Volpe Co. v. Sausal Corp. CA1/5 ( 2021 )


Menu:
  • Filed 9/29/21 Volpe Co. v. Sausal Corp. CA1/5
    NOT TO BE PUBLISHED IN OFFICIAL REPORTS
    California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
    publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or
    ordered published for purposes of rule 8.1115.
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    FIRST APPELLATE DISTRICT
    DIVISION FIVE
    VOLPE CO., INC.,
    Plaintiff and Respondent,
    A157577, A159372
    v.
    SAUSAL CORP.,                                                          (Marin County
    Super. Ct. No. CIV1402511)
    Defendant and Appellant.
    Numerous laws regulate disputes between a primary contractor and its
    subcontractors in the construction of public projects. Two such laws are at
    issue in this case: Public Contract Code section 4107,1 which, among other
    things, regulates the authority of a prime contractor to substitute a new
    subcontractor in place of the subcontractor listed in the original bid; and
    Business and Professions Code section 7108.5, a prompt payment statute. In
    a jury trial, the plaintiff subcontractor prevailed on a breach of contract claim
    resting on section 4107, and a prompt payment claim, and was awarded
    prejudgment interest and attorney fees. We reverse judgment on the
    subcontractor’s breach of contract claim, direct modification of the award
    pursuant to the prompt payment statute, and remand for further
    proceedings.
    1   All undesignated section references are to the Public Contract Code.
    1
    BACKGROUND2
    In the summer of 2012, the City of Novato (City) awarded a contract to
    build a new City office building (Project) to Sausal Corporation (Prime
    Contractor). Prime Contractor entered into a subcontract (Contract) with
    Volpe Co., Inc. (Subcontractor) to perform grading, paving, and underground
    utility work on the Project, for a payment of approximately $400,000. Over
    the course of the Project, the Contract amount grew to more than $650,000
    because of change orders approved by the City.
    Subcontractor began work on the Project in August 2012. It continued
    working through the spring of 2013, and then paused its work on the Project
    as other Project work was performed. In late summer, Prime Contractor
    reached out to Subcontractor to schedule its return to the Project site. The
    Subcontractor’s return did not comply with the Prime Contractor’s
    timeframe, and the parties dispute the reasons for this. In September,
    Subcontractor did return but its work progressed more slowly than Prime
    Contractor wanted; the parties submitted conflicting evidence as to whether
    the delays were primarily due to Subcontractor’s failure to return to the
    Project sooner and to sufficiently staff the Project work when it did return, or
    to mistakes by other subcontractors and unforeseen conditions that impeded
    Subcontractor’s progress.
    In October 2013, Prime Contractor brought in another party, G.D.
    Nielson Construction (Nielson), to perform some of the work remaining on the
    Project. Subcontractor also continued to work on the Project in October and
    November. However, Prime Contractor did not pay Subcontractor for any of
    the work it performed following its return to the Project in September 2013.
    2We recite only those background facts relevant to our resolution of the
    appeals.
    2
    Prime Contractor took the position that Subcontractor owed it the amount it
    paid Nielson for work within the scope of the Contract, and that the amount
    it paid Nielson was greater than the remaining amount it owed to
    Subcontractor.
    In 2014, Subcontractor filed the underlying lawsuit for breach of
    contract and other claims. Following a jury trial, the jury found that Prime
    Contractor had breached the Contract, and that Subcontractor had incurred
    approximately $380,000 in damages. The jury also found that as of
    December 31, 2013, approximately $260,000 of this damages amount had
    been paid to Prime Contractor by the City for work performed by
    Subcontractor. Prime Contractor filed a motion for judgment
    notwithstanding the verdict or a new trial, which the trial court denied. The
    court granted Subcontractor’s motions for prejudgment interest, prompt
    payment penalties (Bus. & Prof. Code, § 7108.5), and attorney fees, and
    issued judgment for more than $1 million. Prime Contractor appealed
    separately from the judgment and the attorney fee order, and this court
    consolidated the appeals.3
    3 Subcontractor complains that Prime Contractor failed to provide
    Subcontractor with copies of the reporter’s transcripts designated as part of
    the record on appeal and suggests Prime Contractor improperly submitted
    these transcripts to this court. Prime Contractor’s designation of the record
    permissibly requested reporter’s transcripts be provided by the reporters.
    Pursuant to the Rules of Court, the reporter files the original and one copy of
    the requested transcripts with the superior court, which in turn provides the
    original to this court and the copy to the appellant. (Cal. Rules of Court,
    rules 8.130(f)(1), 8.150(a).) Prime Contractor was not obligated to provide
    Subcontractor with a copy. (See Eisenberg et al., Cal. Practice Guide: Civil
    Appeals and Writs (The Rutter Group 2021) ¶ 4:273 [“Respondent and other
    parties can make arrangements with the clerk and/or reporter to purchase
    additional copies of the record.”].)
