McKinley Home Foundation v. West Hills Construction CA2/2 ( 2020 )


Menu:
  • Filed 12/22/20 McKinley Home Foundation v. West Hills Construction CA2/2
    NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS
    California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions
    not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion
    has not been certified for publication or ordered published for purposes of rule 8.1115.
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    SECOND APPELLATE DISTRICT
    DIVISION TWO
    MCKINLEY HOME                                                   B292720
    FOUNDATION et al.,
    (Los Angeles County
    Plaintiffs and Appellants,                             Super. Ct. No. KC069072)
    v.
    WEST HILLS CONSTRUCTION,
    INC.,
    Defendant and Respondent.
    APPEAL from a judgment of the Superior Court of
    Los Angeles County. Daniel Thomas Oki, Judge. Reversed.
    Kassouni Law and Timothy V. Kassouni for Plaintiffs and
    Appellants.
    Ropers Jajeski, Terry Anastassiou, Tim M. Agajanian, and
    German A. Marcucci for Defendant and Respondent.
    _________________________
    Plaintiffs and appellants McKinley Home Foundation
    (Foundation) and McKinley Children’s Center, Inc. (Children’s
    Center) (collectively appellants) sued West Hills Construction,
    Inc. (respondent) for, inter alia, breach of warranty after the
    failure of a solar power system that respondent installed. The
    trial court granted summary judgment for respondent, concluding
    that the warranty was unambiguous and did not apply because
    the solar power system and its failed components were supplied
    by a third party. We reverse summary judgment because the
    warranty was ambiguous, and there are triable issues as to what
    the warranty covers.
    FACTS
    The Pleadings
    Appellants sued respondent and eventually filed an
    amended complaint. They both alleged causes of action for
    breach of warranty and breach of contract, and Children’s Center
    alleged a cause of action for breach of contract on a third-party
    beneficiary theory.
    The amended complaint averred:
    Foundation contracted with respondent to install a solar
    power system at the Children’s Center campus. “The solar
    energy system was largely manufactured and supplied by
    GreenVolts, Inc. [(Greenvolts)]. [Greenvolts] has since filed [for]
    bankruptcy and has been liquidated. [Respondent] supplied any
    additional components necessary for installation that were not
    supplied by [Greenvolts], including the wiring, its associated
    conduit, and the racking system needed to hold the solar panels.”
    Respondent warranted that the solar energy system would be
    free from defects and would experience less than a 15 percent
    reduction in power output for a period of 10 years. The
    2
    installation was completed in May 2012. “Over 20 of the [solar]
    panels completely failed by April 2015 and many more of them
    were operating at half power. Additionally, investigators found
    burn marks on a number of the inverters. The panels and
    inverters experienced internal stresses, thermal cycling, and
    possible surges that contributed to an imbalance in the solar
    system when the panels failed. This imbalance caused the entire
    system to fail.” As a consequence, appellants suffered various
    types of damage.
    The parties’ contract was attached to the amended
    complaint as an exhibit. It provided certain milestones, two of
    which stated “GV Equipment dropped on-site (Joint Checks to
    [respondent] & [Greenvolts])” and “Greenvolts Equipment
    Installation Completed.” A description of the project, the
    materials to be used and the equipment to be installed was set
    forth in a portion of the contract entitled Scope of Services for
    Renewable Energy Power System (Scope of Services).
    The Scope of Services listed the job site and identified the
    “System Size” as “419.879 kw CEC-AC PV System, with Turn-
    Key installation at customer’s site.” (Emphasis omitted.) It
    listed “Major System Components” and identified Greenvolts as
    the “Module Manufacturer” and the “Inverter Manufacturer.”
    (Emphasis omitted.) The standard components were “[r]acking
    and mounting components,” and “over-current protection . . . ,
    Roofing sealant or flashing as needed.” Appellants initialed the
    portion of the Scope of Services indicating that it was separately
    purchasing the “Greenvolts Monitoring Package with Revenue
    Grade Monitoring and Weather package.”
    Next, the Scope of Services identified the standard labor as,
    inter alia: system design; securing of permit; “[i]nstall specified
    3
    system in good workmanlike manner;” and “[c]omplete and
    submit utility interconnection documents sufficient for
    [Children’s Center] to export energy to Southern California
    Edison[.]”
    The warranty stated that “all components of the [solar]
    power system that [respondent] provides to [appellants], other
    than the meter, will be free from defects in the components and
    workmanship and a reduction in power output by more than
    fifteen (15) percent for a period of ten (10) years from the date of
    installation; the meter will be free from defects in the components
    and workmanship for a period of one (1) year from the date of
    installation. The warranty is limited to the following components
    of the power system: photovoltaic (PV) panels, inverters, solar
    collectors, tracking mechanisms, heat exchangers, pumps, heat-
    driven cooling systems associated with the system, and the
    meter. This warrants at the time of commissioning, [Greenvolts]
    will specify the expected power output for the Equipment and
    shall be the Site Expected Power. Greenvolts warrants that if,
    within twenty (20) years from the original date of commissioning,
    the Site Actual Energy is less than the Site Guaranteed Energy
    (as defined by the full warranty provisions), Greenvolts will
    restore the Equipment through a method at the discretion of
    Greenvolts[] to a state capable of generating the Site Guaranteed
    Energy. Please see Greenvolts[’s] System Warranty[.]” In the
