Sopris Lodging, LLC v. Schofield Excavation, Inc. , 2016 Colo. App. LEXIS 1490 ( 2016 )


Menu:
  • COLORADO COURT OF APPEALS                                       2016COA158
    Court of Appeals No. 15CA1959
    Garfield County District Court No. 13CV30033
    Honorable Gail H. Nichols, Judge
    Sopris Lodging, LLC, a Colorado limited liability company, assignee of the
    claims of TDC/BEI Joint Venture, LLC, a Colorado limited liability company;
    Charles R. Lakin, an individual; and Tyler Casebier, an individual,
    Third-Party Plaintiffs-Appellants,
    v.
    Schofield Excavation, Inc., a Colorado corporation; and Colorado Engineering
    Contractors, Inc., a Colorado corporation,
    Third-Party Defendants-Appellees.
    JUDGMENT AFFIRMED
    Division VI
    Opinion by JUDGE RICHMAN
    Bernard and Fox, JJ., concur
    Announced October 20, 2016
    Wolf Slatkin & Madison, P.C., Albert B. Wolf, Jonathan L. Madison, Denver,
    Colorado, for Third-Party Plaintiffs-Appellants
    Markusson, Green & Jarvis, H. Keith Jarvis, Daniel R. Coombe, Anne K.
    McMichael, Denver, Colorado, for Third-Party Defendant-Appellee Schofield
    Excavation, Inc.
    Stuart D. Morse & Associates, LLC, Stuart D. Morse, Matthew J. Bayma,
    Greenwood Village, Colorado, for Third-Party Defendant-Appellee Colorado
    Engineering Contractors, Inc.
    ¶1    In this construction defect case, Sopris Lodging, LLC, assignee
    of the claims of third-party plaintiffs TDC/BEI Joint Venture, LLC
    (TDC), Charles R. Lakin, and Tyler Casebier, appeals the district
    court’s entry of summary judgment in favor of third-party
    defendants, Schofield Excavation, Inc. (Schofield), and Colorado
    Engineering Contractors, Inc. (CEC). Because we conclude that the
    third-party claims at issue are time barred, we affirm.
    I.    Background
    ¶2    TDC was the general contractor for the construction of a hotel
    owned by Sopris Lodging. On March 11, 2011, Sopris Lodging sent
    TDC a notice of claim regarding alleged construction defects at the
    hotel. On May 24, 2013, Sopris Lodging filed a complaint in district
    court asserting construction defect claims against one of the
    subcontractors of the hotel, and against the TDC’s individual
    principals, Lakin and Casebier, who had guaranteed TDC’s
    performance. On the same date, however, Sopris Lodging and TDC
    entered into an agreement to toll the statute of limitations for Sopris
    1
    Lodging’s claims against TDC. Sopris Lodging later amended its
    complaint in August of 2013 to add claims against TDC.1
    ¶3    In 2014, while those claims were pending, TDC filed third-
    party claims against several subcontractors, including Schofield
    and CEC, for breach of contract, negligence, contribution, and
    indemnification. CEC and Schofield moved for summary judgment,
    asserting that TDC’s third-party claims were barred by the two-year
    statute of limitations set forth in section 13-80-102, C.R.S. 2016,
    and made applicable to TDC’s claims through section
    13-80-104(1)(a), C.R.S. 2016. CEC and Schofield argued that those
    claims accrued on or before March 11, 2011, when Sopris Lodging
    sent the notice of claim to TDC. Because TDC did not file its third-
    party claims until 2014, CEC and Schofield asserted that the claims
    were time barred.
    ¶4    In its response, TDC did not dispute the date of accrual.
    However, it asserted that section 13-80-104(1)(b)(II) tolled the
    statute of limitations for a defendant’s third-party claims until
    1 Hereinafter, we refer to TDC and its principals collectively as
    “TDC.”
    2
    ninety days after a settlement or final judgment on the plaintiffs’
    claims against the defendant.
