Hensel Phelps Construction Co. v. Dept. of Corrections and Rehab. ( 2020 )


Menu:
  • Filed 1/28/20; Certified for publication 2/25/20 (order attached)
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    SECOND APPELLATE DISTRICT
    DIVISION FIVE
    HENSEL PHELPS                                       B293427
    CONSTRUCTION COMPANY,
    (Los Angeles County
    Plaintiff and Respondent,                   Super. Ct. No. BC630469)
    v.
    DEPARTMENT
    OF CORRECTIONS AND
    REHABILITATION,
    Defendant and Appellant.
    APPEAL from a judgment of the Superior Court of Los
    Angeles County, Susan Bryant-Deason, Judge. Affirmed in part,
    reversed in part and remanded with direction.
    Xavier Becerra, Attorney General, Thomas S. Patterson,
    Senior Assistant Attorney General, Tamar Pachter and Jose A.
    Zelidon-Zepeda, Deputy Attorneys General, for Defendant and
    Appellant.
    Watt, Tieder, Hoffar & Fitzgerald, David F. McPherson and
    Robert C. Shaia for Plaintiff and Respondent.
    Plaintiff Hensel Phelps Construction Company (Phelps)
    was the low bidder on a public works contract awarded by the
    California Department of Corrections and Rehabilitation (CDCR)
    through competitive bidding, and commenced work on the
    project. Another bidder challenged the award of the contract to
    Phelps, and was successful, obtaining a ruling in a San Diego
    trial court that Phelps’s bid was “non-responsive as a matter of
    law” due to its inclusion of “non-waivable
    mathematical/typographical errors.” Phelps then brought suit
    against CDCR, seeking to recover the costs it expended on the
    project, under a statute which allows for such relief only if the
    contract is “determined to be invalid due to a defect or defects in
    the competitive bidding process caused solely by the public
    entity.” (Pub. Contract Code, § 5110, italics added.)1 CDCR
    sought judgment on the pleadings, arguing that the San Diego
    trial court’s determination that the contract was invalid because
    Phelps’s bid was non-responsive as a matter of law precluded
    recovery. The trial court disagreed, held a bench trial, and
    concluded that the San Diego trial court’s ruling was itself the
    result of a defect in the competitive bidding process caused solely
    by CDCR. Judgment was entered in favor of Phelps. On CDCR’s
    appeal, we reverse, concluding judgment on the pleadings should
    have been granted. However, we affirm the trial court’s denial of
    recovery on CDCR’s cross-complaint for disgorgement.
    1    All undesignated statutory references are to the Public
    Contract Code.
    2
    FACTUAL AND PROCEDURAL BACKGROUND
    1.     The Award of the Contract to Phelps
    On March 17, 2015, CDCR issued an Invitation for Bid for
    the Ironwood State Prison Heating, Ventilation and Air
    Conditioning System – a project which was estimated to cost
    around $100,000,000.
    The deadline to submit bids was April 30, 2015 at 2:00 p.m.
    Phelps submitted its bid on time. The bids were opened, and
    Phelps was determined to be the “apparent low bidder” with a
    price of $88,160,000.
    On May 1, 2015, Phelps submitted an “amended bidder
    declaration.” The April 30 bid had included a bidder declaration
    containing information pertaining to subcontractors Phelps
    intended to use on the project. Among other things, the original
    bid declaration had indicated the percentage of the contract work
    to be done by each subcontractor; the amended bidder declaration
    changed these subcontractor percentages.
    Phelps believed it was permitted to submit its amended
    bidder declaration on May 1. During the bid process, prospective
    bidders had submitted questions to CDCR, which it answered in
    writing via amendments to the invitation to bid; in this way, all
    of the prospective bidders had access to the same information. It
    is undisputed that CDCR had issued an amendment containing a
    question and answer which permitted bidders to supply certain
    subcontractor information 24 hours after the bid deadline (the
    “Q24 answer”). What was disputed was whether the information
    that could be submitted a day late included the subcontractor
    percentages.2
    2    Phelps’s witness testified that allowing it to submit
    subcontractor percentages after the bid deadline enabled it to
    3
    CDCR took the position that subcontractor percentages
    could not, in fact, be changed by amended bidder declaration. It
    rejected Phelps’s May 1, 2015 submission, and ultimately mailed
    it back to Phelps. Phelps was not immediately informed of the
    rejection, however.
    In the meantime, on May 6, West Coast Air Conditioning
    Company, the second-lowest bidder, sent CDCR a complaint
    letter regarding Phelps’s bid. CDCR did not review it, believing
    that it had no jurisdiction to hear bid protests.
    Phelps was informed on May 13, 2015 that its May 1, 2015
    amended bidder declaration was rejected. That same day, CDCR
    issued a notice of intent to award the project to Phelps. Phelps
    executed the contract on May 18, 2015. The Phelps vice-
    president who signed the contract testified that, when he did so,
    he understood that CDCR had rejected the May 1 submission.
    Nonetheless, he signed the contract, based on the April 30 bid
    alone, believing that the incorrect subcontractor percentages in
    the April 30 bidder declaration constituted an “immaterial
    deviation” which could be waived by CDCR.
