Smith v. Town of Redding , 177 Conn. App. 283 ( 2017 )


Menu:
  • ***********************************************
    The “officially released” date that appears near the be-
    ginning of each opinion is the date the opinion will be pub-
    lished in the Connecticut Law Journal or the date it was
    released as a slip opinion. The operative date for the be-
    ginning of all time periods for filing postopinion motions
    and petitions for certification is the “officially released”
    date appearing in the opinion.
    All opinions are subject to modification and technical
    correction prior to official publication in the Connecticut
    Reports and Connecticut Appellate Reports. In the event of
    discrepancies between the advance release version of an
    opinion and the latest version appearing in the Connecticut
    Law Journal and subsequently in the Connecticut Reports
    or Connecticut Appellate Reports, the latest version is to
    be considered authoritative.
    The syllabus and procedural history accompanying the
    opinion as it appears in the Connecticut Law Journal and
    bound volumes of official reports are copyrighted by the
    Secretary of the State, State of Connecticut, and may not
    be reproduced and distributed without the express written
    permission of the Commission on Official Legal Publica-
    tions, Judicial Branch, State of Connecticut.
    ***********************************************
    BRANDON V. SMITH v. TOWN OF REDDING ET AL.
    (AC 38704)
    Sheldon, Mullins and Sullivan, Js.
    Syllabus
    The plaintiff, who had sustained injuries when he fell off of a municipal
    retaining wall, sought to recover damages for absolute public nuisance,
    claiming that the defendant town had created a nuisance by causing
    the retaining wall to be constructed without a fence on top of it, which,
    in turn, caused his fall and resulting injuries. Prior to trial, the plaintiff
    filed a motion in limine, seeking a preliminary ruling as to the admissibil-
    ity of evidence that, subsequent to his fall, the town had constructed a
    fence on top of the wall and that the Department of Transportation had
    ordered the installation of the fence. In response, the trial court issued
    an order ruling that evidence of any subsequent remedial measures as
    to the retaining wall was inadmissible. Following a trial, the jury returned
    a verdict in favor of the town, determining that the plaintiff had failed
    to prove that the retaining wall was inherently dangerous. Thereafter,
    the trial court denied the plaintiff’s motion to set aside the verdict and
    rendered judgment in accordance with the verdict, from which the
    plaintiff appealed to this court. Held:
    1. The record was inadequate to review the plaintiff’s claim that the trial court
    abused its discretion by excluding evidence regarding the construction
    of the fence on the retaining wall after the plaintiff’s fall; the plaintiff
    failed to provide this court with various transcripts of the trial proceed-
    ings, and without a complete record of the trial, this court did not know
    whether the plaintiff presented other evidence that the retaining wall
    without the fence was inherently dangerous, and could not analyze fully
    whether the trial court’s exclusion of evidence of subsequent remedial
    measures to the retaining wall had affected the jury’s verdict or whether
    the plaintiff had been harmed by the trial court’s ruling.
    2. This court declined to review the plaintiff’s claim that the trial court
    improperly failed to instruct the jury on the town’s zoning regulations
    as a safety standard; the record indicated that the trial court did not
    address or decide this claim, and, therefore, the plaintiff failed to pre-
    serve it for appeal.
    Argued May 30—officially released October 17, 2017
    Procedural History
    Action to recover damages for public nuisance,
    brought to the Superior Court in the judicial district of
    Fairfield, where the court, Radcliffe, J., granted the
    motion to strike filed by the defendant M. Rondano,
    Inc.; thereafter, the court, Radcliffe, J., granted the
    motion for summary judgment filed by the defendant
    BL Companies, Inc.; subsequently, the complaint was
    withdrawn as to the defendant M. Rondano, Inc.; there-
    after, the court, Kamp, J., issued an order regarding
    the admissibility of certain evidence; subsequently, the
    court, Kamp, J., denied the plaintiff’s motion to reargue;
    thereafter, the matter was tried to the jury before Kamp,
    J.; verdict for the named defendant; subsequently, the
    court, Kamp, J., denied the plaintiff’s motion to set
    aside the verdict and rendered judgment in accordance
    with the verdict, from which the plaintiff appealed to
    this court. Affirmed.
