include the
    required “range of reasonable alternatives.” (See Guidelines, § 15126.6 (a).)
    His reply brief goes on to make reference to places in the record where he
    16
    made his argument, rejected above, that the Reach 2 and Reach 3
    alternatives were “intertwined.” But he nowhere identifies in the record any
    challenge to the floodwalls alternative, never mind the specific challenge he
    now raises. Instead, as noted, he points to general comments that the “Reach
    2 and Reach 3 projects are intertwined,” a comment by the Regional Board
    that the “DEIR should be revised to include . . . more robust description of the
    [SFC]JPA’s analysis of potentially feasible alternatives,” and an assertion
    that the California Department of Fish and Wildlife “offered comment on the
    alternatives, including the Floodwalls Alternative.” Obviously, these general
    comments did not “present the exact issue to the administrative agency” and
    were not “sufficiently specific so that the agency has the opportunity to
    evaluate and respond to them.” (Hagopian v. State of California, supra, 223
    Cal.App.4th at p. 371.) Joshua has failed to carry his burden to demonstrate
    that he exhausted his administrative remedies with respect to his challenge
    to the floodwalls alternative.
    The EIR Considered Alternatives Other Than the No Project
    Alternative
    Joshua’s next argument—an argument that occupies only two
    paragraphs in his opening brief—is that since the detention basin
    alternatives and the floodwalls alternative were not “valid,” the No Project
    alternative is the “only true alternative remaining,” and thus the EIR failed
    to consider a reasonable range of alternatives. Because we have rejected
    Joshua’s argument that the detention basin alternatives were invalid, this
    argument necessarily fails as well.4
    4 In addition, as the SFCJPA observes, an EIR that considers only the
    no project alternative does not necessarily fail to consider a reasonable range
    of alternatives. (See Save Our Access-San Gabriel Mountains v. Watershed
    17
    The SFCJPA Did Not Abuse Its Discretion In Adopting the
    Statement of Overriding Considerations
    Joshua’s final argument is that the SFCJPA abused its discretion in
    adopting the statement of overriding considerations without first making the
    requisite findings that the alternatives were “infeasible.” By no means.
    “ ‘An agency may not approve a project that will have significant
    environmental effects if there are feasible alternatives or feasible mitigation
    measures that would substantially lessen those effects. (§§ 21002, 21002.1,
    subd. (b); Guidelines, § 15021, subd. (a)(2); Mountain Lion Foundation v. Fish
    & Game Com. (1997) 
    16 Cal.4th 105
    , 134.) An agency may find, however,
    that particular economic, social, or other considerations make the
    alternatives and mitigation measures infeasible and that particular project
    benefits outweigh the adverse environmental effects. (§ 21081, subds. (a)(3),
    (b); Guidelines, § 15091, subd. (a)(3).) Specifically, an agency cannot approve
    a project that will have significant environmental effects unless it finds as to
    each significant effect, based on substantial evidence in the administrative
    record, that (1) mitigation measures required in or incorporated into the
    project will avoid or substantially lessen the significant effect; (2) those
    measures are within the jurisdiction of another public agency and have been
    Conservation Authority (2021) 
    68 Cal.App.5th 8
    , 31 [“Plaintiff contends
    CEQA, the Guidelines, and Supreme Court case law require an EIR to
    analyze more than the ‘no project’ alternative. That is not correct”]; San
    Franciscans for Liveable Neighborhoods v. City and County of San Francisco
    (2018) 
    26 Cal.App.5th 596
    , 633 [“ To the extent SFLN would have us
    conclude, as a matter of law, that consideration in the EIR only of a proposed
    project and a no project alternative is inadequate, we reject that contention”];
    Mount Shasta Bioregional Ecology Center v. County of Siskiyou (2012) 
    210 Cal.App.4th 184
    , 196–199.) Joshua does not offer any response to these
    cases, except to assert that they are “factually distinct,” without explaining
    how.
    18
    adopted, or can and should be adopted, by that agency; or (3) specific
    economic, legal, social, technological, or other considerations make the
    mitigation measures or alternatives identified in the EIR infeasible, and
    specific overriding economic, legal, social, technological, or other benefits
    outweigh the significant environmental effects. (§§ 21081, 21081.5;
    Guidelines, § 15091, subds. (a), (b).) A finding that specific overriding project
    benefits outweigh the significant environmental effects (§ 21091, subd. (b)) is
    known as a statement of overriding considerations. (Guidelines, § 15093.)’ ”
    (Tiburon Open Space, supra, 78 Cal.App.5th at pp. 725–726.)
    The EIR concluded that, even with mitigation measures, the
    “[c]onstruction activities proposed as part of the project would temporarily
    increase emissions in pollutants of concern,” and “the impact of the project’s
    construction activities on cumulative air quality impacts is expected to be
    significant and unavoidable.” “Primarily due to their more remote locations,
    both the Former Nursery Detention Basin Alternative and the Webb Ranch
    Detention Basin Alternative are estimated at this time to have fewer/less
    potential impacts on the following resources than the proposed project: []
    Aesthetics [] Air Quality [] Hazardous Materials and Public Health [] Noise
    and Vibration [] Recreation [] Transportation and Traffic
    [and] Utilities and Service Systems.”
    However, the EIR went on:
    “Between the Former Nursery Detention Basin Alternative and Webb
