Webcor Construction L.People v. Lendlease (US) Construction, Inc. CA2/4 ( 2020 )


Menu:
  • Filed 12/17/20 Webcor Construction L.P. v. Lendlease (US) Construction, Inc. CA2/4
    NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS
    California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not
    certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been
    certified for publication or ordered published for purposes of rule 8.1115.
    IN THE COURT OF APPEAL OF THE STATE OF
    CALIFORNIA
    SECOND APPELLATE DISTRICT
    DIVISION FOUR
    WEBCOR CONSTRUCTION L.P.,                                                 B299310
    (Los Angeles County
    Plaintiff and Respondent,                                       Super. Ct. No. 19STCV03357)
    v.
    LENDLEASE (US)
    CONSTRUCTION, INC., et al.,
    Defendants and Appellants.
    APPEAL from orders of the Superior Court of Los
    Angeles County, Richard E. Rico, Judge. Affirmed.
    Alston & Bird, John D. Hanover, J. Andrew Howard,
    and Joseph S. Sestay for Defendant and Appellant Lendlease
    (US) Construction, Inc.
    Ralls Gruber & Niece and John Foust; Ken W. Choi
    and Daniel A. Cantor for Defendant and Appellant
    Oceanwide Plaza LLC.
    Gordon Rees Scully Mansukhani, Sandy Kaplan,
    Matthew Peng, and Don Willenburg; Rutan & Tucker,
    William T. Eliopoulos, Heather N. Herd, and Carrie
    MacIntosh for Plaintiff and Respondent Webcor
    Construction L.P.
    __________________________________________
    INTRODUCTION
    Appellant Oceanwide Plaza LLC (Oceanwide) hired
    appellant Lendlease (US) Construction, Inc. (Lendlease) to
    serve as the general contractor on Oceanwide’s development
    project. Although the parties had not yet executed a prime
    contract, Oceanwide gave Lendlease the go-ahead to begin
    work on the project. At the time, the parties had negotiated
    a draft agreement (Negotiated Draft), which included an
    arbitration provision. Lendlease then hired respondent
    Webcor Construction L.P. (Webcor) as a subcontractor, and
    the two executed a subcontract that purported to incorporate
    the prime contract’s arbitration agreement in disputes
    between Webcor and Lendlease that involved Oceanwide’s
    “correlative rights and duties.” Lendlease and Oceanwide
    later executed a prime contract, which included the same
    arbitration provision contained in the Negotiated Draft.
    2
    The project apparently did not go as planned, and
    Webcor filed this action against Lendlease, Oceanwide, and
    others, asserting various causes of action.1 Lendlease and
    Oceanwide separately moved to compel arbitration under the
    subcontract, claiming it incorporated the prime contract’s
    arbitration provision. Oceanwide contended it was entitled
    to enforce the subcontract as a third-party beneficiary.
    Webcor opposed appellants’ motions. It argued the
    subcontract incorporated no arbitration provision because
    the prime contract had not been executed when the
    subcontract was signed and because, according to Webcor,
    the subcontract did not reference the Negotiated Draft.
    Webcor also maintained that Oceanwide had no standing to
    enforce any arbitration agreement in the subcontract. The
    trial court denied the motions. The court did not decide
    whether the subcontract included a valid arbitration
    agreement, but instead concluded that most of Webcor’s
    claims did not involve Oceanwide’s correlative rights and
    duties. As to the one claim that the court found did involve
    Oceanwide’s correlative rights and duties, the court refused
    to compel arbitration because of the risk of conflicting
    rulings in different forums.
    On appeal, Lendlease and Oceanwide contend: (1) the
    subcontract incorporated an arbitration agreement; (2)
    Oceanwide was entitled to enforce the arbitration agreement
    1     The other defendants are not pertinent to the resolution of
    this appeal.
    3
    as a third-party beneficiary; (3) under the arbitration
    agreement, whether Webcor’s claims involved Oceanwide’s
    correlative rights and duties was a question for the
    arbitrator; and (4) alternatively, Webcor’s claims did involve
    Oceanwide’s correlative rights and duties.
    While we agree that the subcontract incorporated an
    arbitration agreement, we conclude that this agreement was
    not intended to benefit Oceanwide, and therefore that
    Oceanwide had no standing to enforce it. As to Webcor’s
    claims against Lendlease, the trial court had discretion to
    refuse to compel arbitration to avoid the risk of conflicting
    rulings. Accordingly, we affirm.
    BACKGROUND
    A. The Project, the Limited Notice to Proceed, and the
    Negotiated Draft
    Oceanwide, the owner and developer of a large,
    mixed-use development project in downtown Los Angeles,
    hired Lendlease to serve as the project’s general contractor.
    Lendlease, in turn, hired Webcor as a concrete subcontractor
    to perform all installations of reinforced concrete in the
    project.