    2.     The San Diego Proceedings Commence
    On May 22, 2015, West Coast filed a petition for writ of
    mandate in the San Diego Superior Court seeking to invalidate
    the contract and prohibit Phelps from constructing the project.
    obtain the best possible deal from its subcontractors, and
    therefore submit the best price it could for the project. That is,
    its subcontractors were permitted to wait until just before the bid
    deadline to submit their best prices to Phelps. Phelps
    incorporated those prices into its bottom line total bid price, but
    did not have time to update the math in its calculation of the
    percentages in its bidder declaration by the deadline.
    4
    In that proceeding, CDCR was the respondent and Phelps was
    the real party in interest.
    3.     Construction Begins
    As we shall discuss, section 5110 provides that when the
    award of a public contract is challenged, the contract may be
    entered into pending final decision of the challenge. On July 3,
    2015, CDCR executed the contract. On July 7, 2015, it issued a
    notice to proceed to Phelps. That day, Phelps began work on the
    project.
    While the San Diego court proceedings were ongoing,
    Phelps continued to work on the project. The parties stipulated
    that CDCR approved and paid Phelps’s first three pay
    applications, in the total amount of $3,510,180.64.
    4.     The San Diego Court Invalidates the Contract
    On September 11, 2015, the San Diego court issued its
    minute order on West Coast’s mandamus cause of action. The
    order explained that West Coast sought to have the award of the
    contract to Phelps set aside for two reasons: (1) Phelps’s bid was
    non-responsive because it failed to list license numbers for its
    subcontractors; and (2) Phelps’s bid “contained numerous
    arithmetical/typographical mistakes which required CDCR to
    reject [Phelps]’s bid as non-responsive because of these admitted
    errors which, according to West Coast, afforded [Phelps] a
    competitive advantage.” The court explained that errors which
    might otherwise render a bid non-responsive, requiring rejection
    of the bid, can be waived only if they could not have affected the
    price and could not have resulted in an advantage or benefit not
    allowed other bidders. Under this standard, the San Diego court
    concluded the first error – the failure to list license numbers –
    was waivable and therefore immaterial. The second error,
    5
    however, was not. The court stated that it was “undisputed that
    the [Phelps] bid contained mathematical errors.” Phelps “argues
    that the errors were not material and . . . that, in essence, the
    defects could be waived.” The court disagreed, finding that the
    changes encompassed not only “immaterial percentages” but
    “certain subcontractor price amounts.” It held these changes
    material and, therefore, not waivable.
    On October 5, 2015, the San Diego court issued a
    temporary restraining order, halting work on the project except
    work necessary to make the worksite safe (e.g., capping pipes,
    backfilling open excavations).
    On December 9, 2015, the San Diego court issued its
    statement of decision to the same effect as its prior minute order.
    The court’s findings of fact included the following. “[Phelps]’s bid
    contained numerous mathematical errors. [Phelps] admitted the
    subcontractor percentages listed in its bid were not accurate or
    consistent. [Phelps] further admitted it submitted a
    subcontractor information form after bid day which was intended
    to correct the subcontractor percentage and dollar amount errors
    in [Phelps]’s bid.” “[Phelps] argued the
    mathematical/typographical errors in its bid were immaterial
    errors because although [Phelps]’s post-bid day form changed the
    percentage of work to be performed by certain subcontractors, it
    did not change [Phelps]’s total bid price. However, the evidence
    shows that [Phelps]’s post-bid subcontractor information form
    changed certain subcontractor prices, including the prices for
    subcontractors Graham Prewitt and Pacific Coast Iron, and that
    the bid day information for subcontractors was internally
    inconsistent in several respects as set forth in the declaration by
    [a witness].” The court noted that Graham Prewitt’s true price,
    6
    as reflected in the May 1 amended bidder declaration was
    $1,644,800 “more than the subcontract price stated by Graham
    Prewitt itself in a different portion of [Phelps]’s bid day bid
    submission.” The court identified a similar $731,520 difference
    between Pacific Coast Iron’s actual price (as stated in the May 1
    amended bidder declaration) and Pacific Coast Iron’s form
    included in the original bid. The court stated that “in at least
    four instances, [Phelps]’s subcontractor percentage listings (both
    on bid day and in the form submitted after bid day), are
    inconsistent with the subcontract prices (in dollars) listed in
    other parts of [Phelps]’s bid.” In its conclusions of law, the court
    found these errors to be non-waivable.
    Judgment was not entered until June 8, 2016. This was
    because West Coast had an additional cause of action against
    CDCR, for recovery of its bid expenses in promissory estoppel,
    which was tried in the interim, and resolved in favor of West
    Coast. The judgment permanently enjoined CDCR and Phelps
    from performing any further work on the project under the
    contract.
    Phelps did not appeal, making the determination that it
    would instead pursue CDCR for its costs of construction in this
    action.
