30 Taylor Morrison of Colorado, Inc. v. Terracon Consultants, Inc ( 2017 )


Menu:
  • COLORADO COURT OF APPEALS                                         2017COA64
    Court of Appeals No. 15CA1030
    Adams County District Court No. 10CV2032
    Honorable C. Scott Crabtree, Judge
    Taylor Morrison of Colorado, Inc., f/k/a Morrison Homes of Colorado, Inc.,
    Plaintiff-Appellant and Cross-Appellee,
    v.
    Terracon Consultants, Inc.,
    Defendant-Appellee and Cross-Appellant.
    JUDGMENT AFFIRMED IN PART, REVERSED IN PART,
    AND CASE REMANDED WITH DIRECTIONS
    Division V
    Opinion by JUDGE LICHTENSTEIN
    Román and Freyre, JJ., concur
    Announced May 18, 2017
    Snell & Wilmer L.L.P., Michael E. Lindsay, Jessica E. Yates, Bethany Gorlin,
    Denver, Colorado, for Plaintiff-Appellant and Cross-Appellee
    McDowell, Rice, Smith, & Buchanan, P.C., Thomas R. Buchanan, Jason L.
    Buchanan, Linda C. McFee, Kansas City, Missouri, for Defendant-Appellee and
    Cross-Appellant
    ¶1    This case requires us to address for the first time how a trial
    court should adjust a jury verdict awarding damages for breach of
    contract when there is both a setoff for the amount recovered from
    other liable parties and a contractual limitation on a defendant’s
    liability.1 We conclude the correct approach is to first apply the
    setoff against the jury verdict and then apply the contractual
    limitation against this reduced amount.
    ¶2    We therefore reverse the judgment as to the final award, and
    remand with directions. In all other respects the judgment and
    orders of the trial court are affirmed.
    I.    Background
    ¶3    Plaintiff, Taylor Morrison of Colorado, Inc. (Taylor), appeals the
    judgment entered following a jury trial on a breach of contract
    theory against defendant Terracon Consultants, Inc. (Terracon).
    ¶4    Taylor was the developer of a residential subdivision known as
    Homestead Hills. In 2004, Taylor contracted with Terracon to
    provide geotechnical engineering and construction materials testing
    services for the development of the subdivision. Through two
    1 We are using the term “setoff” in the broad sense to describe a
    reduction from an amount otherwise owed.
    1
    contracts, Taylor and Terracon agreed that Terracon was
    responsible for testing the soil for compliance with project
    specifications and building codes. Taylor and Terracon further
    agreed to a contractual limitation on liability (Limitation). The
    Limitation capped Terracon’s total aggregate liability to Taylor at
    $550,000 for any and all damages or expenses arising out of its
    services or the contract.
    ¶5    By 2010, many of the homeowners notified Taylor about
    cracks in the drywall of their houses. Taylor investigated the
    complaints and then sued Terracon and other contractors for
    damages relating to those defects.
    ¶6    The court rejected Taylor’s pretrial arguments that the
    $550,000 Limitation was either invalid or inapplicable to the
    action.2 The court then granted Terracon’s motion to dismiss it as a
    defendant after authorizing Terracon to deposit $550,000 into the
    court’s registry, rendering Taylor’s claims moot.
    2 Taylor raised three challenges to the $550,000 cap on liability: (1)
    the Homeowner’s Protection Act of 2007 (HPA) invalidated the
    Limitation; (2) Terracon’s willful and wanton conduct is excluded
    from the Limitation; and (3) any payments from Terracon’s
    Commercial General Liability (CGL) policy are excluded from the
    Limitation.
    2
    ¶7     Taylor proceeded to trial against the other contractors. One of
    these other contractors was Bemas Construction, which performed
    site grading, including overlot and subexcavation work. The jury
    returned a verdict in Bemas’ favor.
    ¶8     Taylor ultimately recovered $592,500 through a settlement
    with the remaining contractors.