    In February 2015, before the execution of a prime
    contract between the parties, Oceanwide and Lendlease
    agreed that Lendlease would begin construction, and
    Oceanwide issued a “Limited Notice to Proceed,” authorizing
    Lendlease to proceed with work while the terms of the prime
    contract were being finalized. At the time, Oceanwide and
    4
    Lendlease had created and tentatively agreed to the
    Negotiated Draft.2
    The Negotiated Draft included an arbitration
    provision: “[A]ny claim, dispute or other matter in question
    arising out of or related to the Contract Documents . . . shall
    be subject to arbitration which, unless the parties mutually
    agree otherwise, shall be administered by the American
    Arbitration Association in accordance with its Construction
    Industry Arbitration Rules in effect on the date of this
    agreement.” The relevant rules of the American Arbitration
    Association (AAA) provided, among other things, that the
    arbitrator shall have the power to rule on the scope of the
    arbitration agreement. (Rule R-9, Construction Industry
    Arbitration Rules and Rules and Mediation Procedures, AAA
    (Amended July 1, 2015) (AAA Rules).)
    B. The Subcontract and the Executed Prime Contract
    Lendlease and Webcor began negotiating the terms of a
    subcontract in mid-2015. During those negotiations, Webcor
    requested that Lendlease provide a copy of the prime
    contract, which at that time had not yet been executed. In
    early 2016, Lendlease suggested that Webcor review the
    Negotiated Draft in Lendlease’s office, but at Webcor’s
    2    In declarations filed in the trial court, Oceanwide’s and
    Lendlease’s representatives described this draft as
    “99%-negotiated” or as a “near-final draft.”
    5
    insistence, it later agreed to send Webcor a copy of the
    document.
    On February 25, 2016, Lendlease and Webcor executed
    the subcontract. As relevant here, Article 1 of the
    subcontract provided: “Subject only to the terms of Article
    27 [the dispute-resolution provision], nothing herein shall be
    construed to be a binding agreement to arbitrate any dispute
    arising hereunder, notwithstanding any provision to the
    contrary in the Contract Documents.” In turn, the first
    paragraph of Article 27 stated: “In the event of any dispute
    between [Webcor] and [Lendlease] arising out of or relating
    to this Subcontract, or the breach thereof, which involves the
    correlative rights and duties of [Oceanwide], the dispute
    shall be decided in accordance with the Contract Documents,
    and [Webcor], its suppliers, subcontractors and its
    guarantors, surety, or sureties, shall be bound to [Lendlease]
    to the same extent that [Lendlease] is bound to [Oceanwide]
    by the terms of the Contract Documents . . . .” As to disputes
    between Webcor and Lendlease that did not involve
    Oceanwide’s correlative rights and duties, the second
    paragraph of Article 27 provided that either party could seek
    redress in court.
    Under Schedule 1 of the subcontract, the “Contract
    Documents” included “[t]his [s]ubcontract” and “[t]he
    Contract,” among other documents. According to the
    subcontract’s cover page, the term “Contract” referred to the
    prime contract. Acknowledging that Lendlease and
    Oceanwide had not yet executed a prime contract, Paragraph
    III.24 of Exhibit B of the subcontract provided: “[Lendlease]
    6
    agrees that all references in this Subcontract to the Contract
    Documents shall mean and refer to the current draft terms
    of the Prime Contract between [Lendlease] and [Oceanwide]
    (the ‘Negotiated Draft’) until such time as [Lendlease] and
    [Oceanwide] execute the Prime Contract, and [Webcor] shall
    be bound by all terms and conditions of the Negotiated
    Draft.” The same paragraph also purported to bind Webcor
    to the terms of the future prime contract, even if they
    differed from those of the Negotiated Draft.3 Lendlease and
    Webcor later added a rider to the subcontract, providing that
    Oceanwide was “an express third party beneficiary of this
    Subcontract.”
    Oceanwide and Lendlease executed the prime contract
    on July 15, 2016, about four and a half months after the
    Webcor subcontract was executed. The executed prime
    contract included the same arbitration provision contained
    in the Negotiated Draft. Acknowledging the execution of the
    prime contract, Lendlease and Webcor later executed
    Change Order No. 7, which removed all of the subcontract’s
    references to the Limited Notice to Proceed and deleted
    Paragraph III.24 from Exhibit B.
    3     An earlier draft of the subcontract included a duplicate
    paragraph at Paragraph 136 of Exhibit B.1 of the agreement, but
    the parties deleted it after Webcor objected to being bound to
    future terms that had not yet been determined. According to the
    deposition testimony of Webcor’s lead negotiator, John
    Harrington, he had not noticed the identical provision at
    Paragraph III.24 of Exhibit B, which made it into the executed
    subcontract.
    7
    C. Webcor’s Complaint and Appellants’ Motions to
    Compel Arbitration
    In December 2018, following delays in the project and
    disagreements among the parties, Webcor recorded a
    mechanic’s lien on the project, and in January 2019, filed
    this action against Lendlease, Oceanwide, and others. In its
    operative complaint, Webcor asserted claims for: (1) breach
    of contract (against Lendlease); (2) foreclosure of mechanic’s
    lien (against Lendlease, Oceanwide, and others); (3) violation
    of prompt-payment duties (against Lendlease); (4) quantum
    meruit (against Lendlease and Oceanwide); and (5)
    declaratory relief (against Oceanwide and others).
    Oceanwide and Lendlease responded with separate
    motions to compel arbitration and stay the proceedings
    under Code of Civil Procedure sections 1281.2 and 1281.4,
    relying on the subcontract’s dispute-resolution provision.