    CDCR appealed only the promissory estoppel award in
    favor of West Coast; Phelps was not a party to that appeal. (West
    Coast Air Conditioning Co., Inc. v. Department of Corrections &
    Rehabilitation (2018) 21 Cal.App.5th 453, 456, fn. 2.)
    5.     The Pleadings in This Case
    On August 12, 2016, Phelps filed its complaint against
    CDCR in this case, bringing a cause of action based on section
    7
    5110.3 Subdivision (a) of that statute provides, in pertinent part,
    “When a project for the construction, alteration, repair, or
    improvement of any structure, building, or road, or other
    improvement of any kind is competitively bid and any intended or
    actual award of the contract is challenged, the contract may be
    entered into pending final decision of the challenge, subject to the
    requirements of this section. If the contract is later determined
    to be invalid due to a defect or defects in the competitive bidding
    process caused solely by the public entity, the contractor who
    entered into the contract with the public entity shall be entitled
    to be paid the reasonable cost, specifically excluding profit, of the
    labor, equipment, materials, and services furnished by the
    contractor prior to the date of the determination that the contract
    is invalid if [certain] conditions are met.”4
    Relying on section 5110 and the invalidation of the
    contract, Phelps sought its unpaid costs on the project. It alleged
    that the contract was “determined to be invalid by the San Diego
    Superior Court as a direct result of CDCR’s actions and decisions
    during the competitive bidding process.”
    CDCR responded with a cross-complaint, pleading a cause
    of action for money had and received. Specifically, CDCR alleged
    3    Phelps also brought a cause of action for declaratory relief
    founded on section 5110.
    4      These conditions are that the contractor proceeded in good
    faith, the public entity reasonably determined the work was
    satisfactory, there was no contractor fraud, and the contract does
    not otherwise violate statutory or constitutional limitations.
    (§ 5110, subds. (a)(1)-(a)(4).) The trial court found that all of
    these conditions were satisfied, and CDCR does not challenge
    that determination on appeal.
    8
    that it had paid Phelps approximately $3.5 million on a contract
    which had since been determined to be void. As a public entity, it
    was permitted to recover those funds.
    6.     Motion for Judgment on the Pleadings
    Relying on the San Diego court’s rulings, CDCR moved for
    judgment on the pleadings with respect to Phelps’s complaint.5
    CDCR argued that Phelps could only prevail on its section 5110
    cause of action if it established that the contract was invalidated
    “[d]ue to a defect or defects in the competitive bidding process
    caused solely by” CDCR. It could not do so, because the San
    Diego court had in fact invalidated the contract because Phelps’s
    bid contained material non-waivable errors.
    Phelps’s opposition argued that the San Diego court’s
    invalidation of the contract was simply a prerequisite to this
    action. It argued that the contract was, in fact, invalidated due
    to a defect in the bidding process chargeable to CDCR –
    specifically, “CDCR’s failure to find [Phelps’s] bid
    non[-]responsive in response to West Coast’s bid protest (or to
    take any action whatsoever in response to West Coast’s bid
    protest and subsequent [p]etition on the same grounds) and
    CDCR’s decision to award the contract to [Phelps].” Phelps
    conceded that it had made a mathematical error in its bid, but
    argued that the “focus of section 5110” is not on “the error in the
    bid itself” but the “ ‘competitive bidding process.’ ” Phelps
    explained, “Mathematical bid errors occur frequently, but if the
    public owner rejects the error, then there is no ‘defect in the
    competitive bidding process.’ In fact, under those proper
    5     CDCR’s motion did not address its cross-complaint; its
    points and authorities stated it was “directed to both the first and
    second causes of action[] of [Phelps’s] complaint.”
    9
    circumstances, the competitive bidding process works correctly.
    The defect in the competitive bidding process in this case
    occurred, as recognized by the San Diego Superior Court, at the
    time the CDCR failed to acknowledge, evaluate, and reject
    [Phelps’s] mathematical bid error, awarded the contract to
    [Phelps], and directed [Phelps] to perform work pursuant to that
    contract. That defect was caused solely by CDCR.”
    The trial court denied the motion for judgment on the
    pleadings, on the basis that Phelps’s allegations were “sufficient
    to establish a factual dispute as to whether [CDCR] was the sole
    cause of the defect in the bidding process, as [CDCR] allegedly
    should have rejected [Phelps]’s bid.”
    7.     Motion in Limine
    The case proceeded to a bench trial. CDCR attempted to
    relitigate the issue from its motion for judgment on the pleadings
    in a motion in limine to preclude all evidence except the San
    Diego court’s statement of decision. CDCR added the argument
    that, even if Phelps were correct and there was some sort of
    defect in its process, the fact that the San Diego court found that
    there were errors in Phelps’s bid meant that CDCR was not the
    sole cause of the bid invalidation.
    In opposition, Phelps reasserted its argument that the San
    Diego court resolved only whether there was an error in Phelps’s
    bid – not whether there were defects in the bidding process and
    which party had caused them. Phelps asserted, for the first time,
    two supposed defects in the bidding process attributable to
    CDCR: (1) it improperly rejected Phelps’s May 1 amended bid
    declaration – had it accepted it, the contract would not have been
    invalidated; and (2) it did not inform Phelps that it had rejected
    the May 1 submission until after the statutory period for seeking
    10
    relief from a mistaken bid had lapsed (see § 5103 [five working
    days from bid opening]).
