Burton v. Dept. of Environmental Protection ( 2021 )


Menu:
  • ***********************************************
    The “officially released” date that appears near the be-
    ginning of each opinion is the date the opinion will be pub-
    lished in the Connecticut Law Journal or the date it was
    released as a slip opinion. The operative date for the be-
    ginning of all time periods for filing postopinion motions
    and petitions for certification is the “officially released”
    date appearing in the opinion.
    All opinions are subject to modification and technical
    correction prior to official publication in the Connecticut
    Reports and Connecticut Appellate Reports. In the event of
    discrepancies between the advance release version of an
    opinion and the latest version appearing in the Connecticut
    Law Journal and subsequently in the Connecticut Reports
    or Connecticut Appellate Reports, the latest version is to
    be considered authoritative.
    The syllabus and procedural history accompanying the
    opinion as it appears in the Connecticut Law Journal and
    bound volumes of official reports are copyrighted by the
    Secretary of the State, State of Connecticut, and may not
    be reproduced and distributed without the express written
    permission of the Commission on Official Legal Publica-
    tions, Judicial Branch, State of Connecticut.
    ***********************************************
    NANCY BURTON v. DEPARTMENT
    OF ENVIRONMENTAL
    PROTECTION
    ET AL.
    NANCY BURTON v. COMMISSIONER
    OF ENVIRONMENTAL
    PROTECTION
    ET AL.
    (SC 20466)
    Robinson, C. J., and McDonald, Mullins, Kahn and Keller, Js.
    Syllabus
    The plaintiff brought an action under the Connecticut Environmental Protec-
    tion Act of 1971 (CEPA) (§ 22a-14 et seq.) against the Commissioner of
    Environmental Protection and D Co., the owner and operator of a nuclear
    power plant in Waterford, seeking, inter alia, an injunction requiring
    the power plant to convert to a closed-cycle cooling system. The plaintiff
    previously had intervened in a proceeding before the Department of
    Environmental Protection to challenge the department’s tentative deter-
    mination to renew a permit authorizing D Co. to withdraw water from
    Niantic Bay, cycle it through the power plant, and then discharge it into
    the Long Island Sound. In her CEPA action, the plaintiff claimed, inter
    alia, that the permit renewal proceeding was inadequate to protect the
    rights recognized by CEPA and that the current operation of the power
    plant would result in unreasonable pollution. The trial court rendered
    judgment dismissing the plaintiff’s CEPA action for lack of standing.
    The plaintiff appealed, and this court reversed the trial court’s judgment,
    concluding that the plaintiff did have standing. Thereafter, the permit
    renewal proceeding continued, and, in 2010, after the department con-
    ducted an evidentiary hearing, the hearing officer issued a proposed final
    decision, in which the hearing officer recommended that the department
    issue a permit. The department subsequently issued the permit, and the
    plaintiff filed an administrative appeal against the department and D
    Co., claiming, inter alia, that the department failed to make a legally
    valid best technology available determination. The administrative appeal
    was then consolidated with the plaintiff’s CEPA action. Thereafter, the
    commissioner and D Co. filed motions to dismiss the CEPA action on
    the ground that it was moot, which the trial court granted. The plaintiff
    appealed from the judgment of dismissal, and this court reversed that
    judgment. On remand, the trial court conducted a hearing on the merits
    of the consolidated actions and rendered judgments in favor of the
    commissioner, the department and D Co. The plaintiff appealed, claim-
    ing, inter alia, that the trial court incorrectly concluded that she had
    failed to prove that the administrative proceeding was inadequate and
    that the operation of the power plant would result in unreasonable
    pollution. Held:
    1. The plaintiff’s claim that the administrative proceeding was inadequate
    to protect the rights recognized by CEPA was unavailing:
    a. The plaintiff could not prevail on her claim that the administrative
    proceeding was inadequate insofar as the hearing officer precluded cer-
    tain claims on which the plaintiff sought to intervene: the hearing officer
    did not abuse her discretion by precluding the plaintiff’s claim challenging
    the permit renewal application on the ground that it failed to implement
    the best technology available, as that claim was duplicative of several
    other claims, and the hearing officer fully considered the plaintiff’s argu-
    ments on this issue; moreover, the hearing officer did not abuse her
    discretion by precluding three additional claims of the plaintiff on the
    ground that they raised issues that were outside the department’s jurisdic-
    tion, as these claims involved matters that were regulated exclusively
    by the federal government, and two of those claims, which raised issues
    concerning federal criminal law and employment practices, were not
    related to environmental issues.
    b. The plaintiff’s claim that the administrative proceeding was inadequate
    because the hearing officer had excluded a 2007 document containing
    a draft best technology available determination was unavailing: contrary
    to the plaintiff’s claim, the department was previously directed by this
    court in Fish Unlimited v. Northeast Utilities Service Co. (
    254 Conn. 1
    ) to review all of its prior determinations regarding the cooling system,
    and the plaintiff mischaracterized this court’s language in Fish Unlim-
    ited, which was not an order but, rather, an explanation of what the
    department would be required to do to renew the permit pursuant to
    the applicable statutory scheme; moreover, the hearing officer’s decision
    to exclude this document was not improper because there was nothing
    in the document or testimony to support its credibility, unlike other
    drafts of the permit, which were formally circulated by the department,
    authenticated, signed by their drafters, and admitted at the hearing.
    c. The plaintiff could not prevail on her claim challenging the neutrality
    of the administrative proceeding on the ground that the hearing officer
    was biased, colluded with D Co. to issue the permit without any consider-
    ation of the closed-cycle cooling system, and prejudged the plaintiff’s
    challenge to the permit’s best technology available determination; the
    plaintiff’s claim was inadequately briefed, as her allegations regarding
    bias were speculative and lacked citations to the administrative record,
    and the plaintiff’s arguments concerning the allegations contained no
    relevant legal authority and were cursorily scattered across different
    headings and sections of her brief.
    2. This court declined to review the plaintiff’s claim that she established that
    unreasonable pollution would result from the power plant’s operation
    as permitted and claim that the permit’s best technology available deter-
    mination violated the Clean Water Act, as they were inadequately briefed:
    the plaintiff provided only minimal citation to the trial or administrative
    record in support of these claims, and she provided no citation to any
    legal authority to define ‘‘unreasonable pollution’’ under CEPA, to define
    ‘‘best technology available’’ under the Clean Water Act, or to support
    either claim; moreover, this court declined to address the plaintiff’s
    claim that the trial court failed to follow this court’s prior remand order
    when it conducted a single hearing because the claim was inadequately
    briefed, as the plaintiff’s briefing of this claim was inconsistent and
    nearly incomprehensible.