    They argued this provision incorporated the arbitration
    provision of either the prime contract or the Negotiated
    Draft. Oceanwide, which was not a signatory to the
    subcontract, contended it was entitled to enforce the
    subcontract’s dispute-resolution provision as a third-party
    beneficiary.
    Webcor opposed both motions. It argued the
    subcontract could not have incorporated the prime contract’s
    arbitration provision because that agreement had not yet
    been executed when the subcontract was executed. As to the
    Negotiated Draft, Webcor asserted the subcontract made no
    mention of that document and thus could not have
    8
    incorporated its arbitration provision. In the alternative,
    Webcor claimed that Oceanwide was not a third-party
    beneficiary of the subcontract’s dispute-resolution provision
    and thus had no standing to enforce any arbitration
    agreement it contained. It contended that granting only
    Lendlease’s motion to compel arbitration carried a risk of
    conflicting rulings in different forums.
    D. The Trial Court’s Rulings
    In July 2019, following a hearing on appellants’
    motions to compel arbitration, the trial court denied both
    motions in separate orders. The court did not decide
    whether the subcontract contained a valid arbitration
    agreement or whether Oceanwide had standing to invoke
    any such agreement. Rather, it ruled that even assuming
    the subcontract contained an enforceable arbitration
    agreement, all but one of Webcor’s claims were outside its
    scope because they did not involve Oceanwide’s correlative
    rights and duties. As to the one claim that according to the
    court did involve Oceanwide’s correlative rights and duties
    (quantum meruit), the court exercised its discretion under
    Code of Civil Procedure section 1281.2, subdivision (c)
    (Section 1281.2(c)), to deny arbitration so as to avoid the risk
    of conflicting rulings in different forums. Lendlease and
    Oceanwide timely appealed.
    9
    DISCUSSION
    We review de novo the trial court’s resolution of legal
    questions underlying its ruling on a motion to compel
    arbitration. (Avery v. Integrated Healthcare Holdings, Inc.
    (2013) 
    218 Cal.App.4th 50
    , 60.) The court’s denial of
    arbitration pursuant to Section 1281.2(c), based on the risk
    of conflicting rulings, is reviewed for abuse of discretion.
    (Bunker Hill Park Ltd. v. U.S. Bank National Assn. (2014)
    
    231 Cal.App.4th 1315
    , 1324.)
    It is undisputed that the substantive rules of the
    Federal Arbitration Act (FAA; 
    9 U.S.C. § 1
     et seq.) govern
    any arbitration agreement in the subcontract. The policy
    underlying the FAA “‘“is to ensure that arbitration
    agreements will be enforced in accordance with their
    terms.”’” (State Farm General Ins. Co. v. Watts Regulator
    Co. (2017) 
    17 Cal.App.5th 1093
    , 1098, italics omitted.)
    “Arbitration is ‘a matter of contract’ and the policy favoring
    arbitration does not displace the need for a voluntary
    agreement to arbitrate. [Citation.] ‘Although the FAA
    preempts any state law that stands as an obstacle to its
    objective of enforcing arbitration agreements according to
    their terms, . . . we apply general California contract law to
    determine whether the parties formed a valid agreement to
    arbitrate their dispute.’” (Ibid.)
    Challenging the trial court’s denial of their motions to
    compel arbitration, Lendlease and Oceanwide argue: (1) the
    subcontract initially incorporated the Negotiated Draft’s
    arbitration provision and later incorporated the executed
    prime contract’s (identical) arbitration provision; (2) while
    10
    Oceanwide was not a signatory to the subcontract, it was
    entitled to enforce its dispute-resolution provision as a
    third-party beneficiary; (3) through the Negotiated Draft’s
    incorporation of the AAA Rules, the parties delegated
    questions about the scope of the arbitration agreement to the
    arbitrator, and thus it was not for the trial court to decide
    whether Webcor’s claims involved Oceanwide’s “correlative
    rights and duties”; and (4) alternatively, Webcor’s claims did
    involve Oceanwide’s correlative rights and duties.
    As we briefly discuss below, we agree that Article 27 of
    the subcontract, the dispute-resolution provision,
    incorporated the prime contract’s arbitration provision.
    However, we conclude that Oceanwide had no standing to
    enforce Article 27, and thus that the trial court acted within
    its discretion in denying Lendlease’s motion to compel
    arbitration to avoid the risk of conflicting rulings.4 We
    therefore do not reach appellants’ final contentions.
    4      Although the trial court’s ruling rested on its analysis of
    the scope of the arbitration agreement, we are not bound by the
    court’s reasoning. “[I]t is a settled appellate principle that if a
    judgment is correct on any theory, the appellate court will affirm
    it regardless of the trial court’s reasoning.” (Young v. Fish &
    Game Com. (2018) 
    24 Cal.App.5th 1178
    , 1192-1193.)
    11
    A. The Subcontract Incorporated the Arbitration
    Provisions of the Negotiated Draft and the Executed
    Prime Contract
    We agree with Lendlease and Oceanwide that the
    subcontract contained an arbitration agreement, initially
    through its reference to the Negotiated Draft’s arbitration
    provision, and later through its reference to the identical
    provision in the executed prime contract. Generally,
    “contract interpretation is an issue of law, which we review
    de novo . . . .” (DFS Group, L.P. v. County of San Mateo
    (2019) 
    31 Cal.App.5th 1059
    , 1079.) “‘The fundamental goal
    of contractual interpretation is to give effect to the mutual
    intention of the parties.’ [Citations.] ‘Such intent is to be
    inferred, if possible, solely from the written provisions of the
    contract.’ [Citations.] ‘If contractual language is clear and
    explicit, it governs.’” (State of California v. Continental Ins.
