United Vending Service, Inc. v. Everglaze, Inc. ( 1966 )


Menu:
  • QUINN, Associate Judge.

    Everglaze sued United Vending Service (hereinafter called “United”) to recover $2,500, the balance due for work, labor and materials under an oral contract to install a “Torginol” 1 floor and wall in Unit*853ed’s commissary. United’s answer alleged inferior and negligent workmanship and failure to comply with the contract and included a counterclaim for $1,000, the amount allegedly required to correct the defective work. The total cost of the installation was $3,500, and United had paid $1,000 on account. Following judgment for Ever-glaze on both the complaint and counterclaim and the denial of a motion for a new trial, United appealed.

    The floor surface was supposed to have the consistency of an orange peel; instead, it was pitted and cratered. In addition, dirt was imbedded in the glaze under the surface so that even after cleaning, it appeared to be dirty. United’s witness claimed that the pitting was caused by a too heavy coating of glaze, although he did admit that it might have been due to the inherent nature of the material. Witnesses for Ever-glaze contended that the condition was brought about because United had not allowed the surface to harden and dry for twenty-four hours as instructed, but had moved in heavy equipment shortly after the job was completed. They also stated that this was the cause of the shading effect and that the subsurface dirt was tracked in by United’s men who were moving the machinery. Testimony concerning cracking in the glaze and alleged leaking was introduced by United, but the location of the leak could not be pinpointed and the crack was explained as an expansion joint. As for the wall, it was not disputed that United had originally ordered a rough finish although it now wanted a smooth one, and that the job was properly done. It was further shown that Everglaze had reglazed about seventy-five percent of the floor but that United had refused to let its workmen finish. As of the date of trial, no expenses had been incurred by United to correct the alleged defects. An estimate of $3,530 was introduced as the cost of redoing the entire installation.

    It is fundamental that an appellate court will not retry issues of fact, and where there is substantial evidence to support the decision of the trial court, that decision will no be disturbed.2 The case at bar involves questions of fact and falls squarely within this rule. After reviewing the record, we are convinced that there was substantial evidence to support the trial court’s decision.

    Affirmed.

    .“Torginol” is a process of floor refinishing utilizing colored chips and liquid glaze which is supposed to he watertight and impervious to grease.

    . D.C.Code § 11-772 (c) (1961); Monarch Const. Corp. v. J. H. Marshall & Assoc., Inc., D.C.App., 213 A.2d 894 (1965); Richardson v. F. C. Flood Company, D.C.App., 190 A.2d 259 (1963).

Document Info

Docket Number: No. 3940

Judges: Hood, Myers, Quinn

Filed Date: 10/3/1966

Precedential Status: Precedential

Modified Date: 10/26/2024