Webster Bank, N.A. v. GFI Groton, LLC ( 2015 )


Menu:
  • ******************************************************
    The ‘‘officially released’’ date that appears near the
    beginning of each opinion is the date the opinion will
    be published in the Connecticut Law Journal or the
    date it was released as a slip opinion. The operative
    date for the beginning of all time periods for filing
    postopinion motions and petitions for certification is
    the ‘‘officially released’’ date appearing in the opinion.
    In no event will any such motions be accepted before
    the ‘‘officially released’’ date.
    All opinions are subject to modification and technical
    correction prior to official publication in the Connecti-
    cut Reports and Connecticut Appellate Reports. In the
    event of discrepancies between the electronic version
    of an opinion and the print version appearing in the
    Connecticut Law Journal and subsequently in the Con-
    necticut Reports or Connecticut Appellate Reports, the
    latest print version is to be considered authoritative.
    The syllabus and procedural history accompanying
    the opinion as it appears on the Commission on Official
    Legal Publications Electronic Bulletin Board Service
    and in the Connecticut Law Journal and bound volumes
    of official reports are copyrighted by the Secretary of
    the State, State of Connecticut, and may not be repro-
    duced and distributed without the express written per-
    mission of the Commission on Official Legal
    Publications, Judicial Branch, State of Connecticut.
    ******************************************************
    WEBSTER BANK, N.A. v. GFI
    GROTON, LLC, ET AL.
    (AC 35575)
    Sheldon, Mullins and Schaller, Js.
    Argued Janaury 20—officially released May 26, 2015
    (Appeal from Superior Court, judicial district of New
    London, Hon. Joseph Q. Koletsky, judge trial referee.)
    Jeffery O. McDonald, with whom, on the brief, was
    Louis N. George, for the appellants (named defendant
    et al.).
    George A. Dagon, Jr., with whom was Eric B. Miller,
    for the appellee (plaintiff).
    Opinion
    MULLINS, J. In this breach of contract action, the
    defendants, GFI Groton, LLC (developer), Steven E.
    Goodman, John DeLiso, GFI Investments V Groton,
    LLC, and CAT Developers, LLC, appeal from the judg-
    ment of the trial court, rendered after a bench trial, in
    favor of the plaintiff, Webster Bank, N.A. (bank). The
    defendants claim that the court improperly (1) deter-
    mined that the bank had complied with its funding
    obligations under an agreement to finance a building
    project and (2) concluded that the bank had made rea-
    sonable efforts to mitigate its damages. We affirm the
    judgment of the trial court.
    The following facts, which the court reasonably could
    have found, and procedural history are relevant to our
    resolution of this appeal. The developer undertook a
    project to acquire land and develop a condominium and
    townhouse complex in Groton (project). The project
    entailed constructing and selling the units of three con-
    dominium buildings on a parcel of land (property). The
    three buildings, respectively, would consist of twelve,
    sixteen and sixteen condominium units. On or about
    September 27, 2004, the developer entered into an
    agreement with the bank to finance the project.
    Under the terms of the parties’ agreement, the bank
    agreed to fund the project in the form of two loans: (1)
    an acquisition and development loan totaling
    $2,044,500; and (2) a revolving loan totaling $1,600,000
    (loans). The acquisition and development loan would
    be used to purchase the property and perform site work
    outside of the building construction. The revolving loan
    would be used to fund the construction of the condo-
    minium units. The loans were made pursuant to corres-
    ponding loan agreements that set forth the obligations
    of the developer and the bank with respect to each
    loan. Additionally, the loans were secured by respective
    promissory notes executed by the developer (notes),
    as well as four ‘‘Payment and Completion Guaranty
    Agreements’’ (guaranties) that separately were exe-
    cuted by Goodman, DeLiso, GFI Investments V Groton,
    LLC, and CAT Developers, LLC (guarantors). The devel-
    oper also executed a mortgage on the property in favor
    of the bank.1
    The notes provided that the developer would initially
    pay only the monthly interest on the loans. The revolv-
    ing loan agreement specified an ‘‘absorption rate’’ at
    which the developer was required to construct and sell
    a specified number of units every year.2 Pursuant to
    the acquisition and development loan agreement, the
    developer was to repay the bank $44,450 of that loan
    upon the sale of each condominium unit and the bank,
    in turn, was to issue a release of a corresponding portion
    of the mortgage.