    Co. (2012) 
    55 Cal.4th 186
    , 195.) “The whole of a contract is
    to be taken together, so as to give effect to every part, if
    reasonably practicable, each clause helping to interpret the
    other.” (Civ. Code, § 1641.)
    “‘“It is, of course, the law that the parties may
    incorporate by reference into their contract the terms of
    some other document.”’” (Shaw v. Regents of University of
    California (1997) 
    58 Cal.App.4th 44
    , 54.) Under Article 27 of
    the subcontract (the dispute-resolution provision), any
    dispute between Webcor and Lendlease that relates to that
    agreement and involves Oceanwide’s correlative rights and
    duties “shall be decided in accordance with the Contract
    12
    Documents . . . .” Under Schedule 1 of the subcontract, the
    “Contract Documents” included “[t]he Contract,” a term that
    according to the subcontract’s cover page referred to the
    prime contract. And while, as Webcor points out, Lendlease
    and Oceanwide had not yet executed the prime contract
    when the subcontract was executed, the subcontract’s
    Exhibit B, Paragraph III.24, acknowledged this fact and
    provided that all references to the Contract Documents
    “shall mean and refer to [the Negotiated Draft]” until
    Lendlease and Oceanwide execute the prime contract.5 It is
    therefore clear that the subcontract’s dispute-resolution
    provision referenced the Negotiated Draft. In turn, the
    Negotiated Draft included an arbitration provision: “[A]ny
    claim, dispute or other matter in question arising out of or
    related to the Contract Documents . . . shall be subject to
    arbitration . . . .”
    After Oceanwide and Lendlease executed the prime
    contract, Lendlease and Webcor executed Change Order No.
    7, deleting Exhibit B, Paragraph III.24, which had
    5      Oceanwide suggests the inclusion of this paragraph was
    potentially a mutual mistake, evidenced by the parties’ deletion
    of the identical Paragraph 136 of Exhibit B.1. Initially, Webcor
    itself does not make this argument. Moreover, we note that
    Webcor and Lendlease deleted the latter after Webcor objected to
    a clause purporting to bind Webcor to the uncertain terms of a
    future prime contract. Webcor never objected to the
    incorporation of the Negotiated Draft. Thus, the extrinsic
    evidence concerning the parties’ negotiations is consistent with
    the language of the subcontract.
    13
    substituted references to the Negotiated Draft for the
    subcontract’s references to the prime contract. With this
    change, the revised subcontract’s dispute-resolution
    provision now incorporated the executed prime contract
    itself, which included the same arbitration provision
    contained in the Negotiated Draft. At all times, then, the
    subcontract incorporated the arbitration provision of either
    the Negotiated Draft or the executed prime contract.
    B. Oceanwide Had No Standing to Enforce the
    Subcontract’s Dispute-Resolution Provision, and the
    Trial Court Had Discretion to Deny Lendlease’s
    Motion to Compel Arbitration as Well
    1. Governing Principles
    “Because arbitration is a matter of contract, generally
    ‘“one must be a party to an arbitration agreement to be
    bound by it or invoke it.”’” (DMS Services, LLC v. Superior
    Court (2012) 
    205 Cal.App.4th 1346
    , 1352,1353 (DMS
    Services).) However, courts have recognized limited
    exceptions to this rule, allowing nonsignatories to an
    agreement containing an arbitration provision to compel
    arbitration of a dispute within the scope of that agreement.
    (Ibid.) Under one of those exceptions, invoked by
    Oceanwide, a nonsignatory may enforce an arbitration
    agreement if the nonsignatory is a third-party beneficiary of
    the agreement. (County of Contra Costa v. Kaiser
    Foundation Health Plan, Inc. (1996) 
    47 Cal.App.4th 237
    ,
    242.)
    14
    “A third party beneficiary may enforce a contract
    expressly made for his benefit.” (Murphy v. Allstate Ins. Co.
    (1976) 
    17 Cal.3d 937
    , 943 (Murphy), citing Civ. Code,
    § 1559.) Status as a third-party beneficiary of a contract,
    however, does not grant a person the power to enforce any
    and every provision of the contract; rather, a third-party
    beneficiary “may enforce those promises directly made for
    him.” (Murphy, supra, at 943; accord, Sessions Payroll
    Management, Inc. v. Noble Construction Co. (2000) 
    84 Cal.App.4th 671
    , 680 (Sessions), quoting Murphy; Clark v.
    California Ins. Guarantee Assn. (2011) 
    200 Cal.App.4th 391
    ,
    398 [“as a third party beneficiary, the judgment creditor can
    only enforce those promises made directly for his benefit”],
    citing Murphy, at 943.)
