Winakor v. Savalle ( 2020 )


Menu:
  • ***********************************************
    The “officially released” date that appears near the be-
    ginning of each opinion is the date the opinion will be pub-
    lished in the Connecticut Law Journal or the date it was
    released as a slip opinion. The operative date for the be-
    ginning of all time periods for filing postopinion motions
    and petitions for certification is the “officially released”
    date appearing in the opinion.
    All opinions are subject to modification and technical
    correction prior to official publication in the Connecticut
    Reports and Connecticut Appellate Reports. In the event of
    discrepancies between the advance release version of an
    opinion and the latest version appearing in the Connecticut
    Law Journal and subsequently in the Connecticut Reports
    or Connecticut Appellate Reports, the latest version is to
    be considered authoritative.
    The syllabus and procedural history accompanying the
    opinion as it appears in the Connecticut Law Journal and
    bound volumes of official reports are copyrighted by the
    Secretary of the State, State of Connecticut, and may not
    be reproduced and distributed without the express written
    permission of the Commission on Official Legal Publica-
    tions, Judicial Branch, State of Connecticut.
    ***********************************************
    LEE WINAKOR v. VINCENT SAVALLE
    (AC 42306)
    Prescott, Moll and Harper, Js.
    Syllabus
    The plaintiff, who had hired the defendant to perform certain home construc-
    tion site work in conjunction with the construction of a new home,
    sought to recover damages for breach of contract and for violation of
    the Connecticut Unfair Trade Practices Act (CUTPA) (§ 42-110a et seq.),
    alleging that the work the defendant performed was in violation of the
    Home Improvement Act (§ 20-418 et seq.). The trial court rendered
    judgment in part in favor of the plaintiff and awarded the plaintiff
    compensatory damages and attorney’s fees. The trial court determined
    that the defendant had breached the contract by failing to complete the
    project on time and had used improper techniques and methods to fulfill
    the contract. On the defendant’s appeal to this court, held:
    1. The trial court improperly determined that the defendant was liable under
    CUTPA on the basis of its finding that the defendant violated the Home
    Improvement Act, as the work performed by the defendant was part of
    new home construction and, thus, fell within the statutory exception
    contained in § 20-419 (4), and as such, the defendant’s services did not
    constitute home improvement and there existed no home improvement
    contract that the defendant violated under the act: contrary to the plain-
    tiff’s claim, interpreting the definition of home improvement to include
    work performed on land regardless of whether there is an existing
    building would render the clause providing for an exception to new
    home construction meaningless; furthermore, as the defendant did not
    violate CUTPA and without any contractual provision on which properly
    to base an award of attorney’s fees, there was no basis for the plaintiff’s
    recovery of any attorney’s fees and costs in connection with the alleged
    CUTPA violation.
    2. The defendant could not prevail on his claim that the trial court improperly
    rendered judgment in favor of the plaintiff on his breach of contract
    claim because the trial court’s findings were clearly erroneous, the
    plaintiff never having proved beyond reasonable speculation that the
    defendant’s conduct caused damage to the plaintiff’s property; the record
    provided sufficient evidence to support the trial court’s finding of a
    breach of contract claim, the trial court was free to credit the testimony
    of the plaintiff’s witnesses in concluding that the defendant’s conduct
    caused the damages suffered by the plaintiff, and the defendant’s argu-
    ment that there were other possible causes for the plaintiff’s damages
    was inconsistent with the standard by this court must review the trial
    court’s findings, which is not whether there were other conceivable
    causes but, rather, whether there was evidence to allow the court to
    find that the defendant’s conduct was the cause.
    Argued March 3—officially released July 7, 2020
    Procedural History
    Action to recover damages for breach of contract,
    and for other relief, brought to the Superior Court in
    the judicial district of New London and tried to the
    court, Frechette, J.; judgment in part for the plaintiff,
    from which the defendant appealed to this court; there-
    after, the trial court granted the plaintiff’s motion for
    attorney’s fees, and the defendant amended his appeal.
    Reversed in part; judgment directed.
    Patrick J. Markey, for the appellant (defendant).
    Paul M. Geraghty, with whom was Jonathan
    Friedler, for the appellee (plaintiff).
    Opinion
    PRESCOTT, J. The principal issue in this appeal is
    whether services provided by a contractor as part of
    the construction of a new residence fell outside of the
    statutory purview of the Home Improvement Act
    (Improvement Act), General Statutes § 20-418 et seq.
    The defendant, Vincent Savalle, appeals from the judg-
    ment of the trial court rendered in favor of the plaintiff,
    Lee Winakor, in which the court concluded that the
    defendant was liable to the plaintiff in the amount of
    $100,173.32 for breach of contract, violation of the
    Improvement Act, and violation of the Connecticut
    Unfair Trade Practices Act (CUTPA), General Statutes
    § 42-110b et seq. On appeal, the defendant claims,
    among other things, that the trial court improperly ren-
    dered judgment in favor the plaintiff on (1) the CUTPA
    count because it predicated CUTPA liability on the erro-
    neous determination that the defendant had violated
    the Improvement Act, and (2) the breach of contract
    count because there was insufficient evidence to estab-
    lish causation, which is necessary to prove damages.
    The defendant also claims that the trial court abused
    its discretion in awarding attorney’s fees to the plaintiff.
    We agree with the defendant on his claim regarding the
    improper imposition of CUTPA liability and the award
    of attorney’s fees but disagree with him on his claim
    that the court improperly found for the plaintiff on the
    count alleging a breach of contract. Accordingly, we
    affirm in part and reverse in part the judgment.
    The following facts, as found by the court in its memo-
    randum of decision or as undisputed in the record,
    and procedural history are relevant to the defendant’s
    claims. In 2005, the plaintiff purchased real property
    located at 217 Legend Wood Road in North Stonington.
