Strazza Building & Construction, Inc. v. Harris ( 2023 )


Menu:
  • ***********************************************
    The “officially released” date that appears near the be-
    ginning of each opinion is the date the opinion will be pub-
    lished in the Connecticut Law Journal or the date it was
    released as a slip opinion. The operative date for the be-
    ginning of all time periods for filing postopinion motions
    and petitions for certification is the “officially released”
    date appearing in the opinion.
    All opinions are subject to modification and technical
    correction prior to official publication in the Connecticut
    Reports and Connecticut Appellate Reports. In the event of
    discrepancies between the advance release version of an
    opinion and the latest version appearing in the Connecticut
    Law Journal and subsequently in the Connecticut Reports
    or Connecticut Appellate Reports, the latest version is to
    be considered authoritative.
    The syllabus and procedural history accompanying the
    opinion as it appears in the Connecticut Law Journal and
    bound volumes of official reports are copyrighted by the
    Secretary of the State, State of Connecticut, and may not
    be reproduced and distributed without the express written
    permission of the Commission on Official Legal Publica-
    tions, Judicial Branch, State of Connecticut.
    ***********************************************
    STRAZZA BUILDING & CONSTRUCTION,
    INC. v. JENNIFER G. HARRIS,
    TRUSTEE, ET AL.
    (SC 20660)
    Robinson, C. J., and McDonald, D’Auria, Mullins and Ecker, Js.
    Syllabus
    The defendants H and T appealed from the trial court’s denial of their motion
    for summary judgment, which was based on that court’s determination
    that the doctrine of res judicata did not preclude the present lien foreclo-
    sure action brought by the plaintiff, S Co. The defendants had hired S
    Co. as a general contractor for renovations to a home on property
    owned by T, a trust for which H served as trustee. After the defendants
    terminated their contractual relationship with S Co. as a result of a
    dispute, S Co. and one of its subcontractors, R Co., filed mechanic’s
    liens, claiming that the defendants owed them for the renovation work.
    H then brought an action against R Co. in which H sought to reduce or
    discharge R Co.’s mechanic’s lien. The trial court in H’s action against
    R Co. concluded that the lienable fund for S Co.’s contract with H and
    T was entirely exhausted and that, as a result, R Co.’s lien was invalid.
    Meanwhile, S Co. brought the present action, seeking to foreclose its
    mechanic’s liens. In their motion for summary judgment in the present
    action, the defendants claimed that the trial court was required to give
    res judicata effect to the court’s prior decision in H’s action against R
    Co. that no lienable fund existed in light of the rebuttable presumption
    of privity between general contractors and subcontractors recognized
    by this court in Girolametti v. Michael Horton Associates, Inc. (
    332 Conn. 67
    ). In denying the defendants’ motion for summary judgment,
    the trial court concluded, inter alia, that a genuine issue of material fact
    existed as to whether there was sufficient privity between R Co. and S
    Co. to preclude S Co. from pursuing the present action. The defendants
    thereafter appealed to the Appellate Court, which upheld the trial court’s
    denial of the motion for summary judgment. The Appellate Court deter-
    mined, inter alia, that the presumption of privity recognized in Girola-
    metti was inapplicable in a case such as the present one, in which the
    property owner sought to bind the general contractor to a ruling in a
    prior action between the property owner and a subcontractor. The
    Appellate Court specifically determined that it would have been inequita-
    ble to bind S Co., the general contractor, to a ruling in the prior action
    brought by H against R Co., a subcontractor, as a clear discrepancy
    existed between S Co.’s and R Co.’s interests, and, therefore, it could
    not be said that R Co. had adequately represented S Co.’s interests in
    the prior action. On the granting of certification, the defendants appealed
    from the Appellate Court’s judgment to this court.
    Held that the Appellate Court correctly concluded that the presumption of
    privity recognized in Girolametti was inapplicable in the present case,
    and, accordingly, this court affirmed the Appellate Court’s judgment:
    The Appellate Court properly declined to apply the presumption that
    this court recognized in Girolametti, namely, that, when a property
    owner and a general contractor enter into a binding agreement to resolve
    a dispute arising from a construction project, subcontractors are pre-
    sumptively in privity with the general contractor with respect to the
    preclusive effect of such agreement on subsequent litigation arising from
    the project, as that presumption arises from the flow down obligation
    that a general contractor owes to a subcontractor, and there is no corres-
    ponding obligation owed by a subcontractor to the general contractor.