    Argued September 10, 2020—officially released January 21, 2021*
    Procedural History
    Action, in the second case, for a temporary injunction
    in connection with the intake and discharge of water
    from the Long Island Sound and nearby bodies of water
    by the defendant Dominion Nuclear Connecticut, Inc.,
    the owner and operator of Millstone Nuclear Power
    Station, and for other relief, brought to the Superior
    Court in the judicial district of Hartford, where the
    court, Tanzer, J., granted the defendants’ motions to
    dismiss and rendered judgment thereon in their favor,
    from which the plaintiff appealed; thereafter, this court
    reversed the trial court’s judgment in the second case
    and remanded that case for further proceedings; admin-
    istrative appeal, in the first case, from the decision of
    the named defendant approving the application of the
    defendant Dominion Nuclear Connecticut, Inc., to
    renew its water discharge permit, brought to the Supe-
    rior Court in the judicial district of Danbury, where the
    case was transferred to the judicial district of Hartford;
    subsequently, the cases were consolidated; thereafter,
    the court, Sheridan, J., granted the defendants’ motions
    to dismiss the action in the second case and rendered
    judgment thereon in their favor, from which the plaintiff
    appealed; subsequently, this court reversed the trial
    court’s judgment in the second case and remanded that
    case for further proceedings; on remand, the cases were
    tried to the court, Moukawsher, J.; judgments for the
    defendants, from which the plaintiff appealed.
    Affirmed.
    Nancy Burton, self-represented, the appellant (plain-
    tiff).
    Matthew I. Levine, assistant attorney general, with
    whom were Daniel M. Salton, assistant attorney gen-
    eral, and, on the brief, William Tong, attorney general,
    and Claire E. Kindall, solicitor general, for the appel-
    lees (named defendants in the first and second cases).
    Elizabeth C. Barton, with whom were Harold M.
    Blinderman and, on the brief, Taylor C. Amato, for the
    appellee (defendant Dominion Nuclear Connecticut,
    Inc.).
    Opinion
    McDONALD, J. This case comes to us for the third
    time following lengthy and highly contested litigation.
    The plaintiff, Nancy Burton, brought an action under
    the Connecticut Environmental Protection Act of 1971
    (CEPA), General Statutes § 22a-14 et seq., against the
    defendants, the Commissioner of Environmental Pro-
    tection1 and Dominion Nuclear Connecticut, Inc., and
    an administrative appeal under General Statutes § 4-
    183 (a) against the defendants, the Department of Envi-
    ronmental Protection2 and Dominion. The actions, now
    consolidated, claim, in part, that the operation of the
    Millstone Nuclear Power Station (plant), which is
    owned and operated by Dominion, is causing unreason-
    able pollution of the waters of the state in violation of
    CEPA. Specifically, the plaintiff challenged the depart-
    ment’s decision to issue a National Pollutant Discharge
    Elimination System permit to Dominion to authorize
    the intake and discharge of water by the plant, claiming
    that the permit renewal proceeding was inadequate to
    protect the rights recognized by CEPA. The trial court
    previously dismissed the plaintiff’s CEPA action for lack
    of standing, which this court reversed in Burton v.
    Commissioner of Environmental Protection, 
    291 Conn. 789
    , 
    970 A.2d 640
     (2009) (Burton I). Thereafter,
    the trial court again dismissed the plaintiff’s CEPA
    action, this time concluding that the action was moot
    because the permit renewal proceeding had terminated.
    This court reversed that decision in Burton v. Commis-
    sioner of Environmental Protection, 
    323 Conn. 668
    , 
    150 A.3d 666
     (2016) (Burton II). On remand from Burton
    II, the trial court conducted a hearing on the merits of
    the plaintiff’s CEPA claim and administrative appeal
    and rendered judgments in favor of the defendants. The
    plaintiff now appeals from those judgments, claiming,
    among other things, that the trial court incorrectly con-
    cluded that she failed to prove that the administrative
    proceeding was inadequate and the operation of the
    plant would result in unreasonable pollution.
    Our decisions in Burton I and Burton II, as supple-
    mented by the record, set forth the following relevant
    facts and procedural history. The plant is a nuclear
    power facility located in Waterford. The plant has a
    once-through cooling system in which it draws water
    from Niantic Bay, cycles it once through the plant, then
    discharges the hot water into the Long Island Sound.
    The plaintiff alleges that this process draws approxi-
    mately two billion gallons of water per day. These activi-
    ties are authorized by a permit that the department
    issued to the owner of the plant—currently, Domin-
    ion—pursuant to the federal Clean Water Act, 
    33 U.S.C. § 1251
     et seq.3
    In 1992, the department issued a five year permit
    authorizing the plant’s water intakes and discharges.
    After it expired, the plant continued to operate under
    that permit’s terms while the department processed
    Dominion’s timely permit renewal application pursuant
    to General Statutes § 4-182 (b). In 2006, the department
    issued a notice of tentative determination to renew the
    permit, which triggered the public aspect of the permit
    renewal proceeding. The plaintiff filed a timely notice
    of intervention in the permit renewal proceeding pursu-
    ant to General Statutes (Rev. to 2005) § 22a-19, as
    amended by No. 06-196, § 256, of the 2006 Public Acts.4
    She claimed, among other things, that the plant’s opera-
    tion, as permitted, would result in unreasonable pollu-
    tion because it would ‘‘entrain and impinge [marine
    life], a natural resource of vital import[ance] to the
    state’’; (internal quotation marks omitted) Burton v.
    Commissioner of Environmental Protection, supra,
    
    291 Conn. 794
    ; and ‘‘continuously release vast quantities
    of hot water [in]to the Long Island Sound . . . .’’ (Inter-
    nal quotation marks omitted.) 
    Id.,
     794–95. She claimed
    that these activities would ‘‘continue the process by
    which indigenous fish stocks have been devastated’’;
    (internal quotation marks omitted) id., 794; and that
    converting the plant’s current cooling system to a
    closed-cycle cooling system ‘‘would virtually eliminate
    waterborne adverse impacts to the marine environment
    . . . .’’ (Internal quotation marks omitted.) Id., 795. The
    hearing officer allowed the plaintiff to intervene on
    certain claims but precluded numerous other claims
    that the plaintiff raised concerning Dominion’s and the
    department’s alleged collusion and illegal activities, as
    well as the plant’s alleged radioactive pollution. At every
    stage of the proceedings, the plaintiff has argued that
    the plant should convert to a closed-cycle cooling sys-
    tem. This cooling system would recirculate the water
    used to cool the plant and result in significantly less
    water intake and discharge. See, e.g., Entergy Corp. v.