    In 2012, he entered into a contract with Golden Hammer
    Builders, LLC (Golden Hammer), through its principal,
    Brian Mawdsley, to construct a new single-family home
    on the property (GH contract). The GH contract con-
    templated site work and construction of the home for
    $425,300 and permitted the plaintiff to find another con-
    tractor to perform the site work and to subtract the
    cost of such work, $55,000, from the total cost.1
    In mid-2012, the plaintiff met with the defendant to
    consider hiring him to perform the site work. After
    meeting with the plaintiff to discuss the scope of the
    site work, the defendant submitted a bid for $50,000,
    which was $5000 less than the $55,000 it would have
    cost the plaintiff under the GH contract. As a result,
    the plaintiff hired the defendant to perform the site
    work. The plaintiff drafted a contract pursuant to which
    the defendant would purchase materials and provide a
    variety of services that originally were included in the
    GH contract.2 The parties subsequently signed a written
    contract on September 1, 2012, in which the plaintiff
    agreed to pay the contract price of $50,000 for the site
    work, and the defendant agreed to complete the con-
    tract within one year of the start date. Subsequently,
    Mawdsley applied, on the plaintiff’s behalf, for a new
    home building permit on September 17, 2012, under
    his new home construction contractor’s license. The
    building permit was issued on January 28, 2013.
    The defendant began working at the site in Septem-
    ber, 2012. The trial court found that ‘‘[h]e hammered
    out a ledge for the foundation, installed a septic tank,
    constructed retaining walls, began site work, installed
    a propane tank and gas lines (which he later agreed
    to do), installed the well electrical line, and partially
    finished the driveway.’’ In December, 2013, Golden
    Hammer finished building the house, and the plaintiff
    received a partial certificate of occupancy. In January,
    2014, a full certificate of occupancy was issued for
    the house.
    At that time, however, the defendant had not yet
    completed his work in accordance with his contract
    with the plaintiff. The Planning and Zoning Commission
    of the Town of North Stonington (town) issued a letter
    to the plaintiff indicating that the house substantially
    conformed to its zoning regulations and would be
    approved for zoning compliance on the conditions that,
    among other things, ‘‘the final grading, landscaping, and
    soil stabilization be completed within [six] months’’ and
    the driveway be widened.
    On January 18, 2014, the defendant entered into a
    second contract with the plaintiff. That agreement
    required the defendant to complete the work that was
    set forth in the first contract by April 1, 2014, for an
    additional $10,000. At this point, the plaintiff already
    had paid the defendant $53,000.
    Over time, it became apparent that there were prob-
    lems associated with the quality of the defendant’s
    work.3 Due to the plaintiff’s dissatisfaction with the
    defendant’s workmanship and the defendant’s failure to
    complete the project according to schedule, the plaintiff
    terminated his relationship with the defendant in April,
    2014. Subsequently, the plaintiff hired another contrac-
    tor, Charles Lindo, to remedy the flaws in the work that
    the defendant had completed and to finish the work that
    the defendant had failed to complete. Lindo ultimately
    completed the project at additional cost to the plaintiff.
    In October, 2014, the town notified the plaintiff that his
    new residence fully complied with its zoning regu-
    lations.
    On May 28, 2015, the plaintiff commenced this action
    against the defendant. The operative amended com-
    plaint asserted five separate counts: breach of contract
    (count one); unjust enrichment (count two); violations
    of the New Home Construction Contractors Act (New
    Home Act), General Statutes § 20-417a et seq. (count
    three);4 (4) violations of the Improvement Act (count
    four); and violations of CUTPA (count five). On August
    12, 2015, the defendant filed his answer and a counter-
    claim, in which he alleged that ‘‘[t]he plaintiff is
    indebted to the defendant in the amount of $28,000
    for the services he performed and the materials he
    supplied.’’ In response, the plaintiff filed his answer and
    a special defense asserting that the defendant is barred
    from recovering from the plaintiff due to his violation
    of the New Home Act.
    The case was tried before the court, Frechette, J.,
    over nine days, beginning on March 6, 2018. Subse-
    quently, the parties submitted posttrial briefs.
    In a memorandum of decision issued on August 21,
    2018, the court found that the defendant had breached
    his contract with the plaintiff by not completing the
    project on time and by ‘‘using improper techniques and
    methods to [perform] the contract . . . [causing] the
    plaintiff [to incur] additional expenses to repair and
    finish the work the defendant was contractually
    required to do.’’ Having found a breach of an enforce-
    able contract, the court concluded that the plaintiff was
    not entitled to recover for unjust enrichment. See Gagne
    v. Vaccaro, 
    255 Conn. 390
    , 401, 
    766 A.2d 416
    (2001) (lack
    of remedy under contract is precondition for recovery
    under unjust enrichment theory). The court further
    determined that the defendant violated the Improve-
    ment Act by failing to comply with certain statutory
    requirements regarding the form of the contract. Specif-
    ically, it found that the contract did not contain the
    name, address, and registration number of the contrac-
    tor; did not include a notice of the homeowner’s cancel-
    lation rights; did not disclose whether the defendant
    worked as a sole proprietor; and did not contain the
    entire agreement by not including, for example, provi-
    sions regarding the propane tank installation. Finally,
    the court concluded that, on the basis of the Improve-
    ment Act violations, the defendant committed a per
    se CUTPA violation. Accordingly, the court rendered
    judgment in favor of the plaintiff on counts one, three,
    four, and five of the complaint and awarded the plaintiff
    compensatory damages totaling $100,173.32. Subse-
    quently, the defendant filed a motion to reargue, chal-
    lenging, among other things, the court’s findings regard-
    ing the applicability of the Improvement Act, the
    existence of a contract, and the damages awarded to the
    plaintiff. The motion was denied, and the defendant’s
    appeal followed.
    After judgment was rendered, the plaintiff also filed
    a motion seeking an award of attorney’s fees on the
    basis of the CUTPA violation. On August 19, 2019, the
    court held a hearing on the plaintiff’s motion for attor-
    ney’s fees. Thereafter, on September 4, 2019, the court
    issued an order awarding the plaintiff $126,126.91 in
    attorney’s fees and $2412.05 in costs. The defendant
    amended his appeal to challenge the court’s order
    regarding attorney’s fees.
    I
    We first address the defendant’s claim that the court
    improperly rendered judgment in favor of the plaintiff
    on the CUTPA count on the basis of its finding that the
    defendant violated the Improvement Act.5 The defen-
    dant primarily asserts that the Improvement Act was
    inapplicable in this case because the work that he per-
    formed constitutes new home construction, which is
    explicitly exempted by the Improvement Act, and, thus,
    could not support the trial court’s imposition of CUTPA
    liability and its subsequent award of damages and attor-
    ney’s fees, which flowed therefrom. We agree that the
    court improperly determined that there was CUTPA
    liability based on an underlying violation of the
    Improvement Act. Accordingly, we reverse the court’s
    judgment on counts three, four, and five.
