Whiting-Turner Contracting Co. v. Guarantee Company of North America USA , 440 P.3d 1282 ( 2019 )


Menu:
  •      The summaries of the Colorado Court of Appeals published opinions
    constitute no part of the opinion of the division but have been prepared by
    the division for the convenience of the reader. The summaries may not be
    cited or relied upon as they are not the official language of the division.
    Any discrepancy between the language in the summary and in the opinion
    should be resolved in favor of the language in the opinion.
    SUMMARY
    March 21, 2019
    2019COA44
    No. 17CA2160, Whiting-Turner v. Guarantee Co. of N. Am. USA
    — Construction Law — Suretyship and Guaranty —
    Performance Bonds; Contracts — Condition Precedent
    For the first time in Colorado, a division of the court of appeals
    applies to surety bonds cases the contract law principles governing
    a party’s satisfaction of conditions precedent. In addition, the
    division considers the proper calculation of the “Balance of the
    Contract Price,” which is a key term in the standard form of surety
    bond used throughout the construction industry. The division
    affirms the trial court’s finding that the general contractor satisfied
    the conditions precedent in the surety bond and thus triggered the
    surety’s obligation to perform.
    COLORADO COURT OF APPEALS                                        2019COA44
    Court of Appeals No. 17CA2160
    City and County of Denver District Court No. 14CV34166
    Honorable Andrew P. McCallin, Judge
    Whiting-Turner Contracting Company,
    Third-Party Plaintiff-Appellee,
    v.
    Guarantee Company of North America USA,
    Third-Party Defendant-Appellant.
    JUDGMENT AFFIRMED
    Division II
    Opinion by JUDGE LIPINSKY
    Dailey and Furman, JJ., concur
    Announced March 21, 2019
    Husch Blackwell LLP, Jeffrey D. Whitney, Jeffrey M. Van der Veer, Denver,
    Colorado, for Third-Party Plaintiff-Appellee
    Woods & Aitken LLP, Kory D. George, Colin P. Baumchen, Denver, Colorado,
    for Third-Party Defendant-Appellant
    ¶1    Performance bonds, like other forms of surety bonds, are
    critical to managing the risk inherent in construction projects. If a
    subcontractor fails to complete its work at a construction site, the
    surety that underwrote the performance bond assumes
    responsibility for the subcontractor’s obligations. Without
    performance bonds, a construction project could come to a halt if a
    single subcontractor walked off the job.
    ¶2    Performance bonds specify the actions that will trigger the
    surety’s obligations. In this appeal, a surety, Guarantee Company
    of North America USA (GCNA), and a general contractor, Whiting-
    Turner Contracting Company, dispute whether Whiting-Turner
    triggered GCNA’s obligations under a performance bond after a
    subcontractor, Klempco Construction (2013) Inc., stopped work at
    Whiting-Turner’s construction project. The parties’ disagreement
    centers on whether Whiting-Turner paid GCNA the “Balance of the
    Contract Price,” a key term in the performance bond, thereby
    satisfying one of the bond’s conditions precedent.
    ¶3    Following a bench trial, the trial court entered judgment in
    favor of Whiting-Turner and against GCNA. The trial court found
    1
    that Whiting-Turner had complied with the condition precedent set
    forth in section 3.3 of the performance bond and that GCNA had
    failed to perform its obligations under the bond.
    ¶4        On appeal, GCNA contends that the trial court applied the
    wrong legal standard in determining whether Whiting-Turner
    complied with section 3.3 of the performance bond, erred in finding
    that GCNA had waived its argument regarding Whiting-Turner’s
    compliance with section 3.3, erroneously found that Whiting-Turner
    satisfied the condition precedent in section 3.3, awarded duplicative
    damages to Whiting-Turner, and improperly awarded attorney fees
    to Whiting-Turner.
    ¶5        We affirm.
    I.      Whiting-Turner’s Disputes with Klempco and GCNA
    A.        Klempco Signs a Subcontract for Work at Whiting-Turner’s
    Project
    ¶6        Whiting-Turner served as the general contractor for an office
    building construction project in Denver (the Project). Whiting-
    Turner and Klempco entered into an agreement (the Subcontract)
    for Klempco’s construction of an anchor system at the Project’s
    underground parking garage. The anchor system was necessary to
    2
    keep the sides of the excavated site from collapsing during the
    initial phases of construction. Klempco’s work included the
    installation of sprayed concrete, known as shotcrete, to support the
    anchoring system. Whiting-Turner and Klempco agreed to a
    Subcontract price of $1,785,783.00.
    B.     GCNA Provides a Performance Bond and a Payment Bond
    ¶7        Whiting-Turner required Klempco to furnish a performance
    bond and a payment bond. (A surety that underwrites a payment
    bond is obligated to pay the sub-subcontractors if the
    subcontractor fails to do so.) Klempco obtained the bonds from
    GCNA. The bonds, which followed American Institute of Architects
    form A312, incorporated the Subcontract by reference. See 4A
    Philip L. Bruner & Patrick J. O’Connor, Jr., Bruner & O’Connor on
    Construction Law § 12:16, Westlaw (database updated June 2018)
    (explaining that the A312 surety bond is a standard form in the
    construction industry).
    ¶8        Section 3 of the performance bond specified the three
    conditions precedent that Whiting-Turner would need to satisfy to
    trigger GCNA’s obligations as surety:
    3
    • provide notice to Klempco and GCNA that Whiting-
    Turner was considering declaring Klempco in default
    (section 3.1);
    • declare Klempco in default, terminate the Subcontract,
    and notify GCNA of these actions (section 3.2); and
    • “pay the Balance of the Contract Price in accordance
    with the terms of the [Subcontract] to [GCNA] or to a
    contractor selected to perform the [Subcontract]”
    (section 3.3).
    ¶9     The performance bond defined “Balance of the Contract Price”
    as “[t]he total amount payable by [Whiting-Turner] to [Klempco]
    under the [Subcontract] after all proper adjustments have been
    made, . . . reduced by all valid and proper payments made to or on