    3
    DISCUSSION
    I.    Public Contract Code Section 4107
    The jury’s verdict finding Prime Contractor breached the Contract was
    based on a provision in Prime Contractor’s contract with the City,
    incorporated by reference into the Contract, obliging Prime Contractor to
    comply with section 4107. Section 4107 provides that a prime contractor may
    not “[s]ubstitute a person as subcontractor in place of the subcontractor listed
    in the original bid, except that the awarding authority, or its duly authorized
    officer, may . . . consent to the substitution of another person as a
    subcontractor in [certain enumerated situations],” with exceptions not
    relevant here. (§ 4107, subd. (a).) The statute further provides, “Prior to
    approval of the prime contractor’s request for the substitution, the awarding
    authority, or its duly authorized officer, shall give notice in writing to the
    listed subcontractor of the prime contractor’s request to substitute and of the
    reasons for the request. . . . The listed subcontractor who has been so notified
    has five working days within which to submit written objections to the
    substitution to the awarding authority. Failure to file these written
    objections constitutes the listed subcontractor’s consent to the substitution.
    [¶] If written objections are filed, the awarding authority shall give notice in
    writing of at least five working days to the listed subcontractor of a hearing
    by the awarding authority on the prime contractor’s request for substitution.”
    (Ibid.)
    Prime Contractor raises several arguments challenging the judgment
    in favor of Subcontractor on this claim. We agree with one of its arguments,
    and reverse and remand the breach of contract claim.
    4
    A.    Additional Factual Background
    Prime Contractor’s contract with the City included the following
    provision: “7.6. No Contractor whose Bid is accepted shall, without consent of
    the awarding authority and in full compliance with section 4100, et seq, of
    the Public Contract Code, including, without limitation, sections 4107,
    4107.5, and 4109 of the Public Contract Code . . . : [¶] 7.6.1. Substitute any
    person as a Subcontractor in place of the Subcontractor designated in the
    original Bid . . . .” Prime Contractor does not dispute that this provision was
    incorporated by reference into the Contract.4 Subcontractor was designated
    in Prime Contractor’s original bid.
    On October 18, 2013—the day Nielson started working on the Project—
    Prime Contractor emailed the City’s city manager, “Just want to let you know
    that we had the new crews start augmenting [Subcontractor’s] forces today.
    After today, any underground utility, grading, and asphalt work in the
    parking lot will be completed by other crews. . . . We will restrict
    [Subcontractor] to working on the water to the building and in the even[t]
    they are not completed by Wednesday of next week we will have other crews
    take over that work also.” The city manager replied, “Much appreciated! It is
    what is needed to get us in.[5] Thanks.” It is undisputed that the City failed
    4 In a footnote, Prime Contractor cursorily contends that a breach of
    contract claim cannot be based on a violation of section 4107. The argument
    is insufficiently raised and we need not, and do not, address it. (Holden v.
    City of San Diego (2019) 
    43 Cal.App.5th 404
    , 419 [“An appellant cannot bury
    a substantive legal argument in a footnote and hope to avoid waiver of that
    argument.”].)
    5The City wanted to move into the Project building by late
    October 2013, the end of the City’s lease at its then-current building.
    5
    to provide Subcontractor with written notice of the substitution or an
    opportunity to object.
    B.    Legal Background
    “The Legislature enacted the Subletting and Subcontracting Fair
    Practices Act (§ 4100, et seq.), of which section 4107 is a part, to prevent ‘bid
    shopping’ and ‘bid peddling’ after the award of a public contract and to give
    the awarding authority the opportunity to investigate and approve the initial
    subcontractors and any replacements.” (Titan Electric Corp. v. Los Angeles
    Unified School Dist. (2008) 
    160 Cal.App.4th 188
    , 202, fn. omitted (Titan
    Electric).) “ ‘Bid shopping is the use of the low bid already received by the
    general contractor to pressure other subcontractors into submitting even
    lower bids. Bid peddling . . . is an attempt by a subcontractor to undercut
    known bids already submitted to the general contractor in order to procure
    the job.’ ” (Id. at p. 202, fn. 6.) “The Legislature found that these practices
    result in ‘poor quality of material and workmanship to the detriment of the
    public, deprive the public of the full benefits of fair competition among prime
    contractors and subcontractors, and lead to insolvencies, loss of wages to
    employees, and other evils.’ (§ 4101.)” (JMS Air Conditioning & Appliance
    Service, Inc. v. Santa Monica Community College Dist. (2018) 
    30 Cal.App.5th 945
    , 951 (JMS Air Conditioning).)