    We begin by setting forth the standard of review
    applicable to this claim.
    ‘‘CUTPA provides that [n]o person shall engage in
    unfair methods of competition and unfair or deceptive
    acts or practices in the conduct of any trade or com-
    merce. . . . It is well settled that whether a defendant’s
    acts constitute . . . deceptive or unfair trade practices
    under CUTPA, is a question of fact for the trier, to
    which, on appellate review, we accord our customary
    deference.’’ (Citation omitted; internal quotation marks
    omitted.) Landmark Investment Group, LLC v. Chung
    Family Realty Partnership, LLC, 
    125 Conn. App. 678
    ,
    699, 
    10 A.3d 61
    (2010), cert. denied, 
    300 Conn. 914
    , 
    13 A.3d 1100
    (2011). Whether a defendant is subject to
    CUTPA and its applicability, however, are questions of
    law.
    Id., 700. ‘‘[If]
    a question of law is presented, review
    of the trial court’s ruling is plenary, and this court must
    determine whether the trial court’s conclusions are
    legally and logically correct, and whether they find sup-
    port in the facts appearing in the record.’’ (Internal
    quotation marks omitted.)
    Id., 701. ‘‘Our
    courts have interpreted [General Statutes] § 42-
    110g (a) to allow recovery only when the party seeking
    to recover damages meets the following two require-
    ments: First, he must establish that the conduct at issue
    constitutes an unfair or deceptive trade practice. . . .
    Second, he must present evidence providing the court
    with a basis for a reasonable estimate of the damages
    suffered. . . . Our Supreme Court has stated on sev-
    eral occasions that under the first requirement, the fail-
    ure to comply with the . . . Improvement Act is a per
    se violation of CUTPA by virtue of General Statutes
    [§ 20-427 (c)], which provides that any violation of the
    . . . Improvement Act is deemed to be an unfair or
    deceptive trade practice.’’ (Internal quotation marks
    omitted.) Scrivani v. Vallombroso, 
    99 Conn. App. 645
    ,
    651–52, 
    916 A.2d 827
    , cert. denied, 
    282 Conn. 904
    , 
    920 A.2d 309
    (2007).
    A
    The defendant argues that the plaintiff failed to satisfy
    the first requirement of proving his CUTPA claim
    because he failed to establish that the defendant’s con-
    duct constitutes an unfair or deceptive trade practice.
    Specifically, he argues that the court’s determination
    that he violated the Improvement Act—which served
    as the sole basis for establishing CUTPA liability—was
    legally flawed because the Improvement Act is not
    applicable under the facts of this case, as there was no
    ‘‘home improvement contract’’ between him and the
    plaintiff, as contemplated by General Statutes § 20-429.
    We agree.
    Resolution of this claim necessarily involves interpre-
    tation of the Improvement Act. The applicability of a
    statute to a given situation is a matter of statutory
    construction. ‘‘Issues of statutory construction raise
    questions of law, over which we exercise plenary
    review. . . . The process of statutory interpretation
    involves the determination of the meaning of the statu-
    tory language as applied to the facts of the case, includ-
    ing the question of whether the language does so
    apply. . . .
    ‘‘When construing a statute, [o]ur fundamental objec-
    tive is to ascertain and give effect to the apparent intent
    of the legislature. . . . In other words, we seek to
    determine, in a reasoned manner, the meaning of the
    statutory language as applied to the facts of [the] case,
    including the question of whether the language actually
    does apply. . . . General Statutes § 1-2z directs us first
    to consider the text of the statute itself and its relation-
    ship to other statutes.’’ (Footnote omitted; internal quo-
    tation marks omitted.) Western Dermatology Consul-
    tants, P.C. v. VitalWorks, Inc., 
    146 Conn. App. 169
    , 199,
    
    78 A.3d 167
    (2013), aff’d, 
    322 Conn. 541
    , 
    153 A.3d 574
    (2016). ‘‘A fundamental tenet of statutory construction
    is that statutes are to be construed to give effect to the
    apparent intention of the lawmaking body. . . . Where
    the words of a statute are clear, the task of a reviewing
    court is merely to apply the directive of the legislature
    since where the wording is plain, courts will not specu-
    late as to any supposed intention because the question
    before a court then is not what the legislature actually
    intended but what intention it expressed by the words
    that it used. . . . When two constructions [of a word]
    are possible, courts will adopt the one which makes
    the statute effective and workable . . . . [Further, a]
    statute should be construed so that no word, phrase or
    clause will be rendered meaningless.’’ (Citations omit-
    ted; internal quotation marks omitted.) Verrastro v.
    Sivertsen, 
    188 Conn. 213
    , 220–21, 
    448 A.2d 1344
    (1982).
    The trial court found that the defendant violated the
    Improvement Act because he did not comply with con-
    tract requirements prescribed by § 20-429.6 Signifi-
    cantly, however, § 20-429 by its express terms applies
    only to ‘‘home improvement contracts.’’ See General
    Statutes § 20-429 (a) (1) (A) (‘‘[n]o home improvement
    contract shall be valid or enforceable against an owner
    unless’’ (emphasis added)). Section 20-419 (5) defines
    a home improvement contract as ‘‘an agreement
    between a contractor and an owner for the performance
    of a home improvement.’’ The defendant argues that
    the work he performed did not constitute a ‘‘home
    improvement’’ for purposes of § 20-419 (4) but, rather,
    involved the construction of a new home, which is
    explicitly exempt from Improvement Act applicability.
    Our starting point is the broad language of § 20-419
    (4), which sets forth the type of work that constitutes
    a home improvement. It provides the following: ‘‘ ‘Home
    improvement’ includes, but is not limited to, the repair,
    replacement, remodeling, alteration, conversion, mod-
    ernization, improvement, rehabilitation or sandblasting
    of, or addition to any land or building or that portion
    thereof which is used or designed to be used as a private
    residence, dwelling place or residential rental property
    . . . . ‘Home improvement’ does not include: (A) The
    construction of a new home . . . .’’ Significantly, § 20-
    419 (4) expressly excludes new home construction as
    constituting home improvement.
