Telligent Masonry, LLC v. Continental Casualty Company ( 2019 )


Menu:
  •                             UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLUMBIA
    )
    TELLIGENT MASONRY, LLC,                      )
    )
    Plaintiff,                    )
    )
    v.                                    )       Civil Action No. 19-1078 (RMC)
    )
    CONTINENTAL CASUALTY                         )
    COMPANY, et al.,                             )
    )
    Defendants.                   )
    )
    MEMORANDUM OPINION
    Grunley Construction Company, Inc. (Grunley) was awarded the prime
    construction contract (Contract) in 2014 for work related to restoration of the Historic Center
    Building at St. Elizabeth’s West Campus for future occupation by the U.S. Department of
    Homeland Security (DHS). Compl. [Dkt. 1] ¶ 6. Grunley executed a payment bond with
    sureties Continental Casualty Company and Liberty Mutual Insurance Company. 
    Id. ¶ 7.
    On or
    about November 23, 2015, Grunley and Telligent Masonry, LLC (Telligent) agreed to a
    subcontract by which Telligent was to perform masonry and related work for compensation of
    $1,725,000.00. 
    Id. ¶ 8.
    At some point, Grunley directed Telligent to perform additional work
    which raised the total value of the subcontract to $2,273,984.83. 
    Id. To date,
    Grunley has paid Telligent a total of $2,159,533.33, which is
    $114,451.50 short of the total subcontract value. 
    Id. ¶ 10.
    On April 17, 2019, Telligent filed suit
    pursuant to the Miller Act, 40 U.S.C. §§ 3131-34, 1 against the two sureties to recover monies
    1
    Under the Miller Act, prospective contractors must furnish performance bonds and payment
    bonds to the government before entering into a contract for any public construction project worth
    1
    allegedly due. Compl. ¶¶ 20-26. Grunley filed a motion to intervene as of right or by permission
    pursuant to Federal Rule of Civil Procedure 24; the Court granted the motion to intervene as of
    right, but permitted Telligent to file a motion to dismiss Grunley’s counterclaims. See Order
    [Dkt. 13]. On July 17, 2019, Telligent moved to dismiss Grunley’s counterclaims for lack of
    subject-matter jurisdiction, or, in the alternative, under the theory of forum non conveniens. The
    motion is ripe for review.2
    I. LEGAL STANDARDS
    A.      Subject-Matter Jurisdiction
    Pursuant to Federal Rule of Civil Procedure 12(b)(1), a defendant may move to
    dismiss a complaint, or any portion thereof, for lack of subject-matter jurisdiction. Fed. R. Civ.
    P. 12(b)(1). When reviewing a motion to dismiss for lack of jurisdiction under Rule 12(b)(1), a
    court must “assume the truth of all material factual allegations in the complaint and ‘construe the
    complaint liberally, granting plaintiff the benefit of all inferences that can be derived from the
    facts alleged.’” Am. Nat’l Ins. Co. v. FDIC, 
    642 F.3d 1137
    , 1139 (D.C. Cir. 2011) (quoting
    Thomas v. Principi, 
    394 F.3d 970
    , 972 (D.C. Cir. 2005)). Nevertheless, “the Court need not
    accept factual inferences drawn by plaintiff[ ] if those inferences are not supported by facts
    alleged in the complaint, nor must the Court accept plaintiff[’s] legal conclusions.” Speelman v.
    United States, 
    461 F. Supp. 2d 71
    , 73 (D.D.C. 2006). The same logic and analysis are required
    over $100,000. 40 U.S.C. § 3131(b). Additionally, subcontractors not paid in full within ninety
    days of completion may bring a civil action to recover the outstanding balance against the
    sureties that supplied the payment bonds within one year of the last day in which labor was
    performed. 40 U.S.C § 3133(b)(2).
    2
    See Pl., United States of America f/u/b/o Telligent Masonry, LLC’s Mot. to Dismiss Grunley
    Constr. Co., Inc.’s Countercl. (Mot.) [Dkt. 15]; Grunley Constr. Co., Inc.’s Opp’n to Pl.’s Mot. to
    Dismiss Countercl. [Dkt. 16]; Mem. in Reply to Grunley Constr. Co., Inc.’s Opp’n to Pl.’s Mot.
    to Dismiss Countercl. [Dkt. 17].
    2
    when evaluating a defendant-intervenor’s counterclaim. See United States v. Intrados/Int’l
    Mgmt. Grp., 
    277 F. Supp. 2d 55
    , 59 (D.D.C. 2003) (summarizing legal standard for motion to
    dismiss counterclaim).
