Emack v. Rushenberger ( 1896 )


Menu:
  • Mr. Justice Morris

    delivered the opinion of the Court:

    This is a proceeding under the mechanics’ lien law, instituted by the appellees, George W. Rushenberger and George W. Harrison, each holding or claiming separate and *250independent liens against the same property, but joining in their prosecution as authorized by the statute.

    The property sought to be subjected to the satisfaction of the liens consists of five lots of ground, numbered from 37 to 41, both included, in square No. 516, in the city of Washington, with the buildings thereon, three in number it would seem,, out of the construction of which the claims of lien grew ; and is the separate estate of the appellant Marion Emack, a married woman, with whom was joined in 'the suit her husband, the co-appellant Charles G. Emack, who, in the construction of the buildings and in the transactions with all the persons concerned therein, seems to have acted as if the property were his own, although he is to be presumed to have acted for his wife and as her agent.

    The .appellee George. W. Rushenberger constructed' the electric bells and speaking tubes in the house, and' all the work necessary for the operation thereof, under a contract to do the same for $96, which sum was increased by some extra work to 3100, which is the amount of his claim, and for which he filed his lien and co-operated in these proceedings. This work he contracted for with the contractors for the buildings on March 2, 1893. Most of the rough work, the putting in of the wires and tubes, he seems to have done in June of 1893 '; and he claims to have finished the work on August 28, 1893. Neither the performance of the work according to the contract,.nor the amount of his claim, is contested. The only controversy as to him is as to the time of the completion of the houses and of his work, which is claimed by the appellants to have been in July of 1893, and before the 25th of that month; and the contention therefrom is that his notice of lien, which was filed on October 28, 1893, w'as too late, and cannot be-enforced. It seems that he had filed an earlier notice of lien on June 27, 1893, which was defective or incorrect in describing the lots as Nos. 465, 467 and 469, in square No. 516, which were the house numbers on the street, and not the numbers of the lots on the land records. It is conceded that he has *251not been paid for his work ; and it is not controverted that he is entitled to compensation for it.

    The other appellee, George W. Harrison, furnished lumber for the buildings to the value of $152.31, and was also a superintendent for the construction of the buildings for an aggregate compensation of $65, all under contracts made by him with William F. Kirby & Brother, the original contractors with Charles G. Emack for the construction of the buildings. The total amount of his claim is $2 x 7.31, diminished in the decree of the court below to the sum of $197.81, in consequence of the deduction of the value ($19.50) of some 'laths removed with his consent to some other building. The contention of the appellants is that Harrison’s claim for labor accrued not under any contract with Kirby & Brother, but under an agreement with Monroe and Campbell, their sureties upon a bond to Emack, who assumed the conduct of the work ■ upon the failure and assignment of Kirby & Brother, which occurred during its progress, and their consequent abandonment of the construction of the houses ; and that, inasmuch as Monroe and Campbell were not made parties to this suit, his failure to join them in it must be fatal to this part of his claim. And as to the portion of his claim that accrued from the furnishing of lumber, it is objected that he was merely a surety; that, if he furnished them otherwise than a surety, it was-not to the contractor, but to a sub-contractor, one Crawford, which would not authorize him to file a lien on the property; and that his conduct in permitting the removal of a certain portion of the lumber, namely, the laths above mentioned, and then attempting to enforce a lien for the full amount of.his claim, was a fraud upon the owner of the.buildings which should preclude him from any recovery in this case. It is not controverted that his notice of lien was filed in time, and that bis claim is otherwise correct. The notice was filed on August 28, 1893.

    There is' a strange uncertainty in the record in regard to the time of the commencement and completion of the *252houses, the former, however, not being until after September 28, 1892, and the latter event having occurred, according to the claim of the appellants, as early as July 25, 1893, and, according to the contention of the appellees, as late as August 28, 1893, when Rushenberger claims to have putin his electrical batteries in the westernmost of the three houses.

    According to the statement of the appellants contained in their answer to the bill filed by the appellees, five notices of lien were filed against the property, therein including the two filed by the appellees. The claims aggregated, according to this statement, the sum of £1,667,30. But the details are not consistent with this statement, fqr the sum of the five different claims specified is only £697.05, exclusive of the interest. It does not appear that any suits have been instituted upon any of these,claims or notices, other than the present proceedings instituted by the appellees.

    The contract price for the construction of the buildings, as stated by the appellants in their answer, was the sum of £11,838.75 ; and of this sum, at the time of filing their, answer, they had paid out only £10.940.55, which left in their hands a balance unexpended amounting to £898.20, and only the five claims above mentioned remaining unsettled. And it appeared, also, that by'means of compromises and the enforcement of forfeitures for non-completion of work in due time, the appellants had saved the further sum of £740 from the contract price of the work.