    Ranch Detention Basin Alternative, the Former Nursery Detention Basin
    Alternative would result in fewer impacts because the nearest noise-sensitive
    land uses to this alternative are 400 feet away. The Webb Ranch Detention
    Basin Alternative is within 35 feet of the nearest sensitive land uses;
    therefore construction of this alternative is expected to expose persons to
    19
    greater noise and vibration impacts relative to the Former Nursery Detention
    Basin Alternative.
    “The Former Nursery Detention Basin Alternative in consideration of
    basin sizing could not provide as much flood protection, as quickly, or provide
    similar benefits to aquatic species (e.g., salmonid habitat), as the proposed
    project. However, information available to date indicates that the Former
    Nursery Detention Basin Alternative would have less environmental impacts
    than the proposed project on many resources. For these reasons, the Former
    Nursery Detention Basin Alternative is identified as the environmentally
    superior alternative. However, by itself, this alternative cannot achieve the
    benefits of the proposed project in terms of the level of flood control that could
    be achieved (one basin could achieve a peak flow reduction of 800–1,000 cfs
    versus the proposed project, which could achieve a reduction of 1,800 cfs).
    Further, this alternative would not achieve the same level of benefit as the
    proposed project in terms of habitat enhancement. These benefits include
    improvement of hydrologic functions through channel widening and
    construction of habitat enhancement features. For these reasons, the Former
    Nursery Detention Basin Alternative was not selected.”
    Joshua’s complaint with the EIR is essentially that it did not expressly
    state that the detention basin alternatives were “infeasible”—indeed, his
    reply brief styles his argument as “SFCJPA Cannot Point to Any Language in
    the Statement of Overriding Considerations Showing That the Board of
    Directors Made a Finding of Infeasibility Regarding Project Alternatives.”
    But although the EIR did not use the word “infeasible,” it makes clear that
    the SFCJPA rejected the detention basin alternatives because they “cannot
    achieve the benefits of the proposed project in terms of the level of flood
    control,” and “would not achieve the same level of benefit as the proposed
    20
    project in terms of habitat enhancement.” In other words, the SFCJPA found
    the detention basin alternatives infeasible for “policy reasons,” including that
    the alternatives would not achieve the desired project objectives. This was a
    proper basis for a finding of infeasibility under CEQA. (See California Native
    Plant Society v. City of Santa Cruz (2009) 
    177 Cal.App.4th 957
    , 1000–1002
    [no abuse of discretion in finding alternatives were infeasible because “they
    failed to achieve what the Council regarded as primary objectives of the
    [project]”]; San Diego Citizenry Group v. County of San Diego (2013) 
    219 Cal.App.4th 1
    , 18 [county properly determined within its discretion that
    alternatives were infeasible because “none would achieve the core objectives
    to the same extent as the Project”].) And Joshua’s disagreement with this
    decision amounts to a policy disagreement with the SFJCPA—a
    disagreement that does not demonstrate an abuse of discretion. (See
    California Native Plant Society v. City of Santa Cruz, supra, 177 Cal.App.4th
    at p. 1001 [appellants’ challenge to infeasibility determination “represents
    nothing more than a ‘policy disagreement with the City’ ”]; San Diego
    Citizenry Group v. County of San Diego, supra, 219 Cal.App.4th at p. 18
    [plaintiff’s “disagreement with the [agency]’s policy determination is not a
    basis for setting aside the [EIR]”.)
    Joshua’s reliance on City of Marina v. Board of Trustees of California
    State University (2006) 
    39 Cal.4th 341
     is unavailing. There, the defendant
    trustees sought to expand a small college campus into a larger institution on
    a former Army base, and prepared an EIR that found in relevant part that
    contributions to the Ford Ord Reuse Authority could mitigate certain of the
    project’s environmental impacts, but that such contributions would amount
    to an assessment prohibited by the state Constitution and constitute a gift of
    public funds and thus be unlawful, such that mitigating the effects through
    21
    contributions was “infeasible” for “legal” reasons. (Id. at 351–353.) Our
    Supreme Court considered the legal question of whether the contributions
    were unlawful under de novo standard of review, concluding that they were
    not and that the trustees had therefore abused their discretion. (Id. at
    p. 355.) In so doing, the court expressly noted that the case involved a purely
    legal question, and not “factual and environmental conclusions in the EIR
    based on conflicting evidence” to which the court would owe “much deference”
    under the abuse of discretion standard of review. (Ibid.) By contrast, in this
    case, the SFCJPA’s finding that the detention basin alternatives were
    infeasible is a “factual and environmental conclusions in the EIR based on
    conflicting evidence,” and we find no abuse of discretion.
    DISPOSITION
    The judgment is affirmed.
    22
    _________________________
    Richman, Acting P. J.
    We concur:
    _________________________
    Miller, J.
    _________________________
    Mayfield, J. *
    Joshua v. San Francisquito Creek Joint Powers Authority (A163294)
    *Superior Court of Mendocino County, Judge Cindee Mayfield, sitting as
    assigned by the Chief Justice pursuant to article VI, section 6 of the California
    Constitution.
    23
    

Document Info

Docket Number: A163294

Filed Date: 8/23/2022

Precedential Status: Non-Precedential

Modified Date: 8/23/2022