    A. Reynolds Gordon, with whom was Frank A. DeNi-
    cola, Jr., for the appellant (plaintiff).
    Thomas R. Gerarde, with whom was Emily E. Hol-
    land, for the appellee (named defendant).
    Opinion
    SULLIVAN, J. In this absolute public nuisance action,
    the plaintiff, Brandon V. Smith, appeals following a jury
    trial from the judgment of the trial court rendered in
    favor of the defendant town of Redding.1 On appeal,
    the plaintiff claims that the trial court improperly failed:
    (1) to admit evidence of involuntary subsequent reme-
    dial measures; and (2) to instruct the jury on the Redd-
    ing Zoning Regulations. We affirm the judgment of the
    trial court.
    On the basis of the record provided, the jury reason-
    ably could have found the following facts. After con-
    suming alcoholic drinks over the course of an evening
    at a couple of establishments in Redding, the plaintiff
    departed the Lumberyard Pub around 2 a.m. on Septem-
    ber 17, 2011.2 Departing the pub, the plaintiff walked
    across the parking lot in front of the pub to the exit
    onto the street. On the edge of the parking lot was a
    wooden guardrail and, on the other side of the guardrail,
    there was a landscaped area atop a retaining wall. The
    retaining wall began on a plane level with the ground,
    and the ground then sloped down along the length of
    the wall. On the night of his fall, the plaintiff stepped
    onto the wall at ground level and walked the length of
    the wall before falling off, landing on his head and
    shoulder.
    The retaining wall had been constructed as part of
    the defendant’s federally funded streetscape project in
    the Georgetown section of the town. The defendant
    hired BL Companies, Inc., to design the project and J.
    Rondano, Inc., to construct it. As designed and con-
    structed, the retaining wall was without a fence atop
    the wall.
    On December 27, 2011, the plaintiff commenced this
    action against the defendant. See footnote 1 of this
    opinion. He then amended his complaint several times.
    In his substituted complaint filed on April 15, 2015, the
    plaintiff alleged that the defendant caused the retaining
    wall to be built without a fence, that such wall consti-
    tuted an absolute public nuisance, and that this caused
    his fall and resulting injuries. Following a jury trial, the
    jury returned a verdict in favor of the defendant on
    November 12, 2015, determining in its interrogatories
    that the plaintiff failed to prove that the retaining wall
    was inherently dangerous, in that it had a natural ten-
    dency to inflict injury on person or property. The plain-
    tiff filed a motion to set aside the verdict, which the
    court denied on December 22, 2015. Thereafter, the
    court rendered judgment in favor of the defendant, and
    this appeal followed. Additional facts will be set forth
    as necessary to the resolution of this appeal.
    I
    The plaintiff claims that the trial court abused its
    that the defendant had built atop the retaining wall
    subsequent to his fall. Although he acknowledges that
    our courts have not recognized such an exception to
    the exclusion of evidence of subsequent remedial mea-
    sures, he argues that the fence was built involuntarily,
    and, thus, the bar to evidence of subsequent remedial
    measures is inapplicable. Without deciding whether
    such evidence could be admitted, we conclude that we
    are unable to review the plaintiff’s claim because the
    record before this court does not allow us to evaluate
    whether the trial court’s ruling harmed him.
    As a preliminary matter, we set forth the standard for
    public nuisance liability as expressed by our Supreme
    Court. ‘‘Our prior decisions have established that in
    order to prevail on a claim of nuisance, a plaintiff must
    prove that: (1) the condition complained of had a natu-
    ral tendency to create danger and inflict injury upon
    person or property; (2) the danger created was a contin-
    uing one; (3) the use of the land was unreasonable or
    unlawful; [and] (4) the existence of the nuisance was
    [the] proximate cause of the plaintiffs’ injuries and dam-
    ages. . . . [W]here absolute public nuisance is alleged,
    the plaintiff’s burden includes two other elements of
    proof: (1) that the condition or conduct complained of
    interfered with a right common to the general public
    . . . and (2) that the alleged nuisance was absolute,
    that is, that the defendants’ intentional conduct, rather
    than their negligence, caused the condition deemed to
    be a nuisance.’’ (Citations omitted; internal quotation
    marks omitted.) State v. Tippetts-Abbett-McCarthy-
    Stratton, 
    204 Conn. 177
    , 183, 
    527 A.2d 688
    (1987).