    An evaluation of the factors courts consider in determining whether
    privity exists for res judicata purposes led to the conclusion that it would
    have been inequitable to bind S Co. to the prior decision against R Co.,
    as there was a discrepancy of interests, insofar as R Co.’s monetary
    interest in the litigation against R Co. was less than 12 percent of the
    amount constituting S Co.’s claim against the defendants, S Co.’s counsel
    was unable to cross-examine witnesses in H’s action against R Co. or
    to participate beyond representing a principal of S Co. when that principal
    testified in the litigation against R Co., and a general contractor should
    not reasonably expect to be bound by a judgment that involves consider-
    ation of only a portion of the work completed in connection with the
    entire project.
    Argued November 15, 2022—officially released February 21, 2023
    Procedural History
    Action to foreclose mechanic’s liens, and for other
    relief, brought to the Superior Court in the judicial dis-
    trict of Stamford-Norwalk, where the named defendant
    et al. filed a counterclaim; thereafter, the court, Genuario,
    J., denied the motion for summary judgment filed by the
    named defendant et al., and the named defendant et al.
    appealed to the Appellate Court, Moll, Alexander and
    Vertefeuille, Js., which upheld the trial court’s decision,
    and the named defendant et al., on the granting of certifi-
    cation, appealed to this court. Affirmed.
    Bruce L. Elstein, for the appellants (named defendant
    et al.).
    Anthony J. LaBella, with whom, on the brief, was Debo-
    rah M. Garskof, for the appellee (plaintiff).
    Opinion
    D’AURIA, J. In Girolametti v. Michael Horton Associ-
    ates, Inc., 
    332 Conn. 67
    , 87, 
    208 A.3d 1223
     (2019), this
    court held that, when a property owner and a general
    contractor have resolved disputes arising from a construc-
    tion project by way of binding arbitration, there arises a
    rebuttable presumption that the general contractor and
    its subcontractors are in privity for purposes of res judi-
    cata in any subsequent litigation. In this certified appeal,
    we must determine whether the Appellate Court correctly
    applied Girolametti to the facts of the present case, in
    which a general contractor had sued the property owner
    to foreclose two mechanic’s liens it served on the owner,
    claiming unpaid balances for labor and materials stem-
    ming from renovations it began on the owner’s home. In
    particular, we consider whether the Appellate Court
    properly upheld the trial court’s denial of the property
    owner’s motion for summary judgment, declining to
    give preclusive effect to the findings of the trial court
    in a prior action between the owner and one of the
    general contractor’s subcontractors. We agree with the
    Appellate Court that the presumption of privity that we
    held to apply in Girolametti does not apply in the pres-
    ent case, in which a property owner seeks to bind a
    general contractor to a prior judgment against a subcon-
    tractor. We also agree that the trial court correctly
    denied the defendants’ motion for summary judgment
    because there remains an issue of material fact as to
    whether the doctrine of res judicata applies to the facts
    of this case.
    We assume familiarity with the Appellate Court’s
    opinion, which contains a full recitation of the factual
    and procedural history in this case. See Strazza Build-
    ing & Construction, Inc. v. Harris, 
    207 Conn. App. 649
    ,
    652–57, 
    262 A.3d 996
     (2021). We briefly summarize that
    history as follows.
    The defendant Jennifer G. Harris (Harris) serves as
    trustee of the Jennifer G. Harris Revocable Trust (trust),
    which owns real property located in Greenwich. The
    defendants1 hired the plaintiff, Strazza Building & Con-
    struction, Inc. (Strazza), to serve as a general contractor
    for substantial renovations to a home located on the
    property. After a dispute arose over the cost and quality
    of the work that had been completed and the estimated
    time remaining to complete the project, the defendants
    terminated their contractual relationship with Strazza.
    Strazza and two subcontractors, Robert Rozmus Plumb-
    ing & Heating, Inc. (Rozmus), and Interstate & Lakeland
    Lumber Corporation, then filed and served mechanic’s
    liens on the defendants, claiming unpaid balances.