    The revolving loan agreement provided a procedure
    by which the developer was to draw funds for the proj-
    ect as construction progressed. To receive disburse-
    ments from the revolving loan, the developer was
    required to submit to the bank its construction costs,
    which, in turn, would determine the amount of funding
    to which the developer was entitled. Specifically, to
    receive funding under terms of the revolving loan
    agreement, the developer was required to submit to the
    bank a letter ‘‘requesting the amount of the particular
    disbursement’’ along with various supporting docu-
    ments. Section 4.02 (a) of the revolving loan agreement
    provided that the developer was permitted to draw up
    to 90 percent ‘‘of the actual vertical hard and soft costs
    of construction,’’ but not more than $117,000 per condo-
    minium unit.3
    During the construction of the first building, the
    developer submitted construction costs to the bank of
    $85,000 per unit. Pursuant to the terms of the revolving
    loan agreement, the bank disbursed to the developer
    $76,500 per unit, which was 90 percent of the develop-
    er’s submitted construction costs. By May, 2006, the
    developer had completed construction on the first
    building, and sold its twelve units. The developer repaid
    the bank pursuant to the loan agreements for each unit
    sold in the first building.
    In 2005, the developer commenced construction on
    the second building and increased the construction
    costs that it submitted to the bank to $113,750 per
    unit. As a result, the bank disbursed to the developer
    $102,375 per unit, or 90 percent of its budgeted cost.
    In August, 2006, when construction on the second
    building was underway, the developer and the bank
    agreed to modify the revolving loan agreement and note
    because of concerns that the developer was not comply-
    ing with its required absorption rate. The parties
    entered into a loan modification agreement and
    amended the revolving loan agreement (2006
    agreement). Under the 2006 agreement, the parties
    agreed to increase the principal balance of the revolving
    loan from $1,600,000 to $2,250,000. The 2006 agreement
    also eliminated the revolving loan’s maximum draw
    restriction of $117,000 per unit. Nonetheless, under the
    2006 agreement, the developer still was obligated to
    submit draw requests to the bank to receive funds, and
    still was only entitled to draw up to 90 percent ‘‘of the
    actual vertical hard and soft construction costs of each
    unit . . . .’’
    After the parties executed the 2006 agreement, the
    developer continued to submit draw requests for the
    second building based on construction costs of $113,750
    per unit; the bank continued to disburse to the devel-
    oper $102,375 per unit. When the developer started to
    construct the third building, it again submitted to the
    bank construction costs of $113,750 per unit for that
    building. The bank, thus, continued to disburse funds
    to the developer for the third building at the rate 90
    percent of the submitted construction costs, or $102,375
    per unit.
    As the September 30, 2007 maturity date on the notes
    approached, the developer was performing the framing
    work on the third building. On September 23, 2007, the
    developer submitted to the bank a draw request from
    the revolving loan in the amount of $62,400 for labor
    to install drywall.4 The bank fully funded that request.
    After the notes matured, however, the developer was
    not permitted under the loan agreements to draw funds
    until the bank agreed to new maturity dates on the
    loans.
    On November 30, 2007, the bank and the developer
    executed a second modification agreement (2007
    agreement), pursuant to which the maturity date of the
    acquisition and development loan was extended until
    September 30, 2009, and the maturity date on the revolv-
    ing loan was extended until September 30, 2010. In
    conjunction with the 2007 agreement, the guarantors
    executed a ‘‘Reaffirmation of Guaranty, Consent and
    Waiver’’ (reaffirmation). Under the terms of the 2007
    agreement and reaffirmation, the parties waived all
    claims and defenses arising prior to November 30, 2007.
    The parties agreed that additional funding would be
    available to the developer under the 2007 agreement
    after the developer completed the work for which the
    bank already had disbursed funds. As a result, the devel-
    oper recognized that the bank would not fund additional
    draw requests until after the developer completed the
    drywall installation.
    After receiving the September, 2007 disbursement
    from the bank for drywall labor, however, the developer
    never completed installing the drywall in the third build-
    ing. A representative from the bank visited the third
    building on a regular basis to monitor progress, and
    observed that the drywall never was installed.
    Additionally, the bank received no further draw
    requests from the developer. In its oral ruling, the court
    stated: ‘‘The court does not have enough evidence to
    make a specific finding, but . . . the clear inference
    that the court draws [is] that no draw request was made
    because no draw request would have been honored
    since the work for which the developers had already
    been paid had not been done.’’