    In Murphy, a judgment creditor sued the judgment
    debtor’s insurer for breach of the duty to settle, which is
    included in the implied covenant of good faith and fair
    dealing. (Murphy, supra, 17 Cal.3d at 939-941.) Insurance
    Code section 11580, subdivision (b)(2), made the judgment
    creditor a third-party beneficiary of the insurance contract
    between the defendant and the insurer, and the implied
    covenant of good faith and fair dealing was a term of the
    contract for purposes of that statutory provision. (Murphy,
    at 942-943.) Our Supreme Court held, however, that despite
    her third-party beneficiary status, the judgment creditor had
    no standing to invoke the insurer’s duty to settle because
    that duty was intended to benefit the insured, rather than a
    third-party claimant. (Id. at 943-944.) The Murphy court
    explained: “A third party should not be permitted to enforce
    15
    covenants made not for his benefit, but rather for others. He
    is not a contracting party; his right to performance is
    predicated on the contracting parties’ intent to benefit him.
    [Citations.] As to any provision made not for his benefit but
    for the benefit of the contracting parties or for other third
    parties, he becomes an intermeddler. Permitting a third
    party to enforce a covenant made solely to benefit others
    would lead to the anomaly of granting him a bonus after his
    receiving all intended benefit.” (Id. at 944.)
    Courts have since applied Murphy’s teachings beyond
    the context of insurance policies and the implied covenant of
    good faith and fair dealing. In Sessions, the Court of Appeal
    applied these principles to reverse an award of attorney fees.
    (Sessions, supra, 84 Cal.App.4th at 680-681.) There, a
    plaintiff sued the defendant, a general contractor, for the
    breach of a contract between the defendant and a
    subcontractor. The plaintiff, who provided payroll services
    to the subcontractor, claimed it was a third-party beneficiary
    of the contract. (Id. at 675-677.) The contract provided that
    “‘[i]n the event it becomes necessary for either party to
    enforce the provisions of this Agreement,’” the prevailing
    party would be entitled to attorney fees. (Id. at 676, italics
    omitted.) The trial court sustained a demurrer without
    leave to amend and awarded the defendant attorney fees
    based on the reciprocity principles of Civil Code section 1717
    16
    and the attorney fee provision in the contract.6 (Id. at 676-
    677.)
    On appeal, the plaintiff argued it would not have been
    entitled to attorney fees had it prevailed on its claim, and
    thus that the defendant was likewise not entitled to fees.
    The Court of Appeal agreed. (Sessions, supra, 84
    Cal.App.4th at 680-681.) Citing Murphy’s explanation of the
    limits of third-party beneficiaries’ ability to enforce
    contractual provisions, the court concluded that even if the
    plaintiff had prevailed on its third-party beneficiary claim,
    the attorney fee provision’s reference to “either party”
    excluded the plaintiff, and thus that the signatories had not
    intended it to benefit the plaintiff. (Sessions, at 680-681,
    italics omitted.)
    Similarly, and as particularly relevant here, in Fuentes
    v. TMCSF, Inc. (2018) 
    26 Cal.App.5th 541
     (Fuentes), the
    court applied Murphy to conclude that a plaintiff had no
    standing to enforce an arbitration provision as a third-party
    beneficiary. (Fuentes, supra, 26 Cal.App.5th at 551-552.)
    6      “Civil Code section 1717 makes an otherwise unilateral
    right [to attorney fees] reciprocal when a defendant sued on a
    contract with a provision awarding attorney fees to the prevailing
    party defends by successfully arguing the inapplicability,
    invalidity, unenforceability, or nonexistence of that contract.”
    (Sessions, supra, 84 Cal.App.4th at 678, italics omitted.) Because
    these arguments are inconsistent with a claim for attorney fees
    under the same contract, a prevailing defendant would not be
    able to obtain attorney fees without the operation of this
    statutory provision. (Ibid.)
    17
    The plaintiff purchased a motorcycle from a dealership and
    executed a separate financing agreement with a third-party
    lender. (Id. at 545.) While the purchase agreement
    contained no arbitration provision (ibid.), the financing
    agreement provided for arbitration of claims between the
    plaintiff and the lender or any of its “‘successors, assigns,
    parents, subsidiaries, or affiliates and/or any employees,
    officers, directors, agents, of the aforementioned . . . ’” (id. at
    546). After the plaintiff brought a putative class action
    against the dealership, the latter sought to compel
    arbitration under the financing agreement, asserting it was
    a third-party beneficiary of that contract. (Id. at 546-547.)
