Bay Cities Paving & Grading v. City of San Leandro CA1/2 , 167 Cal. Rptr. 3d 733 ( 2014 )


Menu:
  • Filed 1/28/14 Bay Cities Paving & Grading v. City of San Leandro CA1/2
    NOT TO BE PUBLISHED IN OFFICIAL REPORTS
    California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
    publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication
    or ordered published for purposes of rule 8.1115.
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    FIRST APPELLATE DISTRICT
    DIVISION TWO
    BAY CITIES PAVING & GRADING,
    INC.,
    Plaintiff and Appellant,                                    A137971
    v.                                                                   (Alameda County
    CITY OF SAN LEANDRO,                                                 Super. Ct. No. RG12657020)
    Defendant and Respondent,
    OLIVER DESILVA, INC.,
    Real Party in Interest, and
    Respondent.
    I. INTRODUCTION
    Appellant Bay Cities Paving & Grading, Inc. (hereafter appellant or Bay Cities)
    appeals from an order and judgment denying its petition for a writ of mandate. Pursuant
    to that petition, Bay Cities challenged the action of the City of San Leandro (hereafter
    City) in awarding a public works contract to a competing contractor, real party in interest
    and respondent Oliver DeSilva, Inc., dba Gallagher & Burk (hereafter G&B), the lowest
    bidder on the project. Bay Cities, the second lowest bidder, alleged that the City could
    not properly award the contract to G&B because a missing page in G&B’s bid was a
    material deviation from the contract specifications. We reject this contention and
    therefore affirm the judgment.
    1
    II. FACTUAL AND PROCEDURAL BACKGROUND
    On September 4, 2012,1 the City approved plans and specifications for the
    construction of a “BART-Downtown Pedestrian Interface Project along San Leandro
    Boulevard” and called for bids on that project. Prospective bidders were notified of the
    project requirements which included submitting a proposal, and using a standard form
    provided by the City, along with a bid deposit securing the bidder’s proposal. This
    security could be in the form of cash, a cashier’s or certified check or a bidder’s bond
    executed by an authorized surety company.
    The City provided prospective bidders with a “Contract Book” for the project
    which contained, among other things, copies of the required proposal form and of the
    City’s standard form of bid bond. (JA 141) The proposal form stated that the
    “completed proposal form shall be submitted in its entirety,” and “shall be accompanied
    by a bidder’s bond executed by an admitted surety insurer, naming the City of San
    Leandro as beneficiary. . . . [¶] . . . The form of Bidder’s Bond to be used [is] included
    with the proposal form.”2
    On October 23, the City opened the bids it had received for this project. All of the
    bidders submitted bid bonds as security for their bids. The lowest bid on the contract was
    submitted by G&B in the amount of $4,846,700. Bay Cities submitted the second lowest
    bid in the amount of $5,359,725, i.e., over $500,000 more than the G&B bid.
    However, the bid package that G&B had submitted was missing page 33, which
    was the first page of its bid bond. G&B’s bid package did include the second page of the
    bond (page 34 of the entire bid), which contained the signatures of both the surety’s
    attorney-in-fact and G&B’s president, as well as notary certificates for both signatures.
    1
    Unless otherwise noted, all further dates are in 2012.
    2
    The “Specifications” section of the contract book also included the following
    provision: “The bidder’s bond shall conform to the bond form in the Bid book for the
    project and shall be properly filled out and executed. The bidder’s bond form included in
    that book may be used.”
    2
    On October 23, G&B submitted the first page of its bid bond to the City, albeit after the
    sealed bids had been opened.
    On October 26, Bay Cities filed a bid protest with the City; it argued that G&B’s
    bid was “nonresponsive and must be rejected” because of the omitted page of G&B’s bid
    bond. On October 30, G&B’s attorney wrote the City, stating that his client’s initial
    failure to include the first page of the two-page bid bond “was due to an inadvertent
    error,” and continued by noting that the City “may waive this irregularity and award the
    contract to G&B” because “the irregularity is minor and waivable by the City . . . .” That
    letter continued by citing legal authorities G&B’s counsel contended supported that
    position.
    In an October 31 letter, City engineer Mark Goralka acknowledged receipt of Bay
    Cities’ bid protest but notified it that the City had determined that G&B’s bid was
    accompanied by an enforceable bond and that the omission of the cover page of the two-
    page bid bond “can be waived as an inconsequential bid defect.” Goralka also advised
    that the City would proceed with awarding the contract to G&B.
    On November 19, the City received a letter from G&B’s bid bond surety,
    Travelers Casualty and Surety Company, confirming that the bid bond it had issued in
    connection with the project “was approved and authorized by” it, and that the omission of
    the first page of the bond from G&B’s bid package “did not affect our commitment under
    the bid bond.”
    That same day, the City Council of San Leandro unanimously adopted a resolution
    which identified G&B’s bid as the lowest responsible bid for the project, rejected all
    other proposals or bids, waived “any irregularities in the proposal or bid of” G&B, and
    awarded the contract for the project “to the lowest responsible bidder therefore, to wit,
    [G&B] . . . .” The November 19 resolution also established that if G&B was unable to
    execute the contract for this project, the City Manager was authorized to award the
    project to the next lowest responsible bidder and to “take all actions necessary to recover
    any bid security from the low bidder necessary to make the City whole in its acceptance
    of the lowest bid.”