    ¶9     Taylor appealed the trial court’s dismissal of Terracon as a
    defendant. In Taylor Morrison of Colo., Inc. v. Bemas Constr., Inc.,
    
    2014 COA 10
    (Taylor I), a division of this court remanded the case
    to the trial court to determine if Taylor should have been permitted
    to introduce evidence of Terracon’s willful and wanton conduct to
    overcome the contract’s Limitation clause, and, if so, to order a new
    trial against Terracon.3
    ¶ 10   On remand, the trial court considered the issue and ordered a
    new trial on Taylor’s breach of contract claim against Terracon.
    Although the court allowed evidence of willful and wanton conduct,
    it excluded opinion testimony from Taylor’s experts that
    3The division also held that the HPA could not constitutionally be
    applied to retroactively invalidate the Limitation clauses in the
    contracts between Taylor and Terracon, as such application would
    be impermissibly retrospective. Taylor Morrison of Colo., Inc. v.
    Bemas Constr., Inc., 
    2014 COA 10
    , ¶¶ 15-31.
    3
    characterized Terracon’s conduct as “willful and wanton.” The jury
    awarded Taylor $9,586,056 in damages, but also found that
    Terracon’s conduct was not willful and wanton.
    ¶ 11   After the court subsequently reviewed the parties’ extensive
    post-trial briefing on damages, it entered a final judgment of zero
    dollars. It arrived at this figure by first concluding that the
    $550,000 Limitation includes costs and prejudgment interest. It
    then concluded that the Limitation must be applied to reduce the
    jury’s $9,586,056 damages award to $550,000. Finally, it deducted
    the $592,500 settlement (received from the other liable parties) to
    arrive at zero dollars.
    ¶ 12   The court found that neither party prevailed for the purposes
    of awarding statutory costs. It also concluded that neither
    Terracon’s deposit of the $550,000 into the court registry nor its e-
    mail to Taylor addressing a mutual dismissal constituted a
    statutory “offer of settlement” that would have allowed Terracon an
    award of actual costs and fees under section 13-17-202(1)(a)(II),
    C.R.S. 2016.
    ¶ 13   Taylor now appeals and Terracon cross-appeals.
    4
    II.   Taylor’s Appeal
    A.    Prior Challenges to the $550,000 Limitation
    ¶ 14   As an initial matter, Taylor reasserts arguments it made in the
    2012 litigation that challenged the validity of the Limitation under
    the Homeowner’s Protection Act of 2007 (HPA) as well as its
    applicability to any payments Terracon received from its
    Commercial General Liability (CGL) insurer. For the reasons stated
    below, we decline to address them.
    ¶ 15   Taylor first requests that we revisit Taylor I, which held that
    the HPA could not be retroactively applied to invalidate the
    Limitation because such application would be unconstitutionally
    retrospective.4
    ¶ 16   True, a division of this court may review another division’s
    ruling in the same case where “the previous decision is no longer
    sound because of changed conditions or law, or legal or factual
    error, or if the prior decision would result in manifest injustice.”
    4 The HPA, enacted in 2007, states that, “[i]n order to preserve
    Colorado residential property owners’ legal rights and remedies, in
    any civil action . . . , any express waiver of, or limitation on, the
    legal rights, remedies, or damages provided by the ‘Construction
    Defect Action Reform Act’ . . . [is] void as against public policy.”
    § 13-20-806(7)(a), C.R.S. 2016 (footnotes omitted).
    5
    Core-Mark Midcontinent, Inc. v. Sonitrol Corp., 
    2012 COA 120
    , ¶ 10
    (quoting Vashone-Caruso v. Suthers, 
    29 P.3d 339
    , 342 (Colo. App.
    2001)).
    ¶ 17    After considering Taylor’s arguments, however, we conclude
    that none of these extraordinary circumstances exist here. Indeed,
    the division in Taylor I considered, and ultimately rejected, the
    arguments that Taylor repeats in this appeal. We are persuaded
    that the ruling in Taylor I correctly stated the law, thus we decline
    to revisit it.