    “The Act seeks to prevent these evils by ‘provid[ing] an opportunity to
    the awarding authority to investigate and approve the initial subcontractors
    and any proposed substitutions.’ [Citation.] It requires that a general
    contractor specifically list in a bid for public work the subcontractors it
    intends to use for the project. (§ 4104.) Once the awarding authority accepts
    a bid, the Act permits the general contractor to substitute out a listed
    subcontractor only on certain enumerated bases, all but one of which relate to
    6
    the subcontractor’s ability or willingness to perform the work, or to perform it
    appropriately. (§ 4107, subd. (a).) The general contractor must receive
    approval from the awarding authority for any such substitution, and the Act
    establishes procedures for such requests. (Ibid.) These procedures require
    that a subcontractor receive written notice of a substitution request and, if
    the subcontractor timely objects, ‘the awarding authority’ must hold a
    hearing to decide if it will allow the substitution.” (JMS Air Conditioning,
    supra, 30 Cal.App.5th at p. 951, fn. omitted.)
    “[S]ubcontractors listed in a public bid enjoy limited statutory rights:
    The right to ‘perform the subcontract unless statutory grounds for a valid
    substitution exist’ and the right to a section 4107 hearing, if the
    subcontractor timely objects to a substitution request. [Citations.] These
    rights are ancillary to the Act’s larger objectives; the Act did not set out to
    create and does not focus on rights for subcontractors.” (JMS Air
    Conditioning, supra, 30 Cal.App.5th at p. 958.)
    C.    Bid Peddling/Shopping
    Prime Contractor first argues that the application of section 4107 is
    limited to cases involving bid peddling or bid shopping. It is undisputed that
    no such conduct occurred here. We conclude the statute is not so limited.
    To be sure, one of the primary statutory purposes was to prevent these
    practices. (§ 4101; JMS Air Conditioning, supra, 30 Cal.App.5th at p. 951
    [“The Act stems from legislative concerns about the practices of ‘bid shopping’
    and ‘bid peddling’ on public works projects.”].) However, the plain language
    of the statute does not limit its application to such conduct, and Prime
    Contractor points to no cases so limiting the statute. Instead, cases have
    considered the statutory purposes in construing the statute, but have applied
    it to other conduct. (See Titan Electric, supra, 160 Cal.App.4th at p. 206
    7
    [applying § 4107 in case where “no bid shopping by [the prime contractor] or
    bid peddling by [the subcontractor] occurred”].) Moreover, the statute is also
    intended to give “the awarding authority the opportunity to investigate and
    approve the initial subcontractors and any replacements.” (Titan Electric, at
    p. 202; see also Southern California Acoustics Co. v. C. V. Holder, Inc. (1969)
    
    71 Cal.2d 719
    , 725–726 [statute’s purposes include “providing the awarding
    authority with an opportunity to approve substitute subcontractors”].)
    Accordingly, while we construe the statute in light of its purposes,
    including the prevention of bid shopping and peddling, we decline to limit its
    application to such conduct.
    D.    Prime Contractor’s Statutory Obligations
    Prime Contractor argues that, if section 4107 applies, Prime
    Contractor’s only obligation under the statute was to obtain the City’s
    consent for the substitution. Subcontractor argued below, and argues here,
    that under section 4107, the City’s consent was not valid unless and until the
    City provided Subcontractor with written notice and, in the absence of such
    notice, Prime Contractor substituted Subcontractor without consent in
    violation of section 4107. We review this question of statutory interpretation
    de novo (Manriquez v. Gourley (2003) 
    105 Cal.App.4th 1227
    , 1233), and agree
    with Prime Contractor.
    First, we see no indication in the statutory language that a prime
    contractor must independently verify that a public entity has complied with
    the notice requirement before relying on the public entity’s consent. The
    statute provides a prime contractor “may not: [¶] (a) Substitute a person as
    subcontractor in place of the subcontractor listed in the original bid, except
    that the awarding authority . . . may . . . consent to the substitution of another
    person as a subcontractor in any of the following situations . . . .” (§ 4107,
    8
    subd. (a), italics added.) Thus, the prime contractor is prohibited from
    substitution except if it receives consent from the public entity. The statute
    separately provides, “Prior to approval of the prime contractor’s request for
    the substitution, the awarding authority . . . shall give notice in writing to the
    listed subcontractor of the prime contractor’s request to substitute and of the
    reasons for the request.” (§ 4107, subd. (a), italics added.) The public entity
    is required to provide notice prior to approving the request; the statute does
    not say the prime contractor cannot rely on the public entity’s consent unless
    notice has been provided. To construe the statute otherwise would effectively
    make prime contractors liable for public entities’ noncompliance. We see no
    basis in the statutory language to impose such liability.