    3
    The following day, November 20, appellant filed a petition for a writ of mandate
    and a complaint in the Alameda County Superior Court. It also filed an Ex Parte
    Application for a Temporary Restraining Order contesting the City’s award of the
    contract to G&B. The trial court conducted a hearing on that application on November
    26; two days later it denied appellant’s request for a temporary restraining order.
    On January 16, 2013, that court held a hearing on appellant’s petition for a writ of
    mandate and, a week later, denied it. In its January 23, 2013, order, the trial court stated:
    “The City of San Leandro put out a project to bid and all prospective bidders were
    required to submit a bid bond with their bids. The City provided all prospective bidders
    with a form Bid Bond. Gallagher & Burk submitted a bid that failed to include page 33
    (the terms of the form bid bond) but included page 34 (the signature page for the bid
    bond). The City staff concluded that the bid bond was enforceable (Letter of 10/31/12)
    and the City Council formally waived the irregularity and accepted the bid (Resolution
    dated 11/19/12.) [¶] The court finds substantial evidence to support the City’s decision
    that Gallagher & Burk’s failure to submit page 33 with its bid package was a ‘minor
    irregularity’ not affecting the amount of the bid that did not give Gallagher & Burk an
    advantage or benefit not allowed to other bidders. (Notice to Bidders, para 10, 27.) The
    bid bond was a form document so that it was apparent that the signature page 34 referred
    to the prior text [on] page 33. In addition the signature page independently identified the
    project at issue. The City reasonably concluded that a court would read page 34 in the
    context of the form bid bond and enforce the bid bond. (Civil Code 1647.)”
    On January 23, 2013, the trial court filed a judgment denying Bay City’s petition
    for writ of mandate. On February 21, 2013, appellant filed a timely notice of appeal.
    III. DISCUSSION
    A.     Standard of Review
    “Appellate review of the award of a public contract is governed by certain well-
    established principles. In a mandamus action arising under Code of Civil Procedure
    section 1085, we limit our review to an examination of the proceedings before the agency
    to determine whether its findings and actions are supported by substantial evidence.
    4
    [Citations.] ‘Our review is limited to an examination of the proceedings to determine
    whether the City’s actions were arbitrary, capricious, entirely lacking in evidentiary
    support or inconsistent with proper procedure. There is a presumption that the City’s
    actions were supported by substantial evidence, and [petitioner/plaintiff] has the burden
    of proving otherwise. We may not reweigh the evidence and must view it in the light
    most favorable to the City’s actions, indulging all reasonable inferences in support of
    those actions. [Citations.] Mandamus is an appropriate remedy to compel the exercise of
    discretion by a government agency, but does not lie to control the exercise of discretion
    unless under the facts, discretion can only be exercised in one way. [Citations.]’
    [Citation.]” (MCM Construction, Inc. v. City and County of San Francisco (1998) 
    66 Cal. App. 4th 359
    , 368 (MCM); see also Ghilotti Construction Co. v. City of Richmond
    (1996) 
    45 Cal. App. 4th 897
    , 900 (Ghilotti).)
    In its briefs to us, appellant argues that the standard of review in this case is
    primarily the “independent judgment” test. To the extent our disposition of this appeal
    requires us to decide questions of statutory interpretation or to determine whether the
    City’s action violated a relevant law, we exercise our independent judgment. (Schram
    Construction, Inc. v. Regents of the University of California (2010) 
    187 Cal. App. 4th 1040
    , 1052; see also Associated Builders and Contractors, Inc. v. San Francisco Airports
    Comm. (1999) 
    21 Cal. 4th 352
    , 361; Valley Crest Landscape, Inc. v. City Council (1996)
    
    41 Cal. App. 4th 1432
    , 1437 (Valley Crest).) However, as we will explain, the dispositive
    issue in this case is a factual one which we review under the substantial evidence
    standard.
    B.     Legal Principles
    “ ‘Generally, cities, as well as other public entities, are required to put significant
    contracts out for competitive bidding and to award the contract to the lowest responsible
    bidder. [Citation.] A bidder is responsible if it can perform the contract as promised.
    [Citation.] A bid is responsive if it promises to do what the bidding instructions require.
    [Citation.]’ ” 
    (MCM, supra
    , 66 Cal.App.4th at p. 368.)
    5
    “ ‘A basic rule of competitive bidding is that bids must conform to specifications,
    and that if a bid does not so conform, it may not be accepted. [Citations.] However, it is
    further well established that a bid which substantially conforms to a call for bids may,
    though it is not strictly responsive, be accepted if the variance cannot have affected the
    amount of the bid or given a bidder an advantage or benefit not allowed other bidders or,
    in other words, if the variance is inconsequential. [Citations.]’ [Citations.]” 
    (Ghilotti, supra
    , 45 Cal.App.4th at p. 904.)
    “ ‘The importance of maintaining integrity in government and the ease with which
    policy goals underlying the requirement for open competitive bidding may be
    surreptitiously undercut, mandate strict compliance with bidding requirements.
    [Citation.]’ [Citation.]” 
