Sierra Club v. United States Army Corps of Engineers ( 2013 )


Menu:
  •                              UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLUMBIA
    )
    SIERRA CLUB, et al.,                           )
    )
    Plaintiffs,                     )
    )
    v.                              )       Civil Action No. 13-cv-1239 (KBJ)
    )
    UNITED STATES ARMY                             )
    CORPS OF ENGINEERS, et al.,                    )
    )
    Defendants.                     )
    )
    MEMORANDUM OPINION
    The Sierra Club and the National Wildlife Federation (“Plaintiffs”) have brought
    this action for a declaratory judgment against several federal agencies and their
    executive officers in their official capacity (the “Federal Agencies”) regarding
    construction of the Flanagan South Pipeline, a domestic oil pipeline running from
    Illinois to Oklahoma (the “FS Pipeline”). 1 Plaintiffs allege that the Federal Agencies
    have failed to assess adequately the environmental impacts of this privately-owned
    pipeline, in violation of the National Environmental Protection Act (“NEPA”), the
    Clean Water Act (“CWA”), and the Administrative Procedure Act (“APA”). In
    addition, Plaintiffs have now filed a motion for a preliminary injunction that asks the
    Court to enjoin the actions of the Federal Agencies in relation to the FS Pipeline, and to
    1
    The specific defendants are: the United States Army Corps of Engineers and its officers Lt. Gen.
    Thomas P. Bostick, Col. Richard A. Pratt, Col. Mark Deschenes, Col. Andrew D. Sexton, and Col.
    Christopher Hall; the United States Department of Transportation Pipeline and Hazardous Materials
    Safety Administration and its officers Anthony Foxx and Cynthia L. Quartermain; the United States
    Fish and Wildlife Service and its officer Daniel M. Ashe; the United States Department of Interior
    Bureau of Indian Affairs and its officers Sally Jewell and Kevin K. Washburn; and the United States
    Environmental Protection Agency and its officer Gina McCarthy. In addition, the pipeline’s owner,
    Enbridge Pipelines (FSP) LLC, has been granted intervenor status on the defendants’ side pursuant to
    Federal Rule of Civil Procedure 24. (See Minute Order of Sept. 5, 2013.)
    1
    enjoin construction and operation of the entire pipeline (which is in the process of being
    constructed mostly on privately-owned land) pending a final ruling on the merits of the
    case.
    This Court has considered the parties’ briefs on the motion for a preliminary
    injunction, the arguments made at the preliminary injunction hearing, the portions of
    the record that the parties have submitted in support of and in opposition to the motion,
    and the complex web of statutes and regulations that Plaintiffs’ allegations implicate.
    Although Plaintiffs have drafted a complaint that attacks the pipeline-related actions of
    the several government agencies separately, Plaintiffs’ central contention in this case is
    that the Federal Agencies had a collective statutory obligation to perform an in-depth
    environmental review of the entire FS Pipeline before any construction on the pipeline
    could commence. At least on the current record, however, Plaintiffs have significantly
    overstated the breadth of federal involvement in the pipeline project and have failed to
    establish sufficiently that applicable federal statutes and regulations would require the
    extensive environmental review process that Plaintiffs seek. Moreover, Plaintiffs have
    fallen short of demonstrating that irreparable harm will result if the current construction
    proceeds during the pendency of this litigation, and the Court is not convinced that the
    balance of harms and public interest factors weigh in Plaintiffs’ favor.
    Consequently, as explained further below, the Court concludes that Plaintiffs’
    motion for a preliminary injunction must be DENIED.
    2
    I.     BACKGROUND
    A. The Flanagan South Pipeline
    The FS Pipeline is a proposed 589-mile domestic oil pipeline that, once
    constructed, will transport tar sands crude oil from Pontiac, Illinois, through the states
    of Missouri and Kansas, and ultimately into Cushing, Oklahoma. Enbridge Pipelines
    (FSP) LLC (“Enbridge”), one of the leading energy transportation companies in North
    America, owns the planned pipeline. Enbridge began construction of the pipeline on
    August 14, 2013, and expects to complete the pipeline in the summer of 2014.
    At least 560 miles of the 589 miles of pipe that will comprise the FS Pipeline
    will traverse land that is entirely privately owned. According to Enbridge, the company
    has identified 2,368 tracts owned by 1,720 separate landowners along the course of the
    pipeline and has secured 96% of the land rights along the entire route. Thus, with
    respect to the vast majority of the pipeline, no federal permission or authorization is
    required for construction. However, it is undisputed that the FS Pipeline will at times
    cross federal lands and waterways at various points along its planned route through the
    heart of the country. Three types of federal crossings will occur and are at issue in this
    litigation: (1) 13.68 total miles of “waters of the United States” (as defined in the CWA
    and its implementing regulations) that are primarily located on private land but are
    subject to the jurisdiction of the Army Corps of Engineers (the “Corps”) under the
    CWA 2; (2) 12.3 miles of Native American land that is subject to the jurisdiction of the
    Bureau of Indian Affairs (“BIA”); and (3) 1.3 miles of land that the federal government
    2
    The statutory definition of “waters of the United States” includes, in addition to interstate waters and
    wetlands, “[a]ll other waters such as intrastate lakes, rivers, streams (including intermittent streams),
    mudflats, sandflats, wetlands, sloughs, prairie potholes, wet meadows, playa lakes, or natural ponds,
    the use, degradation or destruction of which could affect interstate or foreign commerce.” 
    33 C.F.R. § 328.3
     (2013).
    3
    owns and that is also under the Corps’s jurisdiction. To construct and operate the
    portion of the pipeline that traverses these 27.28 total miles, Enbridge must have federal
    approval, and a separate statutory and regulatory scheme, discussed below, governs
    each type of land or water crossing.
    B. Alleged Federal Involvement With The Flanagan South Pipeline
    Because Congress has not authorized the federal government to oversee
    construction of a domestic oil pipeline, Plaintiffs’ complaint relies on a series of federal
    environmental laws and regulations that require federal agencies with some
    involvement in domestic pipeline construction to follow certain procedures. The
    applicable statutes and regulations are set forth in Part C below. The following
    description of Plaintiffs’ allegations regarding federal involvement with the FS Pipeline
    provides the necessary context.
    1. The Corps’s “Verifications” Under the Clean Water Act and Nationwide
    Permit 12
    When constructed, the FS Pipeline will cross approximately 1,950 wetlands or
    waters under the jurisdiction of the Corps—an area that, as noted above, totals 13.68
    miles. To undertake the portions of the FS Pipeline construction project that may
    impact these waterways, Enbridge is required by law to seek federal approval, as
    mentioned above and explained further below. In August and September of 2012,
    Enbridge filed a formal notice under the CWA’s general permitting system requesting
    Corps district engineers from each of the four Corps districts through which the
    proposed FS Pipeline runs to verify that construction of the FS Pipeline project is
    4
    consistent with a pre-existing general permit that the Corps had previously issued. 3
    Enbridge’s notice included specific plans for mitigating any potential adverse impacts
    from the FS Pipeline construction project, as the general permitting system requires.
    One year later, in August and September 2013, each of the four Corps districts issued a
    verification letter to Enbridge, confirming that the FS Pipeline’s water crossings were
    consistent with an applicable general permit, provided Enbridge undertook the
    mitigation plans outlined in its notice.
    2. The Corps’s Consideration Of Easements For Construction On Federal
    Lands
    In addition to the wetlands under the Corps’s jurisdiction, the FS Pipeline passes
    through approximately 1.3 miles of other federal land under the jurisdiction of the
    Corps, consisting of 0.7 miles of land at the Mississippi River near Quincy, Illinois, and
    0.6 miles of land at the Arkansas River near Tulsa, Oklahoma. Congress has
    empowered federal agencies to grant rights-of-way across lands “for pipeline purposes
    for the transportation of oil, natural gas, synthetic liquid or gaseous fuels[,]” 
    30 U.S.C. § 185
    (a) (2012), and the governing statute expressly places numerous responsibilities
    on an agency considering whether to permit construction on federal land, including
    safety requirements, notice requirements, and reporting requirements (including
    reporting to specific Congressional committees), 
    id.
     § 185(g), (k), (w). An agency must
    3
    As Part I.C.2, infra, explains, the CWA offers two routes for getting federal approval to affect the
    nation’s waterways with construction activities: either an individualized permitting process, or a
    mechanism for having one’s project verified as consistent with pre-existing general permits that apply
    to a given geographical area (including nationwide). 
    33 U.S.C. § 1344
    (a), (e) (2012). Enbridge chose
    the latter. Enbridge requested that the district engineers verify that the construction activities related to
    the FS Pipeline were consistent with Nationwide Permit 12, a general permit that the Corps reissued in
    2012 and that authorizes “[a]ctivities required for the construction, maintenance, repair, or removal of
    utility lines and associated facilities in the waters of the United States, provided the activity does not
    result in a loss of more than ½-acre of water for each single and complete project.” Reissuance of
    Nationwide Permits, 
    77 Fed. Reg. 10,184
    , 10,271 (February 21, 2012).
    5
    also comply with applicable environmental statutes and regulations, such as the
    National Environmental Protection Act, discussed below. 
    Id.
     § 185(h).
    In April and May of 2013, Enbridge applied to the relevant Corps districts for
    easements to construct the 1.3 mile segment of the FS Pipeline that runs over federal
    land. Enbridge submitted its applications using a standard form for the construction of
    transportation and utilities systems on federal lands—an application process that the
    Corps subjects to the same review procedures as any third-party request for the use of
    Corps lands. As of the writing of this Opinion, the Corps had informed the relevant
    Congressional committees (the House and Senate Committees on Natural Resources)
    about Enbridge’s easement applications, and had begun an environmental assessment of
    the project, but had not yet reached a decision about whether or not to grant Enbridge’s
    applications.
    3. The BIA’s Consideration Of Easements For Construction On Indian Land
    That The Federal Government Holds In Trust
    Under 
    25 U.S.C. § 323
    , the BIA “is empowered to grant rights-of-way for all
    purposes, subject to such conditions as [the Secretary of the Interior] may prescribe,
    over and across any lands now or hereafter held in trust by the United States for
    individual Indians or Indian tribes.” The BIA has promulgated regulations governing
    the granting of easements over Indian land. See generally 25 C.F.R. Part 169 (2013).
    These regulations include specific guidelines for, among other things, applications,
    surveying, and providing consideration to landowners. 
    Id.
     The regulations also include
    specific provisions pertaining to easements for oil or gas pipelines. See 
    id.
     § 196.25.
    The proposed FS Pipeline crosses over 34 parcels of privately-owned Indian land
    subject to the BIA’s jurisdiction, comprising a total of 12.3 miles. As of the writing of
    6
    this Opinion, Enbridge had applied to the BIA for easements over these parcels, and the
    BIA was in the process of conducting an environmental assessment of the impact of the
    pipeline on those areas. The BIA had not yet determined whether to grant or deny
    Enbridge’s requested easements.
    4. The Fish and Wildlife Service’s Biological Opinion And Incidental Take
    Statement
    As a part of the process for evaluating Enbridge’s request for easements to
    construct portions of the FS Pipeline on the federal lands as described above, the Corps
    and the BIA consulted the Fish and Wildlife Service (“FWS”) about the potential
    impact of the FS Pipeline on animal life in the area. Under the Endangered Species Act
    (“ESA”), 
    16 U.S.C. §§ 1531-1544
     (2012), all federal agencies must consult with the
    FWS to ensure that “any action authorized, funded, or carried out by such agency” is
    unlikely “to jeopardize the continued existence of any endangered species or threatened
    species or result in the destruction or adverse modification of habitat of such species[.]”
    
    16 U.S.C. § 1536
    (a)(2). The agency or agencies must engage in formal consultations
    with the FWS, and the ESA’s implementing regulations contain detailed guidelines that
    govern these consultations. See, e.g., 
    50 C.F.R. § 402.14
    (c) (2013). Moreover, at the
    conclusion of the required consultation, the FWS must issue a written opinion
    “detailing how the agency action affects [any endangered] species or its critical habitat”
    and if any issues are identified, “suggesting . . . reasonable and prudent alternatives”
    that the FWS believes would not run afoul of the ESA’s mandate to protect such
    species. 
    16 U.S.C. § 1536
    (b)(3)(A). If the FWS believes that the agency action might
    result in the “taking” (i.e., killing) of some members of an endangered species, but is
    not likely to jeopardize that species’ existence or adversely affect its environment in
    7
    violation of section 1536(a)(2), the FWS will issue an “incidental take statement” that
    sets out measures that the FWS considers “necessary or appropriate to minimize [the]
    impact” of the agency action on any endangered species. 
    16 U.S.C. § 1536
    (b)(4).
    Pursuant to this statutory and regulatory scheme, in May and June of 2013, both
    the Corps and the BIA requested that the FWS evaluate the impact of the construction
    of the FS Pipeline on certain endangered or threatened species. (FWS Biological
    Opinion on Enbridge Pipelines (FSP) LLC’s Flanagan South Pipeline Project
    (“Biological Opinion”), ECF No. 14-8, at i.) The Corps specifically requested the
    FWS’s opinion regarding the effects of the pipeline on both the decurrent false aster
    plant and the Indiana bat, while the BIA’s consultation request included both of those
    species and also the American burying beetle. (Id.)