    In addition, such a construction would not serve the statutory purposes
    “to prevent ‘bid shopping’ and ‘bid peddling’ after the award of a public
    contract and to give the awarding authority the opportunity to investigate
    and approve the initial subcontractors and any replacements.” (Titan
    Electric, supra, 160 Cal.App.4th at p. 202, fn. omitted.)
    A similar situation was presented in W.J. Lewis Corp. v. C. Harper
    Construction Co. (1981) 
    116 Cal.App.3d 27
     (W.J. Lewis). In that case, a
    subcontractor alleged a prime contractor violated section 4107. (Id. at p. 28.)
    It was undisputed that the prime contractor sought permission to substitute
    and that the public entity granted consent. (Id. at p. 30.) Instead, the
    subcontractor claimed it was not provided with notice of the substitution
    request. (Ibid.) The court reasoned, “if such be the fact, [the prime
    contractor] is not at fault because it, rather than the agency, was not
    required by the statute to give notice of the request.” (Ibid.) The court
    pointed to a later-enacted provision of the Act, section 4107.5, which
    “expressly requires the prime contractor, itself, to give notice of the proposed
    9
    change.”6 (W.J. Lewis, at p. 31.) When the Legislature enacted
    section 4107.5, it “did not amend section 4107 to impose such a requirement
    on the prime contractor, nor did it otherwise impose such a requirement for
    requests grounded on section 4107. [¶] In the light of that legislative action
    (more properly nonaction) we must conclude that no statutory duty rests on a
    prime contractor to, itself, give to a subcontractor notice of its desire to
    substitute except [pursuant to section 4107.5]. Absent such a duty in this
    case, no liability on the part of the [prime contractor] exists.” (W.J. Lewis, at
    p. 31.) Although W.J. Lewis did not address the specific argument presented
    here, its reasoning supports the conclusion a subcontractor cannot
    demonstrate a prime contractor violated section 4107 solely on the ground
    that the public entity failed to provide notice.
    Accordingly, we agree with Prime Contractor that it complied with
    section 4107 if it obtained the City’s consent for the substitution, regardless
    of the City’s failure to provide notice pursuant to section 4107.7
    6 Section 4107.5 provides, in relevant part, “The prime contractor as a
    condition to assert a claim of inadvertent clerical error in the listing of a
    subcontractor shall within two working days after the time of the prime bid
    opening by the awarding authority give written notice to the awarding
    authority and copies of that notice to both the subcontractor he or she claims
    to have listed in error and the intended subcontractor who had bid to the
    prime contractor prior to bid opening.”
    7 We note that Subcontractor was not without a remedy for the City’s
    failure to provide notice: “a subcontractor that believes an awarding
    authority has violated the Act’s statutory mandate may be entitled to bring
    an administrative mandamus under Code of Civil Procedure section 1094.5.”
    (E. F. Brady Co. v. M. H. Golden Co. (1997) 
    58 Cal.App.4th 182
    , 192.) In
    addition, although the parties do not discuss the statutory limitation that a
    public entity’s consent to substitution can only be granted in certain
    enumerated situations, this also appears to be a requirement imposed on the
    public entity, reviewable for substantial evidence in a mandamus action.
    10
    E.    Evidence of Consent
    Prime Contractor argues the undisputed evidence shows the City
    consented to the substitution. Subcontractor does not dispute that the city
    manager’s October 18, 2013 email demonstrates this consent. Nor could it
    reasonably do so: the email was from the city manager, expressed gratitude
    to Prime Contractor for the substitution, and indicated an understanding
    that the substitution was necessary for the timely completion of the Project.
    Instead, Subcontractor argues consent provided after the substitution
    does not satisfy section 4107. On this issue, Titan Electric is instructive. In
    that case, the prime contractor requested substitution and, after receiving
    notice of the request, the subcontractor objected and demanded a hearing.
    (Titan Electric, supra, 160 Cal.App.4th at p. 193.) The public entity held
    hearings but, by the time it granted the substitution request, the substitute
    subcontractor had already completed the work. (Ibid.) The original
    subcontractor petitioned for writ of administrative mandate challenging the
    public entity’s decision, arguing the substitution could not take place before
    the public entity’s consent. (Ibid.) The Court of Appeal rejected the
    challenge, holding “section 4107 contemplates that the awarding authority’s
    consent to substituting out a listed subcontractor and substituting in a
    proposed replacement will occur before the prime contractor permits the
    replacement to perform any work. However, a deviation from this chronology
    . . . is permissible so long as the procedure used actually complies with the
    substance of the reasonable objectives of the statute: namely, the prevention
    of bid peddling and bid shopping after the award of a public works contract,
    (JMS Air Conditioning, supra, 30 Cal.App.5th at pp. 964–967 [public entity’s
    decision that substitution warranted under certain statutory situations
    reviewed on mandamus for substantial evidence].)