    behalf of [Klempco] under the [Subcontract].” (Emphases added.)
    C.   Klempco Stops Work at the Project
    ¶ 10   Klempco fell behind schedule almost immediately and stopped
    paying its sub-subcontractors. Klempco subsequently directed
    Whiting-Turner to assume responsibility for the shotcrete
    4
    installation and to work directly with two of Klempco’s sub-
    subcontractors.
    ¶ 11   Whiting-Turner sent Klempco and GCNA a letter declaring
    Klempco in default under the Subcontract. In the letter, Whiting-
    Turner stated that Klempco was incapable of completing its work at
    the Project and “is apparently unable to complete payments to its
    sub-subcontractors for previously completed work, and by its own
    admissions is unable to cure such default.” Whiting-Turner
    requested a meeting with Klempco representatives “to discuss the
    details of Klempco’s request that Whiting-Turner take over its
    work.” Whiting-Turner asked GCNA to attend the meeting “to
    advise Whiting-Turner on how [GCNA] wishes for Whiting-Turner to
    proceed in connection with the completion of Klempco’s work and
    payment of its vendors.”
    ¶ 12   Representatives of Whiting-Turner, Klempco, and GCNA met
    on April 30, 2014, to discuss, among other issues, Klempco’s
    request that Whiting-Turner take over the shotcrete work and pay
    Klempco’s sub-subcontractors directly. At the meeting, Whiting-
    Turner and Klempco amended the Subcontract to reduce Klempco’s
    5
    payment by $553,707.00 — the price of the shotcrete work.
    Whiting-Turner, Klempco, and GCNA agreed that the shotcrete sub-
    subcontractor would invoice Whiting-Turner directly.
    ¶ 13   Two days later, Klempco notified Whiting-Turner that, because
    Whiting-Turner had declared Klempco in default and was refusing
    to pay Klempco, Klempco would demobilize from the Project.
    Whiting-Turner asked GCNA how Whiting-Turner should proceed in
    light of Klempco’s decision to leave the Project. GCNA did not
    respond.
    D.   Whiting-Turner Terminates Klempco’s Subcontract
    ¶ 14   Whiting-Turner terminated the Subcontract after Klempco
    failed to cure its default. GCNA did not respond to Whiting-
    Turner’s repeated demands that, in light of the termination of the
    Subcontract, GCNA honor its obligations under the performance
    bond and advise Whiting-Turner how GCNA intended to proceed.
    ¶ 15   On June 24, 2014, Whiting-Turner provided GCNA with its
    calculation of the “Balance of the Contract Price.” Whiting-Turner
    said that it had paid $1,064,919.00 of the “Balance of the Contract
    Price” to Klempco and its sub-subcontractors, leaving a balance of
    6
    $720,819.00. Whiting-Turner deducted certain expenses from this
    balance:
    • $256,897.90 for Whiting-Turner’s payments to five
    unpaid sub-subcontractors who had recorded, or were
    threatening to record, mechanic’s liens against the
    Project; and
    • $553,707.00 for the shotcrete work for which Whiting-
    Turner had assumed responsibility.
    These adjustments resulted in a negative “Balance of the Contract
    Price.”
    E.    The Trial Court Enters Judgment Against Klempco and GCNA
    ¶ 16   Klempco filed suit against Whiting-Turner claiming, among
    other allegations, that Whiting-Turner had breached the
    Subcontract by failing to pay sums due to Klempco. Whiting-
    Turner asserted a counterclaim for breach of the Subcontract.
    Whiting-Turner also filed third-party claims against GCNA for
    breach of the performance bond and the payment bond.
    ¶ 17   GCNA argued that Whiting-Turner had failed to comply with
    the condition precedent set forth in section 3.3 of the performance
    7
    bond and, therefore, never trigged GCNA’s obligations under the
    bond. Specifically, GCNA asserted that Whiting-Turner
    miscalculated the “Balance of the Contract Price” and,
    consequently, failed to pay the correct sum to GCNA pursuant to
    section 3.3.
    ¶ 18   The case proceeded to a bench trial. In its findings of fact and
    conclusions of law, the trial court found that Klempco had breached
    the Subcontract. In addition, the trial court found that Whiting-
    Turner had complied with the condition precedent set forth in
    section 3.3 of the performance bond. The trial court further found
    that GCNA had breached the performance bond and the payment
    bond. The trial court held that GCNA was jointly and severally
    liable with Klempco for Whiting-Turner’s damages.
    ¶ 19   Alternatively, the trial court found that GCNA had waived its
    arguments regarding Whiting-Turner’s compliance with section 3.3
    by failing to respond to Whiting-Turner’s repeated requests for
    guidance after Klempco stopped performing under the Subcontract.
    ¶ 20   The trial court found that, as a consequence of GCNA’s breach
    of the performance bond, Whiting-Turner had incurred $798,248.93
    8
    in damages, including $124,146.95 in prejudgment interest. The
    trial court calculated Whiting-Turner’s damages by first determining
    how much Whiting-Turner had paid the sub-subcontractors to
    complete the work specified in the Subcontract. The trial court
    subtracted from this number the sum that Whiting-Turner had
    agreed to pay Klempco in the original Subcontract.
    ¶ 21   The trial court later revised its damage calculations to reflect
    two adjustments to the $798,248.93 figure: (1) a reduction of
    $3,322.90 for unrecoverable overhead and (2) additional
    prejudgment interest in the amount of $37,334.21. The trial court
    awarded Whiting-Turner $832,260.24 in damages against Klempco
    and GCNA, jointly and severally.
    ¶ 22   Whiting-Turner moved for an award of attorney fees and costs
    against Klempco and GCNA under the Subcontract; Colorado’s
    mechanic’s lien statute, section 38-22-128, C.R.S. 2018; and the
    performance and payment bonds. GCNA opposed Whiting-Turner’s
    request for attorney fees and argued, in the alternative, that GCNA
    was liable only for those fees attributable to Whiting-Turner’s
    claims against GCNA. GCNA contended that it was not liable for
    9
    Whiting-Turner’s fees attributable to its defenses to Klempco’s
    claims, Whiting-Turner’s claims against Klempco, or Whiting-
    Turner’s claim against GCNA for breach of the payment bond.
    ¶ 23   The trial court found that it could not apportion Whiting-