    (MCM, supra
    , 66 Cal.App.4th at p. 369.) However, the rule that
    requires “ ‘strict compliance with bidding requirements does not preclude the contracting
    entity from waiving inconsequential deviations.’ [Citation.]” (Ibid.; 
    Ghilotti, supra
    , 45
    Cal.App.4th at p. 908.) Rather “a deviating bid must be set aside despite the absence of
    corruption or actual adverse effect on the bidding process” only if the deviation is
    “capable of facilitating corruption or extravagance, or likely to affect the amount of bids
    or the response of potential bidders. [Citations.]” 
    (Ghilotti, supra
    , 45 Cal.App.4th at p.
    908.)
    In the present case, appellant does not dispute the authority summarized above
    which establishes that the City has the discretion to “waive inconsequential deviations
    from contract specifications in a public contract bid.” 
    (Ghilotti, supra
    , 45 Cal.App.4th at
    p. 900.) Indeed, in this case, the City’s discretion to waive inconsequential or
    nonmaterial defects in the bids submitted for this public contract project was expressly
    confirmed in both the San Leandro Municipal Code and in provisions of the “Notice to
    Bidders” that was issued for this specific project.3
    3
    The San Leandro Municipal Code contains a provision which reads: “AWARD
    TO LOWEST RESPONSIBLE BIDDER. Except as otherwise provided herein, the City
    shall award a contract for a Public Works project to the lowest responsible bidder whose
    bid complies with the specifications. In determining responsibility, the City shall
    6
    However, appellant does contend that the defect in G&B’s bid was material and
    could not be waived. Thus, the question raised by this appeal is whether the City abused
    its discretion by waiving the deviation in the G&B bid as inconsequential. The question
    “ ‘[w]hether in any given case a bid varies substantially or only inconsequentially from
    the call for bids is a question of fact.’ [Citation.]” 
    (Ghilotti, supra
    , 45 Cal.App.4th at p.
    906.) As reflected in the authority summarized above, “[t]o be considered
    inconsequential, a deviation must neither give the bidder an unfair competitive advantage
    nor otherwise defeat the goals of insuring economy and preventing corruption in the
    public contracting process.” (Id. at p. 900.)
    “These considerations must be evaluated from a practical rather than a
    hypothetical standpoint, with reference to the factual circumstances of the case. They
    must also be viewed in light of the public interest, rather than the private interest of a
    disappointed bidder. ‘It certainly would amount to a disservice to the public if a losing
    bidder were to be permitted to comb through the bid proposal or license application of the
    low bidder after the fact, [and] cancel the low bid on minor technicalities, with the hope
    of securing acceptance of his, a higher bid. Such construction would be adverse to the
    best interests of the public and contrary to public policy.’ [Citation.]” 
    (Ghilotti, supra
    , 45
    Cal.App.4th pp. 908-909.)
    consider the known reliability, resources, experience, integrity and the reputation for
    workmanship of the various bidders. The City may waive any informalities or minor
    irregularities in bids received.” (San Leandro Mun. Code, §1-5-225.)
    Furthermore, the “Notice to Bidders” sent out by the City to the prospective
    bidders contained two provisions specifically allowing the City to waive minor
    irregularities. Section 10 of that document read: “CITY’S RIGHT TO REJECT BIDS:
    The right is reserved, as the interest of the City may require, to reject any and all bids, or
    to waive any informality or minor irregularity in the bids.” Section 27, the final
    provision of the “Notice to Bidders,” then concludes with this sentence: “The City
    reserves the right to waive any bid irregularities not affecting the amount of the bid,
    except where such waiver would give the low bidder an advantage or benefit not allowed
    other bidders.”
    7
    C.     Analysis
    The only alleged deviation from competitive bidding requirements that we address
    in this appeal is that one page of G&B’s bid bond was missing from the bid it originally
    submitted in connection with this project. Appellant contends the City exceeded or
    abused its discretion by waiving this bid irregularity.
    Providing a bid security was both a specification of this project as well as a
    requirement imposed by law. (See, e.g., San Leandro Mun. Code, § 1-5-220; Pub.
    Contract Code, §§ 20170, 20171.)4 However, the City determined that the missing page
    of the G&B bond was an inconsequential deviation from the bidding requirements for
    this project because the second page of that two-page bid bond, which was included in
    G&B’s original sealed bid package, provided sufficient information to assure the City
    that G&B had complied with the bid security requirement. Substantial evidence supports
    the City’s determination.
    Substantial evidence establishes that G&B used the City’s standard bid bond form.
    The City provided all prospective bidders with this standard form and the bidders were
    instructed if not required to use that form if they elected to provide a bond as their bid
    security. Furthermore, the bid package that G&B initially submitted contained page two
    of G&B’s two-page bid bond, and the pre-printed text on this form mirrored the bid-bond
    form that the City had generated for this specific project. Among other things, that text
    identified the document as a “Bid Bond” for the “Bart-Downtown Pedestrian Interface”
    project, and it included the City’s project number for the project. From this information,
    the City was able to determine that G&B had used the City’s standard form bid bond.
    4
    “Although provisions for forfeitures in the nature of a penalty are generally not
    favored [citation], ‘the right of municipalities to require guarantee deposits to accompany
    bids, and to forfeit them in the event of the failure or refusal of the successful bidder to
    enter into the contract, has long been upheld.’ [Citation.] Such, ‘provisions requiring a
    deposit accompanying a bid for city contracts, or for forfeiture thereof, are necessary as a
    matter of public policy . . . .’ [Citation.]” (A & A Electric, Inc. v. City of King (1976) 
    54 Cal. App. 3d 457
    , 466.)