    The Fuentes court assumed for the sake of the
    argument that the dealership was a third-party beneficiary
    of the financing agreement. (Fuentes, supra, 26 Cal.App.5th
    at 552.) However, based on the relevant language from
    Murphy, the court concluded the dealership could not invoke
    that agreement’s arbitration provision. (Fuentes, supra, at
    551-552.) It noted that the arbitration clause had “its own
    list of intended third party beneficiaries,” which did not
    include the dealership. (Id. at 552.) The Court of Appeal
    thus concluded, “the contract affirmatively disproves any
    intent that the arbitration clause should benefit [the
    dealership].” (Ibid.) Under this authority, the pertinent
    question is not merely whether Oceanwide was a third-party
    18
    beneficiary of the subcontract generally, but whether it was
    an intended beneficiary of Article 27.7
    As a general matter, it is for the court to decide
    whether a nonsignatory may invoke an arbitration
    agreement.8 (See Benaroya v. Willis (2018) 
    23 Cal.App.5th 462
    , 469 [“‘an arbitrator has no power to determine the
    rights and obligations of one who is not a party to the
    arbitration agreement’”]; Knight et al., Cal. Practice Guide:
    Alternative Dispute Resolution (The Rutter Group 2020)
    ¶ 5:287 [“a trial court must first determine the status of a
    person who demands arbitration under a contract that he or
    7     Oceanwide suggests this rule subjects arbitration
    provisions to “special scrutiny . . . beyond that which is applied to
    the contract as a whole,” and is therefore preempted by the FAA,
    which “‘precludes states from “singling out arbitration provisions
    for suspect status . . . .”’” (Quoting Rosenthal v. Great Western
    Fin. Securities Corp. (1996) 
    14 Cal.4th 394
    , 410.) Not so. The
    rule that third parties may enforce only those promises intended
    to benefit them is generally applicable, and as discussed, has
    been applied in such contexts as attorney fees (see Sessions,
    supra, 84 Cal.App.4th at 680-681) and the implied covenant of
    good faith and fair dealing (see Murphy, supra, 17 Cal.3d at
    943-944), as well as arbitration. Oceanwide offers nothing to
    show that this rule subjects arbitration provisions to special
    scrutiny.
    8      Oceanwide does not contend that either the subcontract or
    the prime contract empowered the arbitrator to decide whether
    Oceanwide was a third-party beneficiary entitled to compel
    arbitration. It has therefore forfeited any contention in this
    regard. (See Browne v. County of Tehama (2013) 
    213 Cal.App.4th 704
    , 726 [failure to raise contention in opening brief constitutes
    forfeiture].)
    19
    she did not sign”].) This determination involves a question
    of law that we review de novo. (DMS Services, supra, 205
    Cal.App.4th at 1352.) “The party claiming to be a third
    party beneficiary bears the burden of proving that the
    contracting parties actually promised the performance which
    the third party beneficiary seeks.” (Loduca v. Polyzos (2007)
    
    153 Cal.App.4th 334
    , 341.)
    2. Analysis
    We conclude that Oceanwide was not entitled to invoke
    Article 27 as a third-party beneficiary. While Oceanwide
    was undoubtedly a third-party beneficiary of the subcontract
    under the rider to that agreement, Oceanwide may not
    enforce Article 27 unless this provision was intended to
    benefit Oceanwide. (See Murphy, supra, 17 Cal.3d at 943;
    Sessions, supra, 84 Cal.App.4th at 680-681.)
    The first paragraph of Article 27 provided: “In the
    event of any dispute between [Webcor] and [Lendlease] . . .
    which involves the correlative rights and duties of
    [Oceanwide], the dispute shall be decided in accordance with
    the Contract Documents, and [Webcor] . . . shall be bound to
    [Lendlease] to the same extent that [Lendlease] is bound to
    [Oceanwide] by the terms of the Contract Documents. . . .”
    The plain terms of Article 27 limit arbitration to claims
    between Webcor and Lendlease.9
    9    We consider the breadth of the arbitration agreement
    under Article 27 only to the extent it informs our assessment of
    (Fn. is continued on the next page.)
    20
    Only certain disputes “between [Webcor] and
    [Lendlease]” must be submitted to arbitration under this
    provision, which made no reference to disputes between
    Webcor and Oceanwide. Nothing in the nature of an
    arbitration provision or the subcontract required such
    restrictive language. Indeed, the Negotiated Draft’s
    arbitration provision stated simply, “[A]ny claim, dispute or
    other matter in question arising out of or related to the
    Contract Documents . . . shall be subject to arbitration . . . .”
    Rather than simply incorporate this provision, Article 27
    included the additional limiting language. The subcontract
    provided in Article 1 that the parties’ arbitration obligations
    would be determined by Article 27 alone, “notwithstanding
    any provision to the contrary in the Contract Documents,”
    demonstrating a recognition that Article 27’s arbitration
    mandate was narrower. Article 27’s reference to disputes
    between Webcor and Lendlease establishes an intent to limit
    arbitration under the subcontract to those parties. (See
    Sessions, supra, 84 Cal.App.4th at 680-681 [attorney fee
    provision’s reference to “either party” excluded nonsignatory
    plaintiff, even if plaintiff had been third-party beneficiary
    (italics omitted)]; Rath v. Managed Health Network, Inc.
    (1992) 
    123 Idaho 30
    , 31 [third-party beneficiary not included
    in provision requiring arbitration of controversies “‘between
    the parties’” (italics omitted)]; 9 Corbin on Contracts (2020)
    Oceanwide’s standing to enforce it. As noted, we do not decide
    whether it would have been for the trial court or the arbitrator to
    determine the agreement’s scope as such.
    21
    § 46.9 [discussing provision limiting arbitration to “‘[a]ny
    dispute between the Parties’” and stating, “If the term ‘party’
    clearly excludes beneficiaries, such an exclusion must be
    enforced to honor the overriding policy that the contract
    terms define and limit the rights of the beneficiary”].)
    Oceanwide does not address this limiting language in
    its briefs, even after Webcor brings it to the forefront in its
    own brief; rather, Oceanwide simply asserts, repeatedly,
    that under the first paragraph of Article 27, “any dispute”
    that involves its correlative rights and duties is subject to
    arbitration. We, however, may not ignore this language, and
    instead must give it effect. (See Advanced Network, Inc. v.