    exclusions paragraph, the warranty stated: “The following
    exclusions apply to the . . . warranty: (1) Work performed by and
    materials provided by any person or entity other than
    [respondent] are not warranted[.]” Next, it stated, inter alia, “If
    any of the components covered by [respondent’s] warranty
    . . . fails at any time during the warranty period, [respondent]
    4
    will, upon prompt written notice . . . make all repairs
    . . . necessary[.]”
    Summary Judgment
    Respondent moved for summary judgment. It claimed that
    Greenvolts manufactured and supplied all the “system
    constituents that [respondent] installed[, including] the solar
    panels, the tilting panel racks, and the power inverters.”
    Further, respondent pointed out that appellants confirmed in
    discovery that the equipment that failed was the solar panels, the
    inverters, and the actuators that move the panels to align with
    the sun. Per respondent, the warranty excluded Greenvolts’s
    work and equipment and respondent could not be liable for the
    system failure.
    In opposition, appellants argued that the warranty covered
    Greenvolts’s equipment or was ambiguous as to its meaning.
    Alternatively, they argued that if the warranty excluded
    Greenvolts’s equipment, then it was illegal because it violated
    Public Resources Code section 25782. Separately, appellants
    argued that respondent breached the contract by failing to install
    a working solar energy system. Finally, they accused respondent
    of spoliation of evidence due to the destruction of e-mails between
    respondent and Greenvolts.
    The trial court granted the motion, ruling that the contract
    was unambiguous, and that Greenvolts warranted its equipment,
    not respondent. The trial court rejected the spoliation of evidence
    accusation, accepting the evidence provided by respondent that
    the e-mails had been automatically deleted before the lawsuit
    was filed.
    Judgment was entered for respondent.
    This timely appeal followed.
    5
    DISCUSSION
    Appellants seek reversal on three grounds: there is a
    triable issue as to whether respondent’s warranty excluded the
    failed components; a 10-year warranty was implied by law into
    the contract pursuant to Public Resources Code section 25782;
    and respondent was guilty of spoliation of evidence. Because we
    conclude that appellants are correct on the first issue, we
    conclude that summary judgment was improper. We need not
    reach the other issues.
    I. Standard of Review.
    Summary judgment is reviewed de novo. (Saelzler v.
    Advanced Group (2001) 
    25 Cal.4th 763
    , 767.) Where, as here, the
    summary judgment motion pertained to contract interpretation
    and the parties did not offer extrinsic evidence to aid that
    interpretation, the trial court was empowered to grant summary
    judgment only if the contractual language is clear and
    unambiguous. (Niederer v. Ferreira (1987) 
    189 Cal.App.3d 1485
    ,
    1499–1500.)
    II. Summary Judgment was Improper.
    The pivotal question is whether the language in the parties’
    contract is ambiguous or unambiguous. We conclude that it is
    ambiguous. Consequently, the trial court erred when it granted
    summary judgment.
    A. Relevant Principles.
    “The language of a contract is to govern its interpretation,
    if the language is clear and explicit, and does not involve an
    absurdity.” (Civ. Code, § 1638.) But not every contract has a
    clear meaning. A contract is ambiguous on its face if it is capable
    of two reasonable interpretations. (Republic Bank v. Marine Nat.
    Bank (1996) 
    45 Cal.App.4th 919
    , 924.)
    6
    B. Analysis.
    On its face, the contract can reasonably be interpreted in
    two ways.
    Read one way, the contract can be interpreted to mean that
    Greenvolts provided the failed panels and inverters, and that
    they were excluded from respondent’s warranty, because:
    Greenvolts was identified as the manufacturer of the modules
    and inverters; the contract specified that Greenvolts would
    deliver the “equipment” and that appellants would pay
    Greenvolts by separate check; the contract alerted appellants to
    Greenvolts’s warranty; and components provided by third parties
    were expressly excluded.
    Alternatively, the contract can be interpreted to mean that
    the parties understood that respondent provided the failed
    components and therefore they were covered by the warranty.
    The warranty stated that respondent “warrants that all
    components of the [solar] power system that [respondent]
    provides to [appellants] . . . will be free from defects in the
    components and workmanship and a reduction in power output
    by more than fifteen (15) percent for a period of ten (10) years
    from the date of installation; the meter will be free from defects
    in the components and workmanship for a period of one (1) year
    from the date of installation.” The warranty was “limited to the
    following components of the power system: photovoltaic (PV)
    panels, inverters, solar collectors, tracking mechanisms, heat
    exchangers, pumps, heat-driven cooling systems associated with
    the system, and the meter.” The warranty also stated, “If any of
    the components covered by [respondent’s] warranty . . . fails at
    any time during the warranty period, [respondent] will, upon
    prompt written notice . . . make all repairs . . . necessary[.]”
    7
    In light of these conflicting reasonable interpretations, the
    contract is facially ambiguous as a matter of law. On remand,
    the onus will be on the parties and the trial court to resolve the
    ambiguity.
    DISPOSITION
    The judgment is reversed. Appellants are entitled to their
    costs on appeal.
    NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS.
    ______________________, J.
    ASHMANN-GERST
    We concur:
    ________________________, P. J.
    LUI
    ________________________, J.
    HOFFSTADT
    8
    

Document Info

Docket Number: B292720

Filed Date: 12/22/2020

Precedential Status: Non-Precedential

Modified Date: 12/22/2020