    8
    By the same token, the material provided in G&B’s original bid, which included
    the second page of its bid bond, was sufficient to establish that G&B satisfied the bid
    security requirement by actually obtaining the required bid bond from an approved
    surety. The City’s standard bid bond was, as the trial court phrased it, a “form
    document” which required only a few insertions by the specific bidder.5 The first page,
    i.e., the page that was originally missing, contained only three blank places for the
    insertion of additional information: (1) the name of the principal (i.e., the bidder), (2) the
    name of the surety, and (3) the date of the submission of the bid.
    Regarding item (3), there can be no dispute that the City had actual notice of the
    date the G&B bid was submitted.6 The first two items of information were provided on
    the second page of the bid bond, i.e., the page that did accompany the bid of G&B. The
    first open lines on that page required the name of the “principal,” i.e., the bidder, a
    signature, and the “title” of the signing party. The other open lines on that page were for
    the naming of the surety, along with its address, phone and fax numbers, and the name
    and title of the attorney-in-fact signing for that surety. All this information was provided
    on the second page of the bid bond which did, in fact, accompany the G&B bid. All the
    rest of the written material on page one of the two-page bid bond form was standard
    material and thus well-known to the City. In short, when the City determined which
    contractor was the lowest responsible bidder it had before it the information needed to
    make clear that G&B had, indeed, satisfied the requirement of supplying the requisite bid
    bond.
    5
    Several documents filed in the trial court by appellant in support of its petition
    for a writ of mandate specifically confirm that the City required that the “ ‘bidder’s bond
    shall conform to the bond form in the Bid book for the project . . . .’ ”
    6
    Appellant contends that the date on the second page of the G&B bond, October
    10, 2012, was actually the “wrong date.” To support this claim, appellant points out that
    the first page of the bond, which G&B submitted after bid opening, states that G&B
    submitted its bid on October 16, 2012. Contrary to appellant’s suggestion on appeal,
    there was nothing suspicious or wrong about these dates. It appears to us that October 10
    was the date the bond was executed while October 16 was the date the bid was submitted.
    9
    Appellant does not dispute the substantial evidence supporting the City’s
    determination in this case but, instead, attempts to lessen its impact by characterizing the
    issue on appeal as a question of law, subject to de novo judicial review. However we are
    not persuaded by appellant’s various legal theories.
    Appellant’s first theory is that the City’s attempted contract with G&B is null and
    void as a matter of law because G&B’s failure to provide a bidder’s bond violated a
    statutory requirement. (Citing, e.g., Miller v. McKinnon (1942) 
    20 Cal. 2d 83
    , 87-88.)
    Thus, it argues: “Because G&B’s bid did not include the mandatory bid security at bid
    time, G&B’s bid was incomplete and materially non-responsive and, consequently,
    ineligible for award.” Such was so, appellant argues, because “there was an utter lack of
    bid security because there were no terms to which the surety was agreeing to be bound.”
    Appellant reiterates this argument in its reply brief, contending numerous times that there
    was no “valid bid bond” or “no enforceable bid bond” supplied with G&B’s bid.
    Appellant’s legal rule is inapposite, however, because the City found that G&B
    did secure its bid with a bid bond. And, as noted above, that determination is supported
    by substantial evidence. Thus, the record undermines appellant’s premise that G&B
    completely failed to comply with the bid bond requirement.
    Appellant next contends that the question of whether the absence of the face page
    of G&B’s bid bond from its original bid package rendered the bond unenforceable was a
    question of law. To support this argument, appellant relies on authority reflecting the
    general principle of contract law that the interpretation of a contract is a judicial function.
    (Citing, e.g., Parsons v, Bristol Development Co. (1965) 
    62 Cal. 2d 861
    , 865; Civ. Code
    §§ 1635-1661.) However, this principle had no bearing on the specific determination by
    the City which is the subject of this appeal. At that stage in the process, the City was not
    required to interpret any substantive provision in any of the bonds submitted by the
    bidders on this project, but only to determine whether the bidders complied with the bid
    security requirement. Here, substantial evidence supports the City’s finding that G&B
    did substantially comply with that requirement, notwithstanding that a page of
    documentation was missing from its original bid package.
    10
    Changing its tack, appellant contends that the City committed legal error by using
    its standard bid bond form to supply information that was missing from G&B’s bid
    package. As reflected in our factual summary, that standard form was included in the
    City’s bid book for this specific project and was supplied to all of the bidders.
    Nevertheless, appellant contends the City committed legal error by looking at that form
    when it evaluated the bids. According to appellant, the City’s award determination had to
    be based solely and exclusively on information within the four corners of G&B’s original
    bid. However, appellant fails to provide any authority imposing such a strict restriction
    on the City in this context.
    Specifically, appellant erroneously relies on Taylor Bus Service, Inc. v. San Diego
    Bd. Of Education (1987) 
    195 Cal. App. 3d 1331
    (Taylor Bus). That case involved a public
    contract for school bus transportation in a San Diego school district. Appellant was the
    low bidder and was conditionally awarded the contract. However, the district
    subsequently rescinded the conditional award after finding that appellant failed to comply
    with competitive bidding requirements. Thereafter, the trial court denied appellant’s
    petition to compel the district to reverse its decision and award the contract to appellant.