    Strazza then brought this action to foreclose its liens,
    totaling $561,155.88, alleging claims for breach of con-
    tract and unjust enrichment. 
    Id., 652
    .
    The preclusion issue presently before us arises because
    Harris, as trustee for the trust, previously initiated a
    separate proceeding against Rozmus (Rozmus action),
    pursuant to General Statutes § 49-35a, seeking to reduce
    or discharge the mechanic’s lien filed by Rozmus. See
    Harris v. Rozmus Plumbing & Heating, Inc., Superior
    Court, judicial district of Stamford-Norwalk, Docket
    No. CV-XX-XXXXXXX-S. A trial was held in the Rozmus
    action to resolve the validity of the mechanic’s lien.
    ‘‘Rozmus’ mechanic’s lien claimed $97,469.86 as the
    amount due to Rozmus for plumbing services and mate-
    rials,’’ which the court reduced to $62,040.36. Strazza
    Building & Construction, Inc. v. Harris, supra, 
    207 Conn. App. 653
    . ‘‘The court [then] determined whether
    Strazza was appropriately owed funds, because Rozmus
    could recover the sum it claimed to be owed only to
    the extent that Strazza, as the general contractor, was
    still owed money. . . . The court in the Rozmus action,
    therefore, reviewed the charges that were included in
    the liens held by Strazza and Rozmus and found that
    Harris was entitled to credits against the liens for many
    of the charges. . . . [T]he court ultimately concluded
    that the total adjusted lienable fund was negative
    $109,605.29. Thus, because the lienable fund for Straz-
    za’s contract was entirely exhausted, the lien held by
    Rozmus was invalid and ordered discharged.’’ (Citations
    omitted.) 
    Id.,
     653–54.
    The central finding of the Rozmus action was that
    no lienable fund existed. The defendants in the present
    case therefore moved for summary judgment, arguing
    that this court’s decision in Girolametti v. Michael Hor-
    ton Associates, Inc., 
    supra,
     
    332 Conn. 67
    , required the
    trial court to give res judicata effect to the trial court’s
    decision in the Rozmus action that no lienable fund
    existed. Strazza opposed the motion, arguing that the
    doctrine of res judicata did not apply because it was
    not a party to the Rozmus action and that there was
    insufficient privity between it and Rozmus to preclude
    it from suing to enforce its liens in the present action.
    Strazza Building & Construction, Inc. v. Harris, supra,
    
    207 Conn. App. 655
    .
    The trial court denied the defendants’ summary judg-
    ment motion, determining that, although three of the
    four required elements of res judicata were met, a genu-
    ine issue of material fact existed regarding whether
    there was sufficient privity between Strazza and Roz-
    mus to preclude Strazza from pursuing its claims against
    the defendants. 
    Id.,
     655–56. In addressing the privity
    issue, the trial court considered, among other things,
    that Strazza’s mechanic’s liens were for a substantially
    greater sum than Rozmus’ lien, that Strazza was not a
    party to the prior proceeding, and that Rozmus, as a
    subcontractor, may not have been in a position to
    defend the defendants’ allegations against Strazza, the
    general contractor. 
    Id.,
     656–57. After considering the
    functional relationship between the parties, the trial
    court ultimately concluded that a genuine issue of mate-
    rial fact existed as to whether Strazza’s interests were
    ‘‘sufficiently represented in the Rozmus action.’’ 
    Id., 663
    .
    The defendants appealed2 to the Appellate Court,
    which affirmed the trial court’s decision. The Appellate
    Court first held that the presumption of privity that we
    held to apply in Girolametti did not apply in the case
    at hand because the facts ‘‘are clearly distinguishable
    . . . .’’ 
    Id., 660
    . Second, the Appellate Court concluded
    that the trial court ‘‘correctly determined that [without
    the presumption of privity] there was a genuine issue
    of fact as to whether [Strazza] was in privity with Roz-
    mus for the purpose of res judicata.’’ 
    Id., 664
    .
    We agree fully with the Appellate Court’s holding in
    this case and have nothing further to add to its cogent
    rationale and conclusion on the second issue. The
    remainder of this opinion addresses the first issue and
    provides us with the opportunity to clarify our holding
    in Girolametti and to expand on the Appellate Court’s
    application of that case to the present case.