    The defendant argues, among other things, that his
    work for the plaintiff does not fall within any of the
    types of work included within the definition of home
    improvement and, in fact, falls within the explicit new
    home construction exemption. In particular, he con-
    tends that new home construction is not confined to
    the physical building itself but can apply to site work
    that accompanies the building of the new home. The
    plaintiff, on the other hand, argues that the defendant’s
    work was ‘‘home improvement’’ under § 20-419 (4)
    because the statute’s list of work that constitutes ‘‘home
    improvement’’ is not exhaustive and the land on which
    the defendant performed work was, at the very least,
    ‘‘designed to be used as a private residence.’’ Thus, the
    plaintiff contends that ‘‘the [Improvement Act], by its
    very words, contemplates improvement to land, regard-
    less of whether or not there is a building thereupon.’’
    A critical determination for our analysis is whether the
    defendant’s conduct falls into the new home construc-
    tion exception, thereby rendering the Improvement Act
    inapplicable. If so, there is no further need to determine
    whether the conduct falls within the nonexhaustive list
    of work that does constitute home improvement.
    Although new home construction is not defined
    within the Improvement Act, our Supreme Court pre-
    viously has held that determining whether work consti-
    tutes new home construction is dependent on whether
    the particular work and the construction of the home
    ‘‘were so interrelated, temporally or otherwise, that the
    [work] constituted an integral part of the construction
    of a new home . . . .’’ (Internal quotation marks omit-
    ted.) Rizzo Pool Co. v. Del Grosso, 
    232 Conn. 666
    , 678,
    
    657 A.2d 1087
    (1995) (Rizzo). In determining whether
    construction work is sufficiently connected to new
    home construction, this court has considered whether
    the services furthered the goal of completing the home
    and whether they were required to make the home
    habitable. See Laser Contracting, LLC v. Torrance
    Family Ltd. Partnership, 
    108 Conn. App. 222
    , 227–29,
    
    947 A.2d 989
    (2008).
    Relying primarily on Rizzo and also citing to Drain
    Doctor, Inc. v. Lyman, 
    115 Conn. App. 457
    , 
    973 A.2d 672
    (2009), the trial court determined that the defendant’s
    work, which ‘‘related to the groundwork and landscap-
    ing of the house,’’ was separate and distinct from the
    new home construction, thereby constituting home
    improvement and implicating the [Improvement Act].
    The cases cited by the trial court, however, are factually
    distinguishable from the present case for the reasons
    that follow.
    In Drain Doctor, Inc., the defendant homeowner con-
    tracted with the plaintiff corporation to fix a broken
    sewer line at his home. Drain Doctor, Inc. v. 
    Lyman, supra
    , 
    115 Conn. App. 459
    . The nature of the construc-
    tion work involved the plaintiff’s repair to an existing
    component of a home that had already been built. This
    is in direct contrast to the present matter where no
    septic system had existed at the time the defendant
    began performing his contractual duties.
    In Rizzo, the defendants, while their new home was
    under construction, signed a contract with the plaintiff
    to install a swimming pool at the new home. 
    Rizzo, supra
    , 
    232 Conn. 669
    . ‘‘Although the defendants antici-
    pated that the pool would be installed prior to the com-
    pletion date of their new home, the contract did not
    contain either a starting date or a completion date.’’
    Id. After a
    dispute regarding when to begin construction
    of the pool ensued, the plaintiff initiated an action for
    breach of contract.
    Id., 670. The
    trial court precluded
    the defendants from asserting a special defense under
    the Improvement Act, holding that the Improvement
    Act was inapplicable to the contract because the con-
    struction of the pool was part of the construction of a
    new home.
    Id., 672–73. On
    appeal in Rizzo, our Supreme Court concluded
    that the pool installation was not part of the construc-
    tion of the new home. In particular, it held that the
    ‘‘pool installation contract was completely separate and
    distinct from the defendants’ home construction con-
    tract . . . . Moreover, the documents that comprise
    the contract for the construction of the swimming pool
    contain no indication that the pool was to have been
    installed at any particular stage of the new home con-
    struction, or even that it was to have been installed
    prior to the completion of the new home. In fact, the
    contract documents make no reference whatsoever to
    the construction of the defendants’ new home.’’ (Foot-
    note omitted.)
    Id., 677–78. Concluding
    that the pool
    installation and the new home construction were not
    ‘‘so interrelated, temporally or otherwise, that the instal-
    lation of the pool constituted an integral part of [t]he
    construction of a new home under § 20-419 (4) (A),’’
    the court held that the Improvement Act was applicable
    to parties’ contract. (Internal quotation marks omitted.)
    Id., 678. Key
    differences exist in the circumstances sur-
    rounding the contract between the parties in Rizzo and
    those in the present case. First, unlike the contract in
    Rizzo, which was entirely independent from the new
    home construction contract and did not make reference
    to the construction of the new residence, the contract
    between the plaintiff and the defendant in the present
    case required the defendant to perform various projects
    originally set forth in the GH contract and, thus, the
    contract was linked directly to the new home construc-
    tion contract. Furthermore, unlike in Rizzo, the con-
    tract in the present case specified that the defendant
    was to complete his work within one year of its signing.
    The fact that the construction of the home was com-
    pleted in December, 2013, a little more than one year
    from the date the defendant signed the contract, Sep-
    tember, 2012, temporally links the defendant’s work to
    the completion of the home and bolsters the argument
    that it was sufficiently ‘‘ ‘interrelated, temporally or oth-
    erwise’ ’’ with the home construction. See
    id., 678. The
    most significant consideration, in our view—and
    the one that most starkly distinguishes Rizzo from the
    present matter—is the nature of the construction work
    itself, namely, its relationship to the habitability of the
    home. In Rizzo, the dispute centered around the instal-
    lation of a pool. In addition to being physically detached
    from the home, the pool itself served only an ancillary
    function and was not significantly related to the habit-
    ability of the home. By contrast, the work the defendant
    contracted to perform in the present matter—in particu-
    lar, hammering out the ledge so that the foundation
    could be poured, digging the septic trench for the septic
    system, building retaining walls, and installing the sep-
    tic tank, among others—directly contributed to the
    overall function and habitability of the home.
    In Laser Contracting, LLC v. Torrance Family Ltd.
    
    Partnership, supra
    , 
    108 Conn. App. 227
    –29, this court
    directly addressed this consideration by holding that if
    the contracted services contribute to making a new
    home habitable that otherwise would be uninhabitable
    without such services, the work falls within the new
    home construction exception to the Improvement Act.