    The FWS issued its Biological Opinion on July 24, 2013. With respect to the
    decurrent false aster, the FWS found that the effects from the FS Pipeline would be
    “small[, and] temporary, and recovery will be rapid.” (Id.) For the American burying
    beetle, the Biological Opinion concluded that the pipeline construction might modify
    approximately 200 acres of species habitat, and that some beetles may be disturbed or
    killed, but that “most of the effects [of construction on the beetle] are expected to be
    infrequent, of short duration, and reversible.” (Id. at i-ii.) Finally, regarding the
    Indiana bat, the FWS predicted that the construction would “potentially” kill 19 non-
    reproductive bats and “harm or harass” no more than 120 other bats, but that “these
    impacts are not likely to cause maternity colony impacts” and therefore “it is unlikely
    that the anticipated effects [of the pipeline] will affect the likelihood of achieving the
    recovery needs of the species[.]” (Id. at ii.) Additionally, because the FWS found that
    8
    it was possible that the pipeline construction would result in the death of some
    endangered beetles and/or bats, it issued an incidental take statement that exempted the
    Corps, the BIA, and Enbridge from the prohibitions against “taking” endangered species
    found in the ESA, provided that any such taking was done in compliance with the terms
    of the incidental take statement. (Id.)
    5. The Pipeline and Hazardous Materials Safety Administration’s Failure To
    Act On The Not-Yet-Filed Oil Spill Response Plan
    Finally, as discussed further below, Plaintiffs rest one claim in the complaint on
    the inaction of a federal agency regarding an assessment of the risks involved with
    transporting oil through the FS Pipeline. The Oil Pollution Act of 1990, 
    33 U.S.C. §§ 2701-2762
    , mandates that operators of oil facilities (which include pipelines)
    “prepare and submit to the President a plan for responding, to the maximum extent
    practicable, to a worst case discharge, and to a substantial threat of such a discharge, of
    oil or a hazardous substance.” 
    33 U.S.C. § 1321
    (j)(5) (2012). The Pipeline and
    Hazardous Materials Safety Administration (“PHMSA”), a division of Department of
    Transportation, has authority to promulgate regulations governing these response plans.
    See Exec. Order No. 12,777 § (2)(d)(2), 
    56 Fed. Reg. 54,757
     (Oct. 22, 1991). PHMSA
    regulations permit pipeline operators to submit spill response plans based on “response
    zones,” such that more than one pipeline may be covered by a single plan if they are in
    the same geographic region. 
    49 C.F.R. §§ 194.5
    , 194.107 (2013). Moreover, the
    required response plan must be submitted before an operator can “handle, store, or
    transport oil in that pipeline,” but the operator does not need to submit a plan prior to
    the pipeline’s construction. 
    Id.
     § 194.7(a). In addition, so long as the operator has
    submitted a plan to the PHMSA and has certified that there is adequate personnel and
    9
    equipment to deal with an oil spill, a pipeline may be in operation for up to two years
    without PHMSA approval of a plan. Id. §§ 194.7(c), 194.119(e).
    As the owner and future operator of the proposed FS Pipeline, Enbridge is
    required to submit a response plan to the PHMSA before the pipeline begins operating.
    The FS Pipeline is still under construction, however. At the time of the writing of this
    Opinion, Enbridge had not yet submitted any oil spill response plan for PHMSA review.
    C. Plaintiffs’ Interests And Specific Claims
    Plaintiffs are the Sierra Club, one of the oldest and largest environmental
    organizations in the country, which currently has approximately 600,000 members and
    traces its roots back to 1892; and the National Wildlife Federation, the nation’s largest
    conservation advocacy and education organization. (First Amended Complaint
    (“Compl.”), ECF No. 7, ¶¶ 12, 16.) Some of the Sierra Club’s members live in each of
    the regions through which the FS Pipeline is planned to run. (Id. ¶ 13.) Plaintiffs
    allege that the construction and operation of the FS Pipeline without proper
    environmental review will injure them, both because they rely on such environmental
    reviews for information used in planning their activities and disseminating information
    to their members, and because they and their members have aesthetic, scientific,
    recreational, business, and property interests in the areas where pipeline construction
    and operation will occur. (Id. ¶¶ 17-18.)
    Based on the complaint and the statements made during the preliminary
    injunction hearing, Plaintiffs’ primary concern appears to be that the proposed FS
    Pipeline will damage the environment and that the federal government has not
    adequately assessed the environmental impact of this pipeline proposal. However, as
    10
    noted above, there is no federal statute that requires or permits federal oversight of an
    entirely domestic oil pipeline such as the one at issue here. Consequently, Plaintiffs
    have brought this action in federal court in reliance on various federal laws that, when
    applicable, require agencies and individuals to comply with certain standards prior to
    undertaking construction projects that may impact the environment.
    Plaintiffs have organized the allegations in their complaint into six separate
    claims, five of which arise under National Environmental Protection Act, the Clean
    Water Act, and the Administrative Procedure Act. (See generally Compl. ¶¶ 143-93.) 4
    As promised, the statutory schemes that these claims implicate are discussed in more
    detail below.
    1. The National Environmental Protection Act (“NEPA”)
    The bulk of Plaintiffs’ complaint arises under NEPA, 
    42 U.S.C. §§ 4321-4347
    (2012). (See Compl. ¶¶ 155-89 (Counts II – V).) As a general matter, Congress
    enacted NEPA as a call to the federal government to consider the environmental
    consequences of its actions, see 
    42 U.S.C. § 4331
    (b)(1), and the regulations
    implementing NEPA describe it as the country’s “basic national charter” for
    environmental protection. 
    40 C.F.R. § 1500.1
     (2013).
    NEPA is, in essence, a “procedural statute” designed to ensure that federal
    agencies make fully-informed and well-considered decisions. New York v. Nuclear
    4
    One of Plaintiffs’ six claims (Count I) invokes the Freedom of Information Act (“FOIA”) and alleges
    that the Corps violated FOIA by denying certain document requests and missing the deadlines to
    produce responsive documents. (Compl. ¶¶ 143-54.) This claim has a distinct procedural history: on
    September 30, 2013, the Court stayed the FOIA portion of the complaint and effectively severed it from
    the remaining claims at issue in the preliminary injunction motion, based on the Federal Agencies’
    representations that they were in the process of producing documents responsive to Plaintiffs’ FOIA
    requests. (See Minute Order of Sept. 30, 2013; Defs.’ Response to Order to Show Cause, ECF No. 30,
    at 4.)
    11
    Regulatory Comm’n, 
    681 F.3d 471
    , 476 (D.C. Cir. 2012) (quoting Vermont Yankee
    Nuclear Power Corp. v. NRDC, 
    435 U.S. 519
    , 558 (1978) (internal quotation marks
    omitted)). To this end, before a federal agency undertakes a “major federal action[]
    significantly affecting the quality of the human environment,” 
    42 U.S.C. § 4332
    (2)(C),
    NEPA requires the agency to evaluate the environmental consequences of that proposed
    action. The required evaluation involves preparing a detailed environmental impact
    statement (“EIS”) that describes the impact of the proposed action on the environment
    and any alternatives to the proposed action, which the agency must publish for public
    review and comment. 
    Id.
     5
    To determine whether a particular agency action qualifies as a “major federal
    action significantly affecting the quality of the human environment” such that an EIS is
    required, an agency may opt to prepare a less-detailed environmental assessment
    (“EA”), which is a “concise public document” that briefly provides evidence and
    analysis to assist an agency in deciding whether the action in question requires an EIS.
    
    40 C.F.R. § 1501.4
    (a)-(c); 
    id.
     § 1508.9 (defining an EA). Based on the information
    contained in the EA, the agency may proceed to prepare an EIS; alternatively, the
    5
    An agency’s preparation of an EIS is an extensive undertaking that is generally prepared in two
    stages, both a draft and a final stage, and the agency is required to invite comments on the draft
    statement before preparation of the final EIS. See 
    40 C.F.R. § 1502.9
     (2013); 40 C.F.R. Part 1503
    (2013). When preparing an EIS, the agency is required to, among other things, consult with other
    federal agencies that may have special expertise with respect to the environmental effects of the
    project, 
    42 U.S.C. § 4332
    (2)(C) (2012), and the EIS must not only detail the unavoidable adverse
    environmental consequences of the proposed project and alternatives to the project, but also address the
    extent to which the project’s adverse effects can be avoided through possible mitigation measures. 
    Id.
    § 4332(2)(C)(i)-(iii); see also 
    40 C.F.R. §§ 1502.14
     (2013) (describing as the “heart” of the EIS the
    section comparing description of the proposed action to reasonable alternatives), 1502.15 (requiring the
    EIS to include a section describing the affected environment), 1502.16 (requiring a section that
    discusses the environmental consequences, which forms the “scientific and analytic basis” for the
    comparison of the proposed action to reasonable alternatives), 1508.25 (describing the scope of an
    EIS).
    12
    agency may conclude that its action will not have a significant effect on the human
    environment such that an EIS is not warranted. 
    40 C.F.R. § 1501.4
    (e). 6
    NEPA is relevant to this case because most of Plaintiffs’ claims allege that, in
    myriad respects, the Federal Agencies have failed to abide by their NEPA review
    obligations with respect to the FS Pipeline. These claims generally fall into two
    categories: first, that the individual actions of certain Federal Agencies regarding the
    FS Pipeline were “major federal actions” requiring those agencies to prepare an EIS or
    at least undertake an EA under NEPA (Compl. ¶¶ 155-79 (Counts II-IV)); and second,
    that the combined actions of all the Federal Agencies gave rise to an unfulfilled NEPA
    obligation to conduct a detailed environmental analysis of the entire 589-mile pipeline
    as a whole (Compl. ¶¶ 180-89 (Count V)).
    2. The Clean Water Act And Nationwide Permit 12
    Plaintiffs maintain that the Corps’ actions in regard to the proposed FS Pipeline
    water crossings violate the CWA, 
    33 U.S.C. §§ 1251-1387
     (2013), both because the
    Corps was required to conduct a NEPA review prior to providing the requested CWA
    verifications (Count II), and because the Corps erred in concluding that the construction
    project at issue here satisfied the requirements of the pre-existing general permit known
    as Nationwide Permit 12 (“NWP 12”) (Count VI). (See Compl. ¶¶ 155-64; 190-93.)
    Plaintiffs’ claims in this regard relate generally to the stated purpose of the CWA—to
    “restore and maintain the chemical, physical, and biological integrity of the Nation’s
    6
    If the agency concludes that no EIS is warranted after preparing an EA, the agency will make a
    finding of no significant impact (“FONSI”), which is reflected in a document that details the agency’s
    conclusion that its action will not have a significant effect on the human environment. See 
    40 C.F.R. §§ 1501.4
    (e), 1508.13 (2013).
    13
    waters,” 
    33 U.S.C. § 1251
    —a goal that Congress has generally sought to accomplish by
    prohibiting the discharge of any pollutant, including dredged or fill material, into the
    “waters of the United States.” See 
    33 U.S.C. §§ 1311
    , 1362(6), (7), (12). Section 404
    of the CWA allows for limited exceptions to this general prohibition against discharges,
    however; in this regard, the statute specifically authorizes the Secretary of the Army
    (acting through the Corps) to issue permits “for the discharge of dredged or fill material
    into the navigable waters at specified disposal sites.” 
    33 U.S.C. § 1344
    (a). 7
    Significantly for present purposes, two alternative types of discharge permits are
    available under Section 404: (1) individual permits that the Corps provides with
    respect to a particular project, and (2) general permits that are issued for a given
    activity within a certain geographical area, i.e., a state, a region, or (as relevant here)
    nationwide. 
    33 U.S.C. §§ 1344
    (a), (e). Individual permits are subject to detailed
    application and processing instructions, and before the Corps can issue an individual
    permit, it must conduct a case-specific review of each application, including
    preparation of an EA or EIS pursuant to NEPA. See generally 33 C.F.R. Parts 323, 325
    (2013) (setting forth the application and review guidelines for individual permits).
    General permits, on the other hand, are designed to streamline the permitting process
    for certain, pre-approved “categor[ies] of activities,” namely, those activities that the
    Corps determines are “similar in nature,” “will cause only minimal adverse
    environmental effects when performed separately,” and “will have only minimal
    cumulative adverse effect on the environment.” 
    33 U.S.C. § 1344
    (e)(1); see generally
    33 C.F.R. Part 330 (2013) (setting forth the purposes of and procedures relating to the
    7
    “Navigable waters” means “the waters of the United States,” which includes certain types of wetlands
    such as those over which the FS Pipeline intermittently traverses. See 
    33 U.S.C. § 1362
    (7); see also
    footnote 2, supra.
    14
    general permit program). A general permit is valid for five years, and can be reissued
    for subsequent five-year periods. See 
    33 U.S.C. § 1344
    (e)(2). Moreover, once the
    Corps has issued or reissued a general permit, regional Corps officials known as
    “division engineers” retain “discretionary authority to modify, suspend, or revoke
    [general permit] authorizations for any specific geographic area, class of activities, or
    class of waters within” a given geographical location. 
    33 C.F.R. § 330.5
    (c)(1).
    Notably, general permits—including the nationwide permit at issue here—
    undergo a stringent pre-approval evaluation process that involves a comprehensive
    environmental assessment under NEPA and also public notice and comment.
    Consequently, once a general permit is issued or reissued, the requisite environmental
    analysis for any conforming project is considered to have been completed, and persons
    who seek to engage in activities that the general permit covers may ordinarily “proceed
    with activities authorized by [general permits] without notifying the [Corps].” 
    Id.