    ¶ 18    Taylor next argues that the Limitation is not applicable to the
    extent damages are paid under Terracon’s CGL policy. Thus, Taylor
    contends that the trial court erred when it rejected Taylor’s request
    to enter a judgment allowing it to pursue Terracon’s CGL insurer.
    ¶ 19    But, as the trial court observed, it had already ruled on the
    CGL insurance issue in the 2012 litigation.5 Taylor did not then
    request the court to reconsider its ruling, and Taylor did not appeal
    5The trial court reviewed the CGL policy and found there was no
    coverage for professional services, the type of services Terracon had
    provided to Taylor. Therefore it rejected Taylor’s request to pursue
    Terracon’s CGL insurer.
    6
    it. We agree with the trial court that Taylor had abandoned the
    issue.
    ¶ 20   In the 2012 litigation, Taylor raised the CGL insurance issue
    as one of two bases for objecting to Terracon’s dismissal as a
    defendant upon its $550,000 deposit into the court registry.6
    Taylor appealed the court’s dismissal of Terracon, but only pursued
    one of its two objections to the dismissal: that the $550,000
    Limitation would not apply to Terracon’s alleged willful and wanton
    conduct. See Taylor I, ¶¶ 8, 35-38.
    ¶ 21   Taylor could have appealed the CGL insurance ruling in Taylor
    I, but did not do so. Thus, Taylor abandoned it. See Giampapa v.
    Am. Family Mut. Ins. Co., 
    64 P.3d 230
    , 245-46 (Colo. 2003) (finding
    appellant waived a damages cap issue in part because the appellant
    did not raise the issue in its previous appeal); Fed. Lumber Co. v.
    Hanley, 
    33 Colo. App. 18
    , 21, 
    515 P.2d 480
    , 482 (1973) (declining
    to consider an appellate challenge to the denial of a motion when an
    appeal had previously been taken from the same denial of that
    motion); In re Marriage of Tognoni, 
    313 P.3d 655
    , 658 (Colo. App.
    6 Taylor had argued that it would be premature to enforce the
    $550,000 cap because the Limitation only applied to the extent that
    the CGL policy did not provide coverage.
    7
    2011) (finding no error where court declined to revisit issue when
    husband had failed to appeal the previous order addressing the
    same issue); see also Crocker v. Piedmont Aviation, Inc., 
    49 F.3d 735
    , 739 (D.C. Cir. 1995) (“We have several times said that
    appellate courts are precluded from revisiting . . . those prior
    rulings of the trial court that could have been but were not
    challenged on an earlier appeal.”).
    B.    Contractual Limitation and Setoff
    ¶ 22   Taylor contends that the trial court erroneously deducted the
    $592,500 setoff from Terracon’s contractual $550,000 limit on
    liability instead of deducting it from the $9,586,056 jury damages
    verdict. We agree.
    ¶ 23   The proper measure of damages presents a question of law
    subject to de novo review. Colo. Ins. Guar. Ass’n v. Sunstate Equip.
    Co., LLC, 
    2016 COA 64
    , ¶ 128; see Ferrelgas, Inc. v. Yeiser, 
    247 P.3d 1022
    , 1026-27 (Colo. 2011) (considering the propriety of a
    setoff under de novo standard of review).
    ¶ 24   No case in Colorado has addressed how a trial court should
    adjust a jury verdict awarding damages for breach of contract when
    8
    there is both a setoff for the amount recovered from other liable
    parties and a contractual limitation on a defendant’s liability.
    ¶ 25   We conclude that a court must first apply the setoff against
    the jury verdict to ascertain the allowable amount of recovery, and
    then apply any contractual limitation against this reduced amount.
    This approach prevents double recovery by the plaintiff, preserves
    the parties’ right to have the terms of a contract enforced, and best
    gives effect to the jury verdict.