    B.        Venue
    Under Federal Rule of Civil Procedure 12(b)(3), a defendant may, at the lawsuit’s
    outset, test whether the plaintiff “has brought the case in a venue that the law deems
    appropriate.” Modaressi v. Vedadi, 
    441 F. Supp. 2d 51
    , 53 (D.D.C. 2006). “If the plaintiff’s
    chosen forum is an improper venue under applicable statutes, or is otherwise inconvenient, the
    Court may dismiss the action or transfer the case to a district where venue would be proper or
    more convenient.” 
    Id. (citing 28
    U.S.C. § 1406 (providing for dismissal or transfer when venue
    is defective) and 28 U.S.C. § 1404 (allowing venue transfer for the convenience of the parties
    and witnesses)).
    “[W]hen parties have agreed to a forum selection clause, the traditional analysis
    is altered and the clause should control absent a strong showing it should be set aside.” Gipson v.
    Wells Fargo & Co., 
    563 F. Supp. 2d 149
    , 154 (D.D.C. 2008) (quoting 2215 Fifth St. Assoc. v. U-
    Haul Int’l, Inc., 
    148 F. Supp. 2d 50
    , 58 (D.D.C. 2001) (internal quotations omitted)); see also
    M/S Bremen v. Zapata Off-Shore Co., 
    407 U.S. 1
    , 10, 12 (1972) (“[Forum-selection] clauses are
    prima facie valid” and “should be honored by the parties and enforced by the courts.”). Forum
    selection clauses are to be enforced unless the party resisting enforcement shows that one of the
    exceptions set forth in Bremen applies. The opponent of enforcement must make a “strong
    showing” that:
    (1) enforcement would be unreasonable and unjust; (2) the clause
    was invalid for such reasons as fraud or overreaching; (3)
    enforcement would contravene a strong public policy of the forum
    in which suit is brought, whether declared by statute or judicial
    decision; or (4) trial in the contractual forum would be so gravely
    3
    difficult and inconvenient that the plaintiff will for all practical
    purposes be deprived of his day in court.
    Cheney v. IPD Analytics, LLC, 
    583 F. Supp. 2d 108
    , 118 (D.D.C. 2008) (quoting 
    Bremen, 407 U.S. at 15
    ) (internal quotations omitted)).
    II. ANALYSIS
    The Court granted Grunley’s motion to intervene as of right pursuant to Federal
    Rule of Civil Procedure 24(a), which does not include the requirement that the intervenor
    demonstrate an “independent basis for jurisdiction.” EEOC v. Nat’l Children’s Ctr., Inc., 
    146 F.3d 1042
    , 1046 (D.C. Cir. 1998). Had the Court granted Grunley’s motion to intervene through
    permissive intervention, under Federal Rule of Civil Procedure 24(b), Grunley would have had
    to establish how its contract claims against Telligent presented the Court with subject-matter
    jurisdiction independent from the Miller Act claims raised by Telligent. See 
    id. (“The first
    requirement for permissive intervention—an independent basis for jurisdiction—stems not from
    any explicit language in Rule 24(b), but rather from the basic principle that a court may not
    adjudicate claims over which it lacks subject matter jurisdiction.”). With intervention as of right,
    Grunley’s counterclaims may be considered by the Court via its supplemental jurisdiction to hear
    “claims that are so related to claims in the action within such original jurisdiction that they form
    part of the same case or controversy.” 28 U.S.C. § 1367(a).
    Telligent argues it is challenging the Court’s jurisdiction to address Grunley’s
    claims, but the arguments are properly understood as challenging venue. Telligent cites the
    dispute resolution section of the Subcontract Agreement between itself and Grunley for the
    proposition that the proper venue for challenges to the agreement or either party’s performance is
    the Maryland state court located in Montgomery County, Maryland. See Mot., Ex. A,
    4
    Subcontract Agreement (Cost Code 04-200-0100) (Agreement) [Dkt. 15-2] ¶ 19. The relevant
    section of the Agreement states:
    All disputes between the Contractor and Subcontractor, not
    involving the Owner’s acts, omissions, or responsibilities shall, at
    the Contractor’s sole option, be resolved by arbitration in
    accordance with the rules of the American Arbitration Association.
    Subcontractor specifically agrees that any such arbitration
    proceedings shall, at the Contractor’s sole option, be consolidated
    with any arbitration proceedings between the Contractor and any
    other party. Subcontractor specifically agrees that any dispute with
    the Owner or the Contractor shall not interfere with Subcontractor’s
    progress of its work in any manner, and that Subcontractor shall
    proceed with its work as ordered, subject to claim, this includes
    disputes involving the timing of payment and/or payment amounts.