    The principal issue in Laser Contracting, LLC, was
    whether installing a modular home7 at a new site and
    in making improvements to the newly installed home
    were services that fell within the ambit of the Improve-
    ment Act’s new home construction exception, thus ren-
    dering the Improvement Act’s requirements inapplica-
    ble to the contract in that case.
    Id., 227. In
    that case,
    this court agreed with the trial court’s conclusion that
    ‘‘the modular house was uninhabitable and in need of
    electrical, plumbing and heating services. A new base-
    ment, septic system, well, garage and driveway were
    constructed where none previously had existed. In sum,
    the project involved the construction of a new home
    . . . .’’
    Id., 227–28. Furthermore,
    in Laser Contracting, LLC, this court
    held that even the specific ‘‘repairs, alterations and
    upgrades’’ to the modular home qualified as new home
    construction under the criteria employed by our
    Supreme Court in Rizzo.
    Id., 228–29. This
    court noted
    that in Rizzo, ‘‘the pool installation contract involved
    services that were physically separate and distinct from
    the new home construction, and performed by separate
    unrelated contractors. . . . In addition, the pool con-
    tract contained no indication that the pool was to be
    installed at any particular stage of the new home con-
    struction or even that it was to have been installed prior
    to the completion of the new home. . . . By contrast,
    the record in [Laser Contracting, LLC] shows that the
    plaintiff’s services . . . were not separate and distinct
    from the underlying project of reassembling and prepar-
    ing a modular home for resale at a new location. . . .
    Unlike the situation in [Rizzo], then, not only was the
    contractor always the same entity, but the services it
    performed consistently served the parties’ common
    goal of completing the house for resale.’’
    Id. Having employed
    the analysis set forth in Rizzo and
    Laser Contracting, LLC, we conclude that the defen-
    dant’s services for the plaintiff were part and parcel of
    the construction of the plaintiff’s new home. Although
    there was more than one contractor involved in the
    construction work here, the defendant’s work was origi-
    nally contemplated as part of the GH contract to con-
    struct a new residence and took place simultaneously
    with Golden Hammer’s construction of the new home.
    The tasks performed were sufficiently interrelated to
    the new home construction so as to fall within the new
    home construction exception of the Improvement Act.
    The inapplicability of the Improvement Act to the
    parties’ contract in this case is also supported by other
    definitions within that act, particularly the definition of
    ‘‘owner’’ as it applies to a home improvement contract.
    Section 20-419 (6) defines an owner as ‘‘a person who
    owns or resides in a private residence and includes any
    agent thereof, including, but not limited to, a condomin-
    ium association. . . .’’ ‘‘‘Private residence’ ’’ is defined
    as ‘‘a single family dwelling . . . .’’ General Statutes
    § 20-419 (8). These definitions, read in conjunction with
    the previously examined case law, bolster the conclu-
    sion that work performed in relation to the construction
    of a home not yet in existence constitutes new home
    construction, which is exempt from the Improvement
    Act. Although § 20-419 (6) explicitly provides that an
    individual need not reside in the private residence in
    order to qualify as an owner, it is axiomatic that there
    needs to be a dwelling within which the individual could
    reside for it to be considered a private residence such
    that it invokes the plaintiff’s status as an ‘‘owner.’’
    The plaintiff’s argument that ‘‘home improvement’’
    includes work performed on the land, regardless of
    whether there is an existing building, would render the
    very clause providing for an exception to new home
    construction meaningless. Under the plaintiff’s logic,
    all site work related to new home construction would
    always constitute ‘‘home improvement’’ and, thus, fall
    within the purview of the Improvement Act. It further
    would render the definition of ‘‘private residence’’
    meaningless, if no dwelling needs to exist for work to
    constitute home improvement. If different interpreta-
    tions of a statute are possible, we must adopt the one
    that creates workable results and does not render any
    words or phrases meaningless. See Verrastro v.
    
    Sivertsen, supra
    , 
    188 Conn. 220
    –21. In the present mat-
    ter, the defendant’s proposed interpretation of ‘‘home
    improvement’’ creates workable results and is sup-
    ported by our case law; on the contrary, the plaintiff’s
    proposed interpretation creates unworkable results.
    In light of the foregoing, we conclude that the work
    performed by the defendant was a part of new home
    construction and, thus, falls within the statutory excep-
    tion contained in § 20-419 (4). As such, the defendant’s
    services were not ‘‘home improvements’’ pursuant to
    § 20-419 (5). Because no home improvement contract
    existed, the defendant could not have violated the
    Improvement Act.8 Because the sole basis for the defen-
    dant’s CUTPA liability was his alleged Improvement
    Act violation, we reverse the court’s judgment finding
    the defendant liable for violating CUTPA.9
    B
    The defendant also claims that the court abused its
    discretion by awarding attorney’s fees to the plaintiff.
    Specifically, he argues that no attorney’s fees should
    have been awarded because (1) the contract he alleg-
    edly breached did not provide for the recovery of attor-
    ney’s fees and (2) he did not violate CUTPA, which
    permits recovery of attorney’s fees only on a finding
    that CUTPA liability exists.10
    In contrast, the plaintiff argues that the court did not
    abuse its discretion in awarding attorney’s fees not only
    on the CUTPA claim but also with respect to the breach
    of contract claim. He contends that because the two
    claims are inextricably related, it would have been
    impracticable to segregate and apportion the fees. We
    agree with the defendant that the court improperly
    awarded attorney’s fees to the plaintiff.
    Before addressing this claim, we first set forth the
    relevant legal principles concerning a court’s award of
    attorney’s fees for breach of contract and CUTPA
    claims. ‘‘[U]nder the American rule,11 the plaintiff ordi-
    narily cannot recover attorney’s fees for breach of con-
    tract in the absence of an express provision allowing
    recovery . . . .’’ (Footnote in original.) Aurora Loan
    Services, LLC v. Hirsch, 
    170 Conn. App. 439
    , 453, 
    154 A.3d 1009
    (2017). In the present matter, the contract
    between the plaintiff and the defendant did not
    expressly authorize the nonbreaching party to recover
    attorney’s fees. Accordingly, the plaintiff may not
    recover attorney’s fees for his breach of contract claim.