    ¶ 26   We begin by acknowledging that a jury verdict must be given
    effect if possible. See Tyler v. Dist. Court, 
    200 Colo. 254
    , 256, 
    613 P.2d 899
    , 901 (1980). Nonetheless, a court must adjust a jury’s
    damages verdict to ensure that a plaintiff’s recovery does not exceed
    the amount of recovery permitted under the law.
    ¶ 27   As pertinent here, a plaintiff may not receive double recovery
    for the same losses arising from the same injury. Lexton-Ancira
    Real Estate Fund, 1972 v. Heller, 
    826 P.2d 819
    , 823 (Colo. 1992);
    Quist v. Specialties Supply Co., Inc., 
    12 P.3d 863
    , 866 (Colo. App.
    2000). Thus, in order to prevent double recovery, a court must set
    off a loss by the amount of compensation a party already received
    9
    from another liable party for the same injury. See Andrews v.
    Picard, 
    199 P.3d 6
    , 11 (Colo. App. 2007).
    ¶ 28   Once the court determines the amount of a plaintiff’s allowable
    recovery, then any bargained-for damages cap comes into play. See
    Alhilo v. Kliem, 
    2016 COA 142
    , ¶ 71 (holding, in a comparative
    negligence tort case, that the amount of proper recovery for a loss
    must be ascertained before addressing a statutory damages cap).
    ¶ 29   Applying the setoff before any contracted damages cap ensures
    that that the amount of damages does not exceed the recovery
    allowable under the law. It also ensures that the parties’
    bargained-for agreement will be enforced. Core-Mark Midcontinent,
    ¶ 13 (a limitation of liability clause is generally enforceable because
    it represents the parties’ bargained-for agreement regarding the
    allocation of risks and costs in the event of a breach or other failure
    of the contemplated transaction).
    ¶ 30   But here, the trial court applied the $550,000 contractual
    limitation on damages before deducting the $592,500 setoff for the
    amounts received from other parties, resulting in a final judgment
    of zero dollars for Taylor. This result effectively rendered the jury’s
    damages finding meaningless. See Alhilo, ¶ 73 (citing Atkins v.
    10
    Strayhorn, 
    273 Cal. Rptr. 231
    , 238 n.8 (Cal. Ct. App. 1990)).
    Neither the terms of the contract nor the prohibition on double
    recovery requires this result.
    ¶ 31   Had the trial court first applied the setoff against the jury
    verdict and then applied the contractual limitation, the court would
    have applied the $592,500 setoff against the $9,586,056 jury
    damages verdict, resulting in new total of $8,993,556. The trial
    court then would have capped Terracon’s liability according to the
    Limitation, and reached a final judgment of $550,000 for Taylor.
    ¶ 32   This approach prevents double recovery because Taylor’s
    recovery from Terracon and the other parties did not exceed the loss
    actually sustained (some nine and one half million dollars). This
    approach also preserves Terracon’s rights to enforce the terms of
    the contract because Terracon would not have paid more than the
    Limitation agreed upon in the contract. And it is more consistent
    with the jury verdict because it avoids an even greater disparity
    between the actual loss and the recovery. See 
    id. at ¶
    74 (The
    plaintiff “is already receiving an amount less than the jury
    determined he was damaged.” (quoting 
    Atkins, 273 Cal. Rptr. at 238
    )).
    11
    ¶ 33   We are not persuaded by Terracon’s argument that Lira v.
    Davis, 
    832 P.2d 240
    (Colo. 1992), settled the issue of whether
    double recovery refers to the jury verdict or the final judgment, and
    therefore also settled whether to apply setoffs to jury verdicts or
    final judgments. Lira involved statutory interpretation of an
    amendment to section 13-21-102(1)(a), C.R.S. 2016, which was part
    of the tort reform legislation capping exemplary damages at one-to-
    one with compensatory damages. 
    Id. at 245.
    There, the supreme
    court compared the statutory phrases “damages assessed” and
    “actual damages awarded” and concluded that by using these
    distinct phrases, the legislature intended that different meanings
    attach to them. 