    11
    and the providing of an opportunity to the awarding authority to investigate
    the proposed replacement subcontractor before consenting to substitution.”
    (Ibid.) The “procedural irregularity” of the public entity granting consent
    after the replacement subcontractor completed the work, did not, “under the
    facts here, . . . violate the purposes of the statute.” (Id. at p. 206.) The record
    showed “no bid shopping . . . or bid peddling . . . occurred,” and therefore “the
    statutory goal of preventing bid shopping and bid peddling was preserved.”
    (Ibid.) Moreover, “[t]he statutory purpose of giving the [public entity] the
    opportunity to investigate [the replacement subcontractor] so as to ensure the
    quality of the work was also met” because the public entity “had the
    opportunity to investigate [the replacement subcontractor] before consenting
    to substitution” and “[n]othing in the record suggests” the public entity found
    the replacement subcontractor’s “work to be substandard.” (Id. at pp. 206–
    207.)
    Here, as in Titan Electric, no bid shopping or bid peddling occurred, the
    City had the opportunity to investigate Nielson before granting consent, and
    there is no indication that Nielson’s work was substandard. Moreover, the
    request was granted just after Nielson’s substitution began, and long before
    the substitute work was complete. Subcontractor argues Titan Electric is
    inapplicable because in that case the public entity provided notice to the
    subcontractor and held a hearing, albeit a delayed one. But, as we explained
    above, the notice requirement was the City’s obligation, not Prime
    Contractor’s. We decline to find Prime Contractor failed to substantially
    comply with the statute based on the City’s statutory duties.
    F.    Conclusion
    We agree with Prime Contractor that the City’s failure to provide
    written notice to Subcontractor did not constitute a violation of Prime
    12
    Contractor’s obligations under section 4107. We further agree with Prime
    Contractor that its receipt of the City’s consent shortly after Nielson started
    work on the Project does not render Prime Contractor noncompliant.
    Accordingly, we will reverse the judgment with respect to Subcontractor’s
    breach of contract claim.8
    However, the failure to comply with section 4107 was only one of the
    breach theories asserted by Subcontractor. Under the special verdict form,
    once the jury determined Prime Contractor breached the Contract by failing
    to comply with section 4107, it did not determine whether Prime Contractor
    committed any other breach. We will therefore remand Subcontractor’s
    breach of contract claim rather than direct entry of judgment for Prime
    Contractor on this claim.
    II.   Business and Professions Code Section 7108.5
    The jury found that, as of December 31, 2013, Prime Contractor had
    not paid Subcontractor $263,552 it had received from the City for
    Subcontractor’s work on the Project. We reject most of Prime Contractor’s
    challenges, but we agree the amount should be slightly reduced.9
    8 Because of this conclusion, we need not address Prime Contractor’s
    arguments that: the relevant Contract provision imposed fewer requirements
    than section 4107; the substitution was pursuant to subdivision (b) of
    section 4107, not subdivision (a); section 4107 only applies to the substitution
    of base contract work; and Subcontractor failed to exhaust administrative
    remedies. In addition, we need not decide whether the trial court erred in
    awarding prejudgment interest on the contract damages.
    9 Neither party suggests that the prompt payment penalties award
    must be vacated if this court reverses the breach of contract claim, and we
    see no basis to so conclude.
    13
    A.    Legal Background
    “ ‘California has a series of so-called “prompt payment” statutes that
    require general contractors to pay their subcontractors within specified, short
    time periods, and that impose monetary penalties for violations.’ [Citation.]
    These prompt payment statutes serve a ‘ “remedial purpose: to encourage
    general contractors to pay timely their subcontractors and to provide the
    subcontractor with a remedy in the event that the contractor violates the
    statute.” [Citation.]’ [Citation.] [¶] One such statute is Business and
    Professions Code section 7108.5, which requires a general contractor to pay
    its subcontractors their respective shares of a progress payment within 10
    days [now seven days, see stats. 2011, ch. 700, § 1] of receiving that payment
    from the project’s owner, unless the parties agree otherwise in writing. If the
    general contractor fails to timely pay, the subcontractor may recover a
    penalty fixed at 2 percent of the amount due per month for every month the
    payment is not made. [Citations.] [¶] However, a contractor may withhold
    progress payments from a subcontractor without exposure to the 2 percent
    penalty if there is a good faith dispute between the general contractor and
    the subcontractor over the amount owed.” (FEI Enterprises, Inc. v. Yoon
    (2011) 
    194 Cal.App.4th 790
    , 795–797, fns. omitted.)