     §
    330.1(e)(1). In some cases, however, a prospective permittee must seek specific
    verification that the relevant general permit covers the activity, id. § 330.1(d), which is
    accomplished when a prospective permittee files a “pre-construction notice” (“PCN”)
    with the relevant Corps district engineer. After reviewing a PCN, the district engineer
    may choose to verify that the general permit is applicable by sending the permitee a
    verification letter immediately, or the district engineer “may add activity-specific
    conditions to ensure that the activity complies with the terms and conditions of the
    [general permit] and that the adverse impacts . . . are individually and cumulatively
    minimal.” Id. § 330.1(e)(2). Alternatively, in response to a PCN, the district engineer
    may determine that the adverse effects of the activity are more than minimal and, as a
    15
    result, either notify the prospective permittee that an individual permit is required, or
    permit the permittee to propose “measures . . . to reduce the adverse impacts to
    minimal.” Id. § 330.1(e)(3). 8
    This case concerns Nationwide Permit 12, a nationwide permit that the Corps
    reissued in 2012. NWP 12 specifically authorizes discharges into federal waterways as
    required for
    the construction, maintenance, repair, and removal of utility
    lines and associated facilities in waters of the United States,
    provided the activity does not result in the loss of greater
    than 1/2-acre of waters of the United States for each single
    and complete project.
    Reissuance of Nationwide Permits, 
    77 Fed. Reg. 10,184
    , 10,271 (Feb. 21, 2012). The
    definition of a “utility line” in NWP 12 includes “any pipe or pipeline for the
    transportation of any gaseous, liquid, liquescent, or slurry substance, for any
    purpose[.]” 
    Id.
     Moreover, for “linear” projects, such as the FS Pipeline, 9 each crossing
    of a water body at a separate and distant location is considered a “single and complete
    project” for the purpose of NWP 12. 77 Fed. Reg. at 10,290.
    Prior to the reissuance of NWP 12 in 2012, the Corps followed the extensive
    evaluation process that the regulatory scheme requires for issuance of a general permit,
    8
    If a permittee proposes additional measures to mitigate the environmental impact of the proposed
    activity involving discharge, the district engineer must review the proposed mitigation strategy and
    “shall add activity-specific conditions to ensure that the mitigation will be accomplished.” 
    33 C.F.R. § 330.1
    (e)(3) (2013). If the district engineer concludes that the mitigation strategy is insufficient, he
    “will instruct the prospective permittee on procedures to seek authorization under an individual
    permit.” 
    Id.
     On the other hand, if the district engineer concludes that the activity in question, coupled
    with any mitigation measures and activity-specific conditions, is qualified to proceed under the relevant
    NWP, he will send a “verification” letter to the permittee.
    9
    A “linear project” is “a project constructed for the purpose of getting people, goods, or services from
    a point of origin to a terminal point, which often involves multiple crossings of one or more
    waterbodies at separate and distant locations.” 77 Fed. Reg. at 10,195. “Roads and pipelines are
    examples of linear projects.” Id. at 10,263. The parties do not dispute that the FS Pipeline is a linear
    project.
    16
    including preparation of a comprehensive EA pursuant to NEPA. 
    42 U.S.C. § 4332
    (2)(C). The Corps also conducted an “impact analysis” under the Environmental
    Protection Agency’s CWA Section 404(b)(1) guidelines, see 40 C.F.R. Part 230
    Subparts C-F, and performed a “public interest review” of the factors set forth in 
    33 C.F.R. § 320.4
    (a)(1) (2013). 10 After conducting the relevant reviews and assessments,
    the Corps then produced a “decision document” that incorporated all of the information
    it gathered and the conclusions it drew from the reviews of the proposed reissuance of
    NWP 12. The Corps released this document (along with a notice in the Federal
    Register) for public notice and comment. See 
    33 C.F.R. § 330.1
    (b); Proposal to Reissue
    and Modify Nationwide Permits, 
    76 Fed. Reg. 9,174
     (Feb. 16, 2011). The Corps
    subsequently published a final version of the NWP 12 decision document, which
    authorized certain discharges in relation to utility projects as described, along with the
    Corps’s responses to any public comments.
    In the instant case, as noted in Part I.B.1 above, Enbridge filed PCNs in August
    and September of 2012, in order to seek verifications from four district engineers that
    the FS Pipeline construction project was consistent with NWP 12. Enbridge’s PCNs
    included extensive mitigation plans to offset the impact the construction might have on
    the environment, including requirements that existing flow rates be maintained; that in-
    stream excavation activities be limited in duration; that the contours of waterbody beds
    and banks be restored and stabilized within 24 hours; and that specific drilling
    10
    The regulations governing proposed general permits required the Corps to assess “[a]ll factors which
    may be relevant to the proposal” including “conservation, economics, aesthetics, general environmental
    concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land
    use, navigation, shore erosion and accretion, recreation, water supply and conservation, water quality,
    energy needs, safety, food and fiber production, mineral needs, considerations of property ownership
    and, in general, the needs and welfare of the people.” 
    33 C.F.R. § 320.4
    (a)(1).
    17
    techniques be employed to avoid any impact (even of a temporary nature) on certain
    large and select water bodies. (See, e.g., Decl. of Joseph McGaver, ECF No. 27-2, ¶¶
    19-23.)
    In August and September of 2013, Enbridge received verifications from each of
    the four district engineers stating that discharges and other activities that impact
    waterways in relation to the construction of the FS Pipeline were consistent with NWP
    12, provided that Enbridge complied in all respects with the environmental mitigation
    measures outlined in its PCNs. (Id. ¶ 12.) The district engineers further conditioned
    their verification on Enbridge’s purchasing wetland bank credits as compensation for
    some temporary and permanent changes of forested wetlands to emergent wetlands, at a
    cost of approximately $4 million. (Id. ¶ 26.)
    Despite these measures, Plaintiffs contend that the CWA requires the Corps to
    have done more to evaluate the environmental impact of the FS Pipeline before
    verifying that the water crossings were consistent with NWP 12; in particular, Plaintiffs
    maintain that the Corps should have conducted a NEPA review and should have
    produced either an EA or an EIS that took into consideration the overall environmental
    effect of the entire FS Pipeline project, including those portions that were to be
    constructed on privately owned land. (See Compl. ¶¶ 155-60 (Count II).) Plaintiffs
    also argue that the district engineers erred in verifying the project’s 1,950 water
    crossings under NWP 12 for two reasons: first, because they failed to take into account
    the “cumulative” effect of the project, and second, because they verified certain water
    crossings that are or will be closer to public water supply intakes than is permitted
    18
    under the general permitting system. (See Compl. ¶¶ 190-93 (Count VI).)
    Significantly, Plaintiffs have eschewed any facial challenge to NWP 12 itself.
    3. The Administrative Procedure Act
    Plaintiffs’ complaint alleges that, insofar as none of the Federal Agencies have
    completed an EA and EIS with respect to the FS Pipeline, the Federal Agencies have
    not only violated NEPA, they have also violated the APA. This coupling of the NEPA
    requirement with APA review arises primarily from the fact that “NEPA does not
    provide a separate cause of action for plaintiffs seeking to enforce its EIS
    requirements.” Nat’l Coal. to Save Our Mall v. Norton, 
    161 F. Supp. 2d 14
    , 19 (D.D.C.
    2001), aff’d, 
    269 F.3d 1092
     (D.C. Cir. 2001). Therefore, Plaintiffs must bring their
    NEPA claims under a separate statutory scheme, typically the general review provision
    of the APA. See, e.g., City of Williams v. Dombeck, 
    151 F. Supp. 2d 9
    , 25 (D.D.C.
    2001).
    Under the APA, a court reviews an agency action to determine whether it is
    “arbitrary or capricious.” 
    5 U.S.C. § 706
    (2)(A) (2012). An agency acts arbitrarily or
    capriciously if it “relie[s] on factors which Congress has not intended it to consider,
    entirely fail[s] to consider an important aspect of the problem, [or] offer[s] an
    explanation for its decision that runs counter to the evidence before the agency[] or is
    so implausible that it could not be ascribed to a difference in view or the product of
    agency expertise.” Stephens v. U.S. Dep’t of Labor, 
    571 F. Supp. 2d 186
    , 191 (D.D.C.
    2008).
    Courts considering an APA claim in the NEPA context often draw a distinction
    between, complaints about the scope of an agency’s NEPA analysis, on the one hand,
    19
    claims that an agency has erred in determining that it is not required to perform a NEPA
    analysis, and on the other. In the first category, courts review an agency’s decision to
    conduct a limited NEPA review under the typical APA “arbitrary and capricious”
    standard because the question presented for review is generally a factual, not legal,
    dispute. See, e.g., Marsh v. Oregon Natural Res. Council, 
    490 U.S. 360
    , 377 (1989)
    (explaining that, when a question presented for review involves a factual dispute, the
    court must defer to “the informed discretion of the responsible federal agencies.”). In
    the second category, where an agency concludes that NEPA does not apply to its actions
    at all, the agency’s decision is “not entitled to the deference that courts must accord to
    an agency’s interpretation of its governing statute and is instead a question of law,
    subject to de novo review.” Sierra Club v. U.S. Dep’t of Agric., 
    777 F. Supp. 2d 44
    , 54
    (D.D.C. 2011) (internal quotation marks omitted).
    Here, in addition to making several APA claims that derive from the Federal
    Agencies’ alleged failure to comply with NEPA (see Compl. ¶¶ 155-89 (Claims II-V)),
    Plaintiffs also contend that the Corps violated the APA insofar as that agency’s district
    engineers verified that the water crossings at issue in this action satisfied the standards
    set forth in NWP 12 (see id. ¶¶ 190-93 (Claim VI)). This latter claim is reviewed under
    the familiar arbitrary and capricious standard applicable to claims arising under the
    APA. See 
    5 U.S.C. § 706
    (2)(A).
    4.   The Instant Complaint
    The aforementioned statutory and regulatory regimes loom large in any
    consideration of Plaintiffs’ complaint, and this is especially so where, as here, Plaintiffs
    have filed a motion for a preliminary injunction, thereby requiring the Court to assess
    20
    the likelihood of their success on the merits. (See infra, Part II.) The Court notes that
    Plaintiffs’ complaint is not a model of clarity with respect to what conduct is being
    alleged as a violation of which statute, however; hence, repeated reminders of the
    specific claims and the implicated statutes are required.
    To summarize what has already been described, the instant complaint contains
    six claims, five of which are relevant to the pending motion. 11 Claim II alleges that the
    Corps violated NEPA and the APA, and references both the Corps’s verifications that
    the water crossings satisfy NWP 12, which were made pursuant to the CWA, and the
    requested easements over federal land, which the Corps is apparently still considering
    pursuant to their authority to grant easements for construction projects that traverse
    land over which the Corps has jurisdiction. In this claim, Plaintiffs maintain that the
    Corps violated federal law when it issued the NWP 12 verifications without performing
    an environmental assessment of the pipeline (Compl. ¶¶ 156-60), and also when it
    “allow[ed] Enbridge to proceed with construction before the easements have been
    granted and before [the] required environmental review has been completed[.]” (Id. ¶
    161.)
    Claim III alleges that the FWS violated NEPA and the APA when, without
    conducting a comprehensive environmental assessment, it issued the required
    Biological Opinion and incidental take statement in response to the other agencies’
    formal request for a consultation regarding the potential impact of the proposed pipeline
    construction project on certain species. (Id. ¶¶ 165-71.)
    11
    As noted in footnote 4, supra, Claim I has been effectively severed from the instant motion and
    therefore is not currently at issue.
    21
    Claim IV alleges that the PHMSA violated NEPA and the APA when it failed to
    approve an oil spill response plan pursuant to the Oil Pollution Act prior to the
    beginning of pipeline construction, even though no such plan has been prepared or
    submitted to the agency. (Id. ¶¶ 172-79.)
    Claim V alleges that all of these federal agency actions or inactions—including
    the actions of the BIA in considering Enbridge’s request for easements over Indian land
    (which are not the subject of a separate claim)—gave rise to an obligation on the part of
    the Federal Agencies to conduct a full-scale NEPA review of the entire FS Pipeline, and
    to select a “lead agency” primarily responsible for preparing the report. (Id. ¶¶ 180-
    89.)
    Finally, Claim VI alleges that the Corps violated NWP 12, the CWA, and the
    APA both when it allegedly failed to include consideration of the cumulative effect of
    all the verifications issued in connection with the FS Pipeline in its analysis of whether
    the verifications satisfied NWP 12, and also when it verified certain water crossings
    that are purportedly outside the scope of NWP 12 because they are in the proximity of a
    public water supply intake. (Id. ¶¶ 190-193.)
    As a result of all of these alleged violations of federal law, Plaintiffs’ complaint
    asks this Court for “a declaratory ruling” that contains the following specific findings:
    (a) the Corps should have prepared an EA or an EIS for its
    verifications and easements; (b) the [FWS] should have
    prepared an EA or EIS for its Biological Opinion and
    Incidental Take Statement; (c) PHMSA should have
    prepared an EA or an EIS for the [FS Pipeline’s] emergency
    response plan; (d) the Corps or one of the other federal
    agencies involved should have prepared an EA or an EIS for
    the entire [FS] Pipeline project, or at a minimum designated
    a lead agency for that comprehensive NEPA analysis; and
    22
    (e) the Corps’ verifications of the [FS Pipeline] were
    contrary to the Clean Water Act and [NWP 12].