    Turner’s fees among the various claims and defenses litigated in the
    case, however, because “all of the claims of both parties ar[o]se out
    of the same operative facts.” The trial court held Klempco and
    GCNA jointly and severally liable to Whiting-Turner for $504,785.27
    in attorney fees and costs and $18,990.14 in interest.
    ¶ 24   GCNA appeals the trial court’s post-trial rulings on damages
    and attorney fees. (The trial court subsequently increased the
    amount of attorney fees awarded to Whiting-Turner. GCNA did not
    file an amended notice of appeal to obtain review of this decision,
    however. We therefore address the two appealed orders only. See
    Baldwin v. Bright Mortg. Co., 
    757 P.2d 1072
    , 1074 (Colo. 1988)
    (holding that attorney fees award is separately appealable from
    judgment on the merits).)
    10
    II.    The Record Does Not Indicate that the Trial Court Applied an
    Incorrect Legal Standard in Analyzing Whether Whiting-Turner
    Complied with Section 3.3 of the Performance Bond
    ¶ 25     GCNA contends that the trial court erred in finding that
    Whiting-Turner was required only to substantially comply, rather
    than strictly comply, with the condition precedent set forth in
    section 3.3 of the performance bond. GCNA asks us to hold that
    contractors must strictly comply with the conditions precedent in a
    performance bond and, therefore, reverse the trial court’s finding
    that Whiting-Turner complied with section 3.3.
    ¶ 26     The record does not support GCNA’s contention, however.
    Because the trial court did not find that Whiting-Turner only
    substantially complied with section 3.3, we need not address in this
    context the proper legal standard for determining whether a
    contractor satisfied a condition precedent in a performance bond.
    See Zingone v. Zingone, 
    136 Colo. 39
    , 43, 
    314 P.2d 304
    , 306 (1957)
    (holding that appellate court may not consider a party’s version of
    what transpired in the lower court that does not appear in the
    record).
    11
    ¶ 27   GCNA’s argument regarding the substantial compliance
    standard rests on a single sentence in the trial court’s discussion of
    Whiting-Turner’s compliance with the notice provision in the
    payment bond. The trial court said that “only substantial
    performance with bond notice requirements is required . . . .”
    ¶ 28   This is a correct statement regarding the standard for
    compliance with the notice provision in a surety bond. Brighton
    Sch. Dist. 27J v. Transamerica Premier Ins. Co., 
    923 P.2d 328
    , 334
    (Colo. App. 1996), aff’d, 
    940 P.2d 348
    (Colo. 1997). But this case
    does not concern Whiting-Turner’s compliance with a notice
    requirement.
    ¶ 29   GCNA does not point to anything in the record demonstrating
    that the trial court found that Whiting-Turner was required only to
    substantially comply with the condition precedent in section 3.3 of
    the performance bond. Moreover, GCNA does not contend that the
    trial court found that Whiting-Turner only substantially complied,
    and did not strictly comply, with section 3.3.
    ¶ 30   We therefore decline to address this argument.
    12
    III.   We Need Not Address GCNA’s Waiver Argument
    ¶ 31   GCNA contends that the trial court erred in finding that GCNA
    waived its argument that Whiting-Turner failed to satisfy the
    condition precedent set forth in section 3.3. The trial court inserted
    a single sentence regarding waiver in the midst of its extensive
    discussion of Whiting-Turner’s compliance with section 3.3,
    however.
    ¶ 32   The trial court’s ruling in favor of Whiting-Turner rested not
    only on waiver but also on the trial court’s thorough analysis of the
    merits of Whiting-Turner’s claims. The trial court’s reference to
    waiver therefore reflected, at most, an alternative basis for its
    findings of fact and conclusions of law.
    ¶ 33   We need not address whether GCNA waived its arguments
    concerning Whiting-Turner’s compliance with section 3.3 because,
    as we explain in Part IV below, we agree with the trial court that
    Whiting-Turner properly triggered GCNA’s obligations under the
    performance bond. See Archuleta v. Gomez, 
    140 P.3d 281
    , 285
    (Colo. App. 2006) (declining to address the trial court’s alternative
    ruling when the record supported the trial court’s findings and
    13
    verdict on the claim). We therefore now turn to the merits of
    GCNA’s argument regarding section 3.3.
    IV.    The Trial Court Did Not Err in Finding that Whiting-Turner
    Satisfied the Condition Precedent Set Forth in Section 3.3 of
    the Performance Bond
    ¶ 34         GCNA contends that the trial court erred in finding that
    Whiting-Turner satisfied the condition precedent in section 3.3 of
    the performance bond. GCNA asserts that Whiting-Turner did not
    comply with section 3.3 because it miscalculated the “Balance of
    the Contract Price” and did not pay the correct amount to GCNA.
    GCNA specifically argues that Whiting-Turner improperly reduced
    the “Balance of the Contract Price” by
    • the amount of Whiting-Turner’s anticipated payments to
    five unpaid sub-subcontractors that had recorded, or
    were threatening to record, mechanic’s liens against the
    Project;
    • the $553,707.00 reduction in the “Balance of the
    Contract Price” to which Whiting-Turner and Klempco
    agreed at the April 30 meeting (which GCNA also
    attended); and
    14
    • a back charge of $30,702.00.
    Lastly, GCNA asserts that we should adopt the reasoning of an
    unpublished New York state trial court decision that, according to
    GCNA, supports its position that Whiting-Turner failed to comply
    with section 3.3.
    ¶ 35   The record supports the trial court’s finding that Whiting-
    Turner satisfied the condition precedent in section 3.3 of the
    performance bond.
    A.    Standard of Review
    ¶ 36   We review de novo questions of law, such as the interpretation
    of a provision in a surety bond. See Brighton Sch. Dist. 
    27J, 923 P.2d at 333
    . We review a court’s findings of fact for clear error. 
    Id. A factual
    finding is clearly erroneous if nothing in the record
    supports it. Loveland Essential Grp., LLC v. Grommon Farms, Inc.,
    