    B.    Good Faith Dispute
    With respect to the good faith nature of the dispute, the jury was
    instructed: “any funds withheld by the prime contractor based on an alleged
    good-faith dispute must be directly related to the adequacy of the
    construction work for which the payment is consideration. [¶] Controversies
    concerning unrelated work will not excuse the delay in payment.” Prime
    Contractor argues the instruction’s limitation to “the adequacy of the
    construction work for which the payment is consideration” was too narrow.
    14
    In United Riggers & Erectors, Inc. v. Coast Iron & Steel Co. (2018)
    
    4 Cal.5th 1082
     (United Riggers), the Supreme Court held that the good faith
    dispute exception applicable in all prompt payment statutes, including the
    one at issue here, “excuses payment only when a good faith dispute exists
    over a statutory or contractual precondition to that payment, such as the
    adequacy of the construction work for which the payment is consideration.
    Controversies concerning unrelated work or additional payments above the
    amount both sides agree is owed will not excuse delay; a direct contractor
    cannot withhold payment where the underlying obligation to pay those
    specific monies is undisputed.” (Id. at p. 1085; see also id. at p. 1097.) For
    example, in United Riggers, which involved the withholding of a retention
    payment, the Supreme Court held that “only withholding for disputes over
    the retention payment itself is allowed.” (Id. at p. 1092.)
    Prime Contractor argues it withheld money from Subcontractor
    because Subcontractor “would not timely complete its work, had forced
    [Prime Contractor] to hire Niels[o]n and . . . Niels[o]n properly took over some
    of [Subcontractor’s] work;” Prime Contractor therefore “had a contractual
    basis to withhold money;” and this constituted a good faith dispute over the
    withheld funds. We assume, without deciding, that a prime contractor’s
    contention that a subcontractor performed certain work too slowly, and that
    the slow pace required the prime contractor to hire another company to finish
    the work encompassed within the subcontractor’s contract, constitutes a good
    faith dispute and was not included in the jury instruction.
    Even so assuming, Prime Contractor fails to demonstrate prejudice.
    Subcontractor argued below that it had performed essentially all of the work
    covered by the Contract, and that Nielson was brought in to perform work not
    covered by the Contract in response to an unforeseen issue discovered in
    15
    early October. The jury accepted Subcontractor’s calculation of the value of
    the work Subcontractor had performed for which the City had paid Prime
    Contractor, essentially the amount of the Contract. (See post, pp. 17–18.)
    Therefore, the jury necessarily found that Subcontractor performed nearly all
    of the Contract work and Nielson performed work that was not covered by the
    Contract. Thus, any dispute over Subcontractor’s liability for Nielson’s work
    is indisputably about “unrelated work” and cannot excuse Prime Contractor’s
    prompt payment obligations. (See United Riggers, supra, 4 Cal.5th at
    p. 1085.) For the same reason, we reject Prime Contractor’s argument that
    the trial court erred in denying its motion for judgment notwithstanding the
    verdict on this issue.
    C.    Substantial Evidence
    Prime Contractor argues the jury’s determination of the amount of
    money Prime Contractor received from the City for Subcontractor’s work but
    failed to pay to Subcontractor is not supported by substantial evidence.
    The jury found the amount that Prime Contractor was paid by the City
    for Subcontractor’s work on the Project but that Prime Contractor did not pay
    Subcontractor as of December 31, 2013 was $263,552. In Subcontractor’s
    closing arguments, counsel urged the jury to find this precise amount based
    on the total Contract amount of $656,036.04, plus $6,331.40 for additional
    sewer reroute work, minus payments to Subcontractor of $398,714.94.10
    Prime Contractor first argues there was no evidence the City paid
    Prime Contractor anything at all. We disagree. The City’s privately-
    10The actual amount based on these figures is $263,652.50.
    Subcontractor apparently rounded down to the nearest dollar. In addition, as
    discussed below, Subcontractor made a $100 mathematical error in Prime
    Contractor’s favor.
    16
    contracted construction manager testified she reviewed Prime Contractor’s
    monthly bills, submitted them to the City for payment, and never heard any
    complaints that the City was not timely paying the bills. Prime Contractor’s
    project manager testified the City was supposed to pay Prime Contractor
    within 30 days of receiving a bill, and he was not aware of any issues with
    the City’s monthly payments to Prime Contractor. Prime Contractor’s pay
    application for December 2013 indicates the City had already paid Prime
    Contractor nearly $9 million. The jury could reasonably infer from this
    evidence that the City promptly paid Prime Contractor’s bills. (County of
    Kern v. Jadwin (2011) 
    197 Cal.App.4th 65
    , 73 [“substantial evidence includes
    circumstantial evidence and the reasonable inferences flowing therefrom”].)