    (Compl. ¶ 8.) Moreover, as mentioned previously, Plaintiffs have now filed a motion
    for a preliminary injunction asking the Court to suspend all actions of the Federal
    Agencies related to the FS Pipeline and to “enjoin[] Enbridge Pipelines LLC and all of
    its agents, officers, employees and anyone acting in concert with it, from construction
    and operation of the [FS Pipeline] pending a final ruling on the merits.” (Plaintiffs’
    Opening Brief (“Pl. Br.”), ECF No. 14, at 1.)
    II.    PRELIMINARY INJUNCTION STANDARD
    A preliminary injunction is “an extraordinary remedy that may only be awarded
    upon a clear showing that the plaintiff is entitled to such relief.” Winter v. Natural Res.
    Def. Council, Inc., 
    555 U.S. 7
    , 22 (2008). A party seeking a preliminary injunction
    “must establish [1] that [it] is likely to succeed on the merits, [2] that [it] is likely to
    suffer irreparable harm in the absence of preliminary relief, [3] that the balance of
    equities tips in [its] favor, and [4] that an injunction is in the public interest.” 
    Id. at 20
    .
    In conducting an inquiry into these four factors, “[a] district court must ‘balance the
    strengths of the requesting party’s arguments in each of the four required areas.’ . . . If
    the showing in one area is particularly strong, an injunction may issue even if the
    showings in other areas are rather weak.” Chaplaincy of Full Gospel Churches v.
    England (“CFGC”), 
    454 F.3d 290
    , 297 (D.C. Cir. 2006) (quoting CityFed Fin. Corp. v.
    Office of Thrift Supervision, 
    58 F.3d 738
    , 746 (D.C. Cir. 1995)). However, “a movant
    23
    must demonstrate ‘at least some injury’ for a preliminary injunction to issue.” 
    Id.
    (citation omitted). 12
    III.      ANALYSIS
    A. Likelihood Of Success On The Merits
    1. Plaintiffs’ NEPA Claims
    Four counts of Plaintiffs’ complaint directly implicate NEPA, as previously
    explained. Although Plaintiffs have opted to plead substantially similar NEPA
    allegations in separate counts, Plaintiffs have repeatedly summarized their overarching
    NEPA contention as the argument that as a result of the Federal Agencies’ participation
    in various aspects of the FS Pipeline construction project, the agencies had a statutory
    obligation to prepare an EIS, or at least to conduct an EA, of the entire pipeline, even
    those portions that are being constructed on private land and that would otherwise not
    be subject to federal oversight. (See, e.g., Pl. Br. at 19-21; Plaintiffs’ Reply Brief (“Pl.
    Reply”), ECF No. 34, at 19-21; Hr’g Tr. (Sept. 27, 2013), at 10:9-11 (statement of
    Plaintiffs’ counsel that “[t]he question [in this case] is whether any federal agency has
    to look at the entire oil pipeline.”).) There is no dispute that the NEPA duty to prepare
    12
    This approach to analyzing the preliminary injunction factors is traditionally used in this Circuit and
    is often referred to as a “sliding scale.” The D.C. Circuit has recently suggested that this sliding scale
    approach may no longer be applicable after the Supreme Court’s decision in Winter and that, instead, a
    more stringent test applies. See Sherley v. Sebelius, 
    644 F.3d 388
    , 393 (D.C. Cir. 2011) (likelihood of
    success on the merits and irreparable harm may be “independent, free-standing requirement[s] for a
    preliminary injunction” (internal quotations marks and citation omitted)); see also Davis v. Pension
    Benefit Guar. Corp., 
    571 F.3d 1288
    , 1296 (D.C. Cir. 2009) (Kavanaugh & Henderson, JJ., concurring)
    (“[U]nder the Supreme Court’s precedents, a movant cannot obtain a preliminary injunction without
    showing both a likelihood of success and a likelihood of irreparable harm, among other things.”).
    However, in the absence of a precedential ruling to this effect, this Court will apply the more lenient
    sliding scale standard to the injunction at issue here. Cf. Kingman Park Civic Ass’n v. Gray, No.
    13-cv-990, 
    2013 WL 3871444
    , at *3 (D.D.C. Jul. 29, 2013) (“[A]bsent . . . clear guidance from the
    Court of Appeals, the Court considers the most prudent course to bypass this unresolved issue and
    proceed to explain why a preliminary injunction is not appropriate under the ‘sliding scale’ framework.
    If a plaintiff cannot meet the less demanding ‘sliding scale’ standard, then it cannot satisfy the more
    stringent standard alluded to by the Court of Appeals.”).
    24
    an EIS or to conduct an EA—hereinafter collectively referred to as an “environmental
    review” under NEPA—only arises when a federal agency undertakes “major federal
    action[] significantly affecting the quality of the human environment[.]” 
    42 U.S.C. § 4332
    (2)(C). For the reasons that follow, the Court concludes that Plaintiffs have not
    demonstrated that they are likely to succeed on the merits of their contention that the
    participation of any of the Federal Agencies, alone or in combination, triggered a NEPA
    obligation to conduct an environmental review of the FS Pipeline before construction
    on the pipeline project commenced.
    a. The Corps’s Verifications Were Issued Under NWP 12 And Thus An
    Individualized Environmental Review Under NEPA Was Not Required
    Plaintiffs’ myriad allegations and assertions regarding the Corps’s CWA
    verifications appear to boil down to two basic contentions: (1) the verifications
    themselves “[c]onstitute [m]ajor [f]ederal [a]ction[s]” that triggered a duty on the part
    of the Corps to conduct an environmental review under NEPA (Pl. Br. at 13), and (2)
    the fact that the verifications in this case involved many water crossings spread out
    throughout the entire pipeline transformed the otherwise private construction project
    into a major federal action such that the Corps should have conducted an environmental
    review of the pipeline pursuant to NEPA (id. at 19). Neither of these assertions is
    likely to be successful on the merits.
    First of all, the linchpin of these related arguments is the mistaken assumption
    that the verifications are the equivalent of a permit insofar as they effectively
    authorized the FS Pipeline to proceed. (See, e.g., 
    id. at 13
     (stating that “[t]he Corps’[s]
    verifications under NWP 12 permit the construction of the Pipeline” and that “Corps’[s]
    approval is ‘essential to completion of the project’” (citation omitted)); see also 
    id. 25
    (“No part of Flanagan South could operate without the verifications.”).) To be sure,
    some courts have held that “‘if a federal permit is a prerequisite for a project with
    adverse impact on the environment, issuance of that permit does constitute a major
    federal action’” for NEPA purposes, as Plaintiffs argue here. (Pl. Br. at 13 (quoting
    Ramsey v. Kantor, 
    96 F.3d 434
    , 444 (9th Cir. 1996)); see also 
    id.
     (citing Wyoming
    Outdoor Council v. U.S. Corps of Eng’rs, 
    351 F. Supp. 2d 1232
    , 1242 (D. Wyo.
    2005)).) But such courts generally were not assessing verifications under the CWA,
    and to characterize the verifications here as “allowing” or “approving” the FS Pipeline
    project is inaccurate—the record suggests that Enbridge evaluated the risks and started
    construction of portions of the pipeline on private land even before it had secured all of
    the necessary federal rights-of-way—and also manifestly inconsistent with the fact that
    no federal approval or permission is required for construction of a domestic oil pipeline
    such as this one. 13
    Moreover, and even more important, the law quite clearly distinguishes between
    “verifications” and “permits” in the CWA context, compare 33 C.F.R. Part 325
    (establishing procedures for individual permits), with 33 C.F.R. Part 330 (detailing
    procedures for verification under general permitting system), and the entire point of the
    general permitting system is to avoid the burden of having to conduct an environmental
    review under NEPA when a verification—as distinguished from an individual discharge
    permit—is sought. As previously and extensively explained, under the general
    13
    Notably, as an entirely domestic pipeline, construction of the FS Pipeline does not require federal
    permission, oversight, or approval, and is therefore fundamentally unlike pipelines that bring oil into
    the United States from other countries. The proposed Keystone XL Pipeline, for example, is an
    international project that requires the State Department to issue a Presidential Permit finding that it is
    in the “national interest” before it can be constructed. See, e.g., Final Environmental Impact Statement
    for the Proposed Keystone XL Project, 
    76 Fed. Reg. 55,155
     (Sept. 6, 2011); see also Exec. Order
    13,337, 
    69 Fed. Reg. 25,299
     (Apr. 30. 2004). For this reason alone, Plaintiffs’ repeated comparisons
    between the FS Pipeline and the Keystone XL Pipeline (see, e.g., Pl. Br. at 4, 26-27) are misguided.
    26
    permitting system, the Corps conducts an extensive environmental review and provides
    the public with notice and an opportunity to comment regarding categories of
    construction activity that the Corps seeks to designate as having minimal impact on
    waterways within specified geographical regions. See 
    33 C.F.R. § 330.1
    (b). The
    purpose of the statute that authorizes general permits such as the nationwide permit at
    issue here is to allow the Corps to designate certain construction projects as eligible for
    CWA discharge permits “with little, if any, delay or paperwork” because they fit within
    these pre-cleared categories of activities. Id.; see also Snoqualmie Valley Pres.
    Alliance v. U.S. Army Corps of Eng’rs, 
    683 F.3d 1155
    , 1164 (9th Cir. 2012) (“The
    purpose of [the NWP] scheme is to enable the Corps to quickly reach determinations
    regarding activities that will have minimal environmental impacts[.]”). Courts have
    found, and this Court agrees, that “[r]equiring an elaborate analysis of the applicable
    regulations and the facts would defeat th[e] purpose[]” of a general permit. Snoqualmie
    Valley, 683 F.3d at 1163.
    Consequently, it makes little sense that, notwithstanding the FS Pipeline
    project’s eligibility for verification under NWP 12, the Corps nevertheless had to
    conduct a full environmental review under NEPA, as Plaintiffs maintain. In other
    words, the requisite comprehensive environmental review is done upfront under the
    general permitting system precisely to avoid a NEPA environmental review regarding
    certain projects that fit into categories of activity that have been predetermined to have
    minimal environmental impact. Therefore, once the Corps’s district engineers verified
    that the discharges resulting from the FS Pipeline satisfied NWP 12, no additional
    environmental review was required.
    27
    It is also conceptually mistaken to characterize a CWA verification as qualifying
    for “major federal action” status when the Corps’s actual role in providing a
    verification letter pursuant to the general permitting process is properly understood.
    Many projects undertaken pursuant to a general permit do not even need to be brought
    to the Corps’s attention; there is no federal action, much less “major” federal action, in
    regard to such projects. See 
    33 C.F.R. § 330.1
    (e)(1). Even when a general permit
    requires that the Corps provide pre-construction verification, such as is the case with
    NWP 12, the Corps’s role is limited to determining whether the project in question does
    or does not satisfy the terms of the general permit, and if not, what steps the party
    seeking verification must take to bring their project within the ambit of that
    authorization. 
    Id.
     § 330.1(e)(3). This type of check-in is far less involved than the
    probing assessment of the particular facts, circumstances, and environmental
    consequences of a specific project proposal that precedes a Corps determination of
    whether or not an individual discharge permit should issue. Put another way, under the
    nationwide permit system, the Corps has already done an environmental review on a
    general categorical basis and has already given its imprimatur to discharges that result
    from the type of construction activity at issue under specified circumstances. When a
    prospective permittee files a pre-clearance notice, the only thing left to be done is for
    the Corps’s district engineers to verify that the planned project does, in fact, fit within
    the category of activities that the Corps has already authorized. And given Congress’s
    stated interest in targeting “major federal actions” for extensive environmental review
    under the NEPA statute, 
    42 U.S.C. § 4332
    (2)(C) (emphasis added), it is unlikely that
    this limited verification process is what Congress had in mind.
    28
    In sum, Plaintiffs do not, and cannot, dispute that the general permitting system
    operates on a different track than the individual project-by-project permitting process
    for construction project discharges that would otherwise apply under the CWA, or that
    only major federal actions trigger a duty to conduct an environmental review under
    NEPA. Plaintiffs also disclaim any facial challenge to the general permitting statute or
    NWP 12 in the context of this action, see Hr’g Tr. at 15:8-13, and it is clear that when a
    project proceeds under a valid general permit, NEPA’s environmental review obligation
    and other permitting requirements that would otherwise apply are irrelevant. See, e.g.,
    Ouachita Riverkeeper, Inc. v. Bostick, 
    938 F. Supp. 2d 32
    , 35-36, 45-46 & 46 n.7
    (D.D.C. 2013) (distinguishing between nationwide and individual permits and finding
    that no NEPA analysis was required where construction was properly verified under
    NWP 12); Snoqualmie Valley, 683 F.3d at 1164 (“Verifying that permittees may
    properly proceed under a nationwide permit does not require a full NEPA analysis at
    the time of the verification.”). With all this considered, the Court sees no clear path to
    victory for Plaintiffs regarding the first aspect of their claim that the Corps violated
    NEPA when it proceeded to verify that the discharges and other activities related to
    construction of the FS Pipeline were consistent with NWP 12 without conducting an
    environmental review.
    Plaintiffs’ related contention regarding the Corps’s verifications—that the large
    number of water crossings and related verifications involved with the FS Pipeline
    project makes this project a major federal action for NEPA purposes—fares no better.