    Riverkeeper, Inc., 
    556 U.S. 208
    , 214 n.2, 
    129 S. Ct. 1498
    ,
    
    173 L. Ed. 2d 369
     (2009).
    In 2007, while the permit renewal proceeding was
    ongoing, the plaintiff brought the first action against
    the commissioner under CEPA, General Statutes § 22a-
    16.5 She claimed, among other things, that (1) the permit
    renewal proceeding was inadequate to protect the rights
    recognized by CEPA, and (2) the current operation of
    the plant would result in unreasonable pollution. She
    sought, among other remedies, an injunction requiring
    the plant to convert to a closed-cycle cooling system.
    The trial court dismissed this action, holding that the
    plaintiff lacked standing under § 22a-16 because her
    claim arose from a permitting proceeding. The plaintiff
    appealed, and this court reversed. We concluded that
    the plaintiff had standing for her claim under § 22a-16
    because her complaint ‘‘sets forth facts to support an
    inference that unreasonable pollution, impairment or
    destruction of a natural resource will probably result
    from [the plant’s] operation.’’ Burton v. Commissioner
    of Environmental Protection, supra, 
    291 Conn. 804
    . We
    also reasoned that the ongoing permit renewal proceed-
    ing did not preclude the plaintiff’s action when, as here,
    the plaintiff claimed ‘‘that the permit renewal proceed-
    ing is inadequate to protect the rights recognized by
    [CEPA] . . . .’’ Id., 812. We remanded the case, direct-
    ing the trial court to afford the plaintiff an opportunity
    to establish that the permit renewal proceeding was
    inadequate to protect the rights recognized by CEPA
    and, if appropriate, to stay that administrative proceed-
    ing. Id., 813.
    Meanwhile, the permit renewal proceeding contin-
    ued. In 2008, the department introduced a revised draft
    permit, which was the product of negotiations between
    Dominion and various environmental organizations that
    had also intervened in the administrative proceeding.
    The department conducted an evidentiary hearing on
    the permit renewal over the course of eighteen days in
    January and February, 2009. During the hearing, the
    plaintiff offered the testimony of two fact witnesses,
    including herself. She also extensively cross-examined
    all of Dominion’s and the department’s witnesses. Addi-
    tionally, the plaintiff offered approximately sixty-one
    exhibits, one of which was initially admitted as a full
    exhibit but was subsequently excluded.
    In 2010, the hearing officer issued her proposed final
    decision6 pursuant to General Statutes (Rev. to 2009)
    § 4-179 (c), in which she recommended that the depart-
    ment issue the revised draft permit. The plaintiff filed
    exceptions to the proposed final decision. The depart-
    ment’s deputy commissioner, who was charged with
    rendering a final decision on the contested permit
    renewal, rejected the plaintiff’s arguments. Thereafter,
    the deputy commissioner issued the permit.7
    The 2010 permit is the center of this dispute. The
    Clean Water Act required the department to determine,
    in its best professional judgment, that the plant’s cool-
    ing system, as permitted, reflects ‘‘the best technology
    available [BTA] for minimizing adverse environmental
    impact.’’ 
    33 U.S.C. § 1326
     (b) (2018); see Natural
    Resources Defense Council, Inc. v. United States Envi-
    ronmental Protection Agency, 
    822 F.2d 104
    , 111 (D.C.
    Cir. 1987) (‘‘[i]f no national standards have been promul-
    gated . . . the permit writer is authorized to use, on a
    case-by-case basis, [the permit writer’s] ‘best profes-
    sional judgment’ to impose’’ applicable effluent limita-
    tions that comply with Clean Water Act). The 2010 per-
    mit evaluated the operation of the plant’s cooling
    system and concluded that it did not reflect the BTA.
    The permit recognized that requiring the plant to con-
    vert to a closed-cycle cooling system, as sought by the
    plaintiff, would reflect the BTA, but the permit declined
    to require the plant to convert to that cooling system
    because the department could not evaluate the feasibil-
    ity of such a requirement. Instead, the permit imposed
    a series of other technological requirements to mitigate
    the current cooling system’s environmental impact. The
    permit also required specific studies to ascertain the
    feasibility of converting the plant to a closed-cycle cool-
    ing system, the results of which may trigger a ‘‘subse-
    quent BTA determination by the commissioner . . . .’’
    In evaluating the permit’s compliance with CEPA and
    the Clean Water Act, the hearing officer and the deputy
    commissioner each concluded that the plant’s current
    cooling system and the additional studies and technol-
    ogy requirements together reflected the BTA. The dep-
    uty commissioner noted that ‘‘the BTA in the present
    case is not a single technology but, rather, a combina-
    tion of various technologies, studies, and commit-
    ments.’’
    Following the department’s issuance of the 2010 per-
    mit, the plaintiff timely filed the second action, an
    administrative appeal from the department’s permit
    renewal under § 4-183 (a).8 The plaintiff claimed, among
    other things, that the final decision and permit failed
    to make a legally valid BTA determination. This action
    was consolidated with the plaintiff’s earlier CEPA
    action.
    Thereafter, the defendants moved to dismiss the
    CEPA action, arguing that it was moot because the
    permit renewal proceeding had terminated. The trial
    court granted the defendants’ motions to dismiss, rea-
    soning that, with the conclusion of the administrative
    proceeding, the court lacked authority to grant equita-
    ble relief consistent with this court’s remand in Burton
    I. The plaintiff appealed, and this court reversed, con-
    cluding that ‘‘the present action is not moot because a
    controversy continues to exist between the parties’’;
    Burton v. Commissioner of Environmental Protection,
    
    supra,
     
    323 Conn. 677
    ; and ‘‘[t]he issuance of the renewal
    permit did not resolve or terminate these controversies,
    and they continue to exist.’’ Id., 678. We also recognized
    that, if the plaintiff prevailed, the trial court’s authority
    to issue an appropriate remedy would not be limited
    to staying the administrative proceeding; rather, the
    court would have the authority to adjudicate the impact
    of the plant’s operation and issue appropriate equitable
    relief. See id. Accordingly, we remanded the case; id.,
    684; directing the trial court to determine ‘‘whether the
    permit renewal proceeding was inadequate because the
    department misinterpreted or misapplied the applicable
    environmental law and, if the hearing is determined to
    have been inadequate, [to] . . . order . . . appro-
    priate declaratory or equitable relief.’’ Id., 679 n.7. We
    further emphasized that ‘‘we express[ed] no opinion
    . . . regarding’’ the appropriate procedures for litigat-
    ing the CEPA action and administrative appeal, as con-
    solidated. Id.