    251 P.3d 1109
    , 1117 (Colo. App. 2010).
    15
    B.    The Trial Court Did Not Err in Finding that Whiting-Turner
    Correctly Calculated the “Balance of the Contract Price”
    1.    Whiting-Turner Properly Deducted from the “Balance of the
    Contract Price” Its Payments to the Five Unpaid Sub-
    Subcontractors
    ¶ 37        GCNA contends that the trial court erred in finding that
    Whiting-Turner properly reduced the “Balance of the Contract
    Price” by the $256,897.90 that Whiting-Turner paid to the five
    unpaid sub-subcontractors. We disagree.
    ¶ 38        The Subcontract authorized Whiting-Turner to pay Klempco’s
    unpaid sub-subcontractors and to subtract those payments from
    the “Balance of the Contract Price.” Under the Subcontract,
    Klempco was required to “. . . take any and all necessary actions to
    keep the Project free and clear of all claims for liens . . . .” If
    Klempco failed to take the “necessary actions,” Whiting-Turner
    could “take all actions which it deems reasonable or necessary to
    protect the Project from liens and claims and the costs of any such
    actions . . . shall be deducted from amounts payable by [Whiting-
    Turner] to [Klempco]” under the Subcontract.
    ¶ 39        Despite this language, GCNA asserts that the “Balance of the
    Contract Price” became fixed in place as of the moment Whiting-
    16
    Turner terminated the Subcontract. Therefore, according to GCNA,
    Whiting-Turner’s post-termination payments to Klempco’s unpaid
    sub-subcontractors, who were clamoring for payment and
    threatening to record liens against the Project, could not reduce the
    “Balance of the Contract Price.”
    ¶ 40   No language in either section 3.3 or the Subcontract barred
    Whiting-Turner from reducing the “Balance of the Contract Price”
    by the amount of its post-termination payments to unpaid sub-
    subcontractors, however. The five sub-subcontractors had already
    completed their work on the Project and had either recorded or were
    threatening to record liens against the Project. Thus, Whiting-
    Turner paid Klempco’s sub-subcontractors “to protect the Project
    from liens and claims . . . .”
    ¶ 41   GCNA cites to several cases to support its assertion that none
    of Whiting-Turner’s payments postdating the termination of the
    Subcontract properly reduced the “Balance of the Contract Price.”
    These cases do not assist GCNA, however. They hold that, when a
    general contractor hires a replacement subcontractor without the
    surety’s consent, the general contractor has failed to satisfy the
    17
    conditions precedent in the performance bond. Under those
    circumstances, the general contractor cannot reduce the “Balance
    of the Contract Price” by the amount of its payments to replacement
    subcontractors. See LaSalle Grp., Inc. v. JST Props., L.L.C., No. 10-
    14380, 
    2011 WL 3268099
    , at *6 (E.D. Mich. July 29, 2011) (“[T]he
    hiring of a replacement contractor fails to satisfy the requirement of
    paragraph 3.3 [of a form A312 bond].”) (emphasis added); Enter.
    Capital, Inc. v. San-Gra Corp., 
    284 F. Supp. 2d 166
    , 177 (D. Mass.
    2003) (explaining that the “notice requirement in the Construction
    Contract exists precisely to provide the surety an opportunity to
    protect itself against loss by participating in the selection of the
    successor contractor”) (emphasis added); Sch. Bd. v. TIG Premier Ins.
    Co., 
    110 F. Supp. 2d 1351
    , 1354 (N.D. Fla. 2000) (obligee “could not
    contract with another party . . . prior to giving [the surety] notice”)
    (emphasis added); Solai & Cameron, Inc. v. Plainfield Cmty. Consol.
    Sch. Dist. No. 202, 
    871 N.E.2d 944
    , 954 (Ill. App. Ct. 2007)
    (“[R]eplacement is a form of mitigation available only to [the surety]
    under the provisions of [the performance bond].”) (emphasis added).
    18
    ¶ 42    None of the sub-subcontractors Whiting-Turner paid was a
    replacement contractor. Klempco had selected all five of the sub-
    contractors. Accordingly, we conclude that the $256,897.90
    Whiting-Turner paid to the five unpaid sub-subcontractors after the
    termination of the Subcontract properly reduced the “Balance of the
    Contract Price.” (GCNA also contends that the trial court
    improperly reduced the “Balance of the Contract Price” by
    $99,901.65 that Whiting-Turner paid to sub-subcontractors. The
    record reflects, however, that these payments were included within
    the $256,897.90 Whiting-Turner paid to the five sub-
    subcontractors.)
    2.    Whiting-Turner Properly Subtracted from the “Balance of the
    Contract Price” the $553,707.00 Reduction in Its Payment to
    Klempco
    ¶ 43    GCNA also contends that the trial court improperly reduced
    the “Balance of the Contract Price” by the $553,707.00 reduction in
    the price payable to Klempco under the Subcontract for the
    shotcrete work. We conclude that the trial court did not err by
    reducing the “Balance of the Contract Price” by this amount.
    19
    ¶ 44        The trial court found that, at their April 30 meeting with
    GCNA, Whiting-Turner and Klempco agreed to reduce the amount
    payable to Klempco by the $553,707.00 specified in the
    Subcontract for the shotcrete work. Whiting-Turner advised GCNA
    and Klempco in letters dated May 2, 2014, and May 9, 2014, that it
    intended to incur the expense of completing the shotcrete work.
    When Whiting-Turner asked GCNA in a May 2, 2014, email if it was
    acceptable for Whiting-Turner to pay for the shotcrete work directly,
    GCNA responded “Yes.” GCNA therefore at least tacitly consented
    to reduction of the “Balance of the Contract Price” by $553,707.00.
    ¶ 45        Whiting-Turner and Klempco had the right to amend their
    agreement memorialized in the Subcontract, and did so when they