    ¶5    After briefing, the district court entered a detailed written
    order ruling that the third-party claims were time barred. Relying
    on CLPF-Parkridge One, L.P. v. Harwell Investments, Inc., 
    105 P.3d 658
    (Colo. 2005), the court concluded that section 13-80-
    104(1)(b)(II) did not apply to TDC’s third-party claims and that
    those claims were barred by the limitations period in section
    13-80-104(1)(a). Accordingly, the court entered summary judgment
    in favor of CEC and Schofield.
    ¶6    Thereafter, Sopris Lodging and TDC reached a settlement
    agreement. TDC assigned its third-party claims to Sopris Lodging,
    and Sopris Lodging, standing in the shoes of TDC, filed this appeal.
    II.      Discussion
    ¶7    Sopris Lodging contends that the court misapplied section
    13-80-104 in ruling that the third-party claims of TDC were time
    barred. We disagree.
    A.         Standard of Review
    ¶8    We review a trial court’s order on a summary judgment motion
    de novo. Gibbons v. Ludlow, 
    2013 CO 49
    , ¶ 11. Summary
    3
    judgment is appropriate when the pleadings and supporting
    documents establish that there is no genuine issue as to any
    material fact and that the moving party is entitled to judgment as a
    matter of law. 
    Id. ¶9 Statutory
    interpretation is a question of law that we review de
    novo. Klinger v. Adams Cty. Sch. Dist. No. 50, 
    130 P.3d 1027
    , 1031
    (Colo. 2006). Our task is to give effect to the intent of the General
    Assembly. 
    Id. To do
    so, we look first to the language of the statute.
    
    Id. We construe
    words and phrases according to their commonly
    accepted and understood meanings. A.S. v. People, 
    2013 CO 63
    ,
    ¶ 10. Where the language is clear and unambiguous, we do not
    resort to other rules of statutory construction. 
    Klinger, 130 P.3d at 1031
    .
    B.   Applicable Law
    ¶ 10   Section 13-80-104(1)(a) provides that the two-year statute of
    limitations set forth in section 13-80-102(1) applies to construction
    defect claims:
    Notwithstanding any statutory provision to the
    contrary, all actions against any architect,
    contractor, builder or builder vendor, engineer,
    or inspector performing or furnishing the
    design, planning, supervision, inspection,
    4
    construction, or observation of construction of
    any improvement to real property shall be
    brought within the time provided in section
    13-80-102 after the claim for relief arises, and
    not thereafter, but in no case shall such an
    action be brought more than six years after the
    substantial completion of the improvement to
    the real property, except as provided in
    subsection (2) of this section.
    ¶ 11   Section 13-80-104(1)(b) provides:
    (I) Except as otherwise provided in
    subparagraph (II) of this paragraph (b), a claim
    for relief arises under this section at the time
    the claimant or the claimant’s predecessor in
    interest discovers or in the exercise of
    reasonable diligence should have discovered
    the physical manifestations of a defect in the
    improvement which ultimately causes the
    injury.
    (II) Notwithstanding the provisions of
    paragraph (a) of this subsection (1), all claims,
    including, but not limited to indemnity or
    contribution, by a claimant against a person
    who is or may be liable to the claimant for all
    or part of the claimant’s liability to a third
    person:
    (A) Arise at the time the third person’s claim
    against the claimant is settled or at the time
    final judgment is entered on the third person’s
    claim against the claimant, whichever comes
    first; and
    (B) Shall be brought within ninety days after
    the claims arise, and not thereafter.
    5
    ¶ 12   In CLPF-Parkridge One, the supreme court held that section
    13-80-104(1)(b)(II) does not bar a defendant contractor from
    asserting third-party claims for indemnity or contribution against
    subcontractors before the resolution of the underlying construction
    defect 
    claims. 105 P.3d at 663-65
    . The court concluded that
    section 13-80-104(1)(b)(II) is not a ripeness provision but instead
    “toll[s] the otherwise applicable statute of limitations in order to
    allow indemnity or contribution claims to be brought in a separate
    lawsuit . . . within ninety days after settlement of or judgment in
    the construction defect lawsuit.” 