    In 2018, following our remand in Burton II, the trial
    court held a single, four day hearing on the merits of
    the two consolidated actions. The trial court rendered
    judgments for the defendants in both actions. It con-
    cluded that the plaintiff did not establish that the plant’s
    operation, as permitted, resulted in unreasonable pollu-
    tion. It also concluded that the plaintiff failed to estab-
    lish that the administrative proceeding contained proce-
    dural irregularities or was otherwise inadequate to
    protect the rights recognized by CEPA. The trial court
    also disagreed with the plaintiff’s challenge to the per-
    mit’s BTA determination, reasoning that the deputy
    commissioner, in her final decision, ‘‘conclude[d] that
    the technology proposed for [the plant] meets the Clean
    Water Act requirement of [BTA].’’
    The plaintiff filed a motion for mistrial, claiming,
    among other things, that the remand in Burton II
    required the trial court to hold a hearing first on the
    adequacy of the administrative proceeding and then a
    distinct hearing on the issue of unreasonable pollution.
    The trial court denied the plaintiff’s motion. The plain-
    tiff appealed from the judgments of the trial court to
    the Appellate Court, and the appeal was transferred to
    this court pursuant to General Statutes § 51-199 (c) and
    Practice Book § 65-1. Additional relevant facts will be
    set forth as necessary.
    Although the plaintiff’s brief appears to assert six
    arguments, they are not clearly articulated, and they
    are more properly distilled into four claims. First, the
    plaintiff argues that the trial court incorrectly con-
    cluded that she failed to establish that the administra-
    tive proceeding was inadequate to protect the rights
    recognized by CEPA. Second, the plaintiff argues that
    the trial court improperly held that she failed to estab-
    lish that unreasonable pollution would result from the
    plant’s operation. Third, the plaintiff argues that the
    trial court incorrectly concluded that the department’s
    BTA determination did not violate the Clean Water Act.
    Finally, the plaintiff argues that the trial court violated
    this court’s remand order in Burton II by failing to
    follow the prescribed two step proceeding. The defen-
    dants argue that the plaintiff has inadequately briefed
    all of her claims. They also argue, in the alternative,
    that the trial court’s procedures and substantive hold-
    ings were proper. We agree with the defendants that
    the majority of the plaintiff’s claims are inadequately
    briefed, and we conclude that those claims that are
    adequately briefed lack merit.9
    I
    We begin with the plaintiff’s claim that the administra-
    tive proceeding was inadequate to protect the rights
    recognized by CEPA.10 Although not clearly explained
    in her brief, the plaintiff appears to raise three argu-
    ments in support of her claim: the plaintiff challenges
    (1) the hearing officer’s decision to preclude certain
    claims on which the plaintiff sought to intervene, (2)
    the hearing officer’s decision to exclude certain evi-
    dence that the plaintiff sought to admit, and (3) the
    neutrality of the proceeding. We address each argument
    in turn.
    A
    The plaintiff first argues that the administrative pro-
    ceeding was inadequate because the hearing officer
    precluded certain claims on which she sought to inter-
    vene. Specifically, the plaintiff asserts that paragraphs
    5B, 5F, 5J and 5K of her notice of intervention were
    improperly precluded. Because the plaintiff does not
    reference the hearing officer’s preclusion of any of her
    other claims, we confine our analysis to those claims
    enumerated in the plaintiff’s brief.
    Paragraph 5B alleged that granting the permit
    renewal application would result in the release of toxic
    and radioactive substances into the Long Island Sound.
    Paragraph 5F alleged that ‘‘[t]he application violates
    the federal Clean Water Act in that it fails to implement
    the [BTA] to avoid unnecessary adverse impacts and
    in other respects.’’ Paragraph 5J baldly alleged that
    Dominion had pleaded ‘‘guilty to committing federal
    felonies’’ due to falsifying environmental monitoring
    reports, releasing carcinogens, and violating permit
    conditions. Paragraph 5K alleged, also with little con-
    text, that Dominion had a ‘‘track record of firing whis-
    tleblowers in retaliation for their truth telling and expo-
    sure’’ of information about the plant’s operation. The
    hearing officer precluded these four claims, among oth-
    ers, because they contained ‘‘allegations that are either
    not relevant to this proceeding, redundant, or have been
    previously resolved,’’ and because they raised issues
    that were ‘‘beyond the scope of the application before
    [the hearing officer] or are otherwise not within the
    jurisdiction of [the department].’’ For its part, the trial
    court noted that the ‘‘hearing officer heard, in one fash-
    ion or another, all of the substantive issues [the plaintiff]
    complains about, including the issue of the closed-cycle
    [cooling] system.’’ The plaintiff argues that preclusion
    of these claims contributed to the inadequacy of the
    administrative proceeding because she was unable to
    raise issues relevant to the contested permit renewal
    decision. The defendants argue that the hearing officer
    correctly concluded that the department lacked juris-
    diction over the precluded claims.
    We begin with the applicable legal principles govern-
    ing a party’s intervention in an administrative proceed-
    ing. Section 22a-19 (a) provides in relevant part: ‘‘In
    any administrative . . . proceeding . . . any person
    . . . may intervene as a party on the filing of a verified
    pleading asserting that the proceeding . . . involves
    conduct which has, or which is reasonably likely to
    have, the effect of unreasonably polluting, impairing or
    destroying the public trust in the air, water or other
    natural resources of the state.’’ In addition, the depart-
    ment’s rules of practice provide that the hearing officer
    in a contested case has discretion to ‘‘restrict the partici-
    pation in the proceeding of [an intervenor], although
    only to the extent necessary to promote justice and the
    orderly conduct of the proceeding.’’ Regs., Conn. State
    Agencies § 22a-3a-6 (k) (7). We therefore consider
    whether the hearing officer abused her discretion by
    precluding the plaintiff’s claims. See, e.g., Board of
    Selectmen v. Freedom of Information Commission, 
    294 Conn. 438
    , 446, 
    984 A.2d 748
     (2010) (‘‘[o]ur ultimate
    duty is to determine, in view of all of the evidence,
    whether the agency, in issuing its order, acted . . .
    in abuse of its discretion’’ (internal quotation marks
    omitted)).