    The Taylor Bus court affirmed the trial court’s denial of the petition.
    The first issue addressed in Taylor 
    Bus, supra
    , 195 Cal.App.3d at page 1341, was
    whether the school district violated appellant’s constitutional right to due process by
    rescinding the conditional award without first conducting a hearing. In concluding that
    no such hearing was required, the court noted, among other things, that a public agency’s
    determination whether a contract bid is responsive is materially less complex than the
    question whether a bidder on a public contract is responsible. In this context, the court
    observed that “[i]n most cases, the determination of nonresponsiveness will not depend
    on outside investigation or information . . . .” (Id. at p. 1342.) The Taylor Bus court also
    stated that, notwithstanding a public agency’s “inherent discretionary power” to disregard
    minor or insubstantial variations from bid specifications, the determination whether a bid
    is responsive “does not have, in most cases, the complex and external nature of a
    determination of nonresponsibility.” (Id. at p. 1342.)
    11
    The Taylor Bus appellant also claimed that, even if it was afforded due process,
    the school district abused its discretion by determining that appellant’s bid was non-
    responsive and rescinding the conditional award of the contract to appellant. (Taylor
    
    Bus, supra
    , 195 Cal.App.3d. at p. 1344.) In addressing this claim, the court applied a
    substantial evidence standard of review, noting that the burden was on the appellant to
    “show there is no substantial evidence whatsoever to support the findings of the District.”
    (Id. at pp. 1340-1341.) Ultimately, the court concluded that the findings of the district
    were supported by substantial evidence and, therefore, it did not abuse its discretion. (Id.
    at pp. 1344-1345.)
    Taylor 
    Bus, supra
    , 
    195 Cal. App. 3d 1331
    , does not support any aspect of
    appellant’s arguments on appeal. First, by noting that the responsiveness of a bid can
    often be determined without “outside investigation,” (id. at p. 1342) the court did not
    hold or in any way imply that a public agency violates the law by using contract materials
    generated for the specific project to evaluate whether a bid is responsive or not. Second,
    although Taylor Bus addressed very different issues, it clearly confirms our conclusion in
    this case that the substantial evidence standard of review applies to appellant’s contention
    that the City abused its discretion by awarding the BART contract to G&B.
    Appellant’s most developed theory on appeal is that the defect in G&B’s bid could
    not properly be waived as an inconsequential or immaterial deviation because it gave
    G&B an advantage or benefit over other bidders. As noted at the outset of our
    discussion, a bid defect cannot be considered inconsequential if it gives the bidder an
    unfair competitive advantage. 
    (Ghilotti, supra
    , 45 Cal.App.4th at p. 900.) Here,
    appellant contends that, as a matter of law, G&B enjoyed such an advantage. To support
    this theory, appellant relies primarily on Valley 
    Crest, supra
    , 
    41 Cal. App. 4th 1432
    .7
    7
    Appellant also relies on federal decisions, including U.S. Court of Claims
    decisions, in support of its position that G&B’s bid was fatally defective. However, there
    is clearly adequate California authority to permit us to decide this case and thus no need
    to consider federal administrative law decisions. (See, e.g., Allegretti & Co. v. County of
    Imperial (2006) 
    138 Cal. App. 4th 1261
    , 1274 and Howard Contracting, Inc. v. G.A.
    MacDonald Construction Co., Inc. (1998) 
    71 Cal. App. 4th 38
    , 52.) As one of our sister
    12
    Valley 
    Crest, supra
    , 
    41 Cal. App. 4th 1432
    , was a mandate proceeding involving a
    “park project” for the city of Davis. Specifications for the project required that the bidder
    perform at least 50 percent of the work itself and that it “set forth the percentage of work
    to be performed by each subcontractor.” (Id. at p. 1435.) However, the low bidder on the
    project, North Bay, submitted a bid which indicated that 83 percent of the work would be
    done by subcontractors. Valley Crest, the second lowest bidder, objected that North
    Bay’s bid was nonresponsive. The city engineer called this point to North Bay’s
    attention, and gave it the opportunity to supplement its bid with additional information,
    noting that if no other information was provided, he would recommend that North Bay’s
    bid be deemed unresponsive and that the contract be awarded to Valley Crest. (Ibid.)
    North Bay responded that the percentages in its bid were not correct and submitted new
    percentages totaling 44.65 percent. After the city awarded the contract to North Bay,
    Valley Crest filed a petition for a writ of mandate to set aside the contract which the trial
    court denied. (Ibid.)
    The Valley Crest court reversed the trial court’s decision, finding that the North
    Bay bid contained a material defect that the city could not properly waive. (Valley 
    Crest, supra
    , 
    41 Cal. App. 4th 1432
    .) The court reasoned that the subcontractor percentage
    requirement, although not a requirement of Public Contact law, was nevertheless a
    material element of the contract specifications for the project. Furthermore, North Bay’s
    bid defect was not a minor variance from that specification; it failed to comply with that
    requirement. This mistake was material, the court found, because it gave North Bay an
    unfair advantage in the bidding process by establishing a ground for North Bay to
    courts recently observed: “Because of its relation to the public treasury and its bearing
    on the public interest, public contracting law has deservedly received considerable
    attention from the courts [of this state].” As that court further observed, “the case law [of
    California] bearing on public contract bidding is remarkably consistent.” (Great West
    Contractors, Inc. v. Irvine Unified School Dist. (2010) 
    187 Cal. App. 4th 1425
    , 1428, fn. 1,
    1447.)