    This court held in Girolametti that, ‘‘when a property
    owner and a general contractor enter into a binding,
    unrestricted arbitration to resolve disputes arising from
    a construction project, subcontractors are presump-
    tively in privity with the general contractor with
    respect to the preclusive effects of the arbitration on
    subsequent litigation arising from the project.’’ (Empha-
    sis added.) Girolametti v. Michael Horton Associates,
    Inc., 
    supra,
     
    332 Conn. 87
    . Although the dispute between
    Rozmus and Harris was litigated in court, rather than
    through arbitration, if res judicata were to apply in the
    present case, the preclusive effect would of course be
    the same. See, e.g., DKN Holdings, LLC v. Faerber, 
    61 Cal. 4th 813
    , 828, 
    352 P.3d 378
    , 
    189 Cal. Rptr. 3d 809
    (2015); CDJ Builders Corp. v. Hudson Group Construc-
    tion Corp., 67 App. Div. 3d 720, 722, 
    889 N.Y.S.2d 64
    (2009). The Appellate Court properly declined to apply
    the presumption of privity in the present case. It rea-
    soned that Girolametti concluded that ‘‘the presump-
    tion of privity arises from the ‘flow down’ obligation
    that a general contractor owes to a subcontractor.’’
    Strazza Building & Construction, Inc. v. Harris, supra,
    
    207 Conn. App. 662
    . The Appellate Court determined
    that there was no basis for concluding that the presump-
    tion of privity also arises in the opposite situation, that
    is, when the prior adjudication is between the owner
    and the subcontractor, because there is no correspond-
    ing obligation owed by the subcontractor to the contrac-
    tor. 
    Id.
     (‘‘there is no corresponding ‘flow up’ obligation
    that extends from a subcontractor to a general contrac-
    tor’’). We agree.
    In Girolametti, we cited decisions from several juris-
    dictions that had similarly adopted a rebuttable pre-
    sumption that subcontractors are in privity with general
    contractors for purposes of res judicata. See Girola-
    metti v. Michael Horton Associates, Inc., 
    supra,
     
    332 Conn. 79
    . We reasoned further that, without this pre-
    sumption, ‘‘a property owner who fails to prevail in
    arbitration against a general contractor often will be
    able to relitigate its claims by simply recharacterizing
    what are essentially contract claims as violations of a
    subcontractor’s allegedly independent, noncontractual
    duties.’’ Id., 81.
    Our analysis in Girolametti focused on the fairness
    of applying the doctrine of res judicata to bind subcon-
    tractors to ‘‘postconstruction arbitration in which the
    subcontractors did not participate.’’ Id., 82. We did not
    discuss at all the effect of the opposite situation, which
    the Appellate Court described as a ‘‘ ‘flow up’ ’’ obliga-
    tion: the fairness of binding a general contractor to
    a previous award against its subcontractor when the
    general contractor was not a party to the prior pro-
    ceeding.3
    Establishing a presumption of privity between two
    parties requires that we consider the factors courts
    look to when establishing the element of privity for res
    judicata purposes. ‘‘These factors include the functional
    relationships between the parties, how closely their
    interests are aligned, whether they share the same legal
    rights, equitable considerations, the parties’ reasonable
    expectations, and whether the policies and rationales
    that underlie res judicata—achieving finality and repose,
    promoting judicial economy, and preventing inconsis-
    tent judgments—would be served. . . . [T]he crown-
    ing consideration, [however, is] that the interest of the
    party to be precluded must have been sufficiently repre-
    sented in the prior action so that the application of [res
    judicata] is not inequitable.’’ (Citations omitted; internal
    quotation marks omitted.) Id., 76–77.
    As the Appellate Court concluded, an evaluation of
    the factors that courts consider when determining
    whether privity exists for res judicata purposes leads
    to the inescapable conclusion that it would be inequita-
    ble in the present case to bind the general contractor
    to a judgment against its subcontractor. First, a clear
    discrepancy exists between the two parties’ interests.
    Common sense tells us that a subcontractor’s monetary
    interest in construction disputes normally will be less
    than that of the general contractor. In this case, Rozmus’
    monetary interest in the litigation between itself and
    the defendants ‘‘was less than 12 percent of the value of
    the claim of [Strazza] . . . .’’ (Internal quotation marks
    omitted.) Strazza Building & Construction, Inc. v.