    We conclude that the hearing officer did not abuse
    her discretion by precluding these four claims. First,
    paragraph 5F, which challenged the permit renewal
    application because it failed to implement the BTA, was
    duplicative of several of the claims on which the hearing
    officer permitted the plaintiff to intervene. In particular,
    the hearing officer considered the plaintiff’s challenge
    regarding the proper implementation of the BTA under
    paragraph 6, which asserted the diminished environ-
    mental impact of a closed-cycle cooling system. The
    hearing officer then issued a detailed ruling that the
    plaintiff had failed to establish a prima facie showing
    of unreasonable pollution. Because paragraph 5F was
    duplicative of several other claims and the hearing offi-
    cer fully considered the plaintiff’s arguments on this
    point, the hearing officer did not abuse her discretion
    by precluding it.
    In addition, we conclude that it was not an abuse of
    discretion for the hearing officer to preclude paragraphs
    5B, 5J and 5K on the ground that they raised issues that
    were outside the department’s jurisdiction. We have
    repeatedly explained that ‘‘[CEPA] grants standing to
    intervenors to raise only those environmental concerns
    that are within the jurisdiction of the particular adminis-
    trative agency conducting the proceeding [in] which
    the party seeks to intervene.’’ Nizzardo v. State Traffic
    Commission, 
    259 Conn. 131
    , 148, 
    788 A.2d 1158
     (2002).
    In 2006, when the plaintiff filed her notice of interven-
    tion, the department had jurisdiction over ‘‘all matters
    relating to the preservation and protection of the air,
    water and other natural resources of the state.’’ General
    Statutes (Rev. to 2005) § 22a-2 (a).11 Because radiologi-
    cal discharge by nuclear power plants is regulated
    exclusively by the federal government, the hearing offi-
    cer’s decision to preclude paragraph 5B for lack of
    jurisdiction was not an abuse of discretion. See Burton
    v. Dominion Nuclear Connecticut, Inc., 
    300 Conn. 542
    ,
    552, 
    23 A.3d 1176
     (2011) (holding, in distinct action
    brought by plaintiff against Dominion, that federal law
    preempted regulation of radiological safety at nuclear
    power plants); see also Pacific Gas & Electric Co. v.
    State Energy Resources Conservation & Development
    Commission, 
    461 U.S. 190
    , 212, 
    103 S. Ct. 1713
    , 
    75 L. Ed. 2d 752
     (1983) (‘‘the [f]ederal [g]overnment maintains
    complete control of the safety and ‘nuclear’ aspects of
    energy generation’’). Regarding paragraphs 5J and 5K,
    federal criminal law and employment practices are like-
    wise outside the department’s jurisdiction.
    Moreover, under CEPA, intervention in administra-
    tive proceedings is limited to claims asserting certain
    environmental issues. See Pond View, LLC v. Plan-
    ning & Zoning Commission, 
    288 Conn. 143
    , 159, 
    953 A.2d 1
     (2008) (‘‘it is axiomatic that [§ 22a-19] encom-
    passes substantive environmental issues only’’). The
    plaintiff does not connect her allegations in paragraphs
    5J and 5K to any such environmental issue. Accordingly,
    it was not an abuse of discretion for the hearing officer
    to preclude these claims.
    B
    The plaintiff next argues that the administrative pro-
    ceeding was inadequate because the hearing officer
    excluded certain evidence that the plaintiff sought to
    introduce. Specifically, the plaintiff identifies a docu-
    ment that she alleges is a draft BTA determination pre-
    pared by department staff, dated September 10, 2007.12
    This document asserts that the closed-cycle cooling
    system satisfies the BTA requirement in the Clean
    Water Act.
    The following additional facts are relevant to our
    analysis. At the administrative hearing, the plaintiff
    sought to introduce the September 10, 2007 document
    during her cross-examination of a Dominion witness,
    but the hearing officer declined to enter it as a full
    exhibit. The hearing officer noted that it was not authen-
    ticated, and, therefore, it was not credible. She observed
    that it was not typed on department letterhead; nor was
    it signed to otherwise indicate its source. The plaintiff
    asserted that the unidentified person who gave her the
    document told her that it was prepared by department
    staff. The hearing officer noted that, without testimony
    by the person who gave the plaintiff the document,
    her assertion was hearsay. Finally, the hearing officer
    concluded that there was no foundation to introduce
    the document as an exhibit because there was nothing
    to link the document to the witness the plaintiff was
    cross-examining.13
    On appeal, the plaintiff appears to argue that the
    exclusion of this document rendered the administrative
    proceeding inadequate for two reasons. First, the plain-
    tiff challenges the hearing officer’s evidentiary ruling
    that the document lacked credibility. Second, the plain-
    tiff argues that the exclusion of this document rendered
    the administrative proceeding inadequate because the
    department was previously ordered by this court to
    ‘‘review all of [the department’s] prior determinations
    that [the plant’s] cooling system is consistent with the
    provisions of the . . . Clean Water Act, which requires
    that the cooling water intake structure represent [the
    BTA] for minimizing environmental impacts.’’ (Internal
    quotation marks omitted.) Fish Unlimited v. Northeast
    Utilities Service Co., 
    254 Conn. 1
    , 14, 
    756 A.2d 262
    (2000), overruled in part on other grounds by Waterbury
    v. Washington, 
    260 Conn. 506
    , 
    800 A.2d 1102
     (2002). In
    Fish Unlimited, which was decided before the permit
    renewal proceeding began, several environmental orga-
    nizations sought an injunction against the prior owners
    and operators of the plant requiring it to convert to a
    closed-cycle cooling system. See 
    id.,
     3 and nn.1 and 2;
    see also 
    id., 9
    . In upholding the trial court’s dismissal
    of the complaint, this court reasoned that the environ-
    mental organizations were first required to exhaust the
    administrative remedies available through the permit
    renewal proceeding. 
    Id.,
     19–21. Although the holding
    in Fish Unlimited regarding the applicability of the
    exhaustion doctrine has since been overturned; see
    Waterbury v. Washington, supra, 545; the plaintiff
    argues that this court ordered the department to review
    prior BTA determinations in the permit renewal pro-
    ceeding, which it failed to do by excluding the Septem-
    ber 10, 2007 draft BTA determination.
    The defendants contend that exclusion of this docu-
    ment was not an abuse of discretion in light of the
    hearing officer’s role to evaluate the reliability of evi-
    dence. Dominion also argues that the plaintiff has not
    shown how the hearing officer’s evidentiary ruling
    affected the outcome of the permit renewal proceeding
    in light of the expansive administrative record. For their
    part, the department and the commissioner argue that
    the passages the plaintiff cites from Fish Unlimited
    ‘‘were not intended to instruct the department on the
    substantive requirements of a hearing.’’
