Torres v. Design Group Facility Soultions, Inc. ( 2020 )


Menu:
  • Filed 2/13/20
    CERTIFIED FOR PUBLICATION
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    SECOND APPELLATE DISTRICT
    DIVISION THREE
    ISMAEL TORRES, JR., an              B294220
    Incompetent Person, etc.,
    (Los Angeles County
    Plaintiff and Appellant,    Super. Ct. No. BC608065)
    v.
    DESIGN GROUP FACILITY
    SOLUTIONS, INC.,
    Defendant and Respondent.
    APPEAL from a judgment of the Superior Court of Los
    Angeles County, Maurice A. Leiter, Judge. Reversed.
    Law Offices of Berglund & Johnson and Daniel W. Johnson
    for Plaintiff and Appellant.
    Lynberg & Watkins, Michael J. Larin, Jerome P. Doctors;
    London Fischer, Richard S. Endres, Nicholas W. Davila and
    Grant R. Mullen for Defendant and Respondent.
    ——————————
    Ismael Torres, Jr. sued Design Group Facility Solutions,
    Inc. (Design) for personal injuries after he fell through a skylight
    at a construction site. Design moved for summary judgment.
    The trial court initially denied the motion. Design moved for
    reconsideration based on new evidence under Code of Civil
    Procedure1 section 1008, subdivision (a). At the hearing on the
    motion, the trial court granted reconsideration and, at the same
    time, granted the motion for summary judgment without giving
    Torres an opportunity to respond to the new evidence. We find
    the trial court abused its discretion. We hold that a party
    unsuccessfully moving for summary judgment cannot circumvent
    the requirements of section 437c by subsequently moving for
    reconsideration under section 1008, subdivision (a).
    BACKGROUND
    Design was hired as the general contractor to renovate and
    expand a seafood processing facility. As part of the project,
    Design subcontracted with C&L Refrigeration (C&L) to install
    new refrigeration units. C&L in turn hired H.J. Vast (Vast) as a
    sub-subcontractor to do electrical work. Torres was an employee
    of Vast.
    The renovation required workers to be on the roof, which
    contained skylights. The roof was roughly divided into western
    and eastern sections by a pipe rack with the skylights on the
    western section closer together than the skylights on the eastern
    section. Design and C&L discussed the safety hazard posed by
    the skylights. To address the hazard, C&L created a pathway on
    the roof, requiring its workers to walk due west and delineating
    1All further statutory references are to the Code of Civil
    Procedure.
    2
    certain paths of travel with caution tape. The eastern section of
    the roof was unmarked. While working on the eastern section of
    the roof, Torres tripped and crashed through a skylight, falling
    33 feet.
    Torres sued Design for damages as a result of his injuries.
    Design moved for summary judgment, arguing Torres’s claims
    were barred by Privette v. Superior Court (1993) 
    5 Cal. 4th 689
    ,
    which generally shields a hirer from liability for an independent
    contractor’s workplace injuries. The summary judgment hearing
    was continued for several months at Torres’s request so that he
    could conduct additional inspections and depositions. Before
    Torres filed his opposition, several witnesses were deposed,
    including Design’s construction site manager, Vast’s project
    foreman, C&L’s safety coordinator, the Vast employee who
    witnessed Torres’s fall, and Torres himself. Torres included some
    of this new discovery in his opposition.
    The trial court denied Design’s motion, finding that there
    were triable issues of fact as to whether Design retained
    sufficient control over the work site and whether Design’s
    negligence contributed to Torres’s injuries. The trial court relied
    on Design’s construction site manager’s statement that he would
    check to see if the delineators marking the roof pathway were
    connected with tape, rope, or some other kind of line. The trial
    court found that this statement created an inference that Design
    affirmatively exercised its control by establishing a pathway and
    periodically checking the safety delineators on site and that its
    negligence in doing so resulted in injury.
    Design then moved for reconsideration under section 1008,
    subdivision (a) based on new facts, submitting that it was unable
    to provide the trial court with the deposition testimony of
    3
    witnesses taken by Torres and C&L after Design moved for
    summary judgment. This included statements from Vast’s
    project manager that his communications were strictly with C&L,
    that Vast had its own safety practices, and that he orally
    instructed Vast employees where to walk. Design submitted the