    Prime Contractor next contends there was no evidence of the amount
    Prime Contractor billed the City for Subcontractor’s work. We again
    disagree. First, there was evidence that the value of Subcontractor’s work
    was close to $656,036.04 plus $6,331.40: (1) Both Subcontractor’s owner and
    Prime Contractor’s project manager testified that the amount of the Contract,
    including approved additional work, was $656,036.04; (2) Subcontractor
    presented evidence that it had completed all but $28,000 of the Contract
    work by the end of October, and that it completed “a big part” of the
    remaining work in November; and (3) Subcontractor submitted evidence that
    it performed an additional $6,331.40 of work which should have been added
    to the Contract. This evidence suggests Subcontractor performed close to the
    full value of the Contract work; Subcontractor concedes in its response brief
    that the evidence shows $693.75 worth of Contract work was not completed.
    A deduction of $693.75 was not reflected in the calculations adopted by the
    jury, and we will direct the judgment be reduced accordingly. Second, there
    was evidence that Prime Contractor promptly billed the City for work
    17
    performed by its subcontractors: Prime Contractor’s project manager testified
    that each month he received billings from subcontractors based on the
    amount of work they performed that month, and that he then compiled the
    total billings onto a standard industry form application for payment which he
    submitted to the City. Prime Contractor argues that Subcontractor failed to
    submit the proper paperwork for its billings, but the record citations provided
    do not demonstrate that Prime Contractor did not submit any of
    Subcontractor’s billings for payment.11 The jury could reasonably infer that
    Prime Contractor had billed the City for all of the work completed by
    Subcontractor.
    Prime Contractor argues there is no evidence of the amount Prime
    Contractor paid Subcontractor. Not so. Subcontractor’s owner testified that
    as of the end of 2013, Prime Contractor had paid $398,714.94 to
    Subcontractor or its suppliers. Although there was evidence Prime
    Contractor subsequently made additional payments to Subcontractor’s
    suppliers or subcontractors, these payments were made after December 31,
    2013, the relevant date identified on the jury’s verdict form.12
    11 Prime Contractor also points to a portion of a pay application
    submitted to the City and argues that it lists all approved change orders but
    does not include Subcontractor’s change orders, thereby purportedly
    demonstrating Prime Contractor did not bill the City for any of
    Subcontractor’s change orders. Prime Contractor cites no record evidence
    supporting its assertion that the cited pay application lists all approved
    change orders for the Project. Moreover, Prime Contractor’s project manager
    testified Subcontractor was paid for all approved change order work
    performed in 2012 and early 2013.
    12Prime Contractor argues the trial court erred in awarding prompt
    payment penalties through the date of judgment for payments Prime
    Contractor made to Subcontractor shortly after December 31, 2013. The
    contention is forfeited: Prime Contractor raised it for the first time in its
    18
    Prime Contractor argues the jury’s adoption of Subcontractor’s
    calculations, including a minor mathematical error contained therein (see
    ante, fn. 10), shows the jury did not independently evaluate the evidence.
    Prime Contractor does not assert—much less provide supporting record
    citations—that it alerted the jury to this error. We will not conclude the
    jury’s failure to catch a minor mathematical error that the opposing party
    also apparently did not catch establishes the jury failed to independently
    evaluate the evidence.
    Finally, Prime Contractor contends the City had not paid Prime
    Contractor withheld retention as of December 31, 2013, so the amount of
    such retention owed to Subcontractor should not have been considered for
    purposes of Business and Professions Code section 7108.5.13 We agree with
    this contention. Prime Contractor’s December 2013 pay application to the
    City demonstrates that the City retained 5 percent of the value of all
    reply brief and fails to provide record citations demonstrating it raised the
    objection below. (Tellez v. Rich Voss Trucking, Inc. (2015) 
    240 Cal.App.4th 1052
    , 1066 [“ ‘ “ ‘points raised in the reply brief for the first time will not be
    considered, unless good reason is shown for failure to present them
    before’ ” ’ ”]; Avalos v. Perez (2011) 
    196 Cal.App.4th 773
    , 776 [“As a general
    rule, a claim of error will be deemed to have been forfeited when a party fails
    to bring the error to the trial court’s attention by timely motion or
    objection.”].)
    13 “As a[] . . . hedge against nonperformance and incentive for
    completion, an owner may withhold a small percentage of the money due at
    each stage—typically 5 to 10 percent—until the project is finished.