    Id. at 665.
    Thus, a defendant in a
    construction defect lawsuit may either (1) bring appropriate
    cross-claims or third-party claims in the same lawsuit or (2) wait to
    file a separate suit within the ninety-day period after a settlement or
    judgment in the construction defect lawsuit in accordance with
    section 13-80-104(1)(b)(II). 
    Id. at 664-65.
    C.   Analysis
    ¶ 13   Relying on CLPF-Parkridge One, Sopris Lodging asserts that
    section 13-80-104(1)(b)(II) tolled the statute of limitations for the
    third-party claims that TDC asserted against subcontractors in this
    case. We disagree.
    6
    ¶ 14   As set forth in CLPF-Parkridge One, section 13-80-104(1)(b)(II)
    gives a contractor the option to bring indemnity or contribution
    claims against subcontractors in a separate lawsuit after the
    underlying claims are resolved, and it tolls the statute of limitations
    for such claims. Here, however, TDC did not wait to file claims
    against subcontractors in a separate lawsuit. It chose instead to
    assert third-party claims in the original construction defect
    litigation. Thus, we conclude that section 13-80-104(1)(b)(II) does
    not apply to TDC’s third-party claims.
    ¶ 15   CLPF-Parkridge One did not address the statute of limitations
    applicable to third-party claims brought in the original construction
    defect lawsuit. Nonetheless, we conclude that those claims are
    subject to the two-year statute of limitations in section
    13-80-104(1)(a) and the accrual provision in section
    13-80-104(1)(b)(I).
    ¶ 16   Section 13-80-104(1)(a) provides that all construction defect
    actions must be brought within two years (the time provided in
    section 13-80-102) after “the claim for relief arises.” See also
    § 13-80-104(1)(c) (such actions include actions for indemnity and
    contribution). Section 13-80-104(1)(b)(I) states that, except as
    7
    otherwise provided in section 13-80-104(1)(b)(II), a claim for relief
    “arises” when the claimant discovers or should have discovered the
    physical manifestations of the defect. Thus, the only exception to
    the generally applicable accrual provision is for claims against third
    parties filed in a separate lawsuit in accordance with section
    13-80-104(1)(b)(II). See CLPF-Parkridge 
    One, 105 P.3d at 663-65
    .
    Because that exception is inapplicable here, TDC was required to
    comply with sections 13-80-104(1)(a) and 13-80-104(1)(b)(I) in filing
    its third-party claims.
    ¶ 17   Our interpretation is supported by Nelson, Haley, Patterson &
    Quirk, Inc. v. Garney Companies, Inc., which concluded that the
    accrual language currently found in section 13-80-104(1)(b)(I)
    required indemnity claims to be brought within the same period of
    time as the underlying construction defect claims. 
    781 P.2d 153
    ,
    155 (Colo. App. 1989). That case was decided before the General
    Assembly amended the statute in 2001 to add section
    13-80-104(1)(b)(II) to permit the filing of contribution and indemnity
    claims within ninety days after the entry of a settlement or
    judgment. However, as explained above, TDC did not pursue its
    third-party claims in accordance with section 13-80-104(1)(b)(II).
    8
    Therefore, like the division in Nelson, we conclude that TDC’s third-
    party claims were governed by the same limitation period and
    accrual provisions applicable to the underlying construction defect
    claims.
    ¶ 18   It is undisputed that TDC received notice of the alleged defects
    on March 11, 2011, when Sopris Lodging sent TDC a notice of
    claim. Under section 13-80-104(1)(b)(I), the claims accrued and the
    two-year limitations period began to run on that date. Apart from
    section 13-80-104(1)(b)(II), which we have deemed inapplicable,
    Sopris Lodging does not contend that any other tolling provision
    applied to TDC’s claims. Therefore, the limitations period expired
    with respect to those claims on March 11, 2013. Because TDC did
    not file its third-party claims until 2014, the claims were time
    barred.