    The following additional procedural facts are relevant
    to this claim. On September 15, 2015, the plaintiff filed
    a motion in limine seeking, inter alia, a preliminary
    ruling as to the admissibility of evidence of a fence
    constructed atop the retaining wall in April, 2015. Spe-
    cifically, the plaintiff sought to introduce evidence at
    trial that the Department of Transportation (depart-
    ment) ordered the installation of the fence. He also
    sought to introduce into evidence photographs of the
    fence. The plaintiff argued, inter alia, that the exclusion-
    ary rule regarding evidence of subsequent remedial
    measures; see § 4-7 of the Connecticut Code of Evi-
    dence;3 did not apply because it excludes evidence of
    voluntary remedial measures but, in this case, construc-
    tion of the fence was required from the start of the
    project and was involuntarily built. In an October 14,
    2015 order, the court determined that evidence of any
    subsequent remedial measures as to the retaining wall
    was inadmissible.
    In his motion to set aside the verdict, the plaintiff
    again raised the issue of the admissibility of evidence
    of the subsequently built fence, citing arguments made
    in prior briefs and oral arguments before the court, as
    a ground to set aside the verdict. The court denied the
    plaintiff’s motion, concluding that any evidence of the
    fence was inadmissible under § 4-7 of the Connecticut
    Code of Evidence.
    ‘‘[Our appellate courts] review the trial court’s deci-
    sion to admit [or exclude] evidence, if premised on a
    correct view of the law . . . for an abuse of discretion.
    . . . Under the abuse of discretion standard, [w]e
    [must] make every reasonable presumption in favor of
    upholding the trial court’s ruling, and only upset it for
    a manifest abuse of discretion. . . . [Thus, our] review
    of such rulings is limited to the questions of whether
    the trial court correctly applied the law and reasonably
    could have reached the conclusion that it did.’’ (Citation
    omitted; internal quotation marks omitted.) Filippelli
    v. Saint Mary’s Hospital, 
    319 Conn. 113
    , 119, 
    124 A.3d 501
    (2015). Nevertheless, ‘‘[b]efore a party is entitled
    to a new trial because of an erroneous evidentiary rul-
    ing, he or she has the burden of demonstrating that the
    error was harmful. . . . [A]n evidentiary impropriety
    in a civil case is harmless only if we have a fair assurance
    that it did not affect the jury’s verdict. . . . A determi-
    nation of harm requires us to evaluate the effect of the
    evidentiary impropriety in the context of the totality of
    the evidence adduced at trial.’’ (Internal quotation
    marks omitted.) Filippelli v. Saint Mary’s 
    Hospital, supra
    , 119.
    We conclude that even if we assumed, arguendo, an
    exception for involuntary measures to the rule against
    the admission of evidence of subsequent remedial mea-
    sures, the record before this court would not allow us
    to analyze whether the plaintiff was harmed by the
    exclusion of such evidence in this case. When an appel-
    lant requests that the court reverse the judgment of
    the trial court on the basis of an allegedly improper
    evidentiary ruling, a complete record is particularly
    important for a reviewing court to consider the extent
    of the harm suffered, if any. See Desrosiers v. Henne,
    
    283 Conn. 361
    , 367–69, 
    926 A.2d 1024
    (2007) (declining
    to review evidentiary claim where defendant provided
    only excerpts of trial transcripts because it was impossi-
    ble for reviewing court to determine whether alleged
    impropriety was harmful); Ryan Transportation, Inc.