    Resolution of this claim is controlled by well settled
    principles. Under the department’s rule governing con-
    tested cases, a hearing officer in a contested case has
    the discretionary power to ‘‘[a]dmit or exclude evidence
    and rule on objections to evidence . . . .’’ Regs., Conn.
    State Agencies § 22a-3a-6 (d) (2) (E). In addition, ‘‘[t]he
    hearing officer shall not admit any evidence which is
    irrelevant, immaterial, unduly repetitious, untrustwor-
    thy, or unreliable.’’14 (Emphasis added.) Id., § 22a-3a-
    6 (s) (1). Moreover, ‘‘administrative tribunals are not
    strictly bound by the rules of evidence and . . . they
    may consider evidence which would normally be incom-
    petent in a judicial proceeding, as long as the evidence
    is reliable and probative.’’ Tomlin v. Personnel Appeal
    Board, 
    177 Conn. 344
    , 348, 
    416 A.2d 1205
     (1979); see
    also, e.g., Connecticut Fund for the Environment, Inc.
    v. Stamford, 
    192 Conn. 247
    , 249, 
    470 A.2d 1214
     (1984)
    (‘‘Although proceedings before administrative agencies
    . . . are informal and are conducted without regard
    to the strict rules of evidence, the hearings must be
    conducted so as not to violate the fundamental rules
    of natural justice. . . . Due process of law requires not
    only that there be due notice of the hearing but that at
    the hearing the parties involved have a right to produce
    relevant evidence, and an opportunity to know the facts
    on which the agency is asked to act, to cross-examine
    witnesses and to offer rebuttal evidence.’’ (Citation
    omitted.)). ‘‘It is within the province of the hearing
    officer to determine the credibility of evidence. . . .
    The plaintiff bears the burden of demonstrating that a
    hearing officer’s evidentiary ruling is arbitrary, illegal
    or an abuse of discretion.’’ (Citation omitted; internal
    quotation marks omitted.) Roy v. Commissioner of
    Motor Vehicles, 
    67 Conn. App. 394
    , 397, 
    786 A.2d 1279
     (2001).
    We disagree with both of the plaintiff’s arguments
    regarding the September 10, 2007 document. First, the
    plaintiff mischaracterizes this court’s language from
    Fish Unlimited. Our statement that ‘‘the department
    must review all of its prior determinations [regarding
    the cooling system]’’; Fish Unlimited v. Northeast Utili-
    ties Service Co., supra, 
    254 Conn. 14
    ; was not an order;
    rather, it was an explanation of what the department
    would be required to do to renew the permit pursuant
    to the applicable statutory scheme. We described this
    process to explain that, contrary to the arguments
    raised by the plaintiff environmental organizations, the
    permit renewal proceeding would not be futile, and
    the department would have the authority to grant the
    requested relief. See 
    id.,
     14–15. Contrary to the plain-
    tiff’s argument, excluding this document did not
    ‘‘def[y]’’ any ‘‘order’’ from this court.
    Second, the hearing officer’s decision to exclude this
    document was not improper because there was nothing
    in the document or testimony to support its credibility.
    This contrasts with the other drafts of the permit, which
    were formally circulated by the department, authenti-
    cated, signed by their drafters, and admitted at the
    hearing. The department’s regulations require a hearing
    officer to exclude evidence that is ‘‘untrustworthy, or
    unreliable’’; Regs., Conn. State Agencies § 22a-3a-6 (s)
    (1); and the plaintiff has not explained how the hearing
    officer’s evidentiary ruling regarding the document’s
    credibility was improper, particularly in light of the
    document’s low probative value.
    C
    Finally, with respect to the adequacy of the proceed-
    ing, the plaintiff challenges the neutrality of the adminis-
    trative proceeding. Specifically, she argues that the
    hearing officer was biased, colluded with Dominion to
    issue the permit without any consideration of the
    closed-cycle cooling system, and prejudged the plain-
    tiff’s challenge to the permit’s BTA determination. The
    defendants argue that the plaintiff’s claim is inade-
    quately briefed because it is conclusory, speculative,
    and without citations to the administrative record. They
    also argue, in the alternative, that the hearing officer’s
    conduct was proper and that, even if there were any
    procedural irregularities, the plaintiff failed to show
    how she was harmed by them.
    We agree with the defendants that this claim is inade-
    quately briefed. The plaintiff’s allegations of the hearing
    officer’s bias are speculative and contain no citations
    to the record.15 See, e.g., Connecticut Coalition Against
    Millstone v. Connecticut Siting Council, 
    286 Conn. 57
    ,
    87, 
    942 A.2d 345
     (2008) (‘‘mere conclusory assertions
    regarding a claim, with no mention of relevant authority
    and minimal or no citations from the record, [are inade-
    quately briefed]’’). Additionally, the plaintiff’s argument
    contains no legal authority discussing the circum-
    stances under which an agency’s action may be invali-
    dated for bias, collusion, or prejudgment. Finally, the
    plaintiff’s argument on this claim is cursorily scattered
    across different headings and sections of her brief, mak-
    ing it short and difficult to comprehend. As such, we
    conclude that it is inadequately briefed.
    II
    The plaintiff raises three additional claims on appeal.
    First, she claims that she established that unreasonable
    pollution would result from the plant’s operation as
    permitted. Second, she claims that the permit’s BTA
    determination violates the Clean Water Act. Specifi-
    cally, the plaintiff argues that the permit functionally
    makes no valid BTA determination at all because it
    determines that the current cooling system does not
    meet the BTA requirement, yet it declines to require
    the plant to convert to the superior cooling system.
    Third, the plaintiff claims that the trial court failed to
    follow this court’s remand order in Burton II when it
    conducted a single hearing on the merits of her actions.
    The defendants contend that each of these claims is
    inadequately briefed. We agree with the defendants.
    ‘‘We repeatedly have stated that [w]e are not required
    to review issues that have been improperly presented
    to this court through an inadequate brief. . . . Analy-
    sis, rather than mere abstract assertion, is required in
    order to avoid abandoning an issue by failure to brief
    the issue properly. . . . [When] a claim is asserted in
    the statement of issues but thereafter receives only
    cursory attention in the brief without substantive dis-
    cussion or citation of authorities, it is deemed to be
    abandoned.’’ (Internal quotation marks omitted.) Con-
    necticut Light & Power Co. v. Dept. of Public Utility
    Control, 
    266 Conn. 108
    , 120, 
    830 A.2d 1121
     (2003). For
    a reviewing court to ‘‘judiciously and efficiently . . .
    consider claims of error raised on appeal . . . the par-
    ties must clearly and fully set forth their arguments in
    their briefs.’’ (Internal quotation marks omitted.) State
    v. Buhl, 
    321 Conn. 688
    , 724, 
    138 A.3d 868
     (2016). In
    addition, briefing is inadequate when it is ‘‘not only
    short, but confusing, repetitive, and disorganized.’’