    The developer completed construction on the second
    building and sold all sixteen of its units. For each of
    the first fifteen units sold in the second building, the
    developer repaid the bank $44,450 toward the principal
    balance on the acquisition and development loan. When
    the final unit of the second building was sold in April,
    2008, however, the bank relinquished its right to receive
    the final $44,450 payment in order to provide the devel-
    oper more liquidity. Nonetheless, that same month, the
    developer ceased making interest payments to the bank
    on the loans.
    On June 5, 2008, the bank notified the defendants by
    certified letter that the loans were in default. Afterward,
    the parties entered into negotiations to save the project.
    The defendants made proposals to the bank, under
    which the bank would advance additional funds to the
    developer for construction. The bank rejected these
    proposals.
    In January, 2009, the developer sent documents to
    the bank that indicated that the developer owed its
    subcontractors hundreds of thousands of dollars for
    unpaid work, as a result of which it was facing numer-
    ous lawsuits. After receiving this notification, the bank
    informed the defendants, by way of a second default
    letter dated March 17, 2009, that the notes were in
    default and that it was exercising its right to accelerate
    payment. After the bank sent the second default letter,
    the defendants made several offers to the bank to pur-
    chase the notes for amounts less than the total debt
    owed. The bank refused those offers. The developer
    never completed the third building.
    On July 21, 2009, the town of Groton (town) filed
    an action against the developer seeking, inter alia, to
    foreclose tax liens on the property for unpaid property
    taxes. On August 24, 2009, the bank filed the present
    action, in which it initially sought to foreclose its mort-
    gage ‘‘in case the town was not working in a timely
    fashion.’’ The town’s tax lien had a higher priority than
    the bank’s mortgage; the bank, thus, was named as a
    subsequent encumbrancer in the town’s foreclosure
    action.
    In October, 2010, the bank’s subsidiary, Birch Bark
    Properties, Inc., purchased the property for $750,000
    through a tax foreclosure sale. After the sale, the bank
    considered the remaining principal on the acquisition
    and development loan satisfied and forgave a portion of
    the revolving loan principal. Nonetheless, the revolving
    loan still had an outstanding principal balance, and the
    interest on both loans remained unpaid.
    Thereafter, the bank amended its complaint to assert
    that the defendants had breached the terms and condi-
    tions of the notes and guaranties. The defendants filed
    a revised answer denying many of the bank’s claims
    against them, asserting multiple special defenses, and
    filing their own counterclaims against the bank.5
    On March 27, 2013, after a seven day trial, the court,
    Hon. Joseph Q. Koletsky, judge trial referee, rendered
    judgment in favor of the bank on all of its breach of
    contract and guaranty claims, and rejected the defen-
    dants’ counterclaims. The court awarded to the bank
    the outstanding principal on the revolving loan, unpaid
    interest on both loans, reimbursement for property
    taxes, and attorneys’ fees and costs. This appeal fol-
    lowed.6 Additional facts and procedural history will be
    set forth as necessary.
    On appeal, the defendants challenge the propriety of
    the trial court’s adverse factual findings. Specifically,
    the defendants maintain that the court improperly (1)
    determined that the bank complied with its funding
    obligations required by the loan agreements and (2)
    concluded that the bank adequately had mitigated its
    damages. We are not persuaded.
    We begin by setting forth the relevant law and applica-
    ble standard of review. ‘‘The elements of a breach of
    contract action are the formation of an agreement, per-
    formance by one party, breach of the agreement by the
    other party and damages.’’ (Internal quotation marks
    omitted.) Hawley Avenue Associates, LLC v. Robert D.
    Russo, M.D. & Associates Radiology, P.C., 
    130 Conn. App. 823
    , 832, 
    25 A.3d 707
     (2011). ‘‘Whether a contract
    has been breached ordinarily is a question of fact, sub-
    ject to the clearly erroneous standard of review.’’ De
    La Concha of Hartford, Inc. v. Aetna Life Ins. Co., 
    269 Conn. 424
    , 431 n.5, 
    849 A.2d 382
     (2004). ‘‘A finding of
    fact is clearly erroneous when there is no evidence in
    the record to support it . . . or when although there
    is evidence to support it, the reviewing court on the
    entire evidence is left with the definite and firm convic-
    tion that a mistake has been committed. . . . In making
    this determination, every reasonable presumption must
    be given in favor of the trial court’s ruling.’’ (Internal
    quotation marks omitted.) Gordon v. Tobias, 
    262 Conn. 844
    , 849, 
    817 A.2d 683
     (2003).