    v. M & G Associates, 
    266 Conn. 520
    , 531, 
    832 A.2d 1180
    (2003) (declining to review evidentiary claim where
    plaintiff did not provide transcript of witness testimony,
    stating, ‘‘even if we assume, arguendo, that the chal-
    lenged evidentiary ruling was improper, we have no
    way of discerning whether any such impropriety was
    harmful in the broader context of the entire trial’’);
    Chester v. Manis, 
    150 Conn. App. 57
    , 62–63, 
    89 A.3d 1034
    (2014) (declining to review evidentiary claim because
    incomplete record left court unable to determine if
    ‘‘alleged impropriety would likely have affected the
    result of the trial’’); Quaranta v. King, 
    133 Conn. App. 565
    , 569–70, 
    36 A.3d 264
    (2012) (declining to review
    plaintiff’s evidentiary claim where plaintiff provided
    only partial transcript of proceedings).
    A review of our appellate record in the present case
    reveals that the plaintiff ordered and delivered a paper
    copy and an electronic copy of the following six tran-
    scripts: (1) the October 14, 2015 argument on the plain-
    tiff’s motions in limine; (2) the October 27, 2015
    argument on the motion to reargue regarding subse-
    quent remedial measures; (3) the October 30, 2015
    direct examination and cross-examination of lay wit-
    ness Aimee Pardee; (4) the November 3, 2015 direct
    examination and cross-examination of lay witness Priti
    Bhardwaj; (5) the November 12, 2015 argument on
    exceptions to the jury charge; and (6) the December
    14, 2015 argument on the motion to set aside the verdict.
    Additionally, the plaintiff’s appendix includes a single
    page transcript described as an excerpt of the October
    30, 2015 testimony of Natalie Ketcham.
    We know for certain that we were not provided with
    the full testimony of Ketcham, the plaintiff’s expert,
    Richard A. Ziegler, and the plaintiff, or with counsels’
    closing arguments. Additionally, we know that we were
    not provided with any testimony from Timothy Wilson
    or Matthew Cleary, engineers from the department. A
    lengthy period passed between jury selection and the
    jury’s verdict, suggesting a trial that covered a couple
    of weeks. Additionally, we are left to speculate about
    who else testified and the scope and content of their
    testimony regarding the dangerousness or safety of the
    retaining wall without a fence. For example, the defen-
    dant disclosed an expert, but we do not know whether
    he testified or the content of his testimony relevant to
    this issue.
    It is the appellant’s burden to provide a complete
    record on appeal. Practice Book § 61-10. He also is
    responsible for establishing that the allegedly improper
    evidentiary ruling of the trial court harmed him. See
    Connecticut Light & Power Co. v. Gilmore, 
    289 Conn. 88
    , 128, 
    956 A.2d 1145
    (2008) (‘‘Even when a trial court’s
    evidentiary ruling is deemed to be improper, we must
    determine whether that ruling was so harmful as to
    require a new trial. . . . In other words, an evidentiary
    ruling will result in a new trial only if the ruling was
    both wrong and harmful.’’ [Internal quotation marks
    omitted.]). We conclude that the plaintiff has not carried
    his burden under the circumstances of this case.
    On the record before this court, we are unable to
    determine whether the trial court’s evidentiary ruling
    affected the jury’s verdict. Even if we assume, arguendo,
    that the court improperly excluded the evidence regard-
    ing the department’s order to construct a fence atop
    the restraining wall, we are unable to assess fully the
    impact of this ruling. The jury’s verdict was based upon
    its conclusion that the plaintiff failed to prove that the
    wall without a fence was inherently dangerous in that
    it had a natural tendency to inflict injury on person or
    property. Although the department’s order may have
    carried some added weight with the jury, the plaintiff
    was able to argue that the department’s bridge design
    manual called for a fence and that the department called
    for a fence during the design of the wall. The bridge
    design manual, the state building code, and The BOCA
    National Building Code (14th Ed. 1999) were admitted
    into evidence. Without the testimony of other witnesses,
    including the plaintiff’s expert and at least two state
    engineers, and counsel’s closing arguments, we are
    unaware of the extent to which the plaintiff was able
    to present other evidence that the wall without a fence
    was inherently dangerous. Accordingly, we are unable
    to analyze whether the other evidence in the case would
    have given us the fair assurance that the exclusion of
    the evidence of subsequent remedial measures did not
    affect the jury’s verdict in order to determine whether
    the plaintiff was harmed by the trial court’s ruling.