    This agreement to arbitrate shall be specifically enforceable under
    the prevailing arbitration law. The award rendered by the arbitrators
    shall be final, and judgment may be entered upon it in any court
    having jurisdiction thereof. Any such award shall be binding and
    enforceable against any persons, surety, and/or bonding company,
    which guarantee the performance by the Subcontractor of this
    Agreement in any manner. Should Contractor choose to litigate any
    actions or lawsuits arising hereunder to the extent permitted by
    Article 19 and by law shall only be brought in a Maryland State court
    of competent jurisdiction with venue in Montgomery County,
    Maryland.
    
    Id. Telligent argues
    that the final sentence of the paragraph binds the parties to litigate any
    disputes in Montgomery County. Grunley disagrees, focusing on the language “[s]hould
    Contractor choose to litigate any actions or lawsuits.” 
    Id. As the
    Contractor, Grunley argues
    that it is only obligated to raise its claims in Montgomery County when it has initiated the
    lawsuit. In this instance, because Telligent initiated the instant litigation in the United States
    District Court for the District of Columbia as required by the Miller Act, Grunley did not
    “choose to litigate” and, therefore, is not bound by the agreement to bring the claims in
    Montgomery County. The Court agrees with Grunley.
    The Agreement sets forth two possible scenarios. First, if Telligent wishes to
    instigate a dispute under the Agreement the parties shall proceed to arbitration. Second, if
    5
    Grunley initiates the action the suit shall be brought in Montgomery County. This case arises in
    a third, distinct, posture. Telligent filed this case against the sureties as required by the Miller
    Act, thus introducing a venue not contemplated by the Agreement. Under the current posture,
    the Agreement contains no controlling language. The Court recognizes the strong presumption
    of validity given to forum selection clauses, see 
    Bremen, 407 U.S. at 10
    , 12, and, if this case
    arose under a procedure discussed in the Agreement, the Court would enforce the clause as
    written. However, given the unanticipated posture of the current lawsuit, the Court will not
    dismiss the counterclaim and require Grunley to refile in Montgomery County.
    Telligent also argues that the Court should dismiss the counterclaim under the
    doctrine of forum non conveniens, citing Azima v. RAK Inv. Auth., 
    926 F.3d 870
    , 874-75 (D.C.
    Cir. 2019), where the Circuit recently confronted the availability of forum non conveniens as a
    proper method to dismiss a complaint due to a mandatory forum selection clause. The Circuit
    noted that where “the plaintiff has entered into a contract to litigate his claims in a specific
    forum, the defendant may enforce that agreement by moving to dismiss for forum non
    conveniens.” 
    Id. at 874.
    Having already decided that the forum selection clause in the
    Agreement does not specifically consider the posture in which the parties currently find
    themselves, the Court relies on the typical forum non conveniens analysis to determine if the case
    can and should proceed elsewhere. For this purpose, the Court considers whether another forum
    is both (1) “available and adequate” to litigate Grunley’s counterclaims and, (2) “upon a
    weighing of public and private interests, the strongly preferred location for the litigation.” MBI
    Grp., Inc. v. Credit Foncier Du Cameroun, 
    616 F.3d 568
    , 571 (D.C. Cir. 2010).
    Again, the unique nature of the challenge presents the answer. Telligent initiated
    this action in the court designated by the Miller Act but now argues that the same court is not
    6
    convenient to decide related issues. While the courts of Montgomery County are certainly
    available and adequate to handle a contract dispute brought by Grunley against Telligent,
    Grunley did not initiate this suit and the public and private interests involved strongly prefer this
    court. The public interest in judicial economy supports a single court deciding all related issues
    which is why the Rules provide for intervention. The fact that Grunley had a right to intervene
    demonstrates that its interests are also at stake in this litigation against Grunley’s sureties and
    demonstrates that private interests also support having its counterclaims decided here. Telligent
    cannot be viewed as inconvenienced by being required to remain in a venue of its choosing for
    all related issues.
    IV. CONCLUSION
    For the foregoing reasons, the Court will deny Telligent Masonry, LLC’s Motion
    to Dismiss Grunley Construction Company, Inc.’s Counterclaim, Dkt. 15. A memorializing
    Order accompanies this Memorandum Opinion.
    Date: October 29, 2019
    ROSEMARY M. COLLYER
    United States District Judge
    7