    Peerless Ins. Co. (2010) 
    190 Cal.App.4th 1054
    , 1063 [“‘We
    must give significance to every word of a contract, when
    possible, and avoid an interpretation that renders a word
    surplusage’”].)
    Oceanwide emphasizes that the first paragraph of
    Article 27 referenced Oceanwide twice. Yet the first
    reference to Oceanwide is an additional limitation of the
    duty to arbitrate. To be subject to arbitration under Article
    27, a matter must both (a) be a dispute between Webcor and
    Lendlease and (b) involve Oceanwide’s correlative rights and
    duties. This limiting language cannot expand the
    signatories’ arbitration obligations. Similarly, the second
    reference to Oceanwide -- providing that Webcor would be
    “bound to [Lendlease]” to the same extent Lendlease is
    bound to Oceanwide by the terms of the Contract Document
    -- does not extend Webcor’s duty to arbitrate to claims
    against Oceanwide. Again, rather than say that Webcor
    22
    would “be bound to Lendlease and Oceanwide” or simply
    that it would “be bound by the terms of the Contract
    Documents,” this provision spoke in terms of Webcor’s duties
    to Lendlease alone. The reference to the extent Lendlease is
    bound to Oceanwide served merely as a measuring stick to
    determine the scope of Webcor’s duties toward Lendlease.
    By providing for arbitration of certain disputes
    between Webcor and Lendlease, Article 27 indicates an
    intent to benefit Lendlease, but not Oceanwide. As in
    Sessions and Fuentes, the exclusion of the third-party
    beneficiary from the scope of the provision negates an intent
    to benefit it. (See Sessions, supra, 84 Cal.App.4th at 680-681
    [attorney fee provision that was limited to signatories was
    not intended to benefit claimed third-party beneficiary];
    Fuentes, supra, 26 Cal.App.5th at 551-552 [arbitration
    provision that was limited to signatories and certain third
    parties not including defendant was not intended to benefit
    defendant].) Oceanwide argues Fuentes is distinguishable
    because unlike Article 27, the arbitration provision there
    had “‘its own list of intended third party beneficiaries,’”
    which did not include the defendant dealership. (Fuentes, at
    552.) But just as the provision in Fuentes limited its
    application to the specified parties -- the lender and its
    “successors, assigns, parents, subsidiaries,” etc. (id. at 546) --
    the first paragraph of Article 27 limited its application to the
    specified parties, Webcor and Lendlease. Additionally,
    Oceanwide does not attempt to distinguish Sessions, even
    after Webcor relies on it in its brief.
    23
    We observe that Article 27’s different treatment of
    disputes between Webcor and Lendlease according to
    whether they involve Oceanwide’s rights and duties made
    sense for Lendlease. Lendlease and Webcor may not have
    wanted to arbitrate claims between the two of them. But
    without the first paragraph of Article 27, Lendlease would
    have faced a risk of arbitrating disputes with Oceanwide (as
    it was required to do under the prime contract) while
    litigating parallel disputes with Webcor in court, leading to
    duplicative litigation efforts, additional expense, and a risk
    of conflicting rulings.10 Oceanwide offers no explanation how
    a provision requiring arbitration between Webcor and
    Lendlease alone was intended to benefit Oceanwide.
    Because Article 27’s arbitration provision was not intended
    to benefit Oceanwide, the latter had no standing to enforce
    it.11 (See Murphy, supra, 17 Cal.3d at 943-944; Sessions,
    10     Under at least some scenarios, Lendlease could implore the
    trial court to deny arbitration with Oceanwide under Section
    1281.2(c). But requiring Webcor to arbitrate relevant claims
    provided more certainty, as it did not require Lendlease to
    depend on a favorable exercise of the court’s discretion.
    11     For the first time at oral argument, Oceanwide argued that
    Article 27 could require Webcor to arbitrate claims against
    Oceanwide because the AAA Rules, which Article 27
    incorporated, allowed for the joinder of parties to an ongoing
    arbitration proceeding. Initially, we note that Oceanwide has
    forfeited this contention by failing to raise it in its briefs. (See
    Haight Ashbury Free Clinics, Inc. v. Happening House Ventures
    (2010) 
    184 Cal.App.4th 1539
    , 1554, fn. 9 (Haight Ashbury) [“We
    do not consider arguments that are raised for the first time at
    (Fn. is continued on the next page.)
    24
    supra, 84 Cal.App.4th at 676; Fuentes, supra, 26 Cal.App.5th
    at 551-552.)
    Oceanwide cites Macaulay v. Norlander (1992) 
    12 Cal.App.4th 1
     for the proposition that a third-party
    beneficiary’s inclusion in an arbitration provision may be
    inferred from the “nature of the agreement as a whole.” We
    are unpersuaded. Initially, the amorphous concept of “the
    nature of the agreement” cannot override the clear language
    of the arbitration agreement. Macaulay itself stated that a
    court must “scrutinize the language [of the contract] to
    determine whether it selectively includes or excludes the
    [third party] from the arbitration provision.” (Id. at 8.)