    II
    The plaintiff also claims that the trial court improp-
    erly failed to instruct the jury on the Redding Zoning
    Regulations (zoning regulations).4 He asserts that the
    zoning regulations were relevant evidence that the
    retaining wall was inherently dangerous without a
    fence. First, he argues that the zoning regulations,
    which included safety as one of its purposes, applied
    to the construction of the wall. Second, he asserts that,
    even if the zoning regulations did not apply to the wall,
    they established a safety standard, which the court
    should have instructed the jury to consider when
    determining whether the wall was inherently danger-
    ous.5 We conclude that the plaintiff has failed to pre-
    serve his claim for appeal.
    The record does not reveal a request to charge regard-
    ing inherent danger and the zoning regulations, or the
    safety standards allegedly evinced by those regulations.
    Although the plaintiff filed a written request to charge
    and a supplemental request to charge, those requests
    did not address the issue of inherent danger as it relates
    to the zoning regulations, and we have not been pro-
    vided with a record of the charge conference.
    Additionally, the plaintiff, in his exception to the
    charge, also did not raise these specific issues. After
    the court delivered its instructions, it asked the parties
    whether they wanted to take exceptions to the charge.
    The plaintiff took exception, stating in relevant part:
    ‘‘Yes, Your Honor. First, Your Honor’s failure to charge
    on the Redding zoning violation, making it a violation
    to have within the town of Redding a retaining wall
    more than four feet tall with no fence.’’ This exception,
    as stated, was insufficient to put the court on notice
    of the nature of the claimed instructional error, as the
    plaintiff did not state any grounds for the exception.
    See generally Herrera v. Madrak, 
    58 Conn. App. 320
    ,
    323, 
    752 A.2d 1161
    (2000).
    Our review of the record provided reveals that the
    first time the plaintiff raised his claim that the court
    should have instructed the jury on the zoning regula-
    tions as evidence that the wall, as constructed, consti-
    tuted an inherently dangerous condition was in his
    motion to set aside the verdict. The plaintiff set forth
    essentially the same argument in his memorandum of
    law in support of his motion to set aside as he does
    before this court on appeal. Specifically, as to the wall’s
    inherent dangerousness, he first argued to the trial court
    that the zoning regulations applied under General Stat-
    utes § 13a-80d6 because the wall and the surrounding
    project were in a state right-of-way and the defendant
    was a tenant or lessee of the state. He cited evidence
    from the trial to support this claim. Alternatively, he
    argued that the zoning regulations were admissible as
    a safety standard to address the inherent danger, even
    if the regulations did not apply to the wall. On December
    14, 2015, the court heard oral arguments on the motion.
    In its memorandum of decision, however, the court
    framed the plaintiff’s argument as follows: ‘‘The second
    ground upon which the plaintiff seeks to set aside the
    verdict is . . . the court’s failure to instruct the jury
    that the retaining wall was unlawful in that it violated
    the . . . zoning regulations.’’ After setting forth the evi-
    dence presented at trial, the court concluded that the
    evidence did not support a charge to the jury concerning
    the application of the zoning regulations.
    Practice Book § 16-20 provides in relevant part: ‘‘An
    appellate court shall not be bound to consider error as
    to the giving of, or the failure to give, an instruction
    unless the matter is covered by a written request to
    charge or exception has been taken by the party appeal-
    ing immediately after the charge is delivered. Counsel
    taking the exception shall state distinctly the matter
    objected to and the ground of objection. . . .’’ ‘‘It is
    fundamental [however] that claims of error must be
    distinctly raised and decided in the trial court before
    they are reviewed on appeal. As a result, Connecticut
    appellate courts will not address issues not decided
    by the trial court.’’ (Internal quotation marks omitted.)