    Their claims remaining unpaid, the appellees filed this bill in equity in this cause to enforce their liens. They made defendants to the bill not .only the appellants here, but also William F. Kirby and Samuel L. Kirby, the original contractors for the construction of .the buildings, and likewise the American Security and Trust Company and Mahlon Ashford and Aldis B. Browne, trustee's, in respect of two deeds of trust by way of mortgage, dated September 28, 1892, and executed to secure to the Trust Company the repayment of two loans, made by it to the appellants, aggregating £4,600.

    *253After answers and replications filed and testimony taken, the Supreme Court of the District of Columbia decreed in favor of the appellees, the complainants below. It adjudged that a decree pro confesso taken against the Kirby brothers be máde final-; that the complainant Rushenberger should, recover against the Kirbys and against Marion Emack the sum of #100, with interest from August 1,1893 ; that the complainant Harrison should recover against the same three defendants the sum of $197.81, with interest from Jyly 13, 1893 ; that said two sums, with the interest thereon, should constitute a lien upon the property herein-before described; and that, unless the said defendants should, within twenty, days thereafter, pay the said sums, the property should be sold, subject to the two deeds of trust above mentioned, for the satisfaction of the claims; and trustees were appointed to make the sale, and their course of proceeding was prescribed.

    The American Security and Trust Company and the trustees Ashford and Browne were satisfied with the decree, which did not disturb their rights in any manner ; and they havfe not appealed; nor have the Kirby Brothers. But Marion Emack, the owner of the property, and her husband', Charles G. Emack, have appealed, and their appeal is now before us for determination.

    In view of the fact that the appellants have in their hands the sum of $898.20, yet remaining of the contract price for the construction of the houses and amply sufficient to satisfy all the outstanding claims for such construction, and that the justice of the claim of the appellant Rushenberger is beyond all question, and that even the claim of Harrison, as finally found by the court below, can scarcely be said to be seriously, controverted, and as there is no important question of principle, so far as we can see, involved in the case, it is very greatly to be regretted that litigation so expensive .should have been indulged in by the parties to the cause over claims so unimportant in their amount. We have no disposition 'to add to the vexation of that litigation by find*254ing error in the decision of the court below, unless that error is made very apparent to us. And certainly in regard to any question of fact involved, such as the question of the time at which these houses were finished, we would be most reluctant to overthrow the conclusion reached by the decree appealed from, unless that conclusion were shown to be clearly erroneous. There is but little in the case beyond this and one or two other minor questions of fact; and we are not satisfied from the perusal of the testimony, which it would serve no good .purpose here-to analyze, that there was error in the determination of any of these questions. The testimony, perhaps, is not very conclusive on either side ; but there is sufficient in any event to warrant the finding of facts upon which the court below based its adjudication ; and, as we have intimated, we do not think that the cause of justice would be subserved in any respect by our disturbance of that finding, whatever might have been our own independent conclusion from the testimony.

    But it is argued, apart from the questions of fact involved, that the decree upon its face is erroneous, as awarding a personal judgment, against Marion Emack, the owner of the property, for the amount found to be due upon the liens. Ordinarily this would be error; for the statute (23 Stat, p.' 65) only authorizes a personal jndgment “ against the party who incurred the debt,” in this case the original contractors, the Kirbys. But here the appellants have admitted assets in their hands to the amount of .$898.20, justly and equitably payable for the construction of these buildings, and under the circumstances of this case, not to the Kirbys, but to their sub-contractors. If the question were one merely of the enforcement of the lien, no such personal judgment could properly be rendered. But this suit involves the disposition of a balance of money in the hands of the appellants, to which the appellees are equitably entitled, if their claims are just, and those claims are found to be just. The appellants themselves are not entitled to that balance under any circumstances as against the other parties in interest; *255and it would have been proper for them to have paid the money into court as under a bill of interpleader. As they have not chosen to pay it into court, it was proper, in. consideration of it, for the court to have awarded a personal judgment against them. And wé may add that, in this view of the case, it would seem to make but little difference whether the appellees were in time with their lien or not. Under the statute they had an equitable right to this money, or to so much of it as was required to pay their claims ; and their right to payment therefrom, independently of the lien upon the property and of the time of filing of that lien, might well be sustained under the peculiar circumstances of-this case,. Whether for that purpose the pleadings should not have been somewhat modified, it is unnecessary to'determine. There was a prayer in the bill of complaint for "general rfelief; and in view of that prayer and of the smallness of the amount involved, there would be no equity in the requirement of a re-cast of the pleadings.

    We are of opinion that there was no error in the decree of the Supreme Court of the District of Columbia in the premises, and. that this decree should be affirmed, with costs. And it is so ordered.