    Id. It held,
    for purposes of that statute, that
    “damages assessed” is synonymous with the amount of
    compensatory damages determined by the jury and “damages
    awarded” with the reduced amount of compensatory damages. 
    Id. ¶ 34
      Lira’s holding is inapposite because it was limited to the
    language of the exemplary damages statute in the context of tort
    reform legislation. Further, Lira never analyzed or even mentioned
    the prohibition on double recovery. Thus, it would be inappropriate
    to extend Lira’s holding on statutory exemplary damages in tort
    12
    cases to this breach of contract case. This is especially true when
    the practical effect would result in damages judgments that
    insufficiently compensate plaintiffs for losses sustained while
    relieving defendants of their bargained-for liability.
    ¶ 35      For these reasons, we reverse the judgment as to damages and
    remand with instructions to apply the setoff to the jury damages
    verdict before applying the contractual limitation and enter a final
    judgment of $550,000 for Taylor.
    C.        Costs and Interest
    ¶ 36      Taylor next contends that the trial court erred when it
    concluded that the $550,000 Limitation, by its terms, includes
    statutory costs and prejudgment interest. We perceive no error.
    1.     Preservation
    ¶ 37      The parties dispute whether Taylor sufficiently preserved this
    claim. However, we need not resolve this dispute because the trial
    court issued a thorough order addressing this claim, and we
    conclude no error occurred. See People v. Vasseur, 
    2016 COA 107
    ,
    ¶ 12.
    13
    2.    Standard of Review
    ¶ 38   We review a trial court’s interpretation of a contract de novo.
    Nat’l Propane Corp. v. Miller, 
    18 P.3d 782
    , 786 (Colo. App. 2000).
    ¶ 39   The Limitation reads:
    Client and Consultant have evaluated the risks
    and rewards associated with this project,
    including Consultant’s fee relative to the risks
    assumed, and agree to allocate certain of the
    risks so, to the fullest extent permitted by law,
    the total aggregate liability of Consultant (and
    its related corporations and employees) to
    Client and third parties granted reliance is
    limited to the greater of [$550,000] or its fee, for
    any and all injuries, damages, claims, losses,
    or expenses (including attorney and expert fees)
    arising out of Consultant’s services or this
    agreement, regardless of cause(s) or the theory
    of liability, including negligence, indemnity, or
    other recovery.
    (Emphasis added.)
    3.   Costs
    ¶ 40   Taylor argues that because the Limitation is silent as to
    statutory costs, the parties intended to exclude them from the
    agreed-upon cap. We are not persuaded.
    ¶ 41   The pertinent language in the contract states that the
    Limitation applies to “any and all” expenses “including attorney and
    expert fees.”
    14
    ¶ 42   Section 13-16-122, C.R.S. 2016, identifies statutory costs
    available in civil actions. It specifically lists among the items
    includable as statutory costs “attorney fees” and “charges for expert
    witnesses.” § 13-16-122(1)(e), (h). Because the Limitation identifies
    attorney fees and expert fees as examples of “any and all . . .
    expenses,” we interpret it to include statutory costs.
    ¶ 43   Taylor nonetheless argues that the Limitation applies only to
    cap the remedial costs resulting from Terracon’s defective services.
    We disagree. The Limitation caps expenses “arising out of
    Consultant’s services or this agreement.” (Emphasis added.) Thus,
    the Limitation’s language covers costs associated with interpreting
    and enforcing the contract — i.e. the costs of litigation, which are
    statutory costs.
    ¶ 44   We also are not persuaded by Taylor’s argument that the
    phrase “certain of the risks” indicates that the Limitation did not
    cover statutory costs. As explained above, by including “any and all
    . . . expenses,” the parties bargained to include statutory costs as
    part of the “certain” risks that the Limitation covers.
    ¶ 45   And we disagree with Taylor’s argument that Heil Valley
    Ranch, Inc. v. Simkin, 
    784 P.2d 781
    (Colo. 1989), requires us to
    15
    strictly construe the Limitation against Terracon. Simkin did not
    address a limitation clause, but instead addressed an exculpatory
    clause that released the defendant for all liability from any claims
    based on negligence and breach of warranty. 