    CUTPA, however, specifically allows the court to
    award legal fees associated with an action brought pur-
    suant to the act. Specifically, § 42-110g (d) provides in
    relevant part: ‘‘In any action brought by a person under
    this section, the court may award, to the plaintiff, in
    addition to the relief provided in this section, costs and
    reasonable attorneys’ fees based on the work reason-
    ably performed by an attorney and not on the amount
    of recovery. . . .’’
    Turning to the present case, the trial court, regarding
    attorney’s fees, stated in its memorandum of decision:
    ‘‘Having found a violation of CUTPA here, the court
    found the plaintiff was entitled to recover attorney’s
    fees and costs.’’ It further concluded that ‘‘the plaintiff
    should be awarded his fees for establishing his breach
    of contract claims . . . .’’
    Given our conclusion that the defendant did not vio-
    late CUTPA, there is no basis for the plaintiff’s recovery
    of any attorney’s fees in the present case. Having
    reversed the court’s judgment on the CUTPA count, and
    without any contractual provision on which properly
    to base an award of attorney’s fees, we accordingly
    reverse the court’s judgment awarding the plaintiff
    $126,126.91 in attorney’s fees and $2412.05 in costs in
    connection with the CUTPA violation.
    II
    Lastly, the defendant claims that the court improperly
    rendered judgment in favor of the plaintiff on his breach
    of contract claim. In particular, the defendant argues
    that the court’s finding that his breach of contract
    caused the plaintiff’s damages was clearly erroneous.
    We disagree and, accordingly, affirm the court’s judg-
    ment on the plaintiff’s breach of contract claim.
    As a preliminary matter, the plaintiff contends that
    the defendant has not adequately challenged the court’s
    judgment as to the breach of contract count but, instead,
    ‘‘only appears to [attack] the findings on [a] cursory
    level.’’ The defendant responds that, although he did
    not expressly label them as such, his general arguments
    that the court’s determinations were based on specula-
    tion and insufficient evidence sufficiently challenge the
    court’s findings with respect to causation as it relates
    to the breach of contract count. Even if we assume for
    purposes of argument that the defendant had ade-
    quately briefed his challenge to the court’s finding of
    causation, we still conclude that he is not entitled to
    relief on this claim.
    We begin by setting forth the standard of review
    and legal principles relevant to this claim. ‘‘It is well
    established that [t]he elements of a breach of contract
    action are the formation of an agreement, performance
    by one party, breach of the agreement by the other
    party and damages. . . . Although this court has inti-
    mated that causation is an additional element thereof
    . . . proof of causation more properly is classified as
    part and parcel of a party’s claim for breach of contract
    damages.’’ (Citations omitted; internal quotation marks
    omitted.) Meadowbrook Center, Inc. v. Buchman, 
    149 Conn. App. 177
    , 186, 
    90 A.3d 219
    (2014). ‘‘Under Con-
    necticut law, the causation standard applicable to
    breach of contract actions asks not whether a defen-
    dant’s conduct was a proximate cause of the plaintiff’s
    injuries, but rather whether those injuries were foresee-
    able to the defendant and naturally and directly resulted
    from the defendant’s conduct.’’ Theodore v. Lifeline
    Systems Co., 
    173 Conn. App. 291
    , 306 n.5, 
    163 A.3d 654
    (2017).
    ‘‘Causation [is] a question of fact for the [fact finder]
    to determine . . . and, thus, is governed by the clearly
    erroneous standard of review.’’ (Citations omitted;
    internal quotation marks omitted.) Meadowbrook Cen-
    ter, Inc. v. 
    Buchman, supra
    , 
    149 Conn. App. 193
    . Under
    this standard, ‘‘we overturn a finding of fact when there
    is no evidence in the record to support it . . . or when
    although there is evidence to support it, the reviewing
    court on the entire evidence is left with the definite and
    firm conviction that a mistake has been committed.’’
    (Internal quotation marks omitted.) Naples v. Keystone
    Building & Development Corp., 
    295 Conn. 214
    , 225, 
    990 A.2d 326
    (2010).
    Here, the court found that the plaintiff proved all
    elements of his breach of contract claim. On the issue
    of damages, the court stated in its memorandum of
    decision that ‘‘the plaintiff provided a detailed account
    of the damages he sustained due to the defendant’s
    poor workmanship,’’ finding that ‘‘[a]s a result [of] the
    defendant’s improper work, the plaintiff paid $50,714.46
    to finish the defendant’s work and $60,508.86 for correc-
    tive work . . . .’’
    On appeal, the defendant argues that the court’s find-
    ing of damages is clearly erroneous because the plaintiff
    never proved beyond speculation that the defendant’s
    conduct caused damage to the plaintiff’s property. He
    contends that ‘‘[t]he intervening period of time between
    [his] conduct and the appearance of any defective con-
    dition, the lack of a definitely identified cause for the
    defective conditions, the fact that the plaintiff had work
    done after [he] left the job which was not necessary or
    that the plaintiff did not do work he should have done,
    and the several other potential causes of the defective
    conditions, ensured that any conclusion of causation
    was premised on mere speculation.’’
    The defendant’s arguments can be best characterized
    as an assertion that there were other possible causes
    for the plaintiff’s damages. This contention, however,
    is inconsistent with the standard by which we must
    review the court’s finding—it is not whether there are
    other conceivable causes but, rather, whether there was
    evidence to allow the court to find that the defendant’s
    conduct was the cause. ‘‘Proof of a material fact . . .
    need not be so conclusive as to exclude every other
    hypothesis. It is sufficient if the evidence produces in
    the mind of the trier a reasonable belief in the probabil-
    ity of the existence of the material fact.’’ Rockhill v.
    Danbury Hospital, 
    176 Conn. App. 39
    , 44, 
    168 A.3d 630
    (2017).
    The plaintiff, on the other hand, argues that there
    was adequate evidence to show that the defendant’s
    work caused his damages, particularly in the form of
    testimony from multiple witnesses, including Charles
    Lindo. We agree.
    Lindo served as a fact witness and as an expert wit-
    ness12 in the areas of site work, excavation, septic instal-
    lation, and site preparation; he testified as to various
    problems that arose as a result of, among other things,
    the defendant’s repeated use of rocks instead of sand
    as backfill.13 Other witnesses who testified regarding
    problems with the defendant’s backfilling included
    George Brennan, the town’s fire marshal,14 and Brett
    Sheldon, a representative from the gas company.15 Lindo
    also testified to problems he saw related to the defen-
    dant’s construction of the retaining walls, as well as
    the driveway.