    The first argument became Phelps’s new theory of the case.
    Phelps asserted, “Our position in this case and the crux of this
    case is the defect in the competitive bidding process that was
    caused by CDCR is their rejection of the May 1st submission.”
    Phelps took the position that the San Diego court “only
    determined that the April 30th portion of the bid was
    non[-]responsive. It did not determine which party was at fault
    for that. In this action we will prove that it was the fault of the
    CDCR when they refused to accept the May 1st supplemental
    submission; that’s what resulted in the April 30th portion of the
    bid being deemed non[-]responsive.”
    The court denied the motion in limine, and proceeded to
    trial.
    8.     The Bench Trial
    A seven-day bench trial was held, in which percipient and
    expert witnesses testified to the bid process and CDCR’s review
    of Phelps’s bid. The parties stipulated to the costs which would
    be recoverable by Phelps under section 5110 if it prevailed on its
    cause of action.
    The trial court ruled in favor of Phelps.
    9.     The Statement of Decision
    The court’s statement of decision first rejected CDCR’s
    argument that the San Diego court’s ruling controlled the result
    in this case. The court explained: “[T]he issues under PCC
    § 5110 that were resolved in this action were not raised,
    addressed or adjudicated in the [p]etition proceeding in the San
    Diego Superior Court. Specifically, the San Diego Superior Court
    did not address or adjudicate whether ‘defects’ existed in the
    11
    ‘competitive bidding process.’ Also, it did not address or
    adjudicate whether the [c]ontract invalidation was due to any
    defects or which party caused those defects. The San Diego
    Superior Court addressed a very limited and singular issue:
    Whether [Phelps’s] April 30, 2015 bid submission was non-
    responsive. The San Diego Superior Court did not consider all of
    [the] documents comprising [Phelps’s] bid as a result of defects in
    the competitive bidding process caused solely by CDCR.”6
    Specifically, the court found that Phelps’s bid “lawfully
    consisted” of both the April 30 bid and the May 1 amended bidder
    declaration, and, as constituted, “fully complied” with the bid
    solicitation. The court found that CDCR erred in rejecting the
    May 1 amended bidder declaration and that, if it had accepted it,
    the contract would not have been invalidated by the San Diego
    court. However, the court also stated, “The only other possible
    scenario is where the CDCR properly accepts the May 1 Amended
    Bidder Declaration and includes that document in its review of
    the [Phelps] bid, as opposed to replacing the April 30 bidder
    declaration with the May 1 Amended Bidder Declaration. Under
    this scenario, 100 [percent] of the bid documents submitted by
    [Phelps] would be reviewed as one package by [CDCR]. The
    evidence submitted at trial confirms that [agents of CDCR]
    performed this exact review and concluded that the changed
    6      The court identified six defects in the competitive bidding
    process it charged to CDCR: failure to follow its own Q24 answer
    in rejecting the May 1 submission; failure to timely notify Phelps
    it rejected the May 1 submission, failure to follow its own bid
    review protocol; failure to follow its contracting guidelines;
    violation of its own policy by issuing the Q24 answer; and failure
    to follow its bid protest protocol.
    12
    percentages in the May 1 Amended Bidder Declaration
    constituted a material deviation. Where a material deviation is
    found, the entire bid must be rejected. Thus, under this second
    scenario, the [c]ontract would not have been awarded to
    [Phelps].”
    The statement of decision also addressed the cross-
    complaint, denying it “in its entirety.”
    10. Judgment and Appeal
    Judgment was entered in favor of Phelps in the amount of
    $2,989,819.35, the difference between the stipulated amount and
    the payments CDCR made. CDCR took nothing on its cross-
    complaint. Prejudgment and post-judgment interest were also
    awarded.
    CDCR filed a timely notice of appeal.
    DISCUSSION
    On appeal, CDCR specifically disclaims any challenge to
    the court’s findings after trial. It argues only that the court
    erred, as a matter of law, in denying its motion for judgment on
    the pleadings. It also seeks judgment on its cross-complaint.
    1.     Standard of Review
    A motion for judgment on the pleadings may be made on
    the same ground as a general demurrer, that the pleading at
    issue fails to state facts sufficient to constitute a legally
    cognizable claim or defense. (Code Civ. Proc., § 438, subd.
    (c)(1)(B)(ii).) Our review is guided by the same rules governing
    the review of the sustaining of a general demurrer. “ ‘We treat
    the demurrer as admitting all material facts properly pleaded,
    but not contentions, deductions or conclusions of fact or law.
    [Citation.] We also consider matters which may be judicially
    noticed.’ [Citation.] Further, we give the complaint a reasonable
    13
    interpretation, reading it as a whole and its parts in their
    context. [Citation.]” (Blank v. Kirwan (1985) 
    39 Cal. 3d 311
    ,
    318.)