    reduced Klempco’s payment by $553,707.00. Accordingly, we
    conclude that the trial court did not err in finding that Whiting-
    Turner properly reduced the “Balance of the Contract Price” by the
    $553,707.00 reduction in the Subcontract price.
    3.    Whiting-Turner Correctly Subtracted the Back Charge from
    the “Balance of the Contract Price”
    ¶ 46        GCNA lastly contends that the trial court improperly reduced
    the “Balance of the Contract Price” by a back charge of $30,702.00
    20
    because the trial court disallowed the amount of the back charge as
    an item of damages. (GCNA fails to acknowledge that the trial court
    adjusted the amount of the back charge to $5,915.00.) We
    disagree.
    ¶ 47        As GCNA notes, the trial court reduced Whiting-Turner’s
    damages by the amount of the back charge. GCNA provides no
    explanation, beyond a one-sentence, conclusory statement, to
    support the proposition that, because Whiting-Turner could not
    recover the amount of the back charge as a component of its
    damages, the payment could not also reduce the “Balance of the
    Contract Price.” We decline to address an undeveloped argument
    without legal support. See Holley v. Huang, 
    284 P.3d 81
    , 87 (Colo.
    App. 2011) (declining to address “bald assertions of error”
    unsupported by legal authority).
    4.     The New York Trial Court Decision on Which GCNA Relies
    Does Not Support GCNA’s Argument that Whiting-Turner
    Failed to Satisfy the Condition Precedent in Section 3.3
    ¶ 48        We are not persuaded that the New York unpublished trial
    court decision cited by GCNA supports its argument that Whiting-
    Turner failed to comply with the condition precedent in section 3.3.
    21
    ¶ 49   In East 49th Street Development II, LLC v. Prestige Air &
    Design, LLC, 
    938 N.Y.S.2d 226
    , 
    2011 WL 4599708
    (N.Y. Sup. Ct.
    Oct. 6, 2011) (unpublished table decision), the contractor failed to
    tender the balance of the contract price to the surety, even though
    the balance of the contract price was positive, in violation of section
    3.3 of the form A312 performance bond. 
    Id. at *9.
    The East 49th
    Street court explained that an offer to pay the contract balance,
    even if the balance was negative, was sufficient to satisfy section
    3.3 of the performance bond. 
    Id. at *10.
    ¶ 50   Unlike the contractors in East 49th Street, Whiting-Turner
    acknowledged in its June 24, 2014, letter that it was required to
    pay GCNA the remainder of the “Balance of the Contract Price.”
    Based on Whiting-Turner’s tender of the “Balance of the Contract
    Price” to GCNA — albeit a negative balance — the trial court
    correctly found that Whiting-Turner had satisfied section 3.3 of the
    performance bond.
    ¶ 51   The law supports this conclusion. See U.S. Fid. & Guar. Co. v.
    Braspetro Oil Servs. Co., 
    369 F.3d 34
    , 59 (2d Cir. 2004) (“[T]he
    relevant inquiry is whether the Obligees actually agreed to pay the
    22
    Balance of the Contract Price — not, as the Sureties urge, whether
    the Obligees agreed with the Sureties’ assessment of what the
    respective Balances were at the time of the declarations of
    default.”). Accordingly, East 49th Street does not support GCNA’s
    argument that Whiting-Turner failed to comply with section 3.3.
    V.   The Trial Court Did Not Award Duplicative Damages to
    Whiting-Turner
    ¶ 52    GCNA contends that “Whiting-Turner essentially ‘triple-
    dipp[ed]’ in that it sought the very same dollars in three ways” by (1)
    reducing the “Balance of the Contract Price” payable to GCNA; (2)
    seeking payment of the same amount under the performance bond;
    and (3) attempting to recover this sum under the payment bond.
    ¶ 53    The record does not reflect that the trial court awarded
    Whiting-Turner any duplicative damages, however. The trial court
    reduced the amount of the judgment to permit Whiting-Turner to
    recover only under the performance bond. In doing so, the trial
    court correctly subtracted from the judgment the sum that Whiting-
    Turner would have been required to pay Klempco had Klempco not
    breached the Subcontract.
    23
    ¶ 54    Therefore, the trial court’s judgment did not reflect “triple
    dipping.” GCNA appears to acknowledge this fact in both its
    opening and reply brief. Accordingly, we disagree with GCNA that
    the trial court awarded duplicative damages to Whiting-Turner.
    VI.   The Trial Court Properly Awarded Whiting-Turner Its Attorney
    Fees
    ¶ 55    GCNA lastly contends that the trial court erroneously awarded
    attorney fees to Whiting-Turner under the performance bond.
    GCNA asserts that, because Whiting-Turner did not satisfy the
    condition precedent in section 3.3, Whiting-Turner could not
    recover attorney fees. Alternatively, GCNA argues that the trial
    court improperly failed to segregate the fees awardable to Whiting-
    Turner for its claim against GCNA from the fees attributable to
    Whiting-Turner’s other claims and defenses. We disagree with both
    contentions.
    A.    Standard of Review
    ¶ 56    When awarding attorney fees and costs under a contractual
    fee-shifting provision, “[t]he determination of which party prevailed
    is committed to the discretion of the trial court and is subject to an
    abuse of discretion standard of review on appeal.” Dennis I. Spencer
    24
    Contractor, Inc. v. City of Aurora, 
    884 P.2d 326
    , 328 n.6 (Colo. 1994)
    (citing Smith v. Freeman, 
    921 F.2d 1120
    , 1122 (10th Cir. 1990)).
    A court abuses its discretion when its decision is manifestly
    arbitrary, unreasonable, or unfair, or when it is based on an
    erroneous view of the law. Zeke Coffee, Inc. v. Pappas-Alstad P’ship,
    