    I
    The defendants claim that the court improperly con-
    cluded that the bank complied with its funding obliga-
    tions under the loan agreements. The defendants
    specifically argue that the bank failed to provide them
    sufficient funding to install the drywall in the third
    building because the developer’s actual construction
    costs were higher than the funding that the bank dis-
    bursed to it. The defendants contend that the bank
    ‘‘misinterpreted the maximum amounts allowable
    under the loan documents,’’ and argue that ‘‘[h]ad the
    trial court properly determined that the [developer]
    [was] entitled to funding of at least $117,000 per unit,
    there would have been adequate funding available to
    complete the sheetrock.’’ We are not persuaded.
    In its oral ruling, the court stated that ‘‘[t]here is no
    doubt that when the loan matured in September of 2007,
    the loan was indeed turned off, but that loan was turned
    back on in November or early December of 2007 [pursu-
    ant to the 2007 agreement], and funds were available
    when work [that] had already been paid for by the
    bank was completed so that additional funds would
    be forthcoming.’’ The court further determined that,
    despite the bank having provided funding to install dry-
    wall in the third building, the developer never com-
    pleted its installation. According to the court, after the
    2007 agreement was implemented, there was ‘‘a clear
    inference . . . that no draw request was made because
    no draw request would have been honored since the
    work for which the developers had already been paid
    had not been done.’’ The record supports the court’s
    conclusions.7
    Here, the language of the revolving loan agreement
    provided that the funding to which the developer was
    entitled was to be determined by the construction costs
    that the developer submitted to the bank. The 2006
    agreement, which was operative when the developer
    made its September 23, 2007 draw request in the amount
    of $62,400 for drywall installation, removed the revolv-
    ing loan’s funding maximum of $117,000 per unit, but
    still provided that the ‘‘[the bank] will advance [to the
    developer] . . . 90 percent of the actual vertical hard
    and soft construction costs, of each unit . . . .’’ Even
    so, the 2006 agreement did not alter the requirement
    that ‘‘[r]equests for disbursements shall be submitted
    by [the developer] on forms satisfactory to [the bank]
    . . . .’’ (Emphasis added.) Indeed, to disburse funding
    to the developer, the bank still required ‘‘[a] letter from
    [the developer] requesting the amount of the particular
    disbursement . . . .’’
    The record reflects that, after the 2006 agreement
    went into effect, the developer never increased the con-
    struction costs that it submitted to the bank. The evi-
    dence in the record demonstrates that, during
    construction on the third building, the developer sub-
    mitted to the bank construction costs in the amount of
    $113,750 per unit, which was the same level of funding
    that the developer had requested for the second build-
    ing, prior to the 2006 amendment. Thus, notwithstand-
    ing the parties’ agreement to remove the $117,000
    maximum funding limit, the bank had no reason or basis
    to fund the developer’s construction costs in excess of
    the amount the developer actually requested. Accord-
    ingly, because the developer continued to submit
    requests for construction costs in the amount of
    $113,750 per unit, the bank fulfilled those requests by
    disbursing to the developer funding at the rate of
    $102,375 per unit, which was 90 percent of the develop-
    er’s submitted construction costs.
    With respect to drywall installation in the third build-
    ing specifically, the developer submitted to the bank
    costs of $6000 per unit.8 As a result, the bank was
    required to disburse $5400 per unit, which was 90 per-
    cent of the developer’s $6000 submitted cost. At the time
    the developer made the September, 2007 disbursement
    request, however, the developer already had received
    draws in the amount of $1500 per unit for drywall instal-
    lation. Thus, the developer requested and received the
    remaining $3900 per unit, or a total of $62,400, for dry-
    wall installation for the sixteen units in the third
    building.
    The record thus demonstrates that the bank complied
    with its contractual obligations by fulfilling the develop-
    er’s requests for funding based on the construction
    costs that the developer submitted. As a result, the bank
    never breached any of its obligations to fund properly
    submitted draw requests for the developer’s construc-
    tion costs.