    2.     Interpretation of Section 5110
    The issue presented by this appeal is actually a simple one.
    Section 5110 provides for recovery if, among other things, “the
    contract is later determined to be invalid due to a defect or
    defects in the competitive bidding process caused solely by the
    public entity.” Does this language mean recovery is possible if
    “the contract is invalidated for a defect or defects in the
    competitive bidding process caused solely by the public entity”?
    Or does it mean that the contractor may recover if, “after the
    contract is invalidated, it is determined that the invalidation
    finding itself was due to a defect or defects in the competitive
    bidding process caused solely by the public entity”? CDCR
    argues for the former interpretation; Phelps the latter.
    This is a question of statutory interpretation. “ ‘In
    statutory construction cases, our fundamental task is to ascertain
    the intent of the lawmakers so as to effectuate the purpose of the
    statute. [Citation.] “We begin by examining the statutory
    language, giving the words their usual and ordinary meaning.”
    [Citations.] If the terms of the statute are unambiguous, we
    presume the lawmakers meant what they said, and the plain
    meaning of the language governs. [Citations.] If there is
    ambiguity, however, we may then look to extrinsic sources,
    including the ostensible objects to be achieved and the legislative
    history. [Citation.] In such cases, we “ ‘ “select the construction
    that comports most closely with the apparent intent of the
    Legislature, with a view to promoting rather than defeating the
    general purpose of the statute, and avoid an interpretation that
    14
    would lead to absurd consequences.” ’ ” [Citation.]’ [Citation.]”
    (Marshall v. Pasadena Unified School Dist. (2004)
    
    119 Cal. App. 4th 1241
    , 1254.)
    “Statutes and ordinances that authorize or require
    competitive bidding in the letting of public contracts ordinarily
    serve the purpose ‘ “of inviting competition, to guard against
    favoritism, improvidence, extravagance, fraud and corruption,
    and to secure the best work or supplies at the lowest price
    practicable.” ’ Such measures ‘are enacted for the benefit of
    property holders and taxpayers, and not for the benefit or
    enrichment of bidders, and should be so construed and
    administered as to accomplish such purpose fairly and reasonably
    with sole reference to the public interest. These provisions are
    strictly construed by the courts, and will not be extended beyond
    their reasonable purpose.’ ” (Eel River Disposal & Resource
    Recovery, Inc. v. County of Humboldt (2013) 
    221 Cal. App. 4th 209
    ,
    232, citations omitted.)
    A.    The Statutory Language
    Turning to the language itself, we conclude CDCR has the
    better argument. We must consider the key language in the
    context of the rest of the statute. The first sentence of section
    5110, subdivision (a) provides, “When a project for [a public work]
    is competitively bid and any intended or actual award of the
    contract is challenged, the contract may be entered into pending
    final decision of the challenge, subject to the requirements of this
    section.” It is the next sentence which provides, “If the contract
    is later determined to be invalid due to a defect or defects in the
    competitive bidding process caused solely by the public entity,
    [the contractor may recover].” The “later” in this sentence must
    refer back to the “pending final decision of the challenge” in the
    15
    sentence immediately preceding. In other words, the subdivision
    provides that the parties to a challenged public contract may
    enter into that contract pending final resolution of the challenge,
    but if the challenge is resolved by invalidation because the public
    entity was at fault, the contractor may recover.
    Phelps’s alternative construction is not reasonable. Phelps
    would interpret the statute to involve two distinct legal
    proceedings: (1) a challenge to the contract, which may result in
    the court invaliding the contract for any number of reasons; and
    (2) a second proceeding which looks beyond the reasons given for
    invalidation, to determine whether the court’s invalidation of the
    contract was caused by any defects in the bidding process caused
    by the public entity. Nothing in the statutory language suggests
    there is to be a second proceeding, to consider the reasons for the
    first court’s ruling.
    We are also mindful of interpreting competitive bidding
    statutes in a manner which best comports with their purpose of
    benefitting property holders and taxpayers, not enriching
    bidders. An interpretation which precludes further contractor
    recovery once a court has invalidated the contract for reasons not
    solely chargeable to the public entity furthers this purpose.
    B.     The Legislative History
    Section 5110’s legislative history confirms the payment
    obligation under the statute rises and falls with the reasons given
    by the court actually invalidating the contract.
    Prior to the enactment of section 5110, all risk of public
    contract invalidation was borne by the contractor. This was
    because compliance with competitive bidding statutes is
    mandatory, and when a contract was made without statutory
    compliance, it was “void and unenforceable as being in excess of
    16
    the agency’s power.” (Miller v. McKinnon (1942) 
    20 Cal. 2d 83
    ,
    87–88.) Such contracts “ ‘cannot be ratified; no estoppel to deny
    their validity can be invoked against the municipality; and
    ordinarily no recovery in quasi contract can be had for work
    performed under them.’ ” (Id. at p. 88.) Under prior law, even if
    the contractor supplied labor and materials in the performance of
    the contract, no quantum meruit recovery was possible. (Ibid;
    see also Amelco Electric v. City of Thousand Oaks (2002)
    
    27 Cal. 4th 228
    , 234–235.) Although this often would create a
    hardship on the contractor, the rule was justified on the theory
    that, when a public entity is legally prohibited from making a
    contract, there is no practical public benefit achieved by allowing
    contractor recovery when the prohibition is disregarded. 