    2015 COA 104
    , ¶ 12, 
    370 P.3d 261
    , 265. We will not disturb such
    a decision if it is supported by the record. Double Oak Constr.,
    L.L.C. v. Cornerstone Dev. Int’l, L.L.C., 
    97 P.3d 140
    , 151 (Colo. App.
    2003).
    B.   The Law Governing Attorney Fees
    ¶ 57   “[I]f the parties agree, in a contract clause known as a fee-
    shifting provision, . . . the prevailing party will be entitled to recover
    its attorney fees and costs.” S. Colo. Orthopaedic Clinic Sports Med.
    & Arthritis Surgeons, P.C. v. Weinstein, 
    2014 COA 171
    , ¶ 10, 
    343 P.3d 1044
    , 1047.
    ¶ 58   A party can recover all of its attorney fees for a lawsuit
    containing “multiple claims ‘involv[ing] a common core of facts’ or
    ‘based on related legal theories,’ [when] counsel’s efforts on an
    individual claim [cannot] be distinguished from work on the whole
    25
    of the litigation . . . .” Rocky Mountain Festivals, Inc. v. Parsons
    Corp., 
    242 P.3d 1067
    , 1073 (Colo. 2010) (quoting Hensley v.
    Eckerhart, 
    461 U.S. 424
    , 435 (1983)). However, when the party
    “presented ‘distinctly different claims for relief that [were] based on
    different facts and legal theories,’” the party may recover only those
    legal fees attributable to the claims on which the party prevailed.
    