    ¶ 19   We acknowledge that this analysis leads us to the somewhat
    anomalous conclusion that the statute of limitations applicable to
    TDC’s third-party claims could have expired before Sopris Lodging
    filed the underlying construction defect claims against TDC.2
    2 However, in this case the statute of limitations may have been
    tolled with respect to Sopris Lodging’s underlying claims against
    9
    Nevertheless, TDC had several options available to preserve its
    third-party claims against subcontractors. When TDC received
    Sopris Lodging’s notice of claim, it could have sent its own notices
    to subcontractors, thereby tolling the statute of limitations during
    the notice of claims process pursuant to section 13-20-805, C.R.S.
    2016. See Shaw Constr., LLC v. United Builder Servs., Inc., 
    2012 COA 24
    , ¶ 28. It also could have sought a tolling agreement with
    those subcontractors. Alternatively, TDC could have waited to file
    indemnity or contribution claims against subcontractors until after
    Sopris Lodging’s underlying claims against it were resolved, in
    accordance with section 13-80-104(1)(b)(II).3 TDC did not pursue
    any of these options.
    TDC for some time during the notice of claim process pursuant to
    section 13-20-805, C.R.S. 2016, and possibly pursuant to the
    tolling agreement between those parties. Although TDC filed a
    motion seeking to dismiss Sopris Lodging’s claims pursuant to the
    statute of limitations, the motion was not ruled upon by the district
    court.
    3 As the district court noted in its order, this option carries the risk
    that the claims will be barred by the six-year statute of repose in
    section 13-80-104(1)(a), C.R.S. 2016, if the underlying claims are
    not resolved within that time. See Thermo Dev., Inc. v. Cent.
    Masonry Corp., 
    195 P.3d 1166
    , 1168 (Colo. App. 2008) (concluding
    that section 13-80-104(1)(b)(II) does not act as a tolling provision for
    the six-year statute of repose). However, we are not persuaded that
    10
    ¶ 20   Therefore, for the reasons set forth above, we conclude that
    TDC’s third-party claims were time barred. In reaching this
    conclusion, we apply the express language of the statutes, and the
    interpretation of the statutes as explained in CLPF-Parkridge One.
    It is not our role to rewrite the statutes, as that is the function of
    the General Assembly.
    III.     Sopris Lodging’s Separate Lawsuit
    ¶ 21   After Sopris Lodging settled its claims against TDC, Sopris
    Lodging, as TDC’s assignee, brought indemnity and contribution
    claims against CEC and Schofield in a separate lawsuit purportedly
    under section 13-80-104(1)(b)(II). CEC and Schofield request that
    we dismiss the complaint in that case and rule that Sopris
    Lodging’s claims are barred by the doctrine of claim preclusion.
    However, those claims are the subject of a separate case and are
    not before us in this appeal. With exceptions not applicable here,
    our jurisdiction is limited to appeals from final judgments, see
    § 13-4-102(1), C.R.S. 2016, and no appeal of a final judgment in
    that case is before us. Accordingly, we do not address those claims.
    the potential effect of the statute of repose should alter our analysis
    of the applicable statute of limitation.
    11
    IV.     Attorney Fees
    ¶ 22   We also reject CEC’s request for an award of appellate attorney
    fees. C.A.R. 39.1 requires a party requesting attorney fees to state
    the legal basis that justifies an award of fees. CEC asserts that
    Sopris Lodging was “on notice that its separate claims were futile
    and this appeal would be unsuccessful.” To the extent that this
    argument refers to the grounds for an award of fees stated in
    section 13-17-102(4), C.R.S. 2016, and C.A.R. 38, we do not deem
    the appeal frivolous, groundless, or vexatious under those
    provisions. See Mission Denver Co. v. Pierson, 
    674 P.2d 363
    , 366
    (Colo. 1984) (an appeal is not frivolous merely because it is
    ultimately unsuccessful).
    V.       Conclusion
    ¶ 23   The judgment is affirmed.
    JUDGE BERNARD and JUDGE FOX concur.
    12