    Id., 726.
    We are mindful that ‘‘[i]t is the established policy of
    the Connecticut courts to be solicitous of [self-repre-
    sented] litigants and when it does not interfere with the
    rights of other parties to construe the rules of practice
    liberally in favor of the [self-represented] party. . . .
    Nonetheless, [a]lthough we allow [self-represented] liti-
    gants some latitude, the right of self-representation pro-
    vides no attendant license not to comply with relevant
    rules of procedural and substantive law.’’ (Citation
    omitted; internal quotation marks omitted.) New Haven
    v. Bonner, 
    272 Conn. 489
    , 497–98, 
    863 A.2d 680
     (2005).
    Moreover, ‘‘[a]n appellant cannot . . . rely on the
    appellee to decipher the issues and explain them to
    the [reviewing court].’’ State v. Buhl, supra, 
    321 Conn. 728
    –29; see, e.g., Traylor v. State, 
    332 Conn. 789
    , 806–
    807, 
    213 A.3d 467
     (2019) (‘‘[w]e acknowledge that the
    plaintiff is a self-represented party and that it is the
    established policy of the Connecticut courts to be solici-
    tous of [self-represented] litigants . . . [but] a litigant
    on appeal [is not] relieved of the obligation to suffi-
    ciently articulate a claim so that it is recognizable to a
    reviewing court’’ (citations omitted; internal quotation
    marks omitted)).
    We conclude that the plaintiff’s claims that she estab-
    lished that unreasonable pollution would result from
    the plant’s operation and that the permit’s BTA determi-
    nation violates the Clean Water Act are inadequately
    briefed. The plaintiff provides only minimal citation to
    the trial court record or administrative record in sup-
    port of those claims.16 She provides no citation to any
    legal authority to define ‘‘unreasonable pollution’’ under
    CEPA, define ‘‘best technology available’’ under the
    Clean Water Act, or support either claim. She also pro-
    vides no meaningful analysis for either claim. See, e.g.,
    MacDermid, Inc. v. Leonetti, 
    328 Conn. 726
    , 748, 
    183 A.3d 611
     (2018) (‘‘[a]nalysis, rather than mere abstract
    assertion, is required in order to avoid abandoning an
    issue by failure to brief the issue properly’’ (internal
    quotation marks omitted)). Accordingly, we decline to
    review these claims.
    In addition, we conclude that the plaintiff’s claim that
    the trial court failed to follow this court’s remand order
    in Burton II when it conducted a single hearing is inade-
    quately briefed. As an initial matter, the plaintiff’s brief-
    ing is inconsistent: she asserts that the trial court should
    have conducted a two step proceeding, but she differs
    in what she argues the two steps should be. At one
    point in her brief, the plaintiff argues that the two steps
    should have been (1) a hearing on the merits of her
    claims, and then (2) a hearing on the appropriate relief.
    Later in her brief, the plaintiff argues that the two steps
    should have been (1) a hearing on the merits on the
    inadequacy of the administrative proceeding issue, and
    then (2) a hearing on the merits on the unreasonable
    pollution issue. Given this inconsistency, the plaintiff’s
    argument on this claim is nearly incomprehensible. See,
    e.g., State v. Buhl, supra, 
    321 Conn. 726
     (declining to
    review claim that was ‘‘not only short, but confusing,
    repetitive, and disorganized’’); see also, e.g., Birch v.
    Polaris Industries, Inc., 
    812 F.3d 1238
    , 1249 (10th Cir.
    2015) (declining to review claim that was ‘‘vague, con-
    fusing, [and] conclusory’’). Additionally, the plaintiff
    devotes less than one page of her main brief to this
    argument. ‘‘Although the number of pages devoted to
    an argument in a brief is not necessarily determinative,
    relative sparsity weighs in favor of concluding that the
    argument has been inadequately briefed.’’ State v. Buhl,
    supra, 726. Accordingly, we consider this claim to be
    inadequately briefed and decline to address it.17
    The judgments are affirmed.
    In this opinion the other justices concurred.
    * January 21, 2021, the date that this decision was released as a slip
    opinion, is the operative date for all substantive and procedural purposes.
    1
    The Commissioner of Environmental Protection is now called the Com-
    missioner of Energy and Environmental Protection. See footnote 2 of this
    opinion.
    2
    In 2011, the Department of Energy and Environmental Protection was
    established as the successor department to the Department of Environmen-
    tal Protection and the Department of Public Utility Control, and the Commis-
    sioner of Energy and Environmental Protection became the head of the
    successor department. See Public Acts 2011, No. 11-80, § 1, codified at
    General Statutes (Supp. 2012) § 22a-2d.
    3
    The department originally issued the permit in 1992 to Dominion’s prede-
    cessor, Northeast Nuclear Energy Company. When Dominion purchased the
    plant from Northeast in 2001, the department approved the transfer of
    Northeast’s permit to Dominion and the substitution of Dominion for North-
    east in the permit renewal application.
    4
    General Statutes (Rev. to 2005) § 22a-19, as amended by No. 06-196,
    § 256, of the 2006 Public Acts (P.A. 06-196), provides in relevant part: ‘‘(a)
    In any administrative, licensing or other proceeding . . . any person . . .
    may intervene as a party on the filing of a verified pleading asserting that
    the proceeding . . . involves conduct which has, or which is reasonably
    likely to have, the effect of unreasonably polluting, impairing or destroying
    the public trust in the air, water or other natural resources of the state. . . .’’
    Hereinafter, all references to § 22a-19 in this opinion are to the 2005
    revision of the statute, as amended by P.A. 06-196, § 256.
    5
    General Statutes § 22a-16 provides in relevant part: ‘‘[A]ny person . . .
    may maintain an action in the superior court . . . for declaratory and equita-
    ble relief against the state, any political subdivision thereof, any instrumen-
    tality or agency of the state or of a political subdivision thereof . . . for
    the protection of the public trust in the air, water and other natural resources
    of the state from unreasonable pollution, impairment or destruction . . . .’’