    Id. (quoting Hensley,
    461 U.S. at 435).
    C.   Discussion
    1.    The Trial Court Properly Awarded Attorney Fees to Whiting-
    Turner Under the Performance Bond
    ¶ 59        Because Whiting-Turner complied with section 3.3, we agree
    with the trial court that Whiting-Turner had the right to recover
    attorney fees under the performance bond. The performance bond
    bound Klempco and GCNA, “jointly and severally, . . . to [Whiting-
    Turner] for the performance of the [Subcontract], which is
    incorporated herein by reference.” The Subcontract required
    Klempco to pay “[t]he amount of completion costs, as well as any
    other costs, damages, or expenses, including [Whiting-Turner’s]
    legal fees and expense[s], incurred as a result of [Klempco’s]
    default . . . .” The Subcontract also required Klempco to indemnify
    26
    Whiting-Turner “against any and all claims, suits, liens, judgments,
    damages, losses and expenses, including, but not limited to,
    attorney’s fees, arising in whole or in part and in any manner for
    the acts or omissions of [Klempco] . . . in the performance of the
    [Subcontract] . . . .”
    ¶ 60   The language of the Subcontract demonstrates that Klempco
    and Whiting-Turner intended that Klempco would pay any legal fees
    that Whiting-Turner incurred as a consequence of Klempco’s
    default. See Powder Horn Constructors, Inc. v. City of Florence, 
    754 P.2d 356
    , 365 (Colo. 1988) (language of the contract determines
    intent (citing Gen. Ins. Co. of Am. v. City of Colorado Springs, 
    638 P.2d 752
    , 757 (Colo. 1981))). Because the performance bond
    provided that GCNA was jointly and severally liable with Klempco
    for all sums that Klempco owed Whiting-Turner under the
    Subcontract, GCNA was liable to Whiting-Turner for the attorney
    fees that Klempco owed to Whiting-Turner. We therefore conclude
    that the trial court did not abuse its discretion in awarding attorney
    fees to Whiting-Turner under the performance bond.
    27
    2.   The Trial Court Did Not Err in Not Segregating the Fees
    Awarded to Whiting-Turner
    ¶ 61    GCNA challenges the lack of segregation between Whiting-
    Turner’s fees attributable to Whiting-Turner’s claims against GCNA
    arising under the performance bond and Whiting-Turner’s fees
    relating to the other claims and defenses in the case. The trial
    court found, however, “that it is improper[ ] to segregate out
    Whiting-Turner defense costs against Klempco versus the cost and
    fees that [Whiting-Turner] incurred in bringing its claims against
    Klempco for completion of the [P]roject.” The trial court explained
    that “all of the claims of both parties arise out of the same operative
    facts . . . .” (Emphasis added.)
    ¶ 62    To prosecute its claim for breach of the performance bond,
    Whiting-Turner had to prove its compliance with each of the three
    conditions precedent set forth in the performance bond: (1)
    notification to Klempco and GCNA that Whiting-Turner was
    considering declaring Klempco in default; (2) notification to GCNA
    that Whiting-Turner had declared a default and terminated the
    Subcontract; and (3) payment of the “Balance of the Contract Price”
    to GCNA or a designated replacement subcontractor. Whiting-
    28
    Turner therefore could not prove its claim under the performance
    bond unless it established, among other facts, that it had properly
    declared Klempco in default and terminated the Subcontract.
    ¶ 63   All the claims in the case, including Whiting-Turner’s claim
    under the performance bond, therefore “involv[ed] a common core of
    facts.” Rocky Mountain Festivals, 
    Inc., 242 P.3d at 1073
    (quoting
    