    Plaintiffs take issue with the fact that four different Corps district engineers verified
    approximately 1,950 separate water crossings related to the FS Pipeline under NWP 12
    29
    without undertaking a comprehensive NEPA analysis of the pipeline. (See, e.g., Pl. Br.
    at 13, 20, 25.) But Plaintiffs have not established that the number of verifications
    requested in relation to a project does or should have any effect on the general
    permitting system, much less that a project can be pushed off the general permit track
    and made to proceed down the alternative individual permit route if more than a certain
    number of verifications are involved. Nor do Plaintiffs provide any reason why the
    number of verifications required by a particular project should have any bearing on that
    project’s ability to be verified as consistent with a general permit. 14 Plaintiffs have not
    identified any authority in the law or in the language of NWP 12 that would allow the
    Court to graft the NEPA requirement attendant to the individualized permitting system
    onto the general permitting system whenever the Corps issues a large number of
    verifications with respect to a linear construction project such as the FS Pipeline, and
    the Court sees no reason for doing so, especially where, as here, importing an
    environmental review obligation would undermine the purpose and efficacy of the
    general permitting system. Moreover, Plaintiffs have also thus far failed to provide an
    answer to the practical concern that requiring additional environmental review for
    projects that qualify for a general permit would give rise to significant and untenable
    uncertainty for any construction project—large or small—that seeks to rely on a general
    permit in lieu of an individual permit and accompanying NEPA review.
    Finally, the Court notes that Spiller v. Walker, No. A 98 CA 255 SS, 
    1998 U.S. Dist. LEXIS 18341
     (W.D. Tex. Aug. 25, 1998), and the dissenting opinion in Sierra
    14
    By Plaintiffs’ logic, one construction project that requires 2,000 verifications for water crossings
    would be subject to further environmental review under NEPA, while 2,000 separate projects that each
    require a single verification for a water crossing would not necessarily require additional review,
    despite the fact that both scenarios theoretically pose the same potential threat to the aquatic
    environment.
    30
    Club v. Bostick, No. 12-6201, 
    2013 WL 5539633
    , at *9 (10th Cir. Oct. 9, 2013)—upon
    which Plaintiffs rely—are unpersuasive primarily because the logic of these cases does
    not sufficiently account for the fact that Congress established a general permitting
    system as an alternative to the requirement that construction projects with a minimal
    potential impact on national waterways obtain an individual permit under the CWA.
    Like the instant case, Spiller involved an oil pipeline that crossed both waterways and
    federal land under the Corps’s jurisdiction. Moreover, although the Spiller court is not
    entirely clear on this point, it appears that the pipeline operator in that case applied to
    have the water crossings verified pursuant to a general permit. See 
    id. at *39
     (“[The
    pipeline operator] has requested a nationwide permit under section 404 of the Clean
    Water Act[.]”). Under the circumstances presented, the Spiller court concluded that
    “[t]he Army’s role in granting permits for construction over navigable waters and
    granting a right-of-way over [federal land] combine to have such a crucial impact on the
    construction of the [pipeline] at so many points along the pipeline that it can only be
    described as ‘major [f]ederal action.’” 
    Id. at *40-41
    . Of particular note in this passage
    is the fact that the Spiller court invoked the “Army’s role in granting permits” as
    indicative of the level of federal involvement in the pipeline, and Plaintiffs point to this
    language as support for the proposition that the issuance of permits under the CWA
    where the federally-controlled waters were found throughout the project required NEPA
    review of the project. (See Pl. Br. at 17.)
    As explained above, however, the Corps does not grant permits pursuant to the
    general permitting process; rather, it simply verifies that an application meets the
    criteria for the pre-existing general authorization. And this difference is not merely
    31
    semantic—rather, the process for the Corps’s issuing an individual permit is very
    different, and far more involved, than the process of verifying that a construction
    project is consistent with the terms of a general permit. The court in Spiller failed
    entirely to consider this crucial distinction; indeed, apart from the single passing
    reference to a nationwide permit mentioned above, the Spiller opinion contains no
    discussion of the general permitting system at all. Therefore, in addition to the fact that
    Spiller is not binding authority in this jurisdiction, this Court finds that it simply cannot
    follow Spiller’s logic.
    Nor does the dissenting opinion in Bostick add any additional heft to Plaintiffs’
    argument that Spiller reached the right result. (See Plaintiffs’ Notice of Supplemental
    Authority (“Pl. Supp. Br.”), ECF No. 42, at 2-3.) Bostick is a Tenth Circuit case that
    was on appeal from the denial of a preliminary injunction where the plaintiffs had
    launched a facial challenge to NWP 12 (that alone distinguishes it from the instant
    matter). 
    2013 WL 5539633
    , at *1. Although the majority opinion reached only the
    question of irreparable harm, the dissenting judge evaluated likelihood of success on
    the merits, and relying extensively on Spiller, concluded that the entire pipeline at issue
    in that case—the nearly 500-mile Gulf Coast Pipeline—should have been subject to
    NEPA review. 
    Id. at *13
    . The principal factual basis for the dissenter’s conclusion was
    the “number of permits issued by the Corps relative to the overall size of the Gulf Coast
    Pipeline,” and in light of this ratio, the dissenter found it “patently ludicrous” to
    32
    maintain that “the Corps’ permitting involves only a ‘link’ in the Gulf Coast Pipeline[]”
    such that it was not a major federal action for NEPA purposes. 
    Id. at *11
    . 15
    But, like the Spiller judge before him, the dissenting judge in Bostick
    inexplicably failed to acknowledge the critical difference between the Corps’s role as
    permitter—an authority it exercises when and if an individual discharge permit is
    requested—and its role as a verifier, which it undertakes when a general permit
    involving construction activity that has already received extensive environmental
    review requires an applicant to file a pre-clearance notice and to obtain the Corps’s
    verification that its project is consistent with the existing general permit. Rather, the
    dissenting opinion (mistakenly) asserts that the Corps “issue[d] 2,227 permits”
    regarding the Gulf Coast Pipeline. 
    Id. at *11
     (emphasis added). And having so
    mischaracterized the Corps’s role with respect to the pipeline project, it is no wonder
    that the dissenting judge believed that the Corps’s verification of the large number of
    water crossings at issue was a major federal action for NEPA purposes. 
    Id. at *12
    .
    The instant Court views the distinction between verifications and permits as
    making all of the difference as far as a NEPA analysis is concerned, as explained above.
    Therefore, even setting aside the fact that a dissenting opinion has no precedential
    value, the Bostick dissent’s failure to acknowledge that the Corps’s verifications are not
    the functional equivalent of permits renders its analysis wholly unpersuasive.
    15
    According to the dissenting opinion, “[t]he Gulf Coast Pipeline is 485 miles long, and required the Corps to issue
    2,227 permits for water crossings[,]” which “means that the Gulf Coast Pipeline crosses United States waters almost
    five times in each mile, or about once every 1150 feet.” Bostick, 
    2013 WL 5539633
    , at *11.
    33
    b. The Fish and Wildlife Service’s Biological Opinion and Incidental
    Take Statement Did Not Trigger A Duty To Undertake A NEPA Review
    Plaintiffs also maintain that the FWS engaged in a major federal action sufficient
    to give rise to an obligation to perform a NEPA environmental review of the FS
    Pipeline when it issued the Biological Opinion and incidental take statement in response
    to formal requests from the Corps and the BIA. (Pl. Br. at 21-22; cf. Defendant’s
    Opposition Brief (“Def. Br.”), ECF No. 28, at 15-16.) The statute pursuant to which the
    FWS issued its opinion and take statement (Section 7 of the ESA, 
    16 U.S.C. § 1536
    (b))
    establishes a “consultation” process whereby other federal agencies considering
    whether or not to exercise their own permitting authority engage with the FWS—a
    process that differs significantly from the kind of agency activity that ordinarily counts
    as major federal action for NEPA purposes. Compare City of Dania Beach, Fla. v.
    FAA, 
    485 F.3d 1181
    , 1189 (D.C. Cir. 2007) (FAA regulation expanding airport runway
    use was “clearly major federal action” requiring NEPA review). The Court’s hesitancy
    to view a Section 7 consultation as a major federal action on the part of the FWS for
    NEPA purposes is especially justified given that, under Section 7, it is the requesting
    agency, not the FWS, that ultimately decides what impact the biological opinion and
    incidental take statement will have on the construction project under consideration. See
    
    50 C.F.R. § 402.15
    (a) (2013) (“Following the issuance of a biological opinion, the
    Federal agency shall determine whether and in what manner to proceed with the action
    in light of its section 7 obligations and the Service’s biological opinion.”). But this is
    not to say that an FWS opinion and incidental take statement issued pursuant to the
    Section 7 consultation process can never rise to the level of major federal action; in
    Ramsey v. Kantor, 
    96 F.3d 434
     (9th Cir. 1996)—the primary legal precedent Plaintiffs
    34
    offer in support of the argument that the FWS’s Biological Opinion and incidental take
    statement constituted a major federal action in this case—the Ninth Circuit held as
    much.
    Ramsey involved a legal challenge to two states’ plans for the management of
    their salmon fisheries. The states of Oregon and Washington sought to issue permits
    for salmon fishing in certain rivers where fishing would otherwise be off limits under
    the Endangered Species Act because endangered species of salmon mingled with non-
    endangered salmon. 
    Id. at 439
    . As the Ninth Circuit panel viewed the facts, salmon
    fishing in those areas as authorized by state law could only proceed consistent with the
    Endangered Species Act if the federal agency that regulates activities impacting
    endangered salmon rendered a biological opinion “examining the proposed action and
    the anticipated effects on the species,” 
    id. at 440
    , and if that agency also issued an
    incidental take statement that effectively waived the otherwise applicable federal
    penalty for the incidental killing of a certain number of the endangered type of salmon.
    The issue presented in Ramsey was whether issuance of an incidental take statement
    under such circumstances constituted a major federal action that gave rise to a NEPA
    duty to conduct an environmental review of the state fishing plans. 
    Id. at 443
    .
    Emphasizing that “it is all but impossible to fish for [non-endangered] salmon . . .
    without incidentally taking salmon that are listed [as endangered species,]” the panel
    held that the federal agency’s incidental take statement was a major federal action for
    the purpose of NEPA. 
    Id. at 444
    .
    The Ramsey court’s conclusion finds no applicability here. Ramsey’s holding
    rested on the court’s observation that “the incidental take statement in this case is
    35
    functionally equivalent to a permit because the activity in question would, for all
    practical purposes, be prohibited but for the incidental take statement.” 
    Id.
     (emphasis
    added). The project that was under consideration in Ramsey was the states’ plan to
    allow fishing for non-endangered salmon in areas that ensured that endangered salmon
    would be caught, and under those circumstances, the federal agency’s incidental take
    statement was clearly essential to the adoption of that plan. See 
    id. at 444
    . Here, by
    contrast, the FWS’s Biological Opinion is at best peripheral to the project in question.
    The FS Pipeline is a private construction project involving the transportation of
    domestic oil reserves that is by no means aimed at the capture of any species, much less
    endangered species, and there is no evidence to suggest that the project could not
    proceed without the FWS’s incidental take statement such that the statement is
    “functionally equivalent to a permit.” Put another way, although the FWS’s Section 7
    consultation responsibilities may sometimes have such a direct impact on a project that
    the incidental take statement rises to the level of major federal action, this will not
    always be so, and there is nothing about the FWS’s consideration of the Indiana bat, the
    American burying beetle, and the decurrent false aster in relation to the FS Pipeline that
    would permit the conclusion that the incidental take statement at issue here had any
    such impact (at least on the record as it currently exists). Accordingly, Plaintiffs have
    failed to show a likelihood of success on the merits with respect to their NEPA claim
    based on the FWS’s actions.
    c. Federal Review Of The Requested Easements Is Ongoing And May Yet
    Result In The Requested NEPA Analysis
    Plaintiffs also argue that the Corps’s and the BIA’s consideration of Enbridge’s
    requests for easements counts as major federal action for NEPA purposes. Unlike other
    36
    aspects of Plaintiffs’ complaint, it appears that there is no dispute that granting an
    easement over federal land qualifies as a major federal action under NEPA, at least with
    respect to the portion of the project that is slated to run over the land under federal
    control. (See Def. Br. at 20-21.) The trouble with this claim is that the requested
    federal easements for the FS Pipeline are still under consideration by the Corps and the
    BIA, and there is evidence in the record that indicates that these agencies may even
    have commenced the environmental review that is the object of Plaintiffs’ allegations.
    (See, e.g., Decl. of Scott L. Whiteford), ECF No. 28-6, ¶ 7; Decl. of Eddie Streater),
    ECF No. 28-7, ¶ 11.) Under these circumstances, the Court has significant concerns
    that Plaintiffs’ NEPA claims regarding the easements are not yet ripe. See Texas v.
    United States, 
    523 U.S. 296
    , 300 (1998) (“A claim is not ripe for adjudication if it rests
    upon contingent future events that may not occur as anticipated, or indeed may not
    occur at all.” (citation and internal quotation marks omitted)).
    Plaintiffs’ briefs in support of the motion for a preliminary injunction do little to
    allay those concerns. Plaintiffs’ primary argument is that, even if an environmental
    review is currently being performed with respect to the requested easements, the Corps
    and the BIA nevertheless violated NEPA by allowing construction of other parts of the
    FS Pipeline prior to the completion of that review. (Pl. Reply at 13.) However, as has
    been repeated numerous times above, federal agencies do not “allow” or “permit”
    construction of a domestic oil pipeline on privately owned land. Indeed, it is precisely
    because domestic oil pipelines do not require federal authorization that Enbridge
    apparently started building the FS Pipeline even before the federal agencies had
    determined whether or not to grant the easements in question.