    Despite the bank’s financial disbursement in compli-
    ance with the construction costs submitted by the devel-
    oper, the defendants argue that the bank nonetheless
    should have been aware that the developer’s actual
    construction costs were higher than what was reflected
    in its construction budget. Specifically, the defendants
    contend that, because the 2006 agreement provided that
    the developer was entitled to ‘‘90 percent of the actual
    vertical hard and soft construction costs,’’ the bank
    breached the terms of the revolving loan by not advanc-
    ing to the developer further sums, in addition to the
    costs the developer submitted, to cover the actual con-
    struction costs. (Emphasis added.) Thus, the defen-
    dants argue that, because the court should have found
    that the bank failed to advance to it further sums, the
    developer’s failure to continue making interest pay-
    ments did not constitute a breach of the loan docu-
    ments. To support this argument, the defendants rely
    on the principle that ‘‘a total breach of the contract by
    one party relieves the injured party of any further duty
    to perform further obligations under the contract.’’
    (Emphasis omitted; internal quotation marks omitted.)
    Shah v. Cover-It, Inc., 
    86 Conn. App. 71
    , 75, 
    859 A.2d 959
     (2004). This claim borders on the frivolous.
    First, and most significantly, the insuperable obstacle
    for the defendants is the language of the loan docu-
    ments. In particular, the loan documents provided that
    the amount of funding to which the developer was enti-
    tled was to be determined by the construction costs
    that the developer submitted to the bank. Therefore,
    the bank was obligated to fund the construction costs
    based on only the submission of such costs by the
    developer. There is no dispute that this is precisely
    what the bank did. There is no provision in the loan
    documents, nor any other sound legal basis, for requir-
    ing the bank to fund construction costs that were not
    properly submitted to it.
    Second, and relatedly, the record demonstrates that
    the developer never once increased the construction
    costs that it submitted to the bank for the third building,
    despite its ability to do so.9 Thus, even if additional
    funds were available for the drywall installation, the
    developer never submitted a draw request to obtain
    those additional funds. It is beyond our comprehension
    to understand how the bank was supposed to divine
    the developer’s actual construction costs and advance
    to it additional funds without the developer submitting
    those costs. Absent any request for additional funds, the
    bank clearly did not breach any contract. Consequently,
    the evidence in the record supports the court’s finding
    that the bank complied with its contractual obligations
    by disbursing funds to the developer at the rate of
    $102,375 per unit for the third building, which was 90
    percent of the construction costs submitted by the
    developer.
    II
    The defendants also claim that the court improperly
    concluded that the bank made reasonable efforts to
    mitigate its damages following the default on the notes.
    Specifically, the defendants argue that the court should
    have found that the bank failed to mitigate its damages
    because (1) it ‘‘refused to provide additional funding
    to complete the units, which would have resulted in
    sales proceeds,’’ and (2) ‘‘it refused to convey the note
    for a reasonable sum.’’ The defendants’ claim has no
    merit.
    We begin by setting forth the standard of review. ‘‘We
    have often said in the contracts and torts contexts that
    the party receiving a damage award has a duty to make
    reasonable efforts to mitigate damages. . . . What con-
    stitutes a reasonable effort under the circumstances of
    a particular case is a question of fact for the trier. . . .
    Furthermore, we have concluded that the breaching
    party bears the burden of proving that the nonbreaching
    party has failed to mitigate damages. . . . The defen-
    dant thus bears the burden of proving that the plaintiff
    failed to make reasonable efforts to mitigate the amount
    of damages.’’ (Citation omitted; internal quotation
    marks omitted.) Vanliner Ins. Co. v. Fay, 
    98 Conn. App. 125
    , 145, 
    907 A.2d 1220
     (2006).
    ‘‘To claim successfully that the plaintiff failed to miti-
    gate damages, the defendant must show that the injured
    party failed to take reasonable action to lessen the
    damages; that the damages were in fact enhanced by
    such failure; and that the damages which could have
    been avoided can be measured with reasonable cer-
    tainty.’’ (Internal quotation marks omitted.) Preston v.
    Keith, 
    217 Conn. 12
    , 22, 
    584 A.2d 439
     (1991). Neverthe-
    less, ‘‘[t]he duty to mitigate damages does not require
    a party to sacrifice a substantial right of his own in
    order to minimize a loss.’’ Camp v. Cohn, 
    151 Conn. 623
    , 627, 
    201 A.2d 187
     (1964).