    Hensley, 461 U.S. at 435
    ). We discern no error in the trial court’s
    finding that Whiting-Turner’s attorney fees could not be
    apportioned amongst Whiting-Turner’s claims against GCNA, claims
    against Klempco, and defenses to Klempco’s claims, as all such
    claims and defenses were intertwined. The trial court thus correctly
    held that, under the performance bond, GCNA was liable to
    Whiting-Turner for all of Whiting-Turner’s attorney fees incurred in
    the litigation.
    ¶ 64   For these reasons, we conclude that the trial court did not
    abuse its discretion in awarding Whiting-Turner its attorney fees
    incurred in this litigation or in calculating the amount of such fees.
    VII. Conclusion
    ¶ 65   The judgment is affirmed.
    29
    JUDGE DAILEY and JUDGE FURMAN concur.
    30
    

Document Info

Docket Number: 17CA2160

Citation Numbers: 2019 COA 44, 440 P.3d 1282

Filed Date: 3/21/2019

Precedential Status: Precedential

Modified Date: 10/10/2019

Authorities (16)

Powder Horn Constructors, Inc. v. City of Florence , 12 Brief Times Rptr. 661 ( 1988 )

Archuleta v. Gomez , 2006 Colo. App. LEXIS 632 ( 2006 )

Rocky Mountain Festivals, Inc. v. Parsons Corp. , 242 P.3d 1067 ( 2010 )

Ronald Smith v. Jessie Freeman, Police Officer , 921 F.2d 1120 ( 1990 )

Dennis I. Spencer Contractor, Inc. v. City of Aurora , 1994 Colo. LEXIS 820 ( 1994 )

Brighton School District 27J v. Transamerica Premier ... , 923 P.2d 328 ( 1996 )

Double Oak Construction L.L.C. v. Cornerstone Development ... , 2003 Colo. App. LEXIS 1502 ( 2003 )

Zingone v. Zingone , 136 Colo. 39 ( 1957 )

Solai & Cameron, Inc v. Plainfield Community Consolidated ... , 374 Ill. App. 3d 825 ( 2007 )

Enterprise Capital, Inc. v. San-Gra Corp. , 284 F. Supp. 2d 166 ( 2003 )

united-states-fidelity-and-guaranty-company-and-american-home-assurance , 369 F.3d 34 ( 2004 )

LOVELAND ESSENTIAL GROUP, LLC. v. Grommon Farms, Inc. , 2010 Colo. App. LEXIS 1356 ( 2010 )

General Insurance Co. of America v. City of Colorado Springs , 1981 Colo. LEXIS 835 ( 1981 )

Baldwin v. Bright Mortgage Co. , 12 Brief Times Rptr. 1118 ( 1988 )

Zeke Coffee, Inc. v. Pappas-Alstad Partnership , 2015 Colo. App. LEXIS 1142 ( 2015 )

School Board of Escambia County v. Tig Premier Insurance , 110 F. Supp. 2d 1351 ( 2000 )

View All Authorities »