    Harris, supra, 
    207 Conn. App. 664
    . Therefore, it cannot
    be said that Rozmus adequately represented Strazza’s
    interests in the prior litigation.
    Additionally, as the Appellate Court emphasized, when
    litigating the amount of the lienable fund in the prior
    action between Rozmus and Harris, the trial court
    decided issues related to many portions of the renova-
    tions in which Rozmus, as a plumbing subcontractor,
    was not involved. See 
    id., 663
    . Compare Lathan Con-
    struction Corp. v. McDaniel Grading, Inc., 
    695 So. 2d 354
    , 355 (Fla. App. 1996) (it is improper for court to
    collaterally estop general contractor from litigating claims
    against his subcontractor without allowing him to par-
    ticipate directly in underlying action between his bond-
    ing surety and subcontractor), with Associated
    Construction Co. v. Camp, Dresser & McKee, Inc., 
    646 F. Supp. 1574
    , 1578 (D. Conn. 1986) (subcontractors
    deemed to be in privity with general contractor, in part
    because general contractor asserted claims in which
    subcontractors had an interest and from which they
    received payment). The trial court in the Rozmus action
    decided these issues without Strazza’s counsel being
    able to cross-examine witnesses or participate in the
    trial beyond representing a principal of Strazza when
    he testified during the proceeding. We cannot hold that
    a finding of privity under these circumstances would
    promote an equitable result, as ‘‘[a subcontractor]
    would not have firsthand knowledge [of] or significant
    involvement [in] many aspects of the required perfor-
    mance of other areas of necessary performance under
    the general contract.’’ (Internal quotation marks omit-
    ted.) Strazza Building & Construction, Inc. v. Harris,
    supra, 
    207 Conn. App. 664
    . Without an opportunity to
    properly defend the entirety of a general contractor’s
    work, the contractor’s interests are not sufficiently rep-
    resented in a proceeding between the subcontractor
    and the property owner.
    Furthermore, when considering the parties’ reason-
    able expectations, we cannot say that a general contrac-
    tor should reasonably expect to be bound by a judgment
    that considered only a portion of the work completed
    on a project. As the amicus in Girolametti explained,
    and we took note of, although ‘‘standard form contracts
    used in the construction industry . . . make the gen-
    eral contractor responsible for the work of all subcon-
    tractors,’’ the opposite is not necessarily true.
    Girolametti v. Michael Horton Associates, Inc., supra,
    
    332 Conn. 78
    . These considerations will likely be true
    in many cases in which a party attempts to bind a
    general contractor to a judgment for or against a sub-
    contractor. Therefore, it would be inappropriate to
    apply a presumption of privity in these cases.
    The judgment of the Appellate Court is affirmed.
    In this opinion the other justices concurred.
    1
    This action originally was brought against Harris, both in her individual
    capacity and as the trustee of the Jennifer G. Harris Revocable Trust, which
    owns the real property at issue, as well as two junior lienholders to the
    property. The junior lienholders are not participating in this appeal. See
    Strazza Building & Construction, Inc. v. Harris, supra, 
    207 Conn. 651
     n.1.
    We hereinafter refer to Harris, in her individual capacity and as trustee,
    as the defendants.
    2
    After the defendants appealed to the Appellate Court, Strazza moved to
    dismiss the appeal for lack of a final judgment. The Appellate Court denied
    that motion, which was the proper ruling under our existing precedents.
    Specifically, this court has held that a denial of a motion based on res
    judicata and/or collateral estoppel grounds is immediately appealable. See
    Lighthouse Landings, Inc. v. Connecticut Light & Power Co., 
    300 Conn. 325
    , 328 n.3, 
    15 A.3d 601
     (2011). We have justified appeals of these interlocu-
    tory rulings under the second prong of State v. Curcio, 
    191 Conn. 27
    , 31,
    
    463 A.2d 566
     (1983), explaining that the defense of res judicata, as well as
    the defense of collateral estoppel, ‘‘is a civil law analogue to the criminal
    law’s defense of double jeopardy, because both invoke the right not to have
    to go to trial on the merits.’’ Convalescent Center of Bloomfield, Inc. v.