    6
    Under General Statutes (Rev. to 2009) § 4-179 (b), a hearing officer makes
    a proposed final decision in a contested case, which ‘‘shall be in writing
    and contain a statement of the reasons for the decision and a finding of
    facts and conclusion of law on each issue of fact or law necessary to
    the decision.’’ Following the hearing officer’s proposed final decision, the
    department’s deputy commissioner issued her final decision under General
    Statutes (Rev. to 2009) § 4-180, which affirmed the hearing officer’s proposed
    final decision, with minor modifications, and conducted an independent
    evaluation as to whether the permit complied with, among other statutes
    and regulations, CEPA and the Clean Water Act.
    7
    This five year permit expired in 2015. Dominion filed a timely application
    for renewal, and the plant continues to operate under this permit pursuant
    to § 4-182 (b).
    8
    General Statutes § 4-183 (a) provides in relevant part: ‘‘A person who
    has exhausted all administrative remedies available within the agency and
    who is aggrieved by a final decision may appeal to the Superior Court as
    provided in this section. . . .’’
    9
    We note that the plaintiff raises numerous arguments throughout her
    brief via superficial and conclusory statements that do not appear to fit into
    any of her four main claims. To the extent they assert claims for relief, we
    conclude that they are inadequately briefed. These arguments include: the
    legality of the department’s emergency authorizations regarding the plant’s
    1992 permit; the question of whether the department applied cost-benefit
    analysis in renewing the permit; the propriety of the other intervenors’
    negotiations and stipulation; the propriety of the trial court’s reviewing
    evidence that was excluded from the administrative proceeding; and the
    veracity of the trial court’s statements about the context of the Clean
    Water Act.
    10
    We note that the plaintiff mischaracterizes the trial court’s decision on
    this issue. She asserts that ‘‘[t]he trial court never ruled on the specific
    question of whether [the administrative] proceedings were inadequate pursu-
    ant to [General Statutes] § 22a-20 . . . .’’ This is not true. Under a heading
    dedicated to the inadequacy of the proceeding, the trial court concluded that
    the administrative proceeding ‘‘suffered from no fundamental procedural
    unfairness.’’
    11
    The department’s jurisdiction was modified in 2011 by No. 11-80, §§ 1
    and 55, of the 2011 Public Acts. See footnote 2 of this opinion.
    12
    The plaintiff also asserts that ‘‘the hearing officer precluded the plaintiff
    from introducing into evidence the most recently expired 1992 permit
    . . . .’’ (Footnote omitted.) To the extent that the plaintiff argues that this
    exclusion contributed to the inadequacy of the proceeding, this argument
    is inadequately briefed because the plaintiff provides no analysis regarding
    why exclusion of this evidence was improper. ‘‘We consistently have held
    that [a]nalysis, rather than mere abstract assertion, is required in order to
    avoid abandoning an issue by failure to brief the issue properly.’’ (Internal
    quotation marks omitted.) Knapp v. Knapp, 
    270 Conn. 815
    , 823 n.8, 
    856 A.2d 358
     (2004).
    Likewise, at oral argument, the plaintiff referenced testimony from litiga-
    tion in another case by an expert, Mark Gibson, which was not admitted
    as evidence in the present case. Because this report was not raised prior
    to oral argument, we decline to consider this newly raised argument. ‘‘[I]t is
    well settled that a claim cannot be raised for the first time at oral argument.’’
    Hornung v. Hornung, 
    323 Conn. 144
    , 160 n.20, 
    146 A.3d 912
     (2016).
    13
    The trial court did not specifically address the issue of whether exclusion
    of this document was proper.
    14
    This subdivision of the regulation supplements General Statutes § 4-
    178, under which ‘‘the agency shall, as a matter of policy, provide for the
    exclusion of irrelevant, immaterial or unduly repetitious evidence . . . .’’
    15
    The only specific evidence that the plaintiff supplies to support her
    allegations of collusion between the department and Dominion is testimony
    by a Dominion witness regarding the stipulation negotiations between the
    department, Dominion, and the other environmental intervenors. In the
    administrative proceeding, the witness testified that a ‘‘ground rule’’ of the
    stipulation negotiations was that the parties would not discuss the issue of
    converting the plant to a closed-cycle cooling system. In objecting to the
    plaintiff’s subsequent line of questioning, Dominion’s attorney restated the
    witness’ testimony as indicating that ‘‘it was clear that all parties were in
    agreement that [the closed-cycle cooling system] was not on the table.’’ In
    this appeal, the plaintiff asserts that the witness’ testimony that the closed-
    cycle cooling system was ‘‘off the table’’ supports her allegations of bias,
    collusion, and prejudgment by the hearing officer. With no analysis or other
    evidence to support them, these allegations are speculative and the claims
    on which they are based are inadequately briefed. See, e.g., Knapp v. Knapp,
    
    270 Conn. 815
    , 823 n.8, 
    856 A.2d 358
     (2004) (‘‘[when] the parties cite no law
    and provide no analysis of their claims, we do not review such claims’’
    (internal quotation marks omitted)). Moreover, the witness’ testimony refer-
    enced the stipulation negotiations, not the hearing. The hearing officer and
    the deputy commissioner were required to evaluate the stipulated revised
    draft permit to ensure that it complied with applicable state and federal
    law, which they did in their proposed final decision and final decision,
    respectively. The plaintiff presents no evidence that these decisions were
    prejudged as a result of the stipulation negotiations.
    16
    For the first time, in her reply brief, the plaintiff quotes, without any
    analysis, a memorandum prepared by an individual who did not testify in
    the trial court and whose credibility as an expert witness could not be
    judged. The short memorandum, circulated internally within the department,
    summarizes a report evaluating the impact of the plant’s operation on fish
    population and entrainment during the year 1996. It is well settled that ‘‘new
    arguments are not to be raised in a reply brief because [the opposing party
    is] preclude[d] . . . from responding.’’ State v. Williams, 
    146 Conn. App. 114
    , 137 n.25, 
    75 A.3d 668
     (2013), aff’d, 
    317 Conn. 691
    , 
    119 A.3d 1194
     (2015);
    see, e.g., Harty v. Cantor Fitzgerald & Co., 
    275 Conn. 72
    , 91 n.9, 
    881 A.2d 139
     (2005) (‘‘[i]t is a well established principle that arguments cannot be
    raised for the first time in a reply brief’’ (internal quotation marks omitted)).
    The plaintiff’s reply brief cursorily states that this memorandum is ‘‘particu-
    larly damning’’ but does not analyze its relevance to her proposition that a
    closed-cycle cooling system would reduce the plant’s environmental impact.
    Accordingly, we decline to consider the memorandum or any related argu-
    ment that the plaintiff raises.
    17
    We also note that the trial court repeatedly clarified the procedures it
    would employ in conducting the hearing, and the plaintiff indicated her
    understanding of and assent to those procedures.