    The following additional facts, which the court rea-
    sonably could have found, and procedural history are
    relevant to this claim. In the summer of 2008, after the
    loans were in default, the defendants and the bank
    entered into negotiations to save the project. The defen-
    dants made an offer to the bank under which the bank
    would loan them an additional $583,000 that they would
    use to complete construction on the third building. As
    part of this offer, the defendants additionally promised
    that, within three months of receiving funding from the
    bank, they would repay the sum of $791,000. The bank
    refused that offer.
    In 2009, after the bank sent the second default letter,
    the defendants made four separate offers to the bank
    to purchase the notes for sums ranging from $1,000,000
    to $1,250,000. The bank also refused those offers.
    Indeed, at the time of trial, the bank represented that
    the payoff of the outstanding balance on the loans was
    nearly $2,000,000 in principal, interest and late charges,
    in addition to more than $100,000 for its payment of
    property taxes to the town.
    In its oral decision, the court stated that ‘‘[t]he failure
    of the bank to take less than fifty cents on the dollar
    was hardly . . . a violation of any covenant of fair deal-
    ing . . . .’’ The defendants then brought the present
    appeal, and filed a motion for articulation on the ground
    that ‘‘the [trial] court’s . . . order was unclear as to
    whether the court considered the defendants’ claim that
    the [bank] did not adequately mitigate its damages.’’
    The trial court issued an articulation, in which it
    stated the following: ‘‘The defendants argued [at trial]
    that among the myriad defalcations [they] claimed . . .
    the bank to have been guilty of, the foreclosing bank
    failed to mitigate damages. Largely, this was a claim
    that by not continuing to fund the defendants’ troubled
    project by infusing additional monies, the bank caused
    the project to fail, thus increasing damages. Basically,
    the defendants’ claim was that if additional funding had
    been provided the project would have been successful
    so there would have been no damages. The defendants
    also claimed that by not accepting settlement offers
    made by the defendants, the bank suffered larger dam-
    ages than would have been the case had the . . . bank
    taken what the court referred to in its original decision
    as less than 50 cents on the dollar. Unfortunately for
    the defendants’ position, the evidence . . . does not
    justify such a conclusion. As the court thought it had
    said in its decision, there was no failure to mitigate
    damages by the [bank].’’ The record supports the con-
    clusions of the court.
    First, the defendants claim that the bank’s refusal to
    provide the developer with additional funds after the
    notes were in default constituted a failure on the part
    of the bank to mitigate its damages. We disagree.
    Under the defendants’ proposal, the bank would have
    been required to expend more than $500,000 on what
    the court characterized as ‘‘the defendants’ troubled
    project.’’ Indeed, by the time that the proposal was
    made, the developer already had defaulted on the notes
    and was facing multiple pending lawsuits as the result
    of failing to pay its subcontractors. The defendants’
    mere promise to repay the bank hardly guaranteed that
    the bank would minimize its losses. See 16 Restatement
    (Second), Contracts § 350, comment (g), p. 132 (1981)
    (it is not ‘‘reasonable to expect [nonbreaching party]
    to take steps to avoid loss if those steps may cause
    other serious loss’’); see also 22 Am. Jur. 2d 345, Dam-
    ages § 368 (2013) (‘‘[a] party to a contract who is not
    in breach need not make substantial expenditures to
    avoid damages from breach because compelling an
    innocent party to spend money to mitigate damages
    might entail risks beyond those assumed in the con-
    tract’’ [footnote omitted]).
    Second, the defendants claim that the court should
    have found that the bank failed to mitigate its damages
    because the bank did not accept their offers to purchase
    the notes. We are not persuaded.
    After the bank sent to the defendants the second
    default letter, the defendants made four offers to buy
    the note for sums ranging from $1,000,000 to $1,250,000.
    The record supports the court’s finding, however, that
    the value of the notes far exceeded those offers. Indeed,
    the court awarded to the bank more than $2,000,000 in
    principal, interest, attorney’s fees and taxes arising from
    the defendants’ default. Thus, as the court noted, the
    defendants did not demonstrate that the bank failed to
    mitigate damages by not accepting ‘‘less than 50 cents
    on the dollar.’’