    13
    withdraw its bid without having to forfeit its bond pursuant to the statutory procedure set
    forth in the Public Contract Code.8
    As the court explained, “[m]isstating the correct percentage of work to be done by
    a subcontractor is in the nature of a typographical or arithmetical error. It makes the bid
    materially different and is a mistake in filling out the bid. As such, under Public Contract
    Code section 5103, North Bay could have sought relief by giving the city notice of the
    mistake within five days of the opening of the bid. That North Bay did not seek such
    relief is of no moment. The key point is that such relief was available. Thus, North Bay
    had a benefit not available to the other bidders; it could have backed out. Its mistake,
    therefore, could not be corrected by waiving an ‘irregularity.’” (Valley 
    Crest, supra
    , 41
    Cal.App.4th at p. 1442.)9
    Here, appellant contends that Valley Crest mandates reversal of the judgment
    because it establishes that the City erred as a matter of law. According to appellant, G&B
    had an unfair advantage in the bidding process because the defect in its bid would have
    allowed it to reject the project without incurring liability under its bidder’s bond. This
    claim appears to be based on two distinct factual theories, both of which are erroneous.
    8
    The Public Contract Code establishes a procedure pursuant to which a bidder
    can be relieved of its obligations under a bid because of a mistake. (Pub. Contract Code,
    §§ 5101, et seq.)
    Public Contract Code section 5103 states: “The bidder shall establish to the
    satisfaction of the court that: (a) A mistake was made. [¶] (b) He or she gave the public
    entity written notice within five working days, excluding Saturdays, Sundays, and state
    holidays, after the opening of the bids of the mistake, specifying in the notice in detail
    how the mistake occurred. [¶] (c) The mistake made the bid materially different than he
    or she intended it to be. [¶] (d) The mistake was made in filling out the bid and not due to
    error in judgment or to carelessness in inspecting the site of the work, or in reading the
    plans or specifications.”
    9
    In reaching these conclusions, the Valley Crest court applied a de novo standard
    of review to resolve the parties’ dispute regarding the proper interpretation of the Public
    Contract Code statutes at issue in that case. (Valley 
    Crest, supra
    , 41 Cal.App.4th at p.
    1437.) In contrast to Valley Crest, in this case the City’s determination did not hinge on
    any disputed interpretation of a statute. Thus, we reject appellant’s contention that Valley
    Crest establishes that this trial court applied the wrong standard of review.
    14
    First, appellant argues that the omitted page of G&B’s bid gave G&B the actual
    option of deciding after bid opening whether it wanted to be bound by the bid bond.
    Under this theory, the only reason that the City had recourse against the G&B bond in the
    event G&B rejected the public contract was because it permitted G&B to correct its bid
    after the bid opening by submitting supplemental material, i.e., the first page of its bond.
    As a consequence, appellant contends, G&B’s bid “improperly was supplemented after
    the bid deadline.” To appellant, this allegedly improper supplementation by G&B and
    the City’s acceptance of it proves that G&B had an unfair advantage in the bidding
    process because, after the bids were submitted and opened, G&B could have elected not
    to provide the missing page and thereby avoided liability under its bond.
    However, this argument misstates the basis upon which the City found that it was
    proper to award the contract to G&B. Before that award was made, appellant’s general
    counsel had addressed a letter to the City arguing that G&B’s bid was “materially
    defective.” The City responded not by relying in the slightest on any supplementation
    theory, but by these statements: “The central issue is whether the material submitted at
    bid opening would constitute a legally enforceable bid bond. It is the City’s belief that
    the bid bond information submitted was enforceable, and that the omission of the bid
    bond cover page can be waived as an inconsequential bid defect. The City had the
    signature of the obligor and the bonding company at bid opening, which would make the
    bond enforceable.” (Italics added.)
    Thus, the record undermines appellant’s contention that the City allowed any sort
    of “supplementation” of, or belated addition to, G&B’s bid. Rather, the City determined
    that G&B’s original bid was supported by a valid bid bond. This fact materially
    distinguishes Valley 
    Crest, supra
    , 
    41 Cal. App. 4th 1432
    . As discussed above, in that case,
    North Bay was actually permitted to correct the mistake in its bid before the City
    accepted it. (Id. at pp. 1436-1437.) Nothing comparable to that happened here.
    Appellant’s second theory is that the very act of omitting a page of the bid bond
    from the original bid package gave G&B a competitive advantage over other bidders
    because it created an opportunity for G&B to dispute the validity of its bid bond.
    15
    Appellant reasons that, “while a signature page had been submitted, there were no terms
    included therewith making any surety liability uncertain and ambiguous at best.” Thus,
    appellant concludes, if G&B had refused to accept the contract for this project, it had the
    opportunity to avoid liability under its bond by contesting its validity in light of the fact
    that a page of documentation was missing from the original bid package. This
    opportunity, appellant contends, gave G&B a competitive advantage that other bidders
    did not have.