    ‘‘[I]t is the exclusive province of the trier of fact to
    weigh . . . conflicting evidence, determine the credi-
    bility of witnesses and determine whether to accept
    some, all or none of a witness’ testimony.’’ Rockhill v.
    Danbury 
    Hospital, supra
    , 
    176 Conn. App. 44
    . The trial
    court, as the trier of fact, was free to credit the testi-
    mony of the plaintiff’s witnesses in concluding that the
    defendant’s conduct caused the damages suffered by
    the plaintiff. We conclude, therefore, that the court’s
    findings were not clearly erroneous and there was evi-
    dence in the record to support the breach of contract
    judgment rendered in favor of the plaintiff.
    The judgment is reversed as to counts three, four,
    and five, and as to the award of attorney’s fees, and
    the case is remanded with direction to render judgment
    in favor of the defendant on those counts; the judgment
    is affirmed in all other respects.
    In this opinion the other judges concurred.
    1
    The GH contract was organized into the following categories: plans and
    permits, excavation, foundation, exterior, windows and doors, garage doors,
    insulation, electrical, plumbing, heating/AC, drywall, roofing, cabinets and
    vanities, flooring, interior trim and doors, stairs, painting, other, landscaping,
    and interior cleaning.
    2
    The contract required the defendant to ‘‘purchase and supply all supplies
    needed, clear the lot, remove stumps, dig the foundation hole and well
    trenches, purchase and install a septic tank, build a wall along the edge of
    the lakeside, build two retaining walls, build two driveways, reclaim asphalt
    for the driveway, grade the driveway at 8 percent, install footing drains and
    backfill foundation, finish the grade, seed the lawn, and conduct any
    blasting.’’
    3
    In its memorandum of decision, the trial court listed numerous deficienc-
    ies in the defendant’s performance. ‘‘First, the defendant did not properly
    backfill the foundation, using large rocks and boulders instead of dirt to
    support the foundation. . . . Additionally, the footing drains for the founda-
    tion were improperly installed, causing flooding in the basement of the
    house.
    ‘‘Second, the defendant improperly installed the septic system because it
    was backfilled with rocks instead of sand and too close to the surface,
    making it more likely it could be crushed. That is exactly what happened
    in 2014, when the defendant crushed the top of the tank, requiring another
    tank to be installed in April, 2014. This tank too was deficient and required
    replacing because the line running from it to the house had a break in
    it. . . . The defendant admitted in his posttrial brief that he crushed the
    septic tank.
    ‘‘Third, the defendant improperly constructed the retaining walls in the
    front and back of the house because they leaned, contained gaps, and washed
    out due to improper backfilling.
    ‘‘Fourth, the defendant improperly installed the patio. . . . [H]is installa-
    tion used rocks instead of sand as backfill, causing the patio to settle
    improperly.
    ***
    ‘‘Sixth, the defendant improperly installed the propane tank. . . . [He]
    used rocks rather than sand as backfill for the tank and pipe, causing the
    propane to leak from the pipe and damaging the tank. After inspection, the
    entire tank and pipe were replaced.
    ‘‘Seventh, the defendant improperly installed the well electrical line, using
    rocks instead of sand as backfill. Consequently, the electric line failed and
    needed replacement.
    ‘‘Eighth, the defendant did not properly reclaim or grade the driveway.
    The driveway was at a grade higher than 8 percent, causing the plaintiff to
    regrade it. Further, the lower half of the driveway was not reclaimed with
    asphalt because it was left as dirt.’’ (Footnote omitted.)
    4
    We note the following procedural posture regarding count three of the
    plaintiff’s complaint. As written, the count alleged: ‘‘The defendant’s conduct
    is in violation of [§] 20-417a [et seq].’’ The court, however, never substantively
    addressed the New Home Act, instead, seeming to treat count three as
    alleging a violation of the Improvement Act, although the plaintiff had
    expressly alleged an Improvement Act violation in count four. This is clearly
    evidenced by the court’s memorandum of decision, wherein the court
    grouped the two counts together in its analysis of the Improvement Act,
    stating: ‘‘The plaintiff’s third and fourth counts allege violations of the
    [Improvement Act] . . . .’’ After its analysis, the court concluded that the
    defendant violated the Improvement Act and stated: ‘‘The court finds for
    the plaintiff on counts three and four of his complaint.’’
    The plaintiff has failed to challenge the court’s decision to treat count
    three as pertaining to the Improvement Act rather than the New Home Act.
    The plaintiff’s motion for reconsideration filed with the trial court did not
    raise this issue. The plaintiff also failed to raise this issue on appeal pursuant
    to Practice Book § 63-4 (a) (1) (B). Accordingly, we conclude that the
    plaintiff has abandoned any claim that the court improperly failed to consider
    separately an alleged violation of the New Home Act.
    5
    We note that the defendant also claims that the trial court improperly
    rendered judgment in favor of the plaintiff on counts three and four of his
    complaint because the Improvement Act does not authorize him to bring a
    private cause of action. No appellate court in this state has directly decided
    whether the Improvement Act authorizes an independent, private cause of
    action. In Hees v. Burke Construction, 
    290 Conn. 1
    , 
    961 A.2d 373
    (2009),
    however, our Supreme Court discussed the scope of General Statutes § 20-
    429 (a). After reviewing the relevant legislative history of the statute, the
    Supreme Court concluded that the statute provides a homeowner with a
    shield from liability sought by a contractor if the contractor failed to comply
    with the Improvement Act.
    Id., 12–13. Additionally,
    ‘‘our Superior Court
    [has] uniformly determined that . . . § 20-429 is a defense and cannot be
    used as an independent cause of action for a homeowner against a contrac-
    tor.’’ (Internal quotation marks omitted.) Huzi v. Anglace, Superior Court,
    judicial district of Ansonia-Milford, Docket No. CV-XX-XXXXXXX-S (October
    13, 2009).
    Here, the trial court expressly stated in its memorandum of decision that
    ‘‘the [Improvement Act] may not be used by a homeowner offensively against
    a contractor except where the homeowner asserts an affirmative CUTPA
    claim against the contractor.’’ This language suggests to us that the court
    understood that the defendant’s violations of the Improvement Act were
    material only to the extent that they served as a predicate for the defendant’s
    liability under the CUTPA claim but cannot serve as an independent basis
    for the defendant’s liability. In light of this conclusion, it is unclear why the
    court rendered judgment in favor of the plaintiff on counts three and four.