    [Citations.] If the contractor defaults, or subcontractors assert mechanics
    liens for nonpayment, the owner can use this retention fund to make
    payment or seek substitute performance. [Citations.] Once work is done to
    the owner’s satisfaction and the period for filing liens has expired, the owner
    will release the retention.” (United Riggers, supra, 4 Cal.5th at pp. 1087–
    1088, fn. omitted.)
    19
    completed work, and Prime Contractor’s January 2015 pay application
    demonstrates the retention was still unpaid at that time.14 The jury adopted
    Subcontractor’s calculations, which did not account for this withheld
    retention. The jury’s verdict indicates it found Prime Contractor billed the
    City $656,036.04 plus $6,331.40 for work performed by Subcontractor; as
    discussed above, we are reducing this by $693.75 for Contract work not
    completed. 5 percent of this amount is $33,083.68, and the amount of
    withheld payment subject to prompt payment penalties should be reduced by
    this amount. We will reverse and remand the prompt payment penalties to
    be recalculated accordingly.
    D.      Documentary Exhibits
    Prime Contractor argues certain documentary exhibits were improperly
    admitted to its prejudice.15 We reject the challenge.
    The challenged documents, Exhibits 15 and 16, were spreadsheets
    prepared by Subcontractor’s owner, Bruce Volpe, to summarize his account of
    Subcontractor’s billings to Prime Contractor and Prime Contractor’s
    payments to Subcontractor.16 Prime Contractor raised hearsay objections to
    the admission of both documents. After Mr. Volpe testified about the billings
    and payments listed in the exhibits, the trial court admitted the documents
    but instructed the jury that “these numbers are in dispute. So they are not
    14Although Prime Contractor asserts the City withheld an additional
    2.5 percent, the record citations provided do not support this claim.
    15 Prime Contractor primarily raises this challenge with respect to the
    jury’s damages award, which will be vacated as a result of our reversing the
    breach of contract judgment. However, Prime Contractor also indicates the
    documents were used to support the prompt payment amount.
    16   Exhibit 16 was a corrected version of Exhibit 15.
    20
    being offered for the truth at this time. This is simply a document created by
    the witness to calculate what he believes is owed to him.”
    Prime Contractor argues the records were not admissible under the
    business records hearsay exception. (Evid. Code, § 1271.) The records were
    not admitted for the truth, and therefore did not need to satisfy the business
    records exception or any other hearsay exception. (Evid. Code, § 1200,
    subd. (a) [“ ‘Hearsay evidence’ is evidence of a statement that was made other
    than by a witness while testifying at the hearing and that is offered to prove
    the truth of the matter stated.”].)
    Prime Contractor also argues that the exhibits may have been used to
    refresh Mr. Volpe’s recollection, but such use did not render them
    independently admissible. (See Vogelsang v. Wolpert (1964) 
    227 Cal.App.2d 102
    , 126–127 [“ ‘When a party produces a witness who uses a writing to
    revive present recollection, or as a record of past recollection, the writing may
    not be introduced in evidence by that party.’ ”].) The documents were not
    admitted for the truth, and Prime Contractor does not challenge either the
    use of the exhibits to refresh Mr. Volpe’s recollection or Mr. Volpe’s testimony
    regarding the billings and payments listed on the exhibits. Accordingly,
    Prime Contractor has failed to demonstrate it was prejudiced by any error in
    admitting the documents. (See Evid. Code, § 353.)17
    III.   Attorney Fees
    Prime Contractor argues the trial court erred in awarding contractual
    attorney fees pursuant to Civil Code section 1717. Because we are reversing
    the judgment on Subcontractor’s breach of contract claim, the attorney fee
    order is also reversed and we need not and do not decide this issue. (Merced
    We reject Prime Contractor’s contention that the trial court’s errors
    17
    cumulatively prejudiced it.
    21
    County Taxpayers’ Assn. v. Cardella (1990) 
    218 Cal.App.3d 396
    , 402 [an order
    awarding attorney fees “falls with a reversal of the judgment on which it is
    based”].)
    DISPOSITION
    The judgment is reversed and remanded as follows: (1) the breach of
    contract judgment is reversed and remanded for retrial; (2) the award of
    prompt payment penalties is reversed and remanded for recalculation based
    on $229,774.57 of unpaid payments18; and (3) the fee award is reversed. The
    parties shall bear their own costs on appeal.
    SIMONS, Acting P. J.
    We concur.
    NEEDHAM, J.
    RODRIGUEZ, J.*
    (A157577, A159372)
    18   $263,552 minus $693.75 minus $33,083.68.
    * Judge of the Superior Court of Alameda County, assigned by the
    Chief Justice pursuant to article VI, section 6 of the California Constitution.
    22
    

Document Info

Docket Number: A157577

Filed Date: 9/29/2021

Precedential Status: Non-Precedential

Modified Date: 9/29/2021