    37
    In any event, given the state of the record at this point, Plaintiffs have failed to
    persuade the Court that an injunction is appropriate when the alleged NEPA violation
    has not yet occurred and is still in the process of being addressed. Because the Court is
    not convinced that Plaintiffs will be successful in sustaining their claim that the
    pending easement requests can be the basis for any cognizable NEPA violation, the
    Court declines to issue an injunction on this ground at this time.
    d. There Is No Basis For Plaintiffs’ Contention That The PHMSA Has A
    NEPA Obligation To Undertake An Environmental Review
    Plaintiffs also provide no support for their argument that the inaction of the
    PHMSA with respect to a contingency oil spill plan triggered a NEPA duty to conduct
    an environmental review of the FS Pipeline, nor can they, because this claim appears to
    be baseless. It is true that there has been no action on the part of the PHMSA, but that
    is primarily because the agency has not even been provided with an opportunity to act.
    To recap what was explained above, under federal law a pipeline owner is only required
    to prepare and submit a spill response plan before a pipeline begins operation—not
    before it is constructed—and, indeed, Enbridge has yet to submit such a plan to the
    PHMSA. See 
    49 C.F.R. § 194.7
     (2013). To argue here, as Plaintiffs do, that the
    PHMSA nevertheless somehow has engaged in a major federal action for NEPA
    purposes defies logic. And unless and until Plaintiffs are able to demonstrate that a
    federal agency that has not been invited to act in any way regarding a project with
    potential environmental impacts can nonetheless be deemed to have engaged in a
    “major federal action[] significantly affecting the quality of the human environment”
    38
    for NEPA purposes, there is little likelihood that Plaintiffs will prevail on the PHMSA
    claim.
    e. Even Viewed Collectively, The Federal Agencies’ Actions Do Not Give
    Rise To Any NEPA Duty To Assess The Environmental Impact Of The
    Entire FS Pipeline
    Finally, we arrive at what Plaintiffs have conceded is the core of their NEPA-
    related concern: that the collective actions of the various Federal Agencies triggered an
    obligation under NEPA for some agency to conduct an environmental review not only
    of the portions of the pipeline that required that agency’s input but also of the entire
    589-mile domestic pipeline project. (See Compl. ¶ 182 (asserting that the federal
    actions “singly, in combination, and cumulatively constitute major federal action and
    thus trigger the requirement under NEPA that the Corps prepare an EA and/or EIS for
    the entire [FS Pipeline.]”); see also Pl. Br. at 19, 24-27.) Plaintiffs’ principal worry
    appears to be that no such comprehensive environmental review of the entire FS
    pipeline was undertaken prior to the beginning of pipeline construction. (Pl. Br. at 29-
    30.) But Plaintiffs cannot deny that the obligation to review a project pursuant to
    NEPA arises only when there is “major federal action.” 
    42 U.S.C. § 4332
    (2)(C)
    (emphasis added). In the Court’s view, Plaintiffs have significantly overstated the
    degree of federal involvement in the FS Pipeline in an attempt to shoehorn this
    essentially private project into the NEPA statute; consequently, at least on the record as
    it currently stands, Plaintiffs’ claim that NEPA requires a comprehensive environmental
    review is unlikely to be successful.
    Plaintiffs’ argument is not unprecedented. The question of how much federal
    involvement is needed to “federalize” an otherwise private project such that NEPA
    39
    review is required for the entire undertaking is a dilemma that has vexed courts and
    commentators for some time. See, e.g., Jeslyn Miller, Note, Clarifying the Scope of
    NEPA Review and the Small Handles Problem, 
    37 Ecology L.Q. 735
    , 737 (2010)
    (“[C]ourts have struggled with the extent to which an environmental analysis under
    [NEPA] must consider the entirety of a private development or just those components
    subject to direct federal jurisdiction.”); see also Save Our Sonoran, Inc. v. Flowers,
    
    227 F. Supp. 2d 1111
    , 1113 (D. Ariz. 2002) (“The scope of analysis of federal action by
    the Corps of Engineers under [NEPA] is a topic not without controversy.” (citation
    omitted)). Put in the parlance of NEPA, the issue is when and under what
    circumstances an otherwise private project is transformed into a “major federal action”
    requiring a federal agency to undertake an environmental review of the entire project.
    
    42 U.S.C. § 4332
    (C). 16
    In Winnebago Tribe of Nebraska v. Ray, 
    621 F.2d 269
     (8th Cir. 1980), the Eighth
    Circuit confronted this question in regard to a fact scenario similar to the one before
    this Court. Winnebago Tribe concerned a tribe’s attempt to enjoin the construction of a
    67-mile power line, 1.25 miles of which crossed waters under the jurisdiction of the
    Corps. 
    Id. at 270
    . While the Corps prepared an EA with respect to the river-crossing
    portion of the power line as part of its consideration of a request for an individual
    permit related to that water crossing, the plaintiff argued that, under NEPA, the Corps
    was obligated to do an environmental assessment of the entire pipeline. 
    Id. at 272
    . In
    addressing the question of the scope of the required environmental review, the Eighth
    16
    This question is apparently common enough to have earned a nickname in the academic literature: the “small
    handles” problem. See generally Elizabeth A. Roche, The Continuing Saga of Rippling Puddles, Small Handles and
    Links of Chains: Wetlands Action Network v. United States Army Corps of Engineers, 
    13 Vill. Envtl. L.J. 119
    (2002); Mary K. Fitzgerald, Comment, Small-Handles, Big Impacts: When Should the National Environmental
    Policy Act Require an Environmental Impact Statement?, 
    23 B.C. Envtl. Aff. L. Rev. 437
     (1996).
    40
    Circuit distinguished between a federal agency’s “[f]actual or veto control” of a
    project—that is, where there is some federal involvement necessary in a piece of a
    project—and an agency’s “legal control or ‘enablement’” of a project—that is, where
    “federal action is a legal condition precedent to accomplishment of an entire nonfederal
    project.” 
    Id.
     (citation omitted). In the former situation, the Winnebago Tribe court
    identified three factors “helpful in determining” whether a “project-wide analysis” was
    required:
    (1) the degree of discretion exercised by the agency over the
    federal portion of the project; (2) whether the federal
    government has given any direct financial aid to the project;
    and (3) whether the overall federal involvement with the
    project (is) sufficient to turn essentially private action into
    federal action.
    
    Id.
     (citation omitted). The Eighth Circuit considered these factors in the context
    presented and ultimately concluded that “the Corps did not have sufficient control and
    responsibility” over the power line “to require it to study the entire project.” 
    Id. at 273
    .
    Turning to the instant case, federal action is not a “legal condition precedent” to
    the construction and operation of the FS Pipeline because there is no comprehensive
    federal permitting system governing domestic oil pipelines; indeed, just as in
    Winnebago Tribe, federal involvement with the FS Pipeline’s construction is purely
    related to the pipeline’s location. Moreover, the Court agrees with the decision in
    Winnebago Tribe that, where federal action is not a legal condition precedent, the
    inquiry into the scope of NEPA review turns on the degree of federal “control and
    responsibility” of a given project as a matter of fact. See 
    id. at 273
    . And given the
    factual similarities between the FS Pipeline and the power line at issue in Winnebago
    Tribe, the Court sees no reason why the two cases should reach different results
    41
    regarding the degree of federal control and responsibility. As noted above, the FS
    Pipeline is essentially a private project, and, like Winnebago Tribe, the federal
    involvement is limited to a very small portion of the overall project. As previously
    explained, the water crossings were verified under NWP 12 and are thus not subject to
    NEPA analysis; consequently, the relevant federal involvement with this particular
    project for the purpose of addressing the extent of federal control and responsibility is
    limited to the 1.3 miles of federal land under the Corps’s jurisdiction and the 13.8 miles
    of land subject to the jurisdiction of the BIA. In this Court’s judgment, these minor
    pieces of federal involvement in a nearly 600-mile pipeline fall short of imbuing the
    federal government with “control and responsibility” over the pipeline as a whole. See
    
    id. at 273
     (“[T]he fact that part of the [project] will cross [land under federal
    jurisdiction] does not suffice to turn this essentially private action into federal action.”).
    The Corps’s regulations outlining the scope of its obligations under NEPA—
    which expressly incorporate the “control and responsibility” standard articulated in
    Winnebago Tribe—buttress this conclusion. These regulations, entitled “NEPA
    Implementation Procedures for the Regulatory Program,” provide guidance specifically
    as to the scope of the Corps’s NEPA responsibilities for a given project. See 33 C.F.R.
    Part 325, Appendix B. In relevant part, the regulations, which generally apply when the
    Corps grants permits, provide:
    Typical factors to be considered in determining whether
    sufficient “control and responsibility” exists include:
    (i) Whether or not the regulated activity comprises “merely a
    link” in a corridor type project (e.g., a transportation or
    utility transmission project).
    42
    (ii) Whether there are aspects of the upland facility in the
    immediate vicinity of the regulated activity which affect the
    location and configuration of the regulated activity.
    (iii) The extent to which the entire project will be within
    Corps jurisdiction.
    (iv) The extent of cumulative Federal control and
    responsibility.
    A. Federal control and responsibility will include the
    portions of the project beyond the limits of Corps
    jurisdiction where the cumulative Federal involvement of the
    Corps and other Federal agencies is sufficient to grant legal
    control over such additional portions of the project. These
    are cases where the environmental consequences of the
    additional portions of the projects are essentially products of
    Federal financing, assistance, direction, regulation, or
    approval[.]
    
    Id.
     Part 325, Appendix B § 7(b)(2) (emphasis added). The regulations go on to provide
    specific examples of how federal control and responsibility in a corridor project should
    be measured:
    For example, a 50-mile electrical transmission cable
    crossing a 1 ¼ mile wide river that is a navigable water of
    the United States requires a [Department of the Army]
    permit. Neither the origin and destination of the cable nor
    its route to and from the navigable water, except as the route
    applies to the location and configuration of the crossing, are
    within the control or responsibility of the Corps of
    Engineers. Those matters would not be included in the
    scope of analysis which, in this case, would address the
    impacts of the specific cable crossing.
    Conversely, for those activities that require a DA permit for
    a major portion of a transportation or utility transmission
    project, so that the Corps permit bears upon the origin and
    destination as well as the route of the project outside the
    Corps regulatory boundaries, the scope of analysis should
    include those portions of the project outside the boundaries
    of the Corps section 10/404 regulatory jurisdiction. To use
    the same example, if 30 miles of the 50–mile transmission
    line crossed wetlands or other “waters of the United
    43
    States,” the scope of analysis should reflect impacts of the
    whole 50–mile transmission line.
    Id. Part 325, Appendix B § 7(b)(3) (emphasis added). Here, for the reasons expressed
    above, there is little doubt that the federal involvement with the FS Pipeline falls under
    the first of the two examples quoted above.
    Undaunted, Plaintiffs attempt to co-opt the regulations to argue that the Corps’s
    involvement with the FS Pipeline does, in fact, extend to a “major portion” of the
    project based on the significant number of water crossings and the fact that they are
    spread throughout the length of the pipeline. (Pl. Br. at 19-20.) In making this
    argument, Plaintiffs rely heavily on cases such as White Tanks Concerned Citizens, Inc.
    v. Strock, 
    563 F.3d 1033
     (9th Cir. 2009), and Save Our Sonoran, Inc. v. Flowers, 
    408 F.3d 1113
     (9th Cir. 2005), in which courts have found that even limited federal
    involvement in a project can be sufficient to “federalize” the project such that NEPA
    review of the entire project is warranted. In the cases Plaintiff cites—both of which
    concerned individual discharge permits related to waters under the Corps’s
    jurisdiction—the courts based their ultimate conclusions on the fact that the waters in
    question were found throughout the project sites at issue. See White Tanks, 
    563 F.3d at 1040
    ; Save Our Sonoran, 
    408 F.3d at 1122
    . In Plaintiffs’ view, the FS Pipeline
    presents precisely this scenario because of the Corps’s verification of 1,950 water
    crossings spread throughout the length of the FS Pipeline.
    However, two crucial aspects of the instant case distinguish it from cases like
    White Tanks and Save Our Sonoran. First, the cases Plaintiffs rely upon concerned
    permits under the individual permitting system of the CWA, not verifications under the
    general permitting system. See White Tanks, 
    563 F.3d at 1037
    ; Save Our Sonoran, 408
    44
    F.3d at 1118. For the reasons discussed at length above, the Corps’s verifications do
    not qualify as a major federal action for NEPA purposes, and without those
    verifications, the requested easements over small pieces of federal land make the facts
    of this case look much more like Winnebago Tribe than White Tanks or Save Our
    Sonoran. Second, neither of the cases that Plaintiffs rely on concerned corridor-type
    projects such as the one at issue here. This fact is especially significant because
    Plaintiffs cite these cases for the proposition that the number of water crossings and the
    fact that they are spread throughout the length of the pipeline—rather than the total
    amount of land or water subject to federal jurisdiction relative to the pipeline as a
    whole—should control the inquiry into what constitutes a “major portion” of the
    pipeline. It is true that the Ninth Circuit emphasized the degree to which the federal
    action in White Tanks and Save Our Sonoran pervaded the respective construction
    projects, but those projects were single-location endeavors, not the corridor-type
    projects that are specifically referred to in the Corps’s regulations. See White Tanks,
    
    563 F.3d at 1040
    ; Save Our Sonoran, 
    408 F.3d at 1121
    . The scenarios in the
    regulations, which expressly apply to corridor-type projects, provide the better model
    for the ratio that governs the “control and responsibility” inquiry, and those examples
    focus on the total amount of land or water under federal jurisdiction relative to the total
    length of the project. See 33 C.F.R. Part 325, Appendix B § 7(b)(3). By that rubric,
    Plaintiffs are unlikely to be able to demonstrate that the Corps had sufficient “control
    and responsibility” over the FS Pipeline to require NEPA review of the entire project.