    The flaw in this logic comes from characterizing any opportunity to dispute the
    validity of a bond as a competitive advantage in the bidding process itself. The idea that
    somebody might attempt to avoid a contractual obligation is not evidence that he has an
    actual competitive advantage. Indeed, any of the bidders for this project could
    conceivably have disavowed its contract with the surety that issued its bidder’s bond by
    arguing that the bond was unenforceable for one reason or another. This speculation
    aside, the City in this case made a factual determination that the omitted page from
    G&B’s original bid package did not create an actual unfair advantage because the
    information that was submitted established compliance with the bid bond requirement.
    Appellant cannot undermine that factual determination by relying solely on speculation.
    Appellant argues that Valley 
    Crest, supra
    , 41 Cal.App.4th at page 1442,
    “instructs” that “what is relevant is whether a bid deviation provides the bidder the
    opportunity to avoid being bound,” regardless whether the bidder attempted or even
    intended to withdraw its bid. Thus, appellant insists that it does not matter whether G&B
    actually secured a bid bond in the first instance or whether that bond was actually
    enforceable because the mere fact that the defect in G&B’s bid gave it an opportunity to
    contest the validity of the bond precluded the City from waiving that defect as a matter of
    law.
    But appellant stretches Valley Crest too far. In that case, the mistake in the North
    Bay bid did not create an opportunity to dispute liability under the bond in the event it
    withdrew its bid; it established an actual concrete ground for doing so under Public
    Contract Code section 5103. Indeed, the Valley Crest court emphasized that “the key
    16
    point is that such relief was available” under that statute. (Valley 
    Crest, supra
    , 41
    Cal.App.4th at p. 1442, emphasis added.) In the present case, by contrast, there is
    nothing in this record to suggest that G&B could have withdrawn its bid and avoided
    liability on its bond by invoking Public Contract Code section 5103. That statute applies
    only when “[a] mistake was made . . . in filling out the bid,” and the mistake “made the
    bid materially different than” the bidder intended. (Pub. Contract Code, § 5103, subds.
    (a), (c), and (d).)
    Appellant concedes that Public Contract Code section 5103, does not apply here.
    However, appellant contends that the fundamental “rule of law” established by Valley
    Crest is not predicated on Section 5103, but rather on the question whether the bid defect
    creates an “opportunity” to withdraw a bid without forfeiting the bidder’s bond. But
    appellant’s ambiguous conception of such an “opportunity” simply is not a principle of
    law. As we have already explained, every bidder has the opportunity to attempt to avoid
    liability under a bid bond by denying its validity. By contrast, an actual competitive
    advantage arises only when a bid defect establishes an actual ground for a successful
    bidder to withdraw its bid without incurring liability under its bond. Conceivably, some
    statute or legal rule other than section 5103 of the Public Contract Code might establish
    that ground, but appellant fails to identify one. Furthermore, and more to the point,
    appellant simply ignores the factual component of this inquiry. Here, the City found that
    the G&B bid defect did not create an unfair competitive advantage because the bid
    documentation that was originally submitted established that the bid security requirement
    was satisfied. Valley Crest does not alter our conclusion that appellant cannot use
    speculation to undermine the City’s finding.
    
    Ghilotti, supra
    , 
    45 Cal. App. 4th 897
    , helps to illustrate our point. That case
    involved competing bids on a road construction project in the city of Richmond. The
    contract specifications included a provision that the contractor would itself perform
    “ ‘contract work amounting to not less than 50 percent of the original total contract
    price.’ ” However, the lowest bid, by a company called GBCI, showed that “it would be
    subcontracting 55.44 percent of the total contract price.” (Id. at pp. 900-901.) After a
    17
    protest by the second lowest bidder, the city decided to “waive the 50% requirement as
    ‘nonsubstantive and inconsequential’ ” and awarded the contract to GBCI. (Id. at p. 902.)
    Thereafter, the trial court issued an order denying a petition for writ of mandate to
    prevent the city from awarding the contract to GBCI, which the Ghilotti court affirmed.
    (Id. at p. 903.)
    The Ghilotti court emphasized the factual and individualized nature of the inquiry
    as to whether a bid variation results in an unfair competitive advantage in the bidding
    process, and ultimately concluded that the appellant had failed to carry its burden on
    appeal of proving that GBCI had an actual unfair competitive advantage. 
    (Ghilotti, supra
    , 45 Cal.App.4th at pp. 906-907.) In reaching its decision, the court rejected the
    contention that a bid defect which only potentially impacts the amount of the bid or the
    bidding process was sufficient to establish a competitive advantage that would prevent
    the city from finding that a bid deviation was inconsequential. (Id. at pp. 905-908.)
    The Ghilotti court also acknowledged that a bid defect cannot be waived if it
    would allow the bidder to withdraw his bid without forfeiting its bid bond, but it found
    that the appellant in that case had not relied on this theory in the trial court. 