    new evidence via attorney declaration with attached deposition
    excerpts, but did not provide a supplemental separate statement.
    Torres opposed reconsideration on the basis that the
    motion did not meet section 1008, subdivision (a)’s requirement
    that the moving party show new or different facts. Torres
    contested whether the deposition testimony was in fact new
    because it was available one to five months before the summary
    judgment hearing, albeit not before Design filed its motion.
    Torres also asserted that Design failed to provide a supplemental
    or amended motion that complied with the rules governing
    summary judgment, including the requisite 75 days’ notice. (See
    § 437c, subd. (a)(2).) Alternatively, Torres submitted that Design
    should have applied ex parte for permission to introduce the
    additional evidence. “[W]e should be able to have the opportunity
    to respond with like evidence and know exactly what facts we’re
    talking about . . . with respect to the summary judgment rules.”
    The trial court addressed both the motion for
    reconsideration and the motion for summary judgment in one
    ruling. The trial court first granted the motion for
    reconsideration, finding that the deposition testimony taken after
    Design moved for summary judgment but before the summary
    judgment hearing, constituted new evidence that was previously
    unavailable. It also noted, ironically, that it would have violated
    Torres’s right to due process if it allowed Design to introduce this
    evidence in its reply to Torres’s opposition to summary judgment.
    4
    The trial court found the new evidence dispositive of Torres’s
    claims and granted the motion for summary judgment.
    DISCUSSION
    Torres raises two issues on appeal. First, he argues the
    trial court erred when it granted Design’s motion to reconsider
    the motion for summary judgment because Design did not show
    new or different facts since they were available to Design before
    the summary judgment hearing. Second, Torres claims by
    granting the motion to reconsider in the manner it did, the trial
    court deprived him of his due process right to respond to the new
    evidence. We offer no opinion on the merits of the first argument
    but find that the trial court abused its discretion by granting
    Design’s motion for reconsideration under section 1008,
    subdivision (a) when it was essentially a renewed summary
    judgment motion subject to the requirements of section 437c.
    Section 1008, subdivision (a) allows a party to move for
    reconsideration of a prior order based on new or different facts or
    a change in law. If the motion to reconsider is based on new
    facts, the moving party must provide a satisfactory explanation
    for its failure to produce the evidence at an earlier time. (Shiffer
    v. CBS Corp. (2015) 
    240 Cal. App. 4th 246
    , 255.) We review the
    trial court’s ruling on a motion for reconsideration for abuse of
    discretion. (New York Times Co. v. Superior Court (2005) 
    135 Cal. App. 4th 206
    , 212.)
    As an initial matter, we offer no opinion on whether Design
    provided a satisfactory explanation for its failure to produce the
    evidence at an earlier time. For our purposes here, we presume
    the trial court was satisfied with Design’s explanation.
    Our concern, however, is that if we affirm the trial court’s
    ruling, we would endorse a procedural bypass to the due process
    5
    protections afforded a party opposing summary judgment under
    section 437c. While Design technically moved for reconsideration
    within the 10-day period under section 1008, subdivision (a), it
    was, in effect, a renewed motion for summary judgment under
    section 1008, subdivision (b) or section 437c, subdivision (f)(2).
    (See Graham v. Hansen (1982) 
    128 Cal. App. 3d 965
    , 970.)
    Therefore, Torres was entitled to the procedural protections
    afforded to parties opposing summary judgment, including
    75 days’ notice and a separate statement of material facts.
    (§ 437c, subds. (a)(2) & (b)(1); see UAS Management, Inc. v. Mater
    Misericordiae Hospital (2008) 
    169 Cal. App. 4th 357
    , 367;
    Schachter v. Citigroup, Inc. (2005) 
    126 Cal. App. 4th 726
    , 737–
    738.) By granting the motion for reconsideration and then
    summary judgment at the same time, the trial court failed to
    enforce these protections and abused its discretion.
    DISPOSITION
    The judgment is reversed. Ismael Torres, Jr., is awarded
    his costs on appeal.
    CERTIFIED FOR PUBLICATION.
    DHANIDINA, J.
    We concur:
    EDMON, P. J.
    LAVIN, J.
    6
    

Document Info

Docket Number: B294220

Filed Date: 2/13/2020

Precedential Status: Precedential

Modified Date: 2/14/2020