    Id. at 783.
    Nor are we
    persuaded by Taylor’s contention that including statutory costs in
    the Limitation would convert it into an unbargained-for exculpatory
    agreement. While the clause in this case limited Terracon’s total
    liability, it did not act as a waiver of any claim that Taylor chose to
    bring. See, e.g., U.S. Fire Ins. Co., v. Sonitrol Management Corp.,
    
    192 P.3d 543
    , 548 (Colo. App. 2008) (acknowledging limitation of
    liability clauses, liquidated damages clauses, and exculpatory
    clauses as distinct categories).
    ¶ 46   Finally, because Taylor cannot recover statutory costs over
    and above the $550,000 cap, we need not address its challenge to
    the court’s finding that it was not a prevailing party for purposes of
    awarding such costs.
    ¶ 47   We affirm the trial court’s order denying the award of costs to
    Taylor on the basis that the $550,000 Limitation included statutory
    costs.
    16
    4.   Prejudgment and Postjudgment Interest
    ¶ 48   Taylor also argues the trial court erred when it ruled that the
    Limitation does not include prejudgment interest within its cap on
    liability. Again, we disagree.
    ¶ 49   Prejudgment interest is an element of damages; its primary
    purpose is to compensate the plaintiff. AE, Inc. v. Goodyear Tire &
    Rubber Co., 
    168 P.3d 507
    , 512 (Colo. 2007) (citing Farmers
    Reservoir & Irrigation Co. v. City of Golden, 
    113 P.3d 119
    , 132-33
    (Colo. 2005)).
    ¶ 50   The Limitation caps Terracon’s liability for “any and all
    injuries, damages, claims, losses, or expenses.” (Emphasis added.)
    Because prejudgment interest is a form of damages, and because
    the Limitation includes language that it applies to “damages,” we
    conclude that the Limitation covers prejudgment interest.
    ¶ 51   Finally, Taylor asserts that postjudgment interest is not
    covered by the Limitation. We agree.
    ¶ 52   Distinct from prejudgment interest, postjudgment interest is
    not an element of compensatory damages. See Allstate Ins. Co. v.
    Starke, 
    797 P.2d 14
    , 21 (Colo. 1990) (recognizing there is a
    substantive difference between prejudgment interest — which is an
    17
    element of compensatory damages — and postjudgment interest —
    which is not).
    ¶ 53   Taylor raised, but the trial court did not rule on, the issue of
    postjudgment interest. However, our decision reverses the
    judgment of the trial court, and directs it to enter a final judgment
    of $550,000 for Taylor. Therefore, we direct the trial court on
    remand to determine the proper postjudgment interest payable on
    that amount. See C.A.R. 37; In re Marriage of Gutfreund, 
    148 P.3d 136
    , 142 (Colo. 2006); see also Thompson v. United Sec. All., Inc.,
    
    2016 COA 128
    , ¶ 35 (citing § 5–12–106(1), C.R.S. 2016).
    D.    Expert Testimony
    ¶ 54   Taylor appeals the trial court’s exclusion of expert testimony
    concerning willful and wanton conduct. Taylor argues this error
    requires a new trial. We disagree.
    1.    Standard of Review
    ¶ 55   A trial court has broad latitude to determine the admissibility
    of evidence. Davis v. People, 
    2013 CO 57
    , ¶ 13. We review such
    decisions for an abuse of discretion. Quintana v. City of
    Westminster, 
    8 P.3d 527
    , 530 (Colo. App. 2007). A trial court
    18
    abuses its discretion if its decision is manifestly unreasonable,
    arbitrary, or unfair. Davis, ¶ 13.
    2.   Analysis
    ¶ 56   Under CRE 704, witness testimony “[o]therwise admissible is
    not objectionable because it embraces an ultimate issue to be
    decided by the trier of fact.” However, CRE 704 does not allow a
    witness to “tell the jury what result to reach.” People v. Gaffney,
    
    769 P.2d 1081
    , 1087 (Colo. 1989) (quoting Fed. R. Evid. 704
    advisory committee’s note). Nor does it allow a witness to testify
    about whether a particular legal standard has been met. People v.