    (Miller, supra
    , 20 Cal.2d at pp. 88–89.) Moreover, the contractor was
    considered just as bound as the public entity to ensure that the
    law’s requirements were met. If the contractor neglected this
    duty or chose to take the risk, the contractor was considered a
    mere volunteer. In short, if the contract was legally forbidden,
    the law took the position that the contractor knew – or should
    have known – of this, and suffered losses it should have
    anticipated. (Id. at p. 89.)
    Section 5110 was enacted as a limited exception to this
    rule, in 2004. The legislation was sponsored by the Construction
    Employers’ Association, which felt trapped between two
    principles: (1) a contractor on a public works contract later found
    to be void could be required to reimburse the public agency
    regardless of fault; and (2) a contractor must pay its
    subcontractors regardless of whether the contractor is paid by the
    project owner. (Sen. Com. on Judiciary, Analysis of Assem. Bill
    No. 453 (2003-2004 Reg. Sess.) July 1, 2003, p. 3.)
    17
    As introduced, the bill allowed for recovery “[i]f the contract
    is later determined to be invalid due to a defect or defects in the
    competitive bidding process . . . .” There was no limitation based
    on which party or parties were responsible for the defects.
    (Assem. Bill No. 453 (2003-2004 Reg. Sess.) as introduced
    Feb. 14, 2003.) It was understood that the bill would “allow a
    contractor who has acted in good faith to recoup his or her costs if
    a contract is invalidated, because a public agency could otherwise
    refuse payment regardless of whether or not the agency or the
    contractor was at fault. Such a case has not yet arisen, but the
    sponsor is concerned that there is nothing to stop a cash-strapped
    public agency from doing so.” (Assem. Com. on Business and
    Professions, Analysis of Assem. Bill No. 453 (2003-2004 Reg.
    Sess.) Apr. 29, 2003, p. 2.)
    The bill was amended in the Senate on June 26, 2003 to
    add the language at issue in this case. It allows for recovery “[i]f
    the contract is later determined to be invalid due to a defect or
    defects in the competitive bidding process caused solely by the
    public entity . . . .” (Assem. Bill. No. 453 (2003-2004 Reg. Sess.)
    as amended June 26, 2003, italics added.)
    A subsequent committee analysis indicated that, in
    opposition to the bill, the League of California Cities argued that
    it had been the law in California for a century that there can be
    no payments on void public contracts. “Supporters respond that
    the issue presented by the bill is one of fundamental fairness. If
    a contract is invalidated solely due to the fault of the agency,
    supporters argue, the contractor who relied upon the contract in
    good faith should be entitled to payment on work already done.”
    (Sen. Com. on Judiciary, Analysis of Assem. Bill No. 453 (2003-
    2004 Reg. Sess.) July 1, 2003, pp. 4–5.)
    18
    In short, in enacting section 5110, the Legislature agreed to
    provide an exception to established law that had placed all the
    risk of public contract invalidation on the contractor. As
    originally proposed, the exception applied in all cases in which a
    contract was entered into while a challenge was pending and the
    contract was ultimately determined to be invalid due to a defect
    in the bidding process. As eventually enacted, the exception was
    limited to those cases where that defect was solely the fault of the
    public entity. But it is the defect for which the contract is
    invalidated – not the invalidation itself – which must be the fault
    of the public entity.
    3.     Application
    Applying this interpretation of section 5110 to this case, it
    is apparent that CDCR’s motion for judgment on the pleadings
    should have been granted. The motion was supported by a
    request for judicial notice of the relevant documents from the San
    Diego case – which indicated that the contract between CDCR
    and Phelps was invalidated “[b]ecause [Phelps]’s bid contained
    non-waivable mathematical/typographical errors” which rendered
    it non-responsive. In short, the contract was invalidated for a
    material error in Phelps’s bid, not for any “defect . . . in the
    competitive bidding process,” much less a defect “caused solely
    by” CDCR. Section 5110 cannot provide a basis for recovery.
    In opposition to the motion for judgment on the pleadings,
    Phelps argued that, while the San Diego court found a material
    error in the bid, the focus of section 5110 is not on the errors in
    the bid but on the competitive bidding process. Phelps argued
    that it would establish that CDCR’s failure to recognize and
    reject Phelps’s mathematical bid error, and its subsequent award
    of the contract to Phelps, was an error in the competitive bidding
    19
    process caused solely by CDCR. In other words, Phelps argued
    that the error in its bid was irrelevant, because all that mattered
    were defects in the competitive bidding process, and the only
    defect in the competitive bidding process was CDCR’s failure to
    reject Phelps’s materially-flawed bid.