    Plaintiffs’ final attempt to convince the Court that the entire FS Pipeline was
    “federalized” for NEPA purposes derives from a legal doctrine that is sometimes
    45
    invoked in NEPA cases: the so-called “independent utility” doctrine. (See Pl. Reply at
    8-10.) This doctrine prevents federal agencies or project operators “from dividing one
    project into multiple individual actions each of which individually has an insignificant
    environmental impact, but which collectively have a substantial impact.” Natural
    Resources Def. Council, Inc. v. Hodel, 
    865 F.2d 288
     (D.C. Cir. 1988) (internal
    quotation marks and citation omitted). Plaintiffs maintain that the “independent utility
    doctrine” requires a NEPA review of the entire FS Pipeline, as opposed to a review of
    just the portions of the pipeline that transect areas of federal jurisdiction, primarily on
    the basis of Hammond v. Norton, 
    370 F. Supp. 2d 226
     (D.D.C. 2005), which concerned
    the question of whether “an agency preparing an EIS may . . . ‘segment’ its analysis so
    as to conceal the environmental significance of the project or projects.” 
    Id.
     at 244
    (citing Coal. on Sensible Transp. v. Dole, 
    826 F.2d 60
    , 68 (D.C. Cir. 1987)). However,
    unlike in Hammond, there are no facts here that tend to show that Enbridge sought to
    circumvent any applicable environmental regulations through creative project
    management. Cf. Hammond, 
    370 F. Supp. 2d at 244
    . To the contrary, the evidence
    indicates that Enbridge has gone out of its way to make sure it has addressed all of its
    obligations, including complying with numerous state environmental regulations,
    consulting with dozens of Native American tribes, obtaining rights of way from
    thousands of individual landowners, conducting a public outreach and consultation
    program, and preparing extensive mitigation plans. (See, e.g., Decl. of Jerrid Anderson,
    ECF No. 27-1, ¶¶ 9, 15-17.) In the absence of any record evidence that Enbridge has at
    any point attempted to hide the ball regarding the environmental impact of the FS
    Pipeline, the Court believes the independent utility doctrine is inapposite.
    46
    Finally, the Court notes its general reluctance to conclude that federal action
    with respect to a small portion of a pipeline or other “linear” project is sufficient to
    federalize the entire project in the absence of any statute that permits or requires federal
    oversight regarding such a project. Because every oil pipeline project of any reasonable
    length is likely to pass over some segment of federal land or waters of the United
    States, the practical effect of the result that Plaintiffs seek would be to transform NEPA
    into a statute that requires federal oversight of all domestic oil pipelines (in the form of
    an environmental review). Congress has not yet seen fit to enact an environmental
    statute that federalizes the construction of private, domestic oil pipelines, and Plaintiffs
    have thus far failed to convince this Court that they will be successful in their bid to
    have NEPA construed in that expansive fashion.
    2. Plaintiffs’ Claim That The Corps’s Verifications Violated The Terms Of NWP 12
    In addition to their NEPA-based arguments, Plaintiffs also maintain that the
    Corps’s decision to issue CWA verifications for the FS Pipeline water crossings was
    arbitrary and capricious under the specific terms of NWP 12. Plaintiffs offer two
    grounds for this contention. First, they contend that the Corps’s verifications were
    arbitrary and capricious because they did not include a determination that the overall
    “cumulative effect” of the FS Pipeline’s multiple water crossings on the environment
    would be minimal. (Pl. Br. at 30.) Second, they assert that some of the water crossings
    that the Corps verified violated a requirement of NWP 12 that “prohibits any NWP 12
    activity ‘in the proximity of a public water supply intake.’” (Pl. Br. at 32 (quoting 77
    Fed. Reg. at 10,283).)
    47
    Plaintiffs’ primary support for the first aspect of this APA claim comes from the
    language of NWP 12, which provides:
    In reviewing the PCN for the proposed activity, the district engineer will
    determine whether the activity authorized by the NWP will result in more
    than minimal individual or cumulative adverse environmental effects . . . .
    For a linear project, this determination will include an evaluation of the
    individual crossings to determine whether they individually satisfy the
    terms and conditions of the NWP(s), as well as the cumulative effects
    caused by all of the crossings authorized by NWP.
    77 Fed. Reg. at 10,287 (emphasis added).
    In Plaintiffs’ view, this language requires the Corps to evaluate the cumulative
    impact of all crossings so verified—including the cumulative effect of the 1,950
    crossings verified for the FS Pipeline in this case—and to include in its verification
    letters a statement to that effect. (See Pl. Br. at 30-32.) But there is no statutory or
    regulatory mandate that verification letters contain any such statement. And there is
    also no reason to believe that the district engineers in the instant case failed to conduct
    the required analysis of the FS Pipeline’s cumulative effects. NWP 12 provides that
    “district engineers will evaluate the cumulative effects of those linear projects when
    determining whether authorization by NWP is appropriate,” 77 Fed. Reg. at 10,260
    (emphasis added), and that regulation also permits district engineers to evaluate
    cumulative effects “on a regional basis” by considering “effects within a wetland,
    stream reach, or coastal waterbody[.]” 77 Fed. Reg. at 10,261-64. Plaintiffs have done
    nothing to establish that the district engineers actually failed to follow these
    prescriptions, and the Court will not assume that the fact that the verification letters
    lack a statement regarding cumulative effects means that the Corps failed to perform
    such an analysis, particularly where NWP 12 directs the district engineers to do so.
    48
    The current record is also insufficient to sustain Plaintiffs’ claim that the Corps
    violated NWP 12 because it verified pipeline construction in the proximity of a public
    water supply in violation of General Condition 7 of NWP 12. Plaintiffs have provided a
    single declaration from a resident of Missouri who maintains that the “intake pumps for
    the [Missouri cities of] Adrian and Archie water supplies are located only a few miles
    downstream” from where the FS Pipeline crosses the South Grand River, “which is the
    sole source of water for these two cities.” (Decl. of Danny Ferguson, ECF No. 14-19, ¶
    6.) This statement is unlikely to prevail over record evidence demonstrating that the
    Corps specifically considered General Condition 7’s “proximity” requirement and, in its
    expert determination, concluded that the relevant pipeline crossings were not in the
    proximity of any such water supply intakes. (See Decl. of Lucius Duerksen, ECF No.
    28-1, ¶ 19.) There is no hint of arbitrariness in this conclusion; moreover, the Corps’s
    expert opinion in this regard is entitled to substantial deference. See, e.g., Colorado
    Wild, Heartwood v. U.S. Forest Serv., 
    435 F.3d 1204
    , 1216 (10th Cir. 2006)
    (“[D]eference to [an] agency is greatest when reviewing technical matters within its
    area of expertise.” (citation omitted)). In any event, it is the Plaintiffs’ burden to
    establish that they are likely to succeed on the merits of their claim that the FS Pipeline
    is so close to water supplies that the crossings were improperly verified, and the scant
    evidence that Plaintiffs have offered in this regard is manifestly insufficient.
    B. Irreparable Harm
    “[T]he basis of injunctive relief in the federal courts has always been irreparable
    harm and inadequacy of legal remedies[.]” Sampson v. Murray, 
    415 U.S. 61
    , 88 (1974)
    (internal quotation marks and citation omitted). Even under the sliding scale approach
    49
    that is utilized in this Circuit, Plaintiffs must demonstrate that they will suffer
    irreparable harm absent an injunction in order to be eligible for injunctive relief. See
    CFGC, 
    454 F.3d at 297
     (“A movant’s failure to show any irreparable harm is . . .
    grounds for refusing to issue a preliminary injunction, even if the other three factors
    entering the calculus merit such relief.” (citation omitted)); see also GEO Specialty
    Chem., Inc. v. Husisian, 
    923 F. Supp. 2d 143
    , 147 (D.D.C. 2013) (“[A] court may refuse
    to issue an injunction without considering any other factors when irreparable harm is
    not demonstrated.”). Accordingly, it is well established that “perhaps the single most
    important prerequisite for the issuance of a preliminary injunction is a demonstration
    that if it is not granted the applicant is likely to suffer irreparable harm before a
    decision on the merits can be rendered.” 11A Charles Alan Wright, Arthur R. Miller &
    Mary Kay Kane, Federal Practice and Procedure § 2948.1 (2d ed. 2013).
    The concept of irreparable harm is not easily defined, but there is no doubt that
    “[t]he irreparable injury requirement erects a very high bar for a movant.” Coalition for
    Common Sense in Government Procurement v. United States, 
    576 F. Supp. 2d 162
    , 168
    (D.D.C. 2008). “[S]everal well-known and indisputable principles” guide the inquiry
    regarding irreparable injury. Wisconsin Gas Co. v. FERC, 
    758 F.2d 669
    , 674 (D.C. Cir.
    1985). The party seeking injunctive relief must demonstrate that the claimed injury is
    “both certain and great” and that the alleged harm is “actual and not theoretical.” 
    Id.
    Moreover, because “the court must decide whether the harm will in fact occur,” a party
    seeking injunctive relief must “substantiate the claim [of] irreparable injury” and “must
    show that the alleged harm will directly result from the action which the movant seeks
    to enjoin.” 
    Id.
     Furthermore, because “[i]njunctive relief will not be granted against
    50
    something merely feared as liable to occur at some indefinite time[,]” the movant “must
    show that [t]he injury complained of [is] of such imminence that there is a clear and
    present need for equitable relief to prevent irreparable harm.” 
    Id.
     (citations and internal
    quotation marks omitted) (second alteration in original). And the certain and immediate
    harm that a Plaintiff alleges must also be truly irreparable in the sense that it is “beyond
    remediation.” CFGC, 
    454 F.3d at 297
    .
    In the instant case, Plaintiffs point to two distinct types of harm that they claim
    will occur if construction of the FS Pipeline is not halted during the pendency of their
    legal challenges. First, Plaintiffs insist that the environment will be irreparably injured
    because the ongoing pipeline construction involves clearing trees and plants to create a
    right-of-way in a manner that, Plaintiffs argue, will both kill fish and wildlife and
    endanger critical wetlands. (See Pl. Br. at 32-33.) Second, Plaintiffs insist that “[t]he
    NEPA procedural violations in this case also constitute irreparable harm since they are
    combined with a showing of environmental or aesthetic injury.” (Id. at 34.)
    Neither of these contentions clears the “irreparable harm” hurdle. First of all,
    notwithstanding Plaintiffs’ bald allegations of concrete injury to flora and fauna, the
    record does not clearly establish that the FS Pipeline construction will have a
    significant or substantial impact on the wildlife in the pipeline’s path. Enbridge has
    purposely designed its construction plan so that 82% of the FS Pipeline will be “co-
    located” (i.e., constructed along the same right of way) with Enbridge’s already existing
    Spearhead Pipeline (Enbridge Br. at 42), a fact that Plaintiffs do not rebut. Enbridge
    also submitted extensive mitigation plans along with its applications for the
    51
    verifications. 17 This suggests that the environmental impact of the pipeline construction
    may be minimal, and the Corps has already verified that the seemingly troublesome
    water crossings will have little or no ultimate environmental effect. That is not to say
    that there will be no impact on the forest when trees that surround the pipeline project
    fall. But Plaintiffs’ sound and fury regarding the land that must be cleared and the
    wetlands that may be altered does not signify that any of these environmental effects
    will be permanent or irreversible, as the preliminary injunction standard requires.
    In short, with respect to their argument that the environment will be irreparably
    harmed if the FS Pipeline project is permitted to proceed, Plaintiffs have offered little
    proof of the type of permanent, devastating impact on the environment that has
    convinced other courts to enjoin construction projects. In the assessments of myriad
    agency experts, the impact of the FS Pipeline construction project on the surrounding
    environment will be both minimal and fleeting. (See, e.g., Kansas City District Mem.
    for Record, ECF No. 28-13, at 2 (“Avoidance, minimization, and compensatory
    mitigation will be used . . . to ensure the project will have a minimal adverse effect on
    the aquatic environment.”); Biological Opinion at i (concluding that “the construction,
    operation and maintenance of the FS Pipeline may affect, but are not likely to adversely
    affect” any of the 18 species the FWS examined).) Therefore, the Court concludes that
    Plaintiffs have not established the requisite “great” harm.
    It is also apparent that Plaintiffs have significantly overstated the certainty and
    imminence of some of the injuries they predict. For example, Plaintiffs assert that
    17
    Enbridge’s plans include, among other things, strict time limits for instream excavation activities, use
    of horizontal directional drills to avoid any impact to larger rivers and water bodies identified during
    consultations with federal and state agencies, and a team of environmental inspectors responsible for
    overseeing and implementing Enbridge’s environmental commitments. (See Decl. of Joseph McGaver,
    ECF No. 27-2, ¶¶ 20-25.)