    In any event, because we conclude that the Improvement Act does not apply
    under the circumstances of this case and, thus, the court should not have
    rendered judgment in favor of the plaintiff on counts three, four, and five,
    we need not decide in this appeal whether the Improvement Act authorizes
    a freestanding private cause of action by a homeowner.
    6
    Specifically, the court found that the contract did not ‘‘contain the name
    and address of the contractor and the contractor’s registration number, did
    not contain a notice of the owner’s cancellation rights, and did not disclose
    whether the defendant worked as a sole proprietor, and did not contain the
    entire agreement’’ as required by § 20-429 (a) (1) (A).
    7
    ‘‘[A] modular home is largely manufactured somewhere away from the
    eventual home site and brought to the local home site for installation.’’
    (Internal quotation marks omitted.) Brenmor Properties, LLC v. Planning &
    Zoning Commission, 
    162 Conn. App. 678
    , 681 n.4, 
    136 A.3d 24
    (2016), aff’d,
    
    326 Conn. 55
    , 
    161 A.3d 545
    (2017).
    8
    The defendant also argues, alternatively, that, even if the Improvement
    Act were applicable, he is exempt due to his status as a licensed septic
    system installer pursuant to General Statutes § 20-428 and as a subcontrac-
    tor. Because we conclude that the Improvement Act is inapplicable, we
    need not address these arguments.
    9
    The defendant also argues that the plaintiff failed to satisfy the second
    CUTPA requirement of proving damages. He argues, among other things,
    that the type of conduct that the court found as the basis of his CUTPA
    violation was not within the purview of the Improvement Act and, therefore,
    damages awarded on that basis were improper. Having reversed the court’s
    judgment on the CUTPA count on a different basis, we need not address
    the merits of the defendant’s claim regarding damages.
    10
    Alternatively, he claims that, even if there were a CUTPA violation, the
    court abused its discretion by awarding the plaintiff all of his attorney’s
    fees instead of only those that he incurred in pursuing the CUTPA action.
    Because we conclude that the plaintiff is not entitled to any attorney’s fees,
    we need not reach the issue of apportionment of such fees.
    11
    ‘‘The general rule of law known as the American rule is that attorney’s
    fees and ordinary expenses and burdens of litigation are not allowed to the
    successful party absent a contractual or statutory exception. . . . Connecti-
    cut adheres to the American rule. . . . There are few exceptions. For exam-
    ple, a specific contractual term may provide for the recovery of attorney’s
    fees and costs . . . or a statute may confer such rights.’’ (Internal quotation
    marks omitted.) Aurora Loan Services, LLC v. Hirsch, 
    170 Conn. App. 439
    ,
    453 n.9, 
    154 A.3d 1009
    (2017).
    12
    The defendant also argues that the court’s finding of causation was
    clearly erroneous because the plaintiff failed to offer expert testimony to
    prove that the defendant’s work caused the plaintiff’s damages. We reject
    the premise of this contention because Lindo testified and offered expert
    opinion regarding a variety of issues involving the defendant’s work based
    on his training, experience, and expertise in this area.
    13
    Lindo testified in response to questioning by the plaintiff’s counsel to the
    following regarding the effect of using rocks as backfill on the septic system:
    ‘‘Q.: And when you were digging do you recall the type of the material
    that was coming out of the trench?
    ‘‘A.: Yeah. I mean, it was just rock. There was no— you know, usually
    you would dig down and hit a layer of sand and that’s where you’d start
    hand shoveling, but it was all rocks. . . .
    ‘‘Q.: And what’s the purpose of putting sand in there instead of the fill
    that you discovered in there?
    ‘‘A.: To protect the pipe from breaking.
    ‘‘Q.: And is there a reason that a pipe might break if it’s in material that’s
    laden with rocks or—?
    ‘‘A.: Yeah. I mean, a pipe’s only so strong. You can’t, you know, put a
    rock on it and then, you know, any kind of pressure on it whether it’d be
    settling, or you know . . . anything’s [going to] break the pipe.’’
    Lindo testified to the following regarding the effect of using rocks as
    backfill for the foundation:
    ‘‘Q.: When you backfill footing—not footings, but foundations, what type
    of material are you supposed to use against the foundation properly?
    ‘‘A.: Backfill on a foundation depends what’s on site. You know, if you
    have bad material there, you try and bring in something decent to keep
    around the foundation wall.
    ‘‘Q.: When you say bad material what are you talking about?
    ‘‘A.: Big rocks, boulders, things like that. . . .
    ‘‘Q.: Was there a lot of bad material on this site?
    ‘‘A.: Yeah.
    ‘‘Q.: And why do you try to avoid putting rocks and so forth up against
    the foundation?
    ‘‘A.: A lot of reasons. You know, cracks in the wall, you know, if you keep
    a lot of —pull out a lot of big boulders in that area where you’ve dug, you’re
    [going to] have the material shifting and settling, and you know, it could
    push on the wall itself.’’
    14
    Brennan testified on direct examination by the plaintiff’s counsel to the
    following regarding the proper material for backfilling:
    ‘‘Q.: It shouldn’t have rocks or other debris?
    ‘‘A.: No, sir.
    ‘‘Q.: And why is that?
    ‘‘A.: Because in New England rocks move under the ground with the frost
    . . . and it will rub against the pipe eventually and cause it to either leak
    or—eventually it will leak.’’
    15
    The following colloquy occurred during the plaintiff’s counsel’s direct
    examination of Sheldon:
    ‘‘Q.: [I]s that something you would have expected in terms of the scratches
    to see if it had been backfilled with proper material?
    ‘‘A.: That is not what would happen if that tank was backfilled properly.
    ‘‘Q.: Okay. In looking at [an exhibit depicting large rocks], is that material
    that should have been used to backfill?
    ‘‘A.: No. Absolutely not.
    ‘‘Q.: [C]ould you tell the court—or if you know why the water might back
    up into the regulator box?
    ‘‘A.: The regulator would have backed up because the water had nowhere
    to flow out because as the fire marshal had stated, the clay that was found
    around [the] tank would have kept the water in there and not allowed it
    [to] have gone through like it would have if sand was around the tank. That
    water would have drained out through the sand.’’