    Even if we were to agree that CDCR were at fault to some
    degree for failing to reject Phelps’s flawed bid, it was at a
    minimum the combination of Phelps’s flawed bid and CDCR’s
    failure to reject it which resulted in an invalid contract. But
    Phelps can only recover under section 5110 if the invalidation
    was due to a defect in the bidding process caused solely by CDCR;
    it cannot recover if the contract was invalidated for reasons that
    were even partly its own fault. The San Diego trial court’s ruling
    establishes Phelps was at fault.
    4.      Collateral Estoppel Confirms the Result
    Viewed as an application of the doctrine of collateral
    estoppel, we reach the same result. “Issue preclusion prevents
    ‘relitigation of issues argued and decided in prior proceedings.’
    [Citation.] The threshold requirements for issue preclusion are:
    (1) the issue is identical to that decided in the former proceeding,
    (2) the issue was actually litigated in the former proceeding,
    (3) the issue was necessarily decided in the former proceeding,
    (4) the decision in the former proceeding is final and on the
    merits, and (5) preclusion is sought against a person who was a
    party or in privity with a party to the former proceeding.
    [Citation.] When those requirements are met, the propriety of
    preclusion depends upon whether application will further the
    public policies of ‘preservation of the integrity of the judicial
    system, promotion of judicial economy, and protection of litigants
    20
    from harassment by vexatious litigation.’ [Citation.]” (Castillo v.
    City of Los Angeles (2001) 
    92 Cal. App. 4th 477
    , 481.)
    Each factor is established. (1) The issue is identical. The
    San Diego court determined whether the contract must be
    invalidated on any basis alleged by West Coast; in this case, the
    issue is on what basis the contract was invalidated. (2) The issue
    was actually litigated; the San Diego court rejected one of West
    Coast’s proferred bases for invalidating the contract (omission of
    subcontractor license numbers) but accepted the other (material
    mathematical errors). (3) The issue was necessarily decided; it
    was not unnecessary to the prior proceeding. The San Diego
    court could not have invalidated the contract without
    determining on what basis, if any, the contract had to be
    invalidated. (4) The decision in the prior proceeding is final and
    on the merits. CDCR appealed a portion of the judgment relating
    to West Coast, but the parties chose not to appeal the
    invalidation of the contract. (5) Phelps was a party in the prior
    action; it was the real party in interest. Additionally, the public
    policies of preservation of the integrity of the judicial system and
    promotion of judicial economy are advanced by the application of
    collateral estoppel. It is difficult to believe the integrity of the
    judicial system would be advanced if, after the San Diego court
    held that the contract must be invalidated for a material error in
    Phelps’s bid, the Los Angeles court could hold, to the contrary,
    that Phelps was actually blameless for the invalidation.
    5.     Phelps’s Late-Raised Alternative Ground
    Although we have determined that judgment on the
    pleadings should have been granted based on the evidence before
    the court and the arguments made at the time, we briefly address
    the alternative theory first raised by Phelps in opposition to the
    21
    motion in limine, on which the trial court ultimately relied. The
    trial court found that the San Diego court’s invalidation of the
    contract was itself due to a defect in the bid process caused solely
    by CDCR: its improper rejection of the May 1st amended bidder
    declaration.
    First, as we have discussed, the statute simply asks why
    the contract was invalidated, and allows relief only if the contract
    was invalidated due to a defect in the bidding process caused
    solely by the public entity. If, as in this case, the contract was
    not invalidated for a defect in the bidding process caused by the
    entity, but instead for a non-responsive bid, that ends the
    inquiry.
    Second, Phelps’s theory at trial, which was also adopted by
    the trial court, was based on the premise that the only reason the
    San Diego court invalidated its bid was because of the errors in
    its April 30 bidder declaration which were corrected in the May 1
    amended bidder declaration. But this is belied by the San Diego
    court’s statement of decision, which states, “in at least four
    instances, [Phelps]’s subcontractor percentage listings (both on
    bid day and in the form submitted after bid day), are inconsistent
    with the subcontractor prices (in dollars) listed in other parts of
    [Phelps]’s bid.” The court specifically identified the prices of two
    subcontractors which were materially different between not only
    the bidder declaration and the amended bidder declaration, but
    other documents in the bid and the amended bidder declaration.
    In other words, the San Diego court invalidated the contract for
    errors which would not have been remedied even if the May 1
    amended bidder declaration had replaced the original bidder
    declaration.
    22
    Third, recovery under section 5110 is only possible when
    certain other requirements are met, including that the contractor
    “proceeded with construction . . . based upon a good faith belief
    that the contract was valid.” The trial court found that Phelps
    acted in good faith, based on testimony from Phelps’s vice-
    president that when he signed the contract on behalf of Phelps,
    he knew CDCR had rejected the May 1 amended bidder
    declaration, but believed the April 30 bid standing alone
    contained only immaterial, waivable errors. In other words,
    knowing that CDCR had rejected the May 1 amended bidder
    declaration – for whatever reason, proper or improper – both
    CDCR and Phelps believed in good faith that the April 30 bid
    standing alone was sufficiently responsive to support an award of
    the contract. That the trial court in this case ultimately
    concluded CDCR should not have rejected the May 1 submission
    is irrelevant; Phelps, with its eyes open, nonetheless agreed to
    risk the contract on the April 30 bid alone.7 It was therefore
    partly responsible.8
    7      The trial court’s finding that CDCR improperly delayed in
    informing Phelps that its May 1 amended bidder declaration was
    rejected means little without testimony that Phelps would have
    withdrawn its bid entirely had it timely been informed of the
    rejection. There was no such testimony; it likely would have been
    contradictory to the testimony that Phelps believed the April 30
    bid contained only immaterial errors.