    Dept. of Income Maintenance, 
    208 Conn. 187
    , 194–95, 
    544 A.2d 604
     (1988);
    see also State v. Curcio, 
    supra, 31
     (second prong of Curcio permits appeal
    of otherwise interlocutory order that ‘‘so concludes the rights of the parties
    that further proceedings cannot affect them’’). In other words, this court
    has held that the defenses of res judicata and collateral estoppel provide
    immunity from suit. See, e.g., Blakely v. Danbury Hospital, 
    323 Conn. 741
    ,
    746–47, 
    150 A.3d 1109
     (2016); see also 
    id., 746
     (‘‘the essence of the protection
    of immunity from suit is an entitlement not to stand trial or face the other
    burdens of litigation’’ (internal quotation marks omitted)).
    Strazza does not challenge the Appellate Court’s final judgment ruling or
    argue that we should reconsider any of our precedents; therefore, we have
    no occasion to do so. Nevertheless, we note that federal case law, applying
    the ‘‘collateral order doctrine’’—a test similar to Curcio for determining the
    appealability of interlocutory orders—does not treat the denial of a motion
    to dismiss or a motion for summary judgment on res judicata grounds as
    an appealable ruling. See Will v. Hallock, 
    546 U.S. 345
    , 354–55, 
    126 S. Ct. 952
    , 
    163 L. Ed. 2d 836
     (2006); see also 
    id., 355
     (‘‘[t]he judgment bar at issue
    in this case [which functions in the same way as res judicata, and which is
    a defense of claim preclusion and not a defense of immunity] has no claim
    to greater importance than the typical defense of claim preclusion . . .
    [and] an order rejecting th[is] defense . . . cries for no immediate appeal
    of right as a collateral order’’); SmileDirectClub, LLC v. Battle, 
    4 F.4th 1274
    ,
    1283 (11th Cir. 2021) (denial of res judicata-claim preclusion defense would
    not merit immediate appeal under collateral order doctrine).
    Recently, our appellate courts have seen their share of interlocutory
    appeals on these grounds, including many in which the judgments at issue
    ultimately have been affirmed. See, e.g., Deutsche Bank AG v. Sebastian
    Holdings, Inc., 
    331 Conn. 379
    , 384, 
    204 A.3d 664
     (2019); Santorso v. Bristol
    Hospital, 
    308 Conn. 338
    , 354, 358, 
    63 A.3d 940
     (2013); Fairlake Capital,
    LLC v. Lathouris, 
    210 Conn. App. 801
    , 808, 818, 
    271 A.3d 689
    , cert. denied,
    
    343 Conn. 928
    , 
    281 A.3d 1186
     (2022); Peterson v. iCare Management, LLC,
    
    203 Conn. App. 777
    , 780, 794, 
    250 A.3d 720
     (2021); State v. Bacon Construc-
    tion Co., 
    160 Conn. App. 75
    , 77, 91, 
    124 A.3d 941
    , cert. denied, 
    319 Conn. 953
    , 
    125 A.3d 532
     (2015); In re Probate Appeal of Cadle Co., 
    152 Conn. App. 427
    , 429, 445, 
    100 A.3d 30
     (2014); Barton v. Norwalk, 
    131 Conn. App. 719
    ,
    733, 
    27 A.3d 513
    , cert. denied, 
    303 Conn. 906
    , 
    31 A.3d 1181
     (2011). In an
    appropriate case, in which the parties have joined issue on this question,
    we might have an opportunity to consider whether res judicata and collateral
    estoppel defenses properly should provide the basis for an interlocutory
    appeal when a trial court has denied those defenses pretrial.
    3
    In response to a subpoena duces tecum, a principal of Strazza testified
    at the trial of the Rozmus action with Strazza’s counsel present. However,
    the trial court did not permit counsel to object to the questions posed to
    the principal. In fact, the court ruled specifically that the principal was
    merely a witness and that Strazza was not a party to the proceedings.
    Although Rozmus’ counsel had no objections to Strazza’s counsel’s repre-
    senting the principal of his client, the court ruled that any objections to the
    principal’s testimony must be ‘‘made by counsel who represent parties in
    [the] case.’’