    Collins, 
    730 P.2d 293
    , 306 (Colo. 1986).
    ¶ 57   Here, the trial court allowed Taylor’s experts to present their
    opinions concerning the quality of Terracon’s performance under
    the contract for engineering services. The experts’ pretrial reports,
    however, opined that Terracon acted willfully and wantonly. Yet,
    during depositions, all of the experts admitted that “willful and
    wanton” is not an engineering concept. Despite previous experience
    as expert witnesses in engineering, none had ever offered an
    opinion about willful and wanton conduct before this case.
    19
    ¶ 58   Based on these facts, the trial court issued a pretrial order
    excluding testimony from the experts that characterized Terracon’s
    conduct as willful and wanton. The trial court permitted the
    experts “to identify the acts or omissions which they claim breached
    the contract or fell below the standard adopted in Terracon’s
    contract” but did not to permit the experts to “characterize those
    acts or omissions as willful and wanton conduct. . . . [o]r
    fraudulently, or with wrongful intent.” Again at trial, the court
    clearly stated: “I’m not going to preclude any party from eliciting
    what they claim are these, sort of, egregious acts.” But the court
    stated that one of the experts “expressed his opinion that it’s willful
    and wanton conduct. I think he can say anything short of that.”
    ¶ 59   During the trial, Taylor’s experts provided detailed testimony
    describing how Terracon’s supervision of technicians, soil testing,
    and review of test results failed to meet the relevant standards of
    care. The experts’ testimony included opinions that Terracon’s
    performance “doesn’t even come close to what should have been
    done in order to provide assurances,” “was a complete disregard of
    their responsibility,” and was “as bad as I’ve seen anywhere, by far
    in – in 40 years of practice.”
    20
    ¶ 60   These experts were allowed to discuss all relevant facts and
    opinions on Terracon’s performance using characterizations within
    their expertise, even if they were not permitted to testify whether
    this conduct met the legal standard of “willful and wanton
    conduct.” See 
    Collins, 730 P.2d at 306
    . Thus, on this record, we
    conclude the trial court’s decision was not manifestly arbitrary,
    unreasonable, or unfair. The trial court’s decision appropriately
    prevented Taylor’s experts from testifying about legal concepts
    outside their expertise and violating CRE 704 by testifying about
    whether a legal standard was met.
    III.   Terracon’s Cross-Appeal
    ¶ 61   Terracon raises three issues on cross-appeal. Based on our
    disposition of this case, we need not address Terracon’s two issues
    raised conditionally in the event the case was remanded for a third
    trial. However, we do consider Terracon’s third issue: whether the
    trial court should have awarded Terracon costs under Colorado’s
    settlement statute. We affirm the trial court’s order concluding that
    Terracon did not make an offer of settlement as contemplated by
    the statute, and therefore it was not entitled to costs.
    21
    ¶ 62   Terracon claims that the trial court erred in refusing to award
    it costs under Colorado’s settlement statute. § 13-17-202. As
    pertinent here, this statute provides:
    If the defendant serves an offer of settlement in
    writing at any time more than fourteen days
    before the commencement of the trial that is
    rejected by the plaintiff, and the plaintiff does
    not recover a final judgment in excess of the
    amount offered, then the defendant shall be
    awarded actual costs accruing after the offer of
    settlement to be paid by the plaintiff.
    § 13-17-202(1)(a)(II).
    ¶ 63   We review issues of statutory construction and application de
    novo. Strunk v. Goldberg, 
    258 P.3d 334
    , 336 (Colo. App. 2011).
    ¶ 64   Terracon claims that it made two settlement offers. We will
    examine each in turn.