    8    Because we conclude the judgment in favor of Phelps on its
    complaint must be reversed, Phelps is no longer entitled to pre-
    and post-judgment interest. We therefore need not address any
    of CDCR’s challenges to the calculation of these amounts.
    23
    6.     The Cross-Complaint
    On appeal, CDCR asks that we not only direct entry of
    judgment in its favor on the complaint, but “remand for entry of
    judgment” for CDCR on its cross-complaint for recovery of monies
    CDCR already paid to Phelps under the contract.
    We question the procedure by which we can direct such
    judgment be entered. CDCR did not move for judgment on the
    pleadings on its cross-complaint. Although the trial court
    resolved the cross-complaint against CDCR at trial, CDCR has
    expressly chosen not to address the court’s findings following the
    bench trial.
    CDCR’s argument on appeal seems limited to: (1) the legal
    proposition that, in the absence of section 5110, when the public
    contract is invalid, the contractor must disgorge payments made;
    (2) the San Diego court invalidated the contract; and (3) the
    parties stipulated to the amount of the payments CDCR made.
    CDCR argues that, in these circumstances, it has a right of action
    for recoupment. We do not question that CDCR had a right of
    action; our concern is that it is not pursuing any adverse
    disposition of that right of action on this appeal.
    As CDCR never sought judgment on the pleadings on its
    cross-complaint; and can point to no stipulation that its cross-
    complaint rises and falls with the complaint, we cannot simply
    direct judgment in favor of CDCR.9
    9      Prior to the bench trial, the parties contemplated a jury
    trial. CDCR did not believe it would be necessary to submit the
    cross-complaint to the jury, taking the position that if it prevailed
    on the complaint, it would necessarily be entitled to recoupment.
    Phelps wanted the issue to go to the jury. The court asked
    CDCR’s counsel, “If you were to get the verdict on their case, then
    24
    Although our disposition may seem hypertechnical, there is
    some equity to this result. The evidence reflects that some
    amount of the work done by Phelps was not work pursuant to the
    void contract, but work done to make the worksite safe after the
    San Diego court issued its injunction. CDCR has made no
    argument that Phelps performed that work as a volunteer, and is
    not entitled to retain any funds to compensate it for its
    substantial efforts returning the worksite to a safe condition.
    We conclude that CDCR is not entitled to judgment on its
    cross-complaint, as it has not properly challenged the trial court’s
    ruling on the cross-complaint.
    DISPOSITION
    The judgment is affirmed in part and reversed in part. The
    matter is remanded with directions to the trial court to vacate its
    order denying CDCR’s motion for judgment on the pleadings on
    Phelps’s complaint and to enter a new and different order
    granting the motion. The judgment is affirmed to the extent it
    denies CDCR recovery on its cross-complaint. The parties shall
    pay their own costs on appeal.
    RUBIN, P. J.
    I CONCUR:
    KIM, J.
    if you don’t have a cross-complaint, then how do you get
    disgorgement? Is there something in the code that automatically
    gives it to you?” CDCR’s counsel responded, “No.” The court
    said, “So then, you do have to have a cross-complaint.”
    25
    Hensel Phelps Construction Company v. California Department
    of Corrections and Rehabilitation
    B293427
    BAKER, J., Concurring
    I join the opinion for the court with the exception of Part 4
    of the Discussion.
    BAKER, J.
    Filed 2/25/20
    CERTIFIED FOR PUBLICATION
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    SECOND APPELLATE DISTRICT
    DIVISION FIVE
    HENSEL PHELPS                              B293427
    CONSTRUCTION COMPANY,
    (Los Angeles County
    Plaintiff and Respondent,    Super. Ct. No. BC630469)
    v.                                 ORDER CERTIFYING OPINION
    FOR PUBLICATION AND
    CALIFORNIA DEPARTMENT                      DENYING PETITION FOR
    OF CORRECTIONS AND                         REHEARING
    REHABILITATION,
    [NO CHANGE IN JUDGMENT]
    Defendant and Appellant.
    THE COURT:
    GOOD CAUSE APPEARING, the opinion in the above-entitled matter
    filed on January 28, 2020, was not certified for publication in the Official
    Reports. For good cause, it now appears that the opinion should be published
    in the Official Reports and it is so ordered.
    There is no change in the judgment.
    Petition for rehearing is denied.
    ________________________________________________________________________
    RUBIN, P. J.                          BAKER, J.                 KIM, J.
    

Document Info

Docket Number: B293427

Filed Date: 2/25/2020

Precedential Status: Precedential

Modified Date: 2/26/2020