    There, the contract expressly included the relevant third
    party in the arbitration provision. (Id. at 7 [relying on
    agreement’s statement that “‘the terms and conditions
    hereof, including the arbitration provision . . ., shall be
    applicable to all matters between [the third party] and
    you’”].) Moreover, nothing in the nature of a construction
    subcontract requires that the owner/developer be included in
    an arbitration provision. (Cf. 9 Corbin on Contracts, supra,
    § 45.3 [addressing third-party status of owners in
    construction subcontracts, generally; “the case law generally
    supports the view espoused in this treatise that the owner is
    typically not an intended beneficiary of such contracts”].) In
    oral argument”].) Moreover, AAA Rule R-7, the rule Oceanwide
    referenced, addresses the procedures governing the joinder of
    parties. It does not provide an independent basis to compel
    arbitration outside the scope of any arbitration agreement.
    25
    short, Oceanwide had no standing to compel arbitration
    under the subcontract as a third-party beneficiary.
    Under Code of Civil Procedure section 1281.2, a trial
    court has discretion to refuse to compel arbitration if “[a]
    party to the arbitration agreement is also a party to a
    pending court action . . . with a third party, arising out of the
    same transaction or series of related transactions and there
    is a possibility of conflicting rulings on a common issue of
    law or fact.” (Section 1281.2(c); see also Daniels v. Sunrise
    Senior Living, Inc. (2013) 
    212 Cal.App.4th 674
    , 680
    [“whether to stay or deny arbitration based on the possibility
    of conflicting rulings on common questions of law or fact is
    reviewed for an abuse of discretion”].) While the trial court
    employed a different analysis than we have, it ultimately
    declined to order arbitration based on the risk of conflicting
    rulings in separate proceedings.12 Appellants do not
    12     It is not the case that parties to arbitration agreements
    may avoid enforcement whenever they include nonsignatories in
    the litigation. The trial court has discretion to compel
    arbitration, even under the circumstances outlined in Section
    1281.2(c). Moreover, under the equitable estoppel doctrine,
    nonsignatories may be able to compel a signatory to arbitrate
    when, inter alia, the signatory “has signed an agreement to
    arbitrate but attempts to avoid arbitration by suing nonsignatory
    defendants for claims that are ‘“based on the same facts and are
    inherently inseparable”’ from arbitrable claims against signatory
    defendants.” (Metalclad Corp. v. Ventana Environmental
    Organizational Partnership (2003) 
    109 Cal.App.4th 1705
    , 1713.)
    Oceanwide did not invoke this doctrine below and does not argue
    it on appeal.
    26
    challenge the court’s authority to do so if Oceanwide could
    not compel Webcor to arbitrate its claims against
    Oceanwide.13 Accordingly, we find no reversible error in the
    court’s orders.
    13    For the first time at oral argument, appellants raised three
    contentions concerning the court’s authority under Section
    1281.2(c) to refuse to compel arbitration if Oceanwide could not
    enforce Article 27 in court: (1) Lendlease suggested there could
    be no risk of conflicting rulings because the arbitrator could join
    Oceanwide as a party to arbitration between Webcor and
    Lendlease under the AAA Rules; (2) Oceanwide contended there
    could be no risk of conflicting rulings even if only Webcor and
    Lendlease alone proceed to arbitration because other than the
    quantum meruit claim, Webcor’s claims against Oceanwide
    depend on Webcor’s contractual claim against Lendlease, and
    Webcor could not proceed to final adjudication on its quantum
    meruit claim without first abandoning its contractual claim; and
    (3) Oceanwide argued Section 1281.2(c) is preempted by the FAA.
    Appellants have forfeited these claims by failing to raise them in
    their briefs. (See Haight Ashbury, supra, 184 Cal.App.4th at
    1554, fn. 9.) Additionally, as to Lendlease’s reference to the AAA
    Rules regarding joinder, we again note that those rules provide
    no independent basis for arbitration between parties who did not
    agree to arbitrate. And as to Oceanwide’s preemption argument,
    we observe that California courts have held that the FAA does
    not preempt Section 1281.2(c) unless the arbitration agreement
    expressly adopts the FAA’s procedural rules. (See Avila v.
    Southern California Specialty Care, Inc. (2018) 
    20 Cal.App.5th 835
    , 840-841 [no preemption of Section 1281.2(c) unless FAA’s
    procedural rules apply, and those rules do not apply in state
    court, absent express provision in arbitration agreement]; Los
    Angeles Unified School Dist. v. Safety National Casualty Corp.
    (2017) 
    13 Cal.App.5th 471
    , 479-482 [same].) Oceanwide has not
    contended that Article 27 expressly adopted the FAA’s procedural
    (Fn. is continued on the next page.)
    27
    DISPOSITION
    The trial court’s orders denying appellants’ motions to
    compel arbitration are affirmed. Webcor is awarded its costs
    on appeal.
    NOT TO BE PUBLISHED IN THE OFFICIAL
    REPORTS
    MANELLA, P. J.
    We concur:
    WILLHITE, J.
    COLLINS, J.
    rules, whether directly or by reference to the Contract
    Documents.
    28
    

Document Info

Docket Number: B299310

Filed Date: 12/17/2020

Precedential Status: Non-Precedential

Modified Date: 12/18/2020