    52
    “[c]onstruction of the [FS Pipeline] will destroy forests and plants, [and] kill fish and
    wildlife[.]” (Pl. Br. at 37.) But Plaintiffs provide no independent proof of this
    allegation. And the FWS’s Biological Opinion and incidental take statement regarding
    the American burying beetle, the decurrent false aster plant, and the Indiana bat says
    only that “[s]ome [American burying beetles] may be disturbed or killed,” that the
    decurrent false aster plant “may be affected,” and that “Indiana bats may be killed or
    injured” during construction of the pipeline. (See Biological Opinion at 58, 59, 62
    (emphasis added).) The FWS also significantly downplays the ultimate impact of these
    possibilities on the ultimate survival of the species. (See id. at 62 (“[T]he FS Pipeline
    will not jeopardize the continued existence the American burying beetle[.]”); 61 (the
    effects on the decurrent false aster will be “small, temporary, and recovery will be
    rapid”); 65 (any “anticipated take is not likely to result in jeopardy to the Indiana
    bat”).)
    In a similar vein, Plaintiffs appear to have exaggerated the extent and effect of
    the pipeline right-of-way building process, which, according to Plaintiffs, includes
    “pipeline and pump-related facility construction, grading, excavation, clearing trees,
    vegetation and ground cover, dragging, chipping, burning, topsoil stripping, digging,
    blasting, dewatering, water withdrawal and discharge, permanent road building, and
    stream crossings.” (Pl. Br. at 32.) And even if such alteration of the environment
    qualifies as harm, Plaintiffs have not established that it is irreparable, as the Federal
    Agencies point out. (Def. Br. at 49 (“Plaintiffs have not shown that any disruption
    caused by construction could not be restored if the Court ultimately required such
    relief.”).) In this respect, Enbridge’s arguments about the efficacy of its “post-
    53
    construction restoration plan” remain unrebutted; Enbridge says its plan is designed “to
    restore the temporary construction [right-of-way] to pre-existing conditions through soil
    restoration management, seeding and plantings, consistent with the Project construction
    plans and as required by state and federal authorizations.” (Defendant-Intervenor
    Enbridge’s Opposition Brief (“Enbridge Br.”), ECF No. 27, at 5; see also id. at 42-43.)
    What is more, Plaintiffs cannot deny that, in regard to the allegedly affected wetlands,
    NWP 12 itself requires that the construction activity in question must not “result in the
    loss of greater than ½-acre of waters of the United States,” 77 Fed. Reg. at 10,271, and
    federal law expressly authorizes courts “to order restoration of jurisdictional wetlands
    that have been unlawfully filled.” (Def. Br. at 49 (citing 
    33 U.S.C. § 1319
    (b).) This
    reality calms the winds of irreparability that might otherwise have kept Plaintiffs’ lofty
    claims of “irreparable harm” afloat.
    Plaintiffs’ second argument—that a NEPA violation constitutes irreparable harm
    in and of itself—does not advance the ball because it begs the very question at issue in
    this action: whether the Federal Agencies’ failure to conduct an environmental review
    prior to construction of the FS Pipeline violates NEPA. Although Plaintiffs are correct
    that an established NEPA violation might rise to the level of irreparable harm when
    coupled with sufficient evidence of environmental injury, see, e.g., Fund For Animals v.
    Norton, 
    281 F. Supp. 2d 209
    , 220 (D.D.C. 2003); Sierra Club v. Marsh, 
    872 F.2d 497
    ,
    500 (1st Cir. 1989), Plaintiffs have thus far failed to demonstrate that they are likely to
    succeed with their arguments that the Federal Agencies have violated any duty to
    conduct an environmental review under NEPA, as discussed above. Surely, after
    having missed the mark with respect to that prerequisite, Plaintiffs cannot expect that
    54
    the alleged but unproven procedural violation will carry the day on the issue of
    irreparable harm.
    Finally, a few words about Plaintiffs’ suggestion that operation of the FS
    Pipeline risks a devastating oil spill that would be damaging to nearby communities,
    and that that harm is sufficient to warrant an injunction. (See Pl. Br. at 37-38; see also
    Pl. Reply at 3-4, 14-15, 37-38.) The Court acknowledges and accepts that some of the
    people who live in areas near the pipeline project are sincerely worried about the harm
    that an oil spill might cause. 18 As genuine as these concerns may be, Plaintiffs have not
    shown that a damaging oil spill is likely to occur, and it is bedrock law that injunctions
    “will not issue to prevent injuries neither extant nor presently threatened, but only
    merely feared.” Comm. in Solidarity With People of El Salvador (CISPES) v. Sessions,
    
    929 F.2d 742
    , 745-46 (D.C. Cir. 1991) (internal quotation marks and citations omitted).
    In other words, the harms that an oil spill might potentially someday cause—however
    fearsome—are not certain, and therefore are not sufficient to satisfy the “irreparable
    harm” standard.
    18
    These fears are explained in detail in the declarations Plaintiffs have submitted. For example,
    Declarant Danny Ferguson opines that “[t]he Flanagan South pipeline poses an unacceptable risk to the
    municipal water supplies for the cities of Adrian and Archie, Missouri” because a spill from the
    pipeline “would contaminate [the cities’] drinking water for years and threaten [the] community’s
    survival.” (Decl. of Danny Ferguson, ECF No. 14-19, ¶¶ 6-7.) Declarant Mary Blackmore speculates
    that “the construction of a toxic tar sands oil pipeline will contaminate” her family’s organic farm “due
    to the operation of construction equipment, [and] spills and leaks from either the pipeline itself or from
    the construction equipment[.]” (Decl. of Mary Blackmore, ECF. No. 14-20, ¶ 9.) And Declarant
    Megan Corrigan states that “a spill in the wetlands of the Marais des Cygnes State Wildlife Area” in
    Kansas “would be and environmental disaster” and that “the area would be ruined for birdwatchers like
    me.” (Decl. of Megan Corrigan, ECF No. 14-17, ¶ 11.)
    55
    C. Balance Of Harms And Public Interest
    The final two factors that a court in this circuit must consider when deciding
    whether to grant a preliminary injunction are the balance of harms and the public
    interest. See Arkansas Dairy Co-op Ass’n, Inc. v. U.S. Dep’t of Agric., 
    573 F.3d 815
    ,
    821 (D.C. Cir. 2009). Although allowing challenged conduct to persist certainly may
    be harmful to a plaintiff and the public, harm can also flow from enjoining an activity,
    and the public may benefit most from permitting it to continue. When “balanc[ing] the
    competing claims of injury,” Winter, 
    555 U.S. 7
    , 24 (2008), the Court must “consider
    the effect on each party of the granting or withholding of the requested relief.” 
    Id.
    (citations omitted). Additionally, “courts of equity should [have] particular regard for
    the public consequences in employing the extraordinary remedy of injunction.” 
    Id.
    (internal quotation marks and citations omitted).
    Plaintiffs maintain that the balance of harms clearly weighs in favor of granting
    an injunction. In their view, the environmental harms they have identified far exceed
    the minimal or non-existent harms that Enbridge and the Federal Agencies face. (Pl.
    Reply Br. at 38.) Plaintiffs reiterate the damaging construction effects, the risks to
    wildlife, and the potential for devastating oil spills that motivated their claims of
    irreparable harm, and they maintain both that the Federal Agencies will suffer no injury
    as a result of an injunction and that the harm Enbridge may suffer would be purely
    economic—and largely “self-inflicted”—and thus is not an adequate basis for denying
    injunctive relief. (Id. at 40.)
    For its part, Enbridge has identified the harms to its business that might follow
    from the issuance of an injunction, including up to $262 million in additional
    56
    construction costs if it is required to “de-mobilize” and then “re-mobilize” its
    construction efforts. (Enbridge Br. at 46-47.) Enbridge notes that relationships with its
    suppliers and customers, and by extension its business operations, would suffer as a
    result of delays in construction. (Id. at 47.) Enbridge also asserts that delaying
    pipeline construction could increase the environmental impact of the project rather than
    prevent it, because current construction plans are tailored to the calendar (i.e., Enbridge
    has coordinated construction with the planting and harvest schedules of farmers along
    the pipeline’s path), and this timing was intentionally established to minimize
    environmental effects. (Id. at 47-48.) In evaluating harms in the balance, Enbridge
    also maintains that the injuries that would be inflicted on its bottom line as a result of
    project delay are a near certainty, while the environmental harms that Plaintiffs identify
    are speculative and thus should be discounted in the balancing test. (Id. at 43-45.)
    The Federal Agencies’ arguments about the comparative harms stem primarily
    from their assessment of the public’s interest. See Nken v. Holder, 
    556 U.S. 418
    , 435
    (2009) (noting that the balance of harms and public interest factors “merge when the
    Government is the opposing party”). In the Federal Agencies’ view, continued
    construction of the FS pipeline will serve the public’s interest in several respects. First,
    the public has an interest in the development of stable North American energy sources.
    (Def. Br. at 54; Enbridge Br. at 49.) Second, the public has a strong interest in the jobs
    and economic growth that construction and operation of the FS pipeline will create.
    (Enbridge Br. at 49 (claiming that the FS pipeline will generate 3,000 jobs in the
    immediate future).) Additionally, according to the Federal Agencies, the public has an
    interest in avoiding the unnecessary costs that would be incurred if, as a result of an
    57
    injunction in this matter, the Corps was required to eschew the NWP 12 permitting
    process and thereby made to devote scarce resources to conducting extensive
    environmental reviews of projects that would otherwise conform to NWP 12 standards
    and consequently have minimal environmental impact. (Def. Br. at 53-54.)
    In the Court’s view, Enbridge and the Federal Agencies have the better of these
    arguments. With respect to the balance of harms, the record as it currently stands
    shows that Enbridge has committed major resources to the FS Pipeline project over the
    last 18 months, including engaging in an intensive effort to comply with the myriad
    state and federal environmental regulations that the pipeline project implicates. The
    evidence of the time and effort that Enbridge has already put in to the project lends
    credence to Enbridge’s argument that it will suffer harm if the pipeline is indefinitely
    delayed. Plaintiffs, by contrast, have failed to demonstrate the harms that they allege
    with specificity in regard to the FS Pipeline in particular, relying instead on general
    harms they have identified by analogizing this project to other pipelines. (See Pl. Br. at
    36-37.) While the Court is aware of the potential negative environmental consequences
    that can accrue from the construction and operation of a large oil pipeline, it is also
    hesitant to weigh these possibilities too heavily without more evidence linking them to
    this particular pipeline project. Consequently, the Court finds that the balance of harms
    tips in favor of Enbridge.
    The Federal Agencies also are on firmer footing than Plaintiffs with respect to
    the public interest factor. The Court deems particularly compelling the Federal
    Agencies’ argument that the public has an interest in regulatory efficiency with respect
    to projects that fall within the rubric of the general permitting system that the Clean
    58
    Water Act expressly authorizes. This system is carefully designed and administered to
    minimize the costs of approving projects that the Corps has already determined will not
    adversely impact the environment. The general permitting system also has the added
    benefit of incentivizing project sponsors to conform their construction activities to
    existing general permits, thereby further reducing the administrative burden while at the
    same time decreasing the potential negative environmental consequences of those
    projects. Overall, then, it is difficult for this Court to see how halting the FS Pipeline
    project, and thereby casting doubt on the general permitting process, is in the public’s
    interest.
    Plaintiffs argue that, because federal agencies have a statutory duty to conduct
    analyses that prevent substantive environmental harms, the public’s interest is clearly
    aligned with enjoining harmful construction projects that proceed without such an
    analysis, no matter the cost. (Pl. Br. at 41- 42 (quoting Colo. Wild Inc. v. U.S. Forest
    Serv., 
    523 F. Supp. 2d 1213
    , 1223 (D. Colo. 2007) (“The public has an undeniable
    interest in the Corps’ compliance with the CWA and NEPA’s environmental review
    requirements and in the informed decision-making that the statutes are designed to
    promote.”)).) This may be so, but this contention is circular where, as here, the
    Federal Agencies’ statutory duty to conduct an environmental review under NEPA has
    not been firmly established. Indeed, Plaintiffs’ argument that there is a significant
    public interest in ensuring that federal agencies comply with their statutory duties (Pl.
    Br. at 41) brings the Court right back to where it started: examining Plaintiffs’ claim
    that the Federal Agencies here failed to comply with a NEPA duty to conduct an
    environmental review of the FS Pipeline. Plaintiffs’ public interest arguments are thus
    59
    derivative of their merits arguments and depend in large part on the vitality of the latter.
    This Court has already concluded that Plaintiffs are not likely to succeed on the merits
    of their claim that the Federal Agencies violated a statutory duty, and the public interest
    in the Federal Agencies’ compliance with their statutory duties must be weighed
    accordingly. See, e.g., Serono Laboratories, Inc. v. Shalala, 
    158 F.3d 1313
    , 1326 (D.C.
    Cir. 1998) (“The final preliminary injunction factor, the public interest, also offers
    [plaintiff] no support because it is inextricably linked with the merits of the case. If, as
    we have held, [plaintiff] is not likely to establish [a likelihood of success in the merits],
    then public interest considerations weigh against an injunction.”); ViroPharma, Inc. v.
    Hamburg, 
    898 F. Supp. 2d 1
    , 29-30 (D.D.C. 2012) (where plaintiff was unlikely to
    establish that agency action did not comply with the law, the public interest factor
    weighed against granting an injunction). Consequently, the Court finds that the public
    interest factor also weighs against granting a preliminary injunction in this case.
    IV.    CONCLUSION
    For the foregoing reasons, Plaintiffs have failed to carry their burden with
    respect to any of the four preliminary injunction factors, and the Court concludes that
    their motion for a preliminary injunction must be DENIED. A separate order will
    follow.
    DATE: November 13, 2013                           Ketanji Brown Jackson
    KETANJI BROWN JACKSON
    United States District Judge
    60