    Tompkins v. Freedom of Information Commission, 
    136 Conn. App. 496
    , 511, 
    46 A.3d 291
    (2012); see also Crest
    Pontiac Cadillac, Inc. v. Hadley, 
    239 Conn. 437
    , 444
    n.10, 
    685 A.2d 670
    (1996) (claims ‘‘neither addressed
    nor decided’’ by trial court not properly before appel-
    late tribunal).
    In the present case, we have no record that indicates
    that the court ever addressed the claim that the plaintiff
    is making on appeal, namely, that the court should have
    instructed the jury on the zoning regulations as a safety
    standard. The court’s decision on the motion to set aside
    the verdict addressed the applicability of the zoning
    regulations to the third element of nuisance, unreason-
    able or unlawful use, rather than the first element, inher-
    ent danger. Because the trial court did not address or
    decide the plaintiff’s claim regarding the zoning regula-
    tions as a safety standard, we decline to address it.
    The judgment is affirmed.
    In this opinion the other judges concurred.
    1
    The plaintiff served his complaint against the defendants, the town of
    Redding, M. Rondano, Inc. (Rondano), and BL Companies, Inc. (BL Compa-
    nies). On December 5, 2014, the court rendered summary judgment in favor
    of BL Companies on the plaintiff’s claims against it. Additionally, on July
    21, 2015, the plaintiff withdrew his claim against Rondano. Although the
    town brought a cross claim against Rondano, the court bifurcated that claim
    to be resolved after the trial between the plaintiff and the town. This appeal
    is from the trial on the plaintiff’s claim of absolute public nuisance against
    the town. Consequently, Rondano and BL Companies are not parties to this
    appeal and, therefore, all references to the defendant herein are to the town
    of Redding.
    2
    The parties agree that the plaintiff’s fall occurred on September 17, 2011.
    3
    Section 4-7 (a) of the Connecticut Code of Evidence provides in relevant
    part: ‘‘[E]vidence of measures taken after an event, which if taken before
    the event would have made injury or damage less likely to result, is inadmissi-
    ble to prove negligence or culpable conduct in connection with the event.
    Evidence of those measures is admissible when offered to prove contro-
    verted issues such as ownership, control or feasibility of precautionary
    measures.’’
    4
    The plaintiff also appears to claim that the court abused its discretion
    in excluding the zoning regulations from evidence. The record includes,
    however, the zoning regulations in their entirety as exhibit 20 and excerpts
    thereof were admitted as exhibit 20a; both exhibits were marked as full
    exhibits. Corroborating the admission of these exhibits, the limited recorded
    provided; see part I of this opinion; includes a trial transcript of the plaintiff’s
    attorney requesting exhibits 20 and 20a, reading from the zoning regulations,
    and questioning the defendant’s zoning enforcement officer on the regula-
    tions. Our examination of the limited record and the parties’ appellate argu-
    ments, does not provide any indication that the court limited the admissibility
    of the regulations or limited the plaintiff’s ability to argue their relevance.
    5
    The jury’s verdict was based on its conclusion that the plaintiff had
    failed to demonstrate that the wall was inherently dangerous. We interpret
    the plaintiff’s arguments that the construction of the wall without a fence
    violated the zoning regulations to go to evidence of inherent dangerousness.
    As far as the plaintiff argues that the purported violation had some indepen-
    dent import, this is irrelevant because the jury did not reach the third element
    of a cause of action for nuisance, which requires that ‘‘the use of the land
    was unreasonable or unlawful . . . .’’ (Internal quotation marks omitted.)
    State v. 
    Tippetts-Abbett-McCarthy-Stratton, supra
    , 
    204 Conn. 183
    .
    6
    General Statutes § 13a-80d provides: ‘‘The use of any space on, over
    or below any state highway right-of-way leased by the Commissioner of
    Transportation to a lessee shall conform with zoning regulations and ordi-
    nances of the local government in which the land is located or as modified
    by a variance pursuant to legal process.’’
    

Document Info

Docket Number: AC38704

Citation Numbers: 172 A.3d 318, 177 Conn. App. 283

Judges: Sheldon, Mullins, Sullivan

Filed Date: 10/17/2017

Precedential Status: Precedential

Modified Date: 10/19/2024