    (Ghilotti, supra
    , 45 Cal.App.4th at p. 912.) In any event, the Ghilotti court rejected the contention
    that “Valley Crest stands for the proposition that a potential competitive advantage
    precludes waiver of a bid irregularity, without the necessity of showing any actual
    advantage.” (Ghilotti at p. 912, fn. 6.) Rather, the reason that the Valley Crest court
    found that the bid deviation in that case gave North Bay a competitive advantage was
    because North Bay could have obtained relief under the Public Contract Code “as a
    matter of law,” and also because the city in that case expressly gave North Bay the
    opportunity to withdraw its bid. (Ghilotti at p. 912, fn. 6.)
    Ghilotti reinforces our conclusion, and the conclusion of the trial court, that
    appellant has failed to carry its burden of proving that the City abused its discretion by
    awarding the BART contract to G&B. The City’s determination that the omitted page of
    the G&B bid was an inconsequential deviation from the competitive bidding
    requirements was a factual conclusion supported by substantial evidence. Furthermore,
    18
    appellant’s abstract theory of a potential competitive advantage does not undermine the
    City’s determination or otherwise prove that the City abused its discretion.
    A unifying theme running throughout appellant’s arguments on appeal is that we
    must disregard the substantial evidence supporting the City’s determination that the G&B
    bid deviation was inconsequential because that deviation was material as a matter of law.
    However in making these arguments, appellant repeatedly confuses a rule of law with an
    issue of law. For example, appellant contends that both Ghilotti and Valley Crest
    recognize “the well-established rule of law that a bidder has an unfair advantage over
    others if it has an opportunity to avoid its bid without penalty.” By the same token,
    however, this authority vividly illustrates that the facts of a given case dictate whether
    this legal rule applies; in Valley Crest, the evidence established that the bidder had the
    option of withdrawing its bid without penalty, while the evidence in Ghilotti did not
    compel that same factual conclusion.
    Finally, appellant mistakenly relies on this court’s decision in 
    MCM, supra
    , 
    66 Cal. App. 4th 359
    . That case involved a public contract for a construction project at the
    San Francisco Airport. The city rejected as nonresponsive a bid submitted by MCM and
    awarded the contract to a company that had submitted a higher bid. (Id. at p. 366.)
    MCM filed a petition for a writ of mandate arguing, among other things, that the city
    abused its discretion by refusing to waive allegedly immaterial defects in its bid. (Ibid.)
    The trial court denied the writ petition and this court affirmed.
    In our MCM decision, we provided two independent reasons for concluding that
    the city did not abuse its discretion by refusing to waive defects in the MCM bid. 
    (MCM, supra
    , 66 Cal.App.4th at p. 373.) First, even if the deviations in that bid were immaterial,
    the city was not required to exercise its discretion by waiving those defects. As we
    explained, “[a]n agency has discretion to waive immaterial deviations from bid
    specifications and may accept the bid under certain conditions. The point of discretion is
    that the agency may properly act in either direction. It may waive or refuse to waive such
    deviations.” (Id. at p. 374.)
    19
    The second independent reason that the city was not required to waive the defects
    in the MCM bid was that the city’s factual determination that those deviations were
    material was supported by substantial evidence. 
    (MCM, supra
    , 66 Cal.App.4th at pp.
    374-375.) The city had found that the defects in MCM’s bid afforded MCM an actual
    competitive advantage by allowing it to withdraw its bid without having to forfeit its bid
    bond. (Id. at pp. 375-376.) Evidence in the record supporting that conclusion showed
    that “MCM had not only an actual opportunity to withdraw its bid, but also was entitled
    to do so under the provisions of Public Contact Code section 5103.” (Id. at pp. 376.) In
    light of this evidence, we affirmed the city’s determination that MCM had a competitive
    advantage not available to other bidders which established that the “City was without
    power to waive the deviation.” (Id. at p. 377.)
    Appellant purports to find support in our opinion in MCM, noting that we said
    there that “[t]he City was without power to waive the deviation.” 
    (MCM, supra
    , 66
    Cal.App.4th at p. 377.) However, we reached that conclusion only after affirming the
    city’s factual determination that the bid defect in that case was material and not
    inconsequential. Indeed, we cited 
    Ghilotti, supra
    45 Cal.App.4th at page 906, for the
    proposition that the question whether “ ‘ “a bid varies substantially or only
    inconsequentially from the call for bids is a question of fact.” [Citation.]’ ” 
    (MCM, supra
    , 66 Cal.App.4th at p. 375.) Here, we apply precisely the same rules that we applied
    in MCM, albeit to a very different set of facts.
    For all of these reasons, we conclude that appellant has failed to establish that the
    City abused its discretion by waiving the deviation in G&B’s bid as inconsequential.
    IV. DISPOSITION
    The judgment and order of the superior court denying appellant’s petition for a
    writ of mandate are affirmed.
    20
    _________________________
    Haerle, J.
    We concur:
    _________________________
    Kline, P.J.
    _________________________
    Brick, J.*
    Judge of the Alameda County Superior Court, assigned by the Chief Justice pursuant to
    article VI, section 6 of the California Constitution.
    21
    

Document Info

Docket Number: A137971

Citation Numbers: 223 Cal. App. 4th 1181, 167 Cal. Rptr. 3d 733, 2014 WL 559565, 2014 Cal. App. LEXIS 140

Judges: Haerle

Filed Date: 1/28/2014

Precedential Status: Non-Precedential

Modified Date: 11/3/2024