    ¶ 65   First, Terracon’s argues that its deposit of $550,000 into the
    court registry, pursuant to C.R.C.P. 67(a), constituted a settlement
    offer. The trial court rejected this argument, as do we. Terracon
    moved the court for dismissal on the basis that, as a matter of law,
    the maximum amount of its liability to Taylor was $550,000. But
    this was not an offer to Taylor, and Taylor did not have the option to
    reject it. Because the settlement statute requires both an offer and
    22
    rejection, Terracon’s actions did not trigger the statute, and
    Terracon is not entitled to costs.
    ¶ 66   Terracon also argues that an e-mail on December 10, 2014,
    from Terracon’s counsel to Taylor’s counsel constituted a settlement
    offer. The e-mail stated as follows:
    Our client would agree to a mutual dismissal
    with prejudice, with full releases, and each
    side to pay their own costs and fees, provided
    it is accepted promptly.
    Aside from any other exposure Taylor Morrison
    might have, we believe Terracon will be the
    prevailing party when a willful and wanton
    finding does not occur and Terracon’s
    recoverable costs will be easily twice the
    amount Taylor Morrison was required to pay to
    Bemas.
    ¶ 67   The trial court ruled that Terracon’s alleged offer of settlement
    in this e-mail did not comply with section 13-17-202 because it
    contained nonmonetary conditions — such as an agreement for
    “mutual dismissal” and “full releases” — which extended the offer
    beyond the claims at issue.7 Under the circumstances of this case,
    we agree.
    ¶ 68   The purpose of section 13-17-202 is to encourage the
    7The court also concluded that the settlement offer’s requirement of
    a “prompt” response did not comport with the statute.
    23
    settlement of litigation by encouraging reasonable settlement offers
    by all parties. 
    Strunk, 258 P.3d at 336
    . However, provisions
    included in an offer of settlement that “extend[] the scope of the
    offer beyond the claims at issue” are contrary to the purposes of
    section 13-17-202. 
    Id. (quoting Martin
    v. Minnard, 
    862 P.2d 1014
    ,
    1019 (Colo. App. 1993)).
    ¶ 69   If a settlement offer injects terms beyond the settlement of
    existing claims, it does not fall under the statute but constitutes a
    settlement agreement based upon contract principles. 
    Martin, 862 P.2d at 1019
    . Such an offer will not allow the offering party to
    recover costs under the statute. 
    Id. ¶ 70
      Here, the only claim at issue was Taylor’s breach of contract
    claim. The e-mail referenced “full releases” without limiting the
    releases to this claim. “Full releases” could include future claims
    arising from any other “exposure Taylor might have” from other
    litigants — a possibility which the e-mail obliquely referenced. See
    URS Grp., Inc. v. Tetra Tech FW, Inc., 
    181 P.3d 380
    , 392 (Colo. App.
    2008) (“[B]y requiring a release of all ‘future claims’ related to the
    project, TTFW imposed a nonmonetary condition that took its offer
    outside the scope of section 13-17-202.”).
    24
    ¶ 71   Further, by referencing a “mutual dismissal,” the full release
    also could apply to the dismissal of any possible counterclaims that
    Terracon had not yet brought, again injecting terms beyond the
    settlement of the breach of contract claim. See 
    Martin, 862 P.2d at 1019
    ; see also Dillen v. HealthOne, L.L.C., 
    108 P.3d 297
    , 303 (Colo.
    App. 2004) (Dailey, J., specially concurring) (A party’s offer of
    settlement under section 13-17-102 should include enough
    information “so that the other party is properly alerted to the
    consequences of rejecting the offer.”).
    ¶ 72   Accordingly, we affirm the trial court’s order denying the
    award of costs to Terracon.
    IV.   Conclusion
    ¶ 73   The judgment of the trial court is reversed as to the final
    award and remanded with instructions to apply the setoff to the
    jury damages verdict before applying the contractual limitation, and
    to determine the proper postjudgment interest payable on that
    amount. In all other respects the judgment and orders of the trial
    court are affirmed.
    JUDGE ROMÁN and JUDGE FREYRE concur.
    25