    The defendants’ claim ignores the fact that the devel-
    oper defaulted on the notes in April, 2008. At that point,
    the bank had the legal right to accelerate payment on
    the notes and collect on the developer’s outstanding
    debt. Additionally, the guarantors all had executed guar-
    anties, whereby they had made absolute promises to
    pay the outstanding debt on the notes upon the develop-
    er’s default. Therefore, once the notes went into default,
    the bank was authorized to collect on the debt by bring-
    ing the present action, and it was under no obligation
    to forgo its right to recover its losses by selling the
    notes at a discount.
    Our Supreme Court has long abided by the principle
    that ‘‘[t]he duty of the plaintiff to keep the damages
    from the breach of the contract as low as reasonably
    possible does not require of it that it disregard its own
    interests or exalt above them those of the defaulting
    defendants. . . . [The plaintiff is] not under an obliga-
    tion to sacrifice any substantial right of its own in order
    to minimize the loss of the defendants.’’ (Citation omit-
    ted.) Raff Co. v. Murphy, 
    110 Conn. 234
    , 243, 
    147 A. 709
     (1929). The evidence in the record supports the
    court’s conclusion that the bank’s refusal of the defen-
    dants’ offers to buy the notes did not constitute a failure
    to mitigate its damages. The bank had the legal right
    to collect on the defaulted notes, and it was not under
    any obligation to accept any of the defendants’ offers
    for settlement.
    In sum, the defendants have not met their burden to
    prove that the bank failed to mitigate damages. After
    a careful review of the record, we conclude that the
    evidence before the court demonstrated that the bank’s
    conduct was reasonable under the circumstances, and,
    thus, that the court’s factual findings were not
    clearly erroneous.
    The judgment is affirmed.
    In this opinion the other judges concurred.
    1
    In this opinion, the loan agreements, notes, guaranties and mortgage are
    referred to collectively as the ‘‘loan documents.’’
    2
    The terms of the revolving loan agreement required the developer to
    ‘‘maintain a minimum unit absorption rate of (i) 12 units in year one (ii) 24
    units in year two and (iii) 25 units in year three.’’
    3
    Section 4.02 (a) of the revolving loan agreement provided in relevant
    part: ‘‘The maximum amount [the developer] shall be entitled to draw down
    on the [p]rincipal [a]mount with respect to each unit shall not exceed the
    lesser of (i) ninety (90%) percent of the actual vertical hard and soft costs
    of construction, including interest but not to include marketing . . . [or] (iv)
    [o]ne [h]undred [s]eventeen [t]housand and 00/100 [d]ollars ($117,000.00) per
    unit.’’
    4
    The terms ‘‘drywall,’’ ‘‘Sheetrock,’’ and ‘‘rock’’ were used interchangeably
    at trial.
    5
    The defendants asserted as special defenses: unclean hands; payment;
    fraud; waiver; estoppel; laches; breach of the implied covenant of good
    faith and fair dealing; and frustration of purpose. The defendants filed the
    following counterclaims: breach of contract; breach of the implied covenant
    of good faith and fair dealing; breach of fiduciary duty; promissory estoppel;
    violation of the Connecticut Unfair Trade Practices Act, General Statutes
    § 42-110a et seq.; fraudulent misrepresentation; negligent misrepresentation;
    and tortious interference with a business relationship. The defendants do
    not raise any issues on appeal regarding the court’s rejection of its special
    defenses or counterclaims.
    6
    During the pendency of this appeal, in response to the defendants’ motion
    for articulation filed with this court, the trial court clarified that it had
    concluded that the bank adequately had mitigated its damages.
    7
    The defendants do not challenge the court’s implicit conclusion that,
    after the bank had paid for the drywall installation and the 2007 agreement
    was implemented, the developer never submitted another draw request.
    Indeed, at oral argument before this court, the defendants’ counsel conceded
    that, after the developer’s September, 2007 request for drywall labor costs
    had been submitted, the developer made no further draw requests of the
    bank.
    8
    In its draw requests, the developer submitted to the bank itemized con-
    struction costs, which specified the costs of constructing different elements
    of the condominium units. Then, pursuant to the terms of the revolving
    loan agreement, the bank disbursed to the developer 90 percent of the
    itemized costs.
    9
    Indeed, the developer increased the construction costs that it submitted
    to the bank from $85,000 per unit for the first building to $113,750 for the
    second building. The developer, thus, was aware that, to receive increased
    funding from the revolving loan, it could increase the construction costs
